Beruflich Dokumente
Kultur Dokumente
Boundary limits are identified to determine what is vital to include in the assessment
The organizing process of aligning priorities, screening risks, and identifying boundaries improves
the efficiency and effectiveness of conducting the RBI assessment and its end-results in
managing risk.
Why the assessment is being done?
How the RBI assessment will be carried out?
What knowledge and skills are required for the assessment?
Who is on the RBI team?
What are their roles in the RBI process?
Who is responsible and accountable for what actions?
Which facilities, assets, and components will be included?
What data is to be used in the assessment?
What codes and standards are applicable?
When the assessment will be completed?
How long the assessment will remain in effect and when it will be updated?
How the results will be used?
What is the plan period?
An RBI assessment made on new equipment or a new project, while in the design stage, may
yield important information on potential risks.
This may allow potential risks to be minimized by design and have a RBI plan in place prior to
actual installation.
The end of life case for plant operation is about gaining the maximum remaining economic benefit
from an asset without undue personnel, environmental, or financial risk
End of life strategies focus the inspection efforts directly on high-risk areas where the inspections
will provide a reduction of risk during the remaining life of the plant.
End of life inspection RBI strategies may be developed in association with a Fitness-For-Service
assessment of damaged components using methods described in API 579-1/ASME FFS-1.
Boundaries for physical assets included in the assessment are established consistent with the
overall objectives.
Typically, RBI is done on multiple pieces of equipment (e.g. an entire process unit) rather than on
a single component
Screening at the facility level may be done by a simplified qualitative RBI assessment. Screening at
the facility level could also be done by the following:
Examples of key questions to answer at the facility level are listed as follows.
Is the facility located in a regulatory jurisdiction that will accept modifications to statutory inspection
intervals based on RBI?
Is the management of the facility willing to invest in the resources necessary to achieve the benefits
of RBI?
Does the facility have sufficient resources and expertise available to conduct the RBI assessment
and sustain the RBI program?
If the scope of the RBI assessment is a multi-unit facility, the first step in the application of RBI is
screening of entire process units to rank relative risk.
Examples of key questions to answer at the process unit level are similar to the questions at the facility
level.
Does the process unit have a significant impact on the operation of the facility?
Are there significant risks involved in the operation of the process unit and would the effect of risk
reduction be measurable?
Do process unit operators see that some benefit may be gained through the application of RBI?
Does the process unit have sufficient resources and expertise available to conduct the RBI
assessment?
What is the failure history in this unit?
Potential high-risk items should receive greater attention in the risk assessment
Screening of equipment items is sometimes conducted to identify the higher risk items to carry
forward to more detailed risk assessment.
An RBI assessment may be applied to all pressure-containing equipment such as the following:
Piping,
Pressure vessels,
Reactors,
Heat exchangers,
Furnaces and boilers,
Tanks,
Pumps (pressure boundary),
Compressors (pressure boundary),
Pressure-relief devices,
Control valves (pressure boundary).
The RBI assessment is being done for an overall optimization of inspection resources and
environmental and business COF are included.
There is a specific reliability problem in a utility system. An example would be a cooling water
system with corrosion and fouling problems. An RBI approach could assist in developing the most
effective combination of inspection, mitigation, monitoring, and treatment for the entire facility.
Reliability of the process unit is a major objective of the RBI analysis.
When emergency systems (e.g. flare systems, emergency shutdown systems) are included in the RBI
assessment, their service conditions during both routine operations and upset should be considered.
Process conditions during start-up and shutdown can have a significant effect on the risk of a plant
especially when they are more severe (likely to cause accelerated deterioration) than normal
conditions and as such should be considered for all equipment covered by the RBI assessment.
A good example is polythionic acid stress corrosion cracking (PASCC).
Start-up lines are often included within the process piping and their service conditions during
start-up and subsequent operation should be considered.
Changes in the process, such as pressure, temperature, or fluid composition, resulting from unit
abnormal or upset conditions should be considered in the RBI assessment.
The RBI assessment on systems with cyclic operation, such as reactor regeneration systems,
should consider the complete cyclic range of conditions.
Cyclic or intermittent conditions could impact the POF due to some damage mechanisms (e.g.
mechanical fatigue, thermal fatigue, corrosion-fatigue, and corrosion under insulation).
Examples
Include pressure swing absorption vessels, catalytic reforming unit regeneration piping systems,
deaerator vessels, and insulated equipment that normally operates at higher temperatures but is
subjected to periods of inactivity.
6.4.4 Operating Time Period
The unit run lengths of the selected process units/equipment is an important limit to consider. The
RBI assessment may include the entire operational life, or may be for a selected period.
For example,
Process units are occasionally shut down for maintenance activities and the associated run
length may depend on the condition of the equipment in the unit.
An RBI analysis may focus on the current run period or may include the current and next-
projected run period.
The time period may also influence the types of decisions and inspection plans that result from
the study, such as inspection, repair, replace, operating, and so on.
Projected operational changes are also important as part of the basis for the operational time
period.
A strategy should be developed, matching the type of assessment to the expected or evaluated
risk.
Processing units that are expected to have lower risk may only require simple, fairly conservative
methods to adequately accomplish the RBI objectives, whereas process units that have a higher
expected risk may require more detailed methods.
Another example would be to evaluate all equipment items in a process unit qualitatively and then
evaluate the higher risk items identified more quantitatively.