REVISION 9.05
Model RC-101
c
Copyright °2005 Turbine Technologies, LTD
Service Publications
410 Phillip Street
Chetek, WI 54728
All rights reserved. No part of this manual may be reproduced, stored in a retrieval system or transmitted by any
means, electronic, mechanical, photocopying, recording or otherwise–without written permission from Turbine
Technologies, LTD, except for the explicit use and inclusion in a course of academic study utilizing the Turbine
Technologies, LTD RankineCycler Steam Turbine Power System
Many of the designations used by manufacturers to distinguish their products are claimed as trademarks or service
marks. Every attempt has been made to supply trademark information about manufacturers and their products
mentioned in this manual. A list of the trademark or service mark designations and their owners appears on page
iii.
Every effort has been made to make this manual as complete and accurate as possible. The purchaser shall be
solely responsible for determining the suitability of the information contained herein. See page v.
iii
TRADEMARK NOTICES
SUITABILITY
The Turbine Technologies, LTD RankineCycler is not offered as and shall not be construed by
the purchaser to be “Consumer Products” within the common definition of the United States Federal
Trade Commission. All Turbine Technologies, LTD products are represented to be, and offered as,
EXPERIMENTAL TECHNOLOGY, subject to the limitations in safety and performance inherent to
equipment so classified. PURCHASER SHALL BE SOLELY RESPONSIBLE for determining, prior
to purchase, at acceptance and for all subsequent usage, the suitability for any purpose(s) intended
of equipment, instructions, procedures or materials offered or supplied by Turbine Technologies, LTD
for use in any educational, laboratory or industrial setting.
vi
Preface
The RankineCycler is the best tool on the market for laboratory teaching of thermodynamic
principles and power generation, and it comes with the lowest price tag. In fact, as far as I can tell,
it is the only available educational equipment of its kind.
- Dr. Andy Gerhart
Assistant Professor Mechanical Engineering
College of Engineering, Lawrence Technological University
Southfield, MI
Since the first century AD and the invention of the aeolipile by Heron of Alexandria, man has
endeavored to harness the power of steam. Refined by Denis Papin and improved throughout the
Industrial Revolution by the likes of Thomas Savery, Thomas Newcomen and James Watt, the steam
engine became an important source of mechanical power. The steam turbine, made practical by
Charles Parson and improved commercially by George Westinghouse, furthered the use of steam
power and helped accelerate the electrification of the modern world.
William Rankine, a Scottish physicist and early pioneer in the study of thermodynamics, compiled
the first comprehensive study of steam power in his 1859 Manual of the Steam Engine and Other
Prime Movers. Describing the production of power with a vapor power plant, the Rankine Cycle
became the basis for all future thermodynamic power system and cycle study.
Challenging generations of engineering students ever since, the Rankine Cycle has been used
to theoretically model and teach the physical processes taking place in power-generating systems.
The Turbine Technologies, LTD RankineCycler takes this abstract modeling to a new level, al-
lowing students to not only measure the various variables that go into the Rankine Cycle, but to
see, hear and even feel the generation of steam power first hand. By making text book academics
come alive, the RankineCycler will help today’s students become the real world engineers of tomorrow.
vii
viii
Manual Structure
Section 1 - General Information Background information to help the new user become familiar
with the RankineCycler unit prior to operation.
Section 2 - Limitations Important limitations for the safe operation of the RankineCycler.
Section 3 - Abnormal Procedures Checklist Procedures for operations that exceed or are outside
the scope of the RankineCycler Limitations or Normal Procedures.
Section 4 - Normal Procedures Checklist Procedures for Normal Operation of the Rank-
ineCycler.
Section 5 - Systems Description of all unique RankineCycler systems and their operation.
Section 6 - Service and Maintenance Information to maintain the RankineCycler in proper op-
erating condition.
