Beruflich Dokumente
Kultur Dokumente
® 8
PRINCE2 Practitioner Resource Book
Question Part 2
7 A Answer
If a product has not been delivered to agreed timescales as a result of
4a incorrect rework, the stage should not be delayed, the rework should be planned
into the next stage. Ref 17.4.4.
There is no indication that the stage is forecast to exceed tolerance.
4b incorrect
Ref 10.3.4.
By checking the target sign-off date the Project Manager will know if
4c correct there is an actual delay or whether the Marketing department has
exceeded the time allocated for follow-up actions. Ref 17.4.4 / 10.3.3.2.
4d incorrect No products should be baselined until they are signed-off. Ref 9.3.2.
Question Part
7 A Answer
There is no indication that a further project has been agreed and the
5a incorrect production of a project mandate is not within the scope of the Calendar
project.
This is not an expected benefit of this project and would not therefore
appear in the Benefits Review Plan. Also, the Benefits Review Plan is
5b incorrect
updated at the end of each stage, not just the end of the project. Ref
A1.
Exception Reports provide information to the Project Board when
5c incorrect
tolerance is forecast to be/or has been exceeded. Ref 10.3.4.
The Lessons Log captures lessons learned during the project that can
usefully be applied to other projects. Notes should be made of any
5d correct
good and bad experiences in the use of the management and specialist
products and tools as they occur. Ref 10.3.3.3.
Question Part
7 A Answer