Beruflich Dokumente
Kultur Dokumente
H
MATERIA
LS
G.I PIPE
1 S/F/F of 40mm dia G.I. pipe ------- etc
Complete.
Data for 30.48 Mtr or 100'-0".
E/W excavation of Pipe line trench in all kinds of
soil.
100.00 x 1'-6' x 2'-0"= 300.00 Cft or 8.49 Cum Cum 8.49 242.50 2058.83
Earth filling with excavated earth after testing the Cum 8.49 162.50 1379.63
pipe line
Cost Materials 40mm G.I. Pipe for 30.48 Rmt 30.48 236.00 7193.28
Mtr
2% extra of cost of pipe towards cost of wastage 143.87
& fitting
labour Pl. Mistry (Spl) Each 0.33 430.00 141.90
Pl. Khalasi Each 0.66 320.00 211.20
7.5% OHC 11128.70
7.5% C.P 834.65
834.65
12798.00
Rate for 1.00 Mtr. 419.88
419.90/Mtr
Earth filling with excavated earth after testing the Cum 8.49 162.50 1379.63
pipe line
Cost Materials 25mm G.I. Pipe for 30.48 Rmt 30.48 232.00 7071.36
Mtr
2% extra of cost of pipe towards cost of wastage 141.43
& fitting
labour Pl. Mistry (Spl) Each 1 430.00 430.00
Pl. Khalasi Each 2 320.00 640.00
11721.24
7.5% OHC 879.09
7.5% C.P 879.09
13479.42
Rate per 1.00 Mtr 442.24
442.20/Mtr
3 S/F/F of 20mm dia G.I. pipe ------- etc
Complete.
Data for 30.48 Mtr or 100'-0".
E/W excavation of Pipe line trench in all kinds of
soil.
100.00 x 1'-6' x 2'-0"= 300.00 Cft or 8.49 Cum Cum 8.49 242.50 2058.83
Earth filling with excavated earth after testing the Cum 8.49 162.50 1379.63
pipe line
Cost Materials 20mm G.I. Pipe for 30.48 Rmt 30.48 85.00 2590.80
Mtr
2% extra of cost of pipe towards cost of wastage 51.82
& fitting
Pl. Mistry (Spl) Each 0.92 430.00 395.60
Pl. Khalasi Each 1.84 320.00 588.80
7065.47
7.5% OHC 529.91
7.5% C.P 529.91
8125.29
Rate per 1.00 Mtr 266.58
266.60/Mtr
4 Providing and laying in trenches galvanized
mild steel tubes (heavy grade) conforming
to
IS:1239/2004, Part-1 of the following
nominal bore and tube fittings including
testing as per
specification complete. (Earth work in
trenches to be measured and paid for
separatly.
80mm diameter
Details of cost for 10 metres
a. Materials
80mm dia G.I Pipe (TATA Heavy) Mtr 10.00 643.00 6430.00
Tube fittings and wastages 2% 128.60
White lead,hemp oil etc 1% 64.30
b. Labour for laying
Plumber Fitter(S) Each 0.25 430.00 107.50
Male worker Each 0.66 280.00 184.80
(a+b) 6915.20
c. Add Contractor's Profit & Overhead 1037.28
charges 15%
Total (a+b+c) 7952.48
Rate per metre is 795.25
Add conveyance , Rayality & tollage Qntl 0.101 64.51 6.52
801.76
801.80/Mt
r
50mm diameter
Details of cost for 10 metres
a. Materials
50mm dia G.I Pipe (TATA Heavy) Mtr 10.00 385.00 3850.00
Tube fittings and wastages 2% 77.00
White lead,hemp oil etc 1% 38.50
b. Labour for laying
Plumber Fitter(S) Each 0.16 430.00 68.80
Male worker Each 0.33 280.00 92.40
(a+b) 4126.70
c. Add Contractor's Profit & Overhead 619.01
charges 15%
Total (a+b+c) 4745.71
Rate per metre is 474.57
Add conveyance , Rayality & tollage Qntl 0.062 64.51 4.00
478.57
478.60/Mt
r
20mm diameter
Details of cost for 10 metres
a. Materials
20 mm dia G.I Pipe (TATA Heavy) Mtr 10.00 163.00 1630.00
Tube fittings and wastages 2% 32.60
White lead,hemp oil etc 1% 16.30
b. Labour for laying
Plumber Fitter(S) Each 0.08 430.00 34.40
Male worker Each 0.16 280.00 44.80
(a+b) 1758.10
c. Add Contractor's Profit & Overhead 263.72
charges 15%
Total (a+b+c) 2021.82
Rate per metre is 202.18
Add conveyance , Rayality & tollage Qntl 0.019 64.51 1.23
203.41
203.40/Mt
r
15mm diameter
Details of cost for 10 metres
a. Materials
15mm dia G.I Pipe (TATA Heavy) Mtr 10.00 73.89 738.90
Tube fittings and wastages 2% 14.78
White lead,hemp oil etc 1% 7.39
b. Labour for laying
Plumber Fitter(S) Each 0.08 430.00 34.40
Male worker Each 0.16 280.00 44.80
(a+b) 840.27
c. Add Contractor's Profit & Overhead 126.04
charges 15%
Total (a+b+c) 966.31
Rate per metre is 96.63
Add conveyance , Rayality & tollage Qntl 0.019 64.51 1.23
97.86
97.90/Mtr
40mm diameter
Details of cost for 10 metres
a. Materials
40mm dia G.I Pipe (TATA heavy) Mtr 10.00 372.00 3720.00
Tube fittings and wastages 2% 74.40
White lead,hemp oil etc 1% 37.20
b. Labour for laying
Plumber Fitter(S) Each 0.16 430.00 68.80
Male worker Each 0.33 280.00 92.40
(a+b) 3992.80
c. Add Contractor's Profit & Overhead 598.92
charges 15%
Total (a+b+c) 4591.72
Rate per metre is 459.17
