QUALITY MANAGEMENT PLAN
DEPARTMENT OR FUNCTION OR PROJECT NO | PROJECT NAME
1.1 EXPLANATORY NOTES ON USING CHECKLISTS:
These checklists have been approved by the Manager – Roads and Maintena
Where there is no specification, the current industry best practice standards ha
The checklists are not just for quality. They include environmental, safety and
Use one checklist for each lot. QER allocates a lot number and enters into the
When each monitoring and measurement activity has been completed, the nom
In certain circumstances, some activities may not be applicable. In such instan
nominated signatory places “N/A” in the activity signature box;
All applicable “Hold Points” are mandatory. They must be released prior to com
separate form. In such instances, a must be placed in the signature box.
When all checklist activities have been completed and signed off, the Project/S
conformance of the lot.
All supporting monitoring and measuring records, test results and as construct
4. Initiate insurances required for the contract and forward evidence to CFO Prior to start Insurances Cer
Superintendent. CFO Prior to start Bank Guarantee Cert
5. Arrange for security deposit (Bank Guarantee) to be forwarded to the Superintendent if required.
6. Prepare and issue Quality Management Plan with a copy to the MQE Upon Contract QMP
Superintendent. award release
7. Prepare and issue an acceptable Safety Management Plan to the Superintendent. Once approved SM Prior to start and mobilisation SMP
issue copies for construction. MQE Prior to start of the EMP
8. Prepare and issue Environmental Management Plan with a copy to the activity
Superintendent.
9. Prepare and submit Traffic Management Plan with a certificate of PM During the contract 1.25
compliance to the Superintendent. Issue approved plan for construction.
10. Review drawings and verify that contract documents conform to MQE/ PM Prior to start Review
construction and tender documents. Review addendums, conditions and variations to the contract. MQE Prior to start Review
11. Check relevant Australian Standards, Test Methods, Acts and
Regulations are available.
12. Obtain and make available to the Superintendent the Laboratory Quality QER 1 week prior to use Lab Qual
Manual a week in advance on site
13. Assess availability of company plant. Obtain quotations and order hired PM Prior to start Review H
plant. Assess fuelling, lubrication and servicing requirements.
14. Assess personnel requirements – surveyor, drainers, operators etc. PM Prior to start Review
Verify and record any on site training required.
15. Organise a briefing of key personnel engaged on the Contract including PM Prior to start Meeting H
quality, safety and environmental.
16. Confirm that subcontractors on this project have been assessed and PM Prior to start Prior to using
approved. Verify Third Party Certification requirement. Provide list to Superintendent including the names, subcontractors on site
addresses and the portion of subcontracted works for approval. Also include subcontractors whose
activities require current technical, managerial, safety and/or environmental competencies. Provide
evidence of Priority Access
Employer status. Verify financial due diligence requirements.
17. Provide subcontractors with all relevant specifications and drawings. If QER Prior to start Prior to start
required, prepare subcontract agreements.
5. Note the pre-existing condition of the verge and reinstate the verge to a S Existing properties 1.33 Restore to original photographic R
similar standard and as approved by the property owner. conditions
6. Verify site access and brief employees at inductions PM/S Prior to start Notify
pe
7. Note working hours and inform all personnel at inductions PM/S Prior to start 1.21 Working hours Induction R
8. Obtain a current NATA endorsed calibration certificate and submit a QER Prior to start on
copy to the Superintendent one week prior to use of NDM on site. site
9. Prior to NDM being stored on site submits to Superintendent a copy of QER Prior to start on Prior to Storing on
he approval obtained from the statutory Authority for the NDM to be emporarily stored in an unoccupied site site
locker vehicle and/or a
ransportable material testing laboratory
10. During the execution of the work under the Contract, have available at S At all times Make available Compete set of R
all times at the Site and other locations where the work is carried out a
complete set of documents for reference by Superintendent.
11. Ensure plant and equipment used on the project is approved by the Superintendent. PM At mobilisation Superintendent approval
15. Obtain setting out information from the Principal and check the digital SV Prior to start 1.22.6
design model to ensure that it corresponds with the drawings and certify to the superintendent that there
is no discrepancy between the digital design model and the drawings.
17. Level check to ascertain the survey bench marks are accurate and SV Prior to clearing 1.22.6 Accurate survey
have not been disturbed. Protect them and Re-establish any disturbed during construction. Confirm that the and topsoiling control points,
existing works conform in level and location with those show on the Drawings before commencing any protect control points
works on site. Notify Contracts Manager any variances.
19. Complete Job Safety Analysis (JSA) Sheets prior t o commencement of S Prior to start of the JSA for e
each hazardous task. Submit copies t o Superintendent. ask hazard
20 Always wear specified PPE. Hard hats to be marked with employee S At all times PPE Complian
Company Logo.
