Reliance Life Sciences Pvt. Ltd.

cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 1 of 195

COMMISSIONING TEST PLAN (CTP)


AHU-101 AIR HANDLING UNIT

Reliance Life Sciences


cGMP2, Navi Mumbai, India

Pre-Execution Approval Name Signature Date

System User

Engineering

Validation

Quality Assurance

Post-Execution Approval Name Signature Date

System User

Engineering

Validation

Quality Assurance

Revision Issue date Revision description By:

T.Pradhan
1.0 25 Jun 07 Issued for Approval
Air Treatment Engineer
Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 2 of 195

Table of Contents
.....
.....
1. SCOPE

2
2. PURPOSE

6
3. CTP PRE-EXECUTION SIGNATURE LIST

6
4. INSPECTION PHASE

8
4.1 Equipment Receipt and Installation Verification.....................................................8
4.2 Control Devices- Receipt, Installation, Calibration, & Loop Check Verification
140
4.4 Control Devices- Receipt, Installation, Calibration, & Loop Check Verification
141
4.3 Electrical Cable and Conduit Installation Check Sheet.........................................143
4.4 GSS Ducting and Insulation Installation Verification..........................................144
4.5 Piping & and Insulation Installation Verification................................................146
4.6. Chilled Water Piping installation Verification......................................................147
4.7 Hot Water Piping Installation Verification...........................................................148
4.8 Drawing and Assembly Inspection......................................................................149
4.9 Safety Check.......................................................................................................150
4.10 Lock Out Tag out Check Sheet.............................................................................151
4.11 Rotating Equipment Installation Verification......................................................152
4.12 Red Lined As Built P&ID......................................................................................157
5. REGULATION, ADJUSTMENT, AND SETTING TO WORK PHASE

158
5.1 Factory Acceptance Test (FAT) Review...............................................................158
5.2 Utility Availability Check Sheet and Log..............................................................159
5.3 Site Acceptance Testing (SAT) Review................................................................160
5.4 Alarm and Interlock Testing................................................................................161
6 SYSTEM FUNCTIONAL TESTING

162
6.1 AHU Operational Test..........................................................................................162
6.2 VFD Operational Testing.....................................................................................163
6.3 HEPA Filter Testing..............................................................................................164
7. MEASUREMENT AND TEST EQUIPMENT

189
Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 3 of 195

8 TURNOVER PACKAGE VERIFICATION

190
9 COMMISSIONING TEST PLAN ACCEPTANCE CRITERIA SUMMARY

191
10 PUNCH LIST LOG/DATA SHEET

193
11Appendix

195

1. Scope

This Commissioning Test Plan (CTP) is for the AHU-101 air Handling Unit in 1 st Interstitial Floor for the Reliance
Life Sciences Pvt Ltd. (RLS) cGMP Plant2 project at Navi Mumbai, India.
The Air Handling Unit system consists of the following major equipment items:
 AHU-101 : Air Handling Unit
 RF-101-01 : Inline Centrifugal Fan (Return Fan)
 EF-101-01 : Inline Centrifugal Fan(Exhaust Fan)
 EF-101-02 : Inline Centrifugal Fan(Exhaust Fan)
 RHC-101-01 : Re-Heat Coil-Room no. L - 121
 RHC-101-02 : Re-Heat Coil-Room No L- 124/120/122/123/123A
 RHC-101-03 : Re-Heat Coil-Room No.L - 137
 RHC-101-04 : Re-Heat Coil-Room No.L – 138/139A/137A/137B/137C
 RHC-101-05 : Re-Heat Coil-Room No.L - 116
 RHC-101-06 : Re-Heat Coil-Room No.L – 119/115/117/118/118A
 RHC-101-07 : Re-Heat Coil-Room No.L – 138
 RHC-101-08 : Re-Heat Coil-Room No.L - 132/131/133/134/135
 RHC-101-09 : Re-Heat Coil-Room No.L - 130
 RHC-101-10 : Re-Heat Coil-Room No.L – 125/126/127/128/129
 AF-101-01 : Air Filter - Pre- Filter Intake to SF-101 (G4)
 AF-101-02 : Air Filter - Intake to SF-101 (F6)
 AF-101-03 : Air Filter –Supply Air Fine Filter (F8)
 HF-101-115 : Terminal HEPA Filter-Room No.L-115
 HF-101-116A : Terminal HEPA Filter-Room No.L-116
 HF-101-116B : Terminal HEPA Filter-Room No.L-116
 HF-101-116C : Terminal HEPA Filter-Room No.L-116
 HF-101-116D : Terminal HEPA Filter-Room No L-116
 HF-101-116E : Terminal HEPA Filter-Room No.L-116
 HF-101-117 : Terminal HEPA Filter-Room No.L-117
 HF-101-118 : Terminal HEPA Filter-Room No.L-118
 HF-101-118AA : Terminal HEPA Filter-Room No.L-118A
Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 4 of 195

 HF-101-119 : Terminal HEPA Filter-Room No.L-119


 HF-101-120 : Terminal HEPA Filter-Room No.L-120
 HF-101-121A : Terminal HEPA Filter-Room No.L-121
 HF-101-121B : Terminal HEPA Filter-Room No.L-121
 HF-101-121C : Terminal HEPA Filter-Room No.L-121
 HF-101-121D : Terminal HEPA Filter-Room No.L-121
 HF-101-121E : Terminal HEPA Filter-Room No.L-121
 HF-101-122 : Terminal HEPA Filter-Room No.L-122
 HF-101-123 : Terminal HEPA Filter-Room No.L-123
 HF-101-123AA : Terminal HEPA Filter-Room No.L-123A
 HF-101-124 : Terminal HEPA Filter-Room No.L-124
 HF-101-125 : Terminal HEPA Filter-Room No.L-125
 HF-101-126 : Terminal HEPA Filter-Room No.L-126
 HF-101-127 : Terminal HEPA Filter-Room No.L-127
 HF-101-128 : Terminal HEPA Filter-Room No.L-128
 HF-101-129 : Terminal HEPA Filter-Room No.L-129
 HF-101-130A : Terminal HEPA Filter-Room No.L-130
 HF-101-130B : Terminal HEPA Filter-Room No.L-130
 HF-101-130C : Terminal HEPA Filter-Room No.L-130
 HF-101-130D : Terminal HEPA Filter-Room No.L-130
 HF-101-130E : Terminal HEPA Filter-Room No.L-130
 HF-101-131 : Terminal HEPA Filter-Room No.L-131
 HF-101-132 : Terminal HEPA Filter-Room No.L-132
 HF-101-133 : Terminal HEPA Filter-Room No.L-133
 HF-101-134 : Terminal HEPA Filter-Room No.L-134
 HF-101-135 : Terminal HEPA Filter-Room No.L-135
 HF-101-136A : Terminal HEPA Filter-Room No.L-136
 HF-101-136B : Terminal HEPA Filter-Room No.L-136
 HF-101-136C : Terminal HEPA Filter-Room No.L-136
 HF-101-136D : Terminal HEPA Filter-Room No.L-136
 HF-101-136E : Terminal HEPA Filter-Room No.L-136
 HF-101-137A : Terminal HEPA Filter-Room No.L-137
 HF-101-137B : Terminal HEPA Filter-Room No.L-137
 HF-101-137C : Terminal HEPA Filter-Room No.L-137
 HF-101-137D : Terminal HEPA Filter-Room No.L-137
 HF-101-137E : Terminal HEPA Filter-Room No.L-137
 HF-101-137AA : Terminal HEPA Filter-Room No.L-137A
 HF-101-137BA : Terminal HEPA Filter-Room No.L-137B
 HF-101-137CA : Terminal HEPA Filter-Room No.L-137C
 HF-101-138 : Terminal HEPA Filter-Room No.L-138
 HF-101-139A : Terminal HEPA Filter-Room No.L-139
 HF-101-139B : Terminal HEPA Filter-Room No.L-139
 HF-101-139C : Terminal HEPA Filter-Room No.L-139
 HF-101-139D : Terminal HEPA Filter-Room No.L-139
 HF-101-139E : Terminal HEPA Filter-Room No.L-139
 FCD-101-01 : Flow Control Damper-Room No.L-121
 FCD-101-02 : Flow Control Damper-Room No.L-124
 FCD-101-03 : Flow Control Damper-Room No.L-120
 FCD-101-04 : Flow Control Damper-Room No.L-122
 FCD-101-05 : Flow Control Damper-Room No.L-123
 FCD-101-06 : Flow Control Damper-Room No.L-123A
Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 5 of 195