Appendix A - Warranty Information
Comments/Questions
Please address comments and questions concerning this Operator’s Manual to the publisher:
A RankineCycler web page featuring an image gallery, press releases, video, product specifications
and operator produced technical papers is available at:
http://www.turbinetechnologies.com/steam.html
Specific questions regarding the operation or servicing of the RankineCycler should be addressed to:
service@turbinetechnologies.com
For more information about Turbine Technologies, LTD and its products for engineering education,
please see the Turbine Technologies web site at:
http://www.turbinetechnologies.com
Or email:
info@turbinetechnologies.com
Contents
Preface vii
Section 2 - LIMITATIONS 7
ix
x CONTENTS
Section 5 - Systems 43
5.1 Steam Turbine System . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43
5.1.1 Burner . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43
5.1.2 Boiler . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 44
5.1.3 Sight Glass . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45
5.1.4 Boiler Pressure Gauge . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45
5.1.5 Steam Admission Valve . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45
5.1.6 Steam Turbine . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45
5.1.7 Generator . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 46
5.1.8 Condenser Tower . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 46
5.1.9 Operator Panel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 46
5.2 Fill/Drain System . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 47
5.3 Data Acquisition System . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 47
5.3.1 Computer . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 47
5.3.2 DAQ Module . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 47
5.3.3 Sensors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 48
5.3.4 Software . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51
5.4 Cabinetry . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51
5.4.1 Chassis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51
5.4.2 Electrical . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51
5.4.3 Fuel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51
5.4.4 Miscellaneous . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51
xi
xii LIST OF TABLES
Section 1
General Information
1.1 Introduction
The Turbine Technologies, LTD RankineCycler Steam Turbine Power System is a complete steam
electric power plant in miniature purposely designed for engineering education and research. The
system accurately represents a typical fossil-fueled vapor power plant in which water is the working
fluid.
Turning heat energy into useful work is the purpose of any vapor power system. With the Rank-
ineCycler, steam is generated by heating water in a multi-pass, flame-through tube type boiler with
a super heat dome. This high-pressure steam is expanded through an axial flow turbine wheel that
drives an AC/DC generator to produce electricity. Leaving the turbine at low pressure, the vapor
then enters a condenser tower, returning to its original liquid state. In a full scale power plant, this
liquid water would then be returned to the boiler.
Initial thermodynamic calculations can be made using the classic Ideal Rankine Cycle model. Nu-
merical predictions based on the temperature-entropy process flows of the cycle can then be measured
directly on the RankineCycler with the integrated data acquisition system. Sensors located at various
points along the vapor path allow accurate measurements to be made of the operating conditions at
those points.
Explaining the differences and accounting for the real world results presents limitless educational
opportunities.∗ For safety and convenience, the RankineCycler is not equipped with a feedwater
return pump. Because actual pump work is significantly less than that in the turbine, neglecting the
pump contribution will have negligible effect on the net work of the cycle and the cycle calculations
overall.
Additional opportunities in the study of Environmental and Pollution engineering are possible
through both qualitative and quantitative analysis of other parameters outside the scope of the stock
RankineCycler.
∗ Reasonable expectations regarding experimental results must be made when operating the RankineCycler or any
similar equipment where scale effects are present. By size and design, the system can only model full-size steam and
power generation. Efficiency, power output and overall system performance will naturally be much different than
that for the same process on a larger scale. Additionally, temperatures and pressures are necessarily kept low for
safety considerations. In whole, the RankineCycler provides an excellent foundation for exploring the shortcomings
(and pitfalls) of applying textbook formulas and ideal data to a problem without considering all aspects of the overall
system. The challenge to the student is in the analysis of experimental run-time data and determining why the results
may differ from analytical expectations. This is the true benefit of hands-on, laboratory and experimental engineering.
Rest assured, no Laws of Thermodynamics are broken during the operation of the RankineCycler.
