Beruflich Dokumente
Kultur Dokumente
March 2016
This page intentionally left blank.
Amtrak Engineering Project Management Manual 2016
This manual details how projects are initiated and completed at Amtrak engineering, with specific
emphasis on the role and duties of the Project Manager to ensure that projects are managed safely,
efficiently, cost-effectively, and uniformly. Some key concepts in this manual that are new to the
Amtrak engineering project process include:
• Project Manager will manage the project from design, procurement and construction phase.
• All projects are the direct product of a strategy for continuing development of infrastructure
and capability at Amtrak, and specific funding/grant sources are defined for each project
before it is initiated.
• Projects initiated are a result of strategic planning both internal and external to Engineering.
The PMO ensures that the portfolio of Engineering projects is aligned with strategic planning.
• All projects have a Project Sponsor and Project Manager who own the project from initiation
through close-out.
• All projects are approved for initiation and will be actively monitored by the Program
Management Office, who will team with the Project Manager to provide timely project
performance information to the Project Executive Group.
This manual should be studied and consistently used as a resource and guide by all persons who are
directly or indirectly involved in any of the various phases of Amtrak engineering projects. Although
the primary focus is the Project Manager and the various functions that individual must routinely
complete to safely navigate a project from its beginning to completion, there are many groups within
Amtrak (Grants, Planning, Environmental, Finance, Procurement, Government Affairs) that either
support the Project Manager’s activities, directly partner with the Project Manager or other project
team members on project-related work or rely on information generated by the project management
effort. It is vital that these persons understand how projects are managed, what their role is required
to be and how all key functions within the project management process are to be completed. There
is no room for non-compliance. The processes in this manual are not discretionary or negotiable.
The degree to which specific processes are applied to individual projects is decided through a formal
tailoring process and approved.
Prepared By Approved By
____________________ ____________________
Acknowledgments
The Project Management Manual was developed by the Engineering Project Management Office
at Amtrak under the leadership of Rodrigo Bitar, Chief Engineer. Specialized input was provided
by Rory Beelek, Cynthia Brey, Craig Caldwell, Johnette Davies, Bruce Looloian, Bernard Reynolds,
Michael Stern and Cheryl Stultz in the areas of grants, facilities, environmental compliance, historic
specialist, real estate, procurement and legal. Assistance in reviewing, editing, formatting and
creative services for the document was provided by Tracey Banks, Raven Padgett, Lisa Pulaski,
Mark Schwartz and Marlon Sharpe.
The Engineering Workgroup was developed by the Engineering Department to specify the content
of the manual and oversee its development, while providing guidance and comments on deliverables.
Members of the Workgroup include the following:
In addition to the members of the Workgroup, we acknowledge Engineering staff from their respective
departments for providing additional in-depth guidance in the development of this manual, as well
as comments on deliverables.
Amtrak Engineering Project Management Manual 2016
Revision History
TABLE OF CONTENTS
Introduction...................................................................................................................... ix
Table of Contents v
Amtrak Engineering Project Management Manual 2016
TABLE OF CONTENTS
vi Table of Contents
Amtrak Engineering Project Management Manual 2016
TABLE OF CONTENTS
CHAPTER 10. PROJECT MANAGEMENT DURING CLOSE-OUT
10.1 Formal Closeout Procedures....................................................................................65
10.2 Project Manager’s Responsibilities during Close-Out................................................66
10.3 Financial Closeout...................................................................................................66
10.4 Record Retention Procedures..................................................................................67
10.5 Project Evaluation Reports.......................................................................................68
LIST OF FIGURES
Figure 1-1 Amtrak Organization Chart............................................................................5
Figure 1-2 Operations Organization Chart......................................................................5
Figure 1-3 Engineering Organization Chart.....................................................................7
Figure 3-1 Sample Project Management Plan Outline....................................................21
Figure 4-1 Project Development Continuum Process.....................................................24
Figure 5-1 NEPA Environmental Review Process.............................................................35
Figure 5-2 Information Required for Probable Categorical Exclusion Projects.................36
Figure 5-3 Sample Outline of a Draft Environmental Impact Statement.........................38
Figure 6-1 Value Engineering Study Task Flow Diagram.................................................42
Figure 11-1 Procurement Responsibilities of Project Manager and
Contracting Administrator............................................................................73
Figure 13-1 Work Breakdown Structure—Maintenance...................................................84
Appendix Glossary........................................................................................................115
INTRODUCTION
A
n important goal of the Engineering Department at Amtrak is the successful completion of
projects on time, on budget and consistent with project objectives. As the Project Manager,
you are key to a project’s success.
To assist you in carrying out your responsibilities and to help you in your professional development
as a Project Manager, Amtrak’s Engineering Department has prepared this manual to help you
successfully manage capital improvements, capital maintenance, production and third-party
projects. While Engineering projects vary in size, scope, cost, schedule and type, they generally have
comparable activities, information and documentation requirements that help ensure a quality
project when handled in a consistent manner.
The purpose of the Engineering’s Project and Program Procedures is to provide a concise, easy-
to-understand summary of the Engineering project management process and practices for capital
improvements, capital maintenance, production and third-party projects and includes the progression
of activities and the interaction with other departments and divisions. It includes lists that will help
take you through the tasks involved in design and construction. By following the steps outlined, you
will be better equipped to guide a project to its successful completion.
The design review procedure included in this manual is the procedure followed by the Engineering
Department. Project Managers in other organizations may follow the procedures of their respective
Departments, which may be similar.
Although this manual charts your course, it is only a framework. Every project has its unique
challenges that require leadership and initiative. As the Project Manager, you are on the front line,
working for open communication and cooperation within the entire Amtrak team and are prepared
to meet problems head on when the need arises.
Introduction ix
Amtrak Engineering Project Management Manual 2016
INTRODUCTION
As a Project Manager, you should recognize that projects will advance smoothly if you identify and
communicate with, on a continuous basis, the key individuals within and outside Amtrak who are
needed to advance the project. This document thus highlights both the organizational structure and
the specific departments that are likely to play some role in assisting you to advance a project. As
emphasized here and throughout this document, it is important to recognize that Project Managers
must anticipate issues, identify who and what will be needed to resolve those issues and communicate
continuously with their clients and those who impact the project.
Engineering is committed to supporting you in every way possible. This document will help you
navigate the complexities of project management, ensuring your success and that of the entire
Engineering team.
For new Project Managers, this manual provides a comprehensive look at the whole project
management process. For experienced Project Managers, it is a refresher course and a reminder of
the many elements that go into project management. For both, the checklists, forms and flowcharts
will be helpful.
• Part I provides a brief overview of the Amtrak organization, including definitions of capital,
production and third-party projects, project management, administration and reporting
procedures and funding agency requirements, so that you have an understanding of these as
you begin a project.
• Part II is the core of the manual, the activities that take place at each stage of a project with
special attention to a Project Manager’s responsibilities in managing the work effort and
producing the required project deliverables.
• Part III provides detailed chapters on the standard administrative and reporting procedures
that must be followed at various stages throughout a project. For example, the RFP process
described can be used to procure a professional services firm in the preliminary design, final
design and/or construction management stage.
x Introduction
Amtrak Engineering Project Management Manual 2016
INTRODUCTION
Updates and Revisions
The current manual will be posted on Amtrak’s Intranet for Project Managers under the PMO content
page and under Engineering on the “How We Work” tab.
• Program and Project Procedures — provides specific guidance on how to administer the
various components of your project and to ensure that each Project Manager accomplishes
his/her work in a standard manner. The current procedures will be posted on Amtrak’s
intranet under the PMO content page and under Engineering on the “How We Work” tab.
• Amtrak Procurement Manual — includes detailed information on procurement
methods of solicitation and selection (chapter 3), contract administration (chapter 5),
responsibilities of the Contract Administrator and the Project Manager (chapter 2) and a
list of definitions of terms used in procurement and contract management (appendix C).
http://wiki.corp.nrpc/download/attachments/31457305/Procurement+Manual+-+July+2008.
pdf?version=1&modificationDate=1238081580573
Other documents used as references during the development of this manual include:
• Federal Transit Administration’s Project and Construction Management Guidelines, July 2011
• Federal Transit Administration’s Construction Project Management Handbook, March 2012
• Project Management Institute’s Project Management Body of Knowledge (PMBOK Guide),
2013
• Amtrak Procurement Manual, Amtrak, July 2008
• Other Commuter Agencies Project Management Manuals and/or Guidelines
Introduction xi
Ten Commandments of
Project Management
1. Safety and Security: To set the standard for safety and security in the transportation industry
to ensure that every passenger and employee goes home injury-free every day.
2. Customer Focus: To acquire and retain the most satisfied customers of any travel company in
the world.
3. Financial Excellence: To be profitable on an operating basis (as defined by our operating
ratio) and be good stewards of capital in order to secure our long-term viability as a company.
4. These goals are highly integrated and Amtrak cannot be successful in one of these areas
without being successful at all of them.
Amtrak’s vision is “Moving America where it wants to go.” This Vision Statement communicates
what we aspire to do as a company in a concise and memorable way. When considered from different
angles, this seven-word phrase communicates many different things about Amtrak and our purpose:
• We serve the United States of America, its people and its guests.
• Our job is to connect the communities and economies that comprise our nation.
• We are not just a railroad, we are a company that moves people.
Amtrak responds to the market — as a business we must offer services that are in-demand and for
which customers are willing to pay.
The Amtrak mission is “Delivering intercity transportation with superior safety, customer service
and financial excellence.” This Mission Statement clarifies how we will achieve our vision. As a
company and as individual employees, our job is to provide safe transportation in a manner that
improves the company’s financial viability while ensuring that our customers have a consistent, high-
quality travel experience.
As the nation’s intercity passenger rail operator, Amtrak connects America in safer, greener and
healthier ways than private vehicles or air travel. With more than 20,000 employees and with 21,000
route miles in 46 states, the District of Columbia and three Canadian provinces, Amtrak operates
more than 300 trains each day — at speeds up to 150 mph — to more than 500 destinations. Amtrak is
also the operator of choice for state-supported corridor services in 15 states and for three commuter
rail agencies.
Amtrak continues to invest in critical projects that will enhance the passenger experience, sustain
the national passenger network and provide much-needed capacity.
Corporate Research and Strategy: Provide leadership to all aspects of Amtrak’s businesses and
corporate activities related to strategy development and execution.
Strategic Rail Initiatives: Facilitate alignment of rail fleet planning and major rail fleet initiatives
with corporate strategies and goals.
General Counsel and Corporate Secretary: Maintain Amtrak in legal, regulatory and corporate
governance compliance in all aspects of its organization, business and operations; provide legal
support to all departments and functions; protect Amtrak and its interests in all claims on behalf of
or against the Corporation; and adhere to the highest professional and personal ethics in said work.
The Executive Vice President, Chief Legal Officer, General Counsel and Corporate Secretary serves
as the Ethics Officer for the Corporation.
Finance: Promote sound financial management in support of the goals and objectives contained
in Amtrak’s Strategic Plan through the delivery of timely and accurate financial information,
sound accounting practices, efficient treasury services, effective financial planning and by providing
procurement and real estate development services.
Northeast Corridor Infrastructure and Investment Development: Plan and develop feasibilities
study and real estate development for Amtrak-owned assets to meet the growing needs of all users
on the existing Northeast Corridor and future high-speed rail development.
Police: Direct plan and manage all system-wide functions and operations of the Amtrak Police De-
partment in the enforcement of laws, the prevention of crime, counterterrorism and protection of the
Corporation’s employees, passengers and physical assets. Ensure the implementation of goals, objec-
tives, policies, procedures, the strategic plan, financial management and standards for the department.
Marketing and Sales: Grow ridership and revenue across the Amtrak system through cost-effective,
creative marketing, advertising and sales systems executed in close collaboration with business lines
and state partners.
Government Affairs and Corporate Communications: Serve as the Corporation’s primary liaison
with Congress, agencies of the federal government, many states and localities; as well as the media,
the general public and other stakeholder groups that support the mission of intercity passenger rail.
Serve as a resource to further the missions and goals of the other departments, where those missions
intersect with the entities noted above, and coordinate federal and state policy initiatives.
Human Capital: Lead the development and delivery of organizational structures, talent and lean
processes providing a competitive advantage in delivering the business strategy and reinforcing the
for-profit aspects of financial excellence. Deliver a pipeline of talent fitting Amtrak’s organizational
needs with the right values and competencies. Serve as a catalyst for creating the environment to
attract and leverage human capital.
Information Technology: Deliver cost-effective, secure, innovative technical business solutions that
exceed our customers’ and business partners’ expectations.
Operations: Operate the national passenger rail system safely and securely, while consistently
improving the Corporation’s bottom line by attracting and retaining loyal customers in the most
efficient manner possible. Drive revenue growth for Amtrak by consistently delivering safe, high-
quality travel experiences to every customer we serve and continuously improving productivity with
better tools and processes in order to optimize operating costs. Implement the Accessible Stations
Development Program and seek other opportunities to improve accessibility such as on equipment
and Amtrak’s on-line presence.
Amtrak also has an Office of Inspector General, which directly reports to the Board. This office
performs independent, objective oversight of Amtrak’s programs and operations through audits,
inspection, evaluation and investigations focused on recommending improvements to Amtrak’s
economy, efficiency, and effectiveness. Project Managers are encouraged to report fraud, waste or
abuse by contacting the OIG Hotline at 800-468-5469.
Joseph H. Boardman
EVP/Chief Human Capital Officer Dir Operations and Coordination EVP/Chief Operations Officer EVP/Chief Lgl Ofcr General Counc...
Human Capital/Lbr Admin/Diversit... Presidents’s Office Operations General Counsel & Corp Secretary
EVP/Chief Human Financial Officer EVP/Chief Information Officer SVP Corporate Research & Strategy SVP/Chief Goverment Affairs & Corp
Fianance Amtrak Information Technology Corporate Research and Strategy GACC - Govt Affairs & Corp Comm
Chief of Staff Corporate Safety Advocate SVP Strategic Rail Innitiatives... EVP/Chief Marketing & Sales
Corporate Liaison Corporate Safety Advocate Strategic Fleet Rail Initiatives Marketing and Sales
Senior Executive Assistant to CEO SVP/Chief of Police EVP/Chief NEC Buisiness Dev... VP Emergency Management
Presidents’s Office Police Dept Chief of Police NEC Business Development Dept of Emergency Mgt & Corp S...
Vice President Operations VP, Enterprise Program Manage... Vice President Operations Vice President Research & Planning
Operations Ops Enterprise Prog Management... Operations A Ops Research & Planning
VP & Chief Transportation Officer SVP & General Manager State Sup.. SVP & Chief Mechanical Officer SVP & General Manager Long Dist...
Ops Transportation Office Ops State Supported (SS) Corr B... Ops Mechanical Ops Log Distance (LD) Svcs Bus...
