Sie sind auf Seite 1von 51

P.

H
MATERIA
LS

G.I PIPE
1 S/F/F of 40mm dia G.I. pipe ------- etc
Complete.
Data for 30.48 Mtr or 100'-0".
E/W excavation of Pipe line trench in all kinds of
soil.
100.00 x 1'-6' x 2'-0"= 300.00 Cft or 8.49 Cum Cum 8.49 242.50 2058.83

Earth filling with excavated earth after testing the Cum 8.49 162.50 1379.63
pipe line
Cost Materials 40mm G.I. Pipe for 30.48 Rmt 30.48 236.00 7193.28
Mtr
2% extra of cost of pipe towards cost of wastage 143.87
& fitting
labour Pl. Mistry (Spl) Each 0.33 430.00 141.90
Pl. Khalasi Each 0.66 320.00 211.20
7.5% OHC 11128.70
7.5% C.P 834.65
834.65
12798.00
Rate for 1.00 Mtr. 419.88
419.90/Mtr

2 S/F/F of 25mm dia G.I.pipe ------- etc


Complete.
Data for 30.48 Mtr or 100'-0".
E/W excavation of Pipe line trench in all kinds of
soil.
100.00 x 1'-6' x 2'-0"= 300.00 Cft or 8.49 Cum Cum 8.49 242.50 2058.83

Earth filling with excavated earth after testing the Cum 8.49 162.50 1379.63
pipe line
Cost Materials 25mm G.I. Pipe for 30.48 Rmt 30.48 232.00 7071.36
Mtr
2% extra of cost of pipe towards cost of wastage 141.43
& fitting
labour Pl. Mistry (Spl) Each 1 430.00 430.00
Pl. Khalasi Each 2 320.00 640.00
11721.24
7.5% OHC 879.09
7.5% C.P 879.09
13479.42
Rate per 1.00 Mtr 442.24
442.20/Mtr
3 S/F/F of 20mm dia G.I. pipe ------- etc
Complete.
Data for 30.48 Mtr or 100'-0".
E/W excavation of Pipe line trench in all kinds of
soil.
100.00 x 1'-6' x 2'-0"= 300.00 Cft or 8.49 Cum Cum 8.49 242.50 2058.83
Earth filling with excavated earth after testing the Cum 8.49 162.50 1379.63
pipe line
Cost Materials 20mm G.I. Pipe for 30.48 Rmt 30.48 85.00 2590.80
Mtr
2% extra of cost of pipe towards cost of wastage 51.82
& fitting
Pl. Mistry (Spl) Each 0.92 430.00 395.60
Pl. Khalasi Each 1.84 320.00 588.80
7065.47
7.5% OHC 529.91
7.5% C.P 529.91
8125.29
Rate per 1.00 Mtr 266.58
266.60/Mtr
4 Providing and laying in trenches galvanized
mild steel tubes (heavy grade) conforming
to
IS:1239/2004, Part-1 of the following
nominal bore and tube fittings including
testing as per
specification complete. (Earth work in
trenches to be measured and paid for
separatly.
80mm diameter
Details of cost for 10 metres
a. Materials
80mm dia G.I Pipe (TATA Heavy) Mtr 10.00 643.00 6430.00
Tube fittings and wastages 2% 128.60
White lead,hemp oil etc 1% 64.30
b. Labour for laying
Plumber Fitter(S) Each 0.25 430.00 107.50
Male worker Each 0.66 280.00 184.80
(a+b) 6915.20
c. Add Contractor's Profit & Overhead 1037.28
charges 15%
Total (a+b+c) 7952.48
Rate per metre is 795.25
Add conveyance , Rayality & tollage Qntl 0.101 64.51 6.52
801.76
801.80/Mt
r
50mm diameter
Details of cost for 10 metres
a. Materials
50mm dia G.I Pipe (TATA Heavy) Mtr 10.00 385.00 3850.00
Tube fittings and wastages 2% 77.00
White lead,hemp oil etc 1% 38.50
b. Labour for laying
Plumber Fitter(S) Each 0.16 430.00 68.80
Male worker Each 0.33 280.00 92.40
(a+b) 4126.70
c. Add Contractor's Profit & Overhead 619.01
charges 15%
Total (a+b+c) 4745.71
Rate per metre is 474.57
Add conveyance , Rayality & tollage Qntl 0.062 64.51 4.00
478.57
478.60/Mt
r
20mm diameter
Details of cost for 10 metres
a. Materials
20 mm dia G.I Pipe (TATA Heavy) Mtr 10.00 163.00 1630.00
Tube fittings and wastages 2% 32.60
White lead,hemp oil etc 1% 16.30
b. Labour for laying
Plumber Fitter(S) Each 0.08 430.00 34.40
Male worker Each 0.16 280.00 44.80
(a+b) 1758.10
c. Add Contractor's Profit & Overhead 263.72
charges 15%
Total (a+b+c) 2021.82
Rate per metre is 202.18
Add conveyance , Rayality & tollage Qntl 0.019 64.51 1.23
203.41
203.40/Mt
r
15mm diameter
Details of cost for 10 metres
a. Materials
15mm dia G.I Pipe (TATA Heavy) Mtr 10.00 73.89 738.90
Tube fittings and wastages 2% 14.78
White lead,hemp oil etc 1% 7.39
b. Labour for laying
Plumber Fitter(S) Each 0.08 430.00 34.40
Male worker Each 0.16 280.00 44.80
(a+b) 840.27
c. Add Contractor's Profit & Overhead 126.04
charges 15%
Total (a+b+c) 966.31
Rate per metre is 96.63
Add conveyance , Rayality & tollage Qntl 0.019 64.51 1.23
97.86
97.90/Mtr
40mm diameter
Details of cost for 10 metres
a. Materials
40mm dia G.I Pipe (TATA heavy) Mtr 10.00 372.00 3720.00
Tube fittings and wastages 2% 74.40
White lead,hemp oil etc 1% 37.20
b. Labour for laying
Plumber Fitter(S) Each 0.16 430.00 68.80
Male worker Each 0.33 280.00 92.40
(a+b) 3992.80
c. Add Contractor's Profit & Overhead 598.92
charges 15%
Total (a+b+c) 4591.72
Rate per metre is 459.17
Add conveyance , Rayality & tollage Qntl 0.044 64.51 2.84
462.01
462.00/Mt
r
25mm diameter
Details of cost for 10 metres
a. Materials
25 mm dia G.I Pipe (TATA Heavy) Mtr 10.00 232.00 2320.00
Tube fittings and wastages 2% 46.40
White lead,hemp oil etc 1% 23.20
b. Labour for laying
Plumber Fitter(S) Each 0.12 430.00 51.60
Male worker Each 0.25 280.00 70.00
(a+b) 2511.20
c. Add Contractor's Profit & Overhead 376.68
charges 15%
Total (a+b+c) 2887.88
Rate per metre is 288.79
Add conveyance , Rayality & tollage Qntl 0.03 64.51 1.94
290.72
290.70/Mt
r

4 Providing and laying in trenches galvanized


mild steel tubes (medium grade) conforming
to
IS:1239/2004, Part-1 of the following
nominal bore and tube fittings including
testing as per
specification complete. (Earth work in
trenches to be measured and paid for
separatly.
25mm diameter
Details of cost for 10 metres
a. Materials
25 mm dia G.I Pipe (TATA Medium) Mtr 10.00 247.88 2478.80
Tube fittings and wastages 2% 49.58
White lead,hemp oil etc 1% 24.79
b. Labour for laying
Plumber Fitter(S) Each 0.12 430.00 51.60
Male worker Each 0.25 280.00 70.00
(a+b) 2674.76
c. Add Contractor's Profit & Overhead 401.21
charges 15%
Total (a+b+c) 3075.98
Rate per metre is 307.60
Add conveyance , Rayality & tollage Qntl 0.03 64.51 1.94
309.53
309.50/Mt
r
20mm diameter
Details of cost for 10 metres
a. Materials
20 mm dia G.I Pipe (TATA Medium) Mtr 10.00 174.40 1744.00
Tube fittings and wastages 2% 34.88
White lead,hemp oil etc 1% 17.44
b. Labour for laying
Plumber Fitter(S) Each 0.08 430.00 34.40
Male worker Each 0.16 280.00 44.80
(a+b) 1875.52
c. Add Contractor's Profit & Overhead 281.33
charges 15%
Total (a+b+c) 2156.85
Rate per metre is 215.68
Add conveyance , Rayality & tollage Qntl 0.019 64.51 1.23
216.91
216.90
40mm diameter
Details of cost for 10 metres
a. Materials
40mm dia G.I Pipe (TATA Medium) Mtr 10.00 289.94 2899.40
Tube fittings and wastages 2% 57.99
White lead,hemp oil etc 1% 28.99
b. Labour for laying
Plumber Fitter(S) Each 0.16 430.00 68.80
Male worker Each 0.33 280.00 92.40
(a+b) 3147.58
c. Add Contractor's Profit & Overhead 472.14
charges 15%
Total (a+b+c) 3619.72
Rate per metre is 361.97
Add conveyance , Rayality & tollage Qntl 0.044 64.51 2.84
364.81
364.80/Mt
r

