Beruflich Dokumente
Kultur Dokumente
GROUP TK 12
GROUP PERSONNEL:
FARADILLA ANDIANI P. (1606886173)
JESSICA ADELINE S. (1606879943)
M. AZKIA RIFQI A. (1606891223)
SULTAN SHIDDIQI S. (1606905374)
TITA TRI YOLANDINI (1506673403)
ii Universitas Indonesia
iii Universitas Indonesia
TABLE OF CONTENT
EXECUTIVE SUMMARY................................................................................... ii
TABLE OF CONTENT ....................................................................................... iv
LIST OF FIGURES .............................................................................................. v
LIST OF TABLES ............................................................................................... vi
1 CHAPTER 1 PIPING AND INSTRUMENTATION DIAGRAM ........... 1
1.1 Pipeline Specification ............................................................................... 1
1.2 Production Process Control Description .................................................. 4
1.3 Utility Control Description....................................................................... 6
1.4 Production Process Piping and Instrumentation Diagram ........................ 6
1.5 Utility Piping and Instrumentation Diagram ............................................ 7
2 CHAPTER 2 HEALTH, SAFETY, AND ENVIRONMENTAL
PROTECTION ...................................................................................................... 8
2.1 Hazard Identification Study (HAZID) ..................................................... 8
2.2 Hazard and Operability Study (HAZOP) ............................................... 16
2.3 Operational Details ................................................................................. 27
2.3.1 Commissioning ............................................................................... 27
2.3.2 Start-up Procedure .......................................................................... 30
2.3.3 Shutdown Procedure ....................................................................... 36
2.4 Personal Protective Equipment (PPE) .................................................... 39
2.5 Material Safety Data Sheet (MSDS) ...................................................... 42
2.6 Area Classification ................................................................................. 48
2.7 Emergency Action Plan .......................................................................... 48
2.7.1 Evacuation Procedures, Escape Routes, and Floor Plans ............... 49
2.7.2 Medical Emergency Plan ................................................................ 50
2.7.3 Fire Fighting Strategy ..................................................................... 50
2.7.4 Emergency Operation Training ....................................................... 51
2.7.5 Policies for Updating and Maintaining the EAP ............................. 53
2.8 Waste Management ................................................................................ 53
2.8.1 Solid Waste ..................................................................................... 54
2.8.2 Liquid Waste ................................................................................... 55
2.8.3 Gas Waste ....................................................................................... 56
2.8.4 Sound .............................................................................................. 56
3 CHAPTER 3 PLANT LAYOUT ............................................................... 58
3.1 Plant Location ........................................................................................ 58
3.2 Plant Layout ........................................................................................... 59
3.2.1 General Consideration of Plant Layout ........................................... 59
3.2.2 Safe Range Between Equipment ..................................................... 59
3.2.3 Area Classification Layout ............................................................. 60
3.2.4 Overall 2D Plant Layout ................................................................. 60
3.2.5 Overall 3D Plant Layout ................................................................. 60
4 CHAPTER 4 CONCLUSION .................................................................... 61
5 REFERENCES ............................................................................................ 62
6 APPENDICES A ......................................................................................... 66
7 APPENDICES B ......................................................................................... 70
8 APPENDICES C ......................................................................................... 74
9 APPENDICES D ......................................................................................... 76
iv Universitas Indonesia
LIST OF FIGURES
v Universitas Indonesia
LIST OF TABLES
Table 2.1. Process Selection Parameter ................. Error! Bookmark not defined.
Table 2.2. Process Selection Matrix ...................... Error! Bookmark not defined.
Table 2.3. Electrode Pair Selection ........................ Error! Bookmark not defined.
Table 2.4. Kinetic Parameter Values for Lithium Chloride Carbonation ...... Error!
Bookmark not defined.
Table 2.5. Operating Conditions and Mass Balance of Brine Evaporation ... Error!
Bookmark not defined.
Table 2.6. Operating Conditions and Mass Balance of Lithium Carbonate Synthesis
................................................................................ Error! Bookmark not defined.
Table 3.1. Mass Balance of E-101 ......................... Error! Bookmark not defined.
Table 3.2. Mass Balance of E-102 ......................... Error! Bookmark not defined.
Table 3.3. Mass Balance of E-103 ......................... Error! Bookmark not defined.
Table 3.4. Mass Balance of R-201 ......................... Error! Bookmark not defined.
Table 3.5. Mass balance of M-201 ......................... Error! Bookmark not defined.
Table 3.6. Mass balance of M-202 ......................... Error! Bookmark not defined.
Table 3.7. Mass Balance of R-202 ......................... Error! Bookmark not defined.
Table 3.8. Mass Balance of F-201 A/B/C .............. Error! Bookmark not defined.
Table 3.9. Mass Balance of V-201 ......................... Error! Bookmark not defined.
Table 3.10. Energy Balance in Evaporation ProcessError! Bookmark not
defined.
Table 3.11. Energy Balance in Extraction Process Error! Bookmark not defined.
Table 3.12. Energy Balance in Drying Process ..... Error! Bookmark not defined.
Table 3.13. Total Energy Balance .......................... Error! Bookmark not defined.
Table 3.14. Overall Mass Balance of Brine EvaporationError! Bookmark not
defined.
Table 3.15. Overall Mass Balance of Lithium Carbonate Synthesis ............. Error!
Bookmark not defined.
Table 4.1. Streams Involved in Heat Exchanger NetworkError! Bookmark not
defined.
Table 4.2. Minimum Utility Requirement ............. Error! Bookmark not defined.
Table 4.3. Shifted Temperature Data ..................... Error! Bookmark not defined.
Table 4.4. The CP of Each Streams ....................... Error! Bookmark not defined.
Table 4.5. Cascade Table ....................................... Error! Bookmark not defined.
Table 4.6. Heat Exchanger Network Design Rule . Error! Bookmark not defined.
Table 4.7. Heat Exchanger Network Final Design Error! Bookmark not defined.
Table 4.8. Mass Flow and Operating Conditions After HENError! Bookmark
not defined.
Table 5.1. Cooling Water Requirement Before HENError! Bookmark not
defined.
Table 5.2. Calculation of Makeup Cooling Water Before HENError! Bookmark
not defined.
Table 5.3. Cooling Water Requirement After HENError! Bookmark not defined.
Table 5.4. Calculation of Makeup Cooling Water After HENError! Bookmark
not defined.
vi Universitas Indonesia
Table 5.5. Steam Requirement in Plant Before HENError! Bookmark not
defined.
Table 5.6. Steam Requirement in Plant After HENError! Bookmark not defined.
