The purpose of this method statement is to specifically describe the tasks that
company needs to perform when installing Kerbstone and Interlock and all the
additional work to complete the project. Our goal is to ensure the quality and
safety of our work.
This Method Statement describes the methods and procedures to be used for
installing Kerbstone and Interlock on Ground floor and Basement 1 & 2 parking
areas according to project requirements
Material
• Steel Reinforcements measuring 10mm in diameter
• Precast Kerbstone measuring: As Approved
• Interlock Tiles measuring: As Approved
Work procedure
1. Preparation
Before interlock work starts, make sure that sub-grade is compacted
when the area is above natural ground.
The sub-base shall be compacted with vibratory roller, size of roller
shall be suitable for the area where it could maneuver and can move
back and fort.
Once compacted and met the specification requirement for compaction
and approved by Engineer, base course shall then be placed above
compacted sub-base but make sure thickness of the bases are as per
approved drawing.
MEP rough-in or underground embedments (wherever applicable)
shall be in placed before interlock work commences.
In the areas where there are kerb stone, the blinding shall be
constructed first serve as the base but make sure it shall be as per
drawing.
3. Safety
All works shall comply with safety procedure or instruction set out in project
safety plan and Municipality rules and regulations.
Basic PPE to be worn by all staff or laborers.
All operatives involve in this work shall be inducted before entering the
site.
Tool box talk shall be conducted regularly
Interlock cutter
Plate compactor
Wheel borrow
Meter