40mm diameter
Details of cost for 10 metres
a. Materials
40mm dia G.I Pipe (TATA Medium) Mtr 10.00 266.00 2660.00
Tube fittings and wastages 2% 53.20
White lead,hemp oil etc 1% 26.60
b. Labour for laying
Plumber Fitter(S) Each 0.16 430.00 68.80
Male worker Each 0.33 280.00 92.40
(a+b) 2901.00
c. Add Contractor's Profit & Overhead 435.15
charges 15%
Total (a+b+c) 3336.15
Rate per metre is 333.62
Add conveyance , Rayality & tollage Qntl 0.044 64.51 2.84
336.45
336.45/Mt
r
4N Providing and laying in trenches galvanized
mild steel tubes (medium grade) conforming
to
IS:1239/2004, Part-1 of the following
nominal bore and tube fittings including
testing as per
specification complete. (Earth work in
trenches to be measured and paid for
separatly.
15mm diameter
Details of cost for 10 metres
a. Materials
15 mm dia G.I Pipe (TATA Medium) Mtr 10.00 131.00 1310.00
Tube fittings and wastages 2% 26.20
White lead,hemp oil etc 1% 13.10
b. Labour for laying
Plumber Fitter(S) Each 0.08 430.00 34.40
Male worker Each 0.16 280.00 44.80
(a+b) 1428.50
c. Add Contractor's Profit & Overhead 214.28
charges 15%
Total (a+b+c) 1642.78
Rate per metre is 164.28
Add conveyance , Rayality & tollage Qntl 0.03 64.51 1.94
166.21
166.20/Mt
r
20mm diameter
Details of cost for 10 metres
a. Materials
20 mm dia G.I Pipe (TATA Medium) Mtr 10.00 160.00 1600.00
Tube fittings and wastages 2% 32.00
White lead,hemp oil etc 1% 16.00
b. Labour for laying
Plumber Fitter(S) Each 0.08 430.00 34.40
Male worker Each 0.16 280.00 44.80
(a+b) 1727.20
c. Add Contractor's Profit & Overhead 259.08
charges 15%
Total (a+b+c) 1986.28
Rate per metre is 198.63
Add conveyance , Rayality & tollage Qntl 0.019 64.51 1.23
199.85
199.85/Mt
r
25mm diameter
Details of cost for 10 metres
a. Materials
25 mm dia G.I Pipe (TATA Medium) Mtr 10.00 227.00 2270.00
Tube fittings and wastages 2% 45.40
White lead,hemp oil etc 1% 22.70
b. Labour for laying
Plumber Fitter(S) Each 0.12 430.00 51.60
Male worker Each 0.25 280.00 70.00
(a+b) 2459.70
c. Add Contractor's Profit & Overhead 368.96
charges 15%
Total (a+b+c) 2828.66
Rate per metre is 282.87
Add conveyance , Rayality & tollage Qntl 0.03 64.51 1.94
284.80
284.80/Mt
r
32mm diameter
Details of cost for 10 metres
a. Materials
32 mm dia G.I Pipe (TATA Medium) Mtr 10.00 241.00 2410.00
Tube fittings and wastages 2% 48.20
White lead,hemp oil etc 1% 24.10
b. Labour for laying
Plumber Fitter(S) Each 0.12 430.00 51.60
Male worker Each 0.25 280.00 70.00
(a+b) 2603.90
c. Add Contractor's Profit & Overhead 390.59
charges 15%
Total (a+b+c) 2994.49
Rate per metre is 299.45
Add conveyance , Rayality & tollage Qntl 0.03 64.51 1.94
301.38
301.40/Mt
r
40mm diameter
Details of cost for 10 metres
a. Materials
40mm dia G.I Pipe (TATA Medium) Mtr 10.00 266.00 2660.00
Tube fittings and wastages 2% 53.20
White lead,hemp oil etc 1% 26.60
b. Labour for laying
Plumber Fitter(S) Each 0.16 430.00 68.80
Male worker Each 0.33 280.00 92.40
(a+b) 2901.00
c. Add Contractor's Profit & Overhead 435.15
charges 15%
Total (a+b+c) 3336.15
Rate per metre is 333.62
Add conveyance , Rayality & tollage Qntl 0.044 64.51 2.84
336.45
336.45/Mt
r
50mm diameter
Details of cost for 10 metres
a. Materials
50mm dia G.I Pipe (TATA Medium) Mtr 10.00 376.00 3760.00
Tube fittings and wastages 2% 75.20
White lead,hemp oil etc 1% 37.60
b. Labour for laying
Plumber Fitter(S) Each 0.16 430.00 68.80
Male worker Each 0.33 280.00 92.40
(a+b) 4034.00
c. Add Contractor's Profit & Overhead 605.10
charges 15%
Total (a+b+c) 4639.10
Rate per metre is 463.91
Add conveyance , Rayality & tollage Qntl 0.044 64.51 2.84
466.75
466.75/Mt
r
65mm diameter
Details of cost for 10 metres
a. Materials
65mm dia G.I Pipe (TATA Medium) Mtr 10.00 476.00 4760.00
Tube fittings and wastages 2% 95.20
White lead,hemp oil etc 1% 47.60
b. Labour for laying
Plumber Fitter(S) Each 0.25 430.00 107.50
Male worker Each 0.66 280.00 184.80
(a+b) 5195.10
c. Add Contractor's Profit & Overhead 779.27
charges 15%
Total (a+b+c) 5974.37
Rate per metre is 597.44
Add conveyance , Rayality & tollage Qntl 0.044 64.51 2.84
600.27
600.30/Mt
r
4N Providing and laying in trenches galvanized
mild steel tubes (Heavy grade) conforming
to
IS:1239/2004, Part-1 of the following
nominal bore and tube fittings including
testing as per
specification complete. (Earth work in
trenches to be measured and paid for
separatly.
15mm diameter
Details of cost for 10 metres
a. Materials
15 mm dia G.I Pipe (TATA Heavy) Mtr 10.00 150.00 1500.00
Tube fittings and wastages 2% 30.00
White lead,hemp oil etc 1% 15.00
b. Labour for laying
Plumber Fitter(S) Each 0.08 430.00 34.40
Male worker Each 0.16 280.00 44.80
(a+b) 1624.20
c. Add Contractor's Profit & Overhead 243.63
charges 15%
Total (a+b+c) 1867.83
Rate per metre is 186.78
Add conveyance , Rayality & tollage Qntl 0.03 64.51 1.94
188.72
188.70/Mt
r
20mm diameter
Details of cost for 10 metres
a. Materials
20 mm dia G.I Pipe (TATA Heavy) Mtr 10.00 186.00 1860.00
Tube fittings and wastages 2% 37.20
White lead,hemp oil etc 1% 18.60
b. Labour for laying
Plumber Fitter(S) Each 0.08 430.00 34.40
Male worker Each 0.16 280.00 44.80
(a+b) 1995.00
c. Add Contractor's Profit & Overhead 299.25
charges 15%
Total (a+b+c) 2294.25
Rate per metre is 229.43
Add conveyance , Rayality & tollage Qntl 0.019 64.51 1.23
230.65
230.65/Mt
r
25mm diameter
Details of cost for 10 metres
a. Materials
25 mm dia G.I Pipe (TATA Heavy) Mtr 10.00 271.00 2710.00
Tube fittings and wastages 2% 54.20
White lead,hemp oil etc 1% 27.10
b. Labour for laying
Plumber Fitter(S) Each 0.12 430.00 51.60
Male worker Each 0.25 280.00 70.00
(a+b) 2912.90
c. Add Contractor's Profit & Overhead 436.94
charges 15%
Total (a+b+c) 3349.84
Rate per metre is 334.98
Add conveyance , Rayality & tollage Qntl 0.03 64.51 1.94
336.92
336.90/Mt
r
32mm diameter
Details of cost for 10 metres
a. Materials
32 mm dia G.I Pipe (TATA Heavy) Mtr 10.00 280.00 2800.00
Tube fittings and wastages 2% 56.00
White lead,hemp oil etc 1% 28.00
b. Labour for laying
Plumber Fitter(S) Each 0.12 430.00 51.60
Male worker Each 0.25 280.00 70.00
(a+b) 3005.60
c. Add Contractor's Profit & Overhead 450.84
charges 15%
Total (a+b+c) 3456.44
Rate per metre is 345.64
Add conveyance , Rayality & tollage Qntl 0.03 64.51 1.94
347.58
347.60/Mt
r
40mm diameter
Details of cost for 10 metres
a. Materials
40mm dia G.I Pipe (TATA Heavy) Mtr 10.00 323.00 3230.00
Tube fittings and wastages 2% 64.60
White lead,hemp oil etc 1% 32.30
b. Labour for laying
Plumber Fitter(S) Each 0.16 430.00 68.80
Male worker Each 0.33 280.00 92.40
(a+b) 3488.10
c. Add Contractor's Profit & Overhead 523.22
charges 15%
Total (a+b+c) 4011.32
Rate per metre is 401.13
Add conveyance , Rayality & tollage Qntl 0.044 64.51 2.84
403.97
404.00/Mt
r

50mm diameter
Details of cost for 10 metres
a. Materials
50mm dia G.I Pipe (TATA Heavy) Mtr 10.00 468.00 4680.00
Tube fittings and wastages 2% 93.60
White lead,hemp oil etc 1% 46.80
b. Labour for laying
Plumber Fitter(S) Each 0.16 430.00 68.80
Male worker Each 0.33 280.00 92.40
(a+b) 4981.60
c. Add Contractor's Profit & Overhead 747.24
charges 15%
Total (a+b+c) 5728.84
Rate per metre is 572.88
Add conveyance , Rayality & tollage Qntl 0.044 64.51 2.84
575.72
575.70/Mt
r
65mm diameter
Details of cost for 10 metres
a. Materials
65mm dia G.I Pipe (TATA Heavy) Mtr 10.00 578.00 5780.00
Tube fittings and wastages 2% 115.60
White lead,hemp oil etc 1% 57.80
b. Labour for laying
Plumber Fitter(S) Each 0.25 430.00 107.50
Male worker Each 0.66 280.00 184.80
(a+b) 6245.70
c. Add Contractor's Profit & Overhead 936.86
charges 15%
Total (a+b+c) 7182.56
Rate per metre is 718.26
Add conveyance , Rayality & tollage Qntl 0.044 64.51 2.84
721.09
721.10/Mt
r
5 Dismantling G.I. pipes (external work)
including excavation and refilling trenches
after taking out
the pipes, manually / by mechanical means
including stacking of pipes within 50 metres
lead as per direction of Engineer in charge.

15 mm to 40 mm nominal bore
Details of cost for 10 metre
a. Labour charges
Male worker unskilled Each 1.32 280.00 369.60
Dismantling G.I. pipe and stacking etc. L.S 53.46
423.06
b. Add Contractor's Profit & Overhead 63.46
charges 15%
Total (a+b) 486.52
Rate per metre 48.65
48.65
[ ii ] Above 40 mm nominal bore
Details of cost for 10 metre
a. Labour charges
Male worker unskilled Each 1.32 280.00 369.60
Dismantling G.I. pipe and stacking etc L.S 106.83
476.43
b. Add Contractor's Profit & Overhead 71.46
charges 15%
Total (a+b) 547.89
Rate per metre 54.79
54.80/Mtr

PVC PIPE
6 S/F/F of 25mm dia PVC pipe line-----
etc complete.Oriplast make S-80
Data for 10.00 Mtr.
25mm dia PVC pipe Rmt. 10 94.40 944.00
15% for fitting & wastage 141.60
3% for wooden plug,clamp, cement etc 28.32
Plumbing Mistry 2nd class Each 0.83 370.00 307.10
Mulia Each 0.67 280.00 187.60
1608.62
7.5% OHC 120.65
7.5% C.P 120.65
Rate for 1.00 Mtr. 1849.91
184.99
185.00/Mtr
7 S/F/F of 20mm dia PVC pipe line-----
etc complete. Oriplast make S-80
Data for 10.00 Mtr.
25mm dia PVC pipe Rmt. 10 64.40 644.00
15% for fitting & wastage 96.60
3% for wooden plug,clamp, cement etc 19.32
Plumbing Mistry 2nd class Each 0.75 370.00 277.50
Mulia Each 0.67 280.00 187.60
1225.02
7.5% O.H.C 91.88
7.5% C.P 91.88
1408.77
Rate for 1.00 Mtr. 140.88
140.90/Mtr
8 S/F/F of 15mm dia PVC pipe line-----
etc complete.Oriplast make S-80
Data for 10.00 Mtr.
25mm dia PVC pipe Rmt. 10 47.70 477.00
15% for fitting & wastage 71.55
3% for wooden plug,clamp, cement etc 14.31
Plumbing Mistry 2nd class Each 0.67 370.00 247.90
Mulia Each 0.67 280.00 187.60
998.36
7.5% O.H.C 74.88
7.5% C.P 74.88
Rate for 1.00 Mtr. 1148.11
114.81
114.80/Mtr
9 Supplying, fitting & fixing of 100mm dia
PVC pipes IS:4985-2000 and specials of the
following out side diameter for all classes
including jointing with supply of approved
solvent cement by heat application method
including testing as per specification
complete. (Waste pipe)

Data for 10 metres


PVC Pipe 100mm dia Rmt 10 124.96 1249.60
Plumber (S) Each 0.18 430.00 77.40
Man Mulia Each 0.36 280.00 100.80
Jointing materials Kg 0.056 171.00 9.58
1437.38
Add contractors profit & overhead charges 215.61
15%
1652.98
Rate per Rmt 165.30
165.30/Mt
r
10 110mm dia PVC pipe line
Data for 10.00mtr (UPVC-SWR pipe
Materials
110mm dia UPVC single socketed pipe (working PAIR 6 129.00 774.00
prass
er 4kg/CM-2
110mm dia UPVCsingle socketed pipe (working each 1.00 20.00 20.00

presser 4kg/CM -2 rubber(seal) ring


Adhecive etc L.S 12.01
Scaffolding L.S 27.7
Labour charge
plumber/Fitter (2nd class) each 0.23 370.00 85.1
Helper to plumber each 0.11 320.00 35.2
Male worker each 0.45 280.00 126
1080.01
7.5% O.H.C 81.00
7.5% C.P 81.00
1242.01
124.20
Rate per 1.00 Meter 124.20/Mt
r
11 Providing and fixing to wall or ceiling and
floor pvc
pipes class conforming to ASTM-D-
1785/89(Sch-80)
and pipe fittings of the following nominal bore
with
clamps including making good the wall,ceiling
and
comp.
15mm diameter
Details of cost for 10 meters
a- Materials
15mm pvc sch-80 pipes Mtr 10 27.94 279.40
Add for fitting& wastage 15% 41.91
Wooden plug , clamps & cement 3% 8.38
b-Labour
2nd class plumber Each 0.67 370.00 247.90
Male worker Each 0.67 280.00 187.60
765.19
15% OHC & C.P 114.78
879.97
Rate per 1.00Mtr 88.00
88.00/Mtr
12 Providing and fixing on wall face unplastivised
rigid PVC soil, waste and water pipes conforming
to IS:13592 type A, including jointing with seal
ring conforming to IS:5382, leaving 10mm gap for
thermal expansion, (i) single socketed pipe.
(DATA FOR 10.00 Mtr.)