 FCD-101-07 : Flow Control Damper-Room No.L-116


 FCD-101-08 : Flow Control Damper-Room No.L-119
 FCD-101-09 : Flow Control Damper-Room No.L-115
 FCD-101-10 : Flow Control Damper-Room No.L-117
 FCD-101-11 : Flow Control Damper-Room No.L-118
 FCD-101-12 : Flow Control Damper-Room No.L-118A
 FCD-101-13 : Flow Control Damper-Room No.L-130
 FCD-101-14 : Flow Control Damper-Room No.L-126
 FCD-101-15 : Flow Control Damper-Room No.L-128
 FCD-101-16 : Flow Control Damper-Room No.L-127
 FCD-101-17 : Flow Control Damper-Room No.L-125
 FCD-101-18 : Flow Control Damper-Room No.L-129
 FCD-101-19 : Flow Control Damper-Room No.L-137
 FCD-101-20 : Flow Control Damper-Room No.L-138
 FCD-101-21 : Flow Control Damper-Room No.L-139A
 FCD-101-22 : Flow Control Damper-Room No.L-137A
 FCD-101-23 : Flow Control Damper-Room No.L-137B
 FCD-101-24 : Flow Control Damper-Room No.L-137C
 FCD-101-25 : Flow Control Damper-Room No.L-136
 FCD-101-26 : Flow Control Damper-Room No.L-132
 FCD-101-27 : Flow Control Damper-Room No.L-131
 FCD-101-28 : Flow Control Damper-Room No.L-133
 FCD-101-29 : Flow Control Damper-Room No.L-134
 FCD-101-30 : Flow Control Damper-Room No.L-135
 ACD-101-01 : Air Control Damper- AHU 101
 PCD-101-01 : Pressure Control Damper-Room No.L-121
 PCD-101-02 : Pressure Control Damper-Room No.L-124
 PCD-101-03 : Pressure Control Damper-Room No.L-120
 PCD-101-04 : Pressure Control Damper-Room No.L-122
 PCD-101-05 : Pressure Control Damper-Room No.L-123
 PCD-101-06 : Pressure Control Damper-Room No.L-123A
 PCD-101-07 : Pressure Control Damper-Room No.L-116
 PCD-101-08 : Pressure Control Damper-Room No.L-119
 PCD-101-09 : Pressure Control Damper-Room No.L-115
PCD-101-10 : Pressure Control Damper-Room No.L-117
 PCD-101-11 : Pressure Control Damper-Room No.L-118
 PCD-101-12 : Pressure Control Damper-Room No.L-118A
 PCD-101-13 : Pressure Control Damper-Room No.L-130
 PCD-101-14 : Pressure Control Damper-Room No.L-126
 PCD-101-15 : Pressure Control Damper-Room No.L-128
 PCD-101-16 : Pressure Control Damper-Room No.L-127
 PCD-101-17 : Pressure Control Damper-Room No.L-125
 PCD-101-18 : Pressure Control Damper-Room No.L-129
 PCD-101-19 : Pressure Control Damper-Room No.L-137
 PCD-101-20 : Pressure Control Damper-Room No.L-138
 PCD-101-21 : Pressure Control Damper-Room No.L-139A
 PCD-101-22 : Pressure Control Damper-Room No.L-137A
 PCD-101-23 : Pressure Control Damper-Room No.L-137B
 PCD-101-24 : Pressure Control Damper-Room No.L-137C
 PCD-101-25 : Pressure Control Damper-Room No.L-136
 PCD-101-26 : Pressure Control Damper-Room No.L-132
Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 6 of 195

 PCD-101-27 : Pressure Control Damper-Room No.L-131


 PCD-101-28 : Pressure Control Damper-Room No.L-133
 PCD-101-29 : Pressure Control Damper-Room No.L-134
 PCD-101-30 : Pressure Control Damper-Room No.L-135
 SF-101-01 : Supply fan

The system is controlled and monitored by a Building Management System (BMS).


Commissioning of the BMS is included under a separate CTP, and is not included in the scope of this document.

This system is depicted on the following HVAC and P&IDs:

 1293-RB5-HB-801 : HVAC AIR FLOW DIAGRAM SYSTEM AHU-101


 RB5-HE-826 : ESC, OCULAR, AND HSC LABSLAB AND OLLAGEN.
 RB5-HE-829 : ESC, OCULAR, AND HSC LABSLAB AND OLLAGEN.
 RB5-HE-830 : ESC, OCULAR, AND HSC LABSLAB AND OLLAGEN.
 RBE-HE-808 : COOLING COIL PIPING CONNECTION DETAILS
 RBE-HE-803 : HOT WATER COIL CONNECTION DETAILS

2. Purpose

This commissioning test plan describes the testing/verification activities that will be completed/documented to
verify that the system is ready for turnover to qualification (for direct impact systems) or to the system owner
(indirect and no impact systems). For direct impact systems, commissioning will further allow for the resolution
of punch list items prior to carryover as deviations to the qualification phase.

The purpose of commissioning is to provide a well-planned, documented approach to ensure that start-up and
turnover of each system results in an operational, safe, and functional system that meets user requirements and
operational expectations. This commissioning document will be executed by completing a series of data
sheets.

Commissioning activities are divided into three phases:


 Inspection
 Regulation, Adjustment, and Setting to Work
 Functional Testing
Datasheets in this commissioning test plan are completed for each of these three phases .
Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 7 of 195

3. CTP Pre-Execution Signature List

This datasheet is signed/initialed/dated by all individuals involved in the execution/approval of the


commissioning test plan (CTP). Each person’s title and company is also indicated on the form.

CTP PRE-EXECUTION SIGNATURE LIST


Printed Name Signature Initials Company/Title Date

Comments

Reviewed By: Date:

4. Inspection Phase
Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 8 of 195

4.1 Equipment Receipt and Installation Verification

Verified
Item Results
By/Date
Tag #/P&ID Number: AHU-101 /
1293-RB5- HB-801 &
6018-11C
System/Equipment Description: Air Handling Unit -101
Manufacturer: CARRYAIRE
Air Flow Capacity/Static pressure/Motor Rating: 19730 CFM/
230MM WG/60HP
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Fan & Motor, Cooling, Coil, Drain tray, Diffuser plate, sight
glass, Service lights etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is equipment name plate and tag number in place? (Yes/No)
Is access door for maintenance as per drawing specification
 (yes or no)
All Utility hook ups are completed (Chilled water, Hot water,
Instrumentation, Electrical supply, Drain, etc) (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 9 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number : RF-101-01/
1293-RB5- HB-801
System/Equipment Description: Duct mounted Inline
Centrifugal Fan(Return
Fan-RF)
Manufacturer: Kruger
Fan CFM/Static Pressure/Motor rating:
19740CFM/3.5INW/20HP
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is access door for maintenance provided as per
specifications, drawings?(Yes/No)
Is the equipment installed and provided with all accessories
(Housing, AVM, Bearings, Couplings, etc. as applicable) in
accordance with drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is Fan name plate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation? (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 10 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: EF-101-01 /
1293-RB5- HB-801
System/Equipment Description: Exhaust Fans
(Centrifugal)
Manufacturer: Kruger
Fan CFM/Static Pressure/Motor rating: 320CFM/2.5 WC/3HP
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is access door for maintenance provided as per
specifications, drawings?(Yes/No)
Is the equipment installed and provided with all accessories
(Housing, AVM, Bearings, Couplings, etc. as applicable) in
accordance with drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Have all gaskets for Fan been installed? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 11 of 195

4.1 Equipment Receipt and Installation Verification (continued)

Verified
Item Results
By/Date
Tag #/P&ID Number: EF-101-02 /
1293-RB5- HB-801
System/Equipment Description: Exhaust Fans
(Centrifugal)
Manufacturer: Kruger
Fan CFM/Static Pressure/Motor rating: 3330CFM/2
WC/2.2KW
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is access door for maintenance provided as per
specifications, drawings?(Yes/No)
Is the equipment installed and provided with all accessories
(Housing, AVM, Bearings, Couplings, etc. as applicable) in
accordance with drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Have all gaskets for Fan been installed? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 12 of 195

4.1 Equipment Receipt and Installation Verification (continued)

Verified
Item Results
By/Date
Tag #/P&ID Number: RHC-101-01 /
1293-RB5-HB-801
System/Equipment Description: Duct mounted Re-Heat
Coil
Manufacturer: Carryaire
Face Velocity/Air Flow: 800 FPM/2530CFM
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Outer Casing, Coil drain etc. as applicable) in accordance
with drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Have all sealing for Re-heat coil been complete? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 13 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: RHC-101-02 /
1293-RB5-HB-801
System/Equipment Description: Duct mounted Re-Heat
Coil
Manufacturer: Carryaire
Face Velocity/Air Flow: 800 FPM/1090CFM
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Outer Casing, Coil drain etc. as applicable) in accordance
with drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Have all sealing for Re-heat coil been complete? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 14 of 195

4.1 Equipment Receipt and Installation Verification (continued)

Verified
Item Results
By/Date
Tag #/P&ID Number: RHC-101-03 /
1293-RB5-HB-801
System/Equipment Description: Duct mounted Re-Heat
Coil
Manufacturer: Carryaire
Face Velocity/Air Flow: 800 FPM/2870CFM
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Outer Casing, Coil drain etc. as applicable) in accordance
with drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Have all sealing for Re-heat coil been complete? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 15 of 195

4.1 Equipment Receipt and Installation Verification (continued)

Verified
Item Results
By/Date
Tag #/P&ID Number: RHC-101-04 /
1293-RB5-HB-801
System/Equipment Description: Duct mounted Re-Heat
Coil
Manufacturer: Carryaire
Face Velocity/Air Flow: 800 FPM/1110CFM
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Outer Casing, Coil drain etc. as applicable) in accordance
with drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Have all sealing for Re-heat coil been complete? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 16 of 195

4.1 Equipment Receipt and Installation Verification (continued)

Verified
Item Results
By/Date
Tag #/P&ID Number: RHC-101-05 /
1293-RB5-HB-801
System/Equipment Description: Duct mounted Re-Heat
Coil
Manufacturer: Carryaire
Face Velocity/Air Flow: 800 FPM/2870CFM
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Outer Casing, Coil drain etc. as applicable) in accordance
with drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Have all sealing for Re-heat coil been complete? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 17 of 195

4.1 Equipment Receipt and Installation Verification (continued)

Verified
Item Results
By/Date
Tag #/P&ID Number: RHC-101-06 /
1293-RB5-HB-801
System/Equipment Description: Duct mounted Re-Heat
Coil
Manufacturer: Carryaire
Face Velocity/Air Flow: 800 FPM /1090 CFM
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Outer Casing, Coil drain etc. as applicable) in accordance
with drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Have all sealing for Re-heat coil been complete? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 18 of 195

4.1 Equipment Receipt and Installation Verification (continued)

Verified
Item Results
By/Date
Tag #/P&ID Number: RHC-101-07 /
1293-RB5-HB-801
System/Equipment Description: Duct mounted Re-Heat
Coil
Manufacturer: Carryaire
Face Velocity/Air Flow: 800 FPM / 2990 CFM
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Outer Casing, Coil drain etc. as applicable) in accordance
with drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Have all sealing for Re-heat coil been complete? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 19 of 195

1.1 Equipment Receipt and Installation Verification (continued)

Verified
Item Results
By/Date
Tag #/P&ID Number: RHC-101-08 /
1293-RB5-HB-801
System/Equipment Description: Duct mounted Re-Heat
Coil
Manufacturer: Carryaire
Face Velocity/Air Flow: 800 FPM / 1090 CFM
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Outer Casing, Coil drain etc. as applicable) in accordance
with drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Have all sealing for Re-heat coil been complete? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 20 of 195