SVP & General Manager NEC Vice President & Chief Safety Officer Vice President Business Operations SVP Chief Engineer
Ops Northeast Corridor (NEC) Bus... Ops Safety Ops Business Operations Ops Engineering
Senior Vice President Operations Senior Executive Assistant Vice President System Operations Vice President Customer Service
Operations Operations Ops System Operations Ops Customer Service
Technical disciplines group create and monitor standards, specifications, policies and procedures for
design, installation and maintenance of assets to improve quality and performance of the following
infrastructure assets:
The Program Management group provides guidelines, project management training and project
control support to Project Managers with a focus on scope, cost, schedule and reporting. The group is
responsible for developing and maintaining processes and procedures to support project integration,
scope, time, cost and communications management, and provides estimates to internal customers
and external partners to assist in the planning, budgeting and staffing of projects. The group also
improves operational performance and cost efficiency by creating, maintaining and distributing
to internal customers and external partners’ performance schedules that reflect all aspects of the
Engineering program.
The Construction group provides construction and project management services to internal and
external stakeholders, ensuring appropriate communication among technical disciplines, front line
personnel, third party contractors and the maintenance organization. The group also promotes
production and quality processes to improve the end product delivered and manages third party
contracts for adherence to scope, schedule, budget and railroad operations.
The Maintenance group maintains the infrastructure to a reliable and safe condition for the
traveling public. The group promotes production and quality assurance processes to improve the
end product delivered and continuously assesses the state of all assets, taking necessary actions to
maintain, improve and drive safety and efficiency. The group also oversees and directs Engineering
Department resources in all construction, inspection and maintenance activities with Amtrak-owned
and/or maintained right-of-way including track, bridges, buildings, communications and signals, and
equipment to provide continued safe and reliable operation of inter-city passenger, commuter rail
and freight trains over the entire Amtrak system.
The Operations Improvement group drives collaboration among Engineering groups and Business
Lines for the purpose of improving the effectiveness and efficiency of Amtrak and, in particular, the
Engineering Department. The group provides the necessary tools for work and asset management
and promotes sound business principles through process development and improvement, reporting,
analysis and business cases. The group also develops the strategic direction for the department,
disciplines and divisions based on Amtrak’s Strategic Objectives and the Chief Engineer’s goals
to acquire, maintain and assign Engineering Maintenance of Way (M/W) equipment and assign
repairmen services.
Rodrigo Bitar
Deputy Chief Engineer Track Deputy Chief Engineer Maintenance Deputy Chief Engineer - Engineer... Executive Assistance
Engr Track Engr Maintenance ENGProjMgmt Ops Engineering
Deputy Chief Engineer C&S Deputy Chief Engineer - Major Ca... Deputy Chief Engineer Structures Deputy Chief Engineer Construction
Engr Communications & Signals Ops Engineering Engr Structures Engr Construction
Senior Director Business Planning... Sr. Human Capital Specialist Deputy Chief Engineer ET Senior Director Business Improve...
Engr Planning & Budgets Engr MAP HC Engr Electric Traction Engr Indust Engrg Bus Improvem...
Throughout the course of a project, a Project Manager will interface with many of these organizations.
Some will provide information that a Project Manager needs to move a project forward; others will
require information in the form of presentations, memos and/or reports. For the most current versions
of the appropriate Amtrak organization charts, please consult with your department manager or
director. They are also available on the Amtrak intranet.
1.7 Funding
Amtrak receives grants and funds for projects from a variety of sources, including but not limited to:
On many projects, the funding agency or funding source requires compliance with certain legal,
administrative and reporting requirements.
A Program is a discrete group of related projects managed in a coordinated way to obtain benefits
and control not available from managing them individually. A program may include elements of
related work outside the scope of the discrete projects in the program. A program may include many
deliverables and usually focuses on business objectives; delivering value and benefits that are not
achieved when handled as an individual project.
A Capital Improvement Project is generally a project that is eligible for capital funding, as defined
by internal guidelines and by outside funding agencies such as the Federal Railroad Administration
(FRA) and the Railroad Rehabilitation and Improvement Financing Program. They enhance the
existing asset functionality (i.e. replacing turnouts with larger size turnouts for higher speed) or
add new assets to the infrastructure for future growth (i.e. additional track, new interlocking, new
facilities, etc. . . .).
A Third-Party Construction (Individual and Corporation) Project is a project in which Amtrak will
provide engineering and force account services for third-party design and construction on Amtrak’s
property or adjacent property. These projects are generally 100% reimbursable by third parties to
Amtrak but there are cases where Amtrak may finance certain portions of the asset improvement.
A Third-Party Protection (Individual and Corporation) Project is a project in which Amtrak will
only provide force account services to protect a third-party general contractor performing work
on Amtrak’s property or adjacent property, specifically flagman and/or A-men. These projects are
always 100% reimbursable by third parties to Amtrak.
A Production Project is a project that is performed primarily by Amtrak’s Force Account labor
using a mechanized system to produce efficient and high-production outputs in short-term durations.
It requires a large number of dedicated production forces, specialized equipment and continuous
outages. Some examples are high-speed surfacing, TLS concrete tie replacement, CWR replacement,
undercutting projects. Production projects may be of a single discipline or a combination of disciplines
working within a discrete location.
Project Management is the process of defining a project in terms of overall objective, scope,
schedule and budget and controlling these elements to deliver a quality project. It is an application
of knowledge, skills, tools and techniques to project activities to meet the project requirements.
The Project Manager is responsible for a project, the project team, and outcomes the team is working
on. The Project Manager will focus on budget, scope content, a schedule, resources, technical tasks,
risk management, project requirements and is responsible for ensuring a project completes on
time and within budget. He/she is assigned by the performing organization to lead the team that is
responsible for achieving the project objectives.
The Program Manager has a greater breadth of responsibilities, overseeing multiple project teams
and being held accountable for the overall outcome of the program. He/she may have some level of
technical knowledge, but is responsible for understanding a wider variety of issues and appreciating
the most salient of those issues and the impact they may have on other projects, the program as a
whole, or other programs. A Program Manager will focus on context, people, politics, negotiating,
strategic tasks, change control management (program and environmental changes), business
strategies and objectives, and is responsible for maximizing cost efficiency and value delivery.
This manual does not apply to non-construction projects. For non-construction projects, the stages of
design may differ based on the type of projects (i.e., Information Technology, Marketing, etc.). In a
To accomplish delivery of a quality project, the responsibilities of the Project Manager include:
• Communicating effectively with clients, consultants, task leaders, project support personnel,
contractors, other Amtrak departments, stakeholders and outside agencies as appropriate.
• Developing a thorough and comprehensive Project Management Plan covering all project
aspects, especially baseline scope, budget and schedule (for projects over $10M). For smaller
projects (under $10M), at a minimum, a Project Management Plan (sometimes referred to as
mini-PMP) will be developed.
• Preparing necessary project documentation, such as project initiation form, approval memos,
status reports, etc., in a clear and timely manner.
• Creating a work breakdown structure and working closely with the schedulers on developing
the schedule.
• Determining human resource requirements and coordinating commitments with Functional
Managers.
• Providing timely input to the accounting system(s) – WebWEE.
• Initiating and participating in design, construction and equipment procurements.
• Managing the work of design consultants, construction managers and contractors.
• Monitoring project status to ensure that project staff, consultants and contractors are working
within project scope, budget and schedule.
• Implementing project design review process.
• Establishing and executing a risk management process.
• Identifying problems before they adversely affect a project and following up to resolve
conflicts, problems and unresolved issues.
• Managing changes to scope, budget forecast and schedule in accordance with the change
management plan and preparing and communicating changes to the project plan. Minimizing
the number of changes.
The Project Manager owns the project until the project is completed and closed out or until the Project
Manager is removed from the project. Ownership means that the Project Manager is responsible for
the successful day-to-day management, final completion of the project and the successful resolution
of all issues that may arise. The Project Manager never gets to say “I do not know” or “That is not my
responsibility.” The Project Manager is the captain of the ship. The Project Manager will ensure that:
• All contract activities are in compliance with the contract and are correctly completed
• All permits are successfully obtained
• All laws and regulations are complied with
• All necessary third party issues are addressed in a timely manner
• All the necessary reports are correct and on time
• All issues are resolved on the spot or elevated to the Program Manager or ultimately to the
Deputy Chief Engineer – Major Capital Projects, Deputy Chief Engineer – Construction for
capital maintenance projects or Deputy Chief Engineer – Technical Discipline for production
and safety specific projects
• All necessary communication is done
• All invoices are properly handled and paid in a timely manner
• All monies due and owed to Amtrak are invoiced accurately, timely and are received timely
• As part of the capital program for rail projects approved by the Board of Directors
• As a request for a feasibility study to be implemented by another Amtrak department or
outside agency
• From the NECIID Major Station Planning and Development (a.k.a. Planning Department),
following a formal planning process
• From a user – a patron or an Amtrak operating department
• As a response to a state or federal legislative mandate
• As a response to emergency conditions
The need can originate within Engineering or other operating groups to satisfy or resolve:
• New regulations
• New technologies
• Permit or legal requirements
• Safety requirements
• Speed increases
• Capacity improvements
Although each project is unique, most projects have a similar progression of activities. A typical
project assignment begins when a project has received funding through the capital programming
process and is passed to the appropriate project management group for implementation. In a typical
project, a Project Manager receives a project after the feasibility study has been completed and
the Project Manager is responsible for taking the project through preliminary and final design,
construction, and start-up.
• By mode – rail
• By type – facility, infrastructure, or equipment
• By construction effort – new construction, renovation, temporary facility
• By project phase – planning, design, construction field services, construction equipment/
vehicle purchase, etc.
A Medium Project is generally a project that has a construction cost of more than $2M, but less than
$10M.
A Large Project is generally a single project that has construction cost of more than $10M but less
than $100M. A large project may require Engineering to obtain permits, perform an environmental
process, require specialized design and construction management staff, perform value engineering
and other items such as Project Management Plan, Peer Review, Risk Management, Constructability
Review, etc.
A Mega Project is generally a project that is over $100M in construction cost. A mega project may
require Engineering to obtain permits, perform an environmental process, require specialized
design and construction management staff, perform value engineering and other items such as
Project Management Plan, Peer Review, Risk Management, Constructability Review, Stakeholder
Management Plan, Communication Plan, etc.
• Professional services or contractor – this method is used for most major projects and the
professional services or contractor is procured through the Request for Proposal (RFP) or
Invitation for Bid (IFB) process
• In-house force account - for projects using Amtrak staff
• Other agency force account – utilities, other railroads, municipalities or other government
agencies (for example, Amtrak may construct a new substation that is used jointly with
Metro-North Railroad or NJ Transit)
The term “force account” refers to the use of in-house forces or staff (whether in-house at Amtrak
or at another public agency) to construct a project.
• Request for Proposal (RFP), used to procure a professional services firm to provide
architectural/engineering/construction management services at Amtrak
• Invitation for Bid (IFB), used to procure a contractor for construction or to purchase
equipment
• Letter of Interest (LOI)
Chapter 12 and 14 – Permits and Approvals, and Coordination with Other Departments/Agencies
Communication and coordination with others is one of the prime responsibilities of a Project Manager,
whether by meetings, memo, letter, report or by filling out forms. In many cases, “coordination” is
legally mandated, as in the case of state and federal agency approvals and permits needed before a proj-
ect can progress past the design stage. For details on the names and types of organizations the Project
Manager typically coordinates with, as well as the overall coordination process, see Chapter 12 – Per-
mits and Approvals, and Chapter 14 – Coordination with Other Departments/Agencies.
• Using generally approved engineering procedures and specifications so that all drawings and
documents are correct, and so that all necessary activities are performed at the appropriate
stage in the project.
• Obtaining reviews, approvals and signoffs from the responsible departments within Amtrak.
There are a number of ways to estimate design and construction management costs. Most Project
Managers use one or a combination of the following methods.
Information supplied by the discipline Deputy Chief Engineers and Project Managers to
Engineering’s Planning and Budget Department is shared with the Financial Planning Department
to develop annual and five-year capital programs approved by the Board of Directors. It is used
as the basis for funding requests to Congress and by the Office of Grants Administration (OGA)
for grant applications and reporting. The Planning and Budget Department is the liaison between
Amtrak and funders on matters regarding the planning, delivery and cost of capital projects pursued
by Engineering. The Planning and Budget Department works with the discipline Deputy Chief
Engineers and Project Managers and Project Sponsors to develop appropriate scope, schedule and
budget data required for Engineering’s overall capital planning, grant applications and progress
reports.
when matching contributions are required). These grants are restricted to achieving specific goals
and usually cannot be reprogrammed to other purposes. These grants may span multiple fiscal years
in order to provide the time and dedicated funding required to achieve their specified goals.
In this competitive environment, it is important to ensure the data provided is based upon a level of
planning and preparation that ensures Engineering, to the best of our ability, can deliver the proposed
projects on time and within budget. Approval of an application and acceptance of a grant award
comes with the expectation that Engineering will implement and complete the project as described
in the application, within the approved project scope, schedule and budget. The project must be
pursued in accordance with all terms and conditions of the application, the funding agreement and
general compliance requirements applicable to grants. While it is recognized that situations change
and it is sometimes possible to revise certain terms of an agreement, it is nevertheless Engineering’s
responsibility to implement projects in accordance with the grant agreement.
3.3 Project Manager’s Responsibilities for Project Proposals and Grant Applications
After a business case has been developed and a project has been included in a capital program
approved by the Amtrak Executive Committee and Board of Directors, the Project Manager consults
with, and provides information to, the Planning and Budget Department, which will work with a core
team comprised of staff from Finance, Law and Grants Administration to identify potential funding
sources and prepare grant applications, where applicable.
Project Managers typically provide the following information to the Planning and Budget Department
for inclusion in project proposals and grant applications:
• Detailed project descriptions, which contain sufficient information for the FRA or other
funding agency to make judgments as to the nature and immediacy of the project and the
specific scope of work to be funded by the application.
• Milestones such as an RFP/IFB advertisement date, anticipated contract award date, vehicle
or equipment delivery schedule and completion dates.
• Projected cash drawdown schedule by month.
• Detailed project budget with cost allocations for engineering internal forces and contract
support forecasts based on scope (task structure breakdown).
• For construction projects at sites eligible for inclusion on the National Register of Historic
Places, a letter from the State Historic Preservation Office advising that the project has “no
effect,” “no adverse effect” or appropriate approvals such as a fully executed Memorandum
of Agreement.
• For construction projects, a justification for a Categorical Exclusion under the National
Environmental Policy Act; or a copy of the FRA approval letter for a Finding of No Significant
Impact (Environmental Assessments); or the Record of Decision (Environmental Impact
Statement).
• Force account plan, if appropriate.
Amtrak conducts internal audits and is subject to monitoring and auditing by the FRA, other federal
entities and the U.S. and Amtrak’s Office of Inspector General. Deviation from an approved project
scope, budget or other grant terms without seeking prior approval can result in compliance findings
with a variety of negative consequences for the company, departments and responsible individuals.
Costs incurred that are not adequately documented, reviewed and approved or are incurred outside
the approved scope, schedule and budget for the project may be disallowed and deemed ineligible
for reimbursement.