Table 5.7. Electricity Requirement After HEN...... Error! Bookmark not defined.
Table 5.8. Utility Requirement Comparison .......... Error! Bookmark not defined.
Table 5.9. Mass Balance for Cooling Water .......... Error! Bookmark not defined.
Table 5.10. Mass Balance for Steam Generation ... Error! Bookmark not defined.
Table 5.11. Energy Balance for Utility Section ..... Error! Bookmark not defined.
1 Universitas Indonesia
Table 1.1. Pipeline Specification Area 100
Inner Outer
Nominal Pipe Length Pressure Drop
Pipe Code Material Diameter Diameter Schedule
Size (inch) (ft) (psi/100 ft)
(mm) (mm)
101 Carbon Steel A53 A106 API5L 278.52 288.83 12.00 40 15.00 0.3024
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
1 Universitas Indonesia
2
Universitas Indonesia
3
Universitas Indonesia
4
Universitas Indonesia
5
Universitas Indonesia
6
Universitas Indonesia
7
Universitas Indonesia
2 CHAPTER 2
HEALTH, SAFETY, AND ENVIRONMENTAL PROTECTION
HAZID studies method, accepted as one of the best techniques for identifying
potential hazards and operability problem, involves the following:
1. Assembly of a team of experienced project personnel.
2. Presentation detailing the scope of the HAZID.
3. Identifying hazards, cause, consequences and safeguards.
9 Universitas Indonesia
Table 2.3. Hazard Index Based on Frequency and Severity
Severity
Frequency
Minor Major Severe
Very Likely Medium High Extreme
Likely Low High Extreme
Unlikely Low Medium High
(Source: Queensland Coke & Energy, 2005)
10 Universitas Indonesia
Table 2.4. Plant Hazard Identification (HAZID)
Existing Hazard
No Guideword Cause Consequences Severity Frequency Action Comments
Controls Index
Brine Evaporation
1 Accident Falls caused by Slippery floors and Tank level Major Unlikely Medium Monitoring tank
Hazards slips, water puddle on control, PPE level regularly,
particularly on floors, Operators Making sure
floors made injury operators are well
slippery as a equipped with PPE,
result of Ensuring strict
extensive use of working procedure
water
Falls from
elevated places
throughout
inspection of
evaporators
Capture of parts
of body between
various parts of
evaporator
11 Universitas Indonesia
Table 2.5. Plant Hazard Identification (HAZID) (continued)
Existing Hazard
No Guideword Cause Consequences Severity Frequency Action Comments
Controls Index
Exposure to
excessive heat
and high
humidity, due to Operators’ fatigue Making sure
Physical
2 wide use of and thermal PPE Major Unlikely Medium operators are well
Hazards
steam exhaustion equipped with PPE
Exposure to
high noise levels
12 Universitas Indonesia
Table 2.6. Plant Hazard Identification (HAZID) (continued)
Existing Hazard
No Guideword Cause Consequences Severity Frequency Action Comments
Controls Index
Small electrodes’ Fire and explosion Ignition
Fire and Ensuring strict
2 gap inducing in electrochemical source Severe Unlikely High
Explosion working procedure
electrical spark reactor control
Damage of the
Regular
3 Damage Bad construction Lithium Carbonate Major Unlikely Medium Inspecting regularly
maintenance
Synthesis unit
PPE, Proper Inspecting regularly,
High voltage Operators can be cable Making sure
Electrocuted unit electrocuted, Fire insulation, operators are well
4 Severe Unlikely High
and Fire Short circuit in electrochemical Neatly equipped with PPE,
reactor arranged Ensuring strict
cables working procedure
High Making sure
temperature Burns, Capture of
operators are well
Accident surface parts of body
5 PPE Severe Unlikely High equipped with PPE,
Hazards High speed between in the
Ensuring strict
rotation reactor
working procedure
Utility
Inspecting and
Boiler blowout and Temperature monitoring
1 Damage High temperature Severe Unlikely High
explosion control temperature
regularly
13 Universitas Indonesia
Table 2.7. Plant Hazard Identification (HAZID) (continued)
Existing Hazard
No Guideword Cause Consequences Severity Frequency Action Comments
Controls Index
Regular inspection
Flammable
Fire and Fire and explosion Flue gas and monitoring,
2 composition of Severe Unlikely High
Explosion around boiler control ensuring no ignition
gases in boiler
source nearby
Cooling water
Cooling Heat release of failure (cooling Temperature Regular inspection
4 Major Unlikely Medium
water failure water water is hotter than control and monitoring
usual)
Entire Site Overview
Corroding Material
Regular corrosion
Piping substance inside Corrosion leading selection,
1 Major Likely High inspection, applying
Corrosion pipe, external to leakage corrosion
corrosion inhibitor
weather factor allowance
Control Room
Error in control Tight
Implementing
System system or Operational working
1 Severe Likely Extreme working procedure
Error equipment, human disruption procedure,
more strictly
error training
14 Universitas Indonesia
Table 2.8. Plant Hazard Identification (HAZID) (continued)
Existing Hazard
No Guideword Cause Consequences Severity Frequency Action Comments
Controls Index
Laboratory
Hazardous
Chemical spill, substance affecting Working Tight laboratory
1 Toxic Major Likely High
unwanted reaction people in procedure working procedure
laboratory
Tight laboratory
Chemical reaction
Explosion in Working working procedure,
2 Explosion leading to Major Unlikely Medium
laboratory procedure providing fire
explosion
extinguisher
Office and Technical Building
Electrical spark, Evacuation HSE training for
Fire in office and
1 Fire fire spread from guide, fire Severe Unlikely High office and technical
technical building
plant hydrant building workers
15 Universitas Indonesia
2.2 Hazard and Operability Study (HAZOP)
Hazard and Operability Analysis (HAZOP) is a structured and systematic
technique for system examination and risk management. In particular, HAZOP is
often used as a technique for identifying potential hazards in a system and
identifying operability problems likely to lead to nonconforming products. HAZOP
is based on a theory that assumes risk events are caused by deviations from design
or operating intentions. Identification of such deviations is facilitated by using sets
of “guide words” as a systematic list of deviation perspectives. This approach is a
unique feature of the HAZOP methodology that helps stimulate the imagination of
team members when exploring potential deviations.
As a risk assessment tool, HAZOP is often described as:
A brainstorming technique.
A qualitative risk assessment tool.
An inductive risk assessment tool, meaning that it is a “bottom-up” risk
identification approach, where success relies on the ability of subject matter
experts (SMEs) to predict deviations based on past experiences and general
subject matter expertise.
