Beruflich Dokumente
Kultur Dokumente
*Status
Consultant: Summer Season Ltd
A - Approved
B - Approved with comments
Status Code: C - Resubmit
D - Reject
Comments:
Reviewed by:
NU/2019/MIR/MS/CIVIL/020 Page 1
CONSTRUCTION OF PROPOSED AMBASSADOR
RESORT & SPA AT MIRISSA, SRI LANKA CLIENT/CONSULTANT:
METHOD STATEMENT FOR CEMENT BLOCK SUMMER SEASON LTD
WORK
NU/2019/MIR/MS/CIVIL/020 Page 2
CONSTRUCTION OF PROPOSED AMBASSADOR
RESORT & SPA AT MIRISSA, SRI LANKA CLIENT/CONSULTANT:
METHOD STATEMENT FOR CEMENT BLOCK SUMMER SEASON LTD
WORK
Table of Contents
1.0 INTRODUCTION ........................................................................................................................................................ 4
2.0 STANDARDS, SPECIFICATIONS & REFERENCE TO BE ADOPTED .................................................. 4
3.0 RESOURCES, ROLE & RESPONSIBILITIES FOR THE RANDOM RUBBLE MASONRY ............... 4
3.1 Role & Responsibilities ........................................................................................................................................... 4
3.2 Allocated Resources................................................................................................................................................. 5
3.2.1 Manpower ....................................................................................................................................................... 5
3.2.2 Machinery / Equipment / Material ............................................................................................................ 5
4.0 WORK DESCRIPTION FLOW CHART FOR THE CEMENT BLOCK WORK ..................................... 7
5.0 CONSTRUCTION SEQUENCE OF CEMENT BLOCK WORK ................................................................. 8
5.1 Cleaning of the Surface ........................................................................................................................................... 8
5.2 Setting out of the RRM Base lines ........................................................................................................................ 8
5.3 Drilling & placing of the stiffener column reinforcements .............................................................................. 8
5.4 Laying of 1st Course ................................................................................................................................................. 9
5.5 Continuation of the Block Wall up to designated stiffener beam/ lintel height ........................................ 10
5.6 Concreting of the stiffener columns/ lintels/ stiffener beams...................................................................... 11
5.7 Continuation of the Block Wall up to finished height .................................................................................... 11
5.6 Curing of the Block wall (From the stage of laying 1st segment & then after up to the end of the block
work) ............................................................................................................................................................................... 12
6.0 QUALITY CONTROL AND QUALITY ASSURANCE METHODOLOGY........................................... 12
7.0 SAFETY PRECAUTIONS ........................................................................................................................................ 13
8.0 ENVIRONMENTAL CONSIDERATIONS ....................................................................................................... 13
NU/2019/MIR/MS/CIVIL/020 Page 3
CONSTRUCTION OF PROPOSED AMBASSADOR
RESORT & SPA AT MIRISSA, SRI LANKA CLIENT/CONSULTANT:
METHOD STATEMENT FOR CEMENT BLOCK SUMMER SEASON LTD
WORK
1.0 INTRODUCTION
The main purpose of this method statement is to outline the procedure of Cement Block Work of the
project. It has been prepared based on the proper construction procedures, standards & required
specification related to the project as well as to outline various activities related with the supply &
laying of the cement blocks of various sizes with a width of 100mm, 150mm & 200mm.
This method statement is a general outline for supply & laying of cement block, also address the
concreting procedures of stiffener columns, stiffener beams & lintels.
During the construction & scope of the work can be slightly changed due to unforeseen site
conditions. Otherwise the methodology & procedures outlined from this MS will be the key guide for
the builders work.
3.0 RESOURCES, ROLE & RESPONSIBILITIES FOR THE RANDOM RUBBLE MASONRY
To have & to ensure smooth operation of total operation period up to complete the block work, each
members of the construction team is assigned a specific role. That would be very helpful to
overview each sequences of the work & to minimize the re works/ errors & to maintain good
quality finished work.
