PROGRESS REPORT

Up to 31st March 2019

Project Description:

Construction of a Building to Provide Accommodation Facilities For


Public Officers (Phase I) At Monaragala District

Submitted to:
Deputy Chief Secretary (Engineering Services)
Office of Deputy Chief Secretary
(Engineering Services)
Pingarawa,
Badulla.

Prepared by:

Central Engineering Services (Private) Limited


No. 37/2A, Bandaranayke Mawatha,
Badulla.
Progress Report – March 2019 Central Engineering Services (Private) Limited

Construction of A Building to Provide Accommodation Facilities for Public Officers (Phase I) At Monaragala District

Table of Contents
1.0 INTRODUCTION2

1.1 Project details……………………………………………………………………………………….….…………02

2.0 P R O J E C T R E V I S E D P R O G R A M M E ……………………………………………………….…….……..03

3.0 FINANCIAL PROGRESS…………………………………………………………………………………………..03


3.1 Cash in (Expected & Actual with graph)……………………………………………………………….….............05

4.0 PHYSICAL PROGRESS……………………………………………………………………………..……….……07

5.0 NEXT MONTH TASK ……………………………………………………………..………………………………09

6.0 REASON FOR DELAYS …………………………………………………………………………..………………09

7.0 MITIGATION MEASUERS ……………………………………………………….……………………………....09

8.0 PROBLEMS AND DIFFICULTIES … …………………………………………....………………………………09

9.0 PROGRESS PHOTOS………………………………………………………………………………………..…….10

1|P age
Progress Report – March 2019 Central Engineering Services (Private) Limited

Construction of A Building to Provide Accommodation Facilities for Public Officers (Phase I) At Monaragala District

1.0 INTRODUCTION

1.1 Project details

Client- Ministry of public Administration and Management


Independence Square,
Colombo 07.

Contractor Central Engineering Services (Pvt.) Ltd.


37/2A,
Bandaranayke Mawatha,
Badulla.

Agreement Date 20th of July 2017 – 18th January 2019

Contract Amount 179,521,259.13 (Without Vat), 206,449,448.00 (With Vat)

Engineer’s Name Deputy Chief Secretary (Engineering Services)


Office of Deputy Chief Secretary
(Engineering Services)
Pingarawa,
Badulla.

Engineer’s representative Director (Buildings)


Uva provincial building Department
Pingarawa,
Badulla.

Time for Completion of work Time for Completion is 547 days from the Commencement

2|P age
Progress Report – March 2019 Central Engineering Services (Private) Limited

Construction of A Building to Provide Accommodation Facilities for Public Officers (Phase I) At Monaragala District

2.0 PROJEC T REV ISED PROGRAM M E


Revised program is attached in appendix.
The program is revised base on the delays occur due to issue in position to the site and also
approval was not granted to demolish the old resident building and delay due to removal of trees.

3.0 FINANCIAL PROGRESS

Financial progress is prepared base on revised program.

Month Actual Cumulative Work Done Revised Cumulative Work Done

Aug-17 2,508,603.57 2,508,603.57


Sep-17 3,307,503.67 3,307,503.67
Oct-17 6,484,865.04 6,484,865.04
Nov-17 9,563,843.80 9,563,843.80
Dec-17 12,198,553.06 12,198,553.06
Jan-18 14,833,262.32 14,833,262.32
Feb-18 18,669,428.57 18,669,428.57
Mar-18 23,938,339.12 23,938,339.12
Apr-18 24,886,956.57 24,886,956.57
May-18 30,641,323.98 30,641,323.98
Jun-18 33,776,598.83 35,500,075.29
Jul-18 43,316,247.84 41,538,801.61
Aug-18 48,547,414.41 47,921,752.93
58,253,708.21 (With material at
Sep-18 58,377,519.24
site 2,143,208.00)
65,401,626.03 (With material at
Oct-18 70,556,979.56
site 3,227,306.45)
75,561,409.31 (With material at
Nov-18 87,685,429.87
site 8,143,247.62)
81,911,107.88 (With material at
Dec-18 108,646,978.19
site 11,086,841.88)
87,227,315.40 (With material at
Jan-19 138,394,803.50
site 7,343,247.62)
90,947,568.18 (With material at site
Feb-19 8,343,247.62) 164,618,067.82

