Sie sind auf Seite 1von 5

ALLOCATING ENERGY WHEELING COST IN A DEREGULATED

ENVIRONMENT

K T. Akindeji*

* Durban University of Technology, Dept. of Electrical Power Engineering, 71 Steve Biko Road,
Durban 4000, South Africa. E-mail: kayodea@dut.ac.za

Abstract: Correct pricing of transmission services in a deregulated environment is vital to power


systems operation, security, and development. This paper presents a viable and economic method of
allocating energy wheeling cost for this purpose. The proposed method reflects the actual system
operating condition, therefore allow the transmission provider to recoup the fixed and operating costs
of the network. The paper includes test results on a 6-bus system and 24-bus model of Nigerian 330kV
power network.

Keywords: Energy Wheeling, deregulation, power flow.

1. INTRODUCTION political consideration could also play major roles in


determining transmission prices.
The power industry has moved rapidly from regulated
convectional setup to a deregulated environment [1]. The Some existing pricing methods, such as postage stamp,
former existed as a monopoly, where the same company contract path, boundary flow, line-by-line, megawatt mile,
generates, transmits and distributes electrical energy. All are considered to be more suitable for applications in
electrical energy consumers were required to purchase vertically regulated utilities, where transmission access is
their energy from the local monopolistic power company not open [4]. Generally, pricing of any service or product
since there was no alternative. Some of the drawbacks to without regard to political considerations, seeks to [5]:
this arrangement are operational inefficiency, unreliable • Increase customer value by providing a wider
power supply, and wrong costing method. However, a variety of services and price options;
number of countries have implemented or are • Promote economic efficiency by ensuring that the
implementing a free market power industry in recent years. value of service and the cost of service are
It is strongly believed that deregulation will have profound balanced;
important implications on technology within the electric • Change customer consumption patterns where
power industry and the operation of industrial systems [2]. appropriate to improve the utilization of existing
resources;
Deregulation changes how energy transaction and costing • Encourage service use for application where it is
are carried out in power system operations. While the the least cost option and discourage its use where
consumers are required to pay whatever price the regulated it is not.
utility offers, deregulation allows for negotiation between Pricing transmission services to account for the above
the generating company (GENCO) and the distributing might be difficult but becomes easy when necessary tools
company (DISCO). With this change, customers have the and data for evaluating the economic impacts of providing
option to purchase services and energy from different transmission services are obtainable. The proposed method
sources. Therefore, in a deregulated power system, is a hybrid of the megawatt-kilometre and the short-run
transmission of electrical energy is treated as a separate marginal cost methods. The former recoups existing and
business to create a fair competition among producers of reinforcement costs while the later covers the operating
electricity [1]. cost of the system. In section 2, the proposed method as
well as its components are presented with explanations.
The general definition of wheeling is the transmission of Section 3 shows the applications of the proposed method
electrical energy from a seller to a buyer through the on a 6-bus network and the 24-bus model of Nigerian
transmission lines which maybe owned by a third party [3]. 330kV power network. Discussions and conclusions
Pricing of transmission services plays a crucial role in follow in section 4.
determining whether providing transmission services is
economically beneficial to both the wheeling utility and 2. PROPOSED METHOD
the wheeling customers. However, it is important to realize
that pricing of transmission services, although a technical 2.1 Short –run marginal cost (SRMC)
issue is not wholly an engineering problem. Engineering
analysis which deals mainly with determining the In the short-run marginal cost, the marginal operating cost
feasibility and the cost of providing transmission services of the power system due to a transmission transaction is
is only one of the many considerations in the overall calculated first. Marginal operating cost is the cost of
process of pricing transmission services. Market and accommodating a marginal increase in the wheeling
transaction. When the objective function is a cost function,
the marginal costs are obtained for each node of the system 𝑃𝑔 = 𝑃𝑑 + 𝑃𝑙 (3)
with the aid of an optimal power flow (OPF) for small
changes around an operating point. As the srmc method
applies to the short run, investment costs remain constant where:
and can hence be considered as fixed costs [6]. The srmc
takes into account only the operating cost of the power Pd = the total load of the system
system. This operating cost includes fuel cost, cost of
transmission line losses as well as system constraints. In Pl , = the transmission losses of the system.
order to incorporate all these in any transaction, an OPF
solution of the problem is required. The power flow equation of the power network is given by