QA/QC Manager & QA/QC Engineer will be the key personal for the coordination of consultant
and Nuwani staff. Zone Incharge Engineer/ Asst. Engineer/ Technical Officers will be carried out
the work with skilled working team and controlling of quality up to standards.
Whole team of directly involved to the builders work will be guided by Construction Manager.
Whole work would be categorized to specified sub tasks to assign the resources effectively. The
capacity/ size/ requirement of the tools, equipment & man power shall be judged in accordance
with the site condition of the time of execution.
NU/2019/MIR/MS/CIVIL/020 Page 4
CONSTRUCTION OF PROPOSED AMBASSADOR
RESORT & SPA AT MIRISSA, SRI LANKA CLIENT/CONSULTANT:
METHOD STATEMENT FOR CEMENT BLOCK SUMMER SEASON LTD
WORK
Position Nos
Construction Manager 01
QA/QC Engineer 01
Site Engineer /Civil Engineer 01
Assistant Engineer 01
Technical Officer 01
Safety Officer 01
Surveyor 01
General Skilled & Unskilled workers As required
Type Nos
100mm/150mm/200mm Solid Cement Block As needed
Cement As needed
Sand As needed
Concrete pot mixture 02
Gauge box 02
Water Bowser 01
Bob Cat Loader 01
Wheel barrows As needed
Water Storage Barrels As needed
Foundation Treads/ Twines As needed
Plumb bobs As needed/ Where necessary
Measuring tape As needed/ Where necessary
Mason trowel As needed
Spirit level As needed/ Where necessary
Box bars/ Levelling Bar As needed/ Where necessary
NU/2019/MIR/MS/CIVIL/020 Page 5
CONSTRUCTION OF PROPOSED AMBASSADOR
RESORT & SPA AT MIRISSA, SRI LANKA CLIENT/CONSULTANT:
METHOD STATEMENT FOR CEMENT BLOCK SUMMER SEASON LTD
WORK
NU/2019/MIR/MS/CIVIL/020 Page 6
CONSTRUCTION OF PROPOSED AMBASSADOR
RESORT & SPA AT MIRISSA, SRI LANKA CLIENT/CONSULTANT:
METHOD STATEMENT FOR CEMENT BLOCK SUMMER SEASON LTD
WORK
4.0 WORK DESCRIPTION FLOW CHART FOR THE CEMENT BLOCK WORK
NU/2019/MIR/MS/CIVIL/020 Page 7
CONSTRUCTION OF PROPOSED AMBASSADOR
RESORT & SPA AT MIRISSA, SRI LANKA CLIENT/CONSULTANT:
METHOD STATEMENT FOR CEMENT BLOCK SUMMER SEASON LTD
WORK
Material approval must be taken in prior to plan the cement block work. Necessary test reports as well
as the specimen samples from the specialized manufacturers to be submit for Engineers approval.
Considering past test results as well as the test results of the submitted samples Engineer will approve
the manufacturer/ manufacturers to proceed the production of the cement blocks.
Necessary approval will be taken in advance to product enough quantity of cement block for the work.
The production to be done in prior to store the blocks under curing period of 28days. Approved
manufacturers will be advised to pelleting the cement blocks as per the production dates & clearly
mention the date of production for easy identification of the lot.
If any missing date of production in some of pallets it will be marked during the unloading process at
the site for easy identification.
5.1 Cleaning of the Surface
Necessary area will be identified earlier referring architectural drawings/ approved shop drawings
for the block work. To setting out the base lines, necessary area of the floor slab will be cleaned.
Cement concrete depositions, mud, dust will be removed & using compressed air line floor cleaning
will be done. If any area to be washed, it will be done by using proper arrangement of the water
line. However before start the setting out area should be cleaned & to be free from water,
otherwise marking cannot be done properly.
5.2 Setting out of the RRM Base lines
With referring the approved drawing for block works, setting out will be done. Necessary offsets to
walls will be demarcated for the verification of the wall positions. After completion of the block
wall setting out, stiffener column locations will be marked before start the base line (1st course).