Add conveyance , Rayality & tollage Qntl 0.044 64.51 2.84
462.01
462.00/Mt
r
25mm diameter
Details of cost for 10 metres
a. Materials
25 mm dia G.I Pipe (TATA Heavy) Mtr 10.00 232.00 2320.00
Tube fittings and wastages 2% 46.40
White lead,hemp oil etc 1% 23.20
b. Labour for laying
Plumber Fitter(S) Each 0.12 430.00 51.60
Male worker Each 0.25 280.00 70.00
(a+b) 2511.20
c. Add Contractor's Profit & Overhead 376.68
charges 15%
Total (a+b+c) 2887.88
Rate per metre is 288.79
Add conveyance , Rayality & tollage Qntl 0.03 64.51 1.94
290.72
290.70/Mt
r
40mm diameter
Details of cost for 10 metres
a. Materials
40mm dia G.I Pipe (TATA Medium) Mtr 10.00 266.00 2660.00
Tube fittings and wastages 2% 53.20
White lead,hemp oil etc 1% 26.60
b. Labour for laying
Plumber Fitter(S) Each 0.16 430.00 68.80
Male worker Each 0.33 280.00 92.40
(a+b) 2901.00
c. Add Contractor's Profit & Overhead 435.15
charges 15%
Total (a+b+c) 3336.15
Rate per metre is 333.62
Add conveyance , Rayality & tollage Qntl 0.044 64.51 2.84
336.45
336.45/Mt
r
4N Providing and laying in trenches galvanized
mild steel tubes (medium grade) conforming
to
IS:1239/2004, Part-1 of the following
nominal bore and tube fittings including
testing as per
specification complete. (Earth work in
trenches to be measured and paid for
separatly.
15mm diameter
Details of cost for 10 metres
a. Materials
15 mm dia G.I Pipe (TATA Medium) Mtr 10.00 131.00 1310.00
Tube fittings and wastages 2% 26.20
White lead,hemp oil etc 1% 13.10
b. Labour for laying
Plumber Fitter(S) Each 0.08 430.00 34.40
Male worker Each 0.16 280.00 44.80
(a+b) 1428.50
c. Add Contractor's Profit & Overhead 214.28
charges 15%
Total (a+b+c) 1642.78
Rate per metre is 164.28
Add conveyance , Rayality & tollage Qntl 0.03 64.51 1.94
166.21
166.20/Mt
r
20mm diameter
Details of cost for 10 metres
a. Materials
20 mm dia G.I Pipe (TATA Medium) Mtr 10.00 160.00 1600.00
Tube fittings and wastages 2% 32.00
White lead,hemp oil etc 1% 16.00
b. Labour for laying
Plumber Fitter(S) Each 0.08 430.00 34.40
Male worker Each 0.16 280.00 44.80
(a+b) 1727.20
c. Add Contractor's Profit & Overhead 259.08
charges 15%
Total (a+b+c) 1986.28
Rate per metre is 198.63
Add conveyance , Rayality & tollage Qntl 0.019 64.51 1.23
199.85
199.85/Mt
r
25mm diameter
Details of cost for 10 metres
a. Materials
25 mm dia G.I Pipe (TATA Medium) Mtr 10.00 227.00 2270.00
Tube fittings and wastages 2% 45.40
White lead,hemp oil etc 1% 22.70
b. Labour for laying
Plumber Fitter(S) Each 0.12 430.00 51.60
Male worker Each 0.25 280.00 70.00
(a+b) 2459.70
c. Add Contractor's Profit & Overhead 368.96
charges 15%
Total (a+b+c) 2828.66
Rate per metre is 282.87
Add conveyance , Rayality & tollage Qntl 0.03 64.51 1.94
284.80
284.80/Mt
r
32mm diameter
Details of cost for 10 metres
a. Materials
32 mm dia G.I Pipe (TATA Medium) Mtr 10.00 241.00 2410.00
Tube fittings and wastages 2% 48.20
White lead,hemp oil etc 1% 24.10
b. Labour for laying
Plumber Fitter(S) Each 0.12 430.00 51.60
Male worker Each 0.25 280.00 70.00
(a+b) 2603.90
c. Add Contractor's Profit & Overhead 390.59
charges 15%
Total (a+b+c) 2994.49
Rate per metre is 299.45
Add conveyance , Rayality & tollage Qntl 0.03 64.51 1.94
301.38
301.40/Mt
r
40mm diameter
Details of cost for 10 metres
a. Materials
40mm dia G.I Pipe (TATA Medium) Mtr 10.00 266.00 2660.00
Tube fittings and wastages 2% 53.20
White lead,hemp oil etc 1% 26.60
b. Labour for laying
Plumber Fitter(S) Each 0.16 430.00 68.80
Male worker Each 0.33 280.00 92.40
(a+b) 2901.00
c. Add Contractor's Profit & Overhead 435.15
charges 15%
Total (a+b+c) 3336.15
Rate per metre is 333.62
Add conveyance , Rayality & tollage Qntl 0.044 64.51 2.84
336.45
336.45/Mt
r
50mm diameter
Details of cost for 10 metres
a. Materials
50mm dia G.I Pipe (TATA Medium) Mtr 10.00 376.00 3760.00
Tube fittings and wastages 2% 75.20
White lead,hemp oil etc 1% 37.60
b. Labour for laying
Plumber Fitter(S) Each 0.16 430.00 68.80
Male worker Each 0.33 280.00 92.40
(a+b) 4034.00
c. Add Contractor's Profit & Overhead 605.10
charges 15%
Total (a+b+c) 4639.10
Rate per metre is 463.91
Add conveyance , Rayality & tollage Qntl 0.044 64.51 2.84
466.75
466.75/Mt
r
65mm diameter
Details of cost for 10 metres
a. Materials
65mm dia G.I Pipe (TATA Medium) Mtr 10.00 476.00 4760.00