Within 30 days of receiving an award, the Office of Grants Administration (OGA) will draft and
circulate a matrix containing the compliance requirements of the agreement and identify the
compliance method and responsible parties. Examples are available on the OGA wiki site: http://wiki.
corp.nrpc/display/FIN/Grants+Administration. Besides the compliance matrices, grant documents
and other resources are available on the intranet site for the OGA.
Project Managers should be aware of these and other resources for their projects and the specific
terms and conditions of the funding source for their projects. The Amtrak Policy and Instruction
Manual on Amtrak’s intranet provide guidance on the general policy requirements for managing
projects within Amtrak’s capital program. Some policies for Project Managers to review include:
grants administration (8.14), capital programming (8.37), equipment control (3.19) and procurement
(11.0).
Project Managers cannot spend funds until approved by Board of Directors during capital
reprogramming request process.
such as: organizational and reporting structure; a detailed budget by task; construction schedule;
document control and record keeping; and quality control/quality assurance. Amtrak must obtain
an official review and approval from FRA of the plan, initially and as changes are made during the
course of the project. Periodic reports on project budget and schedule must be made to the FRA
administrator for the project and/or the FRA Technical Representative, as requested.
Although only major capital projects require a formal written plan, the issues covered in the sample
project management plan outlined in Figure 3.1 should be reviewed by all Project Managers to
ensure that they are properly considered during the course of a project for all capital projects over
$10 million.
4. Stress positives
5. Effective communication
8. Organization is important
These stages are intended to confirm feasibility and merit, so that the commitment of more substantial
resources is confined to initiatives with a high probability of successful execution. The specific work
efforts involved depend on the scope of the project and encompass what is required to comply with
applicable federal and state environmental regulations.
Major projects like prospective new fixed guideway lines or extensions to existing fixed guideway
lines are among the more complex projects and consequently involve the most elaborate work
efforts. These efforts include analyses to fulfill the “major investment study (MIS)” requirements
and the National Environmental Policy Act requirements, culminating in a project concept that is
shown to be feasible and that is sufficiently defined (e.g., site identification and conceptual design) to
set the stage for moving forward with design.
Even for less complex projects, the end result of these early efforts is a finding of feasibility and
sufficient definitional work to describe the project for ensuing stages of design. Since these products
are common to the first stages of a project regardless of scope, it is appropriate to discuss what is
involved in making “feasibility” and “site identification” judgments.
PLANNING ENGINEERING
System Planning
Alternative Analysis
Preliminary Design
Final Design
Procurement
Construction
Operations
Depending on the scope of the project, the result of such an effort can range from a short specific
report to a comprehensive, statewide analysis of services, systems, facilities, materials, etc. (identifying,
evaluating and justifying the need in a specific location).
A similar process could be performed for development of a new service or procurement of equipment.
If a Project Manager takes on responsibility for a project at the beginning of the feasibility study
stage, then the Project Manager will need to gather information from a variety of sources and work
with the user, usually the Maintenance Department.
If a Project Manager takes on responsibility for a project after inception, the Project Manager can
refer for initial information to any planning/feasibility reports prepared by the Planning Department
or by the Maintenance Department. This report should contain most of the information a Project
Manager needs to complete the Project Definition Report and should serve as the basis for discussions
with the user. Occasionally, however, circumstances such as a delay between the feasibility study and
preliminary design or a change in technical specifications will require verification or modification of
this information.
In either case, the Project Manager should meet with and involve the user in determining project
requirements and exploring alternatives relative to cost, time and effectiveness. Where appropriate,
the Project Manager should visit or inspect the project site or subject at key times (peak hours, pull-
in or pull-out times, etc.) to ensure a full understanding of the project scope and/or user needs.
The result of the process will be a formal (but brief) need specific Project Definition Report or a
memo by the Project Manager (or professional services firm if appropriate), including:
Basic project activities that occur during the design stage include:
The scope of preliminary environmental work up to this point is quite basic and attempts to
determine right up front whether the preferred selected site or right-of-way has any fatal flaws.
Typically, more detailed environmental investigations begin during preliminary design and the
project is fairly well-defined. However, this is not always the case. Based on the specifics of a project,
environmental work can:
• Begin in the feasibility study stage and be completed during preliminary design
• Begin and be completed during preliminary design
The Project Manager should coordinate with Amtrak’s Environment and Sustainability Group to
confirm environmental requirements for a project. Detailed environmental studies, if required, are
usually conducted by a professional services firm as part of the scope of work for preliminary design.
Further information on environmental requirements, reviews and permits appear in Chapters 5 and 12.
The end product of the concept plan phase is a Project Definition Report and drawings that will be
used to obtain approvals and funding and guide the subsequent development of the project. This
report will be the basis for the preliminary design.
For projects that are small in scope, the Project Definition Report and Preliminary Design efforts are
often combined to expedite the overall process.
In practice, there will be different applications of preliminary design activities depending on whether
a project is a rail project; a fixed plant or rolling stock project; a simple, low-cost project; or a complex,
high-cost project. But the framework included here provides for a consistent approach to project
management of any capital improvements and maintenance projects.
Often, in developing the design from the Project Definition to the 30% stage, there may be some
redefinition of the Project Definition Report due to new or unexpected data from geotechnical or
other studies, environmental constraints, responses to community concerns, new technical issues or
modification of goals with the passage of time or other factors.
As in the feasibility study, the work is done by a professional services firm procured through the
RFP process or, occasionally, by in-house technical discipline group. See Chapter 11 for details of
the procurement process.
All Engineering projects that receive federal funding or that require other federal approvals (e.g.,
federal permits) require preparation of some level of NEPA documentation. Consult with the
Environment and Sustainability Group or with the Law Department to determine if the project
qualifies for a Categorical Exclusion (CE). If the project qualifies for a CE, Engineering has a pre-
Similarly, all projects must also be evaluated for their impacts on historic resources. Consult with the
Engineering Historic Preservation Specialist for assistance.
For all federally funded projects, the Project Manager should provide sufficient information, working
with the Engineering Planning and Budgeting Department to support the recommended level of
environmental analysis and documentation.
The Project Manager should coordinate with the Environment and Sustainability Group within
the General Counsel Department and the Planning and Budget Group within the Engineering
Department to initially classify projects and to ensure that all applicable environmental requirements,
both state and federal, are defined and eventually satisfied.
Types of specialty studies may include but are not limited to:
• Asbestos/lead sampling and identification – required on all projects involving existing facility
expansion, renovation, rehabilitation or demolition.
• Subsurface (soil/water) sampling and analysis – must be undertaken before any land acquisition
by Amtrak; report should include a map of groundwater and soil sampling locations and
characterization of soil to be excavated as reusable or disposable. Investigations of this nature
can either be included within the project design scope to be performed by the professional
services firm or can be performed on an independent, as-needed basis through the Amtrak’s
Environment and Sustainability Group.
Engineering is responsible for protecting historic resources associated with any project that involves
new construction, demolition, alterations, rehabilitation, sale, primary or secondary encroachment,
permanent signage, easement or lease. Historic resources can include facilities such as station
buildings and associated structures (e.g., interlocking towers), bridges, historic districts, landscapes and
archaeological sites that are listed on or eligible for the State or National Registers of Historic Places.
The Project Manager is responsible for identifying and examining historic issues related to a project
as early as possible and preparing documentation for submittal prior to receiving construction
funding for projects. This identification should occur in the feasibility study or preliminary design
phase of a project and for federally funded work, prior to the submission of a grant application for
construction money. Section 106 consultation must be complete prior to receiving federal approvals
under NEPA.
The Project Manager should consult with Amtrak’s Senior Historic Preservation Specialist during
the preliminary design and throughout the project to assist in discussions with the FRA or other
federal agency, SHPO and other outside parties and the preparation of any relevant applications or
reports. If the project requires the hiring of a Professional Services firm, that firm should have staff
that exceed the Secretary of the Interior’s Professional Qualifications Standards in the appropriate
disciplines (e.g., Architectural History, Archaeology) to assist Engineering with the development
of Section 106 documentation and related services. The SHPO/NEPA questionnaire that must
be completed prior to initiating a project includes questions that will help the Senior Historic
Preservation Specialist assist you with project planning.
There are four steps in the Section 106 process, each summarized below. The lead federal agency
will play a critical role in the process, as the party ultimately responsible. For most projects Amtrak/
FRA will engage the State Historic Preservation Office (SHPO) in the applicable state to review
documentation and, ideally, concur with FRA findings. The Project Manager should engage the
waterfowl refuge or a historic site.1 This report, which includes an alternatives analysis, ensures that
the appropriate planning has taken place to avoid the “use” of a protected property under Section
4(f). Protected resources may be used by federal transportation projects only if there is no feasible
and prudent alternative and all possible planning has been done to avoid the use or minimize harm
to any 4(f) property affected by the project.
Rehabilitation Standards
Rehabilitation of historic buildings and structures, such as rail stations, interlocking towers and
bridges, must be conducted in accordance with the U.S. Secretary of the Interior’s Standards for
Rehabilitation, which provides a framework for maintaining the historic integrity of the structure.
Adherence to the standards typically results in a “no adverse effect” finding under Section 106,
resulting in a relatively simple review process. Preservation Briefs and Tech Notes from the National
Park Service provide specific guidance for roofs, windows, siding, historic building materials, interiors,
rehabilitation, restoration and adaptive reuse. The standards are available online at www.nps.gov/
tps/standards/four-treatments/treatment-rehabilitation.htm. Guidance documents regarding the
approach to rehabilitation and specific issues are also available online at www.nps.gov/tps/standards/
rehabilitation/rehab/stand.htm and www.nps.gov/tps/how-to-preserve.htm.
1 Section 4(f) was originally set forth in Title 49 U.S. Code (USC) Section 1653(f). While still commonly referred to as
“Section 4(f),” the policy has been recodifies at 49 USC Section 303
CE or Other Exemption
Exclusion No
Applies Exclusion
EA
No EIS
EIS Required
Notice of Intent
Scoping Process
DEIS
Agency/Public Review
and Comment
FEIS
FONSI ROD
For purposes of environmental investigation, an FRA or other federally funded project requires
one of three levels of assessment: categorical exclusion, environmental assessment or environmental
impact statement. Determining a project’s classification is not always clear-cut. The regulations
applicable to FRA projects are described in detail in its “Procedures for Considering Environmental
Impacts” (May 26, 1999), “Update to NEPA Implementing Procedures” (January 14, 2013) and
subsequent policies posted in the Federal Register. Project Managers are encouraged to discuss
the project with Amtrak’s Senior Manager Environmental who leads Amtrak’s NEPA compliance
program to assist with determining the appropriate level of effort. The levels of documentation are
described below.
Categorical Exclusion (CE) – If it is determined that the proposed project would not result in
significant adverse impacts, CE documentation is prepared and no further action, other than
permitting, is necessary. Note that FRA has categorical exclusions for many project types that are
routinely undertaken by Amtrak. A typical abbreviated checklist is shown in Figure 5-2.
The FRA has a Categorical Exclusion Worksheet and related guidance on its website (www.fra.
dot.gov/Page/P0550) that will help evaluate the significance of potential impacts to determine if the
project is exempt from further environmental review or if more detailed environmental studies must
be performed. NOTE: A CE under NEPA does not eliminate the need to perform separate analysis
and consultation under Section 106 of the National Historic Preservation Act.
Environmental Assessment (EA) – In cases where the impacts or actions are not known, or there
is potential for environmental impact, a more formal study (EA) is performed. Under FRA rules,
Amtrak may undertake the EA on behalf of the FRA. Regardless, an EA is typically conducted in
close coordination with the FRA and other participating agencies (if any). Note that regardless of
who prepares the EA documentation, the FRA is responsible for the contents and remains fully
in control of the process. At the conclusion of the EA study, Amtrak may receive a Finding of No
Significant Impacts (FONSI) from the FRA. An EA evaluates the potential effects of a project
on the surrounding communities and environment during and after construction. For projects that
require an EA, the process involves the following steps:
• Scoping. The scoping process usually involves meeting with concerned governmental and
other groups to define the project purpose and need and determine the scope of the EA in
terms of subject headings and their degree of detail. Topics that can be included, if relevant,
are: land acquisition and displacements; zoning and land use; traffic and transportation; air
quality; noise and vibration; wetlands; water quality; floodplain and drainage; wildlife and
vegetation; parkland/recreation; historical structures and areas; neighborhood impacts/social
effects; aesthetics and visual quality; utility impacts; and construction considerations.
• Conducting technical studies and producing technical reports. In most instances, the EA is a
series of technical reports followed by a summary report. While a public hearing on the results
of the EA is not required, the documentation is usually compiled, analyzed and published in
a process involving strong public participation.
Final design activities, property acquisition, purchase of construction material or rolling stock or
project construction, cannot proceed until the NEPA process is complete.
Environmental Impact Statement (EIS) – If impacts to the environment may be significant, an EIS
must be prepared. Unlike an EA, FRA rules do not allow Amtrak to undertake an EIS on behalf of
the agency. The FRA generally allows Amtrak to participate in technical discussions with the FRA
and any other participating agencies during the development of an EIS, but Amtrak does not have any
legal authority to influence the outcome of the process. Final design activities, property acquisition,
purchase of construction material or rolling stock and project construction cannot proceed until the
NEPA process is complete. If new information is found or conditions change after FRA approval,
a reevaluation may be required. An EIS may be required for new major construction or extension
of fixed rail transit systems, major bridge replacements or other large-scale projects when there is
an expectation of significant environmental impacts. The process usually begins in the feasibility
study stage with an alternatives analysis; a draft environmental impact statement (DEIS) is prepared
during feasibility study or preliminary design while the final environmental impact statement (FEIS)
is completed during preliminary design.
The key steps of the EIS process are as follows: definition of project purpose and need, alternatives
analysis, scoping, preparation and publications of DEIS, public hearing, selection of preferred
alternative, preparation of FEIS, final EIS and FRA approval and issuance of a Record of Decision.
An alternatives analysis (AA) is required for all EIS studies but for major new transit facilities or
the extension of existing ones the AA must fulfill the prescriptions of the FRA’s “major investment
studies” regulations. Most often the AA is included within the EIS. Amtrak’s Environmental and
Sustainability Group representative can help to define the proper procedures to be followed.
An EIS is also required if the FRA determines that, at any point in the EA process, the proposed
action may have a significant impact on the environment. (The FRA need not necessarily wait until
the EA is completed, especially if a problem is obvious.)
• The EIS includes several sections that are not part of the EA, such as a fiscal analysis and
cost-effectiveness analysis.
• The EIS process is very structured, includes a formal public hearing and requires the
identification and analysis of more alternatives than an EA.
The EIS is produced first as a draft (DEIS) and then as a final document (FEIS). The FEIS includes
more detail on specific mitigation measures and incorporates additional information or modifications
made at the FRA’s request based on public comments on the DEIS. Figure 5.3 presents a table of
contents for a typical DEIS.
4. Transportation Impact
4.1 Transit
a. Service
b. Patronage
c. Farebox revenue and operating deficits
4.2 Highway
a. Congestion
b. Access to stations
c.. Parking
4.3 Freight movements
a. Railroads
b. Trucking and deliveries
In addition to federal environmental and permitting requirements, the Project Manager must ensure
that the project is cleared of state funding requirements for the project in accordance with respective
state requirements.
