Beruflich Dokumente
Kultur Dokumente
a) Application Form
1. Executive Summary
This is a Pilot Project to use Canadian Eco Siphon Hydro Power Stations on existing irrigation canals
in Sri Lanka. This technology is in use in Canada very successfully for over 25 years and the engineers
of the Canadian technology provider visited a number of potential sites in Sri Lanka and decided to
do the Pilot Project at this location on the Ulhitiya Canal Branch 2 (Drop 1), in the Ampara District in
Dehiattakandiya Divisional Secretariat division.
The project aims to promote development of clean and renewable energy sources for public
utilization using innovative and patented Canadian Eco Siphon Hydro Technology. The proposed
hydroelectric plant will consist of Eco Siphon Hydro Power Station, Power House and the
Transmission line. The Project involves no new water diversion or water storage and does not modify
the timing of water diversion or storage within the canal in any way.
The estimated project cost is Rs. 83.7 million. The Installed capacity will be 400kW and the estimated
electricity generation is 1.8 million kWh per year.
This is the first time in Sri Lanka that this Eco Siphon Hydro Technology will be used for hydro electric
power generation. This will open doors for a new area in developing clean energy in the country
using existing infrastructure, without having to alter the structure and with having no impact on
environment and the water flow.
The Company involved in this project is a joint venture between a local Company and a Canadian
based Company in Sri Lanka which has rights for this patented Eco Siphon Hydro technology.
The proposed hydro power project, which is to be implemented by Chelina Ulhitiya Hydro (Private)
Limited is a joint venture between SRI Renewable (Pvt) Limited, a Canadian origin local Company and
Chelina Eco Power (Private) Limited.
The Company was founded to assist in developing Sri Lanka's abundant micro and mini hydro
resource opportunities. As an emerging nation with ever increasing grid usage, expanding power
generation is a national concern.
The Company, in collaboration with a Canadian manufacturer supplies packaged hydro solutions
which are both economically and environmentally viable. We pay close attention to the water
systems in which we operate, and work diligently with local authorities to ensure a harmonious
relationship with all stakeholders.
Figure 1
Figure 2, below shows the Ulhitiya Canal Branch 2 – gate 1 (Drop-1) water flow downstream after
discharging through the gates.
Figure 2
Figure 3
Water Issues - Number of Days per Month (Minimum water issue is 10.0 m3 / s)
Total no
Year\Mth JAN FEB MAR APR MAY JUNE JULY AUG SEP OCT NOV DEC of days / As a %
Year
2003 31 15 10 31 30 31 20 3 30 31 232 64%
2004 31 28 10 11 30 31 31 10 19 31 232 64%
2005 31 28 15 10 31 30 31 25 11 30 31 273 75%
2006 31 28 26 30 31 30 31 31 30 25 293 80%
2007 10 31 30 31 25 11 30 31 199 55%
2008 31 28 2 9 31 30 31 31 10 30 31 264 72%
2009 31 28 6 10 30 31 31 5 15 31 218 60%
2010 31 28 17 8 31 30 31 31 5 16 30 31 289 79%
2111 31 15 29 31 30 31 5 5 31 208 57%
2012 31 29 20 30 31 30 31 202 55%
2013* 31 28 20 79 22%
2013 - Data available only for the first 3 months.
Source: Mahaweli Regional Office - Dehiattakandiya
Avg Monthly Water Discharge (Days per Month)
31 30 31 31
26 26 26 24
15 16 15
15
The proposed hydro power station is based on an existing irrigation canal which is dependent on
regulated water released to the farmers and other water users, and, therefore the normal data such
as rainfall data, catchment area, etc., are not applicable in this project and solely the project is
dependent upon the historical flow data of the canal, which is given above.
Dehiattakandiya has been designed as a service centre' for several hamlets and villages, along with
Girandurukotte for the zone 'C of the Mahaweli settlements. Dehiattakandiya Town is built entirely
on undisturbed land of vegetation. The land is almost flat except for mild slopes, and hears no
significant geographical features.
Primary occupants of the area are farmers, who have come from all over the country. There are
other supportive families as well, who represent about one third of the agricultural community.
Furthermore, the town receives about as much seasonal, immigrating labourers. Majority of the
population of Dehiattakandiya as a whole, are Sinhala Buddhist, who shares a common interest in
agriculture. Therefore, this farmer community shows cultural similarities despite their regional
variations and celebrates cultural, religious and seasonal agricultural festivities together in the town.
