Beruflich Dokumente
Kultur Dokumente
Management
THEME -5.2: Project Planning: Work
Breakdown Structure, Gantt Chart and
Project Budget
4
Information Technology Project Management, Fifth Edition, Copyright 2007
Project Integration Management Processes
Develop the project charter: working with
stakeholders to create the document that formally
authorizes a project—the charter
Develop the preliminary project scope statement:
working with stakeholders, especially users of the
project’s products, services, or results, to develop the
high-level scope requirements and create a
preliminary project scope statement
Develop the project management plan: coordinating
all planning efforts to create a consistent, coherent
document—the project management plan
5
Information Technology Project Management, Fifth Edition, Copyright 2007
Project Integration Management Processes
Direct and manage project execution: carrying out
the project management plan by performing the
activities included in it
Monitor and control the project work: overseeing
project work to meet the performance objectives of
the project
Perform integrated change control: coordinating
changes that affect the project’s deliverables and
organizational process assets
Close the project: finalizing all project activities to
formally close the project
6
Information Technology Project Management, Fifth Edition, Copyright 2007
Project Integration Management Summary
7
Information Technology Project Management, Fifth Edition, Copyright 2007
Project Integration Management Processes
8
Information Technology Project Management, Fifth Edition, Copyright 2007
Project Integration Management Processes
Good project integration management is critical
to providing stakeholder satisfaction
– Interface management – identifying and managing the
points of interaction between various elements of the
project
The number of interfaces can increase exponentially as
the number of people involved in the project increases
Therefore, the PM must establish and maintain good
communication and relationships with all stakeholders,
customers the project team, top management , other PMs
and opponents of the project.
– This was one of Nick Carson’s mistakes – he did not find
out what top management expected of him as PM and
did not see the big picture
Schwalbe, K. (2007) Information Technology Project Management, Fifth Edition. Austria: Course Technology
9
Cengage Learning (Chapter Four)
Example: Airbus A380 What Went Wrong?
The Airbus A380 megajet project was two years behind schedule in Oct. 2006,
causing Airbus’ parent company to face an expected loss of $6.1 billion over
the next four years. (See http://www.widebodyaircraft.nl/a380.htm)
The project suffered from severe integration management problems, or
“integration disintegration”
– Pre-assembled bundles containing hundreds of miles of cabin wiring were
delivered from a German factory to the assembly line in France
– Workers discovered that the bundles didn't fit properly into the plane.
Assembly slowed to a near-standstill, as workers tried to pull the bundles apart
and re-thread them through the fuselage. Now Airbus will have to go back to
the drawing board and redesign the wiring system.”*
– The problem was caused by factories in Toulouse and Hamburg using different versions
of a design software program which made it difficult for the two machines to
communicate with each other. Top management should have made it a priority to have
all sites use the same version of the software.
*Matlack, Carol. “First, Blame the Software,” BusinessWeek Online (October 5, 2006).
10
Recall Figure 2-5. Level of Process
Group Activity Over Time
The most time and money are usually
spent on executing processes
The Project Control Process
Control
The process of comparing actual performance against plan to
identify deviations, evaluate courses of action, and take
appropriate corrective action.
Project Control Steps
1. Setting a baseline plan.
2. Measuring progress and performance.
3. Comparing plan against actual.
4. Taking action.
Tools
Tracking and baseline Gantt charts
Control charts
What is a baseline?
Budget $28,000
Total costs $ 22,000
Unspent money $6,000
Example: Project Schedule Control
Chart
Project Estimation
Estimating Terminology
In industry and commerce it is common to label the estimate
according to its level of detail and accuracy.
The following estimating terms; concept, feasibility, definitive
and costing, relate quite closely to the project life-cycle phases.
This classification depends on the quality of information
available and the amount of effort put into compiling the
estimate.
Three types of estimates according to their purpose, scope of
work, detail and level of accuracy.
Project Estimation
Conceptual Estimate
Also called order of magnitude, budget figure, ball-park figure.
The conceptual estimate addresses the needs of management who
are presented with a number of possible projects.
They need an initial filter to select those projects that warrant further
investigation.
This would occur in the concept and initiation phase.
Conceptual estimate will be based on a limited scope of work using
scale factors to give a low level of accuracy +/- 25%.
Project Estimation
Feasibility Study
Preliminary estimate or comparative estimate.
It is essential at the outset to determine the needs and expectations of all
the stakeholders.
Although the feasibility study is characterised by information gathering,
processing and reporting, the accuracy of the estimate may still be
somewhat limited at about +/-10%.
Project Estimation
Definitive Estimates
Also called detailed estimate, project control estimate, quotation or
tender.