Material
110mm dia UPVC Pipe Pair 6 129.00 774.00
110mm dia UPVC Pipe (working pressure 4Kg / Each 1 20.00 20.00
CM2) Rubber (seal) ring
Adhesive L.S 12.01
Scaffolding L.S 27.70
Labour
Plumber 2nd class Each 0.23 370.00 85.10
Helper to plumber Each 0.11 320.00 35.20
Mail worker Each 0.45 280.00 126.00
1080.01
OHC & C.P 15% 162.00
1242.01
Rate per Mtr 124.20
124.20
13 Providing and laying in trenches unplasticed
PVC pipes conforming to Is 4985 /2000 of
class IV (10 kgf/ cm2) of the following
nominal bore and pipe fittings including
testing as per specification complete.
( Earth work in trenches to be measured
and paid for separately)

50mm diameter (2")


I Details of cost for 10 meters
A.Materials 50mm dia class- IV PVC pipes Mtr 10 51.30 513.00

pipe fittings and wastages 2% 513 10.26


B. Labour for laying . Plumber fitter (S)(2nd Each 0.16 370.00 59.20
class)
Male worker Each 0.33 280.00 92.40
(a+b) 674.86
C. Add CP & O.H.C 15% 674.86 101.23
Total (a+b+c) 776.09
Rate per meter is 776.09/10 77.61
77.60/Mt
r

II 25mm diameter (1")


A. Materials . 25mm dia class -IV PVC pipes Mtr 10 14.56 145.60

Pipe fittings and wastage 2% 145.60 2.912


B. Labour for laying . Plumber fitter (S)(2nd Each 0.12 370.00 44.40
class)
Male worker Each 0.25 280.00 70.00
( A+B) 262.91
C. Add contractors profit & over head 15% 39.44
charges
Total (a+b+c) 302.35
Rate per meter is 302.35/10= 30.23
30.20/Mt
r
III. 20mm diameter
A. Materials .20mm dia class -iv PVC pipes Mtr 10 11.78 117.80

Pipe fitting and wastage 2% 117.8 2.356


B. Labour for laying . Plumber fitter (S) (2nd Each 0.08 370.00 29.60
class)
Male worker Each 0.16 280.00 44.80
(a+b) 194.56
C Add CP & O.H.C 15% 29.18
Total (a+b+c) 223.74
Rate per meter is 223.74/10= 22.37
22.40/Mt
r
14 Providing and fixing on wall face unplasticised
rigid pvc soil, waste and rain water pipes
conforming to IS: 13592 Type A, including jointing
with seal ring conforming to IS: 5382 , leaving
10mm gap for thermal expansion, (i) single
socketed pipes.

(I) 110 mm diameter


Data for 10 meters of U - PVC SWR pipes
Materials
110 mm dia UPVC single socketed pipe (working Pair 6 129.00 774.00
pressure 4 kg/ cm2)
110mm dia UPVC pipe (working pressure 4 kg / Each 1 20.00 20.00
cm2) Rubber (seal)Ring
Adhesive etc LS 12.01
Scaffolding LS 27.70
(II) Labour for charges
Plumber fitter (2nd class) Each 0.23 370.00 85.10
Helper to plumber Each 0.11 320.00 35.20
Male worker Each 0.45 280.00 126.00
A+B 1080.01
(III)Add CP & O.H.C 15% 1080.01 162.00
Total (A+B+C) 1242.01
Rate per meter = 1242.01/10 = 124.20 124.20
124.20/Mt
r
15 S/F/F 4" ( 100mm ) dia PVC pipe for S.W. line (30.48
Mtr)
Pl. khalasi Each 2 320.00 640.00
Pl. Mistry (2nd class) Each 2 370.00 740.00
mason ( 2nd class ) Each 2 370.00 740.00
Mulia Each 0.5 280.00 140.00
2260.00
Gasket Kg 2.19 30.00 65.70
Cement Qntl 0.12 495.30 59.44
Extra for testing the soil pipe including supply of 25.00
material
Rate per 30.48 mtr 2410.14
7.5% OHC 180.76
7.5% C.P 180.76
2771.66
Rate per 1 Rmt 90.93
add cost of 100mm dia PVC pipe 148.00
238.93
238.90/Mtr
16 S/F/F 4" ( 100mm ) dia PVC pipe for S.W. line
(30.48 Mtr)
Pl. khalasi Each 2 320.00 640.00
Pl. Mistry (2nd class) Each 2 370.00 740.00
mason ( 2nd class ) Each 2 370.00 740.00
Mulia Each 0.5 280.00 140.00
2260.00
Gasket Kg 2.19 30.00 65.70
Cement Qntl 0.12 495.30 59.44
Sand L.S. 5.00
Wooden plug nail Each 17 8.50 144.50
Cost of soaking arround L.S. 5.00
scaffolding for each work 30.00
Extra for testing the soil pipe including supply of 25.00
material
Rate per 30.48 mtr 2594.64
7.5% OHC 194.60
7.5% C.P 194.60
2983.83
Rate per 1 Rmt 97.89
add cost of 100mm dia PVC pipe 325.00
422.89
422.90/Mtr
17 Fixing of 100mm dia PVC floor trap of the Each 1 157.55 157.55
followingnominal diameter of out let of self
cleaning design with screwed down or hinged
grating with or without vent arm complete
including cost of cutting and making good the
walls and floors all complete as per specification.

18 S/F/F/ of 32mm dia waste pipe (Details for one


No.
Materials;
Semirigid PVC waste pipe for sink and wash Each 1 21.00 21.00
basin 32mm dia with length not less than 700mm
with PVC waste fitting.
Carriage of materials and fixing charges L.S 30.22
51.22
7.5% O.H.C 3.84
7.5% C.P 3.84
58.90
19 Supplying Fitting Fixing of C.I wall Grating L.S 80.00

EWC PAN
20 S/F/F all materials labour T&P for fitting
E.W.C. pan with 1 no of P.V.C P trap
A. E.W.C. pan: Plumber ( 2nd class ) Each 0.5 370.00 185.00
Mulia Each 0.5 280.00 140.00
325.00
7.5% O.H.C 24.38
7.5% C.P 24.38
2% sundries T&P 6.50
C.C. ( 1:5:10 ) cement Qntl 0.17 495.30 84.20
Sand Cum 0.06 52.38 3.14
Metal Cum 0.12 709.52 85.14
Cost of EWC pan (Parry make) 800.00
1352.74
1351.16
B. P.V.C P trap : Plumber ( 2nd class ) Each 0.5 370.00 185.00
Mulia Each 0.5 280.00 140.00
Helper Each 0.5 320.00 160.00
485.00
7.5% O.H.C 36.38
7.5% C.P 36.38
Cement Qntl 0.12 495.30 59.44
spun yarn Kg 2.18 50.00 109.00
Sand bitumen L.S. 6.60
732.79
Rate per 1 joint 73.28
Cost of HCI P.Trap Each 1 202.32 202.32
275.60
Toal cost (A + B) (1351.16 + 275.49) 1626.76
1626.80/E
ach
21 White vitreous china wash down water
closet (EWC

Material
EWC Pan with P. Trap Each 1.00 1500.00 1500.00
CP screw, washer and wooden plugs, white L.S 19.95
cement finish on cement mortar joint etc.

Jointing trap with siol pipe L.S 28.34


Carriage of materials 20.14
1568.43
B. Labour charge
Plumber (fitter) /Mason (2nd class) Each 0.50 370.00 185.00
Male worker (un skilled) Each 0.50 280.00 140.00
325.00
A+B 1893.43
C. Add contractors profit & over head 15% 284.01
charges
Cost per each 2177.44
2177.40/
Each
27 White vitreous china wash down water closet (EWC

Material
EWC Pan with P. Trap Each 1.00 1225.00 1225.00
CP screw, washer and wooden plugs, white cement L.S 19.95
finish on cement mortar joint etc.
Jointing trap with siol pipe L.S 28.34
Carriage of materials 20.14
1293.43
B. Labour charge
Plumber (fitter) /Mason (2nd class) Each 0.50 370.00 185.00
Male worker (un skilled) Each 0.50 280.00 140.00
325.00
A+B 1618.43
C. Add contractors profit & over head charges 15% 242.76
Cost per each 1861.19
1861.20/Ea
ch
32 N Fixing Wash Down closet (Europen Type W.C Pan)
with integral 'S' or 'P' trap conforming to IS 2556: part 8
-2004 , to the floor with wooden plug and chromium
plated screws including jointing the tap with soil pipe in
cement mortar (1:1) etc all complete as per
specification.

Details of cost for 1 No


Material
White Vitreous china EWC Pan with P. Trap Each 1.00 1225.00 1225.00
CP screw, washer and wooden plugs, white cement L.S 19.95
finish on cement mortar joint etc.
Jointing trap with soil pipe L.S 28.34
Carriage of materials 20.14
1293.43
B. Labour charge
Plumber (fitter) /Mason (2nd class) Each 0.50 370.00 185.00
Male worker (un skilled) Each 0.50 280.00 140.00
325.00
A+B 1618.43
Plastic seat & cover with CP brass hinges and rubber Each 1 310.00 310.00
buffers
Labour for fitting of Seat & Cover of EWC (P-148 vide L.S 19.95 19.95
SL No. 3.4.5)
1948.38
7.5% O.H.C & CP 15% 292.26
2240.64
2240.60/Ea
ch
IWC PAN
22 Dismantling of IWC pan with 'P' trap etc for one
set.
Data for one set.
Labour
Man Mulia Each 0.50 280.00 140.00
15% OHC & CP 21.00
161.00
161.00/E
ach
23 S/F/F of I.W.C pan (560 x 410)---------- etc
complete.
Cost of IWC Pan Each 1 850.00 850.00
Cost & Lead Cement Qntl 0.12 495.30 59.44
Sand Cum 0.06 52.38 3.14
Metal 40mm Cum 0.12 709.52 85.14
Labour Plumber 2nd class Each 0.5 370.00 185.00
Man Mulia Each 0.5 280.00 140.00
1322.72
7.5% OHC 99.20
7.5% C.P 99.20
cost of P-Trap Each 1 263.00 263.00
cost of One joint Each 1 21.26 21.26
1805.39
1805.40/E
ach
24 S/F/F of I.W.C pan (580 mm---------- etc
complete.
Cost of IWC Pan Each 1 340.00 340.00
Cement Qntl 0.206 495.30 102.03
Sand Cum 0.058 52.38 3.04
Metal 40mm Cum 0.115 709.52 81.59
Labour Plumber 2nd class Each 0.5 370.00 185.00
Man Mulia Each 0.5 280.00 140.00
851.66
7.5% OHC 63.87
7.5% C.P 63.87
cost of P-Trap Each 1 263.00 263.00
cost of One joint Each 1 21.26 21.26
1263.67
Lead Chart Cement Qntl 0.206 64.51 13.29
Sand Cum 0.058 551.87 32.01
Metal Cum 0.115 771.73 88.75
Conveyance charge of IWC Pan Each 1 39.40 39.40
1437.12
1437.10/E
ach
25 S/F/F of I.W.C pan (560 x 410)---------- etc
complete.
Cost of IWC Pan Each 1 850.00 850.00
Cost & Lead Cement Qntl 0.12 495.30 59.44
Sand Cum 0.06 52.38 3.14
Metal 40mm Cum 0.12 709.52 85.14
Labour Plumber 2nd class Each 0.5 370.00 185.00
Man Mulia Each 0.5 280.00 140.00
1322.72
7.5% OHC 99.20
7.5% C.P 99.20
cost of One joint Each 1 21.26 21.26
1542.39
1542.40/E
ach
26 Dismantling indian water closet( I.W.C/ O.W. C)