5.7 Reviews and Approvals at the End of 30% (Go/No-Go Decision Point)
At the end of the 30% design stage, the Project Manager is responsible for obtaining reviews and
approvals of the project plans and specifications, an essential part of the design review process. For
details of the review and approval process, see Chapter 15.
The Project Manager (or professional services firm) should prepare a Final Summary Project
Definition Report to facilitate the review/approval process. The report includes:
• Changes from the project definition documents, including significant design changes
• Updated schedule and cost estimates
• A list of permits received or needed
• Information on project funding
• Operating impacts
At the end of 30% design, following a formal review and approval by all appropriate involved
parties, including the user, a decision is made by the Chief Engineer whether to advance the project
to a final design.
At this point in a project, overall project scope consensus from all internal and external parties,
including local officials, is essential to ensure that no major changes are requested beyond this point.
Engineering can be proud that our modern railway is the best in the world. However, if we are to
maintain this position, we cannot simply sit back and design railway the “old fashioned way.” We
need to constantly strive to improve our standards, methods and philosophy of railroad design. One
way we can do this is to apply the Value Engineering (VE) process to our rail and facility designs. The
VE team looks for the optimum blend of scheduling, performance, constructability, maintainability,
environmental awareness, safety and cost consciousness.
In order to obtain this optimum, Engineering’s capital improvements and maintenance projects over
$10 million in construction costs will conduct Value Engineering (VE) at the completion of 30%
design. Although a formal VE process is required for major projects, VE principles should be applied
to all projects, regardless of size, to ensure a lowest total cost (capital, operating and maintenance)
over the life of a project consistent with the requirement of performance, reliability, maintainability,
safety and esthetics. Figure 6.1 provides an overview of the VE process and flow diagram.
Plan VE Study Prepare for Workshop Prepare Cost, LCC & Energy Models
• Obtains Project Documents Distribute Documents to Team Members: Team Leader Revise Cost Estimate & Prepares:
• Verify VE Schedule & Agenda Drawings, Specifications, Cost Estimates, • Cost Models
• Suggest Format for Designer Presentation Design Criteria, Site Conditions, Utilities, • Identify High Cost Areas
• Outline Project Responsibilities Operation & maintenance Issues • Life Cycle Costs.
• Establish Owners Performances &
Acceptance Requirements Team Members Become Familiar with Project
• Conduct Coordination Meeting
• Identify Project Constraints
• Designer Gives Project Presentation • Identify Areas of High Cost/Low • Quality of Ideas • Rank Idea
• Discuss Owner Requirements Value • Association of Ideas • List Advantages
• Review Project Data • Brainstorm Project • List Disadvantages
• Identify Objectives of Study • Do Creative Thinking • Potential for Acceptance
• Conduct Site Visit List ideas Generated During Function • Individual Thinking
• Examine Project Functionally Develop Best Ideas
Analysis
The value methodology (VM) is a systematic and structured approach for improving
projects, products and processes. VM, which is also known as value engineering, is used
to analyze and improve manufacturing products and processes, design and construc-
tion projects, and business and administrative processes. VM helps achieve an optimum
balance between function, performance, quality, safety and cost. The proper balance
results in the maximum value for the project. Value is the reliable performance of func-
tions to meet customer needs at the lowest overall cost and it can be calculated like this:
Value = Function/Cost
Function is what the product or service is supposed to do.
The best results are achieved by a multidisciplinary team with experience and expertise relevant to
the project being studied. A Certified Value Specialist® usually leads the team to ensure the Value
Methodology is properly followed.
VE is not a design review; rather, it is a cost-benefit and energy analysis that focuses on the total life
of the project. By analyzing the projected costs of a project throughout its life cycle, VE accounts
for the future impacts of higher labor, energy, and material costs, thereby giving Amtrak a full
understanding of the costs and operating requirements they are likely to assume while providing an
opportunity to examine whether there are modifications to design that can lower these costs without
affecting the project goals and objectives.
The VE Process
The first phase, selection of the team and CVS, is followed by three workshop phases: the pre-
workshop (several weeks), the workshop (5 days, 40 hours) and the post-workshop (several weeks).
The process concludes with delivery of the VE report.
The goal of the pre-workshop phase is to gather pertinent information, finalize workshop and post-
workshop agendas and orient the VE team. The VE team:
In the workshop, the VE team evaluates the total project design for high capital as well as operating
costs, presents creative ideas and prepares alternate designs for consideration. The team:
• Gathers information
• Studies other solutions
• Analyzes candidate ideas
• Develops and evaluates alternate design solutions
• Presents recommendations
Amtrak and the professional services firm staff participate in the first and last steps of the workshop
and remain available, upon request by the CVS, during the other steps.
In the post-workshop phase, the CVS prepares the preliminary VE study report and presents the
recommendations to Amtrak and the professional services firm. The report, which must be prepared
and completed in a timely manner so the design effort can continue, should include:
As part of the post-workshop phase, the Amtrak Project Manager and Project Specialists, supported
by senior members of the professional services firm, will respond to each proposed design and accept,
reject, modify or table for further information each of the recommendations.
Following the presentation/implementation meeting, the VE team will prepare the final VE report,
which will respond to comments generated during the meeting and record the disposition of each
recommendation.
VE Applications
Although VE is required at or near the end of 30% design on all projects exceeding $10 million
in construction contract cost, it can be scheduled at any stage, for any value of project design. VE
may also be worthwhile at the 10%, 60% or 90% stages for some projects or for specific areas of
investigation, regardless of the stage.
In addition to Value Engineering, the Project Manager should consider the Peer Review,
Constructability Review and Partnering for projects over $10 million in construction costs. These
items are described in brief detail below.
Peer Reviews can be used to provide an independent critique of the planning, operation considerations
and design products. As the name implies, experienced individuals in the subject matter of the
project (i.e., peers) are provided the necessary background documentation and asked to review
and critique the approaches, findings and decisions reached on any variety of topics relevant to the
implementation of the project. These critiques are intended as independent input to the grantee on
issues that present unique problems. Topics of Peer Review have run the gamut from planning for
operations, project financing, contract packaging and contracting methods of delivery, engineering
solutions to complex areas for design such as bridges or tunnels, O&M facilities, revenue vehicles
and just about any topic wherein an outside critique is desired. These are not normally either as
robust or formal as Value Engineering exercises, and the level of detailed analysis usually is limited
to concepts or functionality, with advice given more in a “lessons learned,” give-and-take critique,
with reference to where or what to look for as additional grantee consideration on developing
work plans or processes. Engineering encourages the Project Manager to confer with other transit
operators and maintenance experts to benefit from their experiences. Learning from others has been
used to review rail extensions, new start projects and the planning of O&M facilities. The purpose of
Peer Review is to improve the performance of the process or product being reviewed. Basically, the
question Peer Reviewers are asked to answer is “can we do this better?”
Engineering encourages Peer Review to be conducted for projects over $10 million in construction
costs and should be held at 30%, 60% and 90% design levels. Project Managers should conduct a
Peer Review of its design in order to validate that the overall engineering and quality objectives of
a project has been successfully addressed. One of the primary objectives shall be to ensure that the
integration of the different systems and disciplines are advancing the project successfully.
The Peer Review team should consist of senior Engineering personnel from the professional services
firm who are not associated with or have had any knowledge or involvement with the technical
details of the project prior to being assigned to the team. The review team may also involve other
transit agency personnel, third party contractors and/or FRA/MTAC personnel. The Peer Review
team personnel should be approved by Engineering’s Project Manager and should include selected
Amtrak personnel. Information and data to be presented during the Peer Review should not be made
available to any member of the Peer Review team prior to the review. The Peer Review discussion
and results should be documented in a report at the completion of the Peer Review.
6.4 Partnering
For projects that have more than $10 million in construction costs, Project Managers are encouraged
to adopt the Partnering concept for the project where multiple stakeholders are involved. There
has been an increasing desire on the part of grantees and contractors to foster an environment that
is less adversarial and based on a desire to achieve mutual objectives. A concept called Partnering
emerged that is aimed at creating an environment where trust and teamwork prevent disputes and
where stakeholders establish bonds to complete a project successfully. Partnering is applicable to
any stakeholder relationships; it involves the grantee and its contractors, including the professional
services firms, construction contractor(s) or equipment supplier(s) or, in some cases, a large
multidiscipline D/B or DBOM consortium.
• Strong commitment by top management to the process, both owners and contractors
• Equity of all stakeholders in the process
• Trust between the parties
• Development of mutual goals and objectives
• Continuous evaluation of the process to ensure that all parties are working toward the goals
and objectives
• A method for achieving timely response to concerns
Partnering, itself, will not eliminate all claims but, when used in conjunction with other claims man-
agement techniques, it may help with claims resolution by encouraging mutual trust and by specifying
mutually agreed upon procedures for resolving issues. Sources of information on dispute resolution and
Partnering are also available from the Construction Industry Institute.
PROJECT
STAGES OF
MANAGEMENT
A PROJECT DURING FINAL DESIGN
A
s in preliminary design, the Project Manager is responsible for overseeing the work of a
professional services firm or force account staffs to ensure that the project remains within
scope, budget and schedule and that all required deliverables are produced to Engineering’s
quality standards.
In the majority of cases, final design will generally continue under the same Project Manager as
preliminary design. Where it may differ in some instances is when there has been a time lag between
the two phases or unsatisfactory performance of a Project Manager during the preliminary design
phase. If a professional services firm is used to perform the design, the same professional services
firm may continue under an extension of the preliminary design contract or a new procurement of
professional services may be undertaken through the RFP process.
Most major design issues should have been resolved by the end of the 30% stage, so that the
final design stage can be devoted to producing the detailed plans and specifications needed for
construction. If any preliminary design issues remain to be resolved, they should be included as part
of the scope of work in final design. The final design stage also responds to and incorporates the
recommendations of value engineering studies, if they have not already been incorporated at the
end of preliminary design.
The activities of final design are generally divided into subtasks for 60%, 90%, 100% and bid
submission, with reviews at the end of each subtask. For small projects, this process may be condensed
somewhat, but there still should be at least one review in final design, usually at approximately 90%
design completion.
The construction documents, including plans and specifications, must be completed and detailed
in order to obtain accurate bids from contractors and manufacturers. To avoid claims during
construction, constructability review of the plans and specifications becomes an important activity
during final design. If a construction management firm is to participate in the project, it is important
that procurement of the construction management firm begins early in the final design stage. This
allows the Construction Manager to participate in constructability review and other services during
final design.
• Site plans at 1”=30’, which show all elements of construction work, with dimensioned layouts,
grades and elevations
PROJECT
STAGES OF
• Construction staging and execution plans as necessary to execute the construction work
• Elevations as necessary to show the layout and configuration of all construction elements
• Typical sections and details as necessary
• Electrical plans showing line diagrams, load protection, typical lighting fixtures and other
electrical equipment (electronics, security)
• Environmental, drainage and landscaping plans
MANAGEMENT
• Signage plans that conform to the Amtrak’s Graphics Signage Standards Manual (2010)
• Title sheet with key and location plans in sufficient detail and clarity indicating the surrounding
areas
• Site plans that indicate:
–– contours at intervals appropriate to the nature of the project (typically 6 inches to 1 foot)
–– property and easement lines, site survey information
–– structures, buildings, pavement types and limits
–– drainage, utilities and other features that define the existing site
–– plan and profile of underground utilities
–– the proposed construction
–– the final site configuration
• Details and typical sections as necessary to define the site work
• Architectural, electrical, environmental, drainage, landscaping, signage and structural plans
as required
• Demolition plans as required
• General provisions (as supplied by Amtrak)
7.5 100% Design Documents (Final Design and Construction Bid Package)
At the 100% design stage, the technical specifications and final plans, which include revisions
incorporated as a result of the 90% review, undergo one final review. The approved plans and
specifications, known as the contract plans or construction bid documents, are then used by Engineering
in the procurement process to solicit construction services and equipment for the project.
• Provides all drawings signed and sealed by a principal of the firm who is a Professional
Engineer or Registered Architect in the State the work is being performed.
• Submits complete design computations and drawings covering all structural framing and
support.
• Provides engineering calculation sheets that are numbered, dated, indexed and signed by a
Professional Engineer in the State the work is being performed.
• Provides a description and proof of the adequacy of the program; design criteria used; loading
diagram; indexed output sheets; and a diagram of all member forces for each loading condition
controlling the design for computations submitted in computer printout form.
• Provides a final design estimate in sufficient detail to facilitate bid analysis upon opening.
• Provides an estimated construction schedule, for Engineering internal use, of the time required
to complete construction, in Primavera P6 format, indicating coordination of construction
activities with other agencies and utilities.
• Prepares a materials list for all long-lead or Engineering-supplied materials and equipment
and materials supplied by the construction contractor.
PROJECT
STAGES OF
Additional services that may be required of a professional services firm as part of 100% design
include:
MANAGEMENT
• Prepare bid document addenda as requested by Engineering
Project Managers should adhere to the manual for the design reviews process, as provided in more
detail in the Project and Program Procedures or as required by the Project Manager.
• Determines the scope of work for the Construction Manager (CM) for the project
• Oversees the operations of the Construction Manager and of any remaining design or
construction assistance functions
• Provides reports as required on construction progress, schedule, budget, change orders, etc.
• Evaluates, approves and processes change orders as required
• Reviews, approves and processes progress payments
• Reviews project schedule on a regular basis, at minimum once a month
• Maintains total project budget awareness and control
• Initiates corrective actions for schedule and budget negative trends
• Maintains contact with the stakeholders and other interested organizations
Whether in-house or contracted, to be most effective, the CM should begin providing services during
final design as a general technical advisor to the Project Manager and professional services team.
Care must be taken to delineate the CM’s scope of work so that it does not duplicate that of the
architect/engineer performing the final design. Generally, the CM functions are to assist the Project
Manager during the final design as a reviewer and advisor on such items as:
• Providing construction inspection, including confirmation that all work is being carried out
in accordance with original or modified plans and specifications and that approved materials
are being used
• Reviewing contractor safety program
• Managing the Change Order process
The size of the Construction Management team and its organizational structure will depend on the
size and complexity of the project, and its overall technical requirements. Whether Construction
Management is performed in-house or by a professional services firm, there should be a clearly
defined scope of work and clear lines of communication and responsibility among the Project
Manager, the Construction Manager, the Contract Administrator, the architect/engineering firm and
the contractor.
• Construction Manager - Directs the activities of all CM field forces and serves as the on-site
Amtrak representative, monitors all contract work and is the day-to-day liaison between the
contractor and Project Manager.
• Resident Engineer or Office Engineer(s) - Prepares field reports, cost estimates, schedules and
other administrative and technical documents and provides input into solutions of technical
problems. Also may assist in negotiation of a change order.
• Inspectors - Monitors the work done and materials furnished. For large equipment or material
procurements, the CM may send an inspector to the manufacturer’s facility.
Often, when substantial completion has been declared, the contractor and/or subcontractors may
still be working in a facility after the end user has moved in. This work should be of a nature that
does not interfere with normal operations of the facility.