An OPF solution gives the active and reactive power


𝑃𝑖 (|𝑣|,𝛿)−𝑃𝑁𝑒𝑡
𝑖
generated and consumed at each bus and the nodal prices.
The nodal prices are of special interest because they reflect 𝑔(|𝑣|, 𝛿) = | 𝑄𝑖 (|𝑣|,𝛿)−𝑄𝑁𝑒𝑡
𝑖
| =0 (4)
the marginal generation and load at each bus. These prices 𝑃𝑚 (|𝑣|,𝛿)−𝑃𝑁𝑒𝑡
𝑚
are also called locational prices and are found to be the
optimal prices, maximizing social welfare and taking Pi and Qi are respectively calculated real and reactive
transmission constraints into account. They can provide powers for PQ bus i; PiNet and QiNet are respectively
the right incentives to market players and to society [7]. specified real and reactive powers for PQ bus i; P m and
PmNet are respectively calculated and specified real power
The MATLAB Package (MATPOWER 3.2) was used to for PV bus m. |v| and δ are voltage magnitude and phase
solve the OPF problem. The OPF was solved before and angles of different buses.
after the wheeling transaction. After these solutions were
obtained, the SRMC for the wheeling transactions were 2.2 Megawatt-km (Mw-km)
found using equation (1).
Megawatt-km method requires two power flow
𝑠𝑟𝑚𝑐 = ∑(𝐵𝑀𝐶𝑖 × 𝑃𝑖,𝑡𝑟𝑎𝑛𝑠𝑎𝑐𝑡𝑖𝑜𝑛 ) (1) calculations, one without the wheeling transaction and
another one with the wheeling transaction. The Newton –
Raphson technique (formulated in polar form) was used in
where: this work. The first step is to establish the base case for the
test systems. The Megawatt-km method requires that two
BMCi = bus marginal cost of bus i power flow programmes be executed successively, this
involves solving the power flow problem without
Pi,transaction = net power injected at bus i due to the wheeling considering any transaction and computing the voltage
transaction. (Power generation at bus i after transaction - magnitude, voltage phase angle at each bus and the power
power generation at bus i before transaction). flow on each transmission line. The next step is to include
any available transaction one at a time. This requires that
The expression in parenthesis in equation (1) was the generator and load bids be included at the appropriate
computed in a tabular form for all generator buses and the buses. The Megawatt-km is calculated for every
sum calculated to give the wheeling cost of the transaction. transmission line by multiplying the MW flow on it by its
length in km for both power-flow cases. The wheeling cost
Optimal Power Flow (OPF) Formulation: The objective is thus obtained as;
of the OPF is to minimize the operation cost for a given
transaction such that the power flow equations are satisfied
𝐸𝐺 ∑(∆𝑀𝑊−𝑘𝑚)
and no limit is violated. For a given power system network, 𝐶𝑇 = ( )( ∑ 𝑀𝑊−𝑘𝑚
) (2)
8760
the objective is to minimize the cost function subject to

where:
𝐹 = ∑𝑛𝑖=1 𝑓𝑖 (𝑃𝑔 ) (2)
EG = existing transmission cost (fixed)
where:
8760 = number of hours in a year
F = the optimal cost of generation
Three options exist for calculating the impact of the
fi(Pg) = the fuel cost of the ith generator wheeling transaction on the power system network as
follows [8].
n = total number of generators connected in the network. (a) The negative and positive changes in power flow (∆
The cost is optimized with the following power system MW) on all lines are added together. The wheeling cost is
constraint; correspondingly small and may have negative value. It
might not be economical because of the small or negative
value.
(b) The absolute value of changes in powers, │∆ MW│ are
added to obtain the wheeling costs. This might not be fair
because of the high cost.
(c) Negative ∆ MW changes are ignored and only positive
∆ MW are used in computing the sum of the changes in
MW. The option described in (c) was used in this work in
order to have an economical and fair wheeling cost.