2.1 Equipment Receipt and Installation Verification (continued)

Verified
Item Results
By/Date
Tag #/P&ID Number: RHC-101-09 /
1293-RB5-HB-801
System/Equipment Description: Duct mounted Re-Heat
Coil
Manufacturer: Carryaire
Face Velocity/Air Flow: 800 FPM / 2970 CFM
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Outer Casing, Coil drain etc. as applicable) in accordance
with drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Have all sealing for Re-heat coil been complete? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 21 of 195

3.1 Equipment Receipt and Installation Verification (continued)

Verified
Item Results
By/Date
Tag #/P&ID Number: RHC-101-10
/
1293-RB5-HB-801
System/Equipment Description: Duct mounted Re-Heat
Coil
Manufacturer: Carryaire
Face Velocity/Air Flow: 800 FPM / 1190 CFM
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Outer Casing, Coil drain etc. as applicable) in accordance
with drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Have all sealing for Re-heat coil been complete? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 22 of 195

4.1 Equipment Receipt and Installation Verification (continued)

Verified
Item Results
By/Date
Tag #/P&ID Number: AF-101-01 /
1293-RB5- HB-801
System / Equipment Description: Air Filter-Pre filter Intake
Manufacturer: Thermodyne
Air Flow capacity(each)/Pressure Drop: 3400 CMH / 3-10
mm WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Have the filter been installed- if applicable (Yes/No)?
Is name plate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 23 of 195

4.1 Equipment Receipt and Installation Verification (continued)

Verified
Item Results
By/Date
Tag #/P&ID Number: AF-101-02 /
1293-RB5- HB-801
System/Equipment Description: Air Filter-Intake to SF-
101
Manufacturer: Thermodyne
Air Flow capacity(each)/Pressure Drop: 3400CMH/3-10 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 24 of 195

4.1 Equipment Receipt and Installation Verification (continued)

Verified
Item Results
By/Date
Tag #/P&ID Number: AF-101-03 /
1293-RB5- HB-801
System/Equipment Description: Air Filter-Supply Air Fine
Filter
Manufacturer: Thermodyne
Air Flow capacity(each)/Pressure Drop: 3400CMH/3-10 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 25 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-115 /
1293-RB5- HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity (each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 26 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-116A /
1293-RB5- HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 27 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-116B /
1293-RB5- HB-801
System/Equipment Description:. Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 28 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-116C/
1293-RB5- HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 29 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-116D /
1293-RB5- HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 30 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-116E /
1293-RB5- HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 31 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-117 /
1293-RB5-HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

1.4 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 32 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-118 /
1293-RB5- HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 33 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-118AA/1293-
RB5-
HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 34 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-119/1293-RB5-
HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Is vessel stamped with code and pressure/temperature rating
(if applicable)? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 35 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-120/1293-RB5-
HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Is vessel stamped with code and pressure/temperature rating
(if applicable)? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 36 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-121A/1293-RB5-
HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Is vessel stamped with code and pressure/temperature rating
(if applicable)? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 37 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-121B /
1293-RB5- HB-801
System/Equipment Description:. Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 38 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-121C/1293-RB5-
HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 39 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-121D/1293-RB5-
HB-801
System/Equipment Description:. Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 40 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-121E/1293-RB5-
HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 41 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-122/1293-RB5-
HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 42 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-123/1293-RB5-
HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 43 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-123AA/1293-
RB5-
HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 44 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-102-124/1293-RB5-
HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 45 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-125/1293-RB5-
HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity (each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1.Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 46 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-126/1293-RB5-
HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 47 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-127/1293-RB5-
HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Have the filter been installed- if applicable (Yes/No)?
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 48 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-128/1293-RB5-
HB-801
System/Equipment Description:. Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 49 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-129/1293-RB5-
HB-801
System/Equipment Description:. Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 50 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-130A/1293-RB5-
HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 51 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-130B/1293-RB5-
HB-801
System/Equipment Description:. Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Have the filter been installed- if applicable (Yes/No)?
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 52 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-130C/1293-RB5-
HB-801
System/Equipment Description:. Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Have the filter been installed- if applicable (Yes/No)?
Is nameplate and tag number in place? (Yes/No)
Is vessel stamped with code and pressure/temperature rating
(if applicable)? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 53 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-130D/1293-RB5-
HB-801
System/Equipment Description:. Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 54 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-130E/1293-RB5-
HB-801
System/Equipment Description:. Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 55 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-131/1293-RB5-
HB-801
System/Equipment Description:. Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Have the filter been installed- if applicable (Yes/No)?
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 56 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-132/1293-RB5-
HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 57 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-133/1293-RB5-
HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 58 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-134/1293-RB5-
HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 59 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-135/1293-RB5-
HB-801
System/Equipment Description:. Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 60 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-136A/1293-RB5-
HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Have the filter been installed- if applicable (Yes/No)?
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 61 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-136B/1293-RB5-
HB-801
System/Equipment Description:. Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Have the filter been installed- if applicable (Yes/No)?
Is nameplate and tag number in place? (Yes/No)
Is vessel stamped with code and pressure/temperature rating
(if applicable)? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 62 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-136C/1293-RB5-
HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 63 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-136D/1293-RB5-
HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 64 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-136E/1293-RB5-
HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 65 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-137A/1293-RB5-
HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Have the filter been installed- if applicable (Yes/No)?
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 66 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-137B/1293-RB5-
HB-801
System/Equipment Description:. Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Have the filter been installed- if applicable (Yes/No)?
Is nameplate and tag number in place? (Yes/No)
Is vessel stamped with code and pressure/temperature rating
(if applicable)? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 67 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-137C/1293-RB5-
HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 68 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-137D/1293-RB5-
HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 69 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-137E/1293-RB5-
HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 70 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-137AA/1293-
RB5-
HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Have the filter been installed- if applicable (Yes/No)?
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 71 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-137BA/1293-
RB5-
HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Have the filter been installed- if applicable (Yes/No)?
Is nameplate and tag number in place? (Yes/No)
Is vessel stamped with code and pressure/temperature rating
(if applicable)? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.6 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 72 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-137CA/1293-
RB5-
HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 73 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-138/1293-RB5-
HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 74 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-139A/1293-RB5-
HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 75 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-139B/1293-RB5-
HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Have the filter been installed- if applicable (Yes/No)?
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 76 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-139C/1293-RB5-
HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Have the filter been installed- if applicable (Yes/No)?
Is nameplate and tag number in place? (Yes/No)
Is vessel stamped with code and pressure/temperature rating
(if applicable)? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 77 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-139D/1293-RB5-
HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 78 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: HF-101-139E/1293-RB5-
HB-801
System/Equipment Description: Terminal HEPA Filter
Manufacturer: Camfill
Air Flow capacity(each)/Pressure Drop: 610 CFM/10-30 mm
WC
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and sealed in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Filter frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Has all protective packing been removed? (Yes/No)
Is nameplate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 79 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: FCD-101-01 /
1293-RB5-HB-801
System/Equipment Description: Flow Control Damper
Manufacturer: Ravistar/Trox
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 80 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: FCD-101-02 /
1293-RB5-HB-801
System/Equipment Description: Flow Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 81 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: FCD-101-03 /
1293-RB5-HB-801
System/Equipment Description: Flow Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 82 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: FCD-101-04 /
1293-RB5-HB-801
System/Equipment Description: Flow Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 83 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: FCD-101-05 /
1293-RB5-HB-801
System/Equipment Description: Flow Control Damper
Manufacturer: Ravistar/Trox
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 84 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: FCD-101-06 /
1293-RB5-HB-801
System/Equipment Description: Flow Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 85 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: FCD-101-07 /
1293-RB5-HB-801
System/Equipment Description: Flow Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 86 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: FCD-101-08 /
1293-RB5-HB-801
System/Equipment Description: Flow Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 87 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: FCD-101-09 /
1293-RB5-HB-801
System/Equipment Description: Flow Control Damper
Manufacturer: Ravistar/Trox
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 88 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: FCD-101-10 /
1293-RB5-HB-801
System/Equipment Description: Flow Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 89 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: FCD-101-11 /
1293-RB5-HB-801
System/Equipment Description: Flow Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 90 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: FCD-101-12 /
1293-RB5-HB-801
System/Equipment Description: Flow Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 91 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: FCD-101-13 /
1293-RB5-HB-801
System/Equipment Description: Flow Control Damper
Manufacturer: Ravistar/Trox
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 92 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: FCD-101-14 /
1293-RB5-HB-801
System/Equipment Description: Flow Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 93 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: FCD-101-15 /
1293-RB5-HB-801
System/Equipment Description: Flow Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 94 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: FCD-101-16 /
1293-RB5-HB-801
System/Equipment Description: Flow Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 95 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: FCD-101-17 /
1293-RB5-HB-801
System/Equipment Description: Flow Control Damper
Manufacturer: Ravistar/Trox
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 96 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: FCD-101-18 /
1293-RB5-HB-801
System/Equipment Description: Flow Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 97 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: FCD-101-19 /
1293-RB5-HB-801
System/Equipment Description: Flow Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 98 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: FCD-101-20 /
1293-RB5-HB-801
System/Equipment Description: Flow Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 99 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: FCD-101-21 /
1293-RB5-HB-801
System/Equipment Description: Flow Control Damper
Manufacturer: Ravistar/Trox
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 100 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: FCD-101-22 /
1293-RB5-HB-801
System/Equipment Description: Flow Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 101 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: FCD-101-23 /
1293-RB5-HB-801
System/Equipment Description: Flow Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 102 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: FCD-101-24 /
1293-RB5-HB-801
System/Equipment Description: Flow Control Damper
Manufacturer: Ravistar/Trox
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 103 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: FCD-101-25 /
1293-RB5-HB-801
System/Equipment Description: Flow Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 104 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: FCD-101-26 /
1293-RB5-HB-801
System/Equipment Description: Flow Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 105 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: FCD-101-27 /
1293-RB5-HB-801
System/Equipment Description: Flow Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Adequate access to equipment is provided for service and
adjustments (Yes/No).
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 106 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: FCD-101-28 /
1293-RB5-HB-801
System/Equipment Description: Flow Control Damper
Manufacturer: Ravistar/Trox
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 107 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: FCD-101-29 /
1293-RB5-HB-801
System/Equipment Description: Flow Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 108 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: FCD-101-30 /
1293-RB5-HB-801
System/Equipment Description: Flow Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 109 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: ACD-101-01 /
1293-RB5-HB-801
System/Equipment Description: Air Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 110 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: PCD-101-01 /
1293-RB5-HB-801
System/Equipment Description: Pressure Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 111 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: PCD-101-02 /
1293-RB5-HB-801
System/Equipment Description: Pressure Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 112 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: PCD-101-03 /
1293-RB5-HB-801
System/Equipment Description: Pressure Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 113 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: PCD-101-04 /
1293-RB5-HB-801
System/Equipment Description: Pressure Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 114 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: PCD-101-05 /
1293-RB5-HB-801
System/Equipment Description: Pressure Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 115 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: PCD-101-06/
1293-RB5-HB-801
System/Equipment Description: Pressure Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 116 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: PCD-101-07 /
1293-RB5-HB-801
System/Equipment Description: Pressure Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 117 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: PCD-101-08 /
1293-RB5-HB-801
System/Equipment Description: Pressure Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 118 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: PCD-101-09 /
1293-RB5-HB-801
System/Equipment Description: Pressure Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 119 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: PCD-101-10 /
1293-RB5-HB-801
System/Equipment Description: Pressure Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 120 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: PCD-101-11 /
1293-RB5-HB-801
System/Equipment Description: Pressure Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 121 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: PCD-101-12 /
1293-RB5-HB-801
System/Equipment Description: Pressure Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 122 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: PCD-101-13 /
1293-RB5-HB-801
System/Equipment Description: Pressure Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 123 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: PCD-101-14 /
1293-RB5-HB-801
System/Equipment Description: Pressure Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 124 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: PCD-101-15/
1293-RB5-HB-801
System/Equipment Description: Pressure Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 125 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: PCD-101-16 /
1293-RB5-HB-801
System/Equipment Description: Pressure Control Damper
Manufacturer: Ravistar
Air Flow capacity (each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 126 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: PCD-101-17 /
1293-RB5-HB-801
System/Equipment Description: Pressure Control Damper
Manufacturer: Ravistar
Air Flow capacity (each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 127 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: PCD-101-18 /
1293-RB5-HB-801
System/Equipment Description: Pressure Control Damper
Manufacturer: Ravistar
Air Flow capacity (each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 128 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: PCD-101-19 /
1293-RB5-HB-801
System/Equipment Description: Pressure Control Damper
Manufacturer: Ravistar
Air Flow capacity (each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 129 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: PCD-101-20 /
1293-RB5-HB-801
System/Equipment Description: Pressure Control Damper
Manufacturer: Ravistar
Air Flow capacity (each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 130 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: PCD-101-21 /
1293-RB5-HB-801
System/Equipment Description: Pressure Control Damper
Manufacturer: Ravistar
Air Flow capacity (each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 131 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: PCD-101-22 /
1293-RB5-HB-801
System/Equipment Description: Pressure Control Damper
Manufacturer: Ravistar
Air Flow capacity (each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 132 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: PCD-101-23 /
1293-RB5-HB-801
System/Equipment Description: Pressure Control Damper
Manufacturer: Ravistar
Air Flow capacity (each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 133 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: PCD-101-24/
1293-RB5-HB-801
System/Equipment Description: Pressure Control Damper
Manufacturer: Ravistar
Air Flow capacity (each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 134 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: PCD-101-25 /
1293-RB5-HB-801
System/Equipment Description: Pressure Control Damper
Manufacturer: Ravistar
Air Flow capacity (each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 135 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: PCD-101-26 /
1293-RB5-HB-801
System/Equipment Description: Pressure Control Damper
Manufacturer: Ravistar
Air Flow capacity (each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 136 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: PCD-101-27 /
1293-RB5-HB-801
System/Equipment Description: Pressure Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 137 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: PCD-101-28 /
1293-RB5-HB-801
System/Equipment Description: Pressure Control Damper
Manufacturer: Ravistar
Air Flow capacity(each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 138 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: PCD-101-29 /
1293-RB5-HB-801
System/Equipment Description: Pressure Control Damper
Manufacturer: Ravistar
Air Flow capacity (each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings, and
other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:

