Sie sind auf Seite 1von 5

REDUCING WIP INVENTORY BY IMPLEMENTING LEAN TOOLS

T.NITHISH BABU, R.GOUTHAM

FINAL YEAR M.E. INDUSTRIAL ENGG,PSG COLLEGE OF TECHNOLOGY,COIMBATORE.

ABSTRACT: Inventory is the worst form of all the seven wastes of Lean Manufacturing.
It is making products in too great a quantity or before it is actually needed leading to
excessive inventory. Principle of Lean Manufacturing is application of what is
required and when is required by the customer, pulling only what is ordered through
the work flow. Heavy inventories lead to cash crunch leading to failure of business
houses as lot of money has already been put in the inventory lying idle. All of this is a
cost to business and can be converted to useful savings and uplifting the profits. The
objective of this study was to apply lean manufacturing techniques to a production
job shop environment to reduce the lead time from the current average to an
acceptable average established by customer demand. To accomplish the objective,
the following procedure was followed. The independent variable was identified as the
manufacturing process. Dependent variables were lead time, WIP, and material flow.

KEY WORDS: WIP inventory, Lean Manufacturing principles.

INTRODUCTION: three sources of loss: waste, variability


and inflexibility.
Lean manufacturing is a production Lead time is the difference between
philosophy that strives to eliminate the times recorded as the product is
waste in all activities within an released as a raw material, and when
organization. The elimination of waste the product is completed. Reduction in
allows a product to flow through the lead time allows the manufacturer to
manufacturing process in smaller more quickly recover investments in
quantities than that required by the time and material. Lean manufacturing
batch and queue process. Lean addresses lead time by removing non-
manufacturing incorporates a pull value-added steps that create waste in
system to move the product through the production cycle. Every value
the production process. According to added and non value added activity
the lean operating system consists of required to bring a product through the
the following: production flow from raw material to
• A lean operating system follows the customer is called the value
certain principles to deliver value to the stream. The purpose of value stream
customer while minimizing all forms of mapping is to highlight the sources of
loss. waste and eliminate them by
• Each value stream within the implementation of a future state value
operating system must be optimized stream. The current-state value stream
individually from end to end. map establishes a baseline of the
• Lean tools and techniques are current process under investigation.
applied selectively to eliminate the Work In Process (WIP) causes the
most non value added time during a 2. Lean refers to the total enterprise,
production process. Mass production from the shop floor to the executive
techniques group equipment by similar suite, and from the supplier to
function not by product groups, which customer value chain;
create material inventories at each 3. Lean requires rooting out everything
operation. Production facilities that use that is non- value added; and
the mass production strategy have 4. Becoming lean is a complex
equipment located in all areas of the business - there is no single thing that
plant. Plant layouts following this will make an organization lean.
strategy create physical distance Burton and Boeder (2003) reported the
between subsequent operations. five lean manufacturing principles are
Storage racks or staging areas are as under:
necessary because products flow 1. Accurately specific values from the
through the facility in large lot sizes customer’s perspective for both
waiting for the next operation. products and services.
2. Identify the value stream for
LITERATURE REVIEW: products and services and remove
non-value-adding waste along the
Lean is a systematical approach to value stream.
identify and eliminate waste through 3. Make the product and services flow
continuous improvement following the without interruption across the value
product at the pull of customer in stream.
pursuit of perfection. In lean 4. Authorize production of products
manufacturing, the value of product is and services based on pull by
defined solely by the customer[1]. Goal customer.
of lean manufacturing is to reduce the 5. Strive the perfection by constantly
wastage in any form such as human removing the waste.
effort, inventory, time to market, space Chrisrmansson et al (2002) discussed
to become highly responsive to a material kitting case study using
customer demand. Value added alternative methods like picker to –
activities make the product more material principle and material – to –
closely resemble what the customer picker approach. The material kitting
wants. Non value Non-value added was video recorded and pickers
activities do not create customers physical exposure were assessed. The
value. Anything that is not adding material kitting shows improved
value is defined as waste. productivity as compared with other
Womack et. al, (1990) explained the kitting methods[3]. The analysis and
several features of lean, According to evaluation of the effect of process
studies that were initially performed in parameters on the performance of
the automobile industry [2]. manufacturing systems were done
1. Lean is a dynamic process of using two softwares Arena 10.0 and
change driven by a systematic set of SPSS 9.0 statistical package by Ekren
principles and best practices aimed at and Ornek[4].
continuously improving;
3. CASE STUDY:
The project was done at an Sri Krishna the influence of an efficient layout on
Techno Components Private limited to the manufacturing function: it makes it
improve productivity & WIP inventory. smooth and efficient. Operating
efficiencies, such as economies in the
STATEMENT OF PROBLEM : cost of handling materials,
 Excessive Waiting time and minimization of production delays and
transportation time of materials avoidance of bottlenecks all these
in various stages of the process depend on a proper layout.
 Large WIP inventory and
finished goods inventory
 Lack of maintenance of
machines leading to higher
downtime
Objectives:
 To Reduce the transportation
and waiting time by optimizing
the layout.
 To reduce the inventory by
providing conveyor system for
transportation.

METHODOLOGY:

FIG 2. AS-IS model of the plant

TIME STUDY DATA OF CASE


GOVERNOR:

Fig 1. Methodology
4. ANALYSIS:

Factory Layout:
The importance of a layout would be
better appreciated if one understands
Table 1. Time study data
 In process inventory (i.e. WIP )
LAYOUT OPTIMIZATION may be improved by
 The proper set up of layout or
implementing material handling
machine orientation will help
reduce the NVA time system like conveyor
 Witness simulation can be  Preventive maintenance may
used to predict the performance
help reduce downtime
improvement of modified layout
and inclusion of conveyor
system
 The performance measures like
mean waiting time, mean flow
time(LT),Travel distance and
cycle time for each component
are to be checked.

FIG 4. FUTURE STATE VSM

INFERENCES FROM FUTURE


STATE VSM:
Total lead time =1548 min

FIG 3. CURRENT STATE VSM VA time=86 min


WIP=375 min
The work in process inventory time
Inferences from current state VSM and the total lead time of the process
Total lead time =1870 min is reduced by optimizing the layout and
VA time=90 min by removing the unwanted process in
WIP=439 min the system.
 The large lead time is due to ARENA MODEL:
high finished goods waiting to The simulation is done using arena
dispatch and raw material software. It is an user friendly software
that enables data input and analysis
waiting to process this can be used to simulate any
 Lack of proper transportation manufacturing system and therefore
facility to supplier and customer we have used arena to simulate
aluminium die casting process, the
process model and details are as CONCLUSION:
follows: Our main objective was to reduce the
work in process inventory using
various lean tools and also the
manufacturing cycle time has been
reduced by line balancing and value
stream mapping. The simulation model
was used to improve the performance
of the existing system there by
increasing the productivity of the plant.

REFERNCES:

Fig 5. Simulation model 1. Burton, T.T., Boeder, S.M., “The


The simulation results Lean Extended Enterprise: Moving
VA time – 71 % beyond the Four Walls to Value
Stream Exellence,” APICS, The
NVA time – 29 %
education society of resource
WIP – 34 numbers management (2003).
2. Womack, J.P., and D.T. Jones,
“From Lean production to the Lean
RESULTS:
Enterprise”, Harvard Business Review,
Thus, by various implementation of pp. 93-103(1994).
lean tools, the lead time for the 3. Chrisrmansson, M., Medbo, L.,
Hansson, G.A., Ohlsson, K., Unge, J.,
process is reduced by 15% and the
Bystrom, Moller, T. and Forsman, M.
inventory in the plant has been “A case study of a principally new way
reduced to the optimum level thereby of materials kitting –an evaluation of
reducing the WIP inventory. The time consumption and physical
workload”, International Journal of
proposed model coupled with process
Industrial Ergonomics, Vol. 30, pp. 49-
control has the potential to achieve null 65,2002.
defect castings at the least cost. This 4. Ekren B. Y. and Ornek A. M., A
Simulation based experimental design
work gives up many challenges that
to analyze factors affecting production
need a new generation of researchers flow time”, Journal of Simulation
to come forward and help the mother Modeling Practice and theory, 16,
2008, 278-293.
of all industries.

Das könnte Ihnen auch gefallen