JAKARTA CIKAMPEK II ELEVATED TOLL ROAD

SECTION : CIKUNIR TO CIKARANG BARAT


MASTER SCHEDULE PENYELESAIAN PEKERJAAN 1 OF 3

STA.9+500 TO STA.47+600
AREA 1 & AREA 2 - DETAIL SCHEDULE

ID Task Task Name % Complete Duration Actual Start Actual Finish


Mode Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019
Mar Apr May Jun Jul Aug Sep Oct
1 JAKARTA CIKAMPEK ELEVATED II TOLL ROAD PROJECT 52% 255 days Sat 09/02/19 NA

2 PENYELESAIAN PROYEK JAPEK II ELEVATED 52% 255 days Sat 09/02/19 NA


3 Penyelesaian Geoteknik (Extend Pilecap) 100% 104 days Fri 22/03/19 Thu 25/07/19 22/03 25/07
160 Penyelesaian AREA 1 (STA 9+500 S.D 17+100) 55% 229 days Thu 07/03/19 NA3
161 Cut Off Date 100% 0 days Fri 22/03/19 Fri 22/03/19 22/03
162 Zona 1 ‐ Interchange Cikunir (STA 9+500 s.d  33% 223 days Wed 13/03/19 NA/03
10+500)
163 Widening Works 42% 176 days Fri 22/03/19 NA 22/03 05/10
164 Widening Works (Existing) 42% 176 days Fri 22/03/19 NA 22/03 05/10
165 Ramp 2 (Pd. Indah ‐ Cikampek) 100% 18 days Mon 22/04/19 Thu 09/05/19 22/04 09/05
166 Japek Overpass Duplication (North  100% 18 days Mon 22/04/19 Thu 09/05/19 22/04 09/05
Overpass)
184 Artery Road Duplication (South  100% 17 days Tue 23/04/19 Thu 09/05/19 23/04 09/05
Overpass)
190 Ramp 5 (Tj. Priok ‐ Cikampek) 100% 51 days Fri 22/03/19 Sat 11/05/19 22/03 11/05
191 Structure Widening (After Portal  100% 51 days Fri 22/03/19 Sat 11/05/19 22/03 11/05
Concrete Ramp F)
197 Ramp 1 (Bintara ‐ Cawang) ‐ Looping D 0% 69 days NA NA 29/07 05/10
198 Relocation Toll Gate GT1 Cikunir 0% 68 days NA NA 29/07 04/10
199 Demolition Toll Gate GT1 Existing 0% 68 days NA NA 29/07 04/10
206 Subtitute for Toll Gate GT1 Cikunir (in 0% 55 days NA NA 29/07 21/09
GT3 or shifting in GT1)
213 Operational Ramp 1 0% 1 day NA NA 05/10 05/10
214 Structure Works 40% 223 days Wed 13/03/19 NA/03
215 Ramp A 58% 199 days Wed 13/03/19 NA/03 19/
216 Structure Works 100% 72 days Fri 22/03/19 Sun 23/06/19 22/03 23/06
336 Steel Box Girder 100% 84 days Wed 27/03/19 Wed 10/07/19 27/03 10/07
397 Diafragma + Torsi 67% 79 days Wed 24/04/19 NA 24/04 02/08
413 Deck Slab 58% 147 days Wed 13/03/19 NA/03 28/08
665 LRB 26% 96 days Sun 05/05/19 NA 05/05 30/08
686 Link Slab 12% 59 days Fri 12/07/19 NA 12/07 08/09
707 Parapet 9% 128 days Fri 19/04/19 NA 19/04 15/09
728 Ekspansion Join 0% 25 days NA NA 25/09 19/
748 Ramp B 51% 164,5 days Fri 12/04/19 NA 12/04 15/10
749 Steel Box Girder 100% 20 days Wed 15/05/19 Tue 25/06/19 15/05 25/06
758 Diafragma + Torsi 100% 37 days Sun 23/06/19 Mon 29/07/19 23/06 29/07
761 Deck Slab 70% 103 days Sun 21/04/19 NA 21/04 23/08
