Beruflich Dokumente
Kultur Dokumente
Payback Period
2
Time value of money
Denote r: interest rate/rate of return/ Present 1$
opportunity cost of capital (the loss of After 1 year 1$.(1 + r)
potential gain when financing for project
After t year 1$.(1 + r)t
instead of other investment chances.
3
Investment criteria for project appraisal
Net
present
value
(NPV)
Benefit/
Cost ratio
(B/C)
Internal
Payback
rate of
Period
return
(Tpp)
(IRR)
4
1. Net Present Value (NPV)
Denote:
5
1. Net Present Value (NPV)
n
B0 B1 Bn Bt
PV ( B) = + + ... + =∑
(1 + r ) (1 + r )
0 1
(1 + r ) t =0 (1 + r )
n t
n
C0 C1 Cn Ct
PV (C ) = + + ... + =∑
(1 + r ) (1 + r )
0 1
(1 + r ) t =0 (1 + r )t
n
t t
Bt Ct
NPV = PV(B) - PV(C) = ∑ t
−∑ t
t=0 (1+ r) t=0 (1+ r)
Or
(B0 − C0 ) (B1 − C1 ) (Bn − Cn )
NPV = 0
+ 1
+ ...+
(1+ r) (1+ r) (1+ r)n
n
(Bt − Ct ) n NCFt
=∑ t
=∑ t
t=0 (1+ r) t=0 (1+ r)
6
The cash flows are given as below with discount rate of 15% per year
36 36 836
PV (B) = + +
(1+ 0.15)1 (1+ 0.15)2 (1+ 0.15)3
= 31.3+ 27.2 + 549.7 = 608.2
PV (C) = 650
NPV = PV(B) - PV(C) = 608.2 - 650 = −41.8 $800
$36 $36
$36
0 1 2 3
- $650
7
Using with Excel
Use function Fx/ Financial/NPV:
8
Using with Excel
9
Decision Rule 1 of NPV
• Do not accept any project unless it generates a positive
NPV when discounted by the opportunity cost of funds.
o NPV = 0: investors can expect to recover their incremental
investment and also earn a rate of return on their capital that
would have been earned elsewhere and is equal to the private
discount rate used to compute the present values à investors
would be neither worse off nor better off than they would have
been if they had left the funds in the capital market.
o NPV > 0: investors can expect not only to recover their capital
investment, but also to receive a rate of return on capital
higher than the discount rate.
o NPV < 0: investors cannot expect to earn a rate of return equal
to the discount rate, nor can they recover their invested capital.
10
Decision Rule 1 of NPV
An investor has 4 independent investment opportunities without
budget constraint. All projects are discounted by equity's cost of
capital. Which one is chosen?
11
Decision Rule 2 of NPV
Within the limit of a fixed budget, choose the subset of the
available projects that maximizes the NPV.
• Suppose the following set of projects describes the investment
opportunities faced by an investor with a fixed budget for capital
expenditures of $4.0 million. All projects are discounted by equity's
cost of capital. Which one is chosen?
• Perpetuity
• Annuity
14
Perpetuity
o r: discount rate
P
PV ( P) =
r
15
Annuity
• An annuity (denotes as A) is a cash flow stream in which
the cash flows are equal and occur at a regular interval.
• Types of annuity:
o Ordinary annuity: the equal payments are made at the end
of each compounding period starting from the first
compounding period.
o Annuity due: the equal payments are made at the
beginning of each compounding period starting from the
first period.
o Deferred annuity: the first payment is deferred a certain
number of k compounding periods after the first.
16
Present value of ordinary annuity
Denote art as equal-payment-series present-worth factor
A A A 1− (1+ r)−t
PV (A) = 1
+ 2
+ ...+ t
= A.[ ] = A.ar
t
A A A A A A
……………
Year
0 1 2 3 4 …………… t-1 t
t periods, (t – 1) payments
of ordinary annuity
18
Present value of deferred annuity
r r(1+ r)t
k deferment periods A A A A
……………
Năm
0 1 2 3 4 …………… t-1 t
t periods, (t –k) payments
of ordinary annuity
19
Ordinary annuity applications
• Calculate annually equal cash flows (e.g., loan repayment method
as even total repayment (interest and principal)).
à Use function Fx/ Financial/PMT: PMT(rate,nper,pv,fv,type)
o Rate : interest rate
o Nper : number of payments
o Pv : present value (loan amount).
o Fv : future value, or the amount left after final principal payment is
made. If not, it is assumed “Fv = 0” in Excel.
o Type : number 0 or 1, refer to the point of payment time. In Excel, it is
assumed as ending of each period if typing 0 or untying; as beginning
of each period if typing 1.
