MAIN FEATURES
• Project Information and Cost Estimation (PRICE) is a total solution for estimate
preparation and online approval.
• It is developed by the Kerala Public Works Department with the Technical support
of NIC
• PRICE is based on CPWD Schedule of Rates, Specification, Rate Analysis and
cost index.
• Online preparation of estimates
• Observed data preparation, if necessary
• Online submission of estimates to higher offices
• View of estimate by higher officers and editing
• Digitization of SOR and dynamic generation of data book
• Returning estimates for correction/modification
• Noting observations by subordinate technical staff
• Automatic generation of A.S. and T.S. slips while issuing sanction
• Automatic transfer of details to AS and TS register along with issue of sanctions
• Automatic generation of BOQ which can be exported to the e-tender portal.
• View of current status of an estimate by all officers
• Display of latest Government orders and department news
• An User ID and password will be issued by PWD
• Users should change the password at the first Login

PRICE USER GUIDE ( For OEO) Powered by Pradeepen Thulika Page 1


Password should contain minimum 8 letters and have minimum one Capital letter,
one small letter one special character and an integer.

With this User ID and password you can login to the PRICE

• WEB ADDRESS

http://price.kerala.gov.in/price_oeo_id/about

• FLOW CHART
• CREATE ESTIMATE
• Project details
• Estimation
• Generation of Abstract and Detailed estimate
• Data Analysis
• Forward/ Approval
• CREATE OBSERVED DATA
• VIEW OF DAR ,MORTH, MORD ,LMR etc.

VISIT BLOG

• www.sahaayidotcom.blogspot.com
• From this Blog You will get direct access to various sites Including PRICE.
• New updates are available.
Free down load of Excel tools

HELP DESK
pradeepenthulika@gmail.com

PRICE USER GUIDE ( For OEO) Powered by Pradeepen Thulika Page 2


KEY POINTS

1. Only Assistant Engineers have the power to create estimate files. So there will be an option
“Draft Estimates” and a “Create Estimate” button in addition to the “Inbox” and “Files Viewed
By Me” options.
2. All the fields with red asterisk (*) marks are mandatory.
3. In the field, “Proposed Duration of work” – The actual duration of the work shall be
calculated and given since it appears in the TS Slip also.
4. In “Type of Execution”, if Beneficiary Committee is chosen, the rates will be calculated
without Contractor’s Profit but including overhead charge as per Government Order.

5. Plan/ Non-Plan Work will be active for works other than Annual Plan Works. Although it is
not mandatory, if it is selected, then Head of Account should also be given

6. Sanctioning of Estimates
Project Sanction (AS/FS)

Always use SAVE AND PROCEED button to move from one sheet to another.

(i) In Details 2 sheet, Mandatory Estimate report shall be given


(ii) In Details 4 sheet, in the Declaration Section, the Provisions are adequate should be
checked. Otherwise while creating Observed Data, error will be shown.
(iii) Clicking the “Save and proceed” button will open the estimate sheet.

Estimate Preparation

1) To start the preparing of estimates, click the “Add Heading” button. A heading shall be
given in the description box (Eg: Appendix A, Building Proper, etc). The specification to be
used for preparing the estimate shall be selected from the combo. For each specification,
the CP and OH will be different. So selection shall be based on the needs. If “LS Amount”
is specified, then a detailed estimate cannot be prepared. If electrical estimate is available,
it can be uploaded as an attachment.
2) Using the “Add Specification” button, the different chapters and the specifications in each
chapter can be accessed. Select the required specification and click the “Save” button to
add them to the estimate.