1
2 SECTION 1
1.2 SAFETY
As with any piece of laboratory equipment, basic safety precautions must be followed
at all times. Protective eyewear must be worn whenever the equipment is in operation
or receiving service. Complete familiarization with all aspects of the RankineCycler
system and its operation must be made prior to usage.
The RankineCycler boiler has been low cycle fatigue pressure tested to 150% of normal
operating pressure. The boiler is NOT ASME rated, nor is it approved by any other
testing facility or regulatory body.
1.3 Specifications
• DIMENSIONS - Steam Turbine Power System
– LENGTH . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30.0 inches (77 cm)
– WIDTH . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 48.0 inches (122 cm)
– HEIGHT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 58.0 inches (148 cm)
– HEIGHT with FILL BEAKER . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 82.0 inches (209 cm)
– WEIGHT operational . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 175 lbs (80 kg)
The steps necessary to uncrate the RankineCycler and prepare it for initial use are outlined as
follows. NOTE: DO NOT discard ANY material within the shipping container until a complete
inventory has been made of the included contents.
1. Remove Shipping Container Front Door DO NOT pry the container open! Locate the
front door of the container as indicated by the “DOOR - OPEN THIS SIDE ONLY” stencil.
Approximately 21 screws, indicated by 1.0 inch (2.5 cm) red squares and located around the
door perimeter, need to be removed to open the container front door. Only remove those screws
delineated by the red squares. With all the screws removed, the door may be opened and set
aside.
2. Remove Packaged Contents Boxes Various items are separately boxed and/or located under
the RankineCycler cabinet. The following items are typically included:
(a) Important Documents and System Keys A box marked Important Documents
contains all documents essential to the operation of the RankineCycler (including backup
software disks and sensor calibration data). Included are two copies of the RankineCycler
Steam Turbine Power System Operator’s Manual. One copy should be removed at
this time and used for the remainder of the SET-UP process and all subsequent operation.
The other copy should be set aside for safe keeping. A set of QuickCheck operator checklists
are included for convenient reference and efficient operation of the RankineCycler. The keys
for the RankineCycler Master Switch are located within the manual binder, attached to
the top binder ring. It is recommended that one key be left in the binder for safe keeping
and the other placed into the Master Switch until a specific key storage location and usage
policy is determined.
(b) Boiler Fill/Drain Beaker The fill/drain beaker is located in a box and wrapped in
protective plastic.
(c) Computer Equipment Any computer equipment and accessories ordered with the system
will be found in a box. All software required to operate the data acquisition system is
preloaded on this computer.
3. Remove Hold Down Clips Three hold down clips secure the RankineCycler to the shipping
container. These clips are indicated by 2.0 inch (5.0 cm) red squares, one each on the left, right
and rear exterior sides of the shipping container. By removing the items in Step 2 above, access
is gained to the clips and the corresponding fasteners on the interior of the box. Remove these
three clips and corresponding fasteners.
† Turbine Technologies, LTD is not responsible for damage due to shipping. It is the recipient’s responsibility to
inspect the shipping container for obvious external damage and to make the appropriate claims with the shipping agent
prior to accepting the contents or opening the shipping container.
4 SECTION 1
4. Remove Perimeter Base Screws At the base of the left, right and rear exterior sides of
the shipping container are the perimeter base screws holding the upright sides of the shipping
container to the pallet base. Approximately 12 screws, indicated by 1.0 inch (2.5 cm) red squares,
need to be removed around the container base. No other screws need be removed.
5. Remove Shipping Container Side/Top Assembly With the perimeter base screws removed
in Step 4 above, the three container sides (with the top still attached) can be removed. This
is accomplished by tilting the container assembly “back,” away from the open door. Take care
that the sides continue to clear the RankineCycler as the entire assembly is tilted back. Once
it is clear of the RankineCycler, the container side assembly can be set aside.