When the decision has been made to proceed to the next phase, the
design and development phase, or planning phase, this will initiate
another mini project to provide detailed designs and plans to build and
manage the project.
The definitive estimate will be based on considerable amount of data
incorporating a developed scope of work, detailed WBS, detailed
drawing, specification, vendor quotations (that are legally binding) and
site surveys to give an improved accuracy of +/- 5%.
Project Estimation: Accuracy of
Estimate
The level of accuracy is presented as a continuum from conceptual estimate at
25% to closeout report at 0%.
As the graph moves from estimating to costing so the data moves from
historical to actual information, and the level of accuracy increases, but so
does the time to produce the estimate and the associated cost to produce
the estimate.
The relationship between a higher level of accuracy and increasing cost of
producing it.
Although it is not the project manager’s function to set the company’s profit
margin, the project managers does need to know what the profit margin is,
as this will influence the accuracy of the estimate and subsequent level of
control.
Project Estimation
Estimating Costing
(Historical Data) (Actual info)
Accuracy of Estimate
25% 10% 5% 0%
Conceptual Estimate
Feasibility Study
Definite Estimate
Closeout Report
Project Estimation: Costing
If estimating is defined as a quick method for pricing a project based on
incomplete data, then costing may be defined as a detailed price based on
a complete bill of materials (BOM) and parts list.
Costing requires the following items to be complete:
Design and calculations
Scope of work, bill of materials (BOM) and parts list
Detailed planning
Firm prices from subcontractors and suppliers, man-hours and
labour costs.
Almost every aspect of the project must be quantified, and with this high
level of information and effort, accurate quotations of +/-1 can be
achieved.
Exercise 1
– 10 Minutes
Product Breakdown Structure
H.M.S PINAFORE
1.0.0
Media
advertising
1.2.5
Project Estimation/Budget
Project Costs
• A project estimate can be subdivided into a number of different
costs, consider the following:
- Direct costs
- Indirect costs
- Time related costs
- Labour costs
- Materials and equipment costs
- Transport costs
- Preliminary and general (P&G) costs
- Project Office Costs
- Project Team Costs
Project Estimation
Direct Costs
Direct costs are those costs that can be specifically identified
with an activity or project.
The current trend is to assign as much as possible, if not all costs
to direct costs, direct cost can be budgeted, monitored and
controlled far more effectively than indirect costs.
The distinctive nature of direct costs is that the total expense can
be charged to an activity or project.
Project Estimation
Indirect Costs
Indirect costs, also called overheads, are those costs that cannot
be directly booked to an activity or project, but are required to
keep the company operational.
Indirect management costs refer to:
- senior managers,
- the estimating department,
- sales and marketing, accounts,
- IT,
- general office staff,
- secretarial, administration and personal department.
Project Estimation
Indirect Costs
Indirect labour costs refer to
- the reception,
- maintenance,
- security and cleaners.
and
Activity 5 – Advertise
to hire crew and cast
Can
go simultaneously
Questioning the activity duration Activity 10: Cast rehearsal
is shortened by
1 week
84 days
becomes
73 days
Activity 2: Hire publicity director
Duration Uncertainty
o m p (o+4m+p)/6 t [(p-o)/6]2 Variance (σ2)
10 days 12 days 14 days (10+4x12+14)/6 12 [(14-10)/6]2 0.81
for reference
Cons:
× Insufficient time to find a capable publicity director
× Difficult to monitor all the activities on the 2 critical paths
× Some volunteers under pressure may quit
Time Time Cost Cost Crash cost Critical
Activity Normal Crash Normal Crash /day path?
Cons:
× Cost increases by $2,240
× 10 weeks for rehearsal may affect the performance quality
× Volunteers will be under high pressure and may quit
Go for option 2
Hire an extra master builder
Reduce the rehearsal time by 2 weeks, but add an additional half
an hour per day
Use the Vroom’s Expectancy Theory of Motivation to get the
volunteers commitment.
Provide small monetary rewards for volunteers after performance
is over, allocated from revenue.
No formal organisation chart or line of authority, control and
reporting were more challenging - open communication is critical
throughout the pre-production, production and post-production
stages of the show.
Lesson recap
The first step in successfully managing project costs is to have a project
budget that realistically reflects the costs for executing the project.
We have learnt that estimates of times and costs are fundamental to project
success
To be sensitive to the factors and number of factors that influence estimates
To understand various types of costs
We now understood the relationship between costs and schedules / the need
for time based estimates
We have understood the relationship between time and money
The implications of time constrained projects
We have also understood the costs and total implications of crashing in
terms of risk, quality, costs, etc.
As well as the concept of optimum duration / optimum cost projects
We have also understood the process for crashing a project