785 LRB  0% 4 days NA NA 24/08 27/08
788 Link Slab 0% 11 days NA NA 26/08 05/09
791 Parapet  0% 137 days Fri 12/04/19 NA 12/04 17/09
795 Ekspansion Join 0% 5 days NA NA 10/10 15/10
798 Ramp C 7% 146,5 days Sat 18/05/19 NA 18/05
799 Steel Box Girder 56% 55 days Mon 20/05/19 NA 20/05 04/08
828 Diafragma + Torsi 21% 27 days Sun 14/07/19 NA 14/07 09/08
836 Deck Slab 3% 70 days Thu 27/06/19 NA 27/06 04/09
917 LRB 0% 40 days NA NA 29/07 06/09
928 Link Slab 0% 47 days NA NA 31/07 15/09
939 Parapet 0% 106 days Sat 18/05/19 NA 18/05 22/09
950 Ekspansion Join 0% 25 days NA NA 08/10
961 Ramp D 85% 186,5 days Sat 16/03/19 NA6/03 10/10
962 Steel Box Girder 100% 61 days Thu 21/03/19 Mon 20/05/19 21/03 20/05
988 Diafragma + Torsi 100% 89 days Sun 14/04/19 Fri 02/08/19 14/04 02/08
994 Deck Slab 100% 120 days Sat 16/03/19 Sun 04/08/196/03 04/08
1092 LRB 100% 62 days Tue 23/04/19 Mon 15/07/19 23/04 15/07
1101 Link Slab 65% 36 days Tue 02/07/19 NA 02/07 06/08
1110 Parapet 89% 83 days Mon 22/04/19 NA 22/04 04/08
1119 Ekspansion Join 0% 10 days NA NA 30/09 10/10
1129 Ramp E 21% 153,5 days Mon 15/04/19 NA 15/04 07/10
1130 PCU Girder & Steel Box Girder 100% 51 days Mon 15/04/19 Wed 26/06/19 15/04 26/06
1138 Diafragma + Torsi 0% 5 days NA NA 29/07 02/08
1140 Deck Slab 22% 103 days Tue 30/04/19 NA 30/04 01/09
1164 LRB 0% 2 days NA NA 28/08 29/08
1166 Link Slab 0% 9 days NA NA 30/08 07/09
1168 Parapet 13% 91 days Sat 15/06/19 NA 15/06 14/09
1171 Ekspansion Join 0% 5 days NA NA 02/10 07/10
1173 Ramp F 13% 190 days Mon 15/04/19 NA 15/04
1174 Structure Works 100% 1 day Sun 16/06/19 Sun 16/06/19 16/06 16/06
1179 Steel Box Girder 77% 93,7 days Mon 15/04/19 NA 15/04 08/08
1224 Diafragma + Torsi 44% 51,7 days Sun 23/06/19 NA 23/06 13/08
1236 Deck Slab 7% 111 days Sat 04/05/19 NA 04/05 13/09
1363 LRB 0% 73,7 days Tue 02/07/19 NA 02/07 13/09
1379 Link Slab 0% 55,7 days NA NA 29/07 22/09
1395 Parapet 0% 53,7 days NA NA 07/08 29/09
1413 Ekspansion Join 0% 25 days NA NA 19/10
1429 Pavement (Asphalt) 0% 34 days NA NA 15/09 18/1
1430 Ramp A 0% 10 days NA NA 15/09 24/09
1451 Ramp B 0% 2 days NA NA 08/10 10/10
1456 Ramp C 0% 6 days NA NA 02/10 08/10
1469 Ramp D 0% 5,5 days NA NA 25/09 30/09
1481 Ramp E 0% 2 days NA NA 30/09 02/10
1486 Ramp F 0% 8,5 days NA NA 10/10 18/1
1504 Drainage 0% 97,5 days NA NA 29/07
1505 Ramp A 0% 84 days NA NA 29/07 20/
1566 Ramp B 0% 79,5 days NA NA 29/07 16/10
1579 Ramp C 0% 97,5 days NA NA 29/07
1613 Ramp D 0% 74,5 days NA NA 29/07 11/10
1644 Ramp E 0% 71,5 days NA NA 29/07 08/10
1654 Ramp F 0% 47,7 days NA NA 29/07 14/09

Page 1
JAKARTA CIKAMPEK II ELEVATED TOLL ROAD
SECTION : CIKUNIR TO CIKARANG BARAT
MASTER SCHEDULE PENYELESAIAN PEKERJAAN 2 OF 3

STA.9+500 TO STA.47+600
AREA 1 & AREA 2 - DETAIL SCHEDULE

ID Task Task Name % Complete Duration Actual Start Actual Finish


Mode Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019
Mar Apr May Jun Jul Aug Sep Oct
1703 Concrete Double Barrier 11% 98 days Tue 16/07/19 NA 16/07 21
1715 Lighting and Electrical 0% 28,25 days NA NA 25/09 23
1716 Ramp A 0% 5 days NA NA 25/09 29/09
1737 Ramp B 0% 1 day NA NA 10/10 11/10
1742 Ramp C 0% 3 days NA NA 08/10 11/10
1755 Ramp D 0% 2,75 days NA NA 30/09 03/10
1767 Ramp E 0% 1 day NA NA 19/10 19/
1772 Ramp F 0% 4,25 days NA NA 19/10 23
1790 Miscellaneous Works 0% 85,7 days NA NA 05/08
1880 Toll Gate IC Cikunir 10% 213 days Fri 22/03/19 NA 22/03
1906 Zona 2 ‐ P1 s.d P42 (STA 10+500 s.d 13+400) 76% 215,5 days Thu 14/03/19 NA /03
1907 Deck Slab 100% 51 days Thu 21/03/19 Fri 10/05/19 21/03 10/05
2040 LRB  95% 100 days Sun 31/03/19 NA 31/03 30/07
2148 Link Slab 83% 136 days Tue 19/03/19 NA19/03 23/08
2606 Parapet 95% 129 days Thu 14/03/19 NA /03 11/08
3456 Expansion Joint Installation 0% 45 days NA NA 22/09
3474 Pavement (Asphalt)  0% 11 days NA NA 17/09 28/09
3561 Drainage 17% 124 days Tue 02/04/19 NA 02/04 25/08
3562 Deck Drain 15% 102 days Tue 02/04/19 NA 02/04 03/08
3605 Median Drain Relocation  6% 62 days Tue 25/06/19 NA 25/06 25/08
3648 Drainage Pipe 26% 88 days Thu 18/04/19 NA 18/04 05/08
3691 Concrete Double Barrier 18% 51 days Wed 10/07/19 NA 10/07 29/08
3734 Lighting and Electrical 0% 10,5 days NA NA 19/09 30/09
3821 Miscellaneous Works 0% 69,25 days NA NA 29/07 06/10
3822 Road Mark 0% 10,5 days NA NA 25/09 06/10
3909 Traffic Sign 0% 30 days NA NA 29/07 27/08
3910 Kilometer Post 0% 30 days NA NA 29/07 27/08
3911 Zona 3 ‐ P43 s.d P103 (STA 13+400 s.d 17+100) 66% 219,5 days Thu 07/03/19 NA3
3912 Steel Box Girder 100% 112 days Thu 14/03/19 Thu 25/07/19 /03 25/07
3979 Diafragma + Torsi 71% 71 days Thu 02/05/19 NA 02/05 02/08
3987 Deck Slab 74% 167 days Thu 07/03/19 NA3 11/09
4210 LRB 89% 142 days Sat 23/03/19 NA 23/03 02/09
4331 Pendulum 0% 4 days NA NA 26/09 29/09
4341 Link Slab 76% 184 days Fri 22/03/19 NA 22/03 13/10
4975 Parapet 76% 160 days Wed 20/03/19 NA 20/03 18/09
6240 Expansion Joint Installation 3% 134,5 days Sat 22/06/19 NA 22/06
6264 Pavement (Asphalt)  0% 16 days NA NA 18/09 04/10
6389 Drainage 30% 180 days Sat 30/03/19 NA 30/03 17/1
6390 Deck Drain 66% 144 days Sat 30/03/19 NA 30/03 11/09
6452 Median Drain Relocation  0% 81 days NA NA 29/07 17/1
6514 Drainage Pipe 34% 142 days Wed 03/04/19 NA 03/04 13/09
6576 Concrete Double Barrier 11% 128 days Wed 05/06/19 NA 05/06 21/
6638 Lighting and Electrical 0% 15,25 days NA NA 10/09 25/09
6700 Miscellaneous Works 0% 30 days NA NA 19/09 18/1
6701 Road Mark 0% 15,25 days NA NA 27/09 12/10
6826 Traffic Sign 0% 30 days NA NA 19/09 18/1
6827 Kilometer Post 0% 30 days NA NA 19/09 18/1
6828 Finish Area 1 0% 0 days NA NA
6829 Penyelesaian AREA 2 (STA 14+350 S.D 28+450) 48% 250,75 days Sat 09/02/19 NA
6830 Cut Off Date 100% 0 days Fri 22/03/19 Fri 22/03/19 22/03
6831 ZONA 4 ‐ P104 s.d P176 (STA 17+100 s.d 21+400) 55% 250,75 days Sat 09/02/19 NA
6832 Hand Over Lokasi SUTET KCIC 0% 1 day NA NA 29/07 29/07
6833 Portal Grand Wisata 100% 33 days Fri 12/04/19 Tue 14/05/19 12/04 14/05
6853 Steel Box Girder 89% 110 days Thu 28/03/19 NA 28/03 06/08
6927 Deck Slab 69% 164 days Tue 12/03/19 NA 03 13/09
7199 LRB 72% 181 days Sat 09/02/19 NA 30/08
7233 Pendulum 0% 3 days NA NA 14/09 16/09
7237 Link‐Slab 66% 163 days Sat 30/03/19 NA 30/03 30/09
7820 Parapet 61% 182 days Tue 19/03/19 NA19/03 08/10
9565 Ekspansion Joint 0% 29 days NA NA 10/10
9590 Pavement (Asphalt) 0% 18,25 days NA NA 22/09 10/10
9738 Drainage 16% 169,75 days Tue 23/04/19 NA 23/04
9739 Deck Drain 82% 123 days Tue 23/04/19 NA 23/04 14/09
9813 Median Drain Relocation  0% 94,75 days NA NA 29/07
9887 Drainage Pipe 0% 50 days NA NA 29/07 16/09
9961 Concrete Double Barrier 9% 121,75 days Sat 06/07/19 NA 06/07
10035 Lighting and Electrical 0% 64,75 days NA NA 06/08 09/10
10108 Miscellaneous Works 0% 35,5 days NA NA 23/09
10109 Road Marking 0% 18 days NA NA 10/10
10256 Traffic Sign 0% 30 days NA NA 23/09 22/
10257 Kilometer Post 0% 30 days NA NA 28/09 2
10258 ZONA 5 ‐ P177 s.d P231 (STA 21+400 s.d 24+700) 47% 213,75 days Mon 18/03/19 NA18/03
10259 Structure Works (Bored Pile, Pile Cap, Pierhead) 100% 26 days Mon 25/03/19 Fri 19/04/19 25/03 19/04

10269 Steel Box Girder 97% 110 days Wed 20/03/19 NA 20/03 29/07


10310 Erection Longspan IC Cibitung (P229 ‐ P230 ‐  100% 67 days Sun 14/04/19 Thu 11/07/19 14/04 11/07
P231 ‐ P232)
10362 Deck Slab 63% 158 days Mon 18/03/19 NA18/03 13/09
10628 LRB 67% 131 days Fri 22/03/19 NA 22/03 21/08
10655 Pendulum 0% 3 days NA NA 14/09 16/09
10659 Link‐Slab 47% 166 days Wed 27/03/19 NA 27/03 30/09
11152 Parapet 51% 179 days Fri 22/03/19 NA 22/03 08/10
12507 Ekspansion Joint 0% 15 days NA NA 24/10
12530 Pavement (Asphalt) 0% 14,25 days NA NA 10/10 2
12643 Drainage 16% 164 days Sun 07/04/19 NA 07/04 09/10
12644 Deck Drain 82% 141 days Sun 07/04/19 NA 07/04 16/09
12700 Median Drain Relocation  0% 73 days NA NA 29/07 09/10
12756 Drainage Pipe 0% 52 days NA NA 29/07 18/09

Page 2
JAKARTA CIKAMPEK II ELEVATED TOLL ROAD
SECTION : CIKUNIR TO CIKARANG BARAT
MASTER SCHEDULE PENYELESAIAN PEKERJAAN 3 OF 3

STA.9+500 TO STA.47+600
AREA 1 & AREA 2 - DETAIL SCHEDULE

ID Task Task Name % Complete Duration Actual Start Actual Finish


Mode Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019
Mar Apr May Jun Jul Aug Sep Oct
12812 Concrete Double Barrier 16% 106 days Fri 28/06/19 NA 28/06 11/10
12868 Lighting and Electrical 0% 65,5 days NA NA 05/08 09/10
12924 Miscellaneous Works 0% 51,75 days NA NA 09/09
12925 Road Marking 0% 13,75 days NA NA 17/10
13038 Traffic Sign 0% 30 days NA NA 09/09 08/10
13039 Kilometer Post 0% 30 days NA NA 09/09 08/10
13040 ZONA 6.1 ‐ P232 s.d P294 (STA 24+700 s/d  40% 178 days Tue 19/03/19 NA19/03 04/10
28+450)
13041 Structure Works (Bored Pile, Pile Cap, Pierhead) 100% 0 days Fri 22/03/19 Fri 22/03/19 22/03
13042 Steel Box Girder 83% 114 days Fri 22/03/19 NA 22/03 04/08
13099 Deck Slab 42% 125 days Sun 07/04/19 NA 07/04 31/08
13333 LRB 59% 102 days Thu 02/05/19 NA 02/05 02/09
13367 Link‐Slab 37% 167 days Wed 27/03/19 NA 27/03 01/10
13980 Parapet 53% 144 days Tue 19/03/19 NA19/03 31/08
15413 Ekspansion Joint 0% 15 days NA NA 12/09 26/09
15446 Pavement (Asphalt) 0% 16 days NA NA 26/08 11/09
15578 Drainage 17% 144 days Sun 21/04/19 NA 21/04 03/10
15579 Deck Drain 83% 112 days Sun 21/04/19 NA 21/04 01/09
15643 Median Drain Relocation  0% 67 days NA NA 29/07 03/10
15707 Drainage Pipe 0% 37 days NA NA 29/07 03/09
15771 Concrete Double Barrier 20% 102 days Tue 25/06/19 NA 25/06 04/10
15835 Lighting and Electrical 0% 39 days NA NA 29/07 05/09
15900 Miscellaneous Works 0% 31,65 days NA NA 29/07 29/08
15901 Road Marking 0% 6,4 days NA NA 23/08 29/08
16032 Traffic Sign 0% 30 days NA NA 29/07 27/08
16033 Kilometer Post 0% 30 days NA NA 29/07 27/08
16034 Finish Area 2 0% 0 days NA NA
16035 Hand Over to JJC 0% 14 days NA NA 28/10
16038 Open Traffic (Area 1 & 2 Functional Finish) 0% 0 days NA NA