Beruflich Dokumente
Kultur Dokumente
Units. The contracted load or the sanctioned load is 5KW for MPPT Range 175-800 V
the considered building floor. The solar policy of the state has Maximum Voltage 850 V
to be studied before selection of plant capacity i.e. for (Voc Inv)
Telangana state for commercial building the solar plant is Short Circuit Current 18 A
upto 80% of the sanctioned load whereas it is 100% for (Isc Inv)
domestic. Table 2 Technical Specifications of Selected On-Grid
Inverter
Month Units
B. Selection of Solar Panels
January 665 The ratio of how much DC capacity (the quantity and
wattage of solar panels) is installed to the inverter’s AC
February 652 power rating is called the DC-to-AC ratio, or DC load ratio,
over sizing ratio or overloading ratio, etc[4]. For example, a
March 791 120 kW DC array with a 100 kW AC inverter has a
DC-to-AC ratio of 1.2. It often makes sense to oversize a
April 1052 solar array, such that the DC-to-AC ratio is greater than 1.
Generally DC-to-AC ratio is taken 10 to 13% and also
May 1039 depends on different locations.
June 1087 𝐷𝐶
= 1 𝑡𝑜 1.3
𝐴𝐶
July 987
𝐷𝐶
August 983 = 1.10 (𝑂𝑣𝑒𝑟𝑠𝑖𝑧𝑖𝑛𝑔 10%)
4𝐾𝑊
October 687
Thus 4.4 KWp is solar plant Capacity.
November 557 There are variety of solar panels available in the market. For
this site Waree solar i.e. of 250 Wp polycrystalline panel is
December 539 chosen. Table 3 shows the technical specifications of the
solar panel chosen.
Average 804.83
Nominal Maximum Power 250
Table 1 Consumption as per Annual Electricity Bill (Pm) in Watts
Power tolerance 0/+5W
37 V x 18 850 V
= 666V
Thus 666 V is obtained (which less than 850 V) and is safe
for inverter as it is less than its Voc.
E. Financial Analysis Thus it would take 4 years to get back our invested money.
The Telangana State Electricity Regulatory Commission To know the profit of the plant we use Return on my
(TSERC) has approved net metering for solar rooftop Investment (ROI) which shows the profitability index of our
customers in the state with systems ranging from 1 kW to 1 plant, it is given as
MW.Here the state government is set to buy power at Rs 3.50
per unit.Net metering scheme is shown in fig 5 where export Capital savings – Capital Cost
ROI =
means solar panel to grid and import means consumption Capital Cost
from grid i.e. DISCOM.
15 lac −2.4 lac
= 5.25
2.4 lac
III. CONCLUSION
The simple designing and installation techniques for
4 kWp On-Grid plant is studied. Below fig 6 shows the photo
Fig 5 Illustration of Net Metering Scheme of SPV plant after installation. The plant is supplying about
500 KWh per month. A new technique for interconnection of
panels is proposed and found that it is advantageous in saving
Energy from Solar Power Plant the length of DC cable to some extent. Finally, financial
Average Units Consumed Per Month analysis is carried out and found that payback period of the
plant is 4 years and also Return on Investment is about 5.25
= 804.83 KW hr/Month times the initial investment.
Average Units Consumed Per Day
=26.82 KW hr/Day
No of Units generated by SPV Plant
= 4 KW x 0.8 x Sun Hours of Location
=17KW hr/Day (Sun hours for Hyderabad is taken as 5.31)
Thus for 1 KW, panel will generate about 4 to 5 Units per
Day
Therefore for 1 Month =17 x 4 = 510 Units
Calculation of Import
Units consumed = 804.83 KW hr/Month Fig 6 Photo of 4 KWp On-Grid SPV Plant after Installation
Units Generated =510 KW hr/Month
Import = 294.83 KW hr ACKNOWLEDGMENT
We like to thank our trainer Mr. Hari Krishna who helped
From section LT(II) B of TSPDCL which is state’s us through the installation and also 2e Skills (Steinbeis
DISCOM, the Tariff rate for commercial consumers is Academy for Advanced Technical Training, Hyderabad) for
From 0-100 Units = Rs 7.5 and 100-300 =Rs 8.90 providing technical data and equipments for installation.
From above, the charges which has to be paid to the
Government is Rs 2485.5 REFERENCES
Payback period calculates the time period to get back our AUTHORS PROFILE
invested money on installing solar plant. It defines as Shariq Ayjaz Mohammed received the B.E degree in
electrical and electronics engineering with honors from
the Osmania University, Hyderabad, India, in 2017.He is
Total Plant Cost or Capital cost currently perusing Masters in Power electronic systems
Payback period =
Yearly savings from Osmania University, Hyderabad, India.
His research interests include design, modeling, and
2.4 lac control of power electronics converters,
=4 renewable energy systems and
60,000