HAZOP is best suited for assessing hazards in facilities, equipment, and
processes and is capable of assessing systems from multiple perspectives:
1. Design
Assessing system design capability to meet user specifications and safety
standards
Identifying weaknesses in systems
2. Physical and operational environments
Assessing environment to ensure system is appropriately situated,
supported, serviced, contained, etc.
3. Operational and procedural controls
Assessing engineered controls (ex: automation), sequences of operations,
procedural controls (ex: human interactions) etc.
Assessing different operational modes – start-up, standby, normal
operation, steady & unsteady states, normal shutdown, emergency
shutdown, etc.
16 Universitas Indonesia
HAZOP is performed by a group of experts from multiple disciplines and
led by an experienced safety specialist or training consultants. The main HAZOP
procedures are (Timmerhaus, 1991):
1. Collecting all process lineation for each process in the plant.
2. Process breakdown into little and more detail sub-process. To clarify the
breakdown of sub-process is given nodes in upper-ends of each sub-process.
There is no particular rule about limiting the distance of process.
3. Searching all possibilities of deviation in each process through uses of
systematic questions (HAZOP model for question is made by using
keywords, intended to make the analysis process easier).
4. Scoring for each negative effect that caused by every deviation mentioned
before. The criterion of harmful degrees for those negative effects is
determined by safety and efficiencies operational condition of the plant in
normal condition.
5. Determination of overcome action to every deviation happened.
We use two groups of keywords to emphasize systematic question in
HAZOP procedure, which are
1. Primary Keywords
Primary keyword is every word that is related to condition or parameter of a
process. For example: flow, pressure, temperature, viscosity, corrosion,
erosion, level, density, relief, composition, addition, and reaction
2. Secondary Keywords
Secondary keywords are every word which is merged with primary keyword
will shows probability of deviation that can be happened. For example: no,
more, less, reverse, and as well as.
HAZOP analysis of the plant and office is shown in the tables below.
17 Universitas Indonesia
Table x. Plant Hazard and Operability Study
Operation Unit Consequence/
Parameter Deviation Possible Causes Prevention/ Action Control
Units Code Hazard
Pump fails Material quantity
Flow
(electrical or target is not Controlling the flow
Low Indicator
mechanical), valve accomplished, sales of the stream
Control
shut interrupted
The product
Controlling the flow
specification is
Flow Overworked pump, of the stream to
overwhelmed and can
valve is not prevent feed loss in Flow
not be controlled,
E-103 High working (open high pressure pump Indicator
possible overheating
Evaporator E-104 widely, and reverse osmosis Control
pump, the impurities
E-105 uncontrolled) and installing safety
harms the next
valve
process, flooding
Controlling the
The source is concentration of
High impurities that Analyzer
disturbed (by waste before being
Concentration High will harms next Indicator
ocean wave, waste, pump to the ocean
process Control
sands) and waste water
treatment
18 Universitas Indonesia
Table x. Plant Hazard and Operability Study
Operation Unit Consequence/
Parameter Deviation Possible Causes Prevention/ Action Control
Units Code Hazard
Under performance
Material quantity
pump (electrical or
Less target is not
mechanical), valve
accomplished
shut
Flow Overworked pump,
valve is not
Material overflow in
More working (open
the reactor, flooding
widely,
Flow
Electrochem uncontrolled) Controlling the flow
R-201 Indicator
ical Reactor Overworked pump, of the stream
Control
valve is not Product does not meet
Less working (open the minimum
widely, specification
Concentration uncontrolled)
Under performance
pump (electrical or Less production
More
mechanical), valve quantity
shut
19 Universitas Indonesia
Table x. Plant Hazard and Operability Study
Operation Unit Consequence/
Parameter Deviation Possible Causes Prevention/ Action Control
Units Code Hazard
Feed temperature The reaction is not
is too low, steam done as far as Controlling the steam Temperatur
Less
flow is less than expected and need flow e Control
Carbonation necessary. more time to be done.
R-202 Temperature
Reactor Feed temperature
More steam is needed,
is too high, steam Controlling steam Temperatur
More reaction can’t be
flow is more than flow e Control
controlled.
necessary.
Flow from There will be no
steam after There is loss more enough steam for Controlling make up Flow
Less
usage than expected recycle back to main water flow Control
(condensate) process
Boiler B-401
Monitoring
Lack of Heat Steam doesn’t reach Temperature, Temperatur
Temperature Less
Supplier desired specification controlling the e Control
natural gas flow
Less flow of Temperature of
Heat E-101, Install High Temperatur
Flow Less cooling water, pipe process fluid remains
Exchanger E-102, Temperature Alarm e Control
blockage constant
20 Universitas Indonesia
E-106, High cooling flow,
Temperature of Install Low Temperatur
E-201 More failure of cooling
process fluid decrease Temperature Alarm e Control
water valve
Failure on control
More on Install High Pressure Pressure
Pressure valve of tube side Bursting of tube
tube side Alarm Control
stream
Leakage of Contamination,
More in
heating/cooling affecting product Proper maintenance Operator
Contamination process
fluid to process quality and further and operator alert Control
fluid line
fluid processes
Hardness of water,
Corrosion Leakage, fouling, heat Operator
Corrosion erosion corrosion, Proper maintenance
of tube transfer resistance Control
embrittlement
21 Universitas Indonesia
Table x. Plant Hazard and Operability Study
Operation Unit Consequence/
Parameter Deviation Possible Causes Prevention/ Action Control
Units Code Hazard
Material quantity
Pump fails
target is not Flow
(electrical or Controlling the flow
Less accomplished, product Indicator
mechanical), valve of the stream
does not meet the Control
shut
specification
The product
Flow specification is
Overworked pump,
overwhelmed and can
valve is not Controlling the flow Flow
not be controlled,
More working (open of the stream to Indicator
possible overheating
Mixer M-201 widely, prevent feed loss Control
pump, the impurities
uncontrolled)
harms the next
process, flooding
Agitator fails
(rotates slower Product does not meet
Less than the specified the specification (does Monitoring the
RPM
Mixing operating not mixed well) agitator condition
Control
condition) regularly
Agitator fails
More Waste of electricity
(rotates faster than
22 Universitas Indonesia
the specified
operating
condition)
23 Universitas Indonesia
High water supply to next
Excessive impeller unit. When the fluid flow is
performance, feed too fast, the pump will run
More
flowrate is too out of fluid and could cause
high heat and fires at the pump
so the pump can be broken
Cavitation may occur,
Suction pressure is reverse flow occur, pump Control pressure Pressure
Less
too low can't distribute the liquid to periodically Control
the next process
Pressure
Decrease the inlet
Suction pressure is flow to pump,
More Pumps quickly broken
too high switch into
secondary pump
24 Universitas Indonesia
The product
specification is
Overworked pump,
overwhelmed and can
valve is not
not be controlled,
More working (open
possible overheating
widely,
pump, the impurities
uncontrolled)
harms the next
process, flooding
Under
High humidity level of
Less performing/not
product Install temperature Temperatur
Temperature working heater
indicator e Control
Harming the next
More Overheated heater
process
Under performance Material quantity
pump (electrical or target is not
Less
Dryer V-201 mechanical), valve accomplished, sales
shut interrupted
Flow
The product Controlling the flow
Flow Overworked pump, Indicator
specification is of the stream
valve is not Control
overwhelmed and can
More working (open
not be controlled,
widely,
possible overheating
uncontrolled)
pump, the impurities
25 Universitas Indonesia
harms the next
process, flooding
Cooling CT- Temperature Less Flow of reboiler Temperature of Control the Temperatur
Tower 301 hot fluid is low, operation condition temperature of stream e Indicator
under heated does not achieve, low before entering Control
stream quality specification, reactor to adjust the
low production operating condition
More Overheated stream, Overheated unit, low
flow of reboiler hot quality product
fluid is high
Flow More Fan speed is too Ineffective heat removal Increasing fan speed Temperature
slow by cold utility (make up Control
water)
26 Universitas Indonesia
27
Universitas Indonesia
28
a procedure that must be carried before every start up. The activity of this step
includes:
Check line by line against flowsheet and locate all items. All piping and
instrument must be completed as per piping and instrumentation diagram
(P&ID).
