UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: WBLFF (excavation) (Masjid) PAGE NO:1

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
1 Excavate to reduce level;
commencing from 1,656m2 2 Excavator 1 Site Excavator 4/2
formation level; cart supervisor output =1.82 days
away, excess earth, =2 days
deposit, spread and 2 Machine = 37m2/hr
levelled where directed operator
within the site: - 1,656m2/37m2/
8hrs

= 3.64 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: WBLFF (excavation) (Masjid) PAGE NO:2

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
2 Excavate pit starting from
reduced level including 110m3 1 Excavator 1 Site Excavator 1 days
backfilling with approved supervisor output
excavated material,
compaction in layers and 1 Machine = 15m3/hr
disposal of surplus operator
excavated material where 110m3/15m3/8
directed within the site: - hrs

=0.92 day
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: WBLFF (excavation) (Masjid) PAGE NO:3

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
3 Excavate trench starting
from reduced level; 120 m3 1 Excavator 1 Site Excavator 1 day
including backfill with supervisor output
approved excavated
material, compaction in 1 Machine = 15m3/hr
layers and disposal of operator
surplus excavated 120m3/15m3/8
material where directed hrs
within the site: -
= 1 day
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: WBLFF (hardcore)(Masjid) PAGE NO: 4

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
4 Hardcore as specified: -
150mm Thick bed 1,456m2 2 compactors 1 Site Compactor 6/2
hardcore as described supervisor output = 3 days
spread, levelled and
compacted to receive 2 Machine = 33m2
concrete slab. operator
1,456m2/33m2/
8hrs

=5.52 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: WBLFF (hardcore)(Masjid) PAGE NO: 5

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
5 Hardcore as specified: -
100mm to receive apron 200m2 1 compactor 1 Site Compactor 1 day
slab supervisor output

1 Machine = 33m2
operator
200m2/33m2/8
hrs

=0.76 day
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: WBLFF (Lean conc. grd 15) (Masjid) PAGE NO: 6

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
6 Lean Concrete (Grade
15) as specified; as 68m2 3 Trowel 1 Skill labor Workers 1 day
blinding screed laid on output
earth or hardcore: - 3 General
50mm Thick under: - labor = 2.56m2
Pile cap
2.56m2 x 4

= 10.24m2

68m2/10.24m2/
8

= 0.83 day
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: WBLFF (Lean conc. grd 15) (Masjid) PAGE NO: 7

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
7 Lean Concrete (Grade
15) as specified; as 185m2 3 Trowel 1 Skill labor Workers 2 days
blinding screed laid on output
earth or hardcore: - 4 general labor
50mm Thick under: - = 2.56m2
Ground beam
2.56m2 x 5

= 12.8m2

185m2/12.8m2/
8hrs

= 1.81 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: WBLFF (Lean conc. grd 15) (Masjid) PAGE NO: 8

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
8 Lean Concrete (Grade
15) as specified; as 1,456m2 6 Trowel 1 Skill labor Workers 4 days
blinding screed laid on output
earth or hardcore: - 9 general labor
50mm Thick under: - = 4.55m2/hr
Ground floor slab
4.55m2/hr x 10

=45.5m2/hr

1,456m2/45.5m
2
/hr/8hrs

= 4 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: WBLFF (Lean conc. grd 15) (Masjid) PAGE NO: 9

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
9 Lean Concrete (Grade
15) as specified; as 200m2 3 Trowel 1 Skill labor Workers 2 days
blinding screed laid on output
earth or hardcore: - 3 General
50mm Thick under: - labor = 4.55 m2
Apron slab
4.55m2 x 4

=18.2m2

200m2/18.2m2/
8hrs

= 1.37 day
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: WBLFF (Reinforced Conc. grd 25) (Masjid) PAGE NO: 10

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
10 Reinforced Concrete
(Grade 25) as specified 50m3 3 Trowel 1 Skill labor Workers 1 days
in: - output
Pile caps 2 General
labor = 3.67m3

3.67m3 x 3

= 11.01m3

50m3/11.01m3/
8hrs

= 0.57 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: WBLFF (Reinforced Conc. grd 25) (Masjid) PAGE NO: 11

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
11 Reinforced Concrete
(Grade 25) as specified 8m3 3 Trowel 1 Skill labor Workers 1 days
in: - output
Column stumps 2 General
labor = 3.67m3

3.67m3 x 3

= 11.01m3

8m3/11.01m3/8
hrs

= 0.10 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: WBLFF (Reinforced Conc. grd 25) (Masjid) PAGE NO: 12

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
12 Reinforced Concrete
(Grade 25) as specified 75m3 3 Trowel 1 Skill labor Workers 1 days
in: - output
Ground beams 2 General
labor = 3.67m3

3.67m3 x 3

= 11.01m3

75m3/11.01m3/
8hrs

= 0.85 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019

ELEMENT: WBLFF (Reinforced Conc. grd 25) (Masjid) PAGE NO: 13

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
13 Reinforced Concrete
(Grade 25) as specified 1,456m2 6 Trowel 1 Skill labor Workers 2 days
in: - output
Floor slab 7 General
labor = 12.5m2/hr

12.5m3/hr x 8

=100m2/hr

1,456m2/100m
2
/hr/8hrs

= 1.82 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/20
ELEMENT: WBLFF (Reinforced Conc. grd 25) (Masjid) PAGE NO: 14