6. Lift RankineCycler Clear of Pallet With adequate assistance, the RankineCycler may now
be lifted clear of the container pallet and set on the floor. To avoid damage to the system, only
lift on the area adjacent to the cabinet legs. DO NOT lift by grasping any of the components
on the top side of the system cabinet.
7. Unlock Caster Wheels All four caster wheels under the system cabinet are lockable and will
be locked for shipping. Lifting the locking tab releases the lock mechanism. Release all four
caster wheel locks as necessary.
8. Remove Protective Packing Material A large piece of plastic will be draped over the entire
RankineCycler. Bubble-wrap type material will be wrapped around the entire system. The two
boiler doors will be secured with a length of plastic wrap. Remove all of this material from the
RankineCycler.
9. Inventory / General Condition Assessment / Cleaning Using Table 1.1 as a guide, in-
ventory all received contents and verify their general condition. Separate Packing and Inventory
lists will be found within the shipping container to further assist in this process. If any item is
found to be missing or damaged, contact Turbine Technologies, LTD immediately. With a soft
cloth, wipe any dust or dirt from the system cabinetry and accessories.
10. Retain Shipping Container / Materials With all RankineCycler components accounted for
in Step 9, the shipping container may be removed for storage. All packing material should be
placed within the container and the container side assembly and front door reattached with the
original screws previously removed. While the container may be disposed of at this time, it is
recommended that the container and packing material be retained for future use should the need
arise to move the RankineCycler over any appreciable distance, store for an extended period of
time or to return the RankineCycler to the factory for service or upgrade.
11. Connect Suitable Fuel Supply An appropriate liquid propane tank with an adequate supply
of fuel is required to operate the RankineCycler. Tanks of the 20, 30 and 40 “pound” variety
common to gas cooking appliances and portable heating equipment are acceptable. The 20
pound size is ideal for classroom use, allowing portable operation with several hours of run-time.
The fuel source gas regulator and hose assembly is tie-wrapped to the front, right cabinet leg.
Cut the tie-wrap loose and connect the provided fuel source gas regulator to the selected fuel
source. This regulator is factory adjusted to work with liquid propane fuel. Please consult the
factory prior to using other fuel types.
The RankineCycler is now ready for operation. See Section 4 - Normal Procedures for further
instructions.
GENERAL INFORMATION 5
ITEM DESCRIPTION
NUMBER 1 2 3 4 Level QTY LOCATION
1 SHIPPING CONTAINER 1
2 . RankineCycler 1 SHIPPING CONTAINER
3 . . Fuel Source Gas Regulator/Hose Assembly 1 RankineCycler Front, Right Leg
4 . Important Documents 1 SHIPPING CONTAINER
5 . . Master Keys 2 Important Documents
6 . . Operator’s Manual 2 Important Documents
7 . . Computer Software various Important Documents
8 . Box 1 1 SHIPPING CONTAINER
9 . . Fill/Drain Beaker 1 Box 1
10 . Box 2 1 SHIPPING CONTAINER
11 . . Computer/Power Cable/Power Adapter 1 each Box 2
12 . . USB Cable 1 Box 2
6 SECTION 1
Section 2
LIMITATIONS
The RankineCycler is designed to be operated within the following limitations. Under no circum-
stances should these limitations be exceeded by any margin. Operator safety and efficient operation
of the RankineCycler is contingent upon these limitations being followed.
