Beruflich Dokumente
Kultur Dokumente
Student ID : z5224608
1
Table of contents
1. INTRODUCTION………………………………………………….…………… 4
2. SITE LOCATION………………………………………………………………… 5
OBSERVATION……………………………………..………………………….. 6
7. PRINCIPAL OF SITE………………………………………………………....... 8
8. LICENSE REQUIREMENTS……………………………………….……...……. 8
8.8 INSURANCES……………………………………………………………… 9
2
9. AUSTRALIAN STANDARDS………………………………………............... 10
13. CONCLUSION………………………………………………………………….. 12
14. REFERENCES………………………………………………………………….. 14
15. APPENDIX……………………………………………………………………… 16
3
1. Introduction
Construction activities and planning is a vital and challenging endeavor in the administration
and execution of building projects. It includes the choice of technology, the definition of
work tasks, the estimation of the required resources and intervals for individual tasks, and the
identification of any interactions among the various scheduled work tasks. As the
construction industry is turning more and more into a tremendously technical and pioneering
undertaking with a keen detail to quality and specification, therefore essential aspects of it
now heavily relies upon heavy-duty vehicles and complex machinery. The general objective
of every construction-related activity is the assembly and erection of a structure or various
structural parts, within a given time period, so that it can grant the required performances
with enhanced productivity and the most sensible cost-effectiveness, along with the
environmental impact assessment guidelines as per the Australian standards.
The following document outlines the details of a development activity being observed over a
period of one month at a high-density housing site. The site in development is going to be a
residential building of Ground + 12 floors with three level of parking. It is estimated that the
construction of the building would be completed in the next three years. Presently, there are
two activities which are being conducted simultaneously on the site, i.e., Excavation and
Piling. Precisely, this report talks about the piling operation which was being carried out
during the observation period.
The selection for the operation of pile foundation depends on different operations and
consideration, such as ground conditions, proximity to other structures, accessibility,
sensitivity to noise and vibration, cost, and, the durability of the materials. Piles can be
classified depending upon their functional design, replacement or their method of
construction. They are formed by slender, columnar and long elements made from steel or
reinforced concrete. As the site location, 280 Coward Street in Mascot, Sydney, NSW is in
proximity to urban buildings, so non-displacement piles (NDP) or bored piles are used for the
foundation as there is the least vibration and, the risk of heave is minimalistic, as well.
The design and installation of piles are done according to the guidelines in AS 2159-2009 in
Australia, which is specified in this report including the machines deployed for the piling
operation as well as the environmental practices on the site.
4
2. Site Location
The observed site recognized as 280 Coward street, Mascot is located on the southwestern
corner of the Bourke street and Coward street intersection which would be bounded with a
suggested extension of John street. The site is bounded by Kent Road, Bourke Street,
Gardeners Road, and Coward Street. It is located approximately 3 km from Sydney
International Airport Terminal and 1 km from Sydney Domestic Airport Terminal. The
developed site is emerging into a luxurious residential infrastructure which is transforming
the precinct from an industrial repository. The developed area is in close proximity to Mascot
station and major road networks which facilitates excellent employment opportunities and
accessibility.
5
4. Date and Time of Observation
The activities at the site were observed for a time period of one month from 10th June 2019 to
9th July 2019. The activity is expected to take two more months for its completion. The exact
date and the corresponding time for the site observation have been listed below in the table: -
Date Time
10/06/2019 2 PM – 3 PM
17/06/2019 10.30 AM – 12 PM
24/062019 1 PM – 2 PM; 7 PM – 8 PM
09/07/2019 10 AM – 1 PM
6
executed by only a specialist contractor or sub-contractor with prior experience and
knowledge, and with the ability to assess the future implications of damage to structures due
to environmental change.
7
6. Contractor and Sub-Contractor handling the operation
The contractor for the observed site is CF Group Pty Ltd. This Australian company
specializes in Geotechnical Engineering techniques such as bored piles, retaining structures,
pile testing in addition to other activities like anchoring and Under-pinning.
The sub-contractors for anchoring activity at the site are Rix Group, while the de-watering
and excavation are overlooked by Coates hire, which is a subsidiary of Seven Group
Holdings and Earthworxrespectively. The concrete contractor for the site is Beton Group.
7. Principal of Site
Meriton is the principal of the site in development. It is Australia’s largest luxurious
apartment developer. They also undertake the development of luxurious apartments in
Sydney, Queensland, and Gold Coast. Meriton has their apartments located all over in
Sydney such as in Bondi, Chatswood, North Ryde, Zetland, and Paramatta to name a few.