Tube fittings and wastages 2% 95.20
White lead,hemp oil etc 1% 47.60
b. Labour for laying
Plumber Fitter(S) Each 0.25 430.00 107.50
Male worker Each 0.66 280.00 184.80
(a+b) 5195.10
c. Add Contractor's Profit & Overhead 779.27
charges 15%
Total (a+b+c) 5974.37
Rate per metre is 597.44
Add conveyance , Rayality & tollage Qntl 0.044 64.51 2.84
600.27
600.30/Mt
r
4N Providing and laying in trenches galvanized
mild steel tubes (Heavy grade) conforming
to
IS:1239/2004, Part-1 of the following
nominal bore and tube fittings including
testing as per
specification complete. (Earth work in
trenches to be measured and paid for
separatly.
15mm diameter
Details of cost for 10 metres
a. Materials
15 mm dia G.I Pipe (TATA Heavy) Mtr 10.00 150.00 1500.00
Tube fittings and wastages 2% 30.00
White lead,hemp oil etc 1% 15.00
b. Labour for laying
Plumber Fitter(S) Each 0.08 430.00 34.40
Male worker Each 0.16 280.00 44.80
(a+b) 1624.20
c. Add Contractor's Profit & Overhead 243.63
charges 15%
Total (a+b+c) 1867.83
Rate per metre is 186.78
Add conveyance , Rayality & tollage Qntl 0.03 64.51 1.94
188.72
188.70/Mt
r
20mm diameter
Details of cost for 10 metres
a. Materials
20 mm dia G.I Pipe (TATA Heavy) Mtr 10.00 186.00 1860.00
Tube fittings and wastages 2% 37.20
White lead,hemp oil etc 1% 18.60
b. Labour for laying
Plumber Fitter(S) Each 0.08 430.00 34.40
Male worker Each 0.16 280.00 44.80
(a+b) 1995.00
c. Add Contractor's Profit & Overhead 299.25
charges 15%
Total (a+b+c) 2294.25
Rate per metre is 229.43
Add conveyance , Rayality & tollage Qntl 0.019 64.51 1.23
230.65
230.65/Mt
r
25mm diameter
Details of cost for 10 metres
a. Materials
25 mm dia G.I Pipe (TATA Heavy) Mtr 10.00 271.00 2710.00
Tube fittings and wastages 2% 54.20
White lead,hemp oil etc 1% 27.10
b. Labour for laying
Plumber Fitter(S) Each 0.12 430.00 51.60
Male worker Each 0.25 280.00 70.00
(a+b) 2912.90
c. Add Contractor's Profit & Overhead 436.94
charges 15%
Total (a+b+c) 3349.84
Rate per metre is 334.98
Add conveyance , Rayality & tollage Qntl 0.03 64.51 1.94
336.92
336.90/Mt
r
32mm diameter
Details of cost for 10 metres
a. Materials
32 mm dia G.I Pipe (TATA Heavy) Mtr 10.00 280.00 2800.00
Tube fittings and wastages 2% 56.00
White lead,hemp oil etc 1% 28.00
b. Labour for laying
Plumber Fitter(S) Each 0.12 430.00 51.60
Male worker Each 0.25 280.00 70.00
(a+b) 3005.60
c. Add Contractor's Profit & Overhead 450.84
charges 15%
Total (a+b+c) 3456.44
Rate per metre is 345.64
Add conveyance , Rayality & tollage Qntl 0.03 64.51 1.94
347.58
347.60/Mt
r
40mm diameter
Details of cost for 10 metres
a. Materials
40mm dia G.I Pipe (TATA Heavy) Mtr 10.00 323.00 3230.00
Tube fittings and wastages 2% 64.60
White lead,hemp oil etc 1% 32.30
b. Labour for laying
Plumber Fitter(S) Each 0.16 430.00 68.80
Male worker Each 0.33 280.00 92.40
(a+b) 3488.10
c. Add Contractor's Profit & Overhead 523.22
charges 15%
Total (a+b+c) 4011.32
Rate per metre is 401.13
Add conveyance , Rayality & tollage Qntl 0.044 64.51 2.84
403.97
404.00/Mt
r
50mm diameter
Details of cost for 10 metres
a. Materials
50mm dia G.I Pipe (TATA Heavy) Mtr 10.00 468.00 4680.00
Tube fittings and wastages 2% 93.60
White lead,hemp oil etc 1% 46.80
b. Labour for laying
Plumber Fitter(S) Each 0.16 430.00 68.80
Male worker Each 0.33 280.00 92.40
(a+b) 4981.60
c. Add Contractor's Profit & Overhead 747.24
charges 15%
Total (a+b+c) 5728.84
Rate per metre is 572.88
Add conveyance , Rayality & tollage Qntl 0.044 64.51 2.84
575.72
575.70/Mt
r
65mm diameter
Details of cost for 10 metres
a. Materials
65mm dia G.I Pipe (TATA Heavy) Mtr 10.00 578.00 5780.00
Tube fittings and wastages 2% 115.60
White lead,hemp oil etc 1% 57.80
b. Labour for laying
Plumber Fitter(S) Each 0.25 430.00 107.50
Male worker Each 0.66 280.00 184.80
(a+b) 6245.70
c. Add Contractor's Profit & Overhead 936.86
charges 15%
Total (a+b+c) 7182.56
Rate per metre is 718.26
Add conveyance , Rayality & tollage Qntl 0.044 64.51 2.84
721.09
721.10/Mt
r
5 Dismantling G.I. pipes (external work)
including excavation and refilling trenches
after taking out
the pipes, manually / by mechanical means
including stacking of pipes within 50 metres
lead as per direction of Engineer in charge.