Identify the location of instruments and the connectivity of each item
Instrument calibration is verified.
All instruments such as level transmitter, level controller, pressure
transmitters, pressure controller, temperature transmitter, temperature
controller and etc. must be installed.
All piping and equipment is compatible with designed pressure.
All piping and equipment is protected against corrosion.
Planned instrumentation is installed and operative.
b. Pressure testing
The purpose of pressure testing is to confirm the mechanical integrity of
the plant, verifying capability of containing the pressures it has been designed
to hold, ensure there are no leaks and verify that the plant can be reliably made
leak free, identify any vulnerabilities well before the plant is placed into service,
and to meet the requirements of legislation, local, international and industry
standards. It is to prove the strength of the materials and weld integrity after
completion of the construction, usually using hydrostatic testing.
Isometric drawings of all systems to be tested should be displayed on a
board and marked up as each section is tested. Hydro testing of piping and
equipment according to code requirements to confirm mechanical strength
should be carried out on groups of equipment naturally suggested by design
pressure and function. All piping should be hydro tested. Major equipment that
has already been tested as part of manufacturing may be isolated by blanks.
c. Cleaning and flushing
Check the process thoroughly to ensure screens have been installed in
front of pump suctions. Regardless of whether pipes are cleaned with water,
steam, air or nitrogen, flow velocities should be high enough to ensure that pipes
Universitas Indonesia
29
will be suitably scoured. Need to ensure that the debris from one piece of
equipment will not simply be flushed into another.
d. Machinery checkout
Machinery check out is the final check of each equipment. It includes:
Indicate the location of all critical valves including valves at critical vent
and drain locations
Check control valves, valves, and globe valves to see that they are installed
properly with respect to flow. Ensure functioning control valves, switching
valves, controllers, emergency shutdown system, etc. Ensure manual valves
are in proper positions.
Check power supply’s functionality.
Pumps are ready for operation: aligned, lubricated, proper rotation.
All plant lines and equipment must be flushed, cleaned, and dewatered.
Complete functional testing all rotating equipment.
Do final inspection of vessels and column.
Ensure there is no leak or any disfunctional.
2.3.1.2.Utilities Commissioning
Utilities commissioning usually represents the first phase of commissioning,
as these usually need to operational first, before the rest of the plant can be
commissioned. Below are the steps taken to complete urilities commissioning:
Check supply pressures of all services (steam, cooling water).
At the most distant points, open drains, vent valves or pipe flanges and
purge until fluids come out clean and rust free.
Purge/blow out lines to each piece of equipment.
Circulate water to waste water system until water lines clear and clean.
Flush waste water and drain systems to ensure no blockages.
Check operation of steam traps.
Drain condensate to waste water until it is clean.
2.3.1.3.Operational Testing
Operational testing is not necessarily be done every start up, but it is
required to maintain the sustainability of production process, to ensure plants
productivity. Periodically of 2-3 weeks, the production process is ideally sufficient
Universitas Indonesia
30
for an operational testing. Before operational testing carried out, the mechanical dry
running of individual pieces of equipment and hot testing must be complete first.
Tests should continue for several days to give all shifts a chance to conduct the
same tests. All shifts should be given the opportunity to start up and shutdown each
closed loop test.
2.3.2 Start-up Procedure
2.3.2.1. General Start Up Procedure
After the commissioning phase is completed, the plant can be declared
ready by the start-up phase. The general start-up procedure is listed below.
Make sure all the raw material is enough for the operation
Check the electricity supply.
Load catalyst into the reactor. The reactor should be purged beforehand.
All parameters in instrument which need controls must be set, such as
pressure, temperature, and level. This step is done to ensure the equipment
is under controlled.
The reactor is then prepared to be ready for the process. This step involves
maintaining temperature and pressure to avoid process shock in the reactor.
Open all inlet valves for process fluid flow in the plant.
Open utility valve for cooling water and steam.
Turn on all rotating equipment such as pump and compressor.
Monitor strictly for the first five hours to ensure the process condition is
similar to that of specified in the design.
Start-up procedure can be repeated if there is significant process deviation.
closed loop test.
2.3.2.2. Electrochemical Reactor
For electrochemical reactor, the start-up procedure is listed below
Make sure electrode is clean from deposit and the reactor is clean from
unknown substance
Check for leaks at every point and make sure inlet stream is flowing
smoothly and recovery solution available
After brine water filled electrochemical reactor until 85% level, electricity
can be conducted to electrode and starting electrochemical reaction
Universitas Indonesia
31
Left the reactor for 63000 second and dispose the brine water, change with
recovery solution until 85% level
Conducted electrode again for 2100 second and product can be obtained and
let out all product flow to next process.
2.3.2.3. Evaporator
TITA
2.3.2.4. Carbonation Reactor
As for the carbonation reactor, the start-up procedure is listed below.
Purge the reactor with nitrogen to make sure the reactor is clean.
Check for leaks at every point and make sure the steam is flowing into the
jacket.
Heat the reactor until temperature desired.
Open inlet stream valve for concentrated brine and natrium carbonate
solution.
Operate the reactor for desired reaction time.