20
Advantages and disadvantages of NPV
• Advantages:
o Maximize investors’ benefits
o Take account the time value of money and risk into
decision-making.
o Consider all cash flows of projects.
o Be able to plus and minus NPV of projects with same
lifetimes.
• Disadvantages:
o Require the guesswork about the project's cost of capital.
o Not useful for comparing projects with different lifetimes.
21
2. Internal rate of return - IRR
• The rate of return:
E.g. Buying a flat and selling it after 1 year. Investment cost C0 =
$350.000. Cash inflow in year 1: C1 = $400.000
22
Internal rate of return - IRR
( Bt − Ct )
n
IRR = r => NPV = ∑
*
=0
t = 0 (1 + r )
* t
23
Decision rule of IRR
Denote MARR as the cost of capital or minimum acceptable
rate of return.
• Good project: NPV ≥ 0 ó IRR ≥ MARR
• Bad project: NPV < 0 ó IRR < MARR
NPV
NPV
IRR
Discount rate %
24
Calculating IRR = ?
Year 0 1 2 3
Cash flow ($000) -350 +16 +16 +466
• IRR is the discount rate at which the NPV of all the cash
flows equal zero. Hence:
⇒ IRR = ?
25
Calculating IRR = ?
• Calculating by interpolation:
o Choose r1 so that NPV1 > 0
o Choose r2 so that NPV2 < 0 (r1 < r2)
(r2 − r1 )NPV1
IRR = r1 +
( NPV1 + NPV2 )
26
A – Advantages of IRR
27
“Safe level” of IRR
Year 0 1 2 3 4 5
NCF ($ million) -22 +15 +15 +15 +15 -40
à IRR = 6% or 28%
29
B – Disadvantages of IRR
NPV
IRR = 6%
IRR = 28%
Discount rate %
NPV
30
B – Disadvantages of IRR
31
B – Disadvantages of IRR
0 1 2 3 4 5 IRR NPV@8%
0 1 2 3 4 IRR NPV@7%
A -350 +400 14.29% +24
B -350 +16 +16 +16 +466 12.96% +59
32
B – Disadvantages of IRR
NPV lines of 2 projects intersect at the interest rate of 12.26% (crossover rate).
• If MARR > 12.26% à IRRA > IRRB and NPVA > NPVB à choose project A
• If MARR < 12.26% à IRRA > IRRB but NPVA < NPVB à which project is chosen?
NPV
B
A
IRRA = 14.29%
0
12,26%
r%
33 IRRB = 12.96%
3. The ratio of Benefit and Cost (B/C)
PV(Benefit)
B/C =
PV(Cost)
B (B – C)
34
Normal B/C
B
PV(Cash inflows)
B/C =
PV(Cash outflows)
PV(Operating cash inflows)
=
PV(Operating cash outflows + Investment cashflows)
35
Adjusted ratio of Benefit and Cost (Adjusted B/C)
(B – C)
Adjusted B/C is the ratio of
present value of net operating
cash flows (benefits) and
present value of investment
costs.
36
Decision rule of B/C
• Good project:
PV(B)
B/C = ≥1
PV(C)
• Bad project:
PV(B)
B/C = <1
PV(C)
37
A – Advantage of B/C
38
B – Disadvantages of B/C
39
B – Disadvantages of B/C
Project A Project B
Present value of benefits (B) 2000 2000
Present value of operating costs (C) 500 1800
40
4. Pay-back Period
41
Calculating Tpp
• Base on net cash flow NCF without consideration to the
time value of money à payback period
42
Calculating Tpp
0 1 2 3 4
43
Calculating Tpp with discount rate r of 10%
0 1 2 3 4
44
Decision rule of Tpp
Tpp < T*
45
A - Advantages of Tpp
• Easy to calculate:
o Just basing on net cash flow or discounted net cash flow can
know about the time to recover investment cost.
• Be a good indicator in case of high-risk projects and investment
costs needed to be recover soon
o A project with short payback period can improve the liquidity
position of the business quickly. The payback period is
important for the firms for which liquidity is very important.
o An investment with short payback period makes the funds
available soon to invest in another project.
o A short payback period reduces the risk of loss caused by
changing economic conditions and other unavoidable
reasons.
46
B - Disadvantages of Tpp
47
Comparison of using all criteria
48
References
49