15 mm to 40 mm nominal bore
Details of cost for 10 metre
a. Labour charges
Male worker unskilled Each 1.32 280.00 369.60
Dismantling G.I. pipe and stacking etc. L.S 53.46
423.06
b. Add Contractor's Profit & Overhead 63.46
charges 15%
Total (a+b) 486.52
Rate per metre 48.65
48.65
[ ii ] Above 40 mm nominal bore
Details of cost for 10 metre
a. Labour charges
Male worker unskilled Each 1.32 280.00 369.60
Dismantling G.I. pipe and stacking etc L.S 106.83
476.43
b. Add Contractor's Profit & Overhead 71.46
charges 15%
Total (a+b) 547.89
Rate per metre 54.79
54.80/Mtr
PVC PIPE
6 S/F/F of 25mm dia PVC pipe line-----
etc complete.Oriplast make S-80
Data for 10.00 Mtr.
25mm dia PVC pipe Rmt. 10 94.40 944.00
15% for fitting & wastage 141.60
3% for wooden plug,clamp, cement etc 28.32
Plumbing Mistry 2nd class Each 0.83 370.00 307.10
Mulia Each 0.67 280.00 187.60
1608.62
7.5% OHC 120.65
7.5% C.P 120.65
Rate for 1.00 Mtr. 1849.91
184.99
185.00/Mtr
7 S/F/F of 20mm dia PVC pipe line-----
etc complete. Oriplast make S-80
Data for 10.00 Mtr.
25mm dia PVC pipe Rmt. 10 64.40 644.00
15% for fitting & wastage 96.60
3% for wooden plug,clamp, cement etc 19.32
Plumbing Mistry 2nd class Each 0.75 370.00 277.50
Mulia Each 0.67 280.00 187.60
1225.02
7.5% O.H.C 91.88
7.5% C.P 91.88
1408.77
Rate for 1.00 Mtr. 140.88
140.90/Mtr
8 S/F/F of 15mm dia PVC pipe line-----
etc complete.Oriplast make S-80
Data for 10.00 Mtr.
25mm dia PVC pipe Rmt. 10 47.70 477.00
15% for fitting & wastage 71.55
3% for wooden plug,clamp, cement etc 14.31
Plumbing Mistry 2nd class Each 0.67 370.00 247.90
Mulia Each 0.67 280.00 187.60
998.36
7.5% O.H.C 74.88
7.5% C.P 74.88
Rate for 1.00 Mtr. 1148.11
114.81
114.80/Mtr
9 Supplying, fitting & fixing of 100mm dia
PVC pipes IS:4985-2000 and specials of the
following out side diameter for all classes
including jointing with supply of approved
solvent cement by heat application method
including testing as per specification
complete. (Waste pipe)
Material
110mm dia UPVC Pipe Pair 6 129.00 774.00
110mm dia UPVC Pipe (working pressure 4Kg / Each 1 20.00 20.00
CM2) Rubber (seal) ring
Adhesive L.S 12.01
Scaffolding L.S 27.70
Labour
Plumber 2nd class Each 0.23 370.00 85.10
Helper to plumber Each 0.11 320.00 35.20
Mail worker Each 0.45 280.00 126.00
1080.01
OHC & C.P 15% 162.00
1242.01
Rate per Mtr 124.20
124.20
13 Providing and laying in trenches unplasticed
PVC pipes conforming to Is 4985 /2000 of
class IV (10 kgf/ cm2) of the following
nominal bore and pipe fittings including
testing as per specification complete.
( Earth work in trenches to be measured
and paid for separately)
EWC PAN
20 S/F/F all materials labour T&P for fitting
E.W.C. pan with 1 no of P.V.C P trap
A. E.W.C. pan: Plumber ( 2nd class ) Each 0.5 370.00 185.00
Mulia Each 0.5 280.00 140.00
325.00
7.5% O.H.C 24.38
7.5% C.P 24.38
2% sundries T&P 6.50
C.C. ( 1:5:10 ) cement Qntl 0.17 495.30 84.20
Sand Cum 0.06 52.38 3.14
Metal Cum 0.12 709.52 85.14
Cost of EWC pan (Parry make) 800.00
1352.74
1351.16
B. P.V.C P trap : Plumber ( 2nd class ) Each 0.5 370.00 185.00
Mulia Each 0.5 280.00 140.00
Helper Each 0.5 320.00 160.00
485.00
7.5% O.H.C 36.38
7.5% C.P 36.38
Cement Qntl 0.12 495.30 59.44
spun yarn Kg 2.18 50.00 109.00
Sand bitumen L.S. 6.60
732.79
Rate per 1 joint 73.28
Cost of HCI P.Trap Each 1 202.32 202.32
275.60
Toal cost (A + B) (1351.16 + 275.49) 1626.76
1626.80/E
ach
21 White vitreous china wash down water
closet (EWC
Material
EWC Pan with P. Trap Each 1.00 1500.00 1500.00
CP screw, washer and wooden plugs, white L.S 19.95
cement finish on cement mortar joint etc.