Open outlet stream valve to let out all products and excess reactant for
further processing.
Purge the reactor again for cleaning.
2.3.2.5. Blower
Do a reverse rotation check to check if the blower is working properly.
Check the suction and discharge gauges to make sure the operating
condition is recorded properly.
Sensor the voltages before the blower starts
Start the blower and check the noise level, make sure it doesn’t exceed the
number of maximum noises allowed.
Check the oil level in order for the blower to work on the highest condition.
2.3.2.6. Filter
Give enough lubricants for the rubber so it moves easier.
Ensure that the belt filter is properly put on the filter so the brine shall go
through the filter.
Universitas Indonesia
32
Check if the indicators are in place and working properly. Clean and connect
interconnected piping. During the flushing operation, check all pipe connections
and valves for leaks. Tighten connections where necessary.
The pump must be aligned, lubricated, and properly rotated.
Start the feed pump
Set the operating condition based on the optimum operating condition.
Make sure if the output of the filter is at the desired target, if not make an
adjustment by changing the operating condition based on the design.
One of the most important things to check in filter is the particle size
distributing (PSD) because it shall be the parameter for filtering the product based
on the size of the product. In the plant, PSD consists of field-mounted sensors,
valves and trip relays, a system logic unit for processing of incoming signals, alarm
and HMI units. The system can process all input signals and activate outputs in
accordance with the applicable Cause and Effect. PSD is integrated with the control
system, such as pressure control and temperature control. When the pressure is far
from its set point, and potentially harms the equipment, human, or environment, the
PSD will automatically initiate. For example, when the temperature of the reactor
is far from the maximum temperature allowed, there will be an alarm on the
operating room for the operator to take action, but if in some cases, the level is still
getting higher, until the highest point. The process shutdown will automatically
initiate to prevent the losses.
2.3.2.7. Dryer
Make sure all the pipes are intact and able to transport all of the feed into
the dryer.
Put all the trays in the suitable places where the drying process will take
place.
Turn on the blower and transport the hot air into the dryer.
Make sure the operating condition is at the right place, or else do an
adjustment.
2.3.2.8. Conveyor
Make sure the outlet flow of the dryer is in the right amount that suit the
capacity of the conveyor.
Universitas Indonesia
33
Make sure the conveyor is plugged in so it gets the right amount of power
to move its motors.
Give proper amount of lubricants to the machinery of the conveyor.
Turn on the conveyor check if the solids can move properly.
2.3.2.9. Crusher
Give enough lubricants on the motors of the crusher.
Make sure the crusher is plugged in with enough amount of power to
accommodate.
Turn on the crusher and make sure the PSD of the product is as the desired
target.
2.3.2.10. Pumps
Centrifugal pumps convert energy of an electric motor or turbine into
velocity or kinetic energy and then into pressure energy of the fluid being pumped.
The energy changes occur around two main parts of the pump, impeller and volute
or diffuser. Pump impeller is the rotating part that converts driver energy into the
kinetic energy. The volute or diffuser is the stationary part that converts the kinetic
energy into pressure energy. The pump driver can be either electric motor or a steam
turbine depending upon application.
These precautions must be followed before centrifugal pump start-up:
Do not operate the centrifugal pump below the minimum rated flows or with
the suction or discharge valves closed. These conditions can quickly lead to
centrifugal pump failure and physical injury.
Always disconnect and lock out power to the driver before you perform any
installation or maintenance tasks.
Centrifugal pump start-up in reverse rotation can result in the contact of
metal parts, heat generation, and breach of containment.
Flush and clean the system thoroughly to remove dirt or debris in the pipe
system in order to prevent failure at initial pump start-up.
Bring variable-speed drivers (if installed) to the rated speed as quickly as
possible.
Generally if the temperatures of the pumped fluid will exceed 200°F (93°C),
then warm up the pump prior to pump start-up.
Universitas Indonesia
34
Circulate a small amount of fluid through the pump until the casing
temperature is within 100°F (38°C) of the fluid temperature prior to pump
start-up to avoid thermal shock to the liner and impeller and prevent damage
of mechanical seal.
General centrifugal pump start-up procedure is listed below.
Open the suction valve.
Open any recirculation or cooling lines.
Fully close or partially open the discharge valve, depending on system
conditions.
Start the driver.
Slowly open the discharge valve until the pump reaches the desired flow.
Check the pressure gauge to ensure that the pump quickly reaches the
correct discharge pressure.
If the pump fail to reach the correct pressure, perform these steps:
a. Stop the driver.
b. Prime the pump again.
c. Restart the driver.
Monitor the pump while it is operating.
a. Check the pump for bearing temperature, vibration, and noise.
b. If the pumps exceed normal levels, then shut down the pump
immediately and correct the problem.
Repeat the last three steps until the pump runs properly.
2.3.2.11. Heat Exchangers
The general heat exchanger start-up procedure is listed below.
Check whether all the parts such as tube shell, heads and valves of the heat
exchanger are fixed.
Check whether all temperature, pressure and flow measuring sensors are
connected to the heat exchanger.
Open all vent connections
First circulate the cold stream.
Close the vents slowly. Make sure cold stream entirely filled before closing
vents.
Universitas Indonesia
35
Then circulate the hot stream and when the heat exchanger is completely
filled with the cold stream.
Close all the vents.
Start the operation gradually. Do not let the heat exchanger subject to
sudden temperature fluctuations
2.3.2.12. Tanks
There needs to be preparation and checking before usage of tank.
Appropriate phases should be repeated after any major repair, alteration, or
replacement during subsequent shutdowns. The phases of preparation for initial
start-up shall be according to the following steps:
Operational checkout list.
Hydrostatic testing.
Final inspection of vessels.
Flushing of lines.
Instruments.
Acid cleaning of compressor lines.
Breaking in pumps.
Breaking in compressors.
Dry-out and boil-out.
Catalyst loading.
Tightness test.
The operational check-out follows the procedures listed as follow.
Check line by line against flowsheet and locate all items.
Identify the location of instruments.
Indicate the location of all critical valves including valves at critical vent
and drain locations.
Check control valves, valves, and globe valves to see that they are installed
properly with respect to flow through their respective lines. Special
attention must be given to check valves regarding their direction of flow.
Review all piping and instrument connections for steam tracing.
Universitas Indonesia
36
Check that the following facilities have been installed so that the plant can
be commissioned and put on stream: start-up bypass lines, purge
connections. stream up-connections, drains, temporary jumpovers, blinds,
check valves, filters and strainers, bleeders.
Check pumps and compressors for start-up.
Check sewer system for operability.
Check blowdown systems.
Check heater for burner installation, refractories, stack damper controls,
burner refractories, etc.