2.3 The hybrid

The proposed method is a hybrid of the two methods


explained above. Considering the fact that a wheeling cost Figure 2: Single-line diagram of 24-bus model of
should enable participants (buyers and sellers of electrical Nigerian 330kv Network
energy) to make efficient wheeling decisions based on
operating costs, embedded capital, and power security [3]. 3.1 Wheeling Cost Calculation for 6-Bus Network
The revenue collected through srmc method generally falls
far short of the cost of transmission reinforcements but Two wheeling transactions were simulated as follows and
accounts for the operating cost. The mw-km on the other applied to all the methods;
hand, consider only the costs of existing transmission Transaction T1: 10 MW Wheeled from Bus 2 (Seller) to
facilities, and do not consider changes in production costs Bus 6 (Buyer)
as a result of required changes in dispatch and or unit Transaction T2: 20 MW Wheeled from Bus 3 (Seller) to
commitment due to the presence of the wheel. Bus 6 (Buyer)

3. TEST RESULTS Megawatt – kilometre: In this case, the power-flow


analysis of the system was executed without the
A 6-bus system and 24-bus model of Nigerian 330kV transaction, this is referred to as the base- case and again
power network are used to demonstrate the applications of the power-flow was solved with the transaction. Tables 1
the proposed method. Four wheeling cost methods were and 2 show the power flow results with transactions T1 and
investigated and analysed. The 6-bus network consists of T2 respectively.
six buses and 11 transmission lines. The one-line diagram
is shown in Figure 1. The 24-bus model of Nigerian Table 1: Power flow result with transaction T1 on the 6-
network is a relatively large system with 24 buses bus network
including 7 generators, 23 loads, and 39 lines. The one-line
diagram of 24-bus model of Nigerian network is shown in Fr To L Base T1 MW- ∆M ∆MW
Figure 2. om (km) Case Branc km W -km
flow h flow
(MW (MW)
)
1 2 4.00 19.10 18.80 75.20 -0.30 -1.20
1 4 3.20 56.50 56.50 180.8 0 0
1 5 8.64 47.20 48.20 416.5 1.00 8.64
2 3 5.12 16.20 19.10 97.79 2.90 14.85
2 4 6.40 75.60 76.20 487.7 0.60 3.84
2 5 10.1 32.30 33.50 337.7 1.20 12.10
2 6 13.92 47.40 52.40 729.4 5.00 69.60
3 5 14.40 28.90 28.10 404.6 -0.80 -11.52
3 6 5.60 57.20 60.80 340.5 3.60 20.16
4 5 8.32 5.50 6.10 50.75 0.60 4.99
5 6 6.72 1.90 0.20 1.34 -1.70 -11.42
Figure 1: Single-line diagram of 6-Bus Network
Srmc: The OPF was first solved without any transaction,
the bus marginal cost and generation dispatched for each
generator bus were recorded. The available transaction
was included and the OPF was solved again. Tables 3 and
4 show the computation of the SRMC for the 6-bus
network.
Table 2: Power flow result with transaction T2 on the 6- Table 4: Wheeling cost for T2 using SRMC Method on
bus network the 6-bus network.

From To L Base T2 MW- ∆MW ∆MW- B Gener BMC Gener BMC Pi,trans BMCi
(km) Case Branch km km u ation ation *
action
flow flow before after
(MW) (MW) s Pi,trans
1 2 4.0 19.10 20.7 82.92 1.63 6.52
before after (MW)
action
Transa Transa
1 4 3.2 56.50 57.9 185.4 1.43 4.58 Transa ction Transa ction (N/h)
ction ction
1 5 8.6 47.20 49.7 429.6 2.52 21.77 (N/M (N/M
(MW) Wh) (MW) Wh)
2 3 5.1 16.20 15 76.80 -1.2 -6.14
1 112.5 0.49 128.73 1.19 16.23 19.31
2 4 6.4 75.60 75.3 482.1 -0.27 -1.73

