Beruflich Dokumente
Kultur Dokumente
1
Q No. 1 When updating project schedule, what does Retained Logic and Progress Override mean,
Discuss with Examples?
Assignment No. 2
Q No. 2 Discuss Activity Types, Activity Duration Types and Activity Percent Complete Types?
Assignment No. 3
Q No. 3 Assume that a ‘‘project’’ with three activities: The first two activities are identical and can be
performed simultaneously. Each one requires the installation of an interior hollow-core wood door,
which costs $200 each (including hardware). Installation of these doors requires one laborer for
2 hours for each door. The third activity requires the installing of hand-carved decorative exterior door
that costs $2,200 and takes three laborers for 3 hours. Assume a man-hour costs $40.
3 – B Now, assume that the first and second activities are completed and the third one has not started
yet (see Figure), what is the percent complete of the ‘‘project’’?
Use all applicable percent complete methods. Assuming that project is on budget and on schedule
1. Units Completed
Now, to make things little more complicated, let’s assume that the hollow-core doors actually cost the
contractor $230 and took an extra hour for installation (each). Also assume that the expectation for the
third activity did not change.
Assignment No. 4
A contractor agreed to build 30 doghouses in 90 days at a price of $800 per unit. Twenty days later, the
contractor has finished 8 doghouses with an actual total cost (that includes his overhead and profit) of
$6,800. What is0020the status of the project?
BCWS or PV?
BCWP or EV?
ACWP or AC?
Cost Variance or CV?
CPI ?
SPI ?