The area houses a very low dense agricultural community and acts as the 'centre' for their needs and
interactions wherein their need for buying seeds, fertilizer and technical advised as well as selling
their crops are satisfied.
The Town Dehiattakandiya can primarily be seen us a concentration of activities along a looped road
that connects the Kandy - Polonnaruwa highway. Hence, the town has two access roads from the
highway focusing on two squares, namely North Square and South Square, which in turn connect the
main road of the town which lies parallel to the Kandy - Polonnaruwa highway. These two squares,
lying along the main street of the town, are focused on a Central Square from which another street
leads away to the interior of the settlements. North and South squares are surrounded by
administrative and institutional buildings, while the Central Square is surrounded by public
amenities.
Figure 7
The house sits in the head pond on 4 adjustable legs. The water conveyance system is submerged in
the head pond and in the tailrace to form a barrier to the entrance of air. Water is drawn into the
turbine through suction generated by a pump until the turbine begins rotation. At this time the
suction pump is no longer needed as the remaining air is mixed with flowing water until all the air is
expelled into the tailrace. The turbine uses a low speed, low velocity fish-friendly runner operating
under a vacuum at the top of the siphon loop formed by the intake, turbine and discharge piping.
The application of the Eco-Siphon Hydro technology is governed by two factors, the size of the
turbine and the elevation between the head pond and tailrace.
The practical application of the technology is limited to about 7 meters in stations using turbines less
than 800 mm, and to 6 meters when using turbines more than 1.5 meters in diameter. The length of
the discharge piping system is limited by friction losses between the water and the piping. This can
reduce the suction on the turbine to the point that the reduction in energy does not leave enough
Design flow rate and 5.0 m3/s for each turbine (Totaling 10.0 m3/s)
Gross head 4.2 m
Net head on turbine 4.0 m
Turbine selection Siphon Turbine size 2 x 52 inch unregulated
Generation capacity 155 kW each (2 x 155kW equals 310kW in total)
Monthly generation is 155 x 2 x numbers of hours in the month
where there is 10 m3/s or more.
Gross annual or monthly
Turbine and generator losses - Gross kilowatts available from
generation, losses, and net sales to
10 m3/s and 4.0 m head is approx. 400kW.Total Losses are 21%
the grid
for turbine, generator and drive system. (Turbine losses are
11%, Generator losses 4%, Drive losses 6%).
Note that the water will quickly rise in the canal if the power grid fails and both units shut down
quickly. The water level will reach the bottom of the discharge pipe and start to flow through the
turbines again. The turbines will then free wheel spilling water as needed to keep the head from
rising further.
The Proposed Project would be constructed on an existing irrigation canal that is used to deliver
irrigation water to Mahaweli System ‘C’ water users, mainly the farmers.
The canal is an essential element of the irrigation conveyance system of the water users. The
proposed project design will preserve the full water conveyance capabilities of the canal and would
therefore not result in any impacts to utilities or infrastructure.
The Proposed Project – Siphon hydroelectric facility would be operated in a run‐of‐canal mode,
meaning that power generation would utilize the water as currently delivered into canal; the
turbines would adjust to any change in flow. Water releases into canal would continue to be made
based on irrigation demand only, as specified by the authorities. There would be no water storage
structures associated with the plant. Because the proposed project does not create any new
impoundment of water it would have no effect on water temperature, nutrients, pH or any other
water quality parameters commonly modified by lake environments. The water quality downstream
of the power plant will be the same as the water quality entering the plant.
Based on the preliminary analysis of the environmental impacts the proposed project would not
materially affect the quality of the human, social and economic environment of the area.
Capital Cost of the Project, Debt Equity Financing and Project Parameters
83,700,000 653,906
Project parameters
Capacity
(Installed) 400 kW
Plant Factor 65%
183,000
219,600
Cost Inflation
Estimated Cost inflation per year 2.50% per year
Depreciation computation
Depreciation
Dep per year
Rs. Project Period, Yr p.a. Rs. Mn
Total Project Rs.