4.1 Equipment Receipt and Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 139 of 195

Verified
Item Results
By/Date
Tag #/P&ID Number: PCD-101-30 /
1293-RB5-HB-801
System/Equipment Description: Pressure Control Damper
Manufacturer: Ravistar
Air Flow capacity (each)/Pressure Drop:
Equipment shows no sign of physical damage (Yes/No).
Is the system/equipment installed, supported and leveled in
accordance with project drawings? (Yes/No)
Is the equipment installed and provided with all accessories
(Gasket, frame, etc. as applicable) in accordance with
drawings? (Yes/No)
Is name plate and tag number in place? (Yes/No)
Equipment is clean and clear of all hazardous and/or
obstructive materials (Yes/No).
Does the equipment conform to specifications, drawings,
and other vendor documentation- (Yes/No)

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 140 of 195

4.2 Control Devices- Receipt, Installation, Calibration, & Loop Check Verification
Calibration/Full CAL/ Full ID Tag in
Calibration Verified
Tag # Description Manufacturer Model # Loop Check Data Loop Check Place
Due Date I By/Date
in TOP (Yes/No) Date (Yes/No)
FMS-101-01 Flow (Mass) Sensor Trox TVM-400 X 100
FMS-101-02 Flow (Mass) Sensor Trox TVM-300 X 300
FMS-101-03 Flow (Mass) Sensor Trox TVM-700 X 400
FMS-101-04 Flow (Mass) Sensor Trox TVM-300 X 300
FMS-101-05 Flow (Mass) Sensor Trox TVM-300 X 100
FMS-101-06 Flow (Mass) Sensor Trox TVM-400 X 100
FMS-101-07 Flow (Mass) Sensor Trox TVM-300 X 200
FMS-101-08 Flow (Mass) Sensor Trox TVM-300 X 200
FMS-101-09 Flow (Mass) Sensor Trox TVM-700 X 400

FMS-101-10 Flow (Mass) Sensor Trox TVM-500 X 400

FMS-101-11 Flow (Mass) Sensor Trox TVM-300 X 300


FMS-101-12 Flow (Mass) Sensor Trox TVM-300 X 200
FMS-101-13 Flow (Mass) Sensor Trox
FMS-101-14 Flow (Mass) Sensor Trox
FMS-101-15 Flow (Mass) Sensor Trox

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 141 of 195

4.2. Control Devices- Receipt, Installation, Calibration, & Loop Check Verification (Continued) .
Calibration/Full CAL/ Full ID Tag in
Calibration Verified
Tag # Description Manufacturer Model # Loop Check Data Loop Check Place
Due Date I By/Date
in TOP (Yes/No) Date (Yes/No)
FMS-101-16 Flow (Mass) Sensor Trox TVM-400 X 100
FMS-101-17 Flow (Mass) Sensor Trox TVM-300 X 300
FMS-101-18 Flow (Mass) Sensor Trox TVM-700 X 400
FMS-101-19 Flow (Mass) Sensor Trox TVM-300 X 300
FMS-101-20 Flow (Mass) Sensor Trox TVM-300 X 100
FMS-101-21 Flow (Mass) Sensor Trox TVM-400 X 100
FMS-101-22 Flow (Mass) Sensor Trox TVM-300 X 200
FMS-101-23 Flow (Mass) Sensor Trox TVM-300 X 200
FMS-101-24 Flow (Mass) Sensor Trox TVM-700 X 400

FMS-101-25 Flow (Mass) Sensor Trox TVM-500 X 400

FMS-101-26 Flow (Mass) Sensor Trox TVM-300 X 300


FMS-101-27 Flow (Mass) Sensor Trox TVM-300 X 200
FMS-101-28 Flow sensor Trox
FMS-101-29 Flow sensor Trox
FMS-101-30 Flow sensor Trox

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 142 of 195

4.2 Control Devices- Receipt, Installation, Calibration, & Loop Check Verification (continued)
Calibration/Full Calibration Due
CAL/ Full Loop ID Tag in Place
Tag # Description Manufacturer Model # Loop Check Data in Date Indicated on Verified By/Date
Check Date (Yes/No)
TOP (Yes/No) Tag (Yes/No)
FS-101-01 Flow sensor

FS-101-02 Flow sensor

FS-101-03 Flow sensor


Pressure Differential
PDI-101-01
Indicator
Pressure Differential
PDI-101-02
Indicator
Humidity Sensor/
MT-101-01
Transmitter
Temperature Sensor/
TT-101-01
Transmitter
Temperature Sensor/
TT-101-02
Transmitter
Temperature Sensor/
TT-101-03
Transmitter
Temperature Sensor/
TT-101-04
Transmitter
Temperature Sensor/
TT-101-05
Transmitter

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 143 of 195

4.3 Electrical Cable and Conduit Installation Check Sheet

This datasheet is completed to verify and document that all conduit and wiring has been installed as per
project specifications.

Results Verified By/Date


Activity
Yes/No

Has all conduit and wiring been installed as per


specifications/drawings?

Are all the termination points, panels, circuit breakers, cables, and
switches properly labeled?

Are all the floor and wall penetrations properly sealed?

Are the conduit seals properly installed?

Have all conduit covers been properly installed?

Is all temporary grounding removed and permanent grounding


properly installed?

Results Acceptable?

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 144 of 195

4.4 GSS Ducting and Insulation Installation Verification

This datasheet is completed to verify and document that all ducting insulation has been installed as per
project specifications.