Material
EWC Pan with P. Trap Each 1.00 1225.00 1225.00
CP screw, washer and wooden plugs, white cement L.S 19.95
finish on cement mortar joint etc.
Jointing trap with siol pipe L.S 28.34
Carriage of materials 20.14
1293.43
B. Labour charge
Plumber (fitter) /Mason (2nd class) Each 0.50 370.00 185.00
Male worker (un skilled) Each 0.50 280.00 140.00
325.00
A+B 1618.43
C. Add contractors profit & over head charges 15% 242.76
Cost per each 1861.19
1861.20/Ea
ch
32 N Fixing Wash Down closet (Europen Type W.C Pan)
with integral 'S' or 'P' trap conforming to IS 2556: part 8
-2004 , to the floor with wooden plug and chromium
plated screws including jointing the tap with soil pipe in
cement mortar (1:1) etc all complete as per
specification.
MIRROR
29 S/F/F of Mirror----- etc complete.
25mm C.P. screw Nos 4 3.10 12.40
Wooden plug screw Nos 4 1.00 4.00
6mm thick A.C. or ply wood sheet Sqm 0.28 100.00 28.00
0.275/sqm
Rubber buffer Nos 4 1.00 4.00
Cement, Sand, Chips L.S. 3.30
Carpenter ( 2nd class ) Each 0.33 370.00 122.10
Mulia Each 0.33 280.00 92.40
7.5% O.H.C 11.56
7.5%C.P 11.56
1% watering charges 1.54
8% sundries T&P 12.33
Cost of mirror (Balegium) Each 1 450.00 450.00
753.19
753.20/Ea
ch
30 S/F/F of Mirror----- etc complete.
Cost of mirror (Balegium) (650 x 450) Each 1 450.00 450.00
25mm C.P. screw Nos 4 3.10 12.40
Wooden plug screw Nos 4 1.00 4.00
6mm thick A.C. or ply wood sheet 0.275 Sqm Sqm 0.27 100.00 27.00
43 URINAL
S/F/F of standing urinal
etc complete (Parry make)
cost of Flat back standing Urinal (parry make) Each 1 565.00 565.00
Material.
2000 Lit capacity double layer cylinderical Liter 2000.00 4.40 8800.00
vertical water storage tank
Lead, paint & yarn LS. 6.60
Pluber (Special) Each 0.50 430.00 215.00
Helper to Plumber Each 0.75 320.00 240.00
Man Mulia Each 5.00 280.00 1400.00
10661.60
Add Contractor perfit & OHC 15% 1599.24
12260.84
12260.80/
Each
45 Fixing Rotational moulded polyethylene
cylindrical vertical water storage tanks
conforming to IS;12701--1996 including
cutting holes through the tank and fixing
mild steel tubes and fittings and providing
extra sockets and jam nut, fixing of ball
valveetc, including hoisting up to a height of
5 meters above ground level and placing
the tank to the required position etc all
complete as per specification and direction
of EIC.
Material.
1000 Lit capacity double layer cylinderical Liter 1000.00 4.40 4400.00
vertical water storage tank
Lead, paint & yarn LS. 6.60
Pluber (Special) Each 0.50 430.00 215.00
Helper to Plumber Each 0.75 320.00 240.00
Man Mulia Each 4.00 280.00 1120.00
5981.60
Add Contractor perfit & OHC 15% 897.24
6878.84
6878.80/
Each
46 Fixing Rotational moulded polyethylene
cylindrical vertical water storage tanks
conforming to IS;12701--1996 including
cutting holes through the tank and fixing
mild steel tubes and fittings and providing
extra sockets and jam nut, fixing of ball
valveetc, including hoisting up to a height of
5 meters above ground level and placing
the tank to the required position etc all
complete as per specification and direction
of EIC.
Material.
As per market rate 1000 Lit capacity Single Liter 1000.00 5.50 5500.00
layer syntex water storage tank
Lead, paint & yarn LS. 6.60
Pluber (Special) Each 0.50 430.00 215.00
Helper to Plumber Each 0.75 320.00 240.00
Man Mulia Each 4.00 280.00 1120.00
7081.60
Add Contractor perfit & OHC 15% 1062.24
8143.84
8143.80/
Each
SINGLE JUNCTION
47 S/f/f of 100mm dia PVC single
junction ------------- etc complete.
Plumbing Mistry 2nd Class Each 0.167 370.00 61.79
Pl. Khalasi Each 0.167 320.00 53.44
Mukia Each 0.167 280.00 46.76
161.99
7.5% OHC 12.15
7.5% C.P 12.15
Gasket Kg 0.257 30.00 7.71
Cement including Lead Qntl 0.014 495.30 6.93
Sand LS 2.00
Sundries T&P LS 1.00
Cost of 100mm dia Single Junction Each 1 209.04 209.04
412.97
413.00/eac
h
48 N S/f/f of 110mm dia PVC single
junction ------------- etc complete.
