Sie sind auf Seite 1von 5

Project: Rehabilitation and Up gradation of Repalle to Eeppurpalem Section from Km 129/927 to Km 195/000 of NH-214A (New NH-216) to two lane

with paved shoulder in the State of Andhra Pradesh under NHDP-IV on EPC Basis

Authority : Ministry of Road Transport & Highways


AUTHORITY ENGINEER : M/s WADIA TECHNO-ENGINEERING SERVICES LIMITED
CONTRACTOR : M/s BSCPL Infrastructure Ltd
PQC PAVING REPORT
Location & Chainage__________________________________ Grade of Concrete _____________ Date: ___________________________
Batching Plant Location_________________________________ Sheet No_______________________
RFI No: _____________________________________ Weather : Sunny/ Cloudy / Rainy
Qty (Cum) Time At Slump (mm) MIX Temperature oC Ambient Approximate
S.No Vehicle No Remarks
per Vehicle Cumulative B/P Unloading at B/P at Site at B/P at Site Temperature oC Chainage
Contractor Representative Authority Engineer Representative
Project: Rehabilitation and Up gradation of Repalle to Eeppurpalem Section from Km 129/927 to Km
195/000 of NH-214A (New NH-216) to two lane with paved shoulder in the State of Andhra Pradesh under
NHDP-IV on EPC Basis

Authority : NH Zone R&B (Government of Andhra Pradesh)


AUTHORITY ENGINEER : M/s WADIA TECHNO-ENGINEERING SERVICES LIMITED.
CONTRACTOR : M/s BSCPL Infrastructure Ltd

EVAPORATION RATE of CONCRETE SURFACE MOISTURE


Location & Chainage__________________________________ Starting Time _________________
Batching Plant Location_________________________________ Ending Time__________________
Weather : Sunny/ Cloudy / Rainy Date Of Laying__________________

Ambient
Relative Concrete Mix Wind Velocity Rate Of
S.No Time Temperature Remarks
Humidity (%) Temperature o
C (Km / Hr) Evaporation (%)
o
c

Contractor Representative Authority Engineer Representative


Project: Rehabilitation and Up gradation of Repalle to Eeppurpalem Section from Km 129/927 to Km
195/000 of NH-214A (New NH-216) to two lane with paved shoulder in the State of Andhra Pradesh under
NHDP-IV on EPC Basis

Authority : NH Zone R&B (Government of Andhra Pradesh)


AUTHORITY ENGINEER : M/s WADIA TECHNO-ENGINEERING SERVICES LIMITED
CONTRACTOR : M/s BSCPL Infrastructure Ltd

MEASURMENT OF TEXTURE DEPTH - SAND PATCH METHOD


As per MORTH Clause 602.12

Laboratory No Date of Laying


Testing Stretch Date of Testing
Propoused Use Tested by

(D) Texture Depth


Offset from Required Texture
Diameter of (mm) Depth (mm) as per
S.No Test Location Centerline
the Patch ((31000/ Morth Table 600-5
(m)
(mm) (DXD))

1
Between 24 hours
and 7 Days after the
2
construction of the
slab 0.75 to 1.25
3

4
Not later than 6
5 Weeks before the
road is opened to
traffic 0.65 To 1.25
Average Texture Depth (mm)

Remarks :

Contractor Representative Authority Engineer Representative


Project: Rehabilitation and Up gradation of Repalle to Eeppurpalem Section from Km 129/927 to Km 195/000 of NH-214A
(New NH-216) to two lane with paved shoulder in the State of Andhra Pradesh under NHDP-IV on EPC Basis

Authority : Ministry of Road Transport & Highways


AUTHORITY ENGINEER : M/s WADIA TECHNO-ENGINEERING SERVICES LIMITED
CONTRACTOR : M/s BSCPL Infrastructure Ltd

PQC Daily Report


Chainage Quantity Authority
S.No Date Length EPC Contractor's Engineer's Remarks
From To Day Cumulative Signature
Quantity Quantity Signature

Das könnte Ihnen auch gefallen