Beruflich Dokumente
Kultur Dokumente
Charger
Index
1. GENERAL
2. MAINTENANCE
3. TROUBLE SHOOTING
4. DO’S AND DONT’S
5. LIST OF TOOLS
CHAPTER 1
GENERAL
1.0 INTRODUCTION
steps so that battery voltage reaches 2.2 Volts/cell. The battery when charged, gives about 2.2
& above Volts/cell. This voltage is known as gassing voltage. Thereafter battery should be
put on “trickle” charge till the voltage comes up to 2.5 volts/cell. This voltage should be
applied for 5 to 6 hours. Thereafter battery is in “fully” charged condition and ready for use.
Check up the specific gravity of battery as per battery manufacturer’s instruction and it
should be same for three consecutive reading.
Before connecting the charger to battery, it must be checked about its polarity. +Ve of
charger output must be connected to battery +Ve & -Ve of charger output to –Ve of battery.
Reverse connection will short the battery through diodes and heavy short circuit current will
pass through rectifier diodes resulting in overload and damage of diodes.
1.1 MAIN PARTS
The battery charger is a robust machine, which is having no moving parts. Following
are the main parts of battery chargers :
(i) TRANSFORMER
This is a dry type, air natural cooled, copper wound, varnish impregnated 3 phase
transformer working on 360/440 volts 50c/s. The transformer is rated for continuous
operation. The insulation is Class ‘F’. The tapping are provided on primary to adjust the
output voltage in between 130 to 150 V DC at 200 Amps.
FIGURE 1.2
(iii) CONTROL
Taps are provided on primary side to vary input voltage from 415 V to 450 V with the
help of rotary switch and fine control switch having 4/6 positions. The charger is provided
with ON/OFF switch along with HRC fuses for back up protection on input side.
FIGURE 1.3
(iv) PROTECTION
CONTROL SWITCHES
Following devices are provided for protection purpose :
FIGURE 1.4
C. Contactor is provided for switching on the unit on load. Contactor gets switched off if
there is a single phasing or over load on the output side.
D. Overload Relay : An over load relay is provided on the mains line. This overload
bimetallic relay will switch off the mains contactor due to overloading. This relay
also protect the unit from single phasing.
E. ELR (Earthing Leakage Relay) is provided to protect the unit from earth fault. This
ELR will trip if fault current exceeds the set value.
F. HRC Fuses are provided on the output side to protect the unit from short circuit and
overload.
FIGURE 1.5
HRC FUSES
G. MCCB : 3 pole MCCB is provided on the
output side. This MCCB will trip due to
overload and isolate the output supply.
H. Indicating pilot lamps are provided on the
mains FIGURE 1.6 incoming and D.C. output.
OUTPUT MCCB
(v) METER
There is a ammeter for each feeder and there are two outgoing feeders. The ammeter
is provided with shunt in the bus-bar. A.C. voltmeter alongwith selector switch is provided to
indicate A.C. voltage. Meters are also provided to measure DC output voltage and current.
Digital meter should be preferable and it must be caliberated.
FIGURE 1.7
PANEL METERS
(vi) VENTILATION
For ventilation purpose, expanded metal is used at the bottom and canopy type cover
is provided on the top. The cover is approximately 30 to 40 mm above top of frame/body.
This helps for free ventilation. Fresh air will be coming from the bottom of the unit and hot
air will be passing from the top. It is advised to see that there is good path for passing the air
from bottom. For, this purpose, unit should be about 0.5 meter away from the wall and top of
the charging room should have sufficient ventilators to pass the air freely.
FIGURE 1.8
2 Nos. earthings are provided on the side of battery charger and they should be
connected properly.
Type - I Chargers for charging battery of 56 lead acid cells of 2Volts, 800 AH capacity
- 110 Volts.
Type - II Chargers for charging 18 mono block (3 cells per monoblock) lead acid cells
of 6 V, 120 AH capacity - 110 volts.
*****
CHAPTER 2
MAINTENANCE
2.1 MONTHLY
iii. Inspect the measuring instruments like ammeter and voltmeter for proper working.
4. Check condition of bus bar heat sink, main diodes. Replace if found
damaged/defective. The polarity of silicon diode must be checked before replacement
of new diode.
5. Check the condition of transformer winding and other electrical parameter. If the
transformer is found defective, take for rewinding.
6. Check the condition of rotary switches, push buttons. Clean and attend them for minor
repairs. Replace with new one if found burnt/defective. The terminals of the rotary
switch should be kept tightened.
7. Check all fuses and replace with new one if found defective.
8. Remove and clean thoroughly terminal board assembly. Replace components with
new one if found damaged/defective.
12. Check all joints and connections of primary and secondary winding.
13. Check the insulation and earth resistance wire of the charger.
15. Check the electrical parameters such as voltage, current, temperature rise and record.
Also check the performance of the equipment for 4 hours.
*****
CHAPTER 3
TROUBLE SHOOTING
*****
CHAPTER 4
4.2 DONT's
CHAPTER 5
LIST OF TOOLS
1. Papers presented from the Railways during Seminar cum Workshop at CAMTECH on 11th
and 12th Oct., 2001.
4. Relevant IS specification
*****