Single Tee with door
Details of cost for 1 Tee
A. Materials
UPVC single equal Tee (with door) 110X 110X Each 1 180.00 180.00
110
110mm dia UPVC pipe (working pressure 4kg / Each 3 20.00 60.00
cm2)Rubber seal ring
B. Adhesive , Carriage of material rubber washer L.S 20.07
etc
(A+B) 260.07
C. Add contractor's profit & over head charges 15% of 260.07 39.01
175.38
175.40/E
ach
PVC COWL
50 N S/F/F of 100mm dia PVC Cowal --------
etc complete.
Plumbing mistry 2nd Class Each 0.083 370.00 30.71
Pl. Khalasi Each 0.167 320.00 53.44
84.15
7.5% O.H.C 6.31
7.5% C.P 6.31
Painting, sundries T&P LS 1.00
cost of 100mm dia PVC Cowal Each 1 78.00 78.00
259.92
259.90/Ea
ch
PVC HILLREST BEND & DOOR BEND
51 S/F/F 100mm dia PVC Hill rest bend
Pl. Mistry Each 0.167 370.00 61.79
Pl. khalasi Each 0.167 320.00 53.44
Mulia Each 0.167 280.00 46.76
161.99
7.5% O.H.C 12.15
7.5% C.P 12.15
186.29
gasket Kg 0.257 30.00 7.71
Cement Qntl 0.014 495.30 6.93
Cost of soaking arround L.S. 2.00
Sundries T&P L.S. 1.00
sand L.S. 1.00
Cost of 100mm dia Hill rest bend 188.00
392.93
392.90/Ea
ch
52 N S/F/F 110mm dia PVC Hill rest bend N
Details of cost for 1 bend
A. Materials
UPVC bend 87.5 110 mm bend Each 1 95.00 95.00
110 mm dia UPVC pipe ( Working pressure 4 kg / Each 1 20.00 20.00
cm2 )Rubber (seal ) ring
Adhesive etc L.S 4.07
B. Carriage and fixing charges L.S 16.08
(A+ B) 135.15
C. Add contractor 's profit & over head charges 15% of 135.15 20.27
155.42
Say
155.40
53 S/F/F 100mm dia PVC door bend
Pl. Khalasi Each 0.125 320.00 40.00
Pl. Mistry each 0.125 370.00 46.25
Mulia Each 0.25 280.00 70.00
156.25
7.5% O.H.C. 11.72
7.5% C.P 11.72
Gasket Kg 0.1285 30.00 3.86
Cement Qntl 0.007 495.30 3.47
Sand L.S. 0.30
Cost of soaking arround 1.00
Earth work, painting two coat 1.50
Cost of door bend Each 1 110.00 110.00
299.81
299.80/Ea
ch
54 S/F of 110mm PVC Bend rain water pipe
110mm Bend Each 1.00 95.00 95.00
Rubber seal ring Each 1.00 20.00 20.00
Adhesive L.S 4.07
Carriage and fixing charges (S.R-2013- Rate
/Each Rs 16.08)
Carriage & fixing rate in 2016 excess 33.40% L.S 21.45
than S.R-2013
140.52
OHC & CP 15% 21.08
161.60
WASTE PIPE
55 S/F/F/ of waste pipe ( Data for 10 nos )
Plumber (2nd class) Each 0.83 370.00 307.10
Unskilled Each 1 280.00 280.00
587.10
7.5% O.H.C 44.03
7.5% C.P 44.03
1% watering charges 5.87
8% sundries T&P 46.97
728.00
Rate per 1 no 72.80
Add cost of waste pipe 67.00
139.80
139.80/Ea
ch
56 S/F/F/ of waste pipe ( Data for 10 mtr )
Add cost of waste pipe Mtr 10 124.96 1249.60
Rubber seal ring Each 10 20.00 200.00
Adhesive etc. L.S 12.00
Scaffolding L.S 27.70
Plumber (2nd class) Each 0.23 370.00 85.10
Helper to Plumber Each 0.11 320.00 35.20
Un-Skilled Each 0.45 280.00 126.00
1735.60
7.5% O.H.C 130.17
7.5% C.P 130.17
1995.94
Rate per 1.00Mtr. 199.59
199.60/Mtr
CPVC PIPE
57 Providing and fixing Chlorinated Polyvinyl
Chloride (CPVC) Pipes conforming to IS 15778,
having thermal stability for hot & cold water
supply including all CPVC plain & brass threaded
fittings. Thios includes jointing of pipes & fittings
with one ster CPVC solvent cement , trenching
,refilling &testing of joints complete as per
direction of EIC.
900 mm diameter.
Materials:
900mm concrete Single socket
Detail of cost for 10 joints. (10 x 2.35)= 23.50 Mtr
3569.78
Add 15% for OHC & CP 535.47
4105.24
Rate per 1.00 Mtr 410.52
Add for road cost of Pipe(1.00 Mtr) Mtr 1 1.65 1.65
(Considering 350 nos pipe carry per
truck i.e 2100 Mtr)
412.17
412.20/M
Say tr
60 Laying in trenches (to level or slope) &
jointing with provision of stiff mixture in
160mm dia PVC pipe with adhesive
Data for 10.00 Mtr.
