Engineering Design & Construction Supervision of the Palma -
Afungi - Highway 00 00

WEEKLY REPORT
REF NO: SWM-T-QAQC-001

Prepared for AMA 1 & CCC

Dates: 14/05/2018 - 19/05/2018


Week 01

This document is issued without any alterations

00 19/05/2018 Issued for Review Lawrence Nyarko Samuel Nhemachena

Rev Date Status Description By Issued to


Document Title: Weekly Report 01 Document Type: Weekly Report

Doc Number: SWM-AMA 1-WR-001 Pages:8 Revision: 00 Status: Review

Page 1
ISO 9001:2008 DOC NO: SWM-AMA 1-WR-001

VERSION Rev.
Engineering Design & Construction Supervision of the Palma -
Afungi - Highway 00 00

WEEKLY REPORT
REF NO: SWM-T-QAQC-001
1. ENGINEERING DESIGN AND CONSTRCTION SUPERVISON OF THE PALMA – AFUNGI ROAD

1.1 QUALITY PLAN AND OBJECTIVES


To ensure construction procedures is compliance to specification and standard and to maintain consistently the
quality of work.

1.2 EXECUTIVE SUMMARY


1. Materials Laboratory is not complete:
a. Calibration certificates are not at site
b. Some of equipment are not complete
c. Borrow pit is not yet sample, due to machinery (excavator breakdown), this is very critical for contractor
production. E-mail was communicated to the contractor Quality Engineer dated 5/17/2018 8:53 AM/ our
ref: SWM-CCCM-LN-001
d. No official test result submitted for approval
e. Sampling road bed at ch. 0+200 for analysis

2. Production: no. 3 teams


a. Ongoing of cleaning and grubbing, approximately at km 10+300 complete, contractor have to submit RFI
for approval
b. Ongoing of roots picking (cleaning) of road bed preparation, approx. 500 meters complete from 0+00 to
0+500 of team 1, contractor have to submit RFI for approval
c. Ongoing of roots picking (cleaning) of road bed preparation, approx. 700 meters complete from 4+000 to
4+700 of team 2, contractor have to submit RFI for approval
d. Team 3 with Dozer cleaning road diversion for traffic for production machinery
e. Ongoing preparation of camp accommodation and site offices for workforce

PRODUCTION
14
12
10
8
6
4
2
0

Total Progress Due

Page 2
ISO 9001:2008 DOC NO: SWM-AMA 1-WR-001

VERSION Rev.
Engineering Design & Construction Supervision of the Palma -
Afungi - Highway 00 00

WEEKLY REPORT
REF NO: SWM-T-QAQC-001
MILESTONE COMPLETION PERCENTAGES Percent Paid Pending

Upon Notice to Proceed - (Milestone Payment) 10%

Upon Company Acceptance of Contractor's Engineering Drawings and Specifications


(Progress Payment) 10%

Upon Site Mobilization - (Milestone Payment) 10%

Upon Site Delivery of Materials (Progress Payment) 20%

Field Construction (Progress Payment) 40%

Upon Final Completion (Milestone Payment) 10%

Total Lump Sum for Base - Afungi Road 100%

No IPC submitted, contractor should advise

1.3 STATUS OF MATERIAL PROCUREMENT/EXPEDITING


CONCRETE MATERIAL FOR TEST PILES
Item Type STATUS Remarks
1 Rock-fill Tested result not yet submitted for approval
2 Cement 0
3 Water Tested result not yet submitted for approval
4 Reinforcement 0
5 Concrete aggregate 0
Concrete sand 0
Admixture 0
Bitumen 0

1.4 DOCUMENT STATUS/CONCERNS/OPEN ITEMS (IF ANY)

S.N. QA/QC DOCUMENTS STATUS REMARKS

1 METHOD STATEMENTS CCCM Reviewed Pending Transmittal

2 FINAL DESIGN REPORT Engineer to Advise

LIST OF EQUIPMENT

Page 3
ISO 9001:2008 DOC NO: SWM-AMA 1-WR-001

VERSION Rev.
Engineering Design & Construction Supervision of the Palma -
Afungi - Highway 00 00

WEEKLY REPORT
REF NO: SWM-T-QAQC-001

1.5 EQUIPMENT ON SITE

Appendix 01. Equipment list

1.6 LABORATORY EQUIPMENT ON SITE

Appendix 02. Equipment list

1.7 STATUS OF REPAIR, INSPECTION AND CALIBRATION OF THE TOOLS AND EQUIPMENT

SURVEY EQUIPMENT
Item Type Model Serial number Due Date Remarks
1 Total station
2 Auto Level
LABORATORY TESTING EQUIPMENT
1 Weighing balance
2 Compressive machine 2000KN
3 CBR rig
4 Oven

1.8 LIST AND STATUS OF DOCUMENTS PROVIDED BY ANADARKO (AMA 1)


No document received from the contractor

1.9 LIST AND STATUS OF DOCUMENTS PREPARED BY SWM

Doc. E-mail: SWM-CCCM-LN-001, Subject: Borrow Pit Material Sampling (Quality of Sub-grade/Sub-base/Base)

Doc. E-mail: SWM-CCCM-LN-002, Subject: Updated Bending schedules for Box Culverts

1.10 PREVIEW ON FINAL QUANTITIES - IF DEVIATIONS FROM CONTRACT BOQ


• Zero VO

1.11 CONSTRUCTION/QAQC ACTIVITIES (TABLE)

Page 4
ISO 9001:2008 DOC NO: SWM-AMA 1-WR-001

VERSION Rev.
Engineering Design & Construction Supervision of the Palma -
Afungi - Highway 00 00

WEEKLY REPORT
REF NO: SWM-T-QAQC-001
Materials Total Progress Due
Clearing and grubbing 11.823 10.300 1.523
Preparation of road bed 11.823 1.7 10.123
General fill 11.823 0 11.823
Rock-fill 0.4 0 0.4
Geotextile filter 0.4 0 0.4
Sub grade (150mm) 11.823 0 11.823
Sub-base (150mm) 11.823 0 11.823
Base (200) 11.823 0 11.823
Sealing 19mm 11.823 0 11.823
Sealing 9.5mm 11.823 0 11.823
Drainage 11.823 0 11.823
Box Culvert 11.823 0 11.823
Kerb stone 11.823 0 11.823
Grouted Stone pitching 11.823 0 11.823
Signage and marking 11.823 0 11.823

1.12 LABORATORY / NONE DESTRUCTIVE TESTS


Geocontrole laboratory is not in operation due calibration of equipment electricity problem

Only one laboratory technical at site for testing, suggestion of additional no. 1 Lab tech and Lab attendants require.

ACTIVITY DESCRIPTION INSPECTION % REMARKS


COMPLETED

1 Road Bed Sample no.1 at km 0+200 for Awaiting CCCM RFI


PSD/PI/CBR/MDD

2 BP Our ref.: SWM-CCCM-LN-001: Subject Awaiting CCCM RFI, No response


Borrow Pit Material Sampling (Quality of Information from CCCM Quality from CCCM
Sub-grade/Sub-base/Base) Manager informed - Excavator
breakdown

1.13 QUALITY ISSUES AND NON CONFORMANCE


• Zero NCR

NCR No. Issued Date Responsible Nature of NCR Status Remarks

Page 5
ISO 9001:2008 DOC NO: SWM-AMA 1-WR-001

VERSION Rev.
Engineering Design & Construction Supervision of the Palma -
Afungi - Highway 00 00

WEEKLY REPORT
REF NO: SWM-T-QAQC-001

1.14 UPDATED OVERALL TIME SCHEDULE

Appendix 000: Expecting CCCM Schedule on production

1.15 QA/QC OBJECTIVES FOR THE NEXT WEEK


• Reducing percentage re-work

• Correcting all arising non-conformance and closing out.

• Implementation of best practices according to ISO 9001:2008

1.16 OUTLOOK ON UPCOMING WORKS DURING NEXT MONTH

CCCM should submit program of work

1.17 HEALTH, SAFETY, ENVIRONMENT AND SOCIAL

SHE SUMMARY

Daily Toolbox Talks are presented @ 06H35 before start of any activities. All employees on site have attended Site Safety
Induction training both CCCM, Scott Wilson Moz and Geocontrole.

Workshop and equipment inspection checklists are being completed on a daily basis and inspected by CCCM HSE supervisor

HSE have been conducting random drug and alcohol testing on the site as part of the desire to see a proactive approach and
ensure the site is kept alcohol and drug free.

A few safety concerns have been observed/raised and discussed at toolbox. Operators and drivers are being monitored
regarding usage of seat belts and PPEs

1.18 THE KEY STAFF OF SCOTT WILSON MOZAMBIQUE TEAM FOR THE PROJECT

Position Name Status

Page 6
ISO 9001:2008 DOC NO: SWM-AMA 1-WR-001

VERSION Rev.
Engineering Design & Construction Supervision of the Palma -
Afungi - Highway 00 00

WEEKLY REPORT
REF NO: SWM-T-QAQC-001
Resident Engineer Workaferahu Degefu Expecting at Site on 24th May, 2018

Deputy R.E Materials Engineer Lawrence NYARKO At Site on Friday 11th May, 2018

Senior Inspector of Works Leonel Silvino Maculuve At Site on Friday 11th May, 2018

1.19 PROGRESS PHOTO

Laboratory sampling road bed Ch. 0+200 CL Concrete batching plant equipment

Page 7
ISO 9001:2008 DOC NO: SWM-AMA 1-WR-001

VERSION Rev.
Engineering Design & Construction Supervision of the Palma -
Afungi - Highway 00 00

WEEKLY REPORT
REF NO: SWM-T-QAQC-001

Road bed root cleaning CH: 0+300

Road bed root cleaning CH: 0+460 mechanical grader CH: 4+740

Page 8