Id Nombre de tarea Duración Comienzo Fin Predecesoras 2020 2021 2022

T2 T3 T4 T1 T2 T3 T4 T1 T2 T3 T4 T1 T2 T3 T4
1 KSB PUMPS 82 sem. 16 sep '19 11 abr '21
2 Signature of the Contract 0 días 16 sep '19 16 sep '19 Signature of the Contract

3 Project Start Arrangements 3 sem. 16 sep '19 6 oct '19 2 Project Start Arrangements

4 Manufacturing Pump 1 43 sem. 7 oct '19 2 ago '20

5 Selecting Pattern Manufacturer Purchsing small components 4 sem. 7 oct '19 3 nov '19 3 Selecting Pattern Manufacturer Purchsing small components

6 Manufacturing Pattern 10 sem. 4 nov '19 12 ene '20 5 Manufacturing Pattern

7 Casting Casing and Hydraulic Pump 1 12 sem. 13 ene '20 5 abr '20 6 Casting Casing and Hydraulic Pump 1

8 Machining 6 sem. 6 abr '20 17 may '20 7 Machining

9 Assembling 3 sem. 18 may '20 7 jun '20 8 Assembling

10 Internal Tests (1 Hydraulic KSB, 1 Site Motor) 5 sem. 8 jun '20 12 jul '20 9 Internal Tests (1 Hydraulic KSB, 1 Site Motor)

11 1 week disassembling & to prepare for coating 1 sem 13 jul '20 19 jul '20 10 1 week disassembling & to prepare for coating

12 1 -2 week coating and packing Casing ready for delivery after 46 2 sem. 20 jul '20 2 ago '20 11 1 -2 week coating and packing Casing ready for delivery after 46 weeks
weeks

13 Readiness for delivery Incoterm EXW of Suction Elbow 1-6 & 0 sem. 2 ago '20 2 ago '20 12 Readiness for delivery Incoterm EXW of Suction Elbow 1-6 & Understructure of M
Understructure of Motor-& pump Support 1-6

14 Manufacturing Pump 2-6 39 sem. 12 jul '20 11 abr '21

15 Start Pump 2-6 0 días 12 jul '20 12 jul '20 10 Start Pump 2-6

16 Casting Casing and Hydraulic Pump 2 to 6 14 sem. 13 jul '20 18 oct '20 15 Casting Casing and Hydraulic Pump 2 to 6

17 Machining 10 sem. 19 oct '20 27 dic '20 16 Machining

18 Assembling 4 sem. 28 dic '20 24 ene '21 17 Assembling

19 Interne Tests (1Gehäuse, 1 Motor, 5 Hydrauliken 4 sem. 25 ene '21 21 feb '21 18 Interne Tests (1Gehäuse, 1 Motor, 5 Hydrauliken

20 External Tests (6 Hydraulic KSB, 5 Motor M-Manufacturer) 3 sem. 22 feb '21 14 mar '21 19 External Tests (6 Hydraulic KSB, 5 Motor M-Manufacturer)

21 Coating 2 sem. 15 mar '21 28 mar '21 20 Coating

22 Packing 2 sem. 29 mar '21 11 abr '21 21 Packing

23 Readiness for delivery Incoterm EXW of 6 Spool Pieces, Cardan 0 sem. 11 abr '21 11 abr '21 22 Readiness for delivery Incoterm EXW of 6 Spool Pieces, Card
Shaft, 6 Motor Stool