• BOILER
– MAXIMUM OPERATIONAL BOILER PRESSURE . . . . . . . . . . . . . . . 120 psi (827 kPa)
– MAXIMUM OPERATIONAL BOILER STEAM TEMPERATURE . . . 608 ◦ F (320 ◦ C)
– MAXIMUM OPERATIONAL BOILER VOLUME . . . . . . . . . . . . . . . . . 203 oz (6,000 ml)
– OPERATING FLUID . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . WATER
• BURNER
– FUEL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .LIQUID PROPANE (LP) ONLY
• GENERATOR
– MAXIMUM GENERATOR OUTPUT, Voltage . . . . . . . . . . . . . . . . . . . . . . . . . . . 15.0 Volts
– MAXIMUM GENERATOR OUTPUT, Current . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.0 Amps
– MAXIMUM GENERATOR OUTPUT, Power . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15 Watts
– MAXIMUM GENERATOR SPEED, RPM . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .4500 RPM
7
8 SECTION 2
Section 3
ABNORMAL PROCEDURES
The RankineCycler is designed with the highest regard to operator safety. It is very unlikely during
the normal course of operation and within the limitations set forth in this manual, that any conditions
will be encountered requiring the use of ABNORMAL PROCEDURES as set forth herein. These
procedures are provided in the event of a “worst case” scenario resulting from multiple system failures.
The procedures in this section outline the minimum steps necessary to achieve a safe system state.
When the system is secured and there is no further potential for personal harm, normal shutdown
procedures should be completed. All further operation of the system should be suspended until a
determination is made of the cause of the abnormal event and the suitability for continued operation
is determined by qualified personnel.
In general, remembering “OFF - OPEN - OFF,” will be all that is necessary to deal with any
abnormal condition encountered with the RankineCycler.
9
10 SECTION 3
ABNORMAL PROCEDURES 11
a. LOAD SWITCH . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ON
b. LOAD RHEOSTAT CONTROL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . TURN FULLY CLOCKWISE
3.1.2 FIRE
1. MASTER SWITCH . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . OFF
2. FIRE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . EXTINGUISH WITH FIRE EXTINGUISHER
3. IF SAFETY IS NOT COMPROMISED
3.1.3 ELECTRICAL
1. MASTER SWITCH . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . OFF
2. STEAM ADMISSION VALVE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . OPEN
3. OPERATOR PANEL GAS VALVE (or FUEL SOURCE) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . OFF
4. LOAD SWITCH . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . OFF
1. The console MASTER SWITCH should be placed in the OFF position. Doing so removes
all electrical power to the system. By removing electrical power, both the gas regulator and
the combustion blower will shut off. Both are needed to support combustion in the boiler.
By eliminating the heat source, no additional energy transfer to the boiler is possible thereby
eliminating the potential for further pressure rise.
2. The STEAM ADMISSION VALVE should be turned counter-clockwise to the fully OPEN
position. This vents boiler pressure through the normal steam path across the turbine and into
the condenser tower. With no heat and an open steam admission valve, the boiler pressure
should begin decreasing immediately.
3. Turn the OPERATOR PANEL GAS VALVE (or FUEL SOURCE) to the OFF position.
Items 1 through 3 should sufficiently eliminate the potential for further pressure rise. If operator
safety is in question, all personnel should leave the area until such time that the boiler has cooled.
4. IF SAFETY IS NOT COMPROMISED in any way, the following additional steps should be
considered:
Engaging the LOAD SWITCH helps to quickly dissipate the steam pressure by placing a load on
the steam turbine (through the generator). This also prevents damage to the turbine, generator
and associated bearings caused by overspeeding the turbine with the higher than normal steam
pressure.
3.2.2 FIRE
The likelihood of a FIRE is virtually non-existent with the RankineCycler. Although a flame is
present within the boiler, only a failure at the operator panel gas valve, the fuel source regulator or
the connecting hose would produce a flame or persistent fire requiring the use of abnormal procedures.
It should be noted that the burner may occasionally “burp” – producing an audible popping noise
with a small blue flame present at the blower inlet. This behavior is normal and should NOT be
considered a fire requiring the execution of the fire abnormal procedures.
1. The console MASTER SWITCH should be placed in the OFF position. Doing so removes all
electrical power to the system. By removing electrical power, both the gas regulator and the
combustion blower will shut off.
14 SECTION 3
2. Using an available and appropriate FIRE EXTINGUISHER (ABC Type), extinguish the flames.
If operator safety is in question, all personnel should leave the area, activate the appropriate fire
alarm and follow the required emergency plan.