Results Verified By/Date


Activity
(Yes/No)
HVAC Plan Drawing Number(s): 1293-RB5-HE-826

Ducting Specifications/Descriptions: Refer : 1293/ HVAC- SOQ/


X1
Manufacturer: GSS Sheets: Jindal/Tata
Duct Pressure/Insulation thickness: Supply air ducts:1500
Pa,Return air ducts:750 Pa.In false ceiling area:38 mm,In
interstitial and external area:50mm thick
All installed Ducting and Insulation materials are as per Ducting
specifications? (Yes/No)
Ducting and Insulation are installed in accordance with project
drawings? (Yes/No)
Manual Flow Control dampers cycle smoothly between
Open/Closed positions? (Yes/No)
Ducting is labeled with service and direction of flow?
The Ducting system has access and inspection doors installed as
per drawings?
Flows, Pressure, Smoke dampers, Filters Reheat coils etc. are
installed in accordance with project drawings? (Yes/No)
Insulation installed as per project specifications?
Duct supports are installed as per project specification and/or
drawings?
Test#_______

All Ducting has been pressure tested/Leak tested (where SOP#s


applicable), cleaned? ________________
(Yes/No)
________________
Record Test, and all applicable Procedure Numbers
(SOPs): ________________
________________

Results Acceptable? (Yes/No)

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 145 of 195

4.4 GSS Ducting and Insulation Installation Verification (continued).

This datasheet is completed to verify and document that all GSS Ducting & Insulation has been installed
as per project specifications.

Results Verified
Activity By/Date
(Yes/No)
HVAC Plan Drawing Number(s):
1293-RB5-HE-826

Ducting Specifications/Descriptions: Refer: 1293/ HVAC- SOQ/ X1


Manufacturer: GSS Sheets: Jindal/Tata
Duct Pressure/Insulation thickness: Supply air ducts: 1500 Pa, Return
air ducts: 750 Pa.In false ceiling area: 38 mm, In interstitial and
external area: 50mm thick.
All installed Ducting and Insulation materials are as per Ducting
specifications? (Yes/No)
Ducting and Insulation are installed in accordance with project
drawings? (Yes/No)
Manual Flow Control dampers cycle smoothly between Open/Closed
positions? (Yes/No)
Ducting is labeled with service and direction of flow?
The Ducting system has access and inspection doors installed as per
drawings?
Flows, Pressure, Smoke dampers, Filters Reheat coils etc. are
installed in accordance with project drawings? (Yes/No)
Insulation installed as per project specifications?
Duct supports are installed as per project specification and/or
drawings?
Test#_______

All Ducting has been pressure tested/Leak tested (where applicable), SOP#s
cleaned? ________________
(Yes/No)
________________
Record Test, and all applicable Procedure Numbers
(SOPs): ________________
________________

Results Acceptable? (Yes/No)

Comments

Reviewed By: Date:

4.5 Piping & and Insulation Installation Verification


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 146 of 195

This datasheet is completed to verify and document that all piping wiring has been installed as per project
specifications.

Results Verified By/Date


Activity
(Yes/No)
P&ID Number(s):, 1293-RB5-HE-808
Piping & Insulation Specifications/Descriptions: Refer
specificationNo. 1293– 2800 – X02

All installed piping materials are as per piping specifications?


(Yes/No)
Piping and valves are installed in accordance with project
drawings? (Yes/No)
Manual valves cycle smoothly between Open/Closed
positions? (Yes/No)
Piping is labeled with service and direction of flow ?
The piping system has high point vents installed as per piping
drawings?
The piping system has low point drains installed as per piping
drawings?
Gaskets installed as per project specifications?
Slope verification was performed and complies with drawings?
Pipe supports are installed as per project specification and/or
drawings?
Fluid#_______

All piping has been pressure tested, cleaned, flushed & SOP#s
drained? ________________
(Yes/No)
________________
Record Fluid, and all applicable Procedure Numbers
(SOPs): ________________
________________

Results Acceptable? (Yes/No)

Comments

Reviewed By: Date:

4.6. Chilled Water Piping installation Verification


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 147 of 195

This datasheet is completed to verify and document that all piping and Insulation has been installed as
per project specifications.

Results Verified By/Date


Activity
(Yes/No)
P&ID Number(s): 1293-RB5-HA-
803
Piping & Insulation Specifications/Descriptions: Refer
specificationNo. 1293– 2800 – X02

All installed piping materials are as per piping specifications?


(Yes/No)
Piping and valves are installed in accordance with project
drawings? (Yes/No)
Manual valves cycle smoothly between Open/Closed positions?
(Yes/No)
Piping is labeled with service and direction of flow?
The piping system has high point vents installed as per piping
drawings?
The piping system has low point drains installed as per piping
drawings?
Gaskets installed as per project specifications?
Slope verification was performed and complies with drawings?
Pipe supports are installed as per project specification and/or
drawings?
Fluid#_______
SOP#s
_______________
All piping has been pressure tested, cleaned, flushed & drained? _
(Yes/No) _______________
Record Fluid, and all applicable Procedure Numbers _
(SOPs): _______________
_
_______________
_

Results Acceptable? (Yes/No)

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 148 of 195

4.7 Hot Water Piping Installation Verification

This datasheet is completed to verify and document that all piping and Insulation has been installed as
per project specifications.

Results Verified By/Date


Activity
(Yes/No)
P&ID Number(s): 1293-RBE-HE-
803
Piping & Insulation Specifications/Descriptions: Refer
specificationNo. 1293– 2800 – X02

All installed piping materials are as per piping specifications?


(Yes/No)
Piping and valves are installed in accordance with project
drawings? (Yes/No)
Manual valves cycle smoothly between Open/Closed positions?
(Yes/No)
Piping is labeled with service and direction of flow?
The piping system has high point vents installed as per piping
drawings?
The piping system has low point drains installed as per piping
drawings?
Gaskets installed as per project specifications?
Slope verification was performed and complies with drawings?
Pipe supports are installed as per project specification and/or
drawings?
Fluid#_______
SOP#s
_______________
All piping has been pressure tested, cleaned, flushed & drained? _
(Yes/No) _______________
Record Fluid, and all applicable Procedure Numbers _
(SOPs): _______________
_
_______________
_

Results Acceptable? (Yes/No)

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 149 of 195

4.8 Drawing and Assembly Inspection

The purpose of this inspection is to verify that all components are in accordance with the General
Arrangement Drawings with respect to connections, line sizes, orientation and overall dimensions.

Test Procedure
 Inspect drawings to ensure they accurately reflect the as-built equipment. If any changes are
noted, drawings are to be redlined by the inspector and transferred to the project manager or
engineering lead.
 Visually inspect the system as described below
Results Meet
Acceptance Verified
Check Description Acceptance Criteria
Criteria By/Date
(Yes/No)
General Record applicable GA Drawing
Arrangement Numbers:____________________________
(GA) Drawing #s ________________________________

General Actual layout and line terminations conform to


Arrangement the GA.
General Overall dimensions conform to the GA.
Arrangement

General Component tags are identified correctly.


Arrangement

Support All lines and components are adequately


supported with appropriate hangers.
Visual Check Finishing are visually aesthetic, line routing
and ducting/piping is tidy and surfaces are
free of debris.
Clearance There is sufficient clearance for accessibility
and maintenance.

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 150 of 195

4.9 Safety Check

This datasheet is completed to ensure that the system is in a safe condition to apply utilities.

Results
Safety Requirements Verified By/Date
(Yes/No)

Process connections are complete and connectors are tight.

Electrical connections are complete and all wires are


terminated.

Safety devices are installed, where applicable.

Regulators are in place and set at correct settings (based on


the P&ID and HVAC Drawings)

Interlocking of Door/Fan motor working correctly

Exhaust and drain lines are routed to a safe area.

Hot Water supply is safely piped and attached with Re Heat


Coil connectors.

E-Stop system is working correctly.

System Passes Safety Check

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 151 of 195

4.10 Lock Out Tag out Check Sheet

This datasheet is completed to verify that all verify each piece of equipment can be isolated per the RLS
Lock-out/Tag-out Procedures. This is a safety check, to ensure that equipment can be locked out from
operation during maintenance, inspection, and equipment check out.

Manufacturer/ Lockout/ Verified


Equipment
Model No. for Tagout Isolation
Tag No. Dwg Verified
Description Voltage Lock-out/ Properly Per
(Vendor No. By/Date
Tag-out Installed Procedures
Ref.#)
Device Yes/ No Yes/ No
SF-101- Motor, 415 V, Pad lock
01 Fan TEFC, IP- 3 SHAH
motor 55 phase R.No. 340718
RF-101- Pad lock
Motor, 415 V,
01 SHAH
TEFC, IP- 3
Return 55 R.No. 340718
phase
Fan
EF-101- Pad lock
01 Motor, 415 V,
TEFC, IP- 3 SHAH
Exhaust 55 phase R.No. 340718
Fan
EF-101- Pad lock
02 Motor, 415 V,
TEFC, IP- 3 SHAH
Exhaust 55 phase R.No. 340718
Fan
EF-101- Pad lock
03 Motor, 415 V,
TEFC, IP- 3 SHAH
Exhaust 55 phase R.No. 340718
Fan

Comments

Reviewed By: Date:

4.11 Rotating Equipment Installation Verification


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 152 of 195

This datasheet is completed to verify that all rotating equipment has been installed as per project
procedure and specifications.

Complete one datasheet for each item

Equipment Tag: SF-101-01: Supply Air Fan

Results Verified By/Date


Activity
Yes/No

Have all conduit and wiring been installed per specification?


Are all the termination points, panels, circuit breakers, cables,
and switches properly labeled per Project specifications?
Does Local Disconnect Switch exist?

Has the equipment been properly lubricated?

Is the direction of rotation correct?


Have all guard covers been properly installed per Project
specifications?
Is the equipment properly and if applicable vibration dampers
installed?
If applicable has the equipment been properly balanced?
Is all temporary grounding removed and permanent grounding
properly installed per project specifications?

Comments

Reviewed By: Date:

4.11 Rotating Equipment Installation Verification (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 153 of 195

This datasheet is completed to verify that all rotating equipment has been installed as per project
procedures and specifications.

Complete one datasheet for each item

Equipment Tag: RF-101-01: Return Air Fan

Results Verified By/Date


Activity
Yes/No

Have all conduit and wiring been installed per specification?


Are all the termination points, panels, circuit breakers, cables, and
switches properly labeled per Project specifications?
Does Local Disconnect Switch exist?

