Project : Proposed Two (2) Storey Warehouse Building

Location : Apelo Cruz Street, Malibay, Pasay City


Subject : BAR CHART WORK SCHEDULE
BAR CHART SCHEDULE
Duration
ITEM DESCRIPTION AMOUNT Wt. (%) Apr 2019 May 2019 Jun 2019 Jul 2019 Aug 2019 Aug 2019
(Weeks)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 17 18 19 20
A General Requirements 1,215,000.00 11.57 20.00 0.57857 0.57857 0.57857 0.57857 0.57857 0.57857 0.57857 0.57857 0.57857 0.57857 0.57857 0.57857 0.57857 0.57857 0.57857 0.57857 0.57857 0.57857 0.57857 0.57857

B Sitework 809,460.86 7.71 6.00 1.28486 1.28486 1.28486 1.28486 1.28486 1.28486

C Formworks/Scaffoldings 610,051.50 5.81 5.00 1.162 1.162 1.162 1.162 1.162

D Concreting Works 1,587,184.00 15.12 6.00 2.51934 2.51934 2.51934 2.51934 2.51934 2.52
E Reinforcing Bars 2,061,836.25 19.64 5.00 3.92731 3.92731 3.92731 3.92731 3.92731

F Masonry Works 543,712.52 5.18 4.00 1.29455 1.29455 1.29455 1.29455

G Structural Steel Works 426,470.00 4.06 4.00 1.0154 1.0154 1.0154 1.0154

H Roofing Works 465,790.60 4.44 4.00 1.10903 1.10903 1.10903 1.10903

I Floor Finishes 125,866.20 1.20 4.00 0.29968 0.29968 0.29968 0.29968

J Wall Finishes 492,297.60 4.69 4.00 1.17214 1.17214 1.17214 1.17214

K Ceiling Finishes 11,330.50 0.11 2.00 0.05395 0.05395

L Windows 215,925.75 2.06 4.00 0.51411 0.51411 0.51411 0.51411

M Doors & Jambs 90,465.00 0.86 3.00 0.28719 0.28719 0.28719

N Painting Works 649,294.60 6.18 6.00 1.03063 1.03063 1.03063 1.03063 1.03063 1.03063

O Architectural Steel Works 105,465.00 1.00 4.00 0.25111 0.25111 0.25111 0.25111

P Plumbing and Sanitary Works 520,000.00 4.95 10.00 0.50 0.49524 0.49524 0.49524 0.49524 0.49524 0.49524 0.49524 0.49524 0.49524

Q Electrical Works (by C.S Almazan) 569,849.62 5.43 10.00 0.54271 0.54271 0.54271 0.54271 0.54271 0.54271 0.54271 0.54271 0.54271 0.54271

TOTAL COST 10,500,000.00 100.00


Weekly Accomplishment % 0.00 0.00 1.86 1.86 1.86 3.03 6.95 9.47 8.19 8.19 9.36 5.73 6.75 4.51 6.27 5.97 5.75 5.75 2.65 2.65 1.61 1.61 0.00 0.00

Cumulative Weekly Accomplishment % 0.00 0.00 1.86 3.73 5.59 8.62 15.57 25.04 33.23 41.41 50.77 56.50 63.25 67.76 74.03 79.99 85.74 91.49 94.13 96.78 98.39 100.00 100.00 100.00

Scheduled Monthly Accomplishment (%) 3.73 21.31 31.46 23.49 16.79 3.22
Cummulative Monthly Accomplishment (%) 3.73 25.04 56.50 79.99 96.78 100.00

Prepared by: Noted by: Evaluated by: Approved by:


Engr. Cherry Ann Layson Engr. Ariel G. Co Arch. Henry G. Wee Ebol THA Dev't. Corp.
Project Engineer President/CEO Principal Architect Owner
ACM Konstructura Builders ACM Konstructura Builders . .