Details of cost for one number


Labour charges: Plumber Fitter Each 0.25 370.00 92.50
Man mulia (unskilled) Each 0.25 280.00 70.00
Mending damages to walls and Floors L.S 13.20
175.70
Add C.P & O.H.C 15% 26.36
202.06
202.10/Ea
ch
C.P TOWEL RAIL
27 S/F of standard size C.P Towel rail with C.P
bracket fixed to wooden plug
25mm CP screw Each 6 3.10 18.60
C.P Towel rail Each 1 180.00 180.00
Wooden Plug Each 2 1.00 2.00
Cement, Sand & Chips LS 2.20
Carpenter (2nd class ) Each 0.17 370.00 62.90
Man Mulia Each 0.17 280.00 47.60
313.30
7.5% O.H.C 5.96
7.5% C.P 5.96
325.22
325.20/Ea
ch
28 S/F of standard size C.P Towel rail with C.P
bracket fixed to wooden plug(25mm x
600mm)N
C.P Towel rail Each 1 700.00 700.00
25mm CP screw Each 6 3.10 18.60
Wooden Plug Each 2 1.00 2.00
Cement, Sand & Chips LS 2.20
Carpenter (2nd class ) Each 0.17 370.00 62.90
Man Mulia Each 0.17 280.00 47.60
833.30
15% OHC & CP 125.00
958.30
958.30/Ea
ch
12 Towel Ring
Fixing standard sized Chromium plated brass
towel ring fixed to wooden plugs with chromium
plated brass screws, complete as per
specification.

Chromium plated brass towel ring


Details of cost for one number
Materials
Chromium plated brass towel ring Each 1 400.00 400.00
Carriage of materials and fixing charges L.S 30.22
(A+B) 430.22
Add C.P & O.H.C 15 % 64.53
494.75
494.75

MIRROR
29 S/F/F of Mirror----- etc complete.
25mm C.P. screw Nos 4 3.10 12.40
Wooden plug screw Nos 4 1.00 4.00
6mm thick A.C. or ply wood sheet Sqm 0.28 100.00 28.00
0.275/sqm
Rubber buffer Nos 4 1.00 4.00
Cement, Sand, Chips L.S. 3.30
Carpenter ( 2nd class ) Each 0.33 370.00 122.10
Mulia Each 0.33 280.00 92.40
7.5% O.H.C 11.56
7.5%C.P 11.56
1% watering charges 1.54
8% sundries T&P 12.33
Cost of mirror (Balegium) Each 1 450.00 450.00
753.19
753.20/Ea
ch
30 S/F/F of Mirror----- etc complete.
Cost of mirror (Balegium) (650 x 450) Each 1 450.00 450.00
25mm C.P. screw Nos 4 3.10 12.40
Wooden plug screw Nos 4 1.00 4.00
6mm thick A.C. or ply wood sheet 0.275 Sqm Sqm 0.27 100.00 27.00

Rubber buffer Nos 4 1.00 4.00


Cement, Sand, Chips L.S. 3.30
Carpenter ( 2nd class ) Each 0.33 370.00 122.10
Mulia Each 0.33 280.00 92.40
715.20
15% OHC & CP 107.28
822.48
822.50/Ea
ch
Dismantling of mirrors , Towel rails etc.
Details of cost for 1 No
Labour charges:- Plumber fitter Each 0.125 370.00 46.25
Man mulia Each 0.125 280.00 35.00
Mendig damages to the wall L.S 3.87
85.12
\Add CP & O.H.C 15% 12.77
97.89
97.90/Eac
h

41 N Fixing Rectangular shape 453 X 357 mm mirror of


superior glass mounted on 6mm thick A.C sheet or ply
wood sheet and fixed to woden plugs with chromium
plated brass screws and washers complete.

Details for one No


A. Materials: Rectangular shape 453 X 357 mm Mirror Each 1 260.00 260.00
with plastic moulded frame.
Hard board 6mm thick Sqm 0.18 170.00 30.60
25MM cp SCREWS 100nos 4 112.00 4.48
Rawl plug 50mm (designation 10 Nos) Each 4 10.00 40.00
Cement , sand and chips & carriage of materials L.S 8.33
B. Labour charges: Carpenter Each 0.33 370.00 122.10
Male worker Each 0.33 280.00 92.40
557.91
C. Add CP & O.H.C 15 % 83.69
641.60
641.60/Each

40 N S/F/F of 600X450mm bevelled edge Mirror----- etc


complete.
Cost of mirror (Bevelled edge) 600X450mm Each 1 290.00 290.00
25mm C.P. screw Nos 4 3.10 12.40
Wooden plug screw Nos 4 1.00 4.00
6mm thick A.C. or ply wood sheet 0.275 Sqm Sqm 0.27 100.00 27.00
Rubber buffer Nos 4 1.00 4.00
Cement, Sand, Chips L.S. 3.30
Carpenter ( 2nd class ) Each 0.33 370.00 122.10
Mulia Each 0.33 280.00 92.40
555.20
15% OHC & CP 83.28
638.48
638.50/Each

HAND WASH BASIN


31 supplying fitting fixing hand wash basin with
bolt , nut,pillar trap
Wash basin with C.I. or MS brackets (Parry Set 1 990.00 990.00
make)
Lead paint yarn cement, sand, wooden L.S. 50.00
plug screw
Labour : Plumber fitter(2nd class) Each 0.33 370.00 122.10
Mason Each 0.33 320.00 105.60
Male worker (un skilled) Each 0.67 280.00 187.60
C.P.brass waste No 1 41.99 41.99
Labour for fixing sundries L.S. 6.60
15mm dia connecting pipi No 1 80.00 80.00
Labour for fixing sundries L.S. 6.60
32mm PVC waste with copline No 1 41.99 41.99
Labour for fixing sundries L.S. 6.60
15 mm dia C.P Pillar Cock No 1 540.00 540.00
2179.08
7.5% OHC 163.43
7.5% C.P 163.43
2505.94
2505.90/E
ach
32 Fixing wash basin with hole for pillar traps
Vitreous china flat back wash basin 550x
400mm
Details of cost for 1 no
A. Materials Vitreous china flat back w b Each 1 990.00 990.00
550x400
C.I bracket for wash basin and sinks Pair 1 53.00 53.00
Lead, paint , yarn cement ,sand ,wooden L.S 24.02
plugs, screws
B. Labour charges
Plumber fitter (2nd class) Each 0.33 370.00122.10
Mason (2nd class) Each 0.33 370.00122.10
Mason worker (un skilled) Each 0.67 280.00187.60
A+B 1498.82
C. C.P & O .H. C 15% 1498.82 224.82
Total A+B+C 1723.64
Cost per each 1723.60/
Each

33 Supplying fitting fixing hand wash basin with


bolt , nut,pillar trap
(A) Wash basin with C.I. or MS brackets (Parry Set 1 990.00 990.00
make)
Lead paint yarn cement, sand, wooden L.S. 50.00
plug screw
Labour : Plumber ( 2nd class ) Each 0.33 370.00 122.10
Helper Each 0.33 320.00 105.60
C.P.brass waste No 1 41.99 41.99
Labour for fixing sundries L.S. 6.60
15mm dia connecting pipe No 1 80.00 80.00
Labour for fixing sundries L.S. 6.60
32mm PVC waste with copline No 1 41.99 41.99
Labour for fixing sundries L.S. 6.60
15 mm dia C.P Pillar Cock No 1 637.30 637.30
2088.78
7.5% OHC 156.66
7.5% C.P 156.66
2402.10
(B) Fixing of Pedestal for wash Basin
Pedestal for wash basin Each 1 975.00 975.00
White Cement motar & Screw L.S 60.05
Carriage of Materials & fixing charges L.S 60.24
1095.29
OHC & CP 15% 164.29
1259.58
Total cost for Fixing of Basin & Pedestal (A + B) 3661.68
(2402.10+ 1259.58)
3661.70/E
ach
40 N supplying fitting fixing hand wash basin with bolt ,
nut,pillar trap with pedestal.
Wash basin (Parry make) Each 1 990.00 990.00
Pedestal for wash basin Each 1 975.00 975.00
Lead paint yarn cement, sand, wooden plug screw L.S. 50.00

Labour : Plumber ( 2nd class ) Each 0.33 370.00 122.10


Helper Each 0.33 320.00 105.60
Mulia Each 0.67 280.00 187.60
C.P.brass waste No 1 41.99 41.99
15mm dia connecting pipe No 1 80.00 80.00
32mm PVC waste with copline No 1 41.99 41.99
15 mm dia C.P Pillar Cock No 1 540.00 540.00
3134.28
7.5% OHC 235.07
7.5% C.P 235.07
3604.42
36 N Supplying fitting fixing hand wash basin with bolt ,
nut,pillar trap
(A) Wash basin with C.I. or MS brackets Set 1 990.00 990.00
Lead paint yarn cement, sand, wooden , plug screw L.S. 50.00

Labour : Plumber ( 2nd class ) Each 0.33 370.00 122.10


Helper Each 0.33 320.00 105.60
Mulia Each 0.67 280.00 187.60
C.P.brass waste No 1 41.99 41.99
15mm dia connecting pipe No 1 80.00 80.00
32mm PVC waste with copline No 1 41.99 41.99
15 mm dia C.P Pillar Cock No 1 540.00 540.00
2159.28
7.5% OHC 161.95
7.5% C.P 161.95
2483.17
2483.20/Ea
ch
KITCHEN SINK
34 S/F/F/of kitchen sink ( steel ) 610X510 mm
cap.
Kitchen sink No 1 2950.00 2950.00
C.I. or M.S. brackets Pair 1 53.00 53.00
Cement , Sand for joints L.S. 40.00
Plumber ( fitter) (2nd class) Each 0.22 370.00 81.40
Mason Each 0.33 370.00 122.10
Unskilled labour Each 0.56 280.00 156.80
3403.30
7.5%OHC 255.25
7.5% C.P 255.25
3913.80
3913.80/E
ach
35 S/F/F/of stainless steel sink with C.I bracket
without drain board 610 X 510 mm bowl depth
200mm .Details of cost for one number.

Materials; Stainless steel kitchen sink without Each 1 2950.00 2950.00


drain board 610 X 510mm bowl depth 200mm.