PRICE USER GUIDE ( For OEO) Powered by Pradeepen Thulika Page 3


3) Clicking on the specifications will open the “Add Items/ Measurements” link. Using this link,
measurements can be added to each specification. “Add Measurements” button will help in
entering the measurements and “Save Measurements” button will help to save the
measurements.
4) Using the “Create Observed Data” link on the left top, observed data (OD) can be created.
Use the “New” button the RHS to create a new OD. OD can be created as New or copied
from existing OD or existing specification. The created ODs will be available for further use
of the creator. Others can see this OD only when this file is once forwarded. They can use
this OD by creating a template of this estimate. Approved ODs of PWD, LSGD, Irrigation,
Harbour and Mechanical are added as chapters in the Specification window.
5) Three types of prints can be generated – Abstract, General and Detailed by clicking the
“Abstract” button.
6) To forward the created file to other officers click the “Forward/ Approval” tab. Select “For
TS” or “For AS/FS” as the case may be. Select appropriate action from the Action box.
Select the person to whom the file shall be forwarded. Write appropriate note in the box
provided. The note should be same as the notes in a manual file. Click the “Submit/
Forward” button to forward the file. Once the file is forwarded, it will leave the user’s ID.
But it can be viewed in the “Files Viewed By Me” option in the Home page.
7) The files forwarded by other officers can be found in the Inbox of the receiver. Files can be
opened from the inbox and viewed. For editing the file, click the “Click here to edit the file”
button. The “File History” tab can be perused to get the details of the officers who have
seen the file. The “Notes” section gives the notes written by each officer in an office. An
officer can see only the notes written by other staff of the same office. Any officer can add
or delete specifications to the estimate.
8) Assistant Engineers can use the “Create Template” button along with each estimate to
create a template of a particular estimate which can be used for further similar estimate
preparation.
9) BOQ can be generated on TS approved estimates.
10) “Estimate – Search” can be used to search estimates created in any office of LSGD. The
searched estimate can be viewed and templates can be created from them.

PRICE USER GUIDE ( For OEO) Powered by Pradeepen Thulika Page 4


LIVE SITE PASSWORD CREATION
Here the Live
site of PRICE

Click Here

Enter the
Login ID

Enter the password


given by the Department

Enter Captcha as in
the left box

Enter a new password as you


like.While selecting the password it
should contain minimum 8 letters and
have minimum one Capital letter, one
small letter one special character and
an integer.
Type again for
confirm
Click here

PRICE USER GUIDE ( For OEO) Powered by Pradeepen Thulika Page 5


Click OK

Click OK

PRICE USER GUIDE ( For OEO) Powered by Pradeepen Thulika Page 6


Click OK

Enter Login ID

Login again with


newly created
Password

Enter Captcha as in
the left box

PRICE USER GUIDE ( For OEO) Powered by Pradeepen Thulika Page 7


PROJECT CREATION

Click on
create
Estimate

Select New for creating a New


Estimate and Template for creating
in an existing estimate

PRICE USER GUIDE ( For OEO) Powered by Pradeepen Thulika Page 8


Enter Name
of Work
Select the
Head of
Account.

Click save
Select and fill other details from
combo and click save and proceed

Enter the Estimate


Report

Click here

PRICE USER GUIDE ( For OEO) Powered by Pradeepen Thulika Page 9


Select the details
and save

Click save

Click on add
heading

PRICE USER GUIDE ( For OEO) Powered by Pradeepen Thulika Page 10


Enter the heading

Select the Type of


Specification and
Click OK

Click on add
specification

PRICE USER GUIDE ( For OEO) Powered by Pradeepen Thulika Page 11


Select the sub head

Select the required


specification and save it

PRICE USER GUIDE ( For OEO) Powered by Pradeepen Thulika Page 12


Click on the specification
for adding measurements

Continue the process till


the end of all
specifications

Click on add
Measurements

PRICE USER GUIDE ( For OEO) Powered by Pradeepen Thulika Page 13


Enter the
measurements
and save it

For adding more


measurements
click on + button

If you want to copy a


measurements click here

For pasting click here.