(A) Materias
160mm dia PVC pipe (Schedule-40) Mtr 10.00 489.23 4892.30
(B) Labour for laying
Plumber (Spl) Each 0.25 430.00 107.50
Male worker Each 0.50 280.00 140.00
© Labour for jointing & fitting
Plumber (Spl) Each 0.46 430.00 197.80
Helper to Plumber Each 1.92 320.00 614.40
Male worker Each 0.25 280.00 70.00
(D) Jointing materials
Cost of solvent cement (133gm or 0.133 Kg) Kg 0.13 171.00 22.74
6044.74
Add 15% for OHC & CP 906.71
6951.45
Rate per 1.00 Mtr 695.15
Add for road cost of Pipe(1.00 Mtr) Mtr 1 3.00 3.00
(Considering 192 nos pipe carry per
truck i.e 1150 Mtr)
698.15
698.15/M
tr
PILLAR COCK
61 Fixing pillar taps ccapstan head screw down high
pressure lettered "Hot" and 'cold 'with long
screws , shanks and back nuts of the following
nominal bore as per specification.
STOP COCK
70 Supplying fitting fixing 15mm dia C.P stop
cock (Brass Concealed Stop Cock)
Data for 10 nos
Plumber(2nd class) Each 0.5 370.00 185.00
Helper Each 0.5 320.00 160.00
345.00
1% watering 3.45
2% jointing materials 6.90
355.35
7.5% OHC 26.65
7.5% C.P 26.65
764.00
Rate per 1 no 76.40
15mm dia CP Brass Concealed Stop Cock 711.10
787.50
say Rs. 787.50/Ea
ch
71 S/F/F of 15mm stop cock (Jaguar)
15mm diameter
Details for 10 nos of Brass screw down stop
cocks
Materials:15mm dia C.P stop cock Each 10 600.00 6000.00
Labour: Plumber fitter (2nd class) Each 0.5 370.00 185.00
Helper to plumber /fitter Each 0.5 320.00 160.00
Jointing materials 2% 345.00 6.90
6351.90
Add C.P & O.H.C 15% 952.79
7304.69
Rate per each is 7304.69/10 730.47
730.50/Ea
ch
72 S/F/F of 15mm dia C.P angular stop cock
(Jaguar)
15mm diameter
Details for 10 nos of Brass screw down stop
cocks
Materials:15mm dia C.P angular stop cock Each 10 480.00 4800.00
Labour: Plumber fitter (2nd class) Each 0.5 370.00 185.00
Helper to plumber /fitter Each 0.5 320.00 160.00
Jointing materials 2% 345.00 6.90
5151.90
Add C.P & O.H.C 15% 772.79
5924.69
Rate per each is 5924.69/10 592.47
592.50/Ea
ch
BIB COCK
73 Supplying, fitting & fixing of 15mm C.P Bib
Cock---- etc complete.Short Body Bib Cock)
(Jaguar)
Data for 10 Nos
Plumber 2nd Class Each 0.33 370.00 122.10
Helper Each 0.33 320.00 105.60
227.70
jointing materials 2 % 2% 227.70 4.55
232.25
Cost of 15mm Short body C.P Bib Cock Each 10 520.00 5200.00
5432.25
Add C.P & O.H.C 15% 814.84
6247.09
Rate per 1 Nos 624.71
624.70/Ea
ch
Materials
25mm dia nominal bore PVC Ball cock Each 1 550.00 550.00
Labour: Plumber Fitter (S) Each 0.125 430.00 53.75
Plumber helper Each 0.125 320.00 40.00
Jointing materials 2% on labour charges 2% 93.75 1.88
645.63
15% O.H.C & C.P 96.84
742.47
742.50/E
ach
81 N S/F/F of 20mm Brass Ball valve ….. etc complete
Data for 10 Nos
Plumber fitter (2nd class) Each 0.125 370.00 46.25
Helper Each 0.125 320.00 40.00
86.25
Cost of Brass Ball Valve (as per prevailing market rate) Each 10 649.25 6492.50
6578.75
7.5% OHC 493.41
7.5% C.P 493.41
7565.56
Rate for one No 756.56
756.60/Each
C.I GRATING
81 Supplying, fitting & fixing of C.I grating
including labour & other materials.
Data for one No.
C.I grating Each 1.00 15.00 15.00
Labour charges for for fixing L.S 3.00
18.00
15% OHC & CP 2.70
20.70
82 Supplying Fitting Fixing of C.I wall Grating L.S 80.00
3.14/4X 1.40 X1.40 X 0.075 =0.12 Cum Cum 0.12 642.05 77.05
(i) PCC of Prop (1:3:6) in foundation using
4cm size hard crusher broken granite metal
of approved quality from approved quarry
including lowering, laying concrete to
required levels laid in layers not exceeding
150mm thick including cost , conveyance,
taxes royalities of materials , cost of all
labour and T&P required for the work etc
complete as per direction of EIC.
3.14/4 X1.20 x1.20 X .15= 0.17 cum Cum 0.17 5085.25 864.4925
iv) Rcc work of M-20 grade wall with 20mm
and down grade hard crusher broken
granite stone chipsincluding hoisting and
laying concrete ,watering and curing for
thre weeks centering and shuttering and
finishing th exposed surfaces smooth,
providing beads or grooves where
necessary including cost , conveyance,
royality, taxes of all materials, dismantling
the centering shuttering work after the
period as specified by EIC and cost of all
labour, T&P required for the work complete
in all respect, excluding cost of
reinforcement , binding wires and labour
charges for bending , binding and tying the
grills as directed by EIc.
