Date 7-Apr-11
Company Boubyan Seaport Project Phase 1
3)Preparation
(1)GPS installation & Survey
- GPS(RTK Type)
- Total station
4)Method
(1) Checking DCM barge condition
①Maintenance of DCM barge.
②Checking condition of drilling equipment(Auger, Rod, Bit and etc ).
③Checking Working platform & Working Section on board.
(5) Atter penetrated under water, drilling would to be carrird out by water.Design data of injection
volumes input on flowmeter then agitate cement paste for 2~3minutes.
①Using removal pump, slully is injected as average 130ℓ/min per pump 1GB
②There is dropped as average 2.0m/min, then rising 2.0m/min for soil improvement.
Method Statement of D. C. M
Sample for unconfined compressive strength test takes at workinr point using Sampling device.
After sampling device fixed on mixing blade, agitator is penetrated then pull out and sampling
device takes off from agitator.
②Specimen fabrication - After removed foreign substances from sample, it puts the sample into
specimen(Φ50*100mm) as devided 3 times(1/3) then to be Underwater Curing after h
harden the sample many times.
(3)Equipment Setting
DCM Barge is located on position using G.P.S system. Operating is conducted by computer system
in wheel room using winch lever with watching computer monitor. After completed setting on po-
sition. After competed setting on position, winch is fixed.
Method Statement of D. C. M
Slurry is gradually injected as speed of 1~4m/min when agitation rod reach on hoe bottom after
drilling. Rod will be dropped with agitation since auger relay gauge is more than 300A.
Plant operator check cement mixing ratio(W/C is based on specification) and mixing codition of
Agitator, pumping, flowmeter and condition of slurry injection on DCM barge.
Method Statement of D. C. M
Operator check bottom and inject slurry on bottom for 2~3 minuts. As speed of 1~4m/min, rod is pul-
ing, at the same time cement past is to be injected and agitated.
Plant operator check slurry injection, agitation, pump pressure on pulling, flowmeter recorder.
Before 30cm of reaching at designed bottom,re-penetration start at bottom in accordance with repea-
ted process
(6)Cleaning
After worked, agitator, hose and inside of rod are cleaned.
After complete the deep mixing disposal, A operater sets rod end at a depth of 50cm~1m from the
ground and clean using pump.
Slurry pipes and Slurry in the inside of rod are disposaled on the ground.
Method Statement of D. C. M
(7)Slime
①slime dredge : After complete construction, use a back+bargeor a grab barge.
(dredge after survey water depth)
(8)Comfirmation Boring
Collect improvemented sample by DCM at the completed part by using investigation equipments.
Set on the position appointed by construction supervision by using the barge or SEP barge that is
equipment for investigating the sea and check that construction conditions and improvemented sampl-
e's homogeneity by collecting homogeneity and N of improvemented sample by testing S.P.T every 3
meter during collecting improvemented sample to judge the strength of improvemented sample.
(implement the S.P.T test because the lengthof boring rod become 3 meters.)
Method Statement of D. C. M
7. Equipment
20ton 3
Winch 15ton 5 for setting DCM barge
5ton 5
· When there is an oil spill, oil should be collected by using an absorbent or an oil reclaimer
, but the case which inject chemicals can take place according to the situations.
The main case is that an oil film spread thinly since it is a long time from the spill or
an oil film is formed thinly since an efflux is few from the beginning and collecting oil
physically is very ineffective in that case.
In that case, after disperse oil into water with chemicals, dispersing agent is the most used
to remove naturally by purifying effects.
As it atomize oil, if oil and seawater mix, oil can be removed more effective than collecting
oil physically since microbial decomposition, evaporation and oxidation with sunshine take
place actively.
Method Statement of D. C. M