2.3.3 Shutdown Procedure
2.3.3.1. General Shutdown Procedure
Generally, there are three type of shutdown implementing in the plant,
which are initiated shutdown, process shutdown, and emergency shutdown.
Initiated shutdown is done to maintain the process equipment in plant. The
procedure is the same as stopping equipment when the process is done. Typical
procedure shutdown process can be seen on the following steps.
Close all the inlet raw material valve
Shut down heating and cooling sources
Purge with nitrogen to clean each equipment
Eliminating undesirable materials (cleaning process)
Pressure trapped between two closed valves or closed process equipment
loops should be released immediately
Bring the vessel to atmospheric pressure
Shut down the electricity
A process shutdown is defined as the automatic isolation and deactivation
of all or part of a process. During a PSD, the process remains pressurized. In the
plant, PSD consists of field-mounted sensors, valves and trip relays, a system logic
unit for processing of incoming signals, alarm and HMI units. The system can
process all input signals and activate outputs in accordance with the applicable
Cause and Effect. PSD is integrated with the control system, such as pressure
control and temperature control. When the pressure is far from its set point, and
potentially harms the equipment, human, or environment, the PSD will
Universitas Indonesia
37
automatically initiate. For example, when the temperature of the reactor is far from
the maximum temperature allowed, there will be an alarm on the operating room
for the operator to take action, but if in some cases, the level is still getting higher,
until the highest point. The process shutdown will automatically initiate to prevent
the losses.
The term Emergency Shutdown System (ESD) refers to the method of
minimizing the consequences of emergency situations, related to typically
uncontrolled flooding or outbreak of fire in hazardous areas. Risk analyses have
concluded that the ESD system needs a high Safety Integrity Level, typically SIL 2
or 3. An emergency shutdown system represent a layer of protection mitigating and
preventing the occurrence of hazardous situation. An ESD system must be highly
reliable. During emergency, it is a must to shut down the plant in safest way. The
situations that initiate the emergency shutdown, such as
Electric power failure
Manual alarm
Pump or compressor failure
The emergency shutdown is conducted with the main objectives listed as
follow.
To shut down the plant safely
To minimize the emission
To prevent overpressure condition in the equipment
To protect equipment from damage
The emergency shutdown procedure is conducted with the steps listed as
follow.
Shutdown all transportation of gas and liquid
Decrease the pressure and temperature of any equipment
Perform electrical isolation
Start all safety equipment
2.3.3.2. Electrochemical Reactor
For electrochemical reactor, the shut-down procedure is listed below
Terminate feed flow to the reactor
Stop electricity to electrode
Universitas Indonesia
38
2.3.3.9. Pumps
Universitas Indonesia
40
Earplugs or
Hearing Excessive noise
earmuffs
Corrosive, toxic
Gloves Hands
materials, electric wires
Universitas Indonesia
41
Corrosive, toxic
Safety Shoes Feet material, against
crushing of toes
Universitas Indonesia
42
Universitas Indonesia
43
Hazard
Number Description
Type
0 No significant risk to health
1 Irritation or minor reversible injury possible.
Health
2 Temporary or minor injury may occur.
(Blue)
Major injury likely unless prompt action is taken and
3
medical treatment is given.
Universitas Indonesia
45
Universitas Indonesia
46
Universitas Indonesia
47
Universitas Indonesia
49
Universitas Indonesia
50
For emergencies occurring inside of the facility (e.g., fires, power outages,
etc.), the main goal is to get everyone out of harm way. To achieve this goal,
staff should be aware of the fastest and safest way out of the building.
Emergencies Outside of the Building
In most cases, when an emergency starts outside of the building, the safest
thing to do is find a safe place within the building. Most often, emergencies
outside of the building will be weather-related or natural disasters.
Health Emergencies
If someone inside of the building is injured or harmed in some way, an EAP
should be initiated quickly. Staff should be prepared to respond to a wide
range of plausible health scares such as a heart attack, seizure, possible
drowning and more.
2.7.2 Medical Emergency Plan
Whenever an employee or visitor is injured or develops a medical
emergency condition on plant property, follow the protocol below and notify your
immediate supervisor as soon as possible. Medical emergency instruction:
Dial the plant infirmary and inform the nurse of emergency and its location
in the plant.
If the nurse cannot be reached, dial emergency call, and inform any hospital
or fire department of the medical emergency. Give the dispatcher the nature
and location in the plant of medical emergency.
Unless you have been designated by management to be a first aid responder,
do not provide first aid. Make the victim as comfortable as possible until
medical help arrives.
2.7.3 Fire Fighting Strategy
Fire-fighting strategy should consider the following items.
Appointment of fire wardens, with subsequent training.
Location plans of safety shower, fire hoses, extinguishers, and water
sources.
Access for emergency services.
Provision of firewater lagoons.
Fire-fighting strategy involves the following basic procedures.
Universitas Indonesia
51
Universitas Indonesia
53
temporal coded signal. Thus, sirens produce a loud piercing wail that
makes them ideally suitable for initiating a site-wide evacuation
Visible Alarm which consists of flashing/steady lights and strobe
lights. Steady lights are well suited for areas where ambient noise
makes audible signals difficult to hear, for an example in area where
the compressor is in. These types of lights come with different
colored covers for increased attention and can be ordered with
rotating or flashing lights. Strobe lights use high intensity flash tubes
that are ideally suited for areas where high ambient light levels make
traditional rotating or flashing lights difficult to distinguish or where
ambient noise makes audible signals difficult to hear.
2.7.5 Policies for Updating and Maintaining the EAP
Since emergencies can occur anytime without warning, it is essential to
develop a policy to train all new staff on the various EAPs and their role
within the EAP. As part of new employee training/orientation, give all new
staff a copy of the EAPs and provide them a layout of the facility along with
where all the emergency exits, and escape routes are. New staff should be
provided with important locations in the event of specific emergencies, such
as where to take shelter. Change is constant. Keeping all EAPs current is a
major undertaking, but is the only way to assure an efficient emergency
response. New hires, building redesigns, new programs, office changes,
remodeling, and much more can all impact the effectiveness of an EAP.
2.8 Waste Management
In an industry, the activities that includes the process usually produces a
residue which is called as waste. The waste from the industries need to be treated
well or else it could have an impact on the environment and/or the sustainability of
the plant production. Regulations are made by the government concerning wastes
in industrial complex based on the Human Safety Environment. The waste is
classified based on their types, which are solid waste, liquid waste, gas waste, and
also the sound (noise) waste. The waste management will be mentioned below.
Universitas Indonesia
54
Universitas Indonesia
55
the fly ash is surrounded by a sintered glassy network structure, which effectively
control the leaching of heavy metals. This method can reduce the volume of waste
by 60% or more, and the products are resistant to leaching, which can be used as
building materials or raw materials for production of glass, ceramics.
Ash is widely used for various purposes but mainly to be used as a
replacement for materials that have a relatively low unit cost. The use of ash for hot
mix asphalt has been utilized in the United States, Japan and some European
countries. After screening and magnetic separation, ferrous and nonferrous metals
are removed from mixed ash which will then be mixed with other aggregates to be
used as a mixture of asphalt pavement. As long as there is proper handling, ash used
as asphalt will not cause environmental pollution. Besides, fly ash also contains
large amounts of SiO2 and Al2O3 and CaO which makes it to have a similar
composition of raw materials for cement production. Therefore it can also be used
as the raw materials for cement. However, washing pre-treatment of fly ash to
reduce water-soluble substances like chloride before cement curing will
significantly enhance the compressive strength and reduce the leaching toxicity of
the products. Ash can also be used for landfill cover as the environmental protection
facilities such as barrier layer and leachate recovery system. The pretreatment
process for ash such as screening, magnetic separation and particle size distribution
is unnecessary if used as landfill cover, therefore, it is a very good choice to utilize
ash for this purpose.
Before the ash is sold to the nearby cement factory, it has to be first treated
to meet the specification. Based on the list of treatment discussed above, this plant
uses the treatment of separation which will then be followed by stabilization using
thermal. After that, the ash will be ready to be transported to the nearby cement
factory and used as landfill cover. The thermal stabilization is preferred rather than
the solidification because it does not require any mixing process with cement and
the operational cost is lower.
2.8.2 Liquid Waste
Most of the liquid type waste comes from the main processes which is the
highest among other wastes in terms of number. The waste water can come from
the lithium carbonate synthesis process with the main objective is to extract the
Universitas Indonesia
56
lithium from water and to mix lithium with the carbonate, which we can determine
the amount of water outlet from the processes such as the electrochemical reactor
and the filtration waste. Whilst the other waste water are transported to the third
party for further treatment so that it won’t have harmful effects on to the
environment.
The liquid waste from the main process are mostly recirculated back into the
utility section so that it could be used back as the boiler feed water for the steam
generation and for the cooling water purposes. Other liquid waste is transported to
the third party.
2.8.3 Gas Waste
Throughout the whole process there is one flow of gas that is disposed and
some are recycled back into the process. The gas that is exposed into the
environment is none other than air itself that has been used as a heating medium in
the dryer unit in the lithium carbonation synthesis specifically in the purifying
process. All other gases are condensed back into the form of liquid and then
recycled back as the boiler feed water and/or as the cooling water.
Another gas waste from this plant is produced as the flue gas from the
combustion of natural gas in the steam generation process. It consists of mostly
carbon dioxide (CO2), and water vapor as well as excess oxygen (also derived from
the combustion air). It further contains a small percentage of a number of pollutants,
such as particulate matter, carbon monoxide, nitrogen oxides, and sulfur oxides.
The standard temperature and pressure for the flue gas is 50oC and 1 atm. The flue
gas for this plant has met the standard temperature and pressure. The gas residue
can be emitted directly to atmosphere because the amount of pollutans is very small.
These gas emissions have met the standards of Minister Environment
Decree No. Kep.13/Menlh/3/1995 about quality standards stationary source
emissions or BSN Standards (5000 ppm). From the standards, we can be directly
released gas waste into the environment by way of venting for CO2 emission and
hydrogen can be directly discharge into the air because it is not dangerous emission.
2.8.4 Sound
Sound can be generated by rotating equipment. Most of the operation tools in
the plant uses rotary tools such as pumps, blower, conveyor and crusher which have
Universitas Indonesia
57
motors and produces noise. The noise itself have levels that depends on the type of
rotary tool, capacity, performance, area and equipment operating effectiveness of
treatment or preventive maintenance programs are conducted. In order to decrease
the noise level, performing regular maintenance and replacing the parts that causes
the noise shall be done.
Noises can damage the health of personnel and also damages the mechanical
systems on the appliance. Regular maintenance and part replacements shall be
performed in order to decrease the noise level. Other actions shall be made such as
using the proper PPE for the personnel such as earplugs in the plants where noises
are made. Tools such as damper can also be applied for equipment or tools that
generates noise.
The noise standards set by the Ministry of Health is 60-70 dB and according to the
Ministry of Manpower Decree No. Kep.51/MEN/1999, the TLV (Threshold Limit
Value) for noise hazard is 85 dBA. Noise level exceeding the limit can cause
disorder includes physiological and psychological disorder. To overcome those
disorders, control of noise is needed by following procedures:
Eliminate noise transmission to workers. To eliminate or reduce the
transmission of noise to do with insulation workers labor or machinery is to
shut down or isolate the machine or equipment that emits noise. Basically,
to cover the noisy machines are as follows: Close the engine as close as
possible, rework the doors and all the holes are acoustic. If necessary, isolate
the machine from the floor to reduce vibration propagation.
Eliminate the noise from the sound source. Eliminating noise from the
sound source can be done by putting the marinade in a vibration source.
Providing protection to employees. Efforts to protect employees from noise
in the work environment can be applied by wearing ear protection devices
or personal protective equipment, in the form of ear plugs and ear muffs.
Universitas Indonesia
58
3 CHAPTER 3
PLANT LAYOUT
Universitas Indonesia
59
Although it still needed further studies for the composition of lithium, but as the
source of seawater is close to one another (PT. Pertamina RU V and PT. Pupuk
Kaltim), it has a high possibility that the composition would be close. The plant is
located close to the sea where the location is considered based on if at any time the
supply from Pertamina RU V’s cooling water unit waste cannot be taken or it is
used up, thus there is another alternative, which is taking the raw materials from
sea water. Sea water will be contained and evaporated first for several months and
only processed when there is lack of raw material from PT Pertamina RU V and
backup PT Pupuk Kalimantan Timur.
Proximity to Markets
Due to a huge amount of demand in consuming lithium carbonate in China
and the target market of this plant is to fulfill 1% of China’s lithium carbonate
demand, the location is determined based on the distance from China to Indonesia,
the closest to region in Indonesia to China with the availability of the raw materials
is in West Balikpapan region. The advantage of having a plant built near the sea is
that the access for shipping to destinations is easy and convenient because it is
located near the harbor where there is a lot of access to the product carrier ships.
Land Development Availability
Lithium carbonate demand in the future will certainly increase due to the
continued development of modernization such as electronic devices, electric tools,
electric vehicles, etc. The chosen location has more area to do expansion project in
the future that considers about the demands of lithium carbonate. The expansion
project also can spread its market in the future in order to supply domestically or to
do export. So, the production later will need additional constructions to fulfill the
demands.
Universitas Indonesia
60
Universitas Indonesia
61
4 CHAPTER 4
CONCLUSION
Universitas Indonesia
5 REFERENCES
Alejandro, R., Rojas, V., Javier, F., Garfias, V., Rodolfo, E., & Rueda, B. (2018).
Simulation of a triple effect evaporator of a solution of caustic soda, sodium
chloride, and sodium sulfate using Aspen Plus. [online] Available at:
https://doi.org/10.1016/j.compchemeng.2018.02.005 [Accessed 20
September 2019].
Bardi, U. (2010). Extracting Minerals from Seawater: An Energy Analysis.
Sustainability, pp. 980-992.
Belghaieb, J., Aboussaoud, W., Abdo, M., Hajji, N. (2011). Simulation and
Optimization of a Triple-Effect Distillation Unit. Gabes University: Tunisia.
Byrne, R. H., Makenzie, F. T. & Duxbury, A. C., 2019. Encyclopaedia Britannica.
[Online] Available at: https://www.britannica.com/science/seawater
[Accessed September 2019].
Calvo, E. (2019). Electrochemical methods for sustainable recovery of lithium from
natural brines and battery recycling. Current Opinion in Electrochemistry,
15, pp.102-108.
Chagnes, A. and Ś wiatowska, J. (2015). Lithium process chemistry. Amsterdam:
Elsevier.
Chen, N., Zhou, E., Duan, D. and Yang, X. (2017). Mechanochemistry synthesis of
high purity lithium carbonate. Korean Journal of Chemical Engineering,
34(10), pp.2748-2755.
Coalition, M. E., n.d. Minerals Database. [Online] Available at:
https://mineralseducationcoalition.org/minerals-database/lithium/ [Accessed
18 September 2019].
Dieselserviceandsupply.com. (2019). Natural Gas Generators vs Diesel
Generators, Gas Power Generator, Gas Generator | Diesel Service. [online]
Available at:
https://www.dieselserviceandsupply.com/Natural_Gas_vs_Diesel_Generato
rs.aspx [Accessed 3 Oct. 2019].
62 Universitas Indonesia
63
Dunn, J., Gaines, L., Barnes, M., Sullivan, J. and Wang, M. (2014). Material and
Energy Flows in the Materials Production, Assembly, and End-of-Life Stages
of the Automotive Lithium-Ion Battery Life Cycle. Energy Systems Division.
El-Dessouky H., Ettouney H.M. and AL-Juwayhel F. (2000). Multiple effect
evaporation-vapour compression desalination processes, Institution of
Chemical Engineers, Trans IChemE, Vol. 78, Part A.
Encyclopedia.che.engin.umich.edu. (2019). Visual Encyclopedia of Chemical
Engineering. [online] Available at:
http://encyclopedia.che.engin.umich.edu/Pages/Reactors/FBR/FBR.html
[Accessed 3 Oct. 2019].
Green Car Congress. (2019). CRU: Lithium prices plunging as hype meets reality;
impact of new supply, disappointing BEV sales. [online] Available at:
https://www.greencarcongress.com/2019/09/20190906-cru.html [Accessed 3
Oct. 2019].
Kesler, S. E. et al., 2012. Ore Geology Reviews. Elsevier, pp. 55-69.
Kim, S., Joo, H., Moon, T., Kim, S. and Yoon, J. (2019). Rapid and selective lithium
recovery from desalination brine using an electrochemical
system. Environmental Science: Processes & Impacts, 21(4), pp.667-676.
Lee, J., Yu, S., Kim, C., Sung, Y. and Yoon, J. (2013). Highly selective lithium
recovery from brine using a λ-MnO2–Ag battery. Physical Chemistry
Chemical Physics, 15(20), p.7690.
Li, L., Deshmane, V., Paranthaman, M., Bhave, R., Moyer, B. and Harrison, S.
(2018). Lithium Recovery from Aqueous Resources and Batteries: A Brief
Review. Johnson Matthey Technology Review, 62(2), pp.161-176.
Liu, G., Zhao, Z. and Ghahreman, A. (2019). Novel approaches for lithium
extraction from salt-lake brines: A review. Hydrometallurgy, 187, pp.81-100.
Marchini, F., Rubi, D., Pozo, M., Williams, F. J., & Calvo, E. J. (2016). Surface
Chemistry and Lithium-Ion Exchange in LiMn 2 O 4 for the Electrochemical
Selective Extraction of LiCl from Natural Salt Lake Brines. [online]
Available at: https://doi.org/10.1021/acs.jpcc.5b11722 [Accessed 20
September 2019].
Universitas Indonesia
64
Universitas Indonesia
65
Omarova, M., Koishybay, A., Yesibolati, N., Mentbayeva, A., Kurmanbayeva, I.,
& Bakenov, Z. (2015). Nickel Hexacyanoferrate Nanoparticles as a Low
Cost Cathode Material for Lithium-Ion Batteries. Electrochimica Acta, 184,
58–63.
Wang, F., Borodin, O., Gao, T., Fan, X., Sun, W., Han, F., Faraone, A., Dura, J. A.,
Xu, K., Wang, C. (2018). Highly reversible zinc metal anode for aqueous
batteries. Nature Materials, Macmillan Publishers.
Wang, G., Qu, Q., Wang, B., Shi, Y., Tian, S., & Wu, Y. (2008). An Aqueous
Electrochemical Energy Storage System Based on Doping and Intercalation:
Ppy//LiMn2O4, 2299–2301.
Kuwabata, S., Masui, S., & Yoneyama, H. (1999). Charge-discharge properties of
composites of LiMn2O4 and polypyrrole as positive electrode materials for 4
V class of rechargeable Li batteries, Electrochimica Acta 44, 4593–4600.
Universitas Indonesia
66
6 APPENDICES A
Sodium Carbonate MSDS
Universitas Indonesia
67
Universitas Indonesia
68
Universitas Indonesia
69
Universitas Indonesia
70
7 APPENDICES B
Lithium Carbonate MSDS
Universitas Indonesia
71
Universitas Indonesia
72
Universitas Indonesia
73
Universitas Indonesia
74
8 APPENDICES C
Air MSDS
Universitas Indonesia
75
Universitas Indonesia
76
9 APPENDICES D
Seawater MSDS
Universitas Indonesia
77
Universitas Indonesia
78
Universitas Indonesia
79
Universitas Indonesia
80
Universitas Indonesia