The Contract Administrator (CA) and PM will, in a timely manner, work in concert with the
contractor to:
• Achieve final completion and acceptance by Amtrak of all remaining punch-list work.
• Ensure receipt by Amtrak of any outstanding deliverables.
• Resolve any outstanding claims.
• Conclude any audits and negotiate settlement amount.
• Prepare resolutions for extended environmental mitigations after project completion, if
required.
• Initiate the preparation and execution by the parties of the required close-out documentation.
• Process the contractor’s final retainage progress payment for payment.
When all items on the final punch-list are satisfactorily completed and verified by the Project Manager
and Construction Manager, the construction is declared complete and final payment to the contractor is
authorized. The Contract Administrator will solicit help from the Law Department or any other depart-
ment, as necessary, to facilitate timely close-out of the contract.
The Project Manager is responsible for coordinating the activities that lead to occupancy and use of
the facility. During this phase, the constructed facility is tested and accepted as meeting the design
specifications and preparations are made for the user to occupy the facility. Testing should be for all
its systems and equipment. Since coordination of testing and employee training are generally part of
the scope of work for the construction management team, the Project Manager is supported during
this stage of the project by the Construction Manager.
For federally funded projects, the requirements may need to develop a test program plan that
includes:
• Identifying and defining test requirements for materials, equipment and systems. Creating a
test plan and test cases to validate that functional requirements have been met.
• Establishing an administration system to monitor, control, document and report on the test
program status.
• Developing a testing sequence and schedule in coordination with the overall project schedule.
In advance of construction, the test program plan should be completed during final design as it is
likely that some testing may take place during construction as well as in the commissioning phase
of a project.
All testing and commissioning events have documentation (test procedures, checklists, etc.). The
Project Manager should have a defined list of this documentation before the events occur and track
completion through the execution of system and facility testing and commissioning. This ensures
all verification and validation activities are fully completed, results are recorded, findings are
documented and corrective actions are scheduled and completed. These completed documents are
critical in determining the completeness and correctness of the deliverables.
The Project Manager should review FRA Monitoring Procedure 54 – Readiness for Revenue
Operations as reference for requirements and guidelines.
Start-up activities refer to those associated with the initiation of revenue service. For example, an ex-
tension to an existing rail system or operation of a new or rehabilitated rail facility.
The Project Manager should initiate move-in/start-up by establishing and directing a move-in/
start-up committee, whose participants include the Project Manager, Construction Manager and
representatives of the contractor, the end user, utilities, affected or involved agencies, Government
Affairs and Corporate Communications, Marketing and Sales and others as appropriate. Typically,
• Furniture, telephones, computers, and other equipment not included as part of the project
• Safety and security
• Facility maintenance
• Training
• Equipment and systems operating and maintenance manuals
• Utility changeovers
• Special events/community outreach/marketing
• Publicity
• Operational issues
• Cash management/finance/payroll/fare restructuring
• Insurance
• Occupancy permits
• Inventory and supplies, including identification of spare equipment
• Deliveries
• Transfer of responsibility for facility to the using department
Major federally funded capital improvement projects, such as initiation of revenue service on a
fixed-guideway project, may require a start-up plan that includes:
• Organization plan
• Mobilization plan
• Training plan
• Draft operations and maintenance (O&M) plans and procedures
• Draft O&M manuals
• Rules books
• Test plan and procedures
• Budget
• QA plan
• Safety and security plan
• Failure/deficiencies report (after start-up)
• Final O&M plan and manuals (after start-up)
• About two weeks after move-in, the Project Manager should reconvene the move-in
committee to discuss the event. All phases of the move-in should be revisited and discussed,
especially those that experienced problems, surprises, breakdowns, etc.
• Following the meeting, a Lesson Learned Report should be written to document the move-in
and highlight the successful and problem experiences to the benefit of those managing move-
in efforts in the future.
• All physical construction work has been completed and accepted by Amtrak;
• All deliverables required by the contract documents have been received and accepted by
Amtrak;
• All outstanding issues, to include audits or claims, have been resolved;
• All required close-out documentation has been received; and
• Final payment of retainage monies has been made.
Closeout of a project is the process whereby Engineering officially accepts all deliverables as being
complete, including the work of contractors, professional services firm and equipment suppliers. This
is a critical point where the project’s documentation management system (DMS) and dedication to
document control is needed. Project close-out requires accurate and complete documentation to
ensure the project met its deliverables and Engineering should make final payments to contractors.
Without a complete and accurate DMS and commitment to its use during the project, Engineering is
at risk of accepting sub-standard deliverables or making payment when it shouldn’t.
activities are closed out in a timely manner. The Contract Administrator will request assistance from
the Law Department or any other Amtrak departments, as necessary, to facilitate timely close-out
of the contract.
Projects funded by federal grants will involve grant closeout actions by the Planning and Budget
Office. Some federally funded projects may require initiation of closeout within 60 days of project
completion. The Project Manager should notify Planning and Budget when work is complete.
MANAGEMENT
A PROJECT DURING CLOSE-OUT
• Ensuring deliverables have been validated and meet safety and quality requirements
• Ensuring all commissioning and testing activities are completed as depicted in Chapter 9
• Ensuring transfer of responsibility for the facility to the end user
• Ensuring the end user or owner has been adequately trained and possesses all needed
manuals, tools, equipment and spare parts
• Monitoring completion of punch-list items and ensuring stakeholders have signed off on the
project completion checklist
• Verifying issuance of Certificate of Occupancy/Substantial Completion as appropriate
• Preparing project management close-out forms as issued by Procurement inclusive as follows:
–– Form 1 - Certification of Final Completion
–– Form 3 - Contractor’s Release and Waiver of Liens and Claims
–– Form 5 - Certification of Substantial Completion
–– Form 29 - Request to Suspend or Release Contract Retainage
–– Form 33 - Construction Punch List
–– Form 34 - Major Equipment Status, if applicable
–– Form 35 - As-Built Record Status, if applicable
–– Form 41 - Close-out Progress Report
–– Form 52 - Prime Contractor’s Warranty
–– Form 53 - Subcontractor’s Warranty, if applicable
–– AIA Form G707A - Consent of Surety, if a bondable project
Once the above steps have been completed, the Project Manager will proceed with the final closeout
steps:
During project planning, operating costs should have been estimated and programmed. These costs
must be re-estimated prior to the budget cycle for the first year of asset operation. These budget
items must address:
• The annual maintenance cost to support the new asset must be estimated
• Any additional or new budget requirements for the maintenance of the asset must be included
in the next fiscal year operating plan
• Distributing and retaining records as appropriate (including as-built drawings)
If the Procurement, Finance and Engineering Planning and Budgeting Departments agree that all
elements of the project are complete, final payments and retainage are released and the Finance
Department locks the budget so that there can be no more payments against the project.
Administrator for inclusion in the close-out file. Special attention should be given to archiving
documentation regarding warranties, change requests and items or issues that were contentious
during construction.
Contract files pertinent to a contract award shall be retained for the period of time specified by
corporate policy. Records to be retained include:
MANAGEMENT
• Change Requests
A PROJECT DURING CLOSE-OUT
Distribution: One set for the Procurement contract file; one set for department project file.
• As-Built Drawings
Preparation: Prepared/assembled by the Contractor, Construction Manager, Professional
Services firm or some combination of effort, after completion of construction and installation
of equipment. As-builts should be based on marked drawings furnished by the Resident
Engineer.
Distribution: The Project Manager must identify the vital project records and prepare them
for storage in conjunction with the Amtrak Procurement Compliance and Corporate Policy.
One set for Procurement contract file, one set retained by Project Manager for department
project files and one set sent to the end user.
• Warranties
Preparation: Prepared/assembled by the Construction Manager.
Distribution: One set for Procurement contract file, one set retained by Project Manager for
department project files and one set sent to the end user.
The reports below should be prepared in consultation with the end users and interested departments.
Lessons Learned Report: Within 60 days, the Project Manager shall prepare, in accordance with the
final acceptance of the project deliverables or operation with input from the Construction Manager,
a Lesson Learned Report and shall include:
Project Evaluation Report: Within one year from construction completion, the Project Manager
shall prepare, jointly with the end user and finalized in accordance with the final acceptance of the
project deliverables or operations, a Project Evaluation Report and shall include:
Lessons learned can consider technical, managerial and process aspects of the project. They will be
discussed and documented as part of the review, and most importantly, applied to future projects to
lead to greater project success.
7. Accept politics
10. Identify major irritants between you and the contractor and
get rid of them
As a recipient of Federal Railroad Administration (FRA) grant funds, Amtrak is required to follow
the applicable procurement provisions found at 2 CFR Part 200 that set forth standards for use by
recipients in establishing procedures for the procurement of goods and services with federal funds.
These federal requirements are set forth in the APM, Appendix A.3. All Amtrak procurements
(except those funded exclusively without FRA grant funds) must be in accordance with these federal
requirements. On some occasions, Amtrak may receive grant funds from one or more entities other
than or in addition to the FRA (e.g., other federal agencies, states or transit agencies). On those
occasions, Amtrak must comply with all applicable funding requirements.
Additionally, federal grants typically require that certain clauses must be included in contracts
that utilize federal grant funds. The clauses flow down to all levels of the federal funding chain
beginning with Amtrak. The Amtrak Law Department compiled the FRA flow down clauses into
relevant documents (Supplementary General Provisions for Construction and for Non-Construction
Contracts) and provided those to Amtrak Procurement (copies are set forth in the APM Appendices
A.1 and A.2, respectively).
The flow down clauses are not required in certain contracts entered into by Amtrak with any state
or local government entity, including any regional transportation or transit agency, because the
procurement policies and procedures of these entities are presumed to be consistent with the federal
requirements. Furthermore, FRA flow down clauses are not required in contracts with any private
STAGES
PROCUREMENT
railroad companies because these entities typically own the rights-of-way being improved with
federal financial assistance and have in place existing procedures for carrying out such improvements
to their property.
The Procurement and Materials Management Department (Procurement Department) has overall
responsibility for the procurement process and for compliance with all applicable federal and state
OF A PROJECT
laws and regulations regarding the acquisition of goods and services, including all laws and regulations
relating to the use of public funds for such acquisitions. Each of the following topics is discussed in
greater detail in the APM. Only the Contracting Official or the Contracting Administrator (as each
is defined in the APM) is permitted to communicate with vendors prior to award of the contract.
PROCESS AND COORDINATION
The Procurement Department requires a purchase requisition through either SAP for regular
inventory items or through eTrax for non-inventory items. The Project Manager is responsible for
initiating the procurement process that includes, preparing the scope of work; developing evaluation
criteria; selecting a technical evaluation committee; and participating in a review of bids or proposals.
The Project Manager and the Procurement Department Contracting Administrator assigned to the
project work collaboratively throughout the procurement process, ensuring that proper procurement
requirements are followed. As noted above, these include all applicable requirements of funding
agencies (state and federal). Additionally, these include all Amtrak requirements such as Amtrak’s
policy regarding the use of disadvantaged business enterprises.
The Project Manager alone cannot procure services or obligate expenditures on behalf of Amtrak.
Only the individuals identified in Amtrak policies as having contracting authority are authorized
to sign contracts on behalf of Amtrak (see Delegations of Contracting Authority, Exhibit I of
Amtrak Policy 11.39.0 or APM, Appendix B.1). Most often, the Chief Logistics (previous title - VP
Procurement) is authorized to execute contracts for goods and services. The Project Manager should
work closely with Procurement on determining where the procurement falls within the Delegations
of Contracting Authority.
Figure 11-1 outlines the responsibilities of the Project Manager and Contract Administrator in the
procurement process.
Contracting Administrator (CA) - The CA is a duly Project Manager (PM) - Depending on the nature of the
• serving as chairman of pre-bid and pre-proposal • Draft the technical portions of IFBs and RFPs, and chair all
conferences; project review and progress meetings;
• preparing official minutes of pre-bid and pre-proposal • Monitor contract performance to ensure that the technical
conferences; requirements of the contract are satisfactorily executed by
the contractor;
• opening bids/proposals;
• Interpret technical specifications and drawings, and judge
• conducting proposal evaluation and contractor selection the quantity, quality, fitness and acceptability of all parts of
meetings; the work;
• conducting contract negotiation sessions; • Bring to the attention of the contractor all performance
• conducting investigations of bidders’/offerors’ past that is not in compliance with contract requirements,
performance; issue guidance on corrective action necessary to bring
performance in line with contract requirements and
• verifying that any necessary approvals have been secured
thoroughly document all performance problems;
and that the contract is awarded within the limits of the
approvals; • When deficient performance is not corrected, notify the CA
promptly in writing and provide sufficient documentation
• obtaining approvals for award;
for appropriate action;
• managing the non-technical aspects of post-award contract
• Maintain complete records of all actions taken. These
administration, including negotiation of modifications and
records include documentation of all inspections and
supplemental agreements;
should be properly annotated to indicate the contractor’s
• consulting with the Project Manager (PM) to monitor the acknowledgment of any notifications of deficiencies;
contractor’s performance;
• Ensure that the contractor performs no work outside
• managing termination for default or convenience the scope of the contract and complies with Amtrak’s
procedures; requirements and policies;
• consulting with the Supplier Diversity Office on • Inform the CA whenever a condition exists that may call for
Disadvantaged Business Enterprise (DBE) issues; a decision resulting in a change in unit price, total contract
• providing support to attorneys, consultants and in-house price, quantity, quality or delivery schedule;
Amtrak personnel in the event of a claim; and • Make final technical inspection of work and submit
• maintaining all official contract files. appropriate acceptance certificates when the specifications
of the contract have been properly fulfilled;
• Make unannounced spot checks to the job site to verify
compliance with applicable labor standards and contract
provisions. Report the results to the CA for review and
placement in the contract file;
• Develop punch lists prior to job closeout, if required and/or
not performed by the construction manager;
• Maintain control of the schedule and budget; and
• Seek approval for the project, as required. This responsibility
includes drafting and presenting to the approving authority.
The RFP is used to procure professional services, operating services, construction, design/build,
equipment/rolling stock, non-construction and/or non-standard items through a formal solicitation
process that typically involves selection based on technical qualifications and price. Generally, for
capital projects, an RFP is used to procure:
OF A PROJECT
• Instructions to Offerors
• Background information
• Scope of Work (SOW)
• Proposal requirements
• Proposal format and page limitations
• Method of selection
• Time consideration and requirements
• Criteria for technical evaluation
• Criteria for cost or price evaluation
• Criteria for oral presentation, if known at the time of solicitation
• Amtrak’s relevant contractual documents, including supplementary general provisions and
special provisions
• Equal employment opportunity (EEO) specification
• Disadvantage Business Enterprise (DBE) requirements
The key elements of a successful RFP procurement are the SOW and evaluation criteria. The Project
Manager is responsible for preparing a detailed SOW that outlines the nature of the work and the
level of effort required, as well as the expected results or deliverables. This SOW should be written
in clear, precise language so that vendors may prepare proposals based on a thorough understanding
of the work required. The Project Manager also prepares a set of evaluation criteria (weighted by
relative importance) against which proposals will be evaluated.