Cement , Sand and grit etc. L.S. 20.14


Carriage of materials L.S. 20.14
40mm dia C.P waste Each 1 55.00 55.00
40mm PVC waste pipe Each 1 27.00 27.00
Labour; Plumber fitter(2nd class) Each 0.22 370.00 81.40
Mason (2nd class) Each 0.33 370.00 122.10
Unskilled labour Each 0.56 280.00 156.80
3432.58
7.5%OHC 257.44
7.5% C.P 257.44
3947.47
3947.50/E
ach
36 S/F/F/of kitchen sink ( steel ) with drain board
(510 x 1040)mm bowel depth 250mm

Kitchen sink No 1 5150.00 5150.00


C.I. or M.S. brackets Pair 1 53.00 53.00
Cement , Sand for joints L.S. 40.00
Carriage of materials L.S 20.14
Plumber ( fitter) (2nd class) Each 0.22 370.00 81.40
Mason Each 0.6 370.00 222.00
Unskilled labour Each 0.82 280.00 229.60
5796.14
7.5%OHC 434.71
7.5% C.P 434.71
6665.56
6665.60/E
ach
GLASS SHELF
37 Supplying & fixing of glass shelve …. etc
complete.
Cost of Glass Shelve Each 1 130.00 130.00
20mm C.P Screw Each 6 3.10 18.60
Wooden Plug Each 2 1.00 2.00
Cost of Cement, sand & Chips LS 2.20
Carpenter 2nd Class Each 0.22 370.00 81.40
Mulia Each 0.56 280.00 156.80
7.5%O.H.C 12.36
7.5% C.P 12.36
415.72
415.70/Ea
ch
38 Supplying & fixing of glass shelve …. etc
complete.
Cost of Glass Shelve (600 x 120)mm Each 1 130.00 130.00
25mm C.P Screw Each 6 3.10 18.60
Wooden Plug Each 2 1.00 2.00
Cost of Cement, sand & Chips LS 2.20
Carpenter 2nd Class Each 0.25 370.00 92.50
Mulia Each 0.25 280.00 70.00
315.30
15% OHC & CP 47.30
362.60
362.60/Ea
ch
PVC LOW LEVEL CISTREN
39 S/f/F of 12.50 liter PVC low level cistren -----
etc complete (parry make)
Cost of Low level cistren PVC(Parry make) Each 1 1195.00 1195.00
Bracket LS 40.00
Seat cover Each 1 315.00 315.00
PVC 15mm connecting Pipe Each 1 65.00 65.00
cement / Gum LS 28.00
Plumber 2nd class Each 0.125 370.00 46.25
Man Mulia Each 0.125 280.00 35.00
1724.25
7.5% OHC 129.32
7.5% C.P 129.32
1982.89
1982.90/E
ach
40 S/f/F of 12.50 liter PVC low level cistren -----
etc complete (parry make)
Cost of Low level cistren PVC(Parry make) Each 1 1275.00 1275.00
Bracket LS 40.00
Seat cover Each 1 315.00 315.00
PVC 15mm connecting Pipe Each 1 65.00 65.00
cement / Gum LS 28.00
Plumber 2nd class Each 0.5 370.00 185.00
Man Mulia Each 0.5 280.00 140.00
2048.00
7.5% OHC 153.60
7.5% C.P 153.60
Labour for fixing of PVC connecting pipe LS 6.60
2361.80
30 N S/f/F of 12.50 liter PVC low level cistren -----
etc complete .
Cost of Low level cistren PVC Each 1 1195.00 1195.00
Bracket LS 40.00
PVC 15mm connecting Pipe Each 1 65.00 65.00
cement / Gum LS 28.00
Plumber 2nd class Each 0.125 370.00 46.25
Man Mulia Each 0.125 280.00 35.00
1409.25
7.5% OHC 105.69
7.5% C.P 105.69
Labour for fixing of PVC connecting pipe LS 6.60
1627.24
1627.20/Ea
ch
SOAP DISH
41 S/F/F of soap dish -- etc complete ( Jaquar )

C.P Screw Each 2 5.00 10.00


Wooden Plug Each 2 1.00 2.00
Sand, Cement And gum 1.10
Cost of Soap dish Each 1 500.00 500.00
Carpenter 2nd class Each 0.12 370.00 44.40
Man Mulia Each 0.112 280.00 31.36
588.86
7.5% OHC 44.16
7.5% C.P 44.16
677.19
677.20/Ea
ch
32 N S/F/F of soap dish -- etc complete ( Jaquar )
Details for one no
Materials: Liquid soap container Each 1 145.00 145.00
25mm CP Screws 100nos 2 112.00 2.24
Wooden plug Each 2 17.40 34.80
Cement, Sand and Chips L.S 6.20
B. Labour Charges
Carepenter (2nd class) Each 0.12 370.00 44.40
Male worker (un skilled) Each 0.12 280.00 33.60
266.24
C. Add C.P & O.H.C 15% 39.94
306.18
306.20/
Each
32N S/F/F of soap dish -- etc complete (ISI)
C.P Screw Each 2 5.00 10.00
Wooden Plug Each 2 1.00 2.00
Sand, Cement And gum 1.10
Cost of Soap dish Each 1 90.00 90.00
Carpenter 2nd class Each 0.12 370.00 44.40
Man Mulia Each 0.112 280.00 31.36
178.86
7.5% OHC 13.41
7.5% C.P 13.41
205.69
205.70/Each

43 URINAL
S/F/F of standing urinal
etc complete (Parry make)
cost of Flat back standing Urinal (parry make) Each 1 565.00 565.00

32mm PVC waste Pipe Each 1 45.00 45.00


12mm PVC connecting Pipe Each 1 65.00 65.00
Wooden block & Screw LS 13.20
Urinal spreader Each 1 250.00 250.00
Plumber 2nd class Each 0.38 370.00 140.60
Mason 2nd Class Each 0.33 370.00 122.10
Man Mulia Each 0.38 280.00 106.40
1307.30
7.5% OHC 98.05
7.5% C.P 98.05
Labour for fixing of PVC connecting pipe LS 6.60
1510.00
1510.00
44 S/F/F of Flat back standing Urinals -----------
etc complete.
cost of Flat back standing Urinal Each 1 805.00 805.00
32mm PVC waste Pipe Each 1 45.00 45.00
12mm PVC connecting Pipe Each 1 65.00 65.00
Wooden block & Screw LS 13.20
Urinal spreader Each 1 250.00 250.00
Plumber 2nd class Each 0.38 370.00 140.60
Man Mulia Each 0.38 280.00 106.40
1425.20
7.5% OHC 106.89
7.5% C.P 106.89
Labour for fixing of PVC connecting pipe LS 6.60
1645.58
1645.60/Ea
ch
SYNTEX TANK
44 Fixing Rotational moulded polyethylene
cylindrical vertical water storage tanks
conforming to IS;12701--1996 including
cutting holes through the tank and fixing
mild steel tubes and fittings and providing
extra sockets and jam nut, fixing of ball
valveetc, including hoisting up to a height of
5 meters above ground level and placing
the tank to the required position etc all
complete as per specification and direction
of EIC.

Material.
2000 Lit capacity double layer cylinderical Liter 2000.00 4.40 8800.00
vertical water storage tank
Lead, paint & yarn LS. 6.60
Pluber (Special) Each 0.50 430.00 215.00
Helper to Plumber Each 0.75 320.00 240.00
Man Mulia Each 5.00 280.00 1400.00
10661.60
Add Contractor perfit & OHC 15% 1599.24
12260.84
12260.80/
Each
45 Fixing Rotational moulded polyethylene
cylindrical vertical water storage tanks
conforming to IS;12701--1996 including
cutting holes through the tank and fixing
mild steel tubes and fittings and providing
extra sockets and jam nut, fixing of ball
valveetc, including hoisting up to a height of
5 meters above ground level and placing
the tank to the required position etc all
complete as per specification and direction
of EIC.

Material.
1000 Lit capacity double layer cylinderical Liter 1000.00 4.40 4400.00
vertical water storage tank
Lead, paint & yarn LS. 6.60
Pluber (Special) Each 0.50 430.00 215.00
Helper to Plumber Each 0.75 320.00 240.00
Man Mulia Each 4.00 280.00 1120.00
5981.60
Add Contractor perfit & OHC 15% 897.24
6878.84
6878.80/
Each
46 Fixing Rotational moulded polyethylene
cylindrical vertical water storage tanks
conforming to IS;12701--1996 including
cutting holes through the tank and fixing
mild steel tubes and fittings and providing
extra sockets and jam nut, fixing of ball
valveetc, including hoisting up to a height of
5 meters above ground level and placing
the tank to the required position etc all
complete as per specification and direction
of EIC.

Material.
As per market rate 1000 Lit capacity Single Liter 1000.00 5.50 5500.00
layer syntex water storage tank
Lead, paint & yarn LS. 6.60
Pluber (Special) Each 0.50 430.00 215.00
Helper to Plumber Each 0.75 320.00 240.00
Man Mulia Each 4.00 280.00 1120.00
7081.60
Add Contractor perfit & OHC 15% 1062.24
8143.84
8143.80/
Each
SINGLE JUNCTION
47 S/f/f of 100mm dia PVC single
junction ------------- etc complete.
Plumbing Mistry 2nd Class Each 0.167 370.00 61.79
Pl. Khalasi Each 0.167 320.00 53.44
Mukia Each 0.167 280.00 46.76
161.99
7.5% OHC 12.15
7.5% C.P 12.15
Gasket Kg 0.257 30.00 7.71
Cement including Lead Qntl 0.014 495.30 6.93
Sand LS 2.00
Sundries T&P LS 1.00
Cost of 100mm dia Single Junction Each 1 209.04 209.04
412.97
413.00/eac
h
48 N S/f/f of 110mm dia PVC single
junction ------------- etc complete.
Single Tee with door
Details of cost for 1 Tee
A. Materials
UPVC single equal Tee (with door) 110X 110X Each 1 180.00 180.00
110
110mm dia UPVC pipe (working pressure 4kg / Each 3 20.00 60.00
cm2)Rubber seal ring
B. Adhesive , Carriage of material rubber washer L.S 20.07
etc
(A+B) 260.07
C. Add contractor's profit & over head charges 15% of 260.07 39.01

Total (a+ b+c ) 299.08


Cost per each 299.10
SHOWER ROSE
49 Fixing Chromium Plated Brass Shower rose with

15mm or 20mm inlet including polishing all


complete
as per specification. (Shower set)
Materials;
Shower rose C.P brass for 15mm to 20mm inlet Each 1 100.00 100.00
100
mm dia
b) Labour
Plumber Fitter (Spl) Each 0.07 430.00 30.10
Helper to plumber Each 0.07 320.00 22.40
a+b 152.50
c) Add contractor profit& over head charges 15% 22.88

175.38
175.40/E
ach
PVC COWL
50 N S/F/F of 100mm dia PVC Cowal --------
etc complete.
Plumbing mistry 2nd Class Each 0.083 370.00 30.71
Pl. Khalasi Each 0.167 320.00 53.44
84.15
7.5% O.H.C 6.31
7.5% C.P 6.31
Painting, sundries T&P LS 1.00
cost of 100mm dia PVC Cowal Each 1 78.00 78.00
259.92
259.90/Ea
ch
PVC HILLREST BEND & DOOR BEND
51 S/F/F 100mm dia PVC Hill rest bend
Pl. Mistry Each 0.167 370.00 61.79
Pl. khalasi Each 0.167 320.00 53.44
Mulia Each 0.167 280.00 46.76
161.99
7.5% O.H.C 12.15
7.5% C.P 12.15
186.29
gasket Kg 0.257 30.00 7.71
Cement Qntl 0.014 495.30 6.93
Cost of soaking arround L.S. 2.00
Sundries T&P L.S. 1.00
sand L.S. 1.00
Cost of 100mm dia Hill rest bend 188.00
392.93
392.90/Ea
ch
52 N S/F/F 110mm dia PVC Hill rest bend N
Details of cost for 1 bend
A. Materials
UPVC bend 87.5 110 mm bend Each 1 95.00 95.00
110 mm dia UPVC pipe ( Working pressure 4 kg / Each 1 20.00 20.00
cm2 )Rubber (seal ) ring
Adhesive etc L.S 4.07
B. Carriage and fixing charges L.S 16.08
(A+ B) 135.15
C. Add contractor 's profit & over head charges 15% of 135.15 20.27