5.3 Drilling & placing of the stiffener column reinforcements
As per the approved details drilling of the floor slab & inserting of the designated re bars for the
drilled holes will be done with cement grout. Drilling depth for respective re bar will be followed
as per the drilling depth specified for the chemical anchoring.
After drilling & placing of the vertical re bar for the specified locations of the stiffeners block
work will be continued. Both side access to be provided for the block wall so the stirrup loading
& binding can be done after completion of the block work up to designated height of the 1st
stage.
There is an advantage for doing the stirrups work after the block work otherwise cement mortar
deposition of the stirrups will be major problem while preparation of the stiffeners for
concreting.
NU/2019/MIR/MS/CIVIL/020 Page 8
CONSTRUCTION OF PROPOSED AMBASSADOR
RESORT & SPA AT MIRISSA, SRI LANKA CLIENT/CONSULTANT:
METHOD STATEMENT FOR CEMENT BLOCK SUMMER SEASON LTD
WORK
Part by part concreting will be done for stiffeners as parallel activity for block work.
NU/2019/MIR/MS/CIVIL/020 Page 9
CONSTRUCTION OF PROPOSED AMBASSADOR
RESORT & SPA AT MIRISSA, SRI LANKA CLIENT/CONSULTANT:
METHOD STATEMENT FOR CEMENT BLOCK SUMMER SEASON LTD
WORK
5.5 Continuation of the Block Wall up to designated stiffener beam/ lintel height
On pre laid starter course (1st course) continuation of the block wall will be done. Necessary door
openings, clearance for stiffeners & plaster thicknesses will be verified during the starter course.
Place masonry top on the starter course to line & leveled with that. Masonry units will be assembled
together overlapped, so that the vertical joints are staggered from course to course. At the corners &
the wall intersections necessary closures for the providing of L joints & T joints will be used. As per
the stiffener column layout some locations of the L joints or T joints may terminated from the
S/Column. So ending of the cement block work will be done providing necessary clear cover
requirement for the reinforcement. Where necessary closures will be provided with grinder cut blocks.
All masonry shall be laid accurately to dimensions indicated, plumed & true alignment line, plumb
corners, with level & accurately spaced courses, with vertical joint plumb, with fully mortared joints
with uniform width.
All the courses to level to be levelled & mortar shall be spread only to the extent that it will be soft &
plastic when masonry units are bedded. Masonry units shall not be move after they have been settled
firmly to the laid mortar. Where the time frame mortar layer at the plastic limit, necessary adjustments
corrections will be don to get the exact accuracy for the course. If any correction identified after
settling the fresh mortar, those area to be removed & relaying of the blocks to be done on fresh
mortar.
Wall shall be kept level at all times. Any portions of wall shall not installed higher than 1.5m in height
in any particular day. Carry up walls in a uniform manner by course by course by providing toothing
for other adjacent walls. Necessary provision for angles & reveals shall be kept true, square & plumb
bob.
Where concrete column to be stiffen with the block work cement grout paste will be applies on the
column faces & then after end closure will be placed with mortar joint.
Where un-finished masonry shall be stepped as follows. Continuation can be done with joining the
new one for provided toothing.
NU/2019/MIR/MS/CIVIL/020 P a g e 10
CONSTRUCTION OF PROPOSED AMBASSADOR
RESORT & SPA AT MIRISSA, SRI LANKA CLIENT/CONSULTANT:
METHOD STATEMENT FOR CEMENT BLOCK SUMMER SEASON LTD
WORK
Verticality accuracy will be checked with the demarcated offset for the base course & above courses
will be plumbed to base course to get the accurate verticality.
Same tolerance for the concrete columns & walls will be applied for the masonry work.
Required off set dimension will be checked in at several locations to achieve the plumbness
accuracy of +/- 5mm up to 1.5m height & +/- 10mm up to 1.5m to 15m.
Contractor shall fulfill the necessary dimensions/ accuracy with in the above tolerance limits.
