Beruflich Dokumente
Kultur Dokumente
2018.01.26
< CONTENT>
1. GENERAL DESCRIPTIONS
1.1 General
1.2 Equipment Specifications
1.3 Lay Out
1.4 Preparation for Commissioning
1.5 Progress Schedule Progress Schedule for Belt Conveyor(Unit)
1.1 General
This guide book is that describes the pipe conveyor and equipment.
This Project will be served as follows to guarantee the good efficiency.
1.3.2 CNV-801A/B
1.3.3 CNV-802
1.3.4 CNV-803
1.3.5 CNV-804
Time(Day)
0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0
Item
No Load Test
Load Test
Time(hr)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Item
Individual Test
Adjust
Interlock Test
Time(hr)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Item
Interlock Test
Adjust
Operation
2. COMMISSIONING CHECK SHEET
Pull-Cord Switch
Inspection Equipment
(Back Stop)
2.2 Method for Commissioning
① Adjust open / pipe part while short commissioning at 10~30 seconds period,
five times by commander of commission.
② After complete method ①, adjust twist of belt during another short
commissioning of 1~2 minutes (make belt proceed one cycle of line) by
judgment of commander.
③ After complete method ②, make a conveyor belt drive for 30~60 minutes
continuously. If there are any troubles, make the conveyor stop and adjust in
detail. Move to next step by judgment of commander.
④ After complete method ③, make the conveyor drive with 'no load condition'
and 'load condition'. And check driven time of each equipment in conveyor.
2.3 Check Point For Commissioning
GIRDER
4
PART
Direction of rotation ○
Output measurement ○
Output measurement ○
Output measurement ○
(Unit : mm)
#1 Head No load
1
Pulley Load
#2 Snub No load
2
Pulley Load
#3 Bend No load
3
Pulley Load
#4 Bend No load
4
Pulley Load
#5 Gravity No load
5
Pulley Load
#6 Tail No load
6
Pulley Load
2.6 Check Sheet for Drive Unit
(Unit : mm)
Ambient temperature : ℃
A(Reducer)
Drive Unit
B(Motor)
#1 Head R
Pulley L
#2 Snub R
Pulley L
#3 Bend R
Pulley L
Bearing Part
#4 Bend R
Pulley L
#5 Gravity R
Pulley L
#6 Tail R
Pulley L
2.6.3 Check the Vibration of Drive Unit
(Unit : ㎛)
Position 1 2 3 4 5 Remark
Motor
Condition Unloading
Loading
2.7 Check Sheet for Take Up Unit
(Unit : mm)
No.
A
Date
(Unit : mm)
No.
A B C D
Date
3. NOTE FOR COMMISSIONING