Sie sind auf Seite 1von 1

Client - Konecranes PO No EC004077 1 dated 22/02/2017

Job Number - J 588.


Scope of work - Double girder crane.
ID Task Name Duration Start Finish April 2017 May 2017
11 14 17 20 23 26 29 01 04 07 10 13 16 19 22 25 28 01 04 07 10
1 Scope
2 Fabrication and ex-works
delivery of Double girder
crane 10 Ton x 32m span
3 Engineering 2 days Wed 15/03/17 Thu 16/03/17
4 Procurement 2 days Fri 17/03/17 Mon 20/03/17
5 Fabrication / CS painting 1 wk Tue 21/03/17 Mon 27/03/17
6 Testing 3 days Mon 27/03/17 Wed 29/03/17
7 Ready for delivery Thu 30/03/17
8
9
10 Payment
11 Advance - nil
12 30 days due 30 days Thu 30/03/17 Wed 10/05/17

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: msproj11
Date: Mon 13/03/17 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 1