Sie sind auf Seite 1von 4

Some Confusing Terminologies.

Analogous Estimating use Expert Judgement (as in the actual


experience from a person) to compare a similar project and provides
rough estimates.
E,g, There's a tall building in front of your house and someone tells you
that the building's construction cost was 100 million. Now you are
asked to calculate the cost of a similar building, which is half the height
of the first building. How much do you think it would cost?
Analogous vs parametric
Parametric use historical data unrelated to type of project (eg. required
Estimating
labor hours to lay a carpet in a room of xx sqare foot) in addition to
current cost of resource (labor hours and carpet cost..).
E.g. It costs $10 psf to install floor tiles. Your house has an area of
1000 sq. ft. How much would it cost to install the flooring in your
entire house?

* Configuration Control is the activity of managing the product (or


project's deliverables) and related documents, throughout the lifecycle
of the product.
* An effective Configuration Control system ensures that:
* The latest approved version of the product and its components are
used at all times.
* No change is made to the product baselines without authorization.
* A clear audit trail of all proposed, approved or implemented
changes exists.
* Change Control is the process of identifying, documenting,
approving or rejecting, and controlling changes to
the project baselines (including scope baselines, schedule baselines,
cost baselines, etc.). In other words, it is used to control changes to all
aspects of an approved project plan. An effective Change Control
Configuration Control vs system ensures that:
Change Control * Proposed changes are reviewed and their impact is analyzed, prior
to approving or rejecting them.
* All requests and changes are properly documented to provide a
clear audit trail.
* Configuration Control and Change Control are distinct in the
following ways:
* Configuration Control addresses the management of the product
(or project's deliverables), whereas Change Control addresses the
management of the project.
* Configuration Control manages changes to the product baseline,
whereas Change Control manages changes to the project baseline.
* Configuration Control is applied throughout the lifecycle of the
product (concept->design->develop/manufacture->service->dispose),
whereas Change Control is applied during the lifecycle of the project
subsequent to establishing the project baselines.
Schedule Baseline is an "approved" version of the Project Schedule
* Project Schedule is a "living" document, whereas Schedule Baseline
is "frozen"
* Project Schedule is the "actual", whereas Schedule Baseline is the
"plan".
* Project Schedule is a Project Document, whereas Schedule Baseline
is a part of the Project Management Plan.
* Project Schedule is updated as the project is being executed, whereas
Schedule Baseline is revised only as a result of an approved change.

* Schedule performance is measured by comparing the actual (Project


Schedule) vs the baseline (Schedule Baseline).
* At the beginning of project execution, the Project Schedule is the
Project Schedule vs same as the Schedule Baseline.
Schedule Baseline * As work is done on the project, the actual progress is updated on
the project schedule.
* At any given date, the latest version of the actual (project)
schedule is referred to as the "Project Schedule".

Few more concepts


* You don't touch the Schedule Baseline except for approved changes.
* Schedule Data includes schedule milestones, schedule activities,
activity attributes, resource requirements, assumptions & constraints
etc.
* Schedule Network Diagram is a schematic display of logical
relationship between project schedule activities.
Enhancing is about increasing the probability of the occurrence of the
event. Here, though the measures will be taken to increase the chance
of happening of the event, but no surety to realize it.
In Enhance Response Strategy, opportunity may or may not be
realized.
Exploiting is about doing everything to make the event happen; i.e. to
make sure that opportunity is realized. Exploit Risk Response strategy
takes the opportunity very seriously and develops an approach to
increase the chance of happening to 100% to realize it.
Enhance vs Exploit
• Enhance - try to realized the opportunity,
• Exploit - ensure to realize the opportunity.
• Enhance - try to increase the probability.
• Exploit - probability increased to 100%.
• Enhance - it can be assumed as opposite of the Mitigation.
• Exploit - it can be assumed as opposite to the Avoid.

Close Procurement
"Close Procurement is the process of completing each project
procurement. It supports the Close Project or Phase Process"
Close Procurement is also known as Contract Closure. A procurement
is said to be closed when contract reaches to its deadline and it ends. A
project can have a multiple procurement contracts, or single contract. If
the project is having multiple contracts then Close Procurement Process
will be performed multiple times with each procurement contract, and
if the project has no contract then there will be no Close Procurement
Process.

Close Project
"Close Project or Phase is the process of finalizing all activities across
all of the project management process groups to formally complete the
project or phase."
Close Project/Phase vs
Close Project or Phase Process is performed when project or phase is
Close Procurements
finally completed and deliverables are accepted. To complete the close
project or phase, close procurement process must has been finished
otherwise project closure cannot happen; however, this is not the case
for Close Procurement where Project Closure is not required in order to
complete the Close Procurement.

Key Points
* Close Procurement must happen before Close Project or Phase.
* Close Procurement can occur many times in life-cycle of the project,
but the Project Closure will be performed once; i.e. at the end.
* Deliverables are accepted in Close Project.
* Every project must be gone through the Close Project process even it
is terminated.
Quality Assurance
* Quality Assurance is a method which makes sure that any process
developed to generate product is such that the product that comes out
from the process must be fit, and conforms to all stated requirements.
To develop the process, Quality Assurance takes input from the Quality
Control Process.
* Quality Assurance is a proactive process, and starts at the very
beginning of the project to understands the stated requirements, not
stated requirements, expectation, and creates a plan to meet those
requirements and expectations.
* Quality Audit is an example of Quality Assurance. Other examples
are training, process definition, and selection of tools etc.
The primary purpose of Quality Assurance is to prevent defects in
deliverables at the planning process stage itself to avoid rework.

Quality Control
* Quality Control is a product based approach and is concerned with
the operational activities and techniques those are used to fulfill the
Quality Assurance vs requirements of quality.
Quality Control * The Quality Control functions starts once the projects work has
begun. It is a reactive approach and helps to find defects in
deliverables. Site inspection and testing etc. are examples of the
Quality Control Process.
* Main purpose of the Quality Control Process is to see if the
deliverables are defect free, acceptable as per quality requirements and
standards set in the Quality Assurance process. If deliverables are not
as per requirements, suitable corrective action will be taken.
* Quality Assurance, and Quality Control processes are dependent on
each other. The Quality Control receives the input from the Quality
Assurance, and in turns gives feedback to the Quality Assurance so that
Quality Assurance could validate the process.
* For example, if the project team finds any defects while executing the
project, it will correct the error by work around and this feedback is
sent to Quality Assurance for further investigation to take corrective
actions in the process so that this error should never happen again in
future. In the same way the Quality Control people will follow the
process defined by Quality Assurance so that these defects do not
recur.

Das könnte Ihnen auch gefallen