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
14 Reinforced Concrete
(Grade 25) as specified 200m2 3 Trowel 1 Skill labor Workers 1 day
in: - output
Apron slab 3 general labor
= 12.5m2

12.5m3 x 4

= 50m2

200m2/50m2/8
hrs

= 0.50 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: WBLFF (Formwork) (Masjid) PAGE NO: 15

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
15 To sides of pile caps
275m2 6 Hammer 1 Carpenter Workers 1 day
output
5 General
labor = 12.5 m2

12.5m2 x 6

=75m2

275m2/75m2/8
hrs

= 0.45 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: WBLFF (Formwork) (Masjid) PAGE NO: 16

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
16 To sides of column
stumps 75m2 2 Hammer 1 Carpenter workers output 1 day
= 3.5m2
2 General
labor 3.5m2 x 3

=10.5m2

75m2/10.5m2/8
hrs

=0.89 day
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: WBLFF (Formwork) (Masjid) PAGE NO: 17

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR

17 To sides of ground 1,150m2 6 Hammer 1 Carpenter Workers 2 days


beams output
7 General
labor = 12.5m2/hr

12.5m2 x 8

= 100m2/hr

1,150m2/100m
2
/hr/8hrs

= 1.44 day
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: WBLFF (Formwork) (Masjid) PAGE NO: 18

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR

18 To edge of apron slab 200m 2 Hammer 1 Carpenter Workers 1 day


100mm thick output
4 General
labor = 5.5m

5.5m x 5

= 27.5m

200m/27.5m/8
hr

= 0.91 day
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: WBLFF (High tensile rod reinforcement) (Masjid) PAGE NO:19

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
19 In Pile Caps
10mm - 25mm Diameter 7,400kg Bar bender 2 Bar benders Workers 2 days
machine output
9 General
labor = 50kg/h

50kg/h x 11

= 550kg/hr

7,400kg/550kg
/h/8 hr

= 1.68 day
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: WBLFF (High tensile rod reinforcement) (Masjid) PAGE NO: 20

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
20 In Column Stumps
10mm - 25mm Diameter 1240kg Bar bender 2 Bar benders Workers 1 days
machine output
4 General
labor = 50kg/h

50kg/h x 6

= 300kg/hr

1240kg/300kg/
h/8 hr

= 0.52 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: WBLFF (High tensile rod reinforcement) (Masjid) PAGE NO: 21

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
21 In Ground Beams
10mm - 25mm Diameter 14,850kg Bar bender 4 Bar benders Workers 3 days
machine output
9 General
labor = 50kg/h

50kg/h x 13

= 650kg/hr

14,850kg/650k
g/h/8 hrs

= 2.85 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: WBLFF (High tensile rod reinforcement) (Masjid) PAGE NO: 22

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
22 In Ground Slab
10mm - 25mm Diameter 21,658kg Bar bender 4 Bar benders Workers 4 days
machine output
10 General
labor = 50kg/h

50kg/h x 14

= 700kg/hr

21,658kg
/700kg/h/8 hrs

= 3.87 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: WBLFF (High tensile rod reinforcement) (Masjid) PAGE NO: 23

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
23 In Apron slab
10mm - 25mm Diameter 3,000kg Bar bender 2 Bar benders Workers 1 day
machine output
6 General
labor = 50kg/h

50kg/h x 8

= 400kg/h

3,000kg x
400kg/h/8 hr

= 0.93 day
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: WBLFF (Damp Proof Membrane) (Masjid) PAGE NO: 24

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
24 A layer of 0.125mm
heavy duty polythene 1,656m2 1 Site Workers 3 days
sheet as described laid supervisor output
below concrete bed
(measured net-no 7 General = 12.5m2
allowance made for laps) labor
12.5m2 x 8

=100m2

1,656m2/100m
2
/8hrs

= 2.07 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: WBLFF (Anti-termite Treatment) (Masjid) PAGE NO: 25

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
25 Supply and apply anti-
termite treatment to 2,153m2 1 Pressure 1 Site Tool output 3 days
ground floor area with 5 spray supervisor
years’ warranty all as per = 12.5m2
S.O approval. 8 Tool
operators 12.5m2 x 9

=112.5m2

2,153m2/112.5
m2/8hrs

= 2.39 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: WBLFF (Perimeter Drain) (Masjid) PAGE NO: 26

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
26 230mm diameter precast
concrete as specified half 250m 4 Trowel 1 Skilled labor Workers 1 day
round drain, finished fair output
or exposed surfaces, 4 General
bedded, jointed and labor = 7.65m
pointed in cement mortar
(1:3) to engineer detail 7.65m x 5
including disposal of
=38.25m
surplus excavated
material and all the entire 250m/38.25m/
satisfaction of the S.O. 8hrs

= 0.82 day
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: WBLFF (M.S Grating) (Masjid) PAGE NO: 27

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
27 Supply and install Mild
steel grating to engineer 75m 1 Skilled labor Workers 1 day
details as per drawing output
2 General
labor = 7.00m

7.00m x 3

= 21.00m

75m/21.00m/8
hrs

= 0.45 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: WBLFF (Staircase (step)) (Masjid) PAGE NO: 28

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
28 To construct and
complete reinforced L.S 1 site - 2 days
concrete step with supervisor
concrete grade 25, fabric
reinforcement, formwork, 3 skilled labor
tiling and including all
necessary accessories 6 general labor
and work all as per
Architect's drawings and
approval.