T2 T3 T4 T1 T2 T3 T4 T1 T2 T3 T4 T1 T2 T3 T4
1 KSB PUMPS 82 sem. 16 sep '19 11 abr '21
2 Signature of the Contract 0 días 16 sep '19 16 sep '19 Signature of the Contract
3 Project Start Arrangements 3 sem. 16 sep '19 6 oct '19 2 Project Start Arrangements
5 Selecting Pattern Manufacturer Purchsing small components 4 sem. 7 oct '19 3 nov '19 3 Selecting Pattern Manufacturer Purchsing small components
7 Casting Casing and Hydraulic Pump 1 12 sem. 13 ene '20 5 abr '20 6 Casting Casing and Hydraulic Pump 1
10 Internal Tests (1 Hydraulic KSB, 1 Site Motor) 5 sem. 8 jun '20 12 jul '20 9 Internal Tests (1 Hydraulic KSB, 1 Site Motor)
11 1 week disassembling & to prepare for coating 1 sem 13 jul '20 19 jul '20 10 1 week disassembling & to prepare for coating
12 1 -2 week coating and packing Casing ready for delivery after 46 2 sem. 20 jul '20 2 ago '20 11 1 -2 week coating and packing Casing ready for delivery after 46 weeks
weeks
13 Readiness for delivery Incoterm EXW of Suction Elbow 1-6 & 0 sem. 2 ago '20 2 ago '20 12 Readiness for delivery Incoterm EXW of Suction Elbow 1-6 & Understructure of M
Understructure of Motor-& pump Support 1-6
15 Start Pump 2-6 0 días 12 jul '20 12 jul '20 10 Start Pump 2-6
16 Casting Casing and Hydraulic Pump 2 to 6 14 sem. 13 jul '20 18 oct '20 15 Casting Casing and Hydraulic Pump 2 to 6
19 Interne Tests (1Gehäuse, 1 Motor, 5 Hydrauliken 4 sem. 25 ene '21 21 feb '21 18 Interne Tests (1Gehäuse, 1 Motor, 5 Hydrauliken
20 External Tests (6 Hydraulic KSB, 5 Motor M-Manufacturer) 3 sem. 22 feb '21 14 mar '21 19 External Tests (6 Hydraulic KSB, 5 Motor M-Manufacturer)
23 Readiness for delivery Incoterm EXW of 6 Spool Pieces, Cardan 0 sem. 11 abr '21 11 abr '21 22 Readiness for delivery Incoterm EXW of 6 Spool Pieces, Card
Shaft, 6 Motor Stool