155.42
Say
155.40
53 S/F/F 100mm dia PVC door bend
Pl. Khalasi Each 0.125 320.00 40.00
Pl. Mistry each 0.125 370.00 46.25
Mulia Each 0.25 280.00 70.00
156.25
7.5% O.H.C. 11.72
7.5% C.P 11.72
Gasket Kg 0.1285 30.00 3.86
Cement Qntl 0.007 495.30 3.47
Sand L.S. 0.30
Cost of soaking arround 1.00
Earth work, painting two coat 1.50
Cost of door bend Each 1 110.00 110.00
299.81
299.80/Ea
ch
54 S/F of 110mm PVC Bend rain water pipe
110mm Bend Each 1.00 95.00 95.00
Rubber seal ring Each 1.00 20.00 20.00
Adhesive L.S 4.07
Carriage and fixing charges (S.R-2013- Rate
/Each Rs 16.08)
Carriage & fixing rate in 2016 excess 33.40% L.S 21.45
than S.R-2013
140.52
OHC & CP 15% 21.08
161.60
WASTE PIPE
55 S/F/F/ of waste pipe ( Data for 10 nos )
Plumber (2nd class) Each 0.83 370.00 307.10
Unskilled Each 1 280.00 280.00
587.10
7.5% O.H.C 44.03
7.5% C.P 44.03
1% watering charges 5.87
8% sundries T&P 46.97
728.00
Rate per 1 no 72.80
Add cost of waste pipe 67.00
139.80
139.80/Ea
ch
56 S/F/F/ of waste pipe ( Data for 10 mtr )
Add cost of waste pipe Mtr 10 124.96 1249.60
Rubber seal ring Each 10 20.00 200.00
Adhesive etc. L.S 12.00
Scaffolding L.S 27.70
Plumber (2nd class) Each 0.23 370.00 85.10
Helper to Plumber Each 0.11 320.00 35.20
Un-Skilled Each 0.45 280.00 126.00
1735.60
7.5% O.H.C 130.17
7.5% C.P 130.17
1995.94
Rate per 1.00Mtr. 199.59
199.60/Mtr
CPVC PIPE
57 Providing and fixing Chlorinated Polyvinyl
Chloride (CPVC) Pipes conforming to IS 15778,
having thermal stability for hot & cold water
supply including all CPVC plain & brass threaded
fittings. Thios includes jointing of pipes & fittings
with one ster CPVC solvent cement , trenching
,refilling &testing of joints complete as per
direction of EIC.

20 mm nominal Outer dia pipes


Details of cost for 10 meter
Materials
A. Chlorinated Polyvinyl -Chloride (CPVC) pipe Mtr 10 63.00 630.00
20mm outer dia
Add 30% for fitting and wastage etc. 189.00
B. Labour
Plumber Fitter (S) Each 0.08 430.00 34.4
Male Worker (unskilled) Each 0.16 280.00 44.80
Trenching & refilling etc.
Male worker (un-skilled)A+B Each 1.32 280.00 369.6
1267.80
C.Add C.P & O.H.C Total (a+b+c) 15% 1267.80 190.17
1457.97
Rate per meter is 1457.97/10=145.80 145.80
145.80/E
ach
58 Supplying & laying (tolevel or slopes) and jointing
with rubber rings pre-cast reinforced socket and
spigot concrete pipes class-N.P-3 conforming to
IS:458-2003 suitable for rubber ring roll on joint
of the following internal diameter as per
specification complete.

900 mm diameter.
Materials:
900mm concrete Single socket
Detail of cost for 10 joints. (10 x 2.35)= 23.50 Mtr

A. Labour for laying (same as C.I Pipe)


Plumber (Spl) Each 0.17 430.00 44.20
Helper to Plumber / Fitter Each 0.17 320.00 54.40
Male worker Each 1.33 280.00 372.40
471.00
For 1.00 Qntl (471.00/5.14) = 91.63
B. Materials.
900mm concrete Single Socket Pipe Class N.P-3 Mtr 23.50 2880.00 67680.00

Weight of 10 pices of Pipe. Qntl 209.63 64.51 13523.23


(23.50 x 2096.34 / 2.35 = 892.059 Kg
892.059 x 23.50 = 20963.40 Kg
Say 209.63 Qntl.

Jointing with rubber ring


900mm dia rubber ring for 10 joints Each 10 480.00 4800.00
Labour charges
Plumber fitter (Spl) Each 5.13 430.00 2205.90
Helper to plumber or fitter Each 5.13 320.00 1641.60
Male worker Each 19.88 280.00 5566.40
95417.13
C. OHC & CP (7.5% + 7.5%) =15% 14312.57
109729.70
Rate per 1.00 Mtr 4669.35
Lead for 1.00 Mtr Pipe Mtr 1 560.76 560.76
5230.11
5230.10/Mt
Say r
59 Laying in trenches (to level or slope) &
jointing with provision of stiff mixture in
100mm dia PVC pipe with adhesive
Data for 10.00 Mtr.
(A) Materias
110mm dia PVC pipe (Schedule-40) Mtr 10.00 277.55 2775.50
(B) Labour for laying
Plumber (Spl) Each 0.18 430.00 77.40
Male worker Each 0.35 280.00 98.00
© Labour for jointing & fitting
Plumber (Spl) Each 0.31 430.00 133.30
Helper to Plumber Each 1.33 320.00 425.60
Male worker Each 0.18 280.00 50.40
(D) Jointing materials
Cost of solvent cement (56gm or 0.056 Kg) Kg 0.06 171.00 9.58

3569.78
Add 15% for OHC & CP 535.47
4105.24
Rate per 1.00 Mtr 410.52
Add for road cost of Pipe(1.00 Mtr) Mtr 1 1.65 1.65
(Considering 350 nos pipe carry per
truck i.e 2100 Mtr)

412.17
412.20/M
Say tr
60 Laying in trenches (to level or slope) &
jointing with provision of stiff mixture in
160mm dia PVC pipe with adhesive
Data for 10.00 Mtr.
(A) Materias
160mm dia PVC pipe (Schedule-40) Mtr 10.00 489.23 4892.30
(B) Labour for laying
Plumber (Spl) Each 0.25 430.00 107.50
Male worker Each 0.50 280.00 140.00
© Labour for jointing & fitting
Plumber (Spl) Each 0.46 430.00 197.80
Helper to Plumber Each 1.92 320.00 614.40
Male worker Each 0.25 280.00 70.00
(D) Jointing materials
Cost of solvent cement (133gm or 0.133 Kg) Kg 0.13 171.00 22.74

6044.74
Add 15% for OHC & CP 906.71
6951.45
Rate per 1.00 Mtr 695.15
Add for road cost of Pipe(1.00 Mtr) Mtr 1 3.00 3.00
(Considering 192 nos pipe carry per
truck i.e 1150 Mtr)
698.15
698.15/M
tr
PILLAR COCK
61 Fixing pillar taps ccapstan head screw down high
pressure lettered "Hot" and 'cold 'with long
screws , shanks and back nuts of the following
nominal bore as per specification.

Details cost for 1 No


Materials : 15 mm dia cp pillar cock Each 1 540.00 540.00
B. Carriage of materials and fixing charges L.S 14.14
554.14
C. Add C.p & O.h.C 15 % 83.12
637.26
637.25/E
ach
F.W VALVE
62 S/F/F of 50mm dia Brass Full-way valve-----
etc complete.
Data for 10 nos
Plumber (2nd class) Each 0.75 370.00 277.50
helper Each 0.75 320.00 240.00
517.50
7.5% O.H.C 38.81
7.5% C.P 38.81
2% jointing materials 10.35
1% watering charges 5.18
3% sundries T&P 15.53
626.18
Rate per 1 no 62.62
Add cost of valve 2243.00
2305.62
2305.60/E
ach
63 Fixing brass or Gun metal fullway valve
conforming to IS- 781 -1995 of the following
nominal sizes with wheel as per
specification complete.
25mm diameter
Details for 10 nos of Brass or Gun metal
Fullway valves
Materials .25mm dia brass or gun metal full Each 10 548.00 5480.00
way valve= 10 nos
B. Labour for laying . Plumber fitter (s)(2nd Each 0.5 370.00 185.00
class)
Helper to plumber /fitter Each 0.5 320.00 160.00
Jointing materials 2% 345.00 6.90
(a+b) 5831.90
C. Add CP & O.H.C 15% 5831.90 874.79
Total (a+b+c) 6706.69
Rate per each is 6706.69/10= 670.67
say 670.70/E
ach
64 S/F/F of 25mm Brass Full-way valve ….. etc
complete.
Data for 10 Nos
Plumber 2nd Class Each 0.5 370.00 185.00
Helper Each 0.5 320.00 160.00
345.00
10% Scaffolding 34.50
Cost of F.W Valve Each 10 750.00 7500.00
7879.50
7.5% OHC 590.96
7.5% C.P 590.96
9061.43
Rate for one No 906.14
906.10/Ea
ch
65 S/F/F of 25mm Brass Ball valve ….. etc
complete.(SHAKTI MAKE)
Data for 10 Nos
Plumber 2nd Class Each 0.5 370.00 185.00
Helper Each 0.5 320.00 160.00
345.00
Cost of Brass Ball Valve Each 10 1078.25 10782.50
11127.50
7.5% OHC 834.56
7.5% C.P 834.56
12796.63
Rate for one No 1279.66
1279.70/
Each
66 S/F/F of 20mm Brass Ball valve ….. etc
complete.(SHAKTI MAKE)
Data for 10 Nos
Plumber 2nd Class Each 0.5 370.00 185.00
Helper Each 0.5 320.00 160.00
345.00
Cost of Brass Ball Valve Each 10 649.25 6492.50
6837.50
7.5% OHC 512.81
7.5% C.P 512.81
7863.13
Rate for one No 786.31
786.30/E
ach
67 B S/F/F of 40mm Brass Full-way valve ….. etc
complete.
Data for 10 Nos
40mm dia Brass or Gun metal Fullway valve Each 10 1080.00 10800.00
Plumber 2nd Class Each 0.75 370.00 277.50
Helper Each 0.75 320.00 240.00
Jointing materials 2% 517.50 10.35
11327.85
7.5% OHC 849.59
7.5% C.P 849.59
13027.03
Rate for one No 1302.70
1302.70/E
ach
68 B S/F/F of 25mm Brass Full-way valve ….. etc
complete.
Data for 10 Nos
Plumber 2nd Class Each 0.5 370.00 185.00
Helper Each 0.5 320.00 160.00
345.00
Jointing materials 2% 2% 6.90
Cost of F.W Valve Each 10 548.00 5480.00
5831.90
7.5% OHC 437.39
7.5% C.P 437.39
6706.69
Rate for one No 670.67
670.70/Ea
ch
69 B S/F/F of 20mm Brass Full-way valve ….. etc
complete.
Data for 10 Nos
Cost of F.W Valve Each 10 360.00 3600.00
Plumber 2nd Class Each 0.5 370.00 185.00
Helper Each 0.5 320.00 160.00
Jointing materials 2% 2% 345.00 6.90
3951.90
7.5% OHC 296.39
7.5% C.P 296.39
4544.69
Rate for one No 454.47
454.50/E
ach