8. License Requirements
As per my observation, all the activities at the site are carried out in compliance with the
regulatory and safety guidelines set by Workplace health and safety (WHS). So that the
health and safety of the employees working at the site can be protected from the risks and
potential hazards in the workplace.
8
8.3 Heavy Vehicle License: -
At the observed site, the Heavy Vehicle License is a necessity to operate loaders, excavators,
pile driving equipment, and dump trucks. This license is issued only after completing Heavy
Vehicle Competency Based Assessment (HVCBA) from a registered organization.
8.8 Insurances: -
It provides coverage for damage to structures due to improper construction or during
renovation, and damage to temporary work. It also provides coverage to employees and
workers who might get injured while working at the site.
9
9. Australian Standards
9.1 AS 1726: 2017 – Site Investigation
This provides information about the geotechnical design of piles, groundwater conditions,
and negative friction effects. It also provides data on the type of soil and problems related to
it, and characteristics of rocks which is helpful in selecting proper machinery for excavation
and piling processes.
It also assesses any potential of contaminated sites, acid sulfate soils, and weak or
compressible layers below the base of the pile. It further discusses the difficulties faced
during the construction of the pile cap and obstructions in installment due to boulders or
rocks. It gives an overview of rock and soil classification which is helpful in execution and
assessment of various activities at the site. (Australian Standard 2017)
11
11. Environmental Requirements
The site near the mascot station is a prime area with a dense population of residentials and
corporate employees so a traffic controller was always present near the intersection of
pedestrian footpaths and entrance to the site to facilitate smooth transportation of construction
materials and large equipment without jeopardizing the public safety.
The excavated soil was sprinkled with water to avoid the dust from rising and causing any
problems to pedestrians and residents in the adjacent buildings. Special efforts were made by
the site management to minimize the noise pollution while operating the piling and drilling
rig and no construction was carried out at night. The soil was diverted to dumping grounds by
trucks to avoid waste pollution.
• Boots
• Gloves
• High Visibility Clothing
• Helmets
• Goggles
• Hearing protective devices, such as earmuffs and earplugs (Safework NSW 2018)
13. Conclusion
From my various observation, it is safe to say that a site manager was always present at the
site to supervise the activities and to make sure each activity is in accordance with the
guidelines of Australian Standards regarding the construction, installation of piles, and testing
of concrete.
This document highlight the piling operation carried out for the construction of a multi-
storeyed residential building. The site was observed for four days with a total of seven hours.
As far as the site productivity is concerned during my first day of observation, casing was
inserted and the drilling of the ground surface for installation of a pile was being carried out
with an LRB 355 rig. During my second and third observations concrete was being poured
and the casing was removed. For my final day of observation, it was observed that
approximately seven piles were already installed into the surface.
Meriton is the principal of the site and CF Group Pty Ltd is the contractor for piling
operation. From my observation, I had the chance to witness how much they emphasize on
safeties in the site. Every worker is demanded to have proper safety equipment along with
appropriate licenses. Even the visitors have to wear a safety helmet to ensure their safety.
Furthermore, appropriate safety signboards were seen to remind employees about their own
safety.
12
The installation of piles is an important task at the site and bored piles are used as the soil
type is sandy and it provides a great load-bearing capacity. As the site is located in a prime
area, the use of bored piles allows the work to progress rapidly and neatly, without disturbing
adjacent structures.
This report also discusses different Australian standards regarding the construction site. The
major standards are the AS 1726: 2017 – Geotechnical Site Investigations, AS 2159: 2009 –
Piling design and installation, AS 1470: 1986 – Health and Safety at work, HB 203: 2012 –
Management of environmental risks, and AS 3600: 2009 – Concrete Structures.
The site observation has really helped me visualize better in whereabouts of piles,
foundations, in-situ concrete, and excavation which are outlined in this report along with
license and environmental requirements.