21 Provide first aid facilities and arrange for emergency treatment of S Make available at First Aid facilit
injuries. all times
22 Where described as such in specification and prior to commencement PM Prior to start 1.24 Approval, Ser
of Works in the vicinity of service, superintendent’s confirmation must relocation by o
be obtained that the required services and public utility alterations or
26 Minimise excess or scrap materials. Store or dispose of such material as directed by PM/S Excess when known Minimise wast
Superintendent. scrap
27 Maintain work areas in a neat, clean and safer condition. On completion of work, remove all S Clean at all times Clean, neat an
temporary structures, excess materials, worksite
plant and equipment and clean up.
7. Use cut material or import select fill material from and place to the S Cut to fill 2.3.4 Suitable fill Visual
shapes and levels shown on the drawings.
8. Control moisture; work the material in compacted layers of 100mm to S Spreading and 2.3.4 Mixing process
300mm. Where the layer is less than 100mm, scarify underlying material with grader to a minimum 100mm mixing
thickness.
9. At all times prevent ponding of water on the embankments. As a S Ponding Avoid ponding Visual
minimum, place material such that the rolled surface slopes down at a grade not less than one percent (1%) S Compaction 2.3.4 Rc > 96% Test res
towards the inside of the embankments (towards tailings).
10. Control moisture and compact the layer to achieve the desired density adding water to adjust
moisture uniformly to within +2% of OMC (-1%
<OMC <2%).
These activities have been inspected and are in accordance with the approved procedure. Lot Conforms
Supervisor: Date: / / QER:
3. Reinforced Concrete Culvert pipes and drainage systems shall be S/QER General Obtain
supplied, handled, stored and installed in accordance to: a) The relevant Project Specification and conformance certificates and sub
with specific Supe
b) The relevant Australian Specifications
c) As indicated on the drawings and
d) The manufacturer’s recommendations
4. Handle and install pipes and structures in such a manner so as to S Plastic pipes
prevent damage to them.
5. Ensure that the equipment used during the compaction of backfill does S Compaction Compact with care Visual S
not damage the pipes and structures. Determine limitations on the type of compaction equipment, and cover to be provided to
the top of the culvert in accordance with Clause 5.5.2 “Protection of Pipeline” AS/NZS
2566.2 and satisfy the manufacturer’s published requirements.
10 Confirm that all relocation of services that may be affected by the S Prior to trench
excavations have been carried out. excavation
11 Ascertain the position of all underground services and structures in the vicinity of the work from S Prior to trench
Contract Drawings and drawings obtained from he appropriate public authority and by site excavation
inspection. Mark and protect
all services.
4. Implement adequate traffic control measures S At all times 1.25 TMP Daily diary H
5. Set out electrical power/street lighting lot. SV Setting out 1.22.6 Set out Survey pegs H
6. Install all electrical works in accordance with the project specification, S At all times Cons
drawings and Australian Standards in a professional manner. s
7. Install conduits for road crossings prior to subgrade construction and S Prior to subgrade Conduits Visual
under retaining walls prior to bedding construction. Mark each end of service crossing for various S Prior to excavation Mark and protect Approval
services i.e. Western Power, water, gas, Telstra and other.
8. Before commencing excavation, locate and protect all underground
services.
9. Before commencing excavation, mark the proposed locations of the S Light pole Site
light poles and cable trenches on-site for Superintendent’s approval positioning
10. Excavate trench straight if possible, and at uniform grade between pits, S Excavation Excavation, min Visual S
personnel access ways, junctions and changes in route, with vertical
sides and uniforms grades. The alignment is in accordance with Western Power Manual DSB 95/3.
11. Install services and equipment and protect from weather, dirt, moisture, S Installation general Protect from Visual S
vandalism and tampering. Provide access for inspection and wea
maintenance. Bed
12. Provide clean sand under and around cables and conduits installed underground. S Cables and conduits
13. Seal buried entries to ducts and conduits using waterproof seals. S Sealing Waterproofing Visual S
20 Evenly balance the connected luminaries across the three phases. S Balance loads Review
21 Carry out all earthing in accordance with the requirements of the supply S authority, the Superintendent and Earthing AS 3000
the regulations set down by AS3000 Wiring Rules.
22 Backfill service trenches as soon as possible after the service has been S ested and inspected in layers < Backfill, tap to AS2648.1
150mm and compact. Install
underground marking tape.
23 Provide and install a suitable light pole footing arrangement to support S Prior to installation Lighting pole
he luminaries and certified by a structural engineer. Provide detailed footings
drawings of the proposed footing for approval prior to construction.
24 Provide and install new lighting columns as detailed on the drawings. In S he event that the lighting location Lighting poles installation Lighting poles
on the drawing does not match the
site conditions, contact the Superintendent for clarification.
31. Paint all electrical equipment including switchboards, poles and light QER Upon completion Painting Visua
fittings unless other wise specified.
32. Prior to practical completion, submit 3 copies of designated documents QER On Practical QA documents Certificate R
including warranties, Electrical Services Quality Assurance Certificate Completion
Practical Completion, as constructed drawings, operation and maintenance manuals, commissioning QER Upon PC Spare parts Liaise
reports, authorities and utilities approvals and the like.
33. Supply spare parts with a copy of the delivery docket signed for
acceptance by the local authority.
34. During the maintenance period, carry out routine maintenance and S During Mainte
inspections and preventive maintenance work in accordance with the operation and maintenance maintenance schedu
manuals an as recommended by manufacturers of supplied equipment. Repair and maintain subject to
breakdown.
35. Following the maintenance period, on final completion, submit ElectricalQER Upon Final QA Certification R
Services Quality Assurance Certificate Final Completion. Completion
36. Submit completed checklist to QER. S R
LEGEND (Column 8 & 10): ‘H’ – Hold Point; ‘W’ – Witness Point; ‘R’ – Document Review; ‘S’ – Surveillance Lot Conforms
These activities have been inspected and are in accordance with the approved procedure. Supervisor: Date: / QER:
/
3 Cut or fill the entire width of the path reserve as necessary. Prepare PS Foundation
foundation, compact and test to depth as per the specifications.
4 Place the clean bedding sand layer to specified thickness and compact PS Bedding sand
to required density.
5 Construct track control joints - Joint spacing at 4.0m intervals (max.) PS Track control Joints 2.15.2
using only cast in-situ “lockjoint” control joints.
6 Construct expansion joints using polyethylene foam expansion joint filler placed every 40 metres in PS Expansion Joints 2.15.2
a straight unhindered path or the start of a deviation of a curve in the path and where the new
path m eets a fixed
object such as another path, a kerb edge or a building.
8 Erect warning signs, lights and barricades to prevent damage from PS Visual
vehicles and pedestrians for minimum 24 hours
9 Verify construction tolerances for the following: PS Submit 2.15
Vertical location in relation to 2% grade line from top of
kerb
Grade access
Surface true to line
Surface irregularities
Spacing of expansion joints
Thickness
Width
10. Submit Checklist and compaction test results to QMR. PS QA file Compliance R
nd Mulching
tion
ction
OJECT NAME
LISTS:
Roads and Maintenance;
practice standards have been assumed;
onmental, safety and project management requirements;
er and enters into the Lot Status Register prior to any work being performed on the lot;
en completed, the nominated signatory must place initials in the signature box;
licable. In such instances the QER or the
x;
e released prior to commencing the next activity. Approval may be obtained on a
signature box.
gned off, the Project/Supervisor and QER signs on the bottom line to certify
OJECT NAME
Insurances Certificate H
Bank Guarantee Certificate H
Review H
Prior to using W
Prior to start H
ITP / Checklist No - 00a
H equipment calibration certificates – validity within 12 months. Submit to
old point H H each batch of bitumen and binder prior to the bitumen being used on Mobilisation
mance
cates
Date: These activities have been inspected and are in accordance with the approved procedure:
Compliance QA file H W
photographic R R
conditions evidence
art Notify on site Induction W W
personnel document
Induction R R
Prior to use on site Hold point H H
release
Prior to Storing on Hold point H H
site release
Compete set of R R
contract
documents
Superintendent approval Hold point release H H
Minutes H
Prior to use TMP Conformance Hold point H H
release
Prior to use TMP amendments Hold point H H
release
Prior to start 1.22.6 Liaise Hold point H H
release
ITP / Checklist No - 04
Daily diary H S
Visual W W 6. Embankment construction material shall be suitable material won from S Cut to fill
Test request H S
Verify results Test results R R
Liaise R R
Lot Status R R
40
ITP / Checklist No - 04
40
ITP / Checklist No - 05
ordance with the specification. QER On receipt Pipe specification Visual, against R R
supply docket
Drg Visual W S
40
ITP / Checklist No - 13
Date: / /
Daily diary H S
Survey pegs H W
s Construction Visual R R
standard
Conduits Visual S S
Mark and protect Approval H W
Visual S S
cover 750mm Max
1100mm
Visual S S
weather
Bedding sand Visual S S
Visual S S
ITP / Checklist No - 13
Identification Visual W W
Review Test R R
AS 3000 Visual S S
AS2648.1 Visual S S
ITP / Checklist No - 13
Visual S S
Match existing Visual S S
Test results W W
requirements
Western
Power
Visual W W
specification
Painting Visual S S
Certificate R R
Maintenance Visual R R
schedule
R R
R R
Lot Conforms Conforming Lot with IR IR No.
QER: Date: / /
ITP / Checklist No - 15
Compact Visual S R
4 m intervals Visual S S
Notice for W W
inspection
Drg, Spec S R
As constructed S S
R W