The Engineering Department has available, for general use, standardized SOW for various phases
of a project. The Contract Agent, working with the Project Manager, coordinates the RFP process,
including:
• Determining contract procurement strategy for all of the phases of the project.
• Awarding contract. The Contracting Administrator completes a staff summary (if needed),
STAGES
PROCUREMENT
obtains approval for the contract amount, obtains approval of the Contracting Official and
ensures that the contract is formally executed. After execution, a kick-off meeting is jointly
organized and chaired by the Project Manager and Contracting Administrator. At the kick-off
meeting, a formal notice to proceed is usually issued. The agenda should include items such
as: project organization structure; communications protocol, construction schedule including
sequence of critical work; change order process; track outage procedures; Amtrak provided
OF A PROJECT
resources/equipment; invoicing criteria; and deliverables, due dates and key milestones.
process. The IFB process is generally used for procurements that are based on detailed specifications,
are not complex and leave little uncertainty to the bidder. This may apply, at the professional
discretion of the Project Manager and Contracting Administrator, for some construction, design/
build or equipment/rolling stock procurement work. A contract is awarded to the lowest responsive
and responsible bidder. IFB’s are not subject to negotiation or change subsequent to bid opening
and prior to execution.
The steps in the IFB process are similar to the RFP process, but given that IFB’s are rarely used
for Amtrak Engineering Procurements, the Project Manager will need to work closely with the
Contracting Administrator in any situation in which an IFB is warranted.
For federally funded projects, a force account plan is needed at the time of grant application. The
Project Manager must identify as early as possible the work requirements for force accounts and
consult with the in-house forces or outside agencies on the scope, schedule, budget and procedures
for such work.
For outside agencies’ force account agreements, there are three types of binding contracts between
Amtrak and other agencies: the force account agreement, the utility agreement and the permit.
• Force account agreements allow Amtrak to reimburse other agencies for Amtrak work on
their property or Amtrak property; sometimes force account agreements allow Amtrak
contractors to enter or construct on other agencies’ property.
• Utility agreements allow Amtrak and its contractors to use agencies such as electric utilities,
water authorities and gas companies to perform relocations and/or abandonment’s on or near
Amtrak property.
• Permits allow entities such as ConEdison to enter upon, use or occupy Amtrak-owned property
to perform work related to their agencies, or to relocate utilities to allow construction.
Force account work may require labor clearance, which may require several months for approval.
The labor clearance determination must be made prior to advertisement for bid.
When emergency procurement action is necessary, the Project Manager must contact the Chief
Logistics Officer, who will determine where the authority resides to approve the requested emergency
action and assist in taking the appropriate actions.
Each permit will bring its unique impact to starting project activities, so each permit should be
individually identified in the project schedule, including sub activities for planning, submittal, approval,
inspections and inspection approvals. Each of these activities has predecessors and successors to be
linked in the schedule. In fact, most are linked to key project milestones. Also, there are associated
costs with these activities that need to be included in the estimate. A determination needs to be
made whether the activity cost is direct to the project or an in-direct, or soft charge, which does not
apply to the project budget. Once baselined, progress of the permit approvals should be monitored
closely for scope, schedule and budget impacts. A good technique is to list them individually on the
Watch Item list for periodic assessment and consideration of elevating to the Project Risk Register.
As an example, a permit may require significant additional environmental protection than initially
planned or retaining of a portion of a building that was to be demolished. These types of changes
driven by permit approvals need to be identified as early as possible in the project. Any commitments
made as a result of permitting or other approvals must be tracked for compliances and execution, as
PERMITSOF
STAGES
The Project Manager is responsible for the timely completion of environmental studies and for
obtaining permits and approvals; in most cases the environmental studies and preparation of permits
will be performed by an environmental firm in coordination with the Project Manager, Environment
and Sustainability Group under the General Counsel Department and the federal, state and local
AND
agencies involved. This chapter covers building, environmental and other permits. Information on
environmental assessments, environmental impact statements, historic preservation regulations and
A PROJECT
The permitting process should be initiated as early as possible to avoid delays. For example, typical
timeframes for permits include:
• A riparian (tidally impacted river bank, lake shore or sea shore) or wetlands issue may take
6-12 months or longer to resolve, depending on the particular project or agency involved.
• Some permits or approvals require pre-application conferences, public notices and/or public
hearings.
• Some permits must be approved 60 or 90 days prior to work commencing. Project Managers
will need to check with federal and/or state requirements.
• Some States may require public notice of the proposed issuance of a draft permit and, if there
is significant public interest, conduct a public hearing.
Following is an overview of the potential environmental permits (limited) that may be required on
• Stormwater Discharge Associated with Construction Activities: The permit regulates the
discharge or potential discharge of stormwater into waters from construction activities,
including clearing and grubbing, grading and excavation activities.
• Control Apparatus Equipment Permit to Construct/Install/Alter; Certificate to Operate: The
permit regulates equipment that emits or controls emission of substances into the air.
• Coastal Area Facility Review Act Permit (CAFRA): The permit regulates the construction of
major industrial, transportation and energy-related facilities in the coastal area, including all
riparian, wetland and tideland acreage.
• Waterfront Development Permit (includes Water Quality Certificate): The permit regulates
the construction, alteration, repair or replacement of docks, wharves, piers, bulkheads,
bridges, pipelines, cables and pilings; the dredging or removing of sand or other materials
from lands under all tidal waters; and limited upland construction adjacent to tidal waters in
many counties.
• Wetlands Permit: The permit regulates the excavation, dredge, fill or erection of structures on
coastal wetlands.
• Freshwater Wetlands Permit/Open Water Fill Permit: The permit regulates most activities in
and around freshwater wetlands, such as removal, excavation, drainage, driving of pilings or
placing of obstructions.
• Stream Encroachment Permit: The permit regulates the construction, installation or alteration
of any structure or permanent fill along, in or across the channel or flood plain of any stream
and the alteration of the flood plain or stream.
• Sewer Systems Permit: The permit regulates the construction, installation, modification or
operation of a sewer system extension including interceptors, collectors, force mains and
pump stations. This permit is required for all construction, which extends an existing sewer
system.
• Disruption of Solid Waste Permit: The permit is required prior to approval of any construction
or excavation activity on or in a closed or existing solid waste land disposal area.
• Well Drilling Permit: The permit regulates the drilling and construction of wells.
Additionally, depending on project location especially for navigable waterways or various wetlands
may require the involvement of federal agencies such as the U.S. Army Corps of Engineers, U.S.
Coast Guard or Federal Aviation Administration (FAA). These organizations must be consulted to
obtain exact requirements and procedures governing projects such as changes to fresh or salt water
wetlands and construction along or over navigable waterways. Federal approval may be required
from the FAA or Federal Communications Commission for construction or alteration of radio
towers. Project Managers are responsible for conducting thorough due diligence to determine what
PERMITSOF
STAGES
identifies the jurisdictional organizations that may impact project implementation and identifies
specific permit issues, which may arise due to project location.
A PROJECT
One of the important project controls tools for cost and schedule control is the Work Breakdown
Structure (WBS), a hierarchical structure that breaks down the scope of the project deliverables
into manageable components for design and construction. Figure 13-1 provides a simplified WBS by
phases into deliverables for a project. The standard WBS shall be adopted for an Engineering project
and the recommended WBS is suggested for the Project Manager to use.
Project
STANDARD WBS
1 2 3 4 5
Planning & Preliminary Testing & Management &
Conceptual Final Design Construction
Design Commissioning Adminstration
Development
MONITORING,
RECOMMENDED WBS
Studies Permitting Control Relocation Start-Up Administration
3.4 5.4
Construction Project
Quality Assurance Communications
& Control
3.5
Construction
Safety
Management
PLANNING ENGINEERING
This chapter discusses the Project Manager’s overall responsibilities relating to monitoring and
reporting schedule, budget and project progress to internal and external stakeholders; WebWEE;
processing contractor invoices and change orders and claims and claims avoidance.
13.1 Schedules
Project schedules guide the development of the project itself; provide other departments and man-
agers with information on the impact of the project on their activities; and provide a method of mea-
suring actual against scheduled progress. It also provides Project Sponsors and other departments
with an accurate budgetary forecast at any point throughout the duration of the project and provides
Project Managers with near and future resource demands. The Project Manager is responsible for
developing and disseminating a project schedule in coordination with in-house and contractor team
members, and then for reviewing and updating progress, including periodic review of Schedule Per-
formance Index (SPI) and comparison of the amount of actual work completed and the budget spent.
Depending on project complexity, project schedules can range from simple bar charts indicating
In the early stages of a project (planning and feasibility study), there are many unanswered ques-
tions and uncertainties to develop a detail schedule. At this stage, the Project Manager will define
initial standardized milestones outlined in the Schedule Management Plan. Typical (and limited)
standardized milestones are start design; complete 30%, 60%, 90%, 100% and IFB design; and start
and complete construction. As additional information becomes known, such as when a design con-
tractor is on board, the schedule should be refined. The schedule should be examined regularly and
updated at the end of 30%, 60% and 90% design stages.
The product of final design (100% design) should include a generalized construction schedule with
milestones and possibly staging requirements. After the construction phase begins, the contractor
and Construction Manager will further define the schedule with details of the construction, testing
and closeout activities.
The schedule shall be detailed, correlate with the work plan described in the scope of work and
organized based on the tasks and major elements of the project. The schedule shall identify all
activities and milestones associated with the Contract’s scope of work. Any change to the schedule
baseline must be managed through a Change Control Request Procedure.
The schedule shall be developed using Project Primavera 6.0 (P6) or latest edition. A baseline
of the schedule shall be maintained at each major update. Progress shall be reported relative to
the baseline schedule. The format of the schedule shall include bar chart plots and shall show, at
minimum, columns for:
• Activity ID
• Activity Description
• Work Breakdown Structure (WBS) Code
• Original Duration
• Early Start, Late Start, Early Finish and Late Finish
• Actual Start and Actual Finish
• Total Floats
The Project Manager is responsible for ensuring schedule specification requirements are part of the
Request for Proposal (RFP) for professional services firm and Invitation for Bid (IFB) for construc-
tion contracts. It is very important for the Project Manager to enforce the schedule specification
requirements are met for both professional services and construction contracts. Releases for invoice
PROJECTOF
STAGES
and/or payment request application should be tied to adhering to this contract requirement.
As part of the contract requirement, professional services firm and construction contractors shall
submit a baseline Progress Schedule and a Monthly Progress Schedule update once the baseline
is approved. The Progress Schedule shall include all current information as of the status date. The
Progress Schedule submittal shall be accompanied by a Schedule Status Report. This narrative
MONITORING,
report shall describe activities completed and progressed during the report period, activities planned
for the forthcoming report period, potential issues, time impact analysis as required and actions
A PROJECT CONTROLS AND REPORTING
required to correct any negative float (actual or predicted). The report shall include an explanation
of potential delays and problems, their estimated impact on performance and their estimated impact
on the contract completion date. In addition, alternatives for possible schedule recovery, complete
with a narrative rationale, to mitigate any potential delay shall be included for consideration. The
Schedule Status Report shall be included in the Monthly Report. No invoice will be accepted for
payment if there is not a current approved Progress Schedule in place.
Timely progress reporting and review by the Project Manager will be critical in avoiding schedule
slippage or delays, which will be detrimental to the schedule given the objectives of the project. At
minimum, the Schedule Status Report shall include the following:
Budgets should include all major cost elements such as design and construction management con-
tractor services, force account efforts, property acquisition, construction, equipment, administration
and contingency. As budgets are updated during the course of a project, the backup calculations and
sources of information should be documented and placed in the project file. Project reporting should
include budget performance, CPI and analysis of contingency reserve.
Any change to the Budget baseline must be managed through an Integrated Change Control process.
Controlling costs due to change is imperative and can be minimized by:
Engineering Cost Estimating Department uses Hard Dollar Estimating Software, a professional cost
estimating tool used in many industries and in particular construction projects, to develop expected
project costs organized by the project WBS. Force account labor (trackman, ET lineman, CS signal
maintainer, etc.) is detailed in every estimate to show what resources will be required to perform the
work along with their associated costs. Hard Dollar enables the user to create and maintain a custom
resource rate library to house all of our labor craft, material and owned equipment rates.
Chapter 16 provides guidelines to help a Project Manager develop the initial cost estimates required
for budgeting purposes.
• Project Progress
–– Activities Completed*
–– Activities Started/Ongoing*
–– Activities Schedule for Following Month
• Critical Issues/Problems Areas/Delays (including problems that may require a change in
MONITORING,
On major projects, regularly scheduled project meetings, involving key team members, should be
established to coordinate design or construction team effort. The Project Manager is responsible for
coordinating progress meetings and ensuring follow-through on action items.
This online reporting system contains information on project name and description, current phase,
baseline budget, schedule, milestones, completion date(s), monthly accomplishments, change or-
der(s), outstanding issues and funding data. It provides screens for input to the FRA Quarterly Prog-
ress Report, Project Status Report (Chief Engineer’s Report), and for additional notes on the project.
Instructions for access to and use of the system are found on the Amtrak Intranet.
The initial loading of information into the system is accomplished during the Project Initiation
process. The Project Manager works with the Engineering Planning and Budgeting staff to set up
the project budgets, by WBS and phase that are required for input into the system. The Project
Manager should review the WebWEE project information periodically, and update the project
information as necessary. Allowable adjustments include moving budgets from one WBS to another,
updating project progress, etc. Earned Value Management metrics are reported in WebWEE – [Cost
Performance Index (CPI) and Schedule Performance Index (SPI)]. CPI and SPI provide integrated
status on schedule and budget. Rules for reporting earned value, such as percent complete, are
defined in schedule and cost management plans.
The Engineering Planning and Budgeting Department can provide guidelines on use of the WebWEE
system and the required Project Manager input.
Professional services firm should submit at least two copies of their monthly invoices, one for
submittal to Accounts Payable via eTrax and one for the Project Manager and files. Invoices should
be submitted monthly within 15 working days of the end of the calendar month. This schedule allows
PROJECTOF
STAGES
for immediate identification, acknowledgment and attention to problems and tight, monthly control
and monitoring of project budgets and schedules.
Professional services firm and/or sub-contractor monthly invoices should include the following:
• Cover letter clearly stating project name, contractor name, client name, contract number,
MONITORING,
purchase order number and request for payment under the invoice
• Copy of contractor’s monthly status/progress reports for billing period
A PROJECT CONTROLS AND REPORTING
The Project Manager thoroughly checks the following before approving the invoice and forwarding
it to Accounts Payable:
Except for where non-professional services are involved, detailed labor, overhead, and direct expense
charges should also be provided and reviewed for second- and third-tier sub-contractors.
The Project Manager should never recommend incorrect monthly invoices for processing. It is the
responsibility of the Project Manager to ensure that all major charges for the month being invoiced
are included or identified every billing period. This is the key to project budget monitoring and
control. However, the Project Manager has some latitude in approval, depending on the terms of the
contract. If only a single item is questioned and the resolution may be lengthy, approval can be given
for the rest of the invoice. The Project Manager should draw a line through the questionable billing
amount, place a new number underneath and attach a memo to Accounts Payable explaining the
action. The professional services firm is also copied. When the matter is resolved, the professional
services firm should acknowledge the corrected amount or be paid the original additional amount
on a subsequent bill.