13
14. References
1. SafeWork NSW 2018, 'White Cards (CIC)', accessed 15 June 2019,
http://www.safework.nsw.gov.au/licences-and-registrations/licences/white-cards-cic
2. SafeWork NSW 2018, 'High-Risk Work Licenses', accessed 15 June
2019,http://www.safework.nsw.gov.au/licences-and-registrations/licences/high-risk-
work-licences
3. Standards Australia 2012, 'Managing environment-related risk', accessed 21 June
2019,www.saiglobal.com
4. Australian Standard 1986, 'Health and Safety at Work - Principles and Practices',
accessed 21 June 2019, www.saiglobal.com
5. Nik Norulaini Nik Ab Rahman, NorizanEsa 2014, ‘Managing Construction
Development Risks to the Environment’, accessed 21 June 2019,
https://link.springer.com/chapter/10.1007/978-4-431-54804-1_16
6. Infostore saiglobal.com 2018, AS 3600-2009 ‘Concrete Structures’, SAI Global, e-
book, accessed 27 June 2019, https://infostore.saiglobal.com/en-us/standards/AS-
3600-2009-1382662/
7. Infostore saiglaobal.com 2018, AS 1726-2017 ‘Geotechnical Site Investigation’, SAI
Global e-book accessed 27 June 2019, https://infostore.saiglobal.com/en-
us/standards/AS-1726-2017-1382662/
8. Toll, D.G. and Abedin, Z. and Buma, J. and Cui, Y. and Osman, A. S. and Phoon,
K.K. (2012) 'The impact of changes in the water table and soil moisture on structural
stability of buildings and foundation systems: systematic review CEE10-005 (SR90),
accessed 29 June 2019, http://dro.dur.ac.uk/18298/
9. A.Zh. Zhussupbekov, J. Frankovská, J. Stacho, Abdullah I. Al-Mhaidib, M.
Doubrovsky, N. Uranhayev, S. Yerzhanovvi, and I. Morev 2016, ‘Geotechnical and
construction considerations of pile foundations in problematical soils’, accessed 29
June 2019,
https://www.researchgate.net/publication/292337405_Geotechnical_and_construction
_considerations_of_pile_foundations_in_problematical_soils
10. Ir. Dr. Gue See Sew 2007, ‘Piled Foundation Design and Construction’, accessed 1
July 2019, https://www.pdfdrive.com/piled-foundation-design-and-construction-
e17133516.html
11. Ken Fleming, Austin Weltman, Mark Randolph, Keith Elson 2008, ‘Piling
Engineering’, accessed 1 July 2019,
https://www.taylorfrancis.com/books/9780429181177
12. William F. Van Impe& Peter Van Impe 2008, ‘Deep Foundations on Bored and
Auger Piles’, accessed 1 July 2019, https://www.pdfdrive.com/deep-foundations-on-
bored-and-auger-piles-bap-v-proceedings-of-the-5th-international-symposium-on-
deep-foundations-on-bored-and-auger-piles-bap-v-8-10-september-2008-ghent-
belgium-e161941606.html
13. Z. Sirozhiddinov 1992, ‘Bearing capacity of driven piles in sandy soils according to
resistance characteristics and their variability’, accessed 3 July 2019,
https://link.springer.com/article/10.1007/BF02094708
14
14. Australian Standard 2009, ‘Piling- Design and Installation’, accessed 5 July 2019,
https://www.scribd.com/document/334696131/AS2159-Piling-Design-and-
Installation
15. https://setxind.com/civil/understanding-role-piling-civil-construction/, accessed 5 July
2019
16. https://medium.com/@groundengineeringltd/function-and-importance-of-the-pile-
foundation-d3f1212db4a6, accessed 6 July 2019
17. https://www.service.nsw.gov.au/services/business-industries-and-employment/motor-
vehicle-and-road-transport-industry/heavy, accessed 8 July 2019
18. http://www.piledrivers.org/benefits-of-driven-piles.htm, accessed 8 July 2019
19. https://www.liebherr.com/en/aus/products/construction-machines/deep-
foundation/piling-and-drilling-rigs/details/lrb355.html, accessed 9 July 2019
20. SafeWork Australia 2018, ‘Personal protective equipment (PPE)’, accessed 9 July
2019, https://www.safeworkaustralia.gov.au/ppe
21. Infostore saiglaobal.com 2018, AS 1012.9 – 2014 ‘Methods of testing concrete
Compressive strength tests - Concrete, mortar and grout specimens’, SAI Global e-
book accessed 10 July 2019, https://infostore.saiglobal.com/en-au/Standards/AS-
1012-9-2014-111734_SAIG_AS_AS_233709/
22. Infostore saiglaobal.com 2018, AS 1012.10 – 2000 (R2014)‘Methods of testing
concrete Determination of indirect tensile strength of concrete cylinders ('Brasil' or
splitting test)’, SAI Global e-book accessed 10 July 2019,
https://infostore.saiglobal.com/en-au/Standards/AS-1012-10-2000-R2014--
129179_SAIG_AS_AS_273253/
23. Infostore saiglaobal.com 2018, AS 1012.11 – 2000 (R2014), ‘Methods of testing
concrete Determination of the modulus of rupture’, SAI Global e-book accessed 10
July 2019, https://infostore.saiglobal.com/en-au/Standards/AS-1012-11-2000-R2014--
129178_SAIG_AS_AS_273250/
15
15. Appendix
16
Figure-3 – Kobelco SK350LC-10 excavator
17