Sie sind auf Seite 1von 3

Particulars Designer Engineer Manager Director

Architecture
Basic layout 8 2 1 0.5
Site master plan 8 2 1 0.5
Equipment layout 8 2 1 0.5
Man / material layout 8 2 1 0.5
Door and windows schedule 8 2 1
Office area furniture BOQ 8 4
Sections 8 2 1 0.5
Elevations 8 2 1 0.5
Civil finishes layouts 8 2 1
Drainage and plumbing 24 16 4 2

Firefighting
Pumphouse layout 8 2 1
Fire schematic 8 2 1
External layout 8 2 1
Internal hydrant layout 8 2 1
Internal sprinklers and piping layout 8 2 1
BOQ 12 4 0.5
Specifications 8 4
Typical details 8 2 1
Extinguisher layouts 8 2 1

HVAC
BOD / DQ 8 4 1
Heat load estimation 16 4
AFD 16 4 1 2
Equipment schedules 8 2
Equipment placement layout 8 2 1
RCP layout 8 2 1
Ducting layout 24 2 1
BOQ 12 4 0.5
Specifications 8 4

Electrical
BOD 8 4 1
Calculations (power, earthing, S/c) 16 4 2
Power layouts 8 4 1
Lighting layouts 8 4 1
Earthing layouts 8 4 1
Panel SLDs 24 8 1
Cable schedule 16 4
Cable tray layouts 16 4 1
panel and DB location layouts 8 2 1

Racking
Racking layout 8 2 1 1
Specifications 8 4
BOQ 8 4 1

Procurement assistance
Floating of bids 4 4
Pre-bid meeting 32 32
Revision in BOQs 8 4
Technical comparison 16 4
Commercial comparison 16 4
Recommendation 16 4

Subtotal 280 204 72 13


Construction drawings and GAD approvals 56 41 15 3
Revisions 84 62 22 4
Meetings and site visits 16 24 24 24
Total 436 331 133 44

Man hour rates 750 1200 1400 1800

Cost for Engineering 327000 397200 186200 79200


Maximum cost
Printing charges
Total
Overheads @ 15%
Profit @ 10%
Grand total
Negotiation Margin @ 10%
Price to be quoted
944

1287.5
1215400
989600
1215400
15000
1230400
184560
123040
1538000
153800
1691800