Rebound
Dial gauge Reading
Location of test & Pavement Deflection in
Srl NO Type of soil
Identification lane Temp o C Initial Intermediate Final mm
Do Di Df 0.02(Do-Df)*
1 Km 0.100, L1 27 Not Recorded 112 6 5 2.14
2 " 0.150, L2 102 8 6 1.92
3 " 0.200, L1 123 3 2 2.42
4 " 0.250, L2 120 5 4 2.32
5 " 0.300, L1 99 9 8 1.82
6 " 1.000, L2 105 13 14 1.82
7 " 1.050, L1 98 4 2 1.92
8 " 1.100, L2 106 5 3 2.06
9 " 1.150, L1 123 6 4 2.38
10 " 1.200, L2 119 9 8 2.22
1 Km 2.000, L1 97 6 4 1.86
2 " 2.050 , L2 98 9 8 1.8
3 " 2.100, L1 141 7 5 2.72
4 " 2.150, L2 120 8 6 2.28
5 " 2.200, L1 98 8 6 1.84
NAME OF ROAD
NAME OF SECTION
NO OF TRAFFIC LANE TWO/ ONE