NU/2019/MIR/MS/CIVIL/020 P a g e 11
CONSTRUCTION OF PROPOSED AMBASSADOR
RESORT & SPA AT MIRISSA, SRI LANKA CLIENT/CONSULTANT:
METHOD STATEMENT FOR CEMENT BLOCK SUMMER SEASON LTD
WORK
up to the beam bottom level. Usage of the cement grout later will be advantage for stopping of the
cracks arising from the block work to plaster finish.
As per the last filling height sometimes cement block to be cut horizontally to get the necessary height.
Both side joint surface preparation will be done to parallel with the block work, otherwise after setting
of the joint mortar balance filling or balance preparation cannot be done properly. While joint mortar
at the plastic limit necessary joint preparation should be done.
5.6 Curing of the Block wall (From the stage of laying 1st segment & then after up to the end of the
block work)
Curing will be started after setting of the 1st stage of the block work. Continues 3 days should be cures
each stage of the block work. Water absorption of the cement block is acceptable stage for self-curing,
so time to time water spraying and wetting of the block wall to be done.
Time to time observation & application of water to the wall to be done to have the desired bonding of
the cement mortar & cement blocks.
For the curing of the stiffener columns, stiffener beams & lintels MasterKure 128 can be used.
Batching of the cement mortar mixer on volume basis will be done. So proper supervision to be done
while batching the mixer. After giving proper training to workers who are batching the mixer, work to
be started.
Mixed mortar to be kept up to 2Hrs after the mixing. In any case 2Hrs exceeding happened, those
mixed mortar volume to be disposed without using for block work. Additional water adding can be
done as per the onsite ambient conditions, but time to be kept should be 2Hrs for the usage.
Time to time accuracy checking (alignment, verticality) to be done to get the desired accuracy for the
masonry wall.
For MEP chasing, designated depth of the chasing for each & every conduct/ pipe should be approved
by the Consultant Engineer. Otherwise increment of the depth of chasing will be a problem for the
strength of the block wall. Unauthorized chasing might adversely affect one or more of the functional
requirements of the walls e.g. its loadbearing capacity.
Do not cut horizontal or raking chases to a depth exceeding one-third the thickness of the single leaf in
walls or leaves contracted of solid units.
NU/2019/MIR/MS/CIVIL/020 P a g e 12
CONSTRUCTION OF PROPOSED AMBASSADOR
RESORT & SPA AT MIRISSA, SRI LANKA CLIENT/CONSULTANT:
METHOD STATEMENT FOR CEMENT BLOCK SUMMER SEASON LTD
WORK
Safety warning boards and sign boards will be displayed on site. Those sign boards will be guide line
for the workers & always it will be a reminder for workers when they are involving to site work.
Workers shall wear all appropriate safety personnel protective equipment such as helmet,
coverall clothing (High visible Jacket), and safety boots, goggles and gloves, wherever
required while they are within the site premises/ working location. All the working personals will be
advices during the tool box talk as well as at the weekly site safety meeting.
A first aid box with the necessary medicine will be placed at the site first aid room in case of an
emergency.
Adequate safe access to the working area shall be provided. Prior to construction of block wall,
necessary scaffolding through the spanning the work area to be constructed up to the level of the
block work completion. The arrangement of the scaffolding to be able to hold the material that is
to be used for the block work construction as well the weight of the workers. Scaffolding to be
erected so that is to allow each masons may have free access without being tied off. Adequate &
safe access to be ensures before working on top.
Sufficient light shall be ensured before start of the work
Necessary skilled personals to be used for the batching & working with the pot mixer, power tools
handling, etc:
While working on top & material handling on top, must secure the bottom space without being
dropping materials, tools, etc: How ever the bottom gap to be enclosed/ seal with timber/
plywood decking to protect the peoples who are working at below levels.
One location will be used for the mixing of cement mortar & while washing the pot mixer washed
water not to be direct to natural streams of sea. Necessary diverting to be done to S/pit before water
divert/ pump out to any other location/ stream.
Waste block parts should be collect & disposed to suitable location.
NU/2019/MIR/MS/CIVIL/020 P a g e 13