Then you can edit the
values

PRICE USER GUIDE ( For OEO) Powered by Pradeepen Thulika Page 14


Click here

Continue till the end of all


measurements

PRICE USER GUIDE ( For OEO) Powered by Pradeepen Thulika Page 15


For rounding click here. Select
the rounding figure

Enter the details


and click OK

If You want to add


Unforseen items if Click and add
any click here the amount

PRICE USER GUIDE ( For OEO) Powered by Pradeepen Thulika Page 16


For the print of For detailed
estimate click here
estimate Click
here

Detailed
estimate in pdf
format

PRICE USER GUIDE ( For OEO) Powered by Pradeepen Thulika Page 17


Click on data Analysis
here you can see the
data

.you can also


take the print
out from here

PREPERATION OF OBSERVED DATA

Click here for creating


observed data

Click here for


preparing a
new data

PRICE USER GUIDE ( For OEO) Powered by Pradeepen Thulika Page 18


If you want to create
If you want to create from existing DAR
New data click here data click here

If you want to create from


existing Observed data click
here

Enter the
specification

PRICE USER GUIDE ( For OEO) Powered by Pradeepen Thulika Page 19


Select unit
from combo

Enter the Enter qty.


If Market rate
item and rate
enter as MR

Rate will automatically


displayed

Click here for


adding next item

Enter DSR code


in 4 digits Enter Qty.

PRICE USER GUIDE ( For OEO) Powered by Pradeepen Thulika Page 20


Like above
add all items

Enter the
header Qty.

Here You will


get the rate
In the same way you can prepare the Observed data
without cost
using existing OD and DAR index

For adding this OD to


the estimate Click on
home button

Click on Draft

PRICE USER GUIDE ( For OEO) Powered by Pradeepen Thulika Page 21


Select the
estimate

Click on
estimation

PRICE USER GUIDE ( For OEO) Powered by Pradeepen Thulika Page 22


Click add
specification

Select observed
data

PRICE USER GUIDE ( For OEO) Powered by Pradeepen Thulika Page 23


Then click
save

Select the OD from


here

Add the
measurements as
described above

PRICE USER GUIDE ( For OEO) Powered by Pradeepen Thulika Page 24


Click here for
approval

Click for
submission

Select the Officer

Here enter your remarks

Click
OK

PRICE USER GUIDE ( For OEO) Powered by Pradeepen Thulika Page 25


Click
OK

FOR GENERATING BOQ AND TEMPLATE OF ESTIMATE

Click the file viewed by me

PRICE USER GUIDE ( For OEO) Powered by Pradeepen Thulika Page 26


Click
Open

Click
here to
make
template

PRICE USER GUIDE ( For OEO) Powered by Pradeepen Thulika Page 27


Click OK

Click OK. The template is saved.


You can open it while creating the
estimate

PRICE USER GUIDE ( For OEO) Powered by Pradeepen Thulika Page 28


Click here
for generate
BOQ

BOQ Generated.
Click OK

PRICE USER GUIDE ( For OEO) Powered by Pradeepen Thulika Page 29


To see the BOQ click Click here for
here saving the file

Save the file in


your Computer

PRICE USER GUIDE ( For OEO) Powered by Pradeepen Thulika Page 30


PREPARATION OF ESTIMATE USING TEMPLATE

Click for estimate


creation

Click
Template

PRICE USER GUIDE ( For OEO) Powered by Pradeepen Thulika Page 31


Click here for selecting the template
.Here all the templates that you have
prepared are displayed

Enter all the details as described


earlier for the new estimate and
save

PRICE USER GUIDE ( For OEO) Powered by Pradeepen Thulika Page 32


Upload the required
documents

PRICE USER GUIDE ( For OEO) Powered by Pradeepen Thulika Page 33


Here the template estimate and
you can edit the values as you
like

PRICE USER GUIDE ( For OEO) Powered by Pradeepen Thulika Page 34


Send the estimate for
approval or verification
as the case may be

If you are experiencing any difficulty for using this software


mail immediately to
pradeepenthulika@gmail.com

CONTACT NUMBERS

1. Pradeepen Thulika ,AE ,LSGD Division, Alappuzha -- 9446242014

You can download the PRICE User Guide from


www.sahaayidotcom.blogspot.com

THANK YOU
(PRICE USER GUIDE (For OEO) CREATED BY PRADEEPEN
THULIKA)
PRICE USER GUIDE ( For OEO) Powered by Pradeepen Thulika Page 35

Das könnte Ihnen auch gefallen