3. IF SAFETY IS NOT COMPROMISED in any way, the following additional steps should be
considered:
a. Because of the elevated heat around the system, the potential exists for a boiler overpressure
condition. The STEAM ADMISSION VALVE should be turned counter-clockwise to the
fully OPEN position.
b. Turn the OPERATOR PANEL GAS VALVE (or FUEL SOURCE) to the OFF position,
positively removing the fuel source and eliminating the potential for re-ignition.
3.2.3 ELECTRICAL
There are two distinct electrical systems within the RankineCycler, the main bus that powers the
indicator lights, boiler combustion blower and the gas regulator system and a separate steam generator
bus allowing the measurement of electrical generating capability of the steam turbine and generator.
The main bus is further divided into a “high” and “low” system, each equipped with its own resettable
circuit breaker (8 and 3 amps respectively). The main bus and the steam generator bus are electrically
isolated preventing any interaction between the two systems. Problems of an electrical nature would
most likely be caused through a short condition in either bus or between the two busses. Any electrical
malfunction of a short or overload nature will trip the on board circuit breaker, the facility circuit
breaker or both.
If an electrical fault is suspected, either through an unexpected shut-down of the RankineCycler or
through more obvious signs such as audible or visible arcing or electrical type smoke caused by melting
insulation, the following steps should be followed. Once the system is secure, a close examination of
the cause of the malfunction should be made prior to resetting any circuit breaker.
1. The console MASTER SWITCH should be placed in the OFF position. Doing so removes all
electrical power to the system.
2. As standard procedure and to maintain consistency with other abnormal procedures, the
STEAM ADMISSION VALVE should be turned counter-clockwise to the fully OPEN posi-
tion.
3. As with Item 2, turn the OPERATOR PANEL GAS VALVE (or FUEL SOURCE) to the OFF
position.
4. The LOAD SWITCH should now be selected OFF to remove any resistance from the steam
generator bus.
The RankineCycler is designed with simplicity and operator convenience in mind. Inexperienced
operators will quickly gain familiarity and confidence with the system permitting the collec-
tion of meaningful data from the very first run. No special knowledge or skills are required to use
the RankineCycler thereby allowing its usage in even the most basic of science and engineering courses.
This section provides a set of standard procedures to follow while operating the RankineCycler.
The steps and the order in which they appear represent the most efficient procedure to initiate
operation of the RankineCycler and to collect run-time data for use in a typical academic setting.
Aside from the necessary cool down time, a complete operational run can be accomplished within a
one-hour lab session.
Familiarity with these procedures must be made prior to operating the RankineCycler for the
first time. Experienced operators should continue to use the checklist for each operational run to
eliminate the possibility of overlooking or inadvertently eliminating a necessary step. With power
removed from the system (electrical service removed), the various switches, valves and controls may
be manipulated without harm to the system. This permits the ability to use the checklists in a “dry
run” or rehearsal fashion prior to operating the RankineCycler under power.
The RankineCycler represents a dynamic system. Operation should not be initiated without a
purpose or plan such as a lab procedure. Each participant needs to be familiar with their role and
what to do in case of an emergency (see Section 3 - ABNORMAL PROCEDURES).
WARNING
Do Not Permit Unattended Operation of the RankineCycler
15
16 SECTION 4
NORMAL PROCEDURES 17
These checklists are presented in order of usage. Each item should be completed before proceeding
to the next item. Each section must be completed before proceeding to the next section. It is
recommended that one operator read the checklist while another performs the task.
2. Section 4.1.2 START and OPERATION - Starts the RankineCycler and establishes a steady
state system.
3. Section 4.1.3 DATA COLLECTION - Uses the data acquisition system to display and record
system operational parameters.
5. Section 4.1.5 MEASUREMENTS - Steps necessary to measure the quantity of boiler water used
and condensate collected.
