1 Soakpit
Main bar 10mm Dia. & 14.166' long @6"C/C upto 12.166 10 1 21 14.166 4.32 90.70 0.617 55.99
Main bar 10mm Dia. &10.166' long @6"C/C upto 14.166' 10 1 29 16.5 5.03 145.88 0.617 90.05
2 Chamber
Main bar 10mm Dia. & 3.5' long @6"C/C upto 2 10 5 7 3.5 1.07 37.35 0.617 23.05
Main bar 10mm Dia. & 3.5' long @6"C/C upto 3 10 5 7 3.5 1.07 37.35 0.617 23.05
S. Total 192.15 kg
Wastage @ 7% of total 13.45
Grand Total 205.60 kg
DETAILED QUANTITY ESTIMATE
Project: Construction of soakpit
S.N. Description No. L (ft.) B (ft.) H (ft.) Quantity Unit Remarks
1 Earthwork in excavation
Soak pit 1 12.00 14.00 10.00 120.000
chamber 5 3.50 3.50 2.00 35.000
Total 120.000 cft
4 Stone soling
Stone soiling at wall foundation 1 36.00 1.25 0.75 33.750
Chamber 5 3.50 3.50 0.75 45.938
Total 79.688 cft
8 Form work
Soakpit slab 1 10.17 12.17 123.680
Chamber Cover 5 3.50 3.50 61.250
Total 184.930 sft
10 Manhole cover
For soakpit 1 1.000
Total 1.000 No.
Total 269,616.61
BILL OF QUANTITY (BOQ)
Project: Construction of Septic Tank & Soak Pit for Pokhara Chamber of Commerce & Industry (PCCI)
SN Description of Items Unit Quantity Rate Amount Remarks
In figures In words
A) Civil Work
Project: Construction of Septic Tank & Soak Pit for Pokhara Chamber of Commerce & Industry (PCCI)
SN Description of Items Unit Quantity Rate Amount Remarks
In figures In words
Cast Iron Manhole cover of size 2'x2' with resting iron plate etc. all
10 complete as per the drawings, specification and instruction of site
Engineer.
no 12.00
DETAILED QUANTITY ESTIMATE
Project: Construction of soakpit
S.N. Description No. L (ft.) B (ft.)
2 Earthwork in excavation
Soak pit 1 12.00 14.00
3 Stone soling
Stone soiling at wall foundation 1 36.00 1.25
Total
4 PCC work (1:3:6 )
Stone soiling at wall foundation 1 36.00 1.25
7 Form work
Soakpit slab 1 10.17 12.17
10 Manhole cover
For soakpit 1
ABSTRACT OF COST
0.75 33.750
Total 33.750 cft
0.25 11.250
Total 11.250 cft
123.680 sft
Total 123.680 sft
205.596 kg
1.000 No.
Total 5.000 No.
2.000 No.
2.000 No.
3.000 No.
Total 7.000 No.
Amount (Rs.)
3,728.40
6,497.55
3,353.74
2,238.25
145,598.40
22,132.41
8,082.46
63.25
3,500.00
195,194.46
General Analysis Page 10
Item : Boulder Soling & levelling works in foundation including 30m lead.
Norms No. C10 (6-5)
Unit Cu.M
Particular Description Unit Quantity Rate Amount Remarks
Labour Skilled Md
Unskilled Md 1.50 800.00 1200.00
Material Boulder Stone Cu.M 1.20 1850.00 2220.00
Item : Plain cement concrete works in foundation including material collection & 30m lead
A In (1:3:6)
Norms No. D1(7-2) ga
Unit Cu.M
Particular Description Unit Quantity Rate Amount Remarks
Labour Skilled Md 1.0 800.00 800.00
Unskilled Md 4.0 1050.00 4200.00
Material Cement(N.S. marks) M.T 0.22 17854.00 3927.88
Agg. 40 mm Cu.M 0.65 1850.00 1202.50
Agg. 20 mm Cu.M 0.24 1900.00 456.00
Course Sand Cu.M 0.47 2350.00 1104.50
Water Litre 120 0.18 21.60
Total (Dept. Rate) 11712.48 331.67
B M20 (1:1.5:3)
Norms No. D2(7-4)kha
Unit Cu.M
Particular Description Unit Quantity Rate Amount Remarks
Labour Skilled Md 0.8 150.00 120.00
Unskilled Md 7.0 800.00 5600.00
Material Cement (OPC) M.T 0.4 17854.00 7141.60
Agg. 20 mm(Crusher) Cu.M 0.57 1900.00 1083.00
Agg. 10 mm(Crusher) Cu.M 0.29 1900.00 551.00
Sand(Crusher screen) Cu.M 0.425 2350.00 998.75
Water ltr 200 0.18 36.00
Sub-Total 15530.35
Total (Dept. Rate) 15530.35 439.79
Item : Brick masonry works including materials collection, preparation of mortar with 30m
A Chimney Bhatta Bricks in c/s mortar 1:4
Norms No. C2(5-1)kha2 / 5(2)ka
Unit Cu.M
Particular Description Unit Quantity Rate Amount Remarks
Labour Skilled Md 1.5 1050.00 1575.00
Unskilled Md 2.2 800.00 1760.00
Material Cement(N.S. marks) M.T 0 17854.00 0.00
Brick No. 560.00 18.08 10124.80
Sand(Crusher Screen) Cu.M 0 2350.00 0.00
Water ltr 0 0.18 0.00
Sub-Total 13459.80
Total (Dept. Rate) 13459.80
D Form works by using iron props and 18mm thick Water proof Ply wood
Norms No. E6(8-4)Ka
Unit 100 Sq.M.
Particular Description Unit Quantity Rate Amount Remarks
Labour Skilled Md 17.200 1050.00 18060.00
Unskilled Md 25.700 800.00 20560.00
Material Local Wood Cu.M 0.232 40606.00 9420.59
18 mm plywood board Sq.m 16.500 1702.86 28097.19
Iron pipe(props) wall 1no Props
th1.65mm and pipesize asumed as 3.5m
50mm dia. no 4.400 1094.52 4815.89 long
Nails Kg 25.000 107.32 2683.00
Sub-Total 83636.67 Per sq.m
Total (Dept. Rate) 83636.67 836.37
Note:- It is assumed that the wood used in form work can be used 6 times and remaining 25% scrap
value.(1.6875x1.1x0.75)/6=0.232 cum.
It is asumed that the ply wood used in form work can be used 6 times and remaining 10% scrap value
100x1.1x0.9/6=16.5
It is asumed that the black Pipe used in form work can be used 15 times and remaining 25% scrap value
88/15x0.75 =4.4
Reinforcement bar for RCC works including cutting, binding, bending & placing as per
12 Item :
drawing with 30m lead
Norms No. D9(7-5)
Unit 1M.T
Particular Description Unit Quantity Rate Amount Remarks
Labour Skilled Md 12.0 1050.00 12600.00
Unskilled Md 12.0 800.00 9600.00
Material T.M.T. Bar Mt 1.05 85880.00 90174.00
Binding wire Kg. 10 101.70 1017.00
Sub-Total 113391.00 Per Kg
Total (Dept. Rate) 113391.00 113.39