Has the equipment been properly lubricated?

Is the direction of rotation correct?


Have all guard covers been properly installed per Project
specifications?
Is the equipment properly and if applicable vibration dampers
installed?
If applicable has the equipment been properly balanced?
Is all temporary grounding removed and permanent grounding
properly installed per project specifications?

Comments

Reviewed By: Date:

4.11 Rotating Equipment Installation Verification (continued).


This datasheet is completed to verify that all rotating equipment has been installed as per project
procedures and specifications.
Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 154 of 195

Complete one datasheet for each item

Equipment Tag: EF-101-01: Exhaust Air Fan

Results Verified By/Date


Activity
Yes/No

Have all conduit and wiring been installed per specification?


Are all the termination points, panels, circuit breakers, cables,
and switches properly labeled per Project specifications?
Does Local Disconnect Switch exist?

Has the equipment been properly lubricated?

Is the direction of rotation correct?


Have all guard covers been properly installed per Project
specifications?
Is the equipment properly and if applicable vibration dampers
installed?
If applicable has the equipment been properly balanced?
Is all temporary grounding removed and permanent grounding
properly installed per project specifications?

Comments

Reviewed By: Date:

4.11 Rotating Equipment Installation Verification (continued).


This datasheet is completed to verify that all rotating equipment has been installed as per project
procedures and specifications.

Complete one datasheet for each item

Equipment Tag: EF-101-02: Exhaust Air Fan


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 155 of 195

Results Verified By/Date


Activity
Yes/No

Have all conduit and wiring been installed per specification?


Are all the termination points, panels, circuit breakers, cables,
and switches properly labeled per Project specifications?
Does Local Disconnect Switch exist?

Has the equipment been properly lubricated?

Is the direction of rotation correct?


Have all guard covers been properly installed per Project
specifications?
Is the equipment properly and if applicable vibration dampers
installed?
If applicable has the equipment been properly balanced?
Is all temporary grounding removed and permanent grounding
properly installed per project specifications?

Comments

Reviewed By: Date:

4.11 Rotating Equipment Installation Verification (continued).


This datasheet is completed to verify that all rotating equipment has been installed as per project
procedures and specifications.

Complete one datasheet for each item

Equipment Tag: EF-101-03: Exhaust Air Fan


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 156 of 195

Results Verified By/Date


Activity
Yes/No

Have all conduit and wiring been installed per specification?


Are all the termination points, panels, circuit breakers, cables, and
switches properly labeled per Project specifications?
Does Local Disconnect Switch exist?

Has the equipment been properly lubricated?

Is the direction of rotation correct?


Have all guard covers been properly installed per Project
specifications?
Is the equipment properly and if applicable vibration dampers
installed?
If applicable has the equipment been properly balanced?
Is all temporary grounding removed and permanent grounding
properly installed per project specifications?

Comments

Reviewed By: Date:

4.12 Red Lined As Built P&ID

This datasheet is completed to document as built condition of the system.

Procedure:

 Obtain the latest copy of the red lined HVAC drawings and Piping & instrument (P&ID) from
the commissioning document or turnover package
 Indicated the HVAC drawing and P&ID Name/Number/Revision in the table below
Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 157 of 195

 Compare the HVAC Drawings and P&ID with the actual system. Walk down the entire HVAC
drawings and P&ID
 Annotate drawing details that are correct with a yellow highlighter, and note any
discrepancies in red. Focus upon only those sections of the drawing that are within the
scope of this CTP.
 Annotate the verified drawings “As-Built”, sign, date, and attach a copy to this completed
CTP.

Copy of Annotated
HVAC drawings
HVAC drawings and P&ID HVAC and P&ID
and P&ID Inspected By / Date
Name/Number Attached to CTP
Revision/Date
(Yes/No)
1293-RB5-HE-801 Rev-2 / 03.04.06

1293-RB5-HE-825 Rev-2 / 05.04.06

1293-RB5-HE-826 Rev-2 / 07.04.06

1293-RB5-HE-830 Rev-3 / 07.04.06

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 158 of 195

5 Regulation, Adjustment, and Setting to Work Phase


5.1 Factory Acceptance Test (FAT) Review

This Check Sheet is completed to verify that the FAT has been completed (where applicable) with punch
list items documented, resolved, or addressed as part of Site Acceptance Test (SAT).

Obtain a copy of the FAT from the Turnover Package (TOP) and complete the table below.

Results
FAT Item Verified By/Date
(Yes/No)

Was the FAT Procedure reviewed and approved by RLS or


designated personnel prior to execution.
Was the final FAT procedure executed? Rev.:_______
Record Revision/Date of FAT document Date:_______
Did RLS Personnel or a designated representative (vendor,
subcontractor) complete all the items in the FAT?
If no, record any items not completed in the “Comments”
section below.
Was leveraged testing (i.e.- testing that will not be repeated at
the site) for cGMP critical items documented as per cGMP
documentation practices?
Was a punch list generated at the completion of testing to
document any items that did not meet acceptance criteria?

Were all vendor and FAT Punch List Items properly closed?

Were the open Punch List Items transferred to the


Construction/Commissioning Punch List?

Is the completed FAT acceptable to the RLS project Team?

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 159 of 195

5.2 Utility Availability Check Sheet and Log


This datasheet is completed to verify that all utility supply and return services for each are
activated/energized.

5.2.1 Electrical:  
Parameter
Design Actual Checked By/Date Verified By/ Date

Voltage 415  10%


Frequency
50  3%
Phase
3

5.2.2 Chilled Water:


Parameter Design Actual Checked By/Date Verified By/ Date
Cooling Coil-1Inlet
7.70C
Temperature
Cooling Coil-1Outlet
16.11.0C
Temperature
Cooling coil Inlet Pressure
Cooling Coil-1 Outlet
Pressure
Cooling Coil-2 Inlet
5.50C
Temperature
Cooling Coil-2 Outlet
10.550C
Temperature
Cooling Coil-2 Inlet
Pressure
Cooling Coil-2 Outlet
Pressure

5.2.3 Hot Water:


Checked
Parameter Design Actual Verified By/ Date
By/Date
Inlet Temperature 82.2oC

Outlet Temperature 71.1oC


Inlet Pressure

Outlet Pressure

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 160 of 195

5.3 Site Acceptance Testing (SAT) Review

This datasheet is completed to verify that the SAT has been completed (where applicable), with punch list
items documented, resolved, or addressed by RLS or an RLS designee as acceptable.

Obtain a copy of the SAT, and from the Turnover Package (TOP) and complete the table below.

Results Verified
SAT Item
(Yes/No) By/Date

Was the SAT Procedure reviewed and approved by RLS or


designated personnel prior to execution?
Was the final SAT procedure executed? If yes, record Rev:___________
revision/date of SAT document. Date:__________
Did RLS Personnel or a designated representative (vendor,
subcontractor) complete all the items in the SAT?
If no, record any items not completed in the “comments” section
below.
Was leveraged testing (i.e. - testing that will not be repeated as
part of IOQ) for cGMP critical items documented as per cGMP
documentation practices?
Was a punch list generated at the completion of testing to
document any items that did not meet acceptance criteria?

Were all SAT Punch List Items properly closed?

Were the Open punch List Items transferred to the


Construction/Commissioning Punch List?

Is the completed SAT acceptable o the RLS Project Team?

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 161 of 195

5.4 Alarm and Interlock Testing


The purpose of this test section is to verify that all the alarms and Interlocks are operating AS
SPECIFIED

All alarms and interlocks are tested during the FAT and SAT.

Note: All alarms/interlocks associated with this system are through the BMS . Testing of these is
included in the BMS validation and not included in this system CTP.
Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 162 of 195

6 System Functional Testing


6.1 AHU Operational Test

Test Procedure:
 Verify all the equipments, Gauges are calibrated and factory tested.
 Verify all Installation checks are completed, punch list attended and resolved.
 Check all safety checks done.
 Check on smooth, quite and vibration free operation of Fan motor
 Check current, rpm for Fan and motor
 Record Air quantity and flow rate of Chilled and Hot water.
 If readings are more/ less compared to Design parameter balance the air and water sides using
control devices like Dampers, Balancing Valves etc.

6.1.1 Operational test


Result
Verified
Test Description Acceptance Criteria Actual Acceptable
By/ Date
(Yes/No)

Record Fan motor current 60 Amps ± 20 Amps

Fan Operating/Maximum
Record Fan RPM
speed, 1434/1550 RPM

Supply air 19760,Return air


Record Supply, Return and
19760 and Fresh air
Fresh air Quantity
19760CFM

Record CHW-1 and CHW-


2 2 inlet water Flow.

Record Hot water


Inlet/outlet Flow rate &
Temperature

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 163 of 195

6.2 VFD Operation Testing

This test verify the VFD and static pressure sensor (PT/PE) is operating as specified and
controlling the speed of supply fan (PY) to meet desired discharge static pressure.

Procedure

Run AHU at full/half and partial speed by adjusting set points


Measure and record actual fan RMP with tachometer
Measure and record discharge static pressure at outlet of the fan
Set values to meet specified discharge pressure

Measured speed is found to meet acceptance criteria if the pressure is within the tolerance of the set
point specified in the table

Measured Acceptance
Measur Acceptance Verified by /
Setting rpm static criteria met
ed rpm Criteria date
pressure yes/no
O

800 RPM ± 50

1000 RPM ± 50

800 RPM ±50

800 RPM ± 50

Acceptance criteria

The measured speed is found to meet acceptance criteria if the pressure is within
the tolerance of the set point specified in the table

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 164 of 195

6.3 HEPA Filter Testing

6.3.1. Air Velocity and Uniformity Test.

These test procedures are performed to determine average airflow velocity and uniformity within a clean
room, clean zone or unidirectional flow work zone, as well as to determine air supply volume flow rate
and volume uniformity.

Pre-Requisites / Reference Documentation


 Air flow velocity: electronic micro manometer with tube array, thermal anemometer, vane
type anemometer or equivalent.
 Air flow volume: electronic macro manometer with appropriate airflow hood or equivalent.
 Suitable support stands where necessary.

