Beruflich Dokumente
Kultur Dokumente
Date – 13th November 2019
The project is aimed to densify the count of workstations within the existing leased floor plate. Planning and
construction activity shall be carried out in 3 phases in a way that there is minimal downtime and least
impact to Rockwell Automation’s business operations during regular business hours.
Project Duration – 2 months per phase inclusive of procurement and onboarding vendors
Project execution hours – Weekends and after business hours
Schedule
o Phase 1
Start 15th November 2019
End – 15th January 2019
o Phase 2
Start ‐ 1st February 2019
End – 15th March 2019
o Phase 3
Start – 1st April 2019
End – 15th May 2019
Project Execution is proposed in the following phase sequence
1. Phase 1 – 2nd Floor South Wing
a. Existing Workstation (8.5 ft x 6 ft) – 70 Nos
b. Proposed Workstations (5ft x 6ft x 5ft H) – 104 Nos
c. Hot desks to be provisioned to maximize utilization of dead space
d. Cabins – NA
2. Phase 2 – 2nd Floor North Wing
a. Existing Workstation (8.5 ft x 6 ft) – 73 Nos
b. Proposed Workstations (5ft x 6ft x 5ft H) – 104 Nos
c. Hot desks to be provisioned to maximize utilization of dead space
d. Cabins – NA
1 | P a g e
Rockwell Automation India Pvt. Ltd., Bangalore
3. Phase 3 – 4th Floor South Wing
a. Existing Workstation (8.5 ft x 6 ft) – 72 Nos
b. Proposed Workstations (5ft x 6ft x 5ft H) – 104 + Nos
c. Hot desks to be provisioned to maximize utilization of dead space
d. Cabins – NA
4. Additional works
a. Creation of 8 seater meeting room in the 3rd floor collab
b. Creation of a store room for APBC in the 3rd floor collab
c. Renovation of ceiling in restrooms including changing light fixtures
d. Creation of achievers wall in 2nd floor north wing atrium
2 | P a g e
Rockwell Automation India Pvt. Ltd., Bangalore
SERVICES SCOPE DOCUMENT
Electrical Upgradation
Required (including new Phase Segregated DB, XLPE 2XWY cables as per IS 7098 (Part 1) 1988)
1. Phase 1 ‐ 2nd Floor South Wing
Workstations
a. 8 UPS power sockets (2 Sockets + 1 Switch – Anchor Roma Plus Make) x 4 installed on
the raceway above the table top
b. 3C X 4 sq. mm FRLS cables to be laid for all workstations (4 w/s in a single circuit)
c. Common Point Ground to be installed in firmware team workstations
2. Phase 2 ‐ 2nd Floor North Wing
Workstations
a. 4 UPS power sockets (2 Sockets + 1 Switch – Anchor Roma Plus Make) x 2 installed on
the raceway above the table top.
b. 3C X 4 sq. mm FRLS cables to be laid for all workstations (4 w/s in a single circuit)
3. Phase 3 – 4th Floor South Wing
a. 4 UPS power sockets (2 Sockets + 1 Switch – Anchor Roma Plus Make) x 2 installed on
the raceway above the table top.
b. 3C X 4 sq. mm FRLS cables to be laid for all workstations (4 w/s in a single circuit)
Hot Desks ‐ Power provision to be given on the facia of the nearest modular workstation in a
user friendly manner as per placement plan given by architect.
Passive IT Upgradation
To be done appropriately to achieve data given in design intent. Existing passive cabling infrastructure to be
reused after testing. New cables to be laid for additional workstations and additionally only for replacing
damaged infrastructure.
4. Phase 1 ‐ 2nd Floor South Wing
Workstations ‐ 4 data ports (2 Local & 2 Secured of which 2 shall be standby) installed on the
raceway below the table top. All faulty data cables shall be identified and replaced as per
design requirement.
3 | P a g e
Rockwell Automation India Pvt. Ltd., Bangalore
5. Phase 2 ‐ 2nd Floor North Wing
Workstations ‐ 4 data ports (2 Local & 2 SDE of which 2 shall be standby) installed on the
raceway below the table top. All faulty data cables shall be identified and replaced as per
design requirement.
6. Phase 3 – 4th Floor South Wing
Workstations ‐ 2 data ports (2 Local of which 1 shall be redundant) installed on the raceway
below the table top. All faulty data cables shall be identified and replaced as per design
requirement.
Hot Desks ‐ Provision to be given on the facia of the nearest modular workstation in a user friendly
manner as per placement plan given by architect.
Active IT Upgradation – Does not apply
HVAC Upgradation ‐ Does not apply
Fire Detection Systems Upgradation ‐ Does not apply
Access Control & CCTV – Applicable to 3F IT Store (part of additional scope of works)
Audio Visual Equipment ‐ Does not apply
4 | P a g e
Rockwell Automation India Pvt. Ltd., Bangalore
2nd Floor (Existing Workstation Set Up)
2F Existing.pdf
5 | P a g e
Rockwell Automation India Pvt. Ltd., Bangalore
2nd Floor Proposed Plan (Phase 1 & 2)
6 | P a g e
Rockwell Automation India Pvt. Ltd., Bangalore
4th Floor (Existing Workstation Set Up)
4F Existing.pdf
7 | P a g e
Rockwell Automation India Pvt. Ltd., Bangalore
4th Floor Proposed Plan (Phase 3)
8 | P a g e
Rockwell Automation India Pvt. Ltd., Bangalore