Sr.No.

Task Qty unit Duration Start Date


1 RCC slab + Beams for staircase head room/OHW tank 78.9 Cum 15 12/16/2019
2 RCC slab + Beams for machine room 0.182 Cum 12 12/16/2019
3 BBM, lintel chhajja door, window frames fixing in basement - - 16 12/16/2019
4 BBM, lintel chajja door frames fixing in GF 40 Cum 11 12/23/2020
5 BBM, lintel chajja door frames fixing in FF 23.4 Cum 5 12/30/2019
6 BBM, lintel chajja door frames fixing in SF 118 Cum 19 12/23/2019
7 BBM, lintel chajja door frames fixing in TF 45 Cum 12 12/30/2019
8 BBM, lintel chhajja door frame fixing in head room - - 12 1/13/2020
9 Construction of ramp 254.1 Sqm 12 1/13/2020
10 Electrical concealed work - - 25 1/6/2020
11 waterproofing work toilets ,terrace, Basement 1135.7 Sqm 17 1/1/2020
12 Plumbing work 690 Rmt 19 1/20/2020
13 plastering work internal 3880 Sqm 26 1/27/2020
14 plastering work external 1580 Sqm 26 2/10/2020
15 tiling work 1375 Sqm 19 2/10/2020
16 door windows shutters fixing 95 nos 19 2/10/2020
17 electrical fitting - - 19 2/24/2020
18 Painting 4760 Sqm 22 3/9/2020
19 compound wall , pavement ,ug tank ,drainage lines - - 19 3/2/2020
20 lift installation 2 nos 8 3/23/2020
21 water supply, electrical supply - - 15 3/16/2020
End Date December January February March April
12/31/2019
12/28/2019
12/31/2020
1/4/2020
1/4/2020
1/11/2020
1/11/2020
1/25/2020
1/25/2020
1/31/2020
1/18/2020
2/8/2020
2/22/2020
3/7/2020
2/29/2020
2/29/2020
3/14/2020
3/31/2020
3/21/2020
3/31/2020
3/31/2020
October Novembe
November December January
January February March
March April