3.14/4 X (1.20X 1.20) -( 0.90X 0.90) X0.60 Cum 0.3 9607.9 2882.37
=0.30 cum
v) Rcc work of M-20 grade Roof Slab with
20mm and down grade hard crusher broken
granite stone chipsincluding hoisting and
laying concrete ,watering and curing for
thre weeks centering and shuttering and
finishing th exposed surfaces smooth,
providing beads or grooves where
necessary including cost , conveyance,
royality, taxes of all materials, dismantling
the centering shuttering work after the
period as specified by EIC and cost of all
labour, T&P required for the work complete
in all respect, excluding cost of
reinforcement , binding wires and labour
charges for bending , binding and tying the
grills as directed by EIc.
10.00 X 0.60 x 0.10 mt= 0.60 cum Cum 0.6 4602.50 2761.5
ii) Rcc work of M-20 grade base with 20mm
and down grade hard crusher broken
granite stone chipsincluding hoisting and
laying concrete ,watering and curing for
thre weeks centering and shuttering and
finishing th exposed surfaces smooth,
providing beads or grooves where
necessary including cost , conveyance,
royality, taxes of all materials, dismantling
the centering shuttering work after the
period as specified by EIC and cost of all
labour, T&P required for the work complete
in all respect, excluding cost of
reinforcement , binding wires and labour
charges for bending , binding and tying the
grills as directed by EIc.
Base= 10.00 X 0.50 x 0.10 = 0.50 Cum Cum 0.5 5085.25 2542.625
iii) Rcc work of M-20 grade wall with 20mm
and down grade hard crusher broken
granite stone chipsincluding hoisting and
laying concrete ,watering and curing for
thre weeks centering and shuttering and
finishing th exposed surfaces smooth,
providing beads or grooves where
necessary including cost , conveyance,
royality, taxes of all materials, dismantling
the centering shuttering work after the
period as specified by EIC and cost of all
labour, T&P required for the work complete
in all respect, excluding cost of
reinforcement , binding wires and labour
charges for bending , binding and tying the
grills as directed by EIc.
RCC wall= 2 X10.00 X .10 X 0.30= 0.60 Cum Cum 0.6 9607.9 5764.74
11068.87
Rateper 1.00 Mtr = 11193.25/10 1106.887
50mm diameter
Details of cost for 10 metres
a. Materials
50mm dia G.I Pipe (TATA Medium) Mtr 10.00 376.00 3760.00
Tube fittings and wastages 2% 75.20
White lead,hemp oil etc 1% 37.60
b. Labour for laying
Plumber Fitter(S) Each 0.16 430.00 68.80
Male worker Each 0.33 280.00 92.40
(a+b) 4034.00
c. Add Contractor's Profit & Overhead 605.10
charges 15%
Total (a+b+c) 4639.10
Rate per metre is 463.91
Add conveyance , Rayality & tollage Qntl 0.062 64.51 4.00
467.91
467.90/Mt
r
25mm diameter
Details of cost for 10 metres
a. Materials
25 mm dia G.I Pipe (TATA medium) Mtr 10.00 227.00 2270.00
Tube fittings and wastages 2% 45.40
White lead,hemp oil etc 1% 22.70
b. Labour for laying
Plumber Fitter(S) Each 0.12 430.00 51.60
Male worker Each 0.25 280.00 70.00
(a+b) 2459.70
c. Add Contractor's Profit & Overhead 368.96
charges 15%
Total (a+b+c) 2828.66
Rate per metre is 282.87
Add conveyance , Rayality & tollage Qntl 0.03 64.51 1.94
284.80
284.80/Mt
r
221 Construction of Inspection Chamber with
RCC top slab in (1:2:4) mix, foundation
concrete (1:4:8), inside plaster 12mm th.
With cement motar (1:3) finished with neat
cement punning, 12mm thick outside plaster
(1:3), brick work with K.B bricks having
crushing strength not less than 75kg/cmsqr
with domensioral tolerance plus minous 8%
in cement motar (1:6), cement concrete
(1:2:4) finished smooth using 12mm sizr
H.G chips, earth work in excavation in all
kinds of soil and refilling the cavity around
the chamber complete as per specification.
i. M.S Reinforcement bars 8mm dia tor steel Qntl 0.17 5432.00 923.44
10 cm c/c bothways in slab including
cutting, bending and binding and tying the
grills including cost of binding wire
(Excluding CP & OHC) 0.17Qntl.
j. Extra labour for making channel
Mason (Special) Each 0.06 430.00 25.80
Mason (2nd class) Each 0.06 370.00 22.20
5920.81
242.50 1142.18
(ii) Supplying of RCC cover slab of size (3'-0") dia
including cost of RCC ring , lead to the site ,
loading and unloading … etc.complete.
Cost of RCC ring (1.37mtr) dia . (as per Each 1 550.00 550.00
market rate)
Labour for unloading and laying Each 1 50.00 50.00
600.00
15 % C.P & O.H.C 90.00
690.00
Add lead conveyance L.S 200.00
890.00
S/F/F of RCC cover slab over RCC ring of
1.37 mtr dia including all labour,
conveyance, necessary mortar.
Cost of RCC cover slab for RCC ring 0f1.37 Each 1 800.00 800.00
mtr (As per market Rate)
Labour for unloading and laying Each 1 50.00 50.00
850.00
15 % C.P & O.H.C 127.50
977.50
Add lead conveyance LS 200.00
1177.50