2 5 10.1 32.30 33.9 341.2 1.55 15.62


2 159.8 0.52 165.00 1.36 5.17 7.03

2 6 13.9 47.40 53.8 748.3 6.36 88.53 3 80.0 0.60 80.00 1.45 0 0
𝑛
3 5 14.4 28.90 31.6 455.0 2.7 38.88 26.34
𝑠𝑟𝑚𝑐 = ∑(𝐵𝑀𝐶𝑖 × 𝑃𝑖,𝑡𝑟𝑎𝑛𝑠𝑎𝑐𝑡𝑖𝑜𝑛 )
3 6 5.6 57.20 53.6 300.2 -3.6 -20.16 𝑖=1

4 5 8.3 5.50 6.6 54.83 1.09 9.07


Srmc: Through the use of the OPF, the srmc methodology
5 6 6.7 1.90 0.8 5.04 -1.15 -7.73 was implemented as discussed earlier. The srmc of the
wheeling transactions was estimated by solving the OPF
for both the system with the transaction and the system
Table 3: Wheeling cost for T1 using SRMC Method on without the transaction in place. After these solutions were
the 6-bus network. obtained, the srmc was calculated.

B Gener BMC Gener BMC Pi,trans BMCi 4. DISCUSSION & CONCLUSION


u ation ation action *
s before after Pi,trans 4.1 6-Bus Network
before after (MW)
action
Transa Transa
Transa ction Transa ction
Four methods of wheeling cost were investigated on the 6-
(N/h) bus network, postage stamp, contract path, Megawatt-
ction ction
(N/M (N/M kilometre and short-run marginal cost. Two wheeling
(MW) Wh) (MW) Wh) transactions were also simulated and the wheeling cost of
each transaction calculated using the four methods. The
1 112.5 0.49 117.95 0.96 5.45 5.23 results are given in Table 5.
2 159.8 0.52 165.00 1.06 5.17 5.48 Table 5: Wheeling cost results for 6-bus network.
3 80.0 0.60 80.00 1.13 0 0 Transa Postage Contract Mw- SRMC Proposed
𝑛 ction Stamp Path km Method
10.71 N/hr N /hr N /hr N /hr N /hr
𝑠𝑟𝑚𝑐 = ∑(𝐵𝑀𝐶𝑖 × 𝑃𝑖,𝑡𝑟𝑎𝑛𝑠𝑎𝑐𝑡𝑖𝑜𝑛 ) T1 33.68 24.93 49.09 10.71 59.80
𝑖=1 T2 67.35 17.28 38.01 26.34 64.35

3.2 Wheeling Cost Calculation for 24-bus model of The Megawatt-kilometre method gave the highest
Nigerian 330kv Network wheeling cost for transaction T1while the postage stamp
method gave the highest for transaction T2. The srmc was
Two wheeling transactions were simulated as follows and the least in transaction T1 and contract path the least in
applied to all the methods; transaction T2. These results for the two transactions
showed that the wheeling cost does not depend only on the
Transaction T1: 50 MW Wheeled from KAINJI (Seller) magnitude of power wheeled but also on distance between
to IKEJA WEST (Buyer) the source and the sink, power flow in Megawatts and the
Transaction T2: 70 MW Wheeled from AFAM (Seller) to cost of the transmission facilities.
NEW-HAVEN (Buyer)
Based on the proposed methodology in this work, that is
Megawatt – kilometre: Also, the power flow analysis of the combination of Megawatt-kilometre and srmc
the system was executed without the transaction, this is (Megawatt-kilometre covers the extent of use of the
referred to as the base- case.
network while srmc covers operating cost), the wheeling
cost for the two transactions are; The various impacts brought by the deregulation of the
power industry led to the unbundling of the services once
Wheeling Cost for T1 = 49.09 + 10.71 = 59.80 N/h provided by the vertically integrated electric utilities. As a
Wheeling Cost for T2 = 38.01 + 26.34 = 64.35 N/h result, utilities that provide transmission services are
separated from other functions in a typical power system.
The wheeling cost for transaction T1 is quite higher than Therefore, accurate wheeling cost is essential for proper
any of the four but that of transaction T2 is lower than the investment planning by the utility and the customers so as
highest of the four. The result will also help the DISCO at to maximize overall social welfare. This work investigated
bus 6 to decide which GENCO to enter into a bilateral four wheeling cost methodologies, postage stamp, contract
contract with based on the cost of energy wheeling not path, Megawatt-kilometre and short-run marginal cost.
considering other factors. The report has been able to propose a viable and economic
method of allocating energy wheeling cost to cover cost
and provide incentive for investment in new infrastructure
4.2 24-bus model of Nigerian 330kv Network as and when necessary. Two of the wheeling cost
methodologies, Megawatt-kilometre and short run
Two wheeling transactions were also simulated and the marginal cost were combined to form a hybrid method of
wheeling cost of each transaction calculated using the four charging for wheeling transactions on power system
methods. Table 6 gives the wheeling cost for the two networks.
transactions.
5. REFERENCES
Table 6: Wheeling cost results for 24-bus network.
[1] Y.R. Sood, N.P. Padhy and H.O. Gupta: “Wheeling of
Transa Postage Contract Mw- SRMC Proposed power under deregulated environment of power
ction Stamp Path km Method system – a bibliographical survey”, IEEE
N /hr N /hr N /hr N /hr N /hr
T1 135.84 82.50 277.91 41.50 319.53 Transactions on Power System, Vol. 17 No. 3, pp.
T2 190.64 161.00 110.92 57.28 168.59 870-878, August 2002.