Pre-test criteria:
 The filter should be completely installed and sealed properly.
 AHU system should be in running condition
 Air flow through the filter to be adjusted and balanced.

Testing Procedure

This test is performed to determine the average airflow velocity uniformity range within unidirectional/non
unidirectional clean rooms.

 Divide the effective HEPA filter face area into equal grids not greater than one square
foot starting six inches in from the inner edge of the filter frame.
 Measurement should be taken at the center of each grid cell.
 Measuring time at each position should be at least 5 seconds duration.
 The minimum, maximum and average values should be recorded.
 Air Volume is then calculated (CFM) by multiplying the effective filter area by the average
velocity

(Effective filter area) ft2 x (Average filter velocity) FPM = (Volume) (CFM)
Note: Air changes can be calculated by Velocity (FPM) x filter area (FT 2) x 60 divided
room volume.
Air changes = FPM x FT2(Filter area) x 60
FT3 (Room Volume)
Acceptance Criteria and Test Results
.
 The average airflow velocity, or the average total airflow volume, for the clean room or
clean zone should be within ±5% of the value specified for the clean room or clean zone,
or within other tolerance limits agreed upon by the buyer and the seller.
 For Class 100 areas, airflow rate of minimum of 240 air changes per hour.
 For Class 10,000 areas, airflow rate of minimum of 50 air changes per hour.
 For Class 100,000 areas, airflow rate of minimum of 25 air changes per hour.

Comments

Reviewed By: Date:


6.3.1. AIR VELOCITY AND UNIFORMITY TEST (CONTINUED)
Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 165 of 195

Obtained Acceptance
HEPA Designed Total Air Verified
Average Acceptance Criteria
Filter Tag Velocity Volume changes by/
Velocity in Criteria achieved
No. in fpm in cfm per hour date
fpm Yes/No

HF-101-
115
HF-101-
116A
HF-101-
116B
HF-101-
116C
HF-101-
116D
HF-101-
116E
HF-101-
117
HF-101-
118
HF-101-
118AA
HF-101-
119
HF-101-
120
HF-101-
121A
HF-101-
121B
HF-101-
121C
HF-101-
121D

Comments

Reviewed By: Date:


6.3.1. AIR VELOCITY AND UNIFORMITY TEST (CONTINUED)
Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 166 of 195

Obtained Acceptance
HEPA Designed Total Air Verified
Average Acceptance Criteria
Filter Tag Velocity Volume changes by/
Velocity in Criteria achieved
No. in fpm in cfm per hour date
fpm Yes/No

HF-101-
121E
HF-101-
122
HF-
101123
HF-101-
123AA
HF-101-
124
HF-101-
125
HF-101-
126
HF-101-
127
HF-101-
128
HF-101-
129
HF-101-
130A
HF-101-
130B
HF-101-
130C
HF-101-
130D
HF-101-
130E

Comments

Reviewed By: Date:

6.3.1. AIR VELOCITY AND UNIFORMITY TEST (CONTINUED)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 167 of 195

Obtained Acceptance
HEPA Designed Total Air Verified
Average Acceptance Criteria
Filter Velocity Volume changes by/
Velocity in Criteria achieved
Tag No. in fpm in cfm per hour date
fpm Yes/No

HF-101-
131
HF-101-
132
HF-101-
133
HF-101-
134
HF-101-
135
HF-101-
136A
HF-101-
136B
HF-101-
136C
HF-101-
136D
HF-101-
136E
HF-101-
137A
HF-101-
137B
HF-101-
137C
HF-101-
137D
HF-101-
137E

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 168 of 195

6.3.2. HEPA filter Integrity Test


To confirm that The HEPA Filter System is properly installed by verifying the absence of bypass leakage
in installation and that filters are free from small leaks and defects.

Pre-Requisites / Reference Documentation


 Aerosol Photometer duly calibrated.
 DOP Generator.
Leak Test Procedure
Pre-test criteria:
 The filter should be completely installed and sealed properly.
 AHU system should be in running condition
 Air flow through the filter to be adjusted and balanced.
Testing Procedure
This test is performed by introducing the specified challenge aerosol upstream of the filters and
searching for leaks by scanning the downstream side of the filters with the photometer probe.
The design airflow velocity should be established and uniformity confirmed according to section 1
prior to performing this test.
The air-generated aerosol challenge and aerosol photometer filter scan test should be performed
as follows:

 The filter must be completely installed and flow uniformity adjustment to be completed.
 An aerosol generated by blowing the compressed air through Di Octyl Phthalate
generator.
 Inject the aerosol at mixing chamber of the air handling unit.
 Place the aerosol generator in an accessible position, and adjust the aerosol
concentration between 10 to 20 microgram per liter. The set compressed air supply
pressure to DOP generator should be 44-PSI minimum.
 The photometer has the sample flow rate of 1 cfm, The probe is held at a distance of 6
inch and at a traverse rate of 3m/ min
 The filter face and perimeter is scanned by passing the probe covering the complete
area so that the entire area of the filter and sealing gasket is sampled
 Scan the filter thoroughly to determine the leakage produced due to DOP sensing during
the test.

Acceptance Criteria and Test Results


.
 Record all leaks that exceed 0.01 % of the upstream challenge concentration or
penetration limit that be established by agreement between buyer and the seller.

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 169 of 195

6.3.2. HEPA Filter Leak Test (continued)


Acceptance Obtained Acceptance
HEPA Filter Upstream Criteria in result in Criteria Test
Verified by/
Tag No. Concentration Down Down achieved Result
date
in % stream % of stream in Yes/No Pass/Fail
Leakage %

HF-101-115
HF-101-
116A
HF-101-
116B
HF-101-
116C
HF-101-
116D
HF-101-
116E

HF-101-117

HF-101-118
HF-101-
118AA

HF-101-119

HF-101-120
HF-101-
121A
HF-101-
121B
HF-101-
121C
HF-101-
121D

Comments

Reviewed By: Date:

6.3.2. HEPA Filter Leak Test (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 170 of 195

Acceptance Obtained Acceptance


HEPA Filter Upstream Criteria in result in Criteria Test
Verified by/
Tag No. Concentration Down Down achieved Result
date
in % stream % of stream in Yes/No Pass/Fail
Leakage %
HF-101-
121E

HF-101-122

HF-101123
HF-101-
123AA

HF-101-124

HF-101-125

HF-101-126

HF-101-127

HF-101-128

HF-101-129
HF-101-
130A
HF-101-
130B
HF-101-
130C
HF-101-
130D
HF-101-
130E

Comments

Reviewed By: Date:

6.3.2. HEPA Filter Leak Test (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 171 of 195

Acceptance Obtained Acceptance


HEPA Filter Upstream Criteria in result in Criteria Test
Verified by/
Tag No. Concentration Down Down achieved Result
date
in % stream % of stream in Yes/No Pass/Fail
Leakage %

HF-101-131

HF-101-132

HF-101-133

HF-101-134

HF-101-135

HF-101-136A

HF-101-136B

HF-101-136C

HF-101-136D

HF-101-136E

HF-101-137A

HF-101-137B

HF-101-137C

HF-101-137D

HF-101-137E

Comments

Reviewed By: Date:

6.3.2. HEPA Filter Leak Test (continued)


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 172 of 195

Acceptance Obtained Acceptance


HEPA Filter Upstream Criteria in result in Criteria Test
Verified by/
Tag No. Concentration Down Down achieved Result
date
in % stream % of stream in Yes/No Pass/Fail
Leakage %
HF-101-
137AA
HF-101-
137BA
HF-101-
137CA

HF-101-138

HF-101-139A

HF-101-139B

HF-101-139C

HF-101-139D

HF-101-139E

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 173 of 195

6.3.3. Room Pressurization Test

The purpose of this test is to verify the capability of the cleanroom system to maintain the pressure
differential between the cleanroom and its surroundings.

Pre-Requisites / Reference Documentation


 This test should be performed after the facility has met the acceptance criteria for air flow
velocity or volume, airflow uniformity, parallelism and other applicable tests.
 Apparatus for the room pressurization test should consist of an electronic micro-
manometer, inclined manometer or mechanical pressure gauge.

Testing Procedure
With all doors closed, the procedure should be performed as follows:

 Measure and record the pressure differential between the clean room an anteroom (if
present), and between the anteroom and the external environment.
 If no anteroom is present, measure and record the pressure differential between the
cleanroom and the external environment.
 If the clean space is subdivided into more than one room, measure the pressure
differential between the innermost room and the next room in order. Continue until the
last room (or anteroom) has been measured against the external environment.

Acceptance Criteria and Test Results


.
 The pressure differential should meet the design specification with a range of  4 Pa

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 174 of 195

6.3.3. Room Pressurization Test (continued)


Differential
Difference Test
Pressure Verified
Room in Acceptance Result
compared by/ date
No/Name. Pressure criteria Pass/Fai
with Room
in Pa l
No./Name

L-115

L-116

L-117

L-118

L-118A

L-119

L-120

L-121

L-122

L-123

L-123A

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 175 of 195

6.3.3. Room Pressurization Test (continued)


Differential
Difference Test
Pressure Verified
Room in Acceptance Result
compared by/ date
No/Name. Pressure criteria Pass/Fai
with Room
in Pa l
No./Name

L-124

L-125

L-126

L-127

L-128

L-129

L-130

L-131

L-132

L-133

L-134

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 176 of 195

6.3.3. Room Pressurization Test (continued)


Differential
Difference Test
Pressure Verified
Room in Acceptance Result
compared by/ date
No/Name. Pressure criteria Pass/Fai
with Room
in Pa l
No./Name

L-135

L-136

L-137

L-137A

L-137B

L-137C

L-138

L-139

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 177 of 195

6.3.4. Airflow Parallelism Test

The purpose of this test is to verify the parallelism of airflow throughout the work zone and whether the
cleanroom is capable of limiting the dispersion of internally generated contamination.

Pre-Requisites / Reference Documentation


 This test is applicable for unidirectional air flow only.
 This test should be performed after the facility has met the acceptance criteria for air flow
velocity or volume, airflow uniformity and other applicable tests.
 An isokinetic smoke generator capable of supplying a smoke source at a specified
discharge speed is required.

