Date of work completed : Block : A,D : 05,22/12/2012 Date of Checking Done : Block : A,D : 07,23/12/2012 Date of Casting : Block : A ,D : 08, 24/12/2012
: Block : E : 24/12/2012 : Block : E : 25/12/2012 : Block : E : 25/12/2012
A - 5th floor, D -6th Floor, E -7th Floor
1 25 mm conduit for Block : A,D,E Flats : A1,A2,A3,A4,D1,D2,E1,E2 : 2243.7 Rmt
2 32 mm conduit for Block : A,D,E Flats : A1,A2,A3,A4,D1,D2,E1,E2 : 92 Rmt
a For Corridor (Shaft to all Points in Corridor and lift Lobby) : 87.3 Rmt
b For Main Circuit (DB to SB (including Power Points, AC& Gysers ) : 315.2 Rmt
c For Room Circuit ( All Rooms circuit Points including loops & drops) : 1100.2 Rmt
d For T.V & Telephone Circuits (From shaft to DB / JN BOX) : 196.3 Rmt
e For T.V & Telephone Circuits (From DB / JN BOX to all Circuit Points ) : 230.2 Rmt
f For Fire Circuit (From Shaft to Flat Entry ) : 100.3 Rmt
g For Fire Circuit (From Flat Entry to Flat Exit ) : 214.2 Rmt
Total : 2243.7 Rmt
Present
S.No. Description Unit Items Issued Items Used Wastage Rate /unit
Balance
1 25 mm Conduit Nos. 679 658 20.79 0.21
2 25mm Couplers Nos. 1175 1063 0 112
3 25mm "L" Bends Nos. 1040 879 0 161
4 25mm 4 Way Junction Boxes Nos. 12 12 0 0
5 25mm 3 Way Junction Boxes Nos. 50 63 0 41.5 -13
6 25mm 2 Way Junction Boxes Nos. 30 37 0 37.5 -7
7 25mm 1 Way Junction Boxes Nos. 22 33 0 35.5 -11
8 32 mm Conduit Nos. 18 32 1.28 216 -14
9 32 mm " L" Bends Nos. 14 22 0 37 -8
10 32 mm Couplers Nos. 15 21 0 11 -6
11 32 mm 4 Way Junction Boxes Nos. 7 0 51 -7
12 Fan Boxes Nos. 22 36 0 84 -14
13 Solvent Nos. 3.5 8.5 0 280 -5
14 Brown Tapes Nos. 32 45 0 40 -13
Remarks:
As per disscussion and acceptance by Mr. Satish Gutam deduction of Rs.:900/- per flat for drop openings till clearance of all flats will be
deducted.
All Drop Openings are opened except 4 points in A , C & E blocks to be repaired so 1 flat amount is kept in hold i.e,.900/-
The use of excess material held with the party with out prior issue from the issuing authority , so the amount is been deducted from the
gross.
Total billed = 28028.4 - 8931.5 = 19096.9 = Rs.19097/- to be paid
Signature of the Contractor Signature of the Billing Engineer Signature of the Paying Authority
(Satish Gutam) For Matrix Technical Services Pvt.Ltd For Moraj Infratech Pvt.Ltd
20.79
1.28
863.064
13521.4