Beruflich Dokumente
Kultur Dokumente
Architecture
Basic layout 8 2 1 0.5
Site master plan 8 2 1 0.5
Equipment layout 8 2 1 0.5
Man / material layout 8 2 1 0.5
Door and windows schedule 8 2 1
Office area furniture BOQ 8 4
Sections 8 2 1 0.5
Elevations 8 2 1 0.5
Civil finishes layouts 8 2 1
Drainage and plumbing 24 16 4 2
Firefighting
Pumphouse layout 8 2 1
Fire schematic 8 2 1
External layout 8 2 1
Internal hydrant layout 8 2 1
Internal sprinklers and piping layout 8 2 1
BOQ 12 4 0.5
Specifications 8 4
Typical details 8 2 1
Extinguisher layouts 8 2 1
HVAC
BOD / DQ 8 4 1
Heat load estimation 16 4
AFD 16 4 1 2
Equipment schedules 8 2
Equipment placement layout 8 2 1
RCP layout 8 2 1
Ducting layout 24 2 1
BOQ 12 4 0.5
Specifications 8 4
Electrical
BOD 8 4 1
Calculations (power, earthing, S/c) 16 4 2
Power layouts 8 4 1
Lighting layouts 8 4 1
Earthing layouts 8 4 1
Panel SLDs 24 8 1
Cable schedule 16 4
Cable tray layouts 16 4 1
panel and DB location layouts 8 2 1
Racking
Racking layout 8 2 1 1
Specifications 8 4
BOQ 8 4 1
Procurement assistance
Floating of bids 4 4
Pre-bid meeting 32 32
Revision in BOQs 8 4
Technical comparison 16 4
Commercial comparison 16 4
Recommendation 16 4
1287.5
1215400
989600
1215400
15000
1230400
184560
123040
1538000
153800
1691800