Testing Procedure
 Divide the entrance and exit planes of the work zone into grids of equal area, having
dimensions of 3m x 3m (10 ft x 10 ft).The minimum distance between entrance and exit
planes should be 0.9m (3 ft).
 Set up the smoke generator with the outlet tube pointing in the direction of flow and
located at the center of the grid area at the work zone entrance plane. Smoke generation
should be performed outside of this grid area.
 Introduce smoke isokinetically and isothermally.
 Measure the offset distance between the theoretical straight-line flow point and the radial
direction of offset.

Acceptance Criteria and Test Results

 Readings must not exceed angle of 14 degrees.

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 178 of 195

6.3.4. Airflow Parallelism Test (continued)


Test
Room Location/Grid Measured Acceptance Verified
result
No./Name no. Offset angle criteria by/date
pass/fail

L-115

L-116

L-117

L-118

L-118A

L-119

L-120

L-121

L-122

L-123

L-123A

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 179 of 195

6.3.4. Airflow Parallelism Test (continued)


Test
Room Location/Grid Measured Acceptance Verified
result
No./Name no. Offset angle criteria by/date
pass/fail

L-124

L-125

L-126

L-127

L-128

L-129

L-130

L-131

L-132

L-133

L-134

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 180 of 195

6.3.4. Airflow Parallelism Test (continued)


Test
Room Location/Grid Measured Acceptance Verified
result
No./Name no. Offset angle criteria by/date
pass/fail

L-135

L-136

L-137

L-137A

L-137B

L-137C

L-138

L-139

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 181 of 195

6.3.5. Enclosure Induction Leak Test

This test is performed to determine if there is intrusion of unfiltered air into the clean work areas from
outside the cleanroom enclosure through joints, seams, and doorways.

Pre-Requisites / Reference Documentation


 Air – generated aerosol source or acceptable substitute.
 Discrete – particle counter having a particle size discrimination capability of 0.5 µm or
smaller.
 An isokinetic smoke generator capable of supplying a smoke source at a specified
discharge speed is required.

Testing Procedure
 Measure the particle concentration outside the cleanroom enclosure immediately
adjacent to the surface or doorway to be evaluated. This concentration should be at least
3.5 x 10 particles /m³. (If the concentration is less, generate an aerosol to increase the
concentration.
 To check for leakage through construction joints or cracks, scan at a distance of 5 to
10 cm (2to 4 inches) from the joint at a rate of approximately 3 m / min (10ft / min.).
 To check for intrusion at open doorways, measure the concentration inside the enclosure
at 0.3 to 3 m ( 1 to 10 ft) from the open door.

Acceptance Criteria and Test Results


.
 All the readings inside the enclosure must be less than 10 -3 times the measure external
concentration.

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 182 of 195

6.3.5. Enclosure Induction Leak Test (continued)


Compared Particle Particle
Room
Room concentration concentration Difference in Acceptance Test result Verified
No./Name
No./Name in Room (A) in Room (B) Concentration criteria Pass/Fail By/date
(A)
(B)

L-115

L-116

L-117

L-118

L-118A

L-119

L-120

L-121

L-122

L-123

L-123A

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 183 of 195

6.3.5. Enclosure Induction Leak Test (continued)


Compared Particle Particle
Room
Room concentration concentration Difference in Acceptance Test result Verified
No./Name
No./Name in Room (A) in Room (B) Concentration criteria Pass/Fail By/date
(A)
(B)

L-124

L-125

L-126

L-127

L-128

L-129

L-130

L-131

L-132

L-133

L-134

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 184 of 195

6.3.5. Enclosure Induction Leak Test (continued)


Compared Particle Particle
Room
Room concentration concentration Difference in Acceptance Test result Verified
No./Name
No./Name in Room (A) in Room (B) Concentration criteria Pass/Fail By/date
(A)
(B)

L-135

L-136

L-137

L-137A

L-137B

L-137C

L-138

L-139

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 185 of 195

6.3.6. Temperature Uniformity and Humidity Test

The purpose of this testing s to demonstrate the capability of the cleanroom air handling system to
maintain temperature and humidity level within the control limits over specified period of time.

Pre-Requisites / Reference Documentation


 Psychometer and temperature/humidity sensor.
 Ensure that the accuracy of the sensor is register.
 Each zone allowed operating minimum of 24 hours before testing is begun.

Testing Procedure
 Divide the area into equal grids approximately 10ft x 10ft .
 With one indicator at work height the center of one grid, temperature is measured in all
the other grids with the second sensor, each time reading both meters simultaneously.
 Two temperatures are recorded at each data point.

Acceptance Criteria and Test Results


.
 Temperature and humidity is throughout the area within the following range 22 o C ± 2 o C
 RH should be 40 to 50 %.

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 186 of 195

6.3.6. Temperature Uniformity and Humidity Test (continued).


Test
Room Location Recorded Recorded Acceptance Verified
Result
No./Name Ref No. Temperature RH in % Criteria by/date
Pass/Fail

L-115

L-116

L-117

L-118

L-118A

L-119

L-120

L-121

L-122

L-123

L-123A

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 187 of 195

6.3.6. Temperature Uniformity and Humidity Test (continued).


Test
Room Location Recorded Recorded Acceptance Verified
Result
No./Name Ref No. Temperature RH in % Criteria by/date
Pass/Fail

L-124

L-125

L-126

L-127

L-128

L-129

L-130

L-131

L-132

L-133

L-134

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 188 of 195

6.3.6. Temperature Uniformity and Humidity Test (continued).


Test
Room Location Recorded Recorded Acceptance Verified
Result
No./Name Ref No. Temperature RH in % Criteria by/date
Pass/Fail

L-135

L-136

L-137

L-137A

L-137B

L-137C

L-138

L-139

Comments

Reviewed By: Date:

7. Measurement and Test Equipment


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 189 of 195

Measurement and test equipment required to conduct commissioning are recorded in this datasheets.
Copies of appropriate calibration certification(s) will be included in the attachments to this test plan.

List the commissioning test equipment used for the execution of this test plan below. Indicate
manufacturer, model number, serial number, and calibration date. Attach a copy of each calibration
certificate.

Manufacturer/
Instrument Tag Serial Date Calibration Verified By /
Model
Description Number Number Calibrated Due Date Date
Number
Anemomete
r vane type
Hot wire
anemometer

Tacho meter

Clamp
Meter

Manometer

Photometer

Aerosol
Generator

Particle
Counter

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 190 of 195

8 Turnover Package Verification

Review the Turn over Package (TOP) Matrix for the system. Verify that all required documentation
associated with this system has been verified as present in the TOP.

Acceptance Criteria Results (Yes/No) Verified By/Date

All required documentation associated


with this system has been verified as
present in the TOP.

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 191 of 195

9 Commissioning Test Plan Acceptance Criteria Summary


This datasheet summarizes the results of the executed CTP and documents that all acceptance criteria
have been satisfied. Any outstanding punch list items are noted in the datasheet.

Results
Acceptance Criteria Acceptable Verified By/Date
(Yes/No)
All equipment, instruments, control devices, electrical
cable and conduit, and piping was installed as per
project specifications
All components of the system are in accordance with
general arrangement drawings.
Safety checks were completed and acceptance
criteria achieved.
Each piece of equipment can be isolated per RLS
Lock Out Tag Out Procedures
Rotating equipment has been installed as per project
procedures and specifications.
A red lined as built HVAC and P&ID(s) was
completed to document the as built condition of the
system. A copy is attached to the CTP and placed in
the TOP. Originals were submitted to engineering for
update.
All utility supply and return services are
activated/energized
HEPA testing verified and documented.
SAT was completed, punch list items documented,
and the SAT accepted by RLS or an RLS designee

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 192 of 195

9. Commissioning Test Plan Acceptance Criteria Summary (continued)


Results
Acceptance Criteria Acceptable Verified By/Date
(Yes/No)
All equipments, instruments/control devices function
as specified.
Functional run testing was completed, with the
results documented and acceptable.
The results in the CTP were documented as per
cGMP documentation practices for cGMP critical
items.
All test instruments are within calibration and all
calibration certificates for test instruments are
attached to this document.
The system turnover package is complete. The
turnover package will include vendor documents as
well as design, construction, and commissioning
documents.
All punch list items were documented. All items
were closed out or accepted by RLS as documented
in the punch list data sheets.

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 193 of 195

10 Punch List Log/Data Sheet


Page ___ of ___

List all punch list items in the table below. Note- for punch list item, a CTP Punch List Data Sheet must
be completed.
Resolv
Quality
Punch List ed Verified
Description Critical
Item # (Yes/N By/Date
(Yes/No)
o)

Comments

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 194 of 195

Page __of __
CTP Punch List Data Sheet

CTP Punch List Data Sheet- PART 1:


This form is to be used for any punch list items found during the execution of this document. A punch list
item is a failure to achieve the requirement indicated in the protocol document. The proposed corrective
action is indicated on the form, and project approval prior to close out of the item.

A separate form is to be used to address each punch list item.


Punch List No.: CTP No. Page No.:
Section No.:
CTP Requirements

Punch List Description

Quality Critical Punch List Item: (Yes/No)


Suggested Corrective Action:

Items Above Documented By/Date:


Punch List Resolution - PART 2:
Corrective Action Completion Date (Verified by/Date)
Retest (if Applicable) Result & Completion Date (Verified by/Date)

Comments

Completed By: Date:

Reviewed By: Date:


Reliance Life Sciences Pvt. Ltd.
cGMP2, DALC, Navi Mumbai

Document Title Commissioning Test Plan (CTP) – AIR HANDLING UNIT-101


Document No. CT/P2/UT/0009
Date 25 Jun 07 Revision No. 1.0 Page No. 195 of 195

Page ____of ____

11 Appendix

Attach all applicable data to the CTP. Itemize data using the following datasheet. Complete the table
noting the number of pages each appendix has. Where the attached pages are not numbered, annotate
these by hand.

Number Appendix Initials /


Appendix Description
of Pages Number Date

Comments

Reviewed By: Date: