RISK ASSESSMENT METHOD STATEMENT (RAMS)

Method Statement and Risk Assessment for


Installation of Sanitary wares at AMC Connectivity
Corridors & Concourse Bridge Project, AL Maryah
island, ABUDHABI
Project No-M- 1467

Document Ref No: GEMC-MC-A-MST-0021 Rev 0

Method Statement Title Installation of Sanitary Wares Doc Ref No: GEMC-MC-A-MST-0021
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 1 of 22 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

Project name AMC Connectivity Corridors & Concourse Bridge Project Project No M1467
Main Contractor McLaren Construction Ltd. Document No GEMC-MC-A-MST-0021
Title/Task Installation of Sanitary wares Revision No 00
Document
Date of issue 29/4/2019 Prepared By Syed Faisal
Duration of
Proposed start date 15/5/2019 task 40 week

Contents
Section A Register of Revisions
Section B Scope of Works to be undertaken:
Section C Location of the Project
Section D Location of the Works to be Undertaken with the Project
Section E Site Access/Egress and Access to the Work Zone
Section F Emergency Contacts Details and Procedures:
Section G McLaren Site Specific HSE Safety Induction:
Section H Welfare facilities:
Section I Personal Protective Equipment
Section J Plant/Equipment and tools to be Used
Section K Materials To be used.
Section L Communication/Toolbox Talks/Training Requirements:
Section M Works Permits
Section N Environmental and Waste Management:
Section O Programme for the Works:
Section P Housekeeping and Storage:
Section Q Hygiene and cleanliness
Section R Working At Height
Section S Occupational Health
Section T Sequence of Works/Activities

Appendices

Appendix A Site Logistic Plans and Other Design Information Relative to the Works
Appendix B Crisis/Emergency Plan
Appendix C COSHH Assessments and Material Data Sheets (to be provided by Subcontractor)
Appendix D Risk Assessments (to be provided by Subcontractor)
Appendix E Technical Information (to be provided by the Subcontractor)
Appendix F Risk Assessment

Method Statement Title Installation of Sanitary Wares Doc Ref No: GEMC-MC-A-MST-0021
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 2 of 22 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

Section A - Register of Revisions

Revision Date Reason for Amendment Amended By Signature Has this amendment been briefed
No (Name) to the operatives involved and have
the operatives signed the register.

This method statement has been prepared in conjunction with the following documents;
1. OSHAD regulation and requirements
2. OHSAD- Code of Practices, HSE Regulations, Technical Guidelines, Mechanisms
3. GR HSE Guidelines and Requirements
4. Federal Environmental Authority Law No 24/1999 and its supplements.
5. Federal Labour Law No 8
6. Articles (3,4,5,7) Local Law No 21/2005 (Waste Management)
7. McLaren SHE Procedures
8. McLaren’s site specific SHEQ Plan (including TMMS, SWMP, EPP).
9. McLaren’s Integrated Management System Policy Statement (IMS) .

Section B- Scope of Works to be undertaken:


The work Describes Installation of Sanitary wares at AMC Connectivity Corridors & Concourse Bridge Project, Abu
Dhabi
The following Critical Hazards have been identified during the preparation of the scope of works, please refer to
the Risk Assessments within Appendix D.

1. Manual Handling Injuries


2. Slip Trips and Falls
3. Fall from Height
4. Use of scaffold/ladders
5. Electrocution
6. Use of Power Tools
7.Falling objects

Section C- Location of the Project


Location of the Project;
Our project is located is located AMC CONCOURSE BRIDGE in between Al Maryah and Galleria Mall as marked
below.

Method Statement Title Installation of Sanitary Wares Doc Ref No: GEMC-MC-A-MST-0021
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 3 of 22 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

Method Statement Title Installation of Sanitary Wares Doc Ref No: GEMC-MC-A-MST-0021
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 4 of 22 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

Section D- Location of the Works to be Undertaken within the Project

Add full sketch of the project and mark up your areas of work (logistics plan to be updated)

Method Statement Title Installation of Sanitary Wares Doc Ref No: GEMC-MC-A-MST-0021
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 5 of 22 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

Section E- Site Access/Egress and Access to the Work Zone

Entrance to the Site will be from Gate no 1 as per attached drawing.


(logistics plan to be attached)

Method Statement Title Installation of Sanitary Wares Doc Ref No: GEMC-MC-A-MST-0021
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 6 of 22 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

Section F- Emergency Contacts Details and Procedures:


The following staff from both McLaren and Genfocus will be on site during the execution of the works and will be
responsible for managing the works;
Name Position Company Contact Details
Paul Carlin Operations Director McLaren 056-1054691
Luke Watson Project Manager McLaren 052-1022402
Prabhu Srinivasulu Construction Manager McLaren 050-9709963
Joby John HSE Manager (First Aider) McLaren 050-6372060
Evangeline Huerto First Aider McLaren 056-1852727
Jijo Mathew Safety Advisor/First Aider McLaren 055-2152903
Ramil Magano QA/QC Engineer(Fire marshal) McLaren 050-2923058
Biju MEP Engineer McLaren 056-8059139
Syed Faisal Ahmed Project Manager Genfocus 056-5465814
Anu Baby Project Engineer Genfocus 056-5465807
Mohmmed Jasim Mechanical Engineer Genfocus 056-5268312
Prabir Kumar HSE Officer/First Aider Genfocus 0547937312
Murgan HVAC Supervisor Genfocus 0547937313
In case of an Emergency/fire Alarm, all operatives, Staff and Visitors are required to report to the Assembly Point,
which is indicated on the site logistics drawing, as indicated by the symbol below. Where the registers will be
checked to ensure that no one is un-accounted. No one will be allowed to leave the assembly point until the
Emergency response Controller confirms that it is safe to do so.

1 Assembly Point No-01 (TBA)


2 Assembly Point No-02 (TBA)

Please refer to the attached Crisis/Emergency Plan, (Appendix B) which is to be implemented where the need
arises.
The Qualified First Aiders for the Project are listed below, and the first Aid Boxes will be available either in the
Induction/First Aid Room or in the Main Office.
McLaren: (details of First Aiders ) Subcontractors(Details of First Aiders )
Joby John- 050-6372060 Prabir Kumar 0547937312
Jijo Mathew 055-2152903 Anu Baby 056-5465807

Please see below the Emergency contact details


Authority/Company Contact Telephone No.
McLaren Construction Ltd 04-3417964
Police 999
Ambulance 997
GR Emergency No 058-2864950
AMC Emergency No 056-7459621

Section G- McLaren Site Specific HSE Safety Induction:


Method Statement Title Installation of Sanitary Wares Doc Ref No: GEMC-MC-A-MST-0021
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 7 of 22 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

Prior to any works taking place, all Operatives arriving at AMC project will be required to undergo a
Multiplex/Gulf Related safety induction followed by McLaren Site Safety induction, which will be held in the
induction room, by McLaren’s HSE Representative or other designated person. Once the operatives have received
the site specific safety induction, they then will be briefed on the contents of this RAMS, by their respective Site
Supervisor, from which they will then be required a sign a RAMS Briefing Register (SAF019 UAE) confirming that
they have been briefed and that they fully understand the RAMS and what is expected from them during the
execution of the site works. The Operatives will also be briefed on the Emergency and Security Procedures for the
project, which is also a part of site safety induction programme.
Any operative who will be operating any plant and equipment will be required to produce a copy of their
competency certificate/card carried out by an OSHAD approved third party training provider, to enable McLaren
to issue them with the Plant Operators Authorisation (SAF023 UAE).
Section H- Welfare facilities:
Drinking Water-
Clean drinking water will be provided on site (as per approved Logistics plan) and all operatives are to ensure they
take on enough fluids throughout the day .

Comply with Summer Working Requirements .

Rest areas and toilet-


Rest area and toilets are being provided at site and located as per AMC logistics layout plan

Section I- Personal Protective Equipment (PPE)


The Following Personal Protective Equipment must be worn/be available during the execution of the works
activities

Type of PPE Required Yes No


Safety Helmet (as per standards) Yes
Safety Footwear (as per standards) Yes
Eye protection (as per standards) Yes
Gloves (as per standards) Yes
Hi- viz Vests Yes
Overalls (for operatives only) Yes
Ear protection Yes
Face Respirator No
Body Harness Yes
Respiratory masks No
Others (other specific requirements)
Please ensure that any specific precautions for PPE as identified within MSDS/COSHH assessment or any
specific requirements by supplier/manufacturer are to be complied and adhered to.

List of additional/task specific PPE to be used


1. N/A
2. N/A
3. N/A
4. N/A
Section J- Plant and Equipment to be Used
Method Statement Title Installation of Sanitary Wares Doc Ref No: GEMC-MC-A-MST-0021
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 8 of 22 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

It is anticipated that the following Plant and Equipment will be used during the execution of the works; other
items will also be identified on the schedule below;

 Drilling Machine / Cutting and Grinding Machine


 Ladder/Mobile Scaffold
 Portable Hand Tools

*Note: All relevant competency certificates (as per OHSAD /GR requirements) to be submitted to HSE
Manager/Eng./Advisor prior to start of any activity.

(Below schedule to be completed by subcontractor)


Type of Plant/Equipment to be Used Yes No Type of Plant/Equipment to be Used Yes No
Lifting Yes Cradle No
Mechanical hoist No Excavation shoring No
Mobile elevating working platform No Hand tools Yes
Ladder Yes Electrical tools Yes
Hoist No CAT & Gen Set No
Test Equipment No Ventilation/Extraction Equip No
Task Lighting No Pump No
Scaffolding No Lifting slings/chains No
Mobile scaffolds Yes Mechanical plant No
Podium Scaffold No Others:

Section K- Materials To be used.

Method Statement Title Installation of Sanitary Wares Doc Ref No: GEMC-MC-A-MST-0021
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 9 of 22 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

The following Materials will be utilised during the execution of the works, the Material Data sheets being
provided, which will allow the relevant COSHH assessments to be carried out; (See Appendix C)

Item Material Description Has MSDS been Has the COSHH


provided and Assessment sheet been
attached? completed and attached?
1 Urinals & Fittings N/A N/A
2 Wash basin & Fittings N/A N/A
3 WC & Fittings N/A N/A
4 Accessories N/A N/A

Section L- Communication/Tool Box Talks/Training Requirements:


Once the RAMS has been briefed to the workforce, we will also hold Tool Box Talk relative to the work activities
being carried out, these will be conducted by the HSE team, in conjunction with the relevant site supervisors, this
will ensure that the message gets across to the workforce, in their own language, thus avoiding any
misinterpretation of the RAMS/Toolbox Talk.
During the Preparation of this RAMS the following training for the staff and operatives has been identified;
Item Description Of Training Has the Training been If not, when will be
completed? (Yes/No) completed(Date)
1 Scaffolding inspection and erection Yes

*Note: All relevant certificates will be submitted prior to works commencing or during induction. Where the
training has not been carried out, it must do so prior to the works/activities commencing.

Section M- Works Permits


The following works permits will be required during the execution of the Works;

Item Description of the Work Permit Permit Issued By Tick only applicable
1 Permit to Enter Confined Space McLaren
2 Permit for Lifting Operations. McLaren
3 Permit to Dig McLaren
4 Permit to work Hot cutting or Welding McLaren
5 Permit to Work in Ceiling Void McLaren
6 Permit for Roof Access McLaren

Method Statement Title Installation of Sanitary Wares Doc Ref No: GEMC-MC-A-MST-0021
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 10 of 22 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

7 Permit to Work with Ladders, steps McLaren 


8 Permit to Work at Height McLaren
9 Permit To Work – Electrical above 110V McLaren 
10 Permit To Work with COSHH Items McLaren
11 Permit To Work At External Face of The Building McLaren
12 Permit For Removal of Existing Fall Protections McLaren
Any other permits if required to be added

Section N- Environmental and Waste Management:


During the execution of the project, waste will accumulate. Skips will be provided by McLaren and will be
required to put all waste in the skips provided. All waste will be segregated for recycling as per below sequence
1. Metal
2. Plastic
3. General waste
4. Concrete waste
5. Food waste
6. Hazardous waste
7. Wood Waste
Due to the nature of the works and the actual conditions of the present site, airborne dust will be minimal,
however where necessary the area affected by the installation of the temporary works, the dust will be
suppressed by spraying water.
Drip trays to be placed under plant and generator to catch any excess oil. Approved Waste Collection Contractor
will then remove excess oil from site in oil containers and sent back to store for collection.

Section O- Programme for the Works.


The works will commence on 15-5-2019 For a duration of 40 week, as the works are scheduled to take place
during day light hours, there will be no requirement for any additional lighting
However if Night shift starts, adequate task lighting to be provided by the subcontractor
Section P- Housekeeping and Storage:
Housekeeping will be carried out as and when required and storage of materials will be in an agreed location ( as
per approved site logistics plan) within the segregated area and as agreed in subcontractor prestart meeting. The
subcontractor will remove from site.
Section Q- Hygiene and cleanliness:
Hygiene and cleanliness are the upmost requirements for the project. All works carried out within the catering
facility should comply with Etihad’s catering Hygiene Procedures and requirements. Compliance of PPE pertaining
to Hygiene and cleanliness to be strictly complied.
Section R- Working at Height
During the preparation of the RAMS, the following activities for working at height have been identified and have
been addressed within the risk assessments within Appendix D. ( to be filled if applicable to your works)

Item Activity Risk Assessment Reference


1 Installation of Sanitary ware Refer attached risk assessment

Method Statement Title Installation of Sanitary Wares Doc Ref No: GEMC-MC-A-MST-0021
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 11 of 22 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

Section S- Occupational Health


During the preparation of the RAMS, the following Occupational Health items have been reviewed and addressed
within this Method Statement.
Item Description of OH Item Preventative Measures, (see also within the Risk Assessments)
1 Bad Back/sprain due to improper All Operatives will be briefed on correct lifting techniques and
Manual handling avoid heavy lifting altogether
2 Hand/Arm Vibration N/A
3 Construction dust Area will be watered to minimise dust
4 Noise N/A
5 Sun Operatives will be required to wear long sleeve and pants to
avoid direct sunlight UV rays and drink plenty of water to avoid
dehydration
6 Skin Coveralls and gloves required at all times

Section T- Sequence of Works/Activities


The works will be carried out in the following sequences; (Subcontractor to detail out the sequence of work, from offloading the
materials at site to final fix including safety precautions taken during the sequence of works )

1 RAMS to be briefed to all the operatives involved in the work


2 STARRT card to be prepared by assessing the area of work prior starting the work.
3 Supervisor to ensure all operatives have received a McLaren site basic induction
4 Supervisor to ensure all operatives have adequate PPE for the job including Full body harness.
5 Supervisor to ensure all operators having Competent certificate.
6 Supervisor to ensure that the site is clean and ready to start the work
7 Supervisor to ensure adequate tools are provided and should be visibly clean and tidy. Advise Site manager
if more tools are needed.
8 Supervisor to ensure that all materials taken into the facility are covered and equipment’s to be used are
clean & coordination of time for access has been agreed.
9 Supervisor to ensure that all operatives have done proper hand wash prior to entering any Production/
Processing area.
10 Supervisor to ensure that all hygienic PPE has been issued & being worn correctly.

Method Statement Title Installation of Sanitary Wares Doc Ref No: GEMC-MC-A-MST-0021
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 12 of 22 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

11 Supervisor to ensure that proper barricade and warning signs are provided before starting any activity.
Proper Barricading to be provided for all Ceiling cutting or dust forming activity, and this barricading will be
provided with scaffolding drops with thick plastic sheets around the area to be sealed properly.
12 Supervisor to ensure proper working platforms such as ladders and scaffoldings are been used and make
sure that all the working platforms are having permit to work.
13 Supervisor to ensure that Competent workers are involved for scaffolding erection, dismantling and
inspection.
14 Transportation to site will be as per site requirement. Timing to be agreed with Mclaren
15 Ensuring that unloading of materials is undertaken in designated area.
Make sure that the lifting equipment is adequately rated for the specified weight (shown on the rated
16
plate).
17 When offloading the materials precaution to be taken to avoid damages
18 Procedures
18.1 Off-loading & Handling of Materials
Materials (Sanitary wares & accessories) will be offloaded from the vehicle manually at site store. Store in
18.1.1
charge / Supervisor to ensure that off load material load is not exceed 20kg/ person
Ensure the unloading area shall be free from debris, levelled and necessary wooden blanks are provided to
18.1.2
keep it properly.
Supervisor/store keeper shall examine thoroughly and ensure that it is free from defects and is
18.1.3
conformance with approved material submittals and required quantities.
18.1.4 Material inspection request to be submitted for McLaren / GHD Approval
18.1.5 Materials will be stored on a flat surface & properly covered and necessary stock registers is maintained
Once the MIR is approved, required quantities and accessories will be manually shifted to work place
18.1.6
through material movement route.
18.2 Installation of Wall Hung Toilets & Disabled Toilet Suite.
Ensure that the work area is ready and safe to start the installation of water closets and all clearances are
18.2.1
obtained.
18.2.2 Ensure the relevant current / approved shop drawings are available with installation team.
Ensure the concealed cisterns and accessories are installed & tested and surface works are completed.
18.2.3
Ensure water flush inlet to WC (water closet) connections shall be completed with suitable fittings.
18.2.4 Drainage pipes shall be positioned properly to receive the WC connector
WC pan shall be mounted on Floor and mark the location of fixing points. Holes made on the floor for
18.2.5
screwing supplied along WC.
18.2.6 Ensure that WC connector rubber seal is correctly located on rim of connector.
18.2.7 Lubricate WC spigot & rubber seal, insert into connector and push together.
Cistern Flush outlet connection shall be done to the WC pan. Flushing Push buttons shall be Installed on
18.2.8
wall surface.
Grab Rails for the Disabled WC will be installed as per the specified location and heights by anchor to the
18.2.9
wall.
18.2.10 Shower spray installations & water supply termination shall be done.
18.2.11 Toilet tissue dispensers will be installed in each toilet screwing to the wall

Method Statement Title Installation of Sanitary Wares Doc Ref No: GEMC-MC-A-MST-0021
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 13 of 22 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

18.2.12 All Joints in the floor/wall shall be sealed with water proof sealants after commissioning works.
18.3 Installation of Console Lavatory and Wall Hung Lavatory.
18.3.1 Water supply & Drainage arrangements shall be made clear & Tidy.
Using basin templates, correct position of wash basin to be determined and necessary cutting shall be
18.3.2
done on the top cover for correct seating of lavatory basins.
18.3.3 Bracket with toggles shall be tightened by screwing on the wall.
18.3.4 Placing the basin on the panels/frames carefully and rim joints shall be properly sealed.
Angle valves shall be installed and necessary connection shall be made to hot/cold water. Drainage will be
18.3.5
connected through P-traps.
18.3.6 Air Blade Tap shall be installed on basin plug hole and shall be secured with washers/gaskets.
18.3.7 Automatic soap dispenser will be installed near the Console lavatory.
Disabled toilets Wall hung lavatory, brackets will be installed by screwing on wall and carefully places the
18.3.8
basin on the supports.
Lavatory faucet will be installed with proper gaskets and terminate the hot/cold water supply. Drainage
18.3.9
will be connected through bottle trap.
18.3.10 Soap dispenser for wall hung lavatory will be installed near to the basin.
18.4 Installation of Urinals & Partitions.
Ensure the concealed outlet points, water supply provisions, concealed urinal flush valves are installed &
18.4.1
tested and surface works are completed.
Urinal bowl supports to be mounting to wall as per manufacturer templates drawings and carefully
18.4.2
position the urinal on the wall hanger.
Install the flush valve, strainers are as per the manufacturer illustrations. Install the drain pipes & gaskets
18.4.3
and secure with urinal by screws and washers.
18.4.4 Steel cover plate for the ECOEFV concealed urinal system shall be installed on wall surface.
18.4.5 Urinal partitions shall be fixed by screwing to the wall.
18.4.6 Seal the gap between wall & partitions/urinals shall be done.
18.5 Installation of Kitchen sink
18.5.1 Water supply & Drainage arrangements shall be made clear & Tidy.
Using sink templates, correct position to be determined and necessary cutting shall be done on the top
18.5.2
cover for correct seating of sink.
18.5.3 Bracket with toggles shall be tightened by screwing on the wall/bottom supports.
18.5.4 Placing the sink on the top cover carefully and rim joints shall be properly sealed.
Kitchen faucet shall be installed and necessary connection shall be made. P-trap will be connected to the
18.5.5
drainage out lets.
18.6 Installation of Hand Dryers
Ensure that the work area is ready and safe to start the installation of Hand Dryers and power supply point
18.6.1
is ready.
Dryers base frame shall be screwed to the wall and power supply shall be terminated by a competent
18.6.2
technicians.
18.6.3 Dryer shall be firmly fix to the base frame.

Method Statement Title Installation of Sanitary Wares Doc Ref No: GEMC-MC-A-MST-0021
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 14 of 22 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

APPENDIX A

Site Logistics Plan


Method Statement Title Installation of Sanitary Wares Doc Ref No: GEMC-MC-A-MST-0021
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 15 of 22 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

APPENDIX B

Method Statement Title Installation of Sanitary Wares Doc Ref No: GEMC-MC-A-MST-0021
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 16 of 22 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

CRISIS PLAN

CRISIS PLAN

1. Upon an incident, being discovered the first member of McLaren’s staff or the site operative
discovering the incident shall inform the Project Manager and Site HSE team through AMC Project
emergency Contact No-056-7459621.

2. Both the HSE Engineer/advisor and the First Aider are to attend the scene with their mobile. The
project Manager or authorised person waits in office ready to contact relevant emergency
services.

3. Both the HSE Engineer/advisor and the first Aider are to assess the situation and put in place the
relevant systems to end/deal with the emergency.

4. Both the HSE Engineer/advisor and the first Aider are to ensure all trades are gathered at the
assembly point and liaise with supervisor to account for all operatives - no person should leave
site.

5. Either the HSE Engineer/advisor or the first Aider phones the project Manager or site receptionist
and informs him/her of which emergency services are required.
Method Statement Title Installation of Sanitary Wares Doc Ref No: GEMC-MC-A-MST-0021
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 17 of 22 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

6. The Project Manager calls all relevant McLaren staff.

7. Both the HSE Engineer/advisor and the first Aider waits for the emergency services at scene.

8. Once emergency services arrive, The Project Manager will telephone the relevant authorities, i.e.
the HSE/Client’s Safety Advisor/QHSE Manager/McLaren’s operations Director.

9. Both the HSE Engineer/advisor and the first Aider keep trades informed of the situation and
releases trades to return to work or leave site only when emergency services or The Project
Manager instruct that it is safe to do so, and all names of witnesses are recorded.

10. Project Manager or Construction Manager are to arrange for photographs of the scene to be
taken, and if necessary the area to be cordoned.
A full investigation of the Incident is to be carried out, with a written report being submitted the
SHEQ Director, as soon as practicably possible after the incident, including all witness statements,
11. photos of the scene, induction and method statement records, recommendation to prevent a re-
occurrence and what action has been taken since the incident taking place.

APPENDIX C

COSHH ASSESSMENTS AND MSDS

Method Statement Title Installation of Sanitary Wares Doc Ref No: GEMC-MC-A-MST-0021
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 18 of 22 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

(Attach if any)

APPENDIX- D

RISK ASSESSMENTS

Method Statement Title Installation of Sanitary Wares Doc Ref No: GEMC-MC-A-MST-0021
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 19 of 22 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

APPENDIX-E

TECHNICAL INFORMATION
Method Statement Title Installation of Sanitary Wares Doc Ref No: GEMC-MC-A-MST-0021
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 20 of 22 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

Method Statement Title Installation of Sanitary Wares Doc Ref No: GEMC-MC-A-MST-0021
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 21 of 22 RISK ASSESSMENT METHOD STATEMENT

SAF009 08/13 rev B RISK ASSESSMENT &METHOD STATEMENT EVALUATION SHEET


Add project/client logo
RISK ASSESSMENT METHOD STATEMENT (RAMS)

Method Statement Title Installation of Sanitary Wares Doc Ref No: GEMC-MC-A-MST-0021
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:

SAF-098 (UAE) 09/16 Rev G 22 of 22 RISK ASSESSMENT METHOD STATEMENT