KINGDOMOFSAUDIARABIA Page 1 of 2

Saline Water Conversion Corporation Form: F1711-06, Rev. 1. Dated: 02/07/2019


STRATEGIC RESERVOIRS PROJECT IN MAKKAH PHASE II AND TAIF PHASE I
Owner: Engineer: Contractor: Sub-Contractor:

WIR No.:WIR-1711-T393-F0001
WELDING INSPECTION REPORT (WIR)
WIR Date: 19-AUG-2019
Mfr. Eq. No.: TK-393 Item: ANNULAR PLATES JONTS JO No.: 17-11
(TK-05)
Tick the Applicable
Mat’l. WPS Welder NDT NDT
Results
Dwg. Joint No. J.Fit-up Post Weld VT
Thk. No. No. Required?
PT MT RT VB PO Air Acc./Rej./Hold

J201-01 16mm 1327 Satisfactory Yes Acc


J202-01 16mm 18946 Satisfactory Yes Acc
J202-02 16mm 1974 Satisfactory Yes Acc
J201-02 16mm 18424 Satisfactory Yes Acc
J201-03 16mm 1973 Satisfactory Yes Acc
J201-04 16mm 18253 Satisfactory Yes Acc
76-QP10-S-116 SHT1of3 REV 0

J201-05 16mm 18253 Satisfactory Yes Acc


JFR/1711/T393/F0001

J201-06 16mm 18165 Satisfactory Yes Acc


MET-06-95 Rev.3

J201-07 16mm 15144 Satisfactory Yes Acc


J201-08 16mm 1940 Satisfactory Yes Acc
J201-09 16mm 15144 Satisfactory Yes Acc
J201-10 16mm 1974 Satisfactory Yes Acc
J201-11 16mm 19169 Satisfactory Yes Acc
J201-12 16mm 18946 Satisfactory Yes Acc
J201-13 16mm 1940 Satisfactory Yes Acc
J201-14 16mm 1932 Satisfactory Yes Acc
J201-15 16mm 1939 Satisfactory Yes Acc
J201-16 16mm 1884 Satisfactory Yes Acc
J201-17 16mm 15144 Satisfactory Yes Acc
J201-18 16mm 1884 Satisfactory Yes Acc

Attachments to the WIR: Inspector’s Comments/Remarks:

Inspection Authority Sign-off:


Prepared By: METSCCO Reviewed By: AICC Reviewed By: KHATIB & ALAMI Reviewed By: SWCC

QCI: Mechanical/Welding
Distribution List: Original – QA/QC Dept., e-copies to Production, Client’s Witnessing Inspector/s.
KINGDOMOFSAUDIARABIA Page 2 of 2
Saline Water Conversion Corporation Form: F1711-06, Rev. 1. Dated: 02/07/2019
STRATEGIC RESERVOIRS PROJECT IN MAKKAH PHASE II AND TAIF PHASE I
Owner: Engineer: Contractor: Sub-Contractor:

WIR No.:WIR-1711-T393-F0001
WELDING INSPECTION REPORT (WIR)
WIR Date: 19-AUG-2019
Mfr. Eq. No.: TK-393 Item: ANNULAR PLATES JONTS JO No.: 17-11
(TK-05)
Tick the Applicable
Mat’l. WPS Welder NDT NDT
Results
Dwg. Joint No. J.Fit-up Post Weld VT
Thk. No. No. Required?
PT MT RT VB PO Air Acc./Rej./Hold

J201-19 16mm 18465 Satisfactory Yes Acc


J201-20 16mm 18465 Satisfactory Yes Acc
76-QP10-S-028 SHT2of2 REV 0

J201-21 16mm 18421 Satisfactory Yes Acc


J201-22 16mm 18412 Satisfactory Yes Acc
JFR-TK389-F001

MET-06-95 Rev.3

J201-23 16mm 18498 Satisfactory Yes Acc


J201-24 16mm 18498 Satisfactory Yes Acc
J201-25 16mm 18465 Satisfactory Yes Acc
J201-26 16mm 19169 Satisfactory Yes Acc
J201-27 16mm 18412 Satisfactory Yes Acc
J201-28 16mm 1973 Satisfactory Yes Acc
J201-29 16mm 1884 Satisfactory Yes Acc
J201-30 16mm 18434 Satisfactory Yes Acc

Attachments to the WIR: Inspector’s Comments/Remarks:

Inspection Authority Sign-off:


Prepared By: METSCCO Reviewed By: AICC Reviewed By: KHATIB & ALAMI Reviewed By: SWCC

QCI: Mechanical/Welding
Distribution List: Original – QA/QC Dept., e-copies to Production, Client’s Witnessing Inspector/s.