Once an invoice has been deemed complete and accurate, the Project Manager approves the
receiving report and arranges for approval by Amtrak management empowered to release the funds.
With approval by the Project Manager, Accounts Payable is able to process the invoice in a manner
All payments are subject to a final audit. No questionable or unauthorized services or expenses
should be paid for up front with the intention of future invoice adjustments. All such issues should
be resolved before payment is processed.
Amtrak analyzes each request to determine a basis for negotiation by the Procurement Department
and the availability of project funding. Change Control Procedure describes the process for analyz-
ing the impact of individual changes requests and the approval process, including the identification
of a Change Control Board (CCB). A log of all change requests and their status is maintained for
the project.
The Project Manager is responsible for analyzing the cost of the change order request and submitting
it to the Procurement Department. The analysis includes a comparison of estimated additional
man-hours, costs and fees with the requirements of the original contract. This serves as a basis for
negotiation with the contractor as well as justification that the price is fair and reasonable, in terms
of both cost and work time.
Once a negotiated settlement is reached, the Project Manager, in conjunction with the Contract
Administrator, must submit formal documentation for the proposed change to the Procurement
Department. This change order package should include:
• A cover sheet summarizing the need for the change and pertinent details of the negotiation
• A copy of the price proposal and any possible time impacts
• The independent engineer’s estimate and analysis of submitted price proposal
• Any other necessary information, such as time and material records, invoices, subcontractor
quotations
Appropriate financial adjustments must also be made to related contract documents, such as purchase
orders, funding form and budget forms, if required. If the contract has been Board approved, the
Project Manager should confirm that the change order execution will not exceed the authorized
approved contract limit.
Major changes of scope and/or revisions to task budgets within a set contract amount are not
PROJECTOF
STAGES
permitted without the processing of a formal “no-cost” change order and are subject to approval by
the Procurement Department.
Change orders cannot be implemented until the Procurement Department Contract Administrator
is satisfied and a written authorization to proceed is sent to the professional services firm. In selected
cases, a Letter of Intent or directive letter may be issued to avoid costly project delays or unnecessary
MONITORING,
cost increases.
A PROJECT CONTROLS AND REPORTING
The Contract Administrator is responsible for ensuring that change orders, back-up documentation,
applicable engineer estimates, cost analysis, descriptions and any other related information are
included in the contract file as the permanent record.
The Project Manager is responsible for ensuring the project baselines for scope, schedule and budget
are updated to reflect approved change requests.
In addition, to avoid design claims, Project Managers are responsible for monitoring the professional
services firm’s work to ensure that it is on schedule and within budget. Monitoring should include:
The Project Manager is responsible for ensuring that Engineering does not request extra work of the
• Design error
• Unforeseen site conditions
• Owner-initiated changes
Design errors must be eliminated to the maximum extent possible during the design process. Care
must also be taken to ensure that the design can be built. In general, materials and methods should
be time proven, underground conditions should be thoroughly investigated, drawings should be
checked and double-checked for proper coordination of trades and a thorough constructability
review should be conducted by either in-house or external Construction Management staff. Issues
raised during the bidding process, relative to the design, should be resolved before bids are accepted.
Changes related to unforeseen site conditions for new construction (generally involving underground
features) usually can be avoided by a thorough investigation of subsurface conditions. There are
methods available to search for underground tanks, subsurface contamination and utilities. Change
orders to remove unsuitable materials, contaminated soil, rock and unknown concrete structures
are especially expensive. In almost all cases, these can be identified before bidding with a thorough
boring and sampling program. In rehabilitation work, it is more difficult to identify what may lie
behind walls and under floors. It is often impractical to partially demolish the structure to determine
all of the existing conditions. Nevertheless, careful review of as-built drawing files, discussions with
long-time company employees, careful mapping of utilities both inside the building and underground
and carefully worded specifications and drawings can minimize unforeseen site claims during
rehabilitation projects.
Owner-initiated changes should be implemented only when it is in the best interest of Engineering
and Engineering can reach an agreement with the contractor on contract price and time impacts
before authorizing the work. The Project Manager should attempt to avoid internally initiated
changes to construction contracts whenever possible.
Although the above three categories include most of the changes encountered during a typical
PROJECTOF
STAGES
construction project, there are several other types of changes that the Project Manager should be
able to avoid with careful planning and attention to detail. These include changes related to:
• Maintaining operations
• Narrow interpretation of plans and specifications
• Excessively rigid specifications
MONITORING,
• Vague requirements
A PROJECT CONTROLS AND REPORTING
Extensive discussions and written agreements are necessary to ensure there is agreement between
the Project Manager and the Maintenance, Mechanical and Transportation Departments regarding
maintaining and operating the railroad during construction. These agreements can be sign-offs
obtained during the design review process, Memoranda of Record or minutes of meetings. The
important point is that these departments’ staff must understand exactly what the project is and how
it will impact the maintenance of operations. Stakeholder requirements, especially the requirements
of end users, should be clearly and accurately captured. The Project Manager also needs to ensure
that specifications are reasonable and clear. Various contingencies that may occur during the
construction should be covered in the construction documents, perhaps using bid allowances or
options. In many cases, using unit pricing can take care of unforeseen site conditions or contingencies
during construction.
If it is not possible to avoid claims, it is often possible to hold them to a minimum and to resolve
them as they arise. The Project Manager must coordinate closely with the Construction Manager
and Contract Administrator to resolve all disputes in as timely a manner as possible. Project and
construction meetings are a proper forum for identifying, listing and resolving all potential changes.
The earlier an issue is negotiated and settled, the less it is likely to cost.
This chapter identifies additional departments and agencies that the Project Manager may need to
interface within the course of a project. All projects exist due to a business need. The representatives
from the business lines are best suited to ensure the completed project achieves the business need.
In addition to the departments detailed in this chapter, the Project Manager should identify and
coordinate with the relevant stakeholder(s) from the four Amtrak business lines: NEC Operations,
Long Distance Services, State Supported Services and NEC Infrastructure and Investment
Development.
Other agencies or departments will complete activities that should be represented in the Project
Schedule. For example, results of community outreach and real estate acquisition have direct impact
to Preliminary Design outcomes. By identifying these activities in the Project Schedule as successors
to the Preliminary Design, design criteria will be more accurate and reduce risk for design change.
The Planning and Budget Department of the Engineering Division is responsible for carrying out
the capital programming activities that precede project approval and funding; preparing grant
applications to federal and state funding agencies; initiating funding in WebWEE; providing general
grant compliance administration; gathering information and submitting the ongoing reports required
once a grant is received; and assuring that Engineering complies with the requirements of the grant.
OF A PROJECT
• The Project Manager is responsible for preparing adequate project definition documentation
for a project to be submitted for capital programming, including scope, budget, cash flow
projections, schedule and other information.
WITH OTHER DEPARTMENTS/AGENCIES
• Planning and Budget is responsible for consulting with internal and external stakeholders
including Technical Disciplines, Construction, Maintenance, Operation Improvements
and other operating departments during the programming phase to ensure that adequate
information is available to make Engineering capital investment decisions and is responsible
for developing annual and five-year capital programs.
• Business Improvement is responsible for ensuring that annual goals are communicated
throughout Engineering through the strategic planning process, leading to the establishment
of priorities for capital projects and programs.
• Engineering Budget and Planning is responsible for issuing annual budget instructions and
developing the operating budgets.
All of the above individuals or departments are responsible for ensuring that obligation schedules
are prepared for inclusion in the annual consolidated budget.
Additional information on the Planning and Budget Department and various funding sources is
found in Chapter 3.
All federal and state-funded capital improvements projects require a community information/
community participation process of some nature. In these projects, an Office of Government Affairs
representative is assigned to the project team at the earliest stage of a project; the earlier the
involvement, the better the opportunity for anticipating potential concerns of the community and
for planning how to address those concerns. Elements of a community information plan typically
include mailings, newsletters, community presentations and meetings with advisory groups and
14.3 Communications
Because many Engineering projects are of interest to the public, Project Managers must know how
and when to release information to the media. The Office of Communications, under the Government
Affairs and Corporate Communications Department, which publicizes projects as required and
responds to all media inquiries, is an important resource in generating positive publicity for a project.
Project Managers should contact the office early in project planning, identifying them as the project
contact so that questions/inquiries can be referred for timely response to the media. This office’s
primary function is to promote enterprise-wide communication to educate employees, the public
and representatives of the media about Amtrak operations through multiple channels including
STAGES
COORDINATING
• Handles all media requests to photograph or film projects or gain access to Amtrak property
If contacted directly by the media, the Project Manager should immediately refer the call to the
Office of Communications. The Project Manager should never respond directly to media inquiries
unless otherwise instructed by the Office of Communications.
14.4 Office of Finance & General Counsel and Corporate Secretary Administration
Insurance risk management involves ensuring all assets and projects to properly protect Engineering
from exposure to loss. Amtrak has a comprehensive Enterprise Risk Management Policy and
Instruction Manual 1.8.0 in place to minimize our exposure to risk. The Project Manager should
involve the Office of Treasury Services under the Finance Department in project reviews as
outlined in Project and Program Procedures. Topics of interest to Risk Management and Claims
Administration for a project include:
The Project Manager should consult with the Office of Treasury Service early in the project design
phases to determine potential exposures and appropriate actions that will minimize risk and/or
losses. The Office of Treasury Service determines which projects warrant attention.
The Project Manager will work with Engineering Planning and Budgeting, who will work with
Finance on pre-bill and invoicing for third party projects. This will include dispute resolutions.
The SAP system, including WebWEE, is the financial system of record. Tools such as WebWEE and
SAP BPC can be used for providing data for reporting progress performance.
The Project Manager is responsible for confirming Amtrak’s property rights (fee ownership,
easement, lease, etc.) and identifying, as early as possible, potential property acquisitions associated
with a project. It is essential that necessary properties not already owned or otherwise legally
controlled by Amtrak be obtained in a timely, orderly and legal manner prior to the award of the
construction contract. Federally assisted construction projects are subject to the legal requirements
of the Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970. All costs
associated with property acquisition must be borne by the project.
Because property acquisition is considered a long lead item, early action is required and usually
involves the following activities, which take place during the site selection phase of a project:
Once the project is approved and funded, the actual property acquisition process begins, comprising
the following basic steps:
• Detailed identification of properties to be acquired, maps and plans prepared by the Project
Manager, professional services firm, surveyors, etc.
• Selection of a third party appraisal and receipt of the appraised amount
• Negotiation of a purchase and sale contract
• Initial deed research as part of survey work
• Title report by outside companies
• Notification to owners for access to property for surveying, soil testing and other work deemed
necessary as allowed by the purchase and sale contract
• Environmental testing and report by consultants
• Environmental report review by Amtrak’s Environmental and Sustainability Group
• If no Amtrak and a property owner are unable to reach agreement and Amtrak complies
with the applicable statutory requirements (49 U.S.C. §24311), Amtrak may proceed with
condemnation of the property
Transportation
• Securing Amtrak Board approval (the timing of Board approval varies with the specific
nature of the project, i.e., number of parcels required). Board approval would be part of the
project approval and should already be in place at this time
• Securing of ownership of property through negotiated agreement or condemnation
OF A PROJECT
Amtrak has agreements with all occupying utilities, which specify relocation fees and/or other
particulars. The Project Manager must check with the Real Estate Development to determine utility
locations within a project area and to verify required actions. Real Estate Development will review
pertinent documents to determine any rights Amtrak may have to demand cancellation or relocation
WITH OTHER DEPARTMENTS/AGENCIES
of the utility.
The Project Manager from Engineering will work with NEC IID planning on the following tasks:
• Any communications with the Northeast Corridor Infrastructure and Operating Advisory
Commission (NEC Commission) regarding project activities.
• Projects resulting from short-term, long-term and future comprehensive infrastructure
investment programs and service plans to accommodate projected train volume, travel time
and reliability goals of all NEC users of Amtrak infrastructure.
• Conduct feasibility study and collaborate with Engineering to develop concepts for station
and facilities in coordination with business lines and commuter users to determine necessary
interface with railroad infrastructure and to ensure such facilities are sized to accommodate
projected needs.
• Develop and coordinate the publication of the annual NEC Capital Plan and related Capital
Program.
• Coordinate the development and refinement of NEC infrastructure and capital investments
with and among Amtrak Engineering, the operating business line and other users to ensure
alignment with the goals and objectives set forth in the strategic plan and recommendations
of the Northeast Corridor Commission, and others.
• Train slot planning for Amtrak infrastructure with the operating business lines and other users
for both existing and new services through network simulation modeling and development of
future train schedules.
• Develop and facilitate plans for the efficient operation and expansion of the Northeast
Corridor/Harmonize state and local project initiatives and agreements affecting NEC Assets.
• The results of feasibility studies and Project-level National Environmental Policy Act
The Project Manager works with NEC IID Management Service on the following activities:
The DRP is critical to the success of the project. The Project Manager is responsible for coordinating
the process, ensuring that requirements are addressed as part of the design and ensuring that
additional requirements are not introduced.
This chapter provides a brief overview of the design review process for capital and non-capital
projects in the Engineering Department. Details can be found in the Project and Program Procedures.
During project definition, the DRP involves the end user in exploring and evaluating project
STAGES
DESIGN REVIEW
alternatives, defining design objectives and criteria and developing a clear definition of the work to
be done.
During design, the DRP generally takes the form of design reviews and approvals by end users,
technical experts, subject matter experts, technical discipline and department heads. Design review
should cover the following fundamentals:
OF A PROJECT
• Quality of design
• Building code compliance
• Identification of errors or omissions
• Meeting operational and functional objectives, including safety
PROCESS
During construction, the DRP should verify, through field testing and inspection, that:
• Equipment, supplies and construction work performed complies with the contract documents
• Changes or modifications are approved and documented
• All equipment is tested throughout development, manufacture and installation
• Problems are detected early and positive corrective action is instituted
• The completed project meets operability and maintainability requirements
This information is provided in a Lessons Learned Report, which involves input from the end user.
The Lessons Learned Report is prepared within 60 days after the project has been put in use. The
Project and Program Procedures provides additional information on this report.
It is important to keep in mind that some projects do not require a design phase, begin with minimal
planning and go straight to execution. For these types of projects, construction estimates are still
required prior to work commencing. It is important to note that for projects that are funded by an
outside entity (i.e., states, cities, DOT’s, freight railroads, etc.), the Project Manager may be involved
with the estimate presented for or as part of an agreement. In these cases, the Project Manager
should consult Finance to validate that they are using the proper overhead rates that will be billed
to the outside entity.
The initial cost estimates developed as part of the project budget are typically completed as a Rough
Order of Magnitude. As planning progresses with fewer assumptions in regards to scope, time and
resources, a budgetary estimate can be completed. When the project scope is fully defined and the
work breakdown structure is completed, a detailed estimate can be completed. This progression to
the most accurate estimate directly aligns with progression during the design phase. Additionally, as
depicted in paragraph 16.4, contingency reserves are adjusted as estimates become more accurate.
