Beruflich Dokumente
Kultur Dokumente
Request for
Interim
Payment A B C D E F G H
SL No. Invoice Net Certified Payment Contract Time for Actual Date of Payment Finance Monthly Finance Monthly Finance Cost
Submition Payment (Cl. 60.10 and Payment Delays (%) Cost (Compound Interest;
Date item 9 of CA) (Simple Interest) Daily)
TOTAL TOTAL
SAR 430,906.95 SAR 436,168.27
Advanc 20-Mar-2014 SAR 13,301,580.00 3 April 2014 31 August 2014 150 6.750 SAR 368,982.18 SAR 374,112.50
1 3-Jun-2014 SAR 2,679,178.53 3 July 2014 21 July 2014 18 6.750 SAR 8,918.36 SAR 8,932.39
2 4-Aug-2014 SAR 804,885.55 3 September 2014 16 September 2014 13 6.750 SAR 1,935.03 SAR 1,937.18
3 14-Aug-2014 SAR 2,778,419.40 13 September 2014 16 September 2014 3 6.750 SAR 1,541.45 SAR 1,541.74
4 18-Sep-2014 SAR 1,886,381.18 18 October 2014 28 October 2014 10 6.750 SAR 3,488.51 SAR 3,491.42
5 15-Oct-2014 SAR 1,930,547.31 14 November 2014 24 November 2014 10 6.750 SAR 3,570.19 SAR 3,573.16
6 19-Nov-2014 SAR 1,879,256.53 19 December 2014 14 December 2014 0 6.750 SAR - SAR -
7 8-Dec-2014 SAR 6,634,094.42 7 January 2015 5 January 2015 0 6.750 SAR - SAR -
8 28-Dec-2014 SAR 3,535,754.56 27 January 2015 22 January 2015 0 6.750 SAR - SAR -
9 1-Feb-2015 SAR 3,734,158.92 3 March 2015 2 March 2015 0 6.750 SAR - SAR -
10 11-Mar-2015 SAR 6,027,898.26 10 April 2015 20 April 2015 10 6.750 SAR 11,147.48 SAR 11,156.76
11 5-Apr-2015 SAR 3,628,606.19 5 May 2015 4 May 2015 0 6.750 SAR - SAR -
12 29-Apr-2015 SAR 2,501,894.16 29 May 2015 8 June 2015 10 6.750 SAR 4,626.79 SAR 4,630.64
13 27-May-2015 SAR 2,538,874.17 26 June 2015 17 July 2015 21 6.750 SAR 9,859.87 SAR 9,878.13
14 27-Jun-2015 SAR 2,144,109.80 27 July 2015 18 August 2015 22 6.750 SAR 8,723.30 SAR 8,740.26
VO 1 29-Apr-2015 SAR 541,660.29 29 May 2015 18 August 2015 81 6.750 SAR 8,113.77 SAR 8,174.09
28 June 2015
VO 2 29-May-2015 SAR 19,259.65 18 August 2015 51 6.750 SAR 181.65 SAR 182.49
25 August 2015
15 26-Jul-2015 SAR 1,608,081.81 18 August 2015 0 6.750 SAR - SAR -
16 30-Aug-2015 SAR 1,493,723.79 29 September 2015 2 November 2015 34 6.750 SAR 9,392.04 SAR 9,420.76
17 12-Oct-2015 SAR 2,074,327.69 11 November 2015 13 December 2015 32 7.750 SAR 14,094.06 SAR 14,140.55
18 10-Nov-2015 SAR 814,745.02 10 December 2015 13 December 2015 3 8.750 SAR 585.95 SAR 586.09
6.750
18 days EOT
1 03-Jun-14 03-Jul-14 03-Jul-14 21-Jul-14 18 Entitlement
13 days EOT
2 04-Aug-14 03-Sep-14 03-Sep-14 16-Sep-14 13 Entitlement
3 days EOT
3 14-Aug-14 13-Sep-14 13-Sep-14 16-Sep-14 3 Entitlement
10 days EOT
4 18-Sep-14 18-Oct-14 18-Oct-14 28-Oct-14 10 Entitlement
10 days EOT
5 15-Oct-14 14-Nov-14 14-Nov-14 24-Nov-14 10 Entitlement
0 days EOT
6 19-Nov-14 19-Dec-14 19-Dec-14 14-Dec-14 0 Entitlement
0 days EOT
7 08-Dec-14 07-Jan-15 07-Jan-15 05-Jan-15 0 Entitlement
0 days EOT
8 28-Dec-14 27-Jan-15 27-Jan-15 22-Jan-15 0 Entitlement
0 days EOT
9 01-Feb-15 03-Mar-15 03-Mar-15 02-Mar-15 0 Entitlement
10 days EOT
10 11-Mar-15 10-Apr-15 10-Apr-15 20-Apr-15 10 Entitlement
0 days EOT
11 05-Apr-15 05-May-15 05-May-15 04-May-15 0 Entitlement
10 days EOT
12 29-Apr-15 29-May-15 29-May-15 08-Jun-15 10 Entitlement
21 days EOT
13 27-May-15 26-Jun-15 26-Jun-15 17-Jul-15 21 Entitlement
22 days EOT
14 27-Jun-15 27-Jul-15 27-Jul-15 18-Aug-15 22 Entitlement
81 days EOT
VO 1 29-Apr-15 29-May-15 29-May-15 18-Aug-15 81 Entitlement
51 days EOT
VO 2 29-May-15 28-Jun-15 28-Jun-15 18-Aug-15 51 Entitlement
0 days EOT
15 26-Jul-15 25-Aug-15 25-Aug-15 18-Aug-15 0 Entitlement
34 days EOT
Entitlement
16 30-Aug-15 29-Sep-15 29-Sep-15 02-Nov-15 34
32 days EOT
17 12-Oct-15 11-Nov-15 11-Nov-15 13-Dec-15 32 Entitlement
3 days EOT
18 10-Nov-15 10-Dec-15 10-Dec-15 13-Dec-15 3 Entitlement
A + 30 days
A + 30 days