Cost 83.7 20 5.00% 4.2 Million
32,695.31 USD
Yr 1 2 3 4 5 6 7 8
Opening balance 41.85 36.6 31.4 26.2 20.9 15.7 10.5 5.2
Average balance 39.23 34.0 28.8 23.5 18.3 13.1 7.8 2.6
Repayments (Capital) 5.23 5.2 5.2 5.2 5.2 5.2 5.2 5.2
Closing balance 36.62 31.4 26.2 20.9 15.7 10.5 5.2 0.0
Interest paid 5.9 5.1 4.3 3.5 2.7 2.0 1.2 0.4
Year ended Yr 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Gross turnover 28.2 28.2 28.2 28.2 28.2 28.2 28.2 28.2 28.2 28.2 28.2 28.2 28.2 28.2 28.2 28.2 28.2 28.2 28.2 28.2
Less: Royalty Provision 10% (2.8) (2.8) (2.8) (2.8) (2.8) (2.8) (2.8) (2.8) (2.8) (2.8) (2.8) (2.8) (2.8) (2.8) (2.8) (2.8) (2.8) (2.8) (2.8) (2.8)
Operational Expenditure 3% (3.6) (3.7) (3.8) (3.9) (4.0) (4.1) (4.2) (4.3) (4.4) (4.5) (4.6) (4.7) (4.8) (5.0) (5.1) (5.2) (5.3) (5.5) (5.6) (5.7)
PBID 21.8 21.7 21.6 21.5 21.4 21.4 21.2 21.1 21.0 20.9 20.8 20.7 20.6 20.5 20.3 20.2 20.1 19.9 19.8 19.7
Profit before depreciation 15.9 16.6 17.3 18.0 18.7 19.4 20.1 20.8 21.0 20.9 20.8 20.7 20.6 20.5 20.3 20.2 20.1 19.9 19.8 19.7
Depreciation (4.2) (4.2) (4.2) (4.2) (4.2) (4.2) (4.2) (4.2) (4.2) (4.2) (4.2) (4.2) (4.2) (4.2) (4.2) (4.2) (4.2) (4.2) (4.2) (4.2)
Operating Profit Bef Tax 11.8 12.4 13.1 13.8 14.5 15.2 15.9 16.6 16.9 16.7 16.6 16.5 16.4 16.3 16.2 16.0 15.9 15.8 15.6 15.5
Taxation (assume) 0% - - - - - - - - - - - - - - - - - - - -
Net profit 11.8 12.4 13.1 13.8 14.5 15.2 15.9 16.6 16.9 16.7 16.6 16.5 16.4 16.3 16.2 16.0 15.9 15.8 15.6 15.5
PBID/Turnover (%) 77% 77% 77% 76% 76% 76% 75% 75% 74% 74% 74% 73% 73% 72% 72% 72% 71% 71% 70% 70%
OP/Turnover (%) 42% 44% 47% 49% 51% 54% 56% 59% 60% 59% 59% 58% 58% 58% 57% 57% 56% 56% 55% 55%
Net profit / Turnover (%) 42% 44% 47% 49% 51% 54% 56% 59% 60% 59% 59% 58% 58% 58% 57% 57% 56% 56% 55% 55%
Table 7: Projected Cash Flow Statement
Inflow PBID 22 22 22 22 21 21 21 21 21 21 21 21 21 20 20 20 20 20 20 20
Equity 41.9
Debt 41.9
Total Cash Inflow 83.7 21.8 21.7 21.6 21.5 21.4 21.4 21.2 21.1 21.0 20.9 20.8 20.7 20.6 20.5 20.3 20.2 20.1 19.9 19.8 19.7
Total Cash Outflow 83.7 11.1 10.3 9.5 8.8 8.0 7.2 6.4 5.6 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Opening Bal 83.7 - 11 22 34 47 60 75 89 105 126 147 168 188 209 230 250 270 290 310 330
Closing Bal - 11 22 34 47 60 75 89 105 126 147 168 188 209 230 250 270 290 310 330 350
Table 8: Financial Ratios
Financial Ratios
Site ownership
The site is owned by the Mahaweli Authority of Sri Lanka (MA). The Company shall submit technical
proposal to Mahaweli Authority and in consultation with the Authority and on its approval will
finalise the final design.
The Company shall enter into agreements with the MA on a mechanism of compensating MA for the
use of Irrigation Canal. These subjects will de addressed in detail at the negotiating stage with the
MA.
6 Provisional Approval
Conditional Approval from Mahaweli
7
Authority / Irrigation Dept.
Detailed technical design including the civil
8 structural in consultation with Engineers of
Mahaweli