95,210,742.46 (With material at site


Mar-19 179,521,259.13
7,043,247.62) ( 63% )

3|P age
Progress Report – March 2019 Central Engineering Services (Private) Limited

Construction of A Building to Provide Accommodation Facilities for Public Officers (Phase I) At Monaragala District

FINANCIAL PROGRESS CHART

CASHFLOW
Actual Cumulative Work Done Revised Cumulative Work Done

200,000,000.00

180,000,000.00

160,000,000.00

140,000,000.00

120,000,000.00
AMOUNT

100,000,000.00

80,000,000.00

60,000,000.00

40,000,000.00

20,000,000.00

0.00

MONTH

4|P age
Progress Report – March 2019 Central Engineering Services (Private) Limited

Construction of A Building to Provide Accommodation Facilities for Public Officers (Phase I) At Monaragala District

3.1 CASH IN FLOW


Month Actual Cumulative Cash In (With VAT)
17-Aug 17,952,125.91
17-Sep 17,952,125.91
17-Oct 17,952,125.91
17-Nov 17,952,125.91
17-Dec 35,904,251.82
18-Jan 39,840,405.07
18-Feb 39,840,405.07
18-Mar 47,888,706.54
18-Apr 51,410,098.10
18-May 53,948,867.32
18-Jun 59,422,264.36
18-Jul 63,354,378.13
18-Aug 70,995,037.00
18-Sep 75,509,188.24
18-Oct 80,499,078.33
18-Nov 83,181,543.52
18-Dec 83,181,543.52
19-Jan 97,711,431.11
19-Feb 98,616,722.58
19-Mar 101,716,722.58

ACTUAL CUMULATIVE CASH IN


120,000,000.00

100,000,000.00

80,000,000.00
AMOUNT

60,000,000.00

40,000,000.00

20,000,000.00

0.00

MONTH

5|P age
Progress Report – March 2019 Central Engineering Services (Private) Limited

Construction of A Building to Provide Accommodation Facilities for Public Officers (Phase I) At Monaragala District

Bill Billed Date Amount (With Amount Received No of Days for


No Vat) Received Date Amount (With bill Received
Vat)
1 11.09.2017 3,936,178.25 12.01.2018 3,936,153.25 123 Days

2 16.10.2017 8,048,326.46 05.03.2018 8,048,301.46 140 Days

3 13.12.2017 3,521,416.59 12.03.2018 3,521,391.56 89 Days

4 15.02.2018 2,538,794.22 14.05.2018 2,538,769.22 88 Days

5 29.03.2018 5,473,422.04 19.06.2018 5,473,397.04 82 Days

6 09.05.2018 3,932,113.77 12.07.2018 3,932,113.76 64 Days

7 05.07.2018 9,020,642.05 30.08.2018 7,640,658.87 56 Days

8 05.08.2018 4,514,151.24 11.10.2018 4,514,151.24 67 Days

9 27.08.2018 4,989,890.09 29.10.2018 4,989,890.09 62 Days

10 25.09.2018 2,682,465.19 05.12.2018 2,682,465.19 70 Days

11 25.11.2018 7,690,306.50 07.02.2019 7,690,306.50 74 Days

12 10.12.2018 6,839,581.09 11.02.2019 6,839,581.09 63 Days

13 07.01.2019 905,291.46 26.03.2019 905,291.46 78 Days

14 08.03.2019 6,839,976.57 26.03.2019 3.1mn On account

15 03.04.2019 4,130,903.04 - SNR

Note: - SNR – Still Not Received

6|P age
Progress Report – March 2019 Central Engineering Services (Private) Limited

Construction of A Building to Provide Accommodation Facilities for Public Officers (Phase I) At Monaragala District