STOP COCK
70 Supplying fitting fixing 15mm dia C.P stop
cock (Brass Concealed Stop Cock)
Data for 10 nos
Plumber(2nd class) Each 0.5 370.00 185.00
Helper Each 0.5 320.00 160.00
345.00
1% watering 3.45
2% jointing materials 6.90
355.35
7.5% OHC 26.65
7.5% C.P 26.65
764.00
Rate per 1 no 76.40
15mm dia CP Brass Concealed Stop Cock 711.10
787.50
say Rs. 787.50/Ea
ch
71 S/F/F of 15mm stop cock (Jaguar)
15mm diameter
Details for 10 nos of Brass screw down stop
cocks
Materials:15mm dia C.P stop cock Each 10 600.00 6000.00
Labour: Plumber fitter (2nd class) Each 0.5 370.00 185.00
Helper to plumber /fitter Each 0.5 320.00 160.00
Jointing materials 2% 345.00 6.90
6351.90
Add C.P & O.H.C 15% 952.79
7304.69
Rate per each is 7304.69/10 730.47
730.50/Ea
ch
72 S/F/F of 15mm dia C.P angular stop cock
(Jaguar)
15mm diameter
Details for 10 nos of Brass screw down stop
cocks
Materials:15mm dia C.P angular stop cock Each 10 480.00 4800.00
Labour: Plumber fitter (2nd class) Each 0.5 370.00 185.00
Helper to plumber /fitter Each 0.5 320.00 160.00
Jointing materials 2% 345.00 6.90
5151.90
Add C.P & O.H.C 15% 772.79
5924.69
Rate per each is 5924.69/10 592.47
592.50/Ea
ch
BIB COCK
73 Supplying, fitting & fixing of 15mm C.P Bib
Cock---- etc complete.Short Body Bib Cock)
(Jaguar)
Data for 10 Nos
Plumber 2nd Class Each 0.33 370.00 122.10
Helper Each 0.33 320.00 105.60
227.70
jointing materials 2 % 2% 227.70 4.55
232.25
Cost of 15mm Short body C.P Bib Cock Each 10 520.00 5200.00
5432.25
Add C.P & O.H.C 15% 814.84
6247.09
Rate per 1 Nos 624.71
624.70/Ea
ch

74 Supplying, fitting & fixing of 15mm PVC Bib


Cock---- etc complete.
Data for 10 Nos
Plumber 2nd Class Each 0.33 370.00 122.10
Helper Each 0.33 320.00 105.60
227.70
jointing materials 2 % 2% 227.70 4.55
232.25
Cost of 15mm Short body PVC Bib Cock Each 10 80.00 800.00
1032.25
Add C.P & O.H.C 15% 154.84
1187.09
Rate per 1 Nos 118.71
118.70/Eac
h

75 Supplying, fitting & fixing of 15mm C.P Bib


Cock---- etc complete.( Short Body Bib Cock)

Data for 10 Nos


Plumber 2nd Class Each 0.33 370.00 122.10
Helper Each 0.33 320.00 105.60
227.70
1% watering 2.28
10% Scaffolding 22.77
252.75
7.5% OHC 18.96
7.5% C.P 18.96
290.66
Rate per 1 Nos 29.07
Cost of 15mm long body C.P Bib Cock Each 1 611.90 611.90
640.97
641.00/Ea
ch
76 Supplying, fitting & fixing of 15mm C.P Bib
Cock---- etc complete.Long Body Bib Cock)
Data for 10 Nos
Plumber 2nd Class Each 0.33 370.00 122.10
Helper Each 0.33 320.00 105.60
227.70
1% watering 2.28
10% Scaffolding 22.77
252.75
7.5% OHC 18.96
7.5% C.P 18.96
290.66
Rate per 1 Nos 29.07
Cost of 15mm long body C.P Bib Cock Each 1 611.90 611.90
640.97
641.00
77 Fixing of Brass screw down Bib cocks
(Taps) npolished bright conforming to IS 781
- 1995 of the following nominal sizes as per
specification complete.
20mm diameter
Details for 10 nos of Brass screw down Bib
cocks
A. Materials . 20mm dia brass screw down Each 10 215.00 2150.00
bib cock=10 nos
B. Labour for laying . Plumber fitter (s)(2nd Each 0.33 370.00 122.10
class)
Helper to plumber / fitter Each 0.33 320.00 105.60
Jointing materials 2% 227.70 4.55
(a+b) 2382.25
C. Add CP & O.H.C 15% 2382.25 357.34
Total (a+b+c) 2739.59
Rate per each is 2739.59/10= 273.96
274.00/E
ach
78 Fixing of Brass Push cock of following
nominal sizes as per specification complete.

20mm dia Brass push cock


Details for 10 nos of Brass push cocks
A. Materials
20mm dia Brass push cock (Plaza make)=10 nos Each 10 450.00 4500.00

B. Labour: Plumber fitter(S) (2nd class) Each 0.33 370.00 122.10


Helper to plumber / fitter Each 0.33 320.00 105.60
Jointing material 2% 227.70 4.55
(A+B) 4732.25
C. Add C.P & O.H.C 15% 709.84
Total (A+B+C) 5442.09
Rate per each is 5442.09/10= 544.21
544.20/E
ach
79 Fixing of Brass Push cock of following
nominal sizes as per specification complete.

15mm dia Brass push cock


Details for 10 nos of Brass push cocks
A. Materials
15mm dia Brass push cock (Plaza make)=10 nos Each 10 375.00 3750.00

B. Labour: Plumber fitter(S) (2nd class) Each 0.33 370.00 122.10


Helper to plumber / fitter Each 0.33 320.00 105.60
Jointing material 2% 227.70 4.55
(A+B) 3982.25
C. Add C.P & O.H.C 15% 597.34
Total (A+B+C) 4579.59
Rate per each is 4509.37/10= 457.96
458.00/E
ach
PVC BALL COCK
80 High pressure/ Low pressure with copper or
PVC floats of the 25mm dia nominal bore
PVc Ball cock.

Materials
25mm dia nominal bore PVC Ball cock Each 1 550.00 550.00
Labour: Plumber Fitter (S) Each 0.125 430.00 53.75
Plumber helper Each 0.125 320.00 40.00
Jointing materials 2% on labour charges 2% 93.75 1.88

645.63
15% O.H.C & C.P 96.84
742.47
742.50/E
ach
81 N S/F/F of 20mm Brass Ball valve ….. etc complete
Data for 10 Nos
Plumber fitter (2nd class) Each 0.125 370.00 46.25
Helper Each 0.125 320.00 40.00
86.25
Cost of Brass Ball Valve (as per prevailing market rate) Each 10 649.25 6492.50

6578.75
7.5% OHC 493.41
7.5% C.P 493.41
7565.56
Rate for one No 756.56
756.60/Each

C.I GRATING
81 Supplying, fitting & fixing of C.I grating
including labour & other materials.
Data for one No.
C.I grating Each 1.00 15.00 15.00
Labour charges for for fixing L.S 3.00
18.00
15% OHC & CP 2.70
20.70
82 Supplying Fitting Fixing of C.I wall Grating L.S 80.00

43 S/f/f of Floor Trap….. Etc Complete.


Plumbing Mistry 2nd Class Each 0.167 370.00 61.79
Mulia Each 0.167 280.00 46.76
108.55
7.5% OHC 8.14
7.5% C.P 8.14
Cost of Floor trap Each 1 80.00 80.00
204.83
204.80/Each

83 PCC (1:3:6) with 40mm size hard granite


chips in the following type of hunching
around sewerage line for 4" dia PVC pipe.

Consider 20.0mtr length(for 4" pipe)


20X 0.25 X0.25 = 1.25cum
Less for pipe
3.14/4 X 0.10 X 0.10 x20 .00=0.16
Total = 1.25- 0.16 =1.09 cum Cum 1.09 4602.50 5016.73
Rate for 1.00mtr pipe is5016.73/20=250.80 250.84
84 Construction of RCC circular man hole
chamber of inside dia 900mm with 600mm
depth

(i) Filling in foundation with river sand at


the site including cost, conveyance, taxes
royalities of materials , cost of all labour and
T&P required for the work etc complete as
per direction of EIC.

3.14/4X 1.40 X1.40 X 0.075 =0.12 Cum Cum 0.12 642.05 77.05
(i) PCC of Prop (1:3:6) in foundation using
4cm size hard crusher broken granite metal
of approved quality from approved quarry
including lowering, laying concrete to
required levels laid in layers not exceeding
150mm thick including cost , conveyance,
taxes royalities of materials , cost of all
labour and T&P required for the work etc
complete as per direction of EIC.

3.14 /4 X 1.40 X1.40 X 0.10=0.15 cum Cum 0.15 4602.5 690.375


iii) Rcc work of M-20 grade base with 20mm
and down grade hard crusher broken
granite stone chipsincluding hoisting and
laying concrete ,watering and curing for
thre weeks centering and shuttering and
finishing th exposed surfaces smooth,
providing beads or grooves where
necessary including cost , conveyance,
royality, taxes of all materials, dismantling
the centering shuttering work after the
period as specified by EIC and cost of all
labour, T&P required for the work complete
in all respect, excluding cost of
reinforcement , binding wires and labour
charges for bending , binding and tying the
grills as directed by EIc.

3.14/4 X1.20 x1.20 X .15= 0.17 cum Cum 0.17 5085.25 864.4925
iv) Rcc work of M-20 grade wall with 20mm
and down grade hard crusher broken
granite stone chipsincluding hoisting and
laying concrete ,watering and curing for
thre weeks centering and shuttering and
finishing th exposed surfaces smooth,
providing beads or grooves where
necessary including cost , conveyance,
royality, taxes of all materials, dismantling
the centering shuttering work after the
period as specified by EIC and cost of all
labour, T&P required for the work complete
in all respect, excluding cost of
reinforcement , binding wires and labour
charges for bending , binding and tying the
grills as directed by EIc.

3.14/4 X (1.20X 1.20) -( 0.90X 0.90) X0.60 Cum 0.3 9607.9 2882.37
=0.30 cum
v) Rcc work of M-20 grade Roof Slab with
20mm and down grade hard crusher broken
granite stone chipsincluding hoisting and
laying concrete ,watering and curing for
thre weeks centering and shuttering and
finishing th exposed surfaces smooth,
providing beads or grooves where
necessary including cost , conveyance,
royality, taxes of all materials, dismantling
the centering shuttering work after the
period as specified by EIC and cost of all
labour, T&P required for the work complete
in all respect, excluding cost of
reinforcement , binding wires and labour
charges for bending , binding and tying the
grills as directed by EIc.