Project Managers should be prepared to complete a detailed estimate for each change request or
change order during project execution.
The Project Manager is responsible for developing the initial design and construction management
cost estimate. This estimate is prepared very early in the project, which is required for budgeting and
planning and can be used for grant applications. The Project Manager is also required to provide a
design cost estimate to the Procurement Department as part of the information needed for the RFP
for design, and similarly a construction management cost estimate as part of the information for the
OF AFOR
There are a number of ways to estimate design and construction management costs. Most Project
Managers use one or a combination of the following methods.
PROJECT
In the past, a percentage of the construction cost was widely used to estimate design costs for the
preparation of drawings, specifications and other contract documents necessary for the construction
of Engineering projects. This method can be used for very rough, order-of-magnitude estimates.
The guidelines provided below should be utilized with caution and Project Managers should verify
their validity based on Engineering’s recent past experience on similar projects.
Currently used guidelines for estimating design and construction management costs for Engineering
projects, as a percentage of construction cost, are:
Some additional services that can increase the design and CM costs are:
• Feasibility studies
• Field investigations and engineering data collection
• Geotechnical engineering
• Toxic and hazardous waste evaluations
• Environmental evaluations
• Environmental assessments and impact statements
• Value engineering
• Safety engineering
When planning the design phase of the project, these services should be documented in the project
scope, captured in the work breakdown structure and estimated accordingly.
Equipment cost estimates must factor in a cost escalation based on the time the equipment is
expected to be ordered.
The Project Manager is responsible for preparing construction cost estimates for physical
improvements to Engineering infrastructure, facilities and properties. These estimates should reflect
the average estimated cost of construction, not the anticipated low bid. Typically, the Project Manager
PROJECT
develops preliminary construction cost estimates early in the project for capital budgeting and grant
purposes and professional services firm develop more refined construction cost estimates as part of
the design scope of work and bid package preparation.
ESTIMATING COSTS
In early work, construction cost estimates may be based on rough parameters, such as total square
footage of structure or total linear footage of railway. As design work progresses, and as the indi-
vidual construction elements are designed and finalized, the estimates will become more detailed
and accurate.
Following are some of the sources that can be used to establish construction cost estimates when
work will be performed by a third party:
The above sources, particularly Means and Dodge, provide details on labor rates and productivity as
well as material costs, which are especially useful in preparing change orders and negotiating with
contractors. Specific adjustments and allowances for pricing should be made for each project and
should be based on the following considerations:
• Project complexity
• Supply/demand for contractor’s services and for materials
• Individual construction contract specifications
• Change Order work
When planning for Engineering construction projects that consist of typical standard railroad
construction activities that will be performed by Amtrak union forces (i.e., joint elimination, tie
replacement, surfacing, air break switches, etc.), a Project Manager can reference the actual unit cost
data in WebWEE that provides an average, minimum and maximum unit cost for these standard
16.4 Contingencies
Cost contingencies provide reserve against the risk of cost increase during the development of the
project. These contingencies must be separately identified in the project’s financial plan and included
in the cost estimates. Contingencies can be established as a specific amount or as a percentage of a
budget estimate (or both). As a project moves through the engineering and design processes, cost
increases due to the refinement of design are less likely and, consequently, the contingency should
be reduced.
The Project Manager is responsible for applying an appropriate range of contingencies based on a
project being either new construction or rehabilitation.
113
This page intensionally left blank.
Amtrak Engineering Project Management Manual 2016
Addendum (Addenda – plural) bidder does not accept award of the contract,
APPENDIX GLOSSARY
A modification of a solicitation (IFB or RFP). the bidder is liable for the amount of loss suf-
fered by Amtrak. Such loss may be partially or
Advertisement completely recovered by Amtrak by exercising
Classified advertisement placed in a general- its rights against the surety.
ly distributed publication notifying the public
and interested contractors of forthcoming so- Bid Protest
licitations. Bidder/Offeror challenges the appropriateness
of a contract award decision. Amtrak does not
Allowable Cost have a formal bid protest procedure.
A direct or indirect cost which, by its nature,
may be reimbursable to a cost-based contract Bidder
and/or change order in accordance with ap- Any individual, firm, partnership, corporation
plicable Federal Acquisition Regulations – 48 or combination thereof submitting a bid for
CFR 31.201-2. goods or services in response to an Invitation
for Bids.
Amendment
A modification of the terms of a contract which, Capital Equipment
although within the general scope of a contract, Any equipment having a useful life of at least
must be executed by both Amtrak and the con- one year, including rolling stock and all other
tractor. (See Contract Modification.) such property.
115
Amtrak Engineering Project Management Manual 2016
areas within Amtrak requiring improvements. The amount of time as set forth in the Contract
Contracts for consultants define a deliverable for completion of the Contract, including any
product for which the consultant is contractu- authorized amendments thereto; also referred
ally responsible. to as Period of Performance.
nishing of goods or services. tracting Official and is responsible for all con-
tractual actions other than those reserved to
Contract Documents the Contracting Official.
Consists of the Contract and all other docu-
ments specifically identified and incorporated Contracting Official (CO)
therein. The Contract Documents may include: The Vice President of Procurement and Ma-
General Provisions; Supplementary General terials Management or such person as may be
Provisions; the Pricing Schedule; Drawings; authorized in writing by Amtrak to execute,
Specifications; Contract Modifications; and any administer and make changes to the Contract
other documents identified as Contract Docu- and to make related determinations and find-
ments in the Contract. Unless specifically iden- ings on behalf of Amtrak. This includes a duly
tified in the Contract, the Contract Documents appointed successor or an authorized represen-
do not include solicitation documents (e.g., tative of the Contracting Official acting within
RFPs, IFBs, Contractor’s bid or proposal, etc.). the limits of his/her authority. He/she assumes
no personal liability under the Contract.
Contract Drawings
The plans, elevations, cross-sections, supple- Contracting Official’s Technical Representa-
mental drawings and details included or re- tive (COTR)
ferred to in the specifications which have been That Amtrak representative designated by the
approved by Amtrak, which show the dimen- Contracting Official to handle one or more
sions, character and details of the work to be technical administrative functions, as set forth
performed. in the contract or separate correspondence
from Amtrak. (Also known as the Project
Contract Modifications Manager.)
Any written alteration in the specifications,
price, delivery date, contract period, quanti- Contractor
ty or other contract provision of an existing The person or organization identified as having
contract, accomplished by unilateral action in been awarded a contract in the contract docu-
accordance with a contract provision or by a ments. Contractor means the contractor or its
mutual action of the parties to the contract. A authorized representative.
Contract Modification is: (a) a written amend-
ment to the Contract signed by both parties; or Cost Analysis
(b) a Change Order issued by the Contracting A detailed review and evaluation of the sep-
Official. arate cost elements and proposed profit of a
vendor’s cost or pricing data and the judgmen-
tal factors applied in estimating the costs. A
116
Amtrak Engineering Project Management Manual 2016
cost analysis is generally conducted to form an tools and apparatus necessary for the proper
APPENDIX GLOSSARY
opinion on the degree to which the proposed and acceptable completion of the project.
cost, including profit, represents what the per-
formance of the contract should cost, assuming Facility
reasonable economy and efficiency. Those structures, buildings, and property that
are to be erected, renovated, reconditioned, re-
Days modeled or removed under the project.
As used in the contract documents, “Days”
shall be understood to mean calendar days, un- Federal Acquisition Regulations (FAR)
less otherwise designated. The regulations that govern procurements by
federal government agencies. Amtrak is sub-
Design Specifications ject to certain (but not all) of these regulations
Specifications based on the design of a prod- when federal grant funds are utilized for a pro-
uct or service. Typical design specifications may curement.
include dimensions, materials used, commonly
and competitively available components, and Federal Requirements
non-proprietary methods of manufacturing. Federal regulations to which Amtrak is subject
via its grant agreement with the FRA. They set
Direct Cost forth standards for the procurement of goods
The cost that can be identified specifically with and services with federal funds. The require-
a particular cost objective. ments are set forth in 49 CFR 19.40 – 19.48
(with exception of 19.44 (b)). (See Appendix
Disadvantaged Business Enterprise (DBE) A.3)
Small business concern owned and controlled
by “socially and economically disadvantaged Force Majeure
individuals” (as that term is defined in 49 CFR An unforeseeable event that results in an ex-
Part 26). cusable delay in the performance of contract
obligations; protects the party from sanctions
Emergency for late performance.
A condition existing when the public exigen-
cy requires the immediate delivery of goods or Federal Railroad Administration (FRA)
services. Such conditions may also cause sig- Federal grantor providing financial assistance
nificant inconveniences to the public, i.e., ser- and operational oversight to Amtrak.
vice delays, hazardous conditions or danger to
property. General Provisions
Part of the contract documents. These provi-
End User Department sions set forth the rights and responsibilities
The term used for any department within Am- of the contracting parties and are generally
trak that initiates a request for procurement standard in all contracts of a specific type (e.g.,
action and that will ultimately benefit from the construction).
goods or services acquired. (Also known as the
Requesting Department.) Grantee
Amtrak as a recipient of an outside source of
Equipment funds, most notably from the FRA.
All machinery, together with the necessary
supplies for upkeep and maintenance, and also
117
Amtrak Engineering Project Management Manual 2016
As defined in P/I 1.6.0, an independent con- A promise to provide goods or services ac-
tractor is an individual retained on a tempo- cording to specified terms and conditions in
rary basis to perform work under the supervi- exchange for material compensation. May take
sion of an Amtrak manager. This work may be the form of a bid or proposal.
professional or clerical in nature. However, the
distinguishing feature from either a Consultant Offeror
OFGLOSSARY
or Professional Services Contract is that the in- Any individual, firm, partnership, corporation
dividual’s work is administered and monitored or combination thereof submitting a proposal
A PROJECT
by an Amtrak manager. (See also P/I 7.13.1.) for goods, services or work in response to a Re-
quest for Proposals.
Invitation for Bids (IFB)
A method of procurement used to solicit sealed Overhead or Indirect Costs
bids where a firm, fixed price contract is to be The costs that are generally associated with or
awarded to the lowest responsive and respon- attributed to the operating of a business and
sible bidder. which may be allocated to one or several cost
pools identified as General and Administra-
Lowest Responsible Bidder tive, Labor Fringes & Benefits, etc.
The bidder who is eligible to be awarded a
contract because its bid in unit price, total cost Payment Bond
or value per dollar is lower than any other bid A payment bond (sometimes known as a labor
submitted for consideration, and who is a re- and material payment bond) ensures payment
sponsible contractor. by the prime contractor as required by law of
all subcontractors supplying labor and material
Negotiation in the performance of work under a contract.
Mutual discussion concerning the terms of a
transaction or agreement between a purchaser Performance Bond
and supplier. A performance bond ensures the completion
of the project by the contractor guaranteeing
Notice of Award that if it defaults, the bonding company will
A letter issued to the successful bidder/offeror step in and finish the work.
stating that its bid/proposal has been accepted
for contract. The letter requests the signature Performance Specifications
of the bidder/offeror on the contract docu- Specifications based on the function and per-
ments, as well as other requirements within a formance of a product or service under speci-
prescribed period of time. The notice of award fied conditions, preferably conditions that can
serves as notification only and is not contractu- be reproduced for testing purposes. Perfor-
ally binding, nor does it authorize the awardee mance specifications may include useful life,
to buy materials or commence work. reliability in terms of average intervals be-
tween failure, and capacity.
Notice to Proceed
A written notice from Amtrak to the contrac- Pre-Bid or Pre-Proposal Conference
tor to perform work, provide a service or deliv- A conference featuring representatives of the
er materials as prescribed in the contract. Procurement Department and the User De-
partment, to discuss questions and concerns
118
Amtrak Engineering Project Management Manual 2016
raised by the prospective bidders/offerors re- out indicates that required services or work
APPENDIX GLOSSARY
garding the preparation of their bids/proposals. have been provided and full payment has been
made. Contract closeout does not necessarily
Pre-Construction Meeting mean that the contractor is released from any
A meeting with the contractor and Amtrak af- claim which Amtrak may have for negligence,
ter awarding the contract and before beginning malpractice and breach of contract.
construction.
Project Manager (PM)
Price Analysis The person delegated the authority to act on
The process of examining and evaluating the behalf of the requesting department for the
reasonableness of a bidder’s/offeror’s price daily technical administration of a contract
without evaluation of the separate cost ele- including the monitoring of the contractor’s
ments and proposed profit, usually by compar- performance in accordance with the contract.
ing the price to verifiable data such as a pub- (Also known as the COTR.)
lished price list or previous purchases.
Proposal
Procurement An Offeror’s response to a Request for Pro-
Procurement and Materials Management De- posal that describes the goods or services be-
partment. ing offered by a prospective vendor. Typically
submitted as two separate proposals, technical
Professional Services and price.
As defined in P/I 1.6.0, professional services
are performed by individuals or organizations Purchase Order
that provide services of a technical or intellec- A type of contractual agreement in which a
tual nature within the field of finance, account- promise to pay is offered in exchange for goods
ing, architecture, land surveys, professional or services.
engineering, law, medicine, computer program-
mer/support, advertising and communication, Purchase Requisition
etc. Contracts for professional services define a A hardcopy or electronic document used to
deliverable product for which the contractor is initiate the procurement process that contains:
contractually responsible. descriptions, technical specifications and cost
estimates of the intended purchase; and autho-
Progress Payments rizing approvals of the appropriate officials.
Reimbursements for costs incurred by a con-
tractor at a percentage or stage of completion Request for Information (RFI)
of the work. These payments are generally used A formal request to determine what type of
when the contract requires an extended period products/services are available in the market-
of time for completion of the work. place when a large or complicated purchase
is being considered and the potential pool of
Progress Reports suppliers must be pre-qualified. (Sometimes
Periodic reporting of progress relating to spe- used interchangeably with Request for Qual-
cific requirements set forth in the contract. ifications.)
119
Amtrak Engineering Project Management Manual 2016
is based on offerors’ rating on various evalua- Copies of original drawings submitted to Am-
tion factors listed in the solicitation. trak by or through the contractor, subcontrac-
tor or any lower tier subcontractor pursuant
Request for Qualifications to the work, showing in detail: the fabrication
A formal request to solicit statements of inter- and assembly of a product or equipment; the
est and firm qualifications to allow Amtrak to installation (that is, the form, fit and attach-
OFGLOSSARY
pre-qualify products or firms. (Sometimes used ment details) of product or equipment; set-up
interchangeably with Request for Informa- of product or equipment with instruments for
A PROJECT
120
Amtrak Engineering Project Management Manual 2016
APPENDIX GLOSSARY
A purchasing entity’s request for offers, includ- The committee whose duties include evaluation
ing a Request for Quotations, an Invitation for and rating of technical proposals and selection
Bids or a Request for Proposals. of a contractor.
121
Contact information
A.J. Nayee
Deputy Chief Engineer
Amtrak Engineering Program Management Office
2955 Market Street, 30th Street Station, 4S-030, Philadelphia, PA 19104
Phone: 215-349-1708 Email: aj.nayee@amtrak.com