Sie sind auf Seite 1von 4

Quarterly Preventive Maintenance Of BSC

Name Of ERICSSON Representative Name Of BSNL official

Sign Sign
1/4
Circle Name
BSC ID
Name Of BSC
Location Quarterly Preventive Maintenance Of BSC
Date of Activity
Next Due Date
Quarter/Phase
Ericsson Comments (if any) :::

BSNL Comments(if any)::

S.N. TASK NAME PROCESS / MML Expected results: Status / Remarks


Complete System Check
1 Software Verification (Patch administration etc. Lasip:block=all;PCORP:BLOCK=ALL;

DPWSP; Units should either be Wo-EX or SP-


2 Monitor the working state of the CP units EX
Check the working states of the IOG/APG I/O IOG Command-immct:spg=0;,imcsp;
3 devices APG--,prcstate –l,cluster node Both node should be working
4 Monitor continuously alarms related to BSC,BTS,etc ALLIP; No active alarms. No Critical Alarms
5 Monitor continuously BSC network PLLDP; And there is traffic utilization.
Name Of ERICSSON Representative Name OfAllBSNL official
the clock & XM should be in
6 Group switch Status GDSTP;GSSTP working condition
7 Monitor redundancy of signaling and traffic. C7ltp:ls=all;m3rsp:dest=all; All links should be active
8 RP Status Exrpp:rp=all; All rp should be working
Sign Sign
9 Check Gb links for GPRS/EDGE. RRGBP; 2/4
Afpls –ls Files should transfer to mediation
10 Charging administration rtrfiles,cdhver,saaep:sae=500,block=chop; properly
Quarterly Preventive Maintenance Of BSC

S.N. TASK NAME PROCESS / MML Expected results: Status / Remarks


19 SWITCHING NETWORK TERMINAL STATE Ntstp:snt=all; All snt should be working
No size alteration alarm should be
20 Check the status of the BSC databases Dbtsp:tab=saactions,PCORP:BLOCK=ALL; present
21 Safe copy the entire BSC software package Fresh back-up should be taken on OD/DAT
22 Monitor the SCCP status. C7ncp:sp=all,ssn=all; SCCP state should be allowed
No devices should be in
23 Check the states of A-interface speech status SPDEP:DEV=RALT-XX; LIBL,MBL,ABL,SEAL
Total number of working Signaling link and their C7ltp:ls=all; links should be in 2,4,8,16
24 utilization. configration
25 Check the synchronization status and mode. Nsstp:,nsdap; All defined synchronization inputs are
26 Monitor the PCM statistics of the ET’s Dtqup:dip=all; All counter values are 0 and if CRC is
Used the availability time is 100%.
Temprature should be below
27 Temperature ,dust, rats entry and door lock, Power threshold & no dust should be present
cable labeling, Earthling check Need to be checked physically on Racks,magazine etc.

28 Local terminal working condition Should be connected


Should not be any power related alarm in
29 Check the DC power supplied to the MSC Rack. the node & Physical checking of EPDU All EPDU should be working

Name Of ERICSSON Representative Name Of BSNL official

Sign Sign
3/4
Quarterly Preventive Maintenance Of BSC

 (This activity should be performed during off Peak Hour/Night)


 Suggestions::

 CP Backup should be taken every week in the OD/DAT.
 Lifeline test should be performed as per schedule.
 Switch should be dust free and proper cleanliness should be done periodically.

Name Of ERICSSON Representative Name Of BSNL official

Sign Sign
4/4