3.14 / 4 X 1.20 X 1.20 X .10=0.11 cum Cum 0.11 9567.3 1052.40


vi) PCC of Prop (1:2:4) in floor using 20mm
down graded chips for approved
3.14 /4 X 0.90 X 0.90 x ( 0.05 + 0.15)/2= Cum 0.06 5892.7 353.56
0.06 cum
vii ) Supplying HYSD bar of approved quality

10mm dia bar (main)


2 X 9 X 2.45 = 44.10 Mtr @ 0.62 kg /Mtr=
27.34 kg
8mm dia bar (binder )
Cover slab
2 X 9 X 1.10 = 19.80 Mtr
(22.61 +19.80)= 42.41 mtr @ 0.40 kg/ mtr=
16.96 kg
27.34 +16.96 = 44.30kg Say 0.44 Qntl Qntl 0.44 6236.65 2744.13

Vii)6mm thick cement plaster (1:4) with


neat cement punning for finished smooth to
inside / outside surface of brick walls in

Base= 3.14/4 X 0.90 X0.90 = 0.64 sqm


Wall = 3.14/4 X0.90 x0.60 = 1.70Sqm
(0.64 +1.70) = 2.34 SqmSay 2.35 Sqm Sqm 2.35 171.6 403.26
Total Rs= 9067.63

12) Extra over for every additional depth of


0.15 mtr or part thereof beyound the intial
lift of 0.90 mtr ht

Cost for 0.90 mtr Height


A0 RCC wall
3.14/4 X (1.20X 1.20) -(0.90X0.90)X 0.90 = Cum 0.44 9607.9 4227.48
0.44 cum
B) Hysd M.S Rod
10mm dia bar main
2 X9 X 0.85 mtr= 15.30 Mtr @ 0.62Kg /mtr=
9.45 Kg
8mm dia rod
6 X 3.14 X 1.20 =22.60 Mtr@ 0.40 Kg
/mtr=9.04 kg
9.45 +9.04 =18.49 Kgor 0.18 qntl Qntl 0.18 6236.65 1122.60
6mm thick C.P with CM (1:4) with neat
cement punning
inside = 3.14 X 0.90 x 0.90 =2.54 sqm Sqm 2.54 171.6 435.86
5785.94
Cost for 0.15 mtr height = 964.3228
5785.94/6=964.30
964.30/E
ach

10) Repair of RCC drain during renovation of


sewerage system.
considering 10.00 mtr length of drain of size
(0.30X0.30) Mtr
(i) PCC of Prop (1:3:6) in foundation using
4cm size hard crusher broken granite metal
of approved quality from approved quarry
including lowering, laying concrete to
required levels laid in layers not exceeding
150mm thick including cost , conveyance,
taxes royalities of materials , cost of all
labour and T&P required for the work etc
complete as per direction of EIC.

10.00 X 0.60 x 0.10 mt= 0.60 cum Cum 0.6 4602.50 2761.5
ii) Rcc work of M-20 grade base with 20mm
and down grade hard crusher broken
granite stone chipsincluding hoisting and
laying concrete ,watering and curing for
thre weeks centering and shuttering and
finishing th exposed surfaces smooth,
providing beads or grooves where
necessary including cost , conveyance,
royality, taxes of all materials, dismantling
the centering shuttering work after the
period as specified by EIC and cost of all
labour, T&P required for the work complete
in all respect, excluding cost of
reinforcement , binding wires and labour
charges for bending , binding and tying the
grills as directed by EIc.

Base= 10.00 X 0.50 x 0.10 = 0.50 Cum Cum 0.5 5085.25 2542.625
iii) Rcc work of M-20 grade wall with 20mm
and down grade hard crusher broken
granite stone chipsincluding hoisting and
laying concrete ,watering and curing for
thre weeks centering and shuttering and
finishing th exposed surfaces smooth,
providing beads or grooves where
necessary including cost , conveyance,
royality, taxes of all materials, dismantling
the centering shuttering work after the
period as specified by EIC and cost of all
labour, T&P required for the work complete
in all respect, excluding cost of
reinforcement , binding wires and labour
charges for bending , binding and tying the
grills as directed by EIc.

RCC wall= 2 X10.00 X .10 X 0.30= 0.60 Cum Cum 0.6 9607.9 5764.74
11068.87
Rateper 1.00 Mtr = 11193.25/10 1106.887

50mm diameter
Details of cost for 10 metres
a. Materials
50mm dia G.I Pipe (TATA Medium) Mtr 10.00 376.00 3760.00
Tube fittings and wastages 2% 75.20
White lead,hemp oil etc 1% 37.60
b. Labour for laying
Plumber Fitter(S) Each 0.16 430.00 68.80
Male worker Each 0.33 280.00 92.40
(a+b) 4034.00
c. Add Contractor's Profit & Overhead 605.10
charges 15%
Total (a+b+c) 4639.10
Rate per metre is 463.91
Add conveyance , Rayality & tollage Qntl 0.062 64.51 4.00
467.91
467.90/Mt
r

25mm diameter
Details of cost for 10 metres
a. Materials
25 mm dia G.I Pipe (TATA medium) Mtr 10.00 227.00 2270.00
Tube fittings and wastages 2% 45.40
White lead,hemp oil etc 1% 22.70
b. Labour for laying
Plumber Fitter(S) Each 0.12 430.00 51.60
Male worker Each 0.25 280.00 70.00
(a+b) 2459.70
c. Add Contractor's Profit & Overhead 368.96
charges 15%
Total (a+b+c) 2828.66
Rate per metre is 282.87
Add conveyance , Rayality & tollage Qntl 0.03 64.51 1.94
284.80
284.80/Mt
r
221 Construction of Inspection Chamber with
RCC top slab in (1:2:4) mix, foundation
concrete (1:4:8), inside plaster 12mm th.
With cement motar (1:3) finished with neat
cement punning, 12mm thick outside plaster
(1:3), brick work with K.B bricks having
crushing strength not less than 75kg/cmsqr
with domensioral tolerance plus minous 8%
in cement motar (1:6), cement concrete
(1:2:4) finished smooth using 12mm sizr
H.G chips, earth work in excavation in all
kinds of soil and refilling the cavity around
the chamber complete as per specification.

A Plain Inspection chamber inside size


900mmx800mm and 450mm deep -Type A

i With cast iron Manhole cover and frame


(light duty rectangular type)450mmx610mm
internal dimension total weight of cover and
frame to be not less than 38 kg (weight of
cover 23 kg and weight of frame 15kg)

Details of cost for one Manhole


a. Earthwork in excavation in all kinds of soil 100 cum 1.011 17574.20 177.68
(Excluding CP
&OHC)1.55mx1.45mx0.45m=1.011
b. Cement concrete (1:4:8) using 40mm size Cum 0.224 3833.52 858.71
hard granite metal on bed (Excluding CP &
OHC) 1.55mx 1.45mx 0.10=0.450

c. Brick work with K.B bricks Cum 0.385 3824.99 1472.62


(25cmx12cmx8cm) having crushing strength
not less than 75kg/ cm sqr with dimensional
tolerence plus minous 8% in cement mortar
(1:6) in F&P (Excluding CP& OHC)
4.40mx0.25mx0.35m=0.385

d Cement concrete (1:2:4) using 12mm size


H.G chips for benching (Excluding
CP&OHC)
2x0.90mx0.80m/2x(0.30m+0.20m)/2 =
0.180 less
pipe=1x0.90mx3.14/4x0.15mx0.15m=
0.016

0.164 Cum 0.164 5274.26 864.98


e 12mm thick cement plaster (1:4) with neat
cement punning to inside face (Excluding
CP &OHC) 3.40m x0.05m =
0.17 2x1/2x
0.80mx0.10m= 0.08

0.25 Sqm 0.25 131.41 32.85


f. 12mm thick cement plaster (1:4) to outside Sqm 1.89 124.86 235.99
(Excluding CP &OHC)
5.40m x 0.35m
=1.89
g. R.C.C(1:2:4)using 12mm size H.G chips for
slab (Excluding CP & OHC)
1.40m x1.30m x0.15m
= 0.182 less cover=0.61m
x0.455m x0.15 = (-) 0.042
Cum 0.14 5274.26 738.40
=0.140
h. Rigid and smooth centering and shuttering Sqm 1.411 402.66 568.15
for Rcc works including false work and
dismantling them after casting including cost
of materials complete.(Excluding CP& OHC)
Inside
area = 0.90m x 0.80m = 0.720
less cover =0.61m x0.455m = ( -) 0.278
= 0.442
shuttering = 5.40m x0.15m =
0.810 (0.61m + 0.45m )0.15m
= 0.159
=
1.411

i. M.S Reinforcement bars 8mm dia tor steel Qntl 0.17 5432.00 923.44
10 cm c/c bothways in slab including
cutting, bending and binding and tying the
grills including cost of binding wire
(Excluding CP & OHC) 0.17Qntl.
j. Extra labour for making channel
Mason (Special) Each 0.06 430.00 25.80
Mason (2nd class) Each 0.06 370.00 22.20
5920.81

II With RCC precast cover (1:2:4) with 12mm 5676.84


size H.G chips of cover 810mm x655 mm
and 100 mm thick to be provided over a
clear opening of 455mmx 610mm in the
man hole slab. Details ofcost one manhole
with cast iron Man hole cover (Excluding
cost of cover ) -- ratesame as in item
No.4.2.1 (A) (i) from a to j

a. Extra cost of reinforced cement concrete Cum 0.028 5274.26 147.68


1:2;4 with 12mm h.g chips for slab
0.61x0.455x0.10 =0.028
b. M.S reinforcement bars 10mm dia tor steel Qntl 0.053 5432.00 287.90
10cm c/c bothways in slab including cutting,
bending, binding and tying the grills
including cost of binding wire 0.81m x
0.655 x 0.10m = 0.053
6112.42
c. Add CP & OHC 15% 916.86
7029.28
7029.30/
Each
222 Constructing of leaching pool within RCC nanda

(i) Earth work excavation in all kinds of soil 22/7 X


(1.0) 2 X
1.5
=4.71cum

242.50 1142.18
(ii) Supplying of RCC cover slab of size (3'-0") dia
including cost of RCC ring , lead to the site ,
loading and unloading … etc.complete.

for 1 No L.S Rs. 2125.00


425.00 X
5 Nos =
(iii) Supplying of RCC cover slab of size (3'-6") dia
including cost of Slab , lead to the site , loading
and unloading … etc.complete.
For 1 no L.S Rs. 280.00
280.00X
1no =
(iv) Labour for fitting and fixing of RCC ring with L.S 50.00
cover slab .
(v) Sand filling 3.14 X
( 0.90) 2
X 0.30 =
0.76
Rs. 487.96
642.05
(vi) Supplying and fitting , fixing of brick khoa 3.14 X
(0.90) 2 X
0.60 =
1.52
Rs. 1662.88
1094.00
5748.01
5748.00/
Each
Supplying all for constructing Man-hole
chaber -------------- etc complete.
Earth work Cum 4.59 242.50 1113.08
C.C (1:3:6) metal Cum 0.68 4602.50 3129.70
C.C (1:2:4) Chips Cum 0.13 5892.70 766.05
Brick Work Cum 1.08 4267.30 4608.68
12mm C.P (1:4) with neat cement punning Sqm 4.65 149.30 694.25
Cement rule pointing (1:3) Sqm 5.2 148.40 771.68
Extra Mason 2nd class Each 0.5 370.00 185.00
Man Mulia Each 0.5 280.00 140.00
11408.44
7.5% OHC 855.63
7.5% C.P 855.63
RCC slab Cum 0.21 9567.30 2009.13
M.S Rod Mt 0.02 62366.40 1247.33
M.S. Step iron Each 1 137.30 137.30
16513.46
16513.50/
Each
S/F/F of RCC ring in position of 1.37mtr dia
including all labour , conveyance,
necessary mortar for joint . Etc.

Cost of RCC ring (1.37mtr) dia . (as per Each 1 550.00 550.00
market rate)
Labour for unloading and laying Each 1 50.00 50.00
600.00
15 % C.P & O.H.C 90.00
690.00
Add lead conveyance L.S 200.00
890.00
S/F/F of RCC cover slab over RCC ring of
1.37 mtr dia including all labour,
conveyance, necessary mortar.

Cost of RCC cover slab for RCC ring 0f1.37 Each 1 800.00 800.00
mtr (As per market Rate)
Labour for unloading and laying Each 1 50.00 50.00
850.00
15 % C.P & O.H.C 127.50
977.50
Add lead conveyance LS 200.00
1177.50

Das könnte Ihnen auch gefallen