4.1.1 PRE-START
1. AREA CHECK . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .VERIFY SUITABILITY FOR OPERATION
2. CASTER WHEELS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . LOCKED
3. KEYED MASTER SWITCH . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . OFF
4. BURNER SWITCH . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . OFF
5. LOAD SWITCH . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . OFF
6. LOAD RHEOSTAT . . . . . . . . . . . . . . . . . . MINIMUM LOAD, FULL COUNTER-CLOCKWISE POSITION
7. OPERATOR PANEL GAS VALVE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . OFF
8. VISUAL INSPECTION
4.1.4 SHUTDOWN
1. TIME . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . NOTED
2. STEAM ADMISSION VALVE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . CLOSED
3. SIGHT GLASS LOWER BEZEL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SET TO WATER LEVEL
4. BURNER SWITCH . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . OFF, RED LIGHT EXTINGUISHED
5. OPERATOR PANEL GAS VALVE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . OFF
6. LOAD RHEOSTAT . . . . . . . . . . . . . . . . . . MINIMUM LOAD, FULL COUNTER-CLOCKWISE POSITION
7. LOAD SWITCH . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . OFF
8. MASTER SWITCH . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .OFF, GREEN LIGHT EXTINGUISHED
9. STEAM ADMISSION VALVE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . OPEN
10. FUEL SOURCE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . OFF
26 SECTION 4
NORMAL PROCEDURES 27
4.1.5 MEASUREMENTS
1. To Measure Condensate Collected
a. INSURE EQUIPMENT HAS SUITABLY COOLED FOR HANDLING and THERE IS NO BOILER
PRESSURE
b. CONDENSER TOWER . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . DRAIN FULLY
c. CONDENSATE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . RECORD VOLUME
d. DISCARD CONDENSATE - DO NOT REUSE
2. To Measure Boiler Water Consumed
a. INSURE EQUIPMENT HAS SUITABLY COOLED FOR HANDLING and THERE IS NO BOILER
PRESSURE
b. STEAM ADMISSION VALVE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . OPEN
c. BOILER . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . FILL TO SIGHT GLASS UPPER BEZEL
d. BOILER . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . DRAIN TO SIGHT GLASS LOWER BEZEL
e. BOILER WATER . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . RECORD VOLUME
f. STOW MEASUREMENT EQUIPMENT
28 SECTION 4
NORMAL PROCEDURES 29
4.1.6 STORAGE
1. COMPUTER DAQ SYSTEM . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . OFF, DISCONNECT, STOW USB CABLE
2. LOAD RHEOSTAT . . . . . . . . . . . . . . . . . . MINIMUM LOAD, FULL COUNTER-CLOCKWISE POSITION
3. LOAD SWITCH . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . OFF
4. BURNER SWITCH . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . OFF
5. KEYED MASTER SWITCH . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . OFF
6. OPERATOR PANEL GAS VALVE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . OFF
7. FUEL SOURCE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . OFF
8. FUEL SOURCE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . DISCONNECT, SUPPLY LINES STOWED
9. RANKINECYCLER ELECTRICAL SERVICE . . . . . . . . . . . . . . . . . . . . . . . . DISCONNECT, CORD STOWED
10. STEAM ADMISSION VALVE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . OPEN
11. INSURE EQUIPMENT HAS SUITABLY COOLED FOR HANDLING and THERE IS NO BOILER PRESSURE
12. BOILER . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . DRAIN
13. FRONT and REAR BOILER DOORS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . CLOSED and LATCHED
14. CONDENSER TOWER . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . DRAIN
15. FINAL CHECK . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . COMPLETE
16. RANKINECYCLER . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SECURED
30 SECTION 4
NORMAL PROCEDURES 31
These steps are presented in order of usage. Each item should be completed before proceeding
to the next item. Each section must be completed before proceeding to the next section. It is
recommended that one operator read the steps aloud while another performs the task.
