SSC02 & PBC 6200 Battery Test

Procedure
How to login Into Cabinet
• Open your Power management SW
• Choose CSU list
– Select your Commend port from CSU connected type
» Press connect
1

2 2

3
How to login Into Cabinet
• Change user permission
– Choose Setting list
– Press Change permission
– Enter permission ID: SADMIN
– Password:8888
1

5
Battery Test Parameter
• Change Battery Parameters
1. Select parameter
2. Choose Battery

2
Battery Test Parameter
• Change Battery Parameters
1. Change Battery test status to Enable
Battery Test Parameter
2. Change Test time to 4H
Battery Test Parameter
3.Change Test Voltage to 46.0 V
Start Battery Test
Before Start Test you mast check b/m point

• Make sure All rectifiers working in normal case


• Make sure the Battery not charging
DCI = Total Current
Create Log File
• To Create Log File
» 1 Choose setting
• 2 select log file location
• 3 change LOG active to start

2-Select log
start file location

3-Select start
Start Battery Test
• Choose CSU
• Press Battery test start
Battery Test Started
• Total Current must be = 0 A
Print Screen During Test
• Take Print Screen for Alarm Screen
Print Screen During Test
• Take (CSU) print screen every 0.15 minutes
Print Screen During Test
• Take (Rectifier) print screen every 0.15 m
Battery Test Requirement
• Total Test Time 4 H
• Make sure Battery not Charging or Discharging
• Don’t turn off AC power before Start test
• Make sure Battery test working well
• Take print screen every 0.15 minutes
• Stop the test IF DCV dropped to 46.01V
• Make Sure End Voltage Test (DCV) 46.01 V
• Need Battery photos
• Need number & type of Batteries
Thanks