Package-2: Rehabilitation of National Bridges Chakdara-Kalam (N-95) REVISED WORK SCHEDULE SH.

ABDUR RAZZAQ&CO(PVT)LTD
Lot # 2: Behrain - Kalam (Bridge Package) Km 106-134 (12 New Bridges) UPTO 15-07-2019 (18 Months)
ID Task Name Duration Start Finish
9 Mar '19 Apr '19 May '19 Jun '19 Jul '19
17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28
0 141 days? Mon 25/2/19 Mon 15/7/19 141 days?
Lot # 2: Behrain - KalamKm 106-134
(12 New Bridges)
1 141 days? Mon 25/2/19 Mon 15/7/19 25/2 15/7
CONSTRUCTION ACTIVITIES
2 STRUCTURES 123 days? Fri 1/3/19 Mon 1/7/19 1/3 1/7

3 Cast in Place concrete Piles dia 1m dia 90 days Fri 1/3/19 Wed 29/5/19 1/3 29/5
in gravel strata boring only
4 Reinforcement Steel Grade 60 100 days Fri 1/3/19 Sat 8/6/19 1/3 8/6

5 Concrete Class 'A3' Underground 90 days Fri 1/3/19 Wed 29/5/19 1/3 29/5

6 Concrete Class 'A1' on Ground 90 days Sun 10/3/19 Fri 7/6/19 10/3 7/6

7 Concrete Class 'A1' Elevated 90 days Sun 10/3/19 Fri 7/6/19 10/3 7/6

8 Concrete Class 'A3' Onground 90 days Fri 15/3/19 Wed 12/6/19 15/3 12/6

9 Concrete Class 'A3' Elevated 90 days Wed 20/3/19 Mon 17/6/19 20/3 17/6

10 Precast Concrete Class 'D1' (5000 Psi) 60 days Sun 10/3/19 Wed 8/5/19 10/3 8/5

11 Launching of Girder 35 days Wed 1/5/19 Tue 4/6/19 1/5 4/6

12 Plum Concrete 78 days? Mon 15/4/19 Mon 1/7/19 15/4 1/7

13 EARTH WORK 103 days Mon 25/2/19 Fri 7/6/19 25/2 7/6

14 Clearing and Grubbing 80 days Mon 25/2/19 Wed 15/5/19 25/2 15/5

15 Compaction of Natural Ground 80 days Mon 25/2/19 Wed 15/5/19 25/2 15/5

16 Excavate unsuitable medium rock 80 days Fri 1/3/19 Sun 19/5/19 1/3 19/5
material

17 Excavate unsuitable soft rock material 80 days Fri 1/3/19 Sun 19/5/19 1/3 19/5

18 Structural Excavation in common 80 days Tue 5/3/19 Thu 23/5/19 5/3 23/5
material

19 Common Backfill 80 days Tue 5/3/19 Thu 23/5/19 5/3 23/5

Task Progress Summary External Tasks Deadline


SARCO(PVT)LTD
Split Milestone Project Summary External Milestone

Note:- This Work Program is subjected to prompt payment of IPCs, prompt reciept of Working Drawings & Designs, Stable Weather Conditions and any unforseen circumstances. Page 1 of 2
Package-2: Rehabilitation of National Bridges Chakdara-Kalam (N-95) REVISED WORK SCHEDULE SH. ABDUR RAZZAQ&CO(PVT)LTD
Lot # 2: Behrain - Kalam (Bridge Package) Km 106-134 (12 New Bridges) UPTO 15-07-2019 (18 Months)
ID Task Name Duration Start Finish
9 Mar '19 Apr '19 May '19 Jun '19 Jul '19
17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28
20 Structural Excavation in soft rock 80 days Sun 10/3/19 Tue 28/5/19 10/3 28/5
material

21 Granular Backfill 80 days Fri 15/3/19 Sun 2/6/19 15/3 2/6

22 Formation of embankment from borrow 80 days Wed 20/3/19 Fri 7/6/19 20/3 7/6
excavation in Common Material

23 SUB BASE & BASE COURSE 47 days? Wed 15/5/19 Sun 30/6/19 15/5 30/6

24 Granular Sub Base 32 days Wed 15/5/19 Sat 15/6/19 15/5 15/6

25 Aggregate Base Course 32 days Mon 20/5/19 Thu 20/6/19 20/5 20/6

26 Asphaltic Base Course Plant Mix 26 days? Wed 5/6/19 Sun 30/6/19 5/6 30/6
(Class-A)

27 SURFACE COURSE AND 31 days? Wed 5/6/19 Fri 5/7/19 5/6 5/7

PAVEMENT
28 Bituminous Prime Coat 26 days? Wed 5/6/19 Sun 30/6/19 5/6 30/6

29 Bituminous Tack Coat 26 days? Mon 10/6/19 Fri 5/7/19 10/6 5/7

30 Asphalt Wearing Course (Class-A) 26 days? Mon 10/6/19 Fri 5/7/19 10/6 5/7

31 DRAINAGE & EROSION WORKS 122 days? Fri 1/3/19 Sun 30/6/19 1/3 30/6

32 RCC Pipe Culvert AASHTO M 170 76 days? Fri 1/3/19 Wed 15/5/19 1/3 15/5
Class IV Dia 1070mm

33 Concrete Class B (4000 Psi) in bedding 81 days? Fri 1/3/19 Mon 20/5/19 1/3 20/5

34 Grouted Riprap class "B" 55 days Wed 1/5/19 Mon 24/6/19 1/5 24/6

35 Filter Layer of granular material 60 days Wed 1/5/19 Sat 29/6/19 1/5 29/6

36 Grouted stone pitching (21-25cm thick) 57 days? Sun 5/5/19 Sun 30/6/19 5/5 30/6

37 ANCILLARY WORKS 76 days? Wed 1/5/19 Mon 15/7/19 1/5 15/7

38 Ancillary Works Complete in all 76 days? Wed 1/5/19 Mon 15/7/19 1/5 15/7
Respects

Task Progress Summary External Tasks Deadline


SARCO(PVT)LTD
Split Milestone Project Summary External Milestone

Note:- This Work Program is subjected to prompt payment of IPCs, prompt reciept of Working Drawings & Designs, Stable Weather Conditions and any unforseen circumstances. Page 2 of 2