4.0 PHYSICAL PROGRESS


As per Revised balance work programme

Total Construction Schedule % Complete %


100 % 60.66 %

BLOCK 01 100 % 67.36 %


Ground floor 100 % 100.00 %
First floor 100 % 80.35 %
Second Floor 100 % 68.19 %
Third Floor 100 % 65.19 %
Fourth Floor 100 % 40.91 %
Roof 100 % 57.13 %

BLOCK 02 100 % 63.33 %


Ground floor 100 % 100 %
First floor 100 % 75.16 %
Second Floor 100 % 64.82 %
Third Floor 100 % 83.11 %
Fourth Floor 100 % 33.92 %
Roof 100 % 57.13 %
BLOCK 03 100 % 47.94 %
Ground floor 100 % 97.52 %
First floor 100 % 59.88 %
Second Floor 100 % 53.53 %
Third Floor 100 % 47.52 %
Fourth Floor 100 % 18.04 %

BLOCK 04 100 % 44.51 %


Ground floor 100 % 100 %
First floor 100 % 53.14 %
Second Floor 100 % 32.59 %
Third Floor 100 % 13.44 %
Fourth Floor 100 % -

7|P age
Progress Report – March 2019 Central Engineering Services (Private) Limited

Construction of A Building to Provide Accommodation Facilities for Public Officers (Phase I) At Monaragala District

BLOCK DRAWINGS

BLOCK - 02

FOOTING H

FOOTING G

FOOTING F

FOOTING E
BLOCK - 03 BLOCK - 01

FOOTING I FOOTING D

FOOTING J FOOTING C

FOOTING K FOOTING B

FOOTING L FOOTING A

BLOCK - 04

8|P age
Progress Report – March 2019 Central Engineering Services (Private) Limited

Construction of A Building to Provide Accommodation Facilities for Public Officers (Phase I) At Monaragala District

5.0 NEXT MONTH TASK


01. Block 03 Finishing works.
02. Block 03 Third & Fourth floor Block works & Plastering works, Painting works. Water Proofing.
03. Block 03 Tile works & Bathroom finishes.
04. Block 02 & 03 Roof works.
05. Block 03 Roof beam concrete.
06. Block 04 Third floor slab & beams concrete.
07. Block 04 fourth floor columns concrete.
08. Second & First floor Stair Case works.
09. Block 03,02 Painting works.

6.0 REASON FOR DELAYS


1. Unexpected weather condition.
2. Payment Delays.
3. Drawing & Details Delays.

7.0 MITIGATION MEASURES


1. Program were revised and speed up the Progress
2. Improve the form work method & drawing, method statement was submitted to the Consultant.
3. The Block casting was started nearby premises. Samples are tested & Now block works are started.

8.0 PROBLEMS AND DIFFICULTIES

1. Site clearing and top soil removing items are not in BOQ and therefor work done which we did already,
cannot be claimed. (SSR was submitted on 11.09.2017 for approval.)
2. Soil Excavation & Disposal Rate is not approved (SSR was submitted for approval) on 19.07.2018.
3. Payment delays.
4. Unexpected Weather condition.
5. Quantity Exceeding problems, Some Variation orders are not approved yet.

9|P age
Progress Report – March 2019 Central Engineering Services (Private) Limited

Construction of A Building to Provide Accommodation Facilities for Public Officers (Phase I) At Monaragala District

9.0 PROGRESS PHOTOS

10 | P a g e
Progress Report – March 2019 Central Engineering Services (Private) Limited

Construction of A Building to Provide Accommodation Facilities for Public Officers (Phase I) At Monaragala District

11 | P a g e
Progress Report – March 2019 Central Engineering Services (Private) Limited

Construction of A Building to Provide Accommodation Facilities for Public Officers (Phase I) At Monaragala District

12 | P a g e
Progress Report – March 2019 Central Engineering Services (Private) Limited

Construction of A Building to Provide Accommodation Facilities for Public Officers (Phase I) At Monaragala District

13 | P a g e
Progress Report – March 2019 Central Engineering Services (Private) Limited

Construction of A Building to Provide Accommodation Facilities for Public Officers (Phase I) At Monaragala District

14 | P a g e