2. Section 4.2.2 START and OPERATION - Starts the RankineCycler and establishes a steady
state system.
3. Section 4.2.3 DATA COLLECTION - Uses the data acquisition system to display and record
system operational parameters.
5. Section 4.2.5 MEASUREMENTS - Steps necessary to measure the quantity of boiler water used
and condensate collected.
4.2.1 PRE-START
The PRE-START checklist must be completed prior to operating the RankineCycler. The checklist
establishes that all systems are ready for operation and that heat can be safely applied to the boiler.
1. The AREA CHECK is a general assessment to VERIFY SUITABILITY FOR OPERATION. This
includes a suitability determination of safety and facilities factors, additional equipment require-
ments and the presence of trained, knowledgeable operators. All operators and personnel in the
immediate area should know the location of fire extinguisher equipment, circuit breakers and fuel
supply valves, as well as being familiar with existing safety policies and procedures, emergency
escape routes, and emergency services telephone numbers/points of contact. The facility must
provide adequate ventilation sufficient to vent the anticipated amounts of steam and combustion
gas production. In addition to safety glasses, all operators should have access to face shields,
gloves, lab coats or other items of personal protection as deemed necessary. All operators must
be thoroughly familiar with the contents of this manual prior to operating the RankineCycler.
It is strongly encouraged that two or more individuals operate the RankineCycler as a team to
enhance safety and insure that all checklist items are completed.
2. CASTER WHEELS must be in the LOCKED position prior to operation, preventing movement
that may either pose a safety hazard or disrupt critical operations such as boiler filling.
3. KEYED MASTER SWITCH to the OFF position puts the system into a known, safe condition from
which it can be properly started. The MASTER SWITCH controls electrical power distribution
to the entire system. With the MASTER SWITCH OFF, no electricity can flow to the burner,
thereby preventing any chance for ignition prior to the system being ready.
4. BURNER SWITCH to the OFF position puts the system into a known, safe condition from which
it can be properly started.
5. LOAD SWITCH to the OFF position puts the system into a known, safe condition from which
it can be properly started.
7. OPERATOR PANEL GAS VALVE to the OFF position puts the system into a known, safe condition
from which it can be properly started.
8. At this point, a thorough VISUAL INSPECTION of each major component or system is performed.
This will verify that the component or system is in a safe condition for proper operation. This
important step verifies that no components were damaged, tampered with or removed since
the last run. If any component is in doubt, qualified personnel should be consulted prior to
operation.
a. The FUEL TANK/SOURCE must be CHECKED for general condition. Liquid Propane (LP)
bottles and corresponding regulators should be free from rust or corrosion, not damaged
in any way and intact with all standard safety features in place. Fuel lines should be free
from cuts and abrasion. All fittings and open lines must be clean and free from dirt and
moisture. Any liquid propane fuel source may be used providing it can accept the Turbine
Technologies, LTD provided fuel source gas regulator and hose assembly.
b. The BURNER must be CHECKED for general condition. All external surfaces should be
free from damage such as dents or cracks. All external fasteners should be in place. The
aluminum fins inside the blower fan should be straight and free from contamination. The
vortex disk, visible through the open boiler doors should appear clean and straight.
34 SECTION 4
c. The BOILER must be CHECKED for general condition. The boiler mantle should be clean
with no obvious signs of leakage. The front and rear boiler doors must fit tight when closed,
with no binding, and latch securely.
d. The BOILER PRESSURE GAUGE must be CHECKED for general condition. There should
be no obvious signs of leakage around the base fittings or the pressure gauge head. The
pressure gauge steam line must be free from kinks or non-original bends. The gauge itself
must be undamaged with no cracks permitted in the clear faceplate.
e. The SIGHT GLASS must be CHECKED for general condition. All fittings should be tight
with no obvious signs of leakage. All external fasteners should be in place. The SIGHT
GLASS