The Megawatt-kilometre method gave the highest [2] C. H. L. Lee and L. D. Swift: “Wheeling charge under
wheeling cost for transaction T1, this is due to the long a deregulated Environment”, IEEE Transactions on
distance (473km) between KAINJI and IKEJA WEST and Industry Applications, Vol. 37 No. 1, pp. 178-183,
the fact that the transaction increased the flow on the lines. January 2001.
The srmc gave the least accounting for the operating cost. [3] C.M. Caramanis, R.E. Bohn and F.C. Schweppe: “The
For transactions T2, the Postage Stamp was the highest and cost of wheeling and optimal wheeling rates”, IEEE
the Megawatt gave the least, this was because of the short Transactions on Power Systems, Vol. 1 No. 1, pp. 63–
distance (257 km) and that the effect of the transaction on 73, February 1986.
the power flow was negligible compared to that of [4] A.A. El-Keib and X. Ma: “Calculating short-run
transaction T1. marginal costs of active and reactive power
production”, IEEE Transactions on Power Systems,
The contract path was also high because the power Vol. 12 No. 2, pp. 559–565, May 1997.
wheeled was the same as the maximum power along the [5] D. Shirmohammadi, X.V. Filho, B. Gorenstin and -
contract path thereby making the ration to be unity. Again V.P. Pereira: “Some fundamental technical concepts
these results, as in the 6-bus network have shown that the about cost based transmission pricing”, IEEE
wheeling cost does not depend only on the magnitude of Transactions on Power Systems, Vol. 11 No. 2, pp.
power wheeled but also on distance between the source 1002–1008, May 1996.
and the sink, power flow in Megawatts and the cost of the [6] H.V. Hitzeroth, D. Braisch, G.Herold and D. Povh:
transmission facilities. Based on the proposed method in “Compensation, stability and losses in the presence of
this work, that is the combination of Megawatt-kilometre wheeling transactions with the use of FACTS
and srmc the wheeling cost for the two transactions are; devices”, IEEE Power Tech.99 Conference BPT99,
Budapest, Hungary, paper DPT99-397-12, August
Wheeling Cost for T1 = 277.91 + 41.62 = 319.53 N/hour 1999.
Wheeling Cost for T2 = 110.92 + 58.67 =168.59 N/hour [7] T. Yong and R. Lasseter: “Optimal power flow
formulation in market of retail wheeling”, IEEE
As obtained in the 6-bus network, the result shows that the Power Engineering Society, Winter Meeting, New
wheeling cost from the proposed method for transaction York, pp. 394-398, Jan. 31-Feb. 4, 1999.
T1 is higher than any of the four methods investigated but [8] H.H. Happ: “Cost of Wheeling Methodologies”,
that of transaction T2 is lower. The result reflects the IEEE Transactions on Power Systems, Vol. 9, No. 1,
impact of distance that is the length of transmission lines pp. 147-156, February 1994.
in the cost of energy wheeling in any power system
network.

Das könnte Ihnen auch gefallen