COMPARISON STATEMENT FOR PILE FOUNDATION

Southern Geotechics A C E Foundation J B Rate

Description of work Unit Rate Quantity Amount Description of work Unit Rate Quantity Amount Description of work Unit Rate Quantity Amount

1 Mobillising boring and Mobillising boring and Mobillising boring and


concreting cast in-situ concreting cast in-situ concreting cast in-situ
D M C R C C Piles with D M C R C C Piles with D M C R C C Piles with
TRACTOR ROTARY DRILLING TRACTOR ROTARY DRILLING TRACTOR ROTARY DRILLING
M20 mix ,Including Cement, M20 mix ,Including Cement, M20 mix ,Including Cement,
Steel&labour Chargeetc Steel&labour Chargeetc Steel&labour Chargeetc
Complete. Complete. Complete.
500mmpile RM 3950.00 1200 4740000.00 500mmpile RM 4100.00 1200 4920000.00 500mmpile RM 3850.00 1200.00 4620000.00
600mmpile RM 5250.00 100.00 525000.00 600mmpile RM 5200.00 100.00 520000.00 600mmpile RM 5000.00 100.00 500000.00
5440000.00 5120000.00
Mobilization Charges Including the Rate Mobilization Charges extra 15000.00 Mobilization Charges extra 9000.00
Marking for Pile Extra charge 4500.00 Marking for Pile 4500.00 Marking for Pile 4500.00
5269500.00 5459500.00 5133500.00
G S T Extra 18% 948510.00 G S T Extra 18% 982710.00 G S T Extra 18% 924030.00
Grand total 6218010.00 Grand total 6442210.00 Grand total 6057530.00

Water charge extra Water included Water included

Data Data
500mmpile 1m 0.20m3 600mmpile 1m 0.28m3
1m Cement 1.60bag 1m Cement 2.24bag
1m Steel 23kg 1m Steel 30kg
Rate of cement/bag 370.00Rs Rate of cement/bag 370.00Rs
1.60 *370 = 592.00 2.24 *370 = 828.80
Rate of steel /Kg 55.00Rs Rate of steel /Kg 55.00Rs
23*55 = 1265.00 30*55 = 1650.00
1m Metal =0.18m3 1m Metal =0.25m3
1m Sand =0.10 1m Sand =0.14m3
Rate of Metal 1Cft 40Rs Rate of Metal 1Cft 40Rs
Rate of Sand 1Cf 65 Rate of Sand 1Cf 65
Metal 6.35Cft*40 = 254.00 Metal 8.83Cft*40 = 353.20
Sand 3.53Cft *65 = 229.45 Sand 4.94Cft *65 = 321.10
Labourcharge for 1m 500.00 Labourcharge for 1m 625.00
Total 2840.45 Total 3778.10
Add CP 10% 284.00 Add CP 10% 377.81
3124.45 4155.91
Rent for Machinery/1m Inculdin Unloading charge 700.00 Rent for Machinery/1m Inculding Unloding charge 700.00
Grand total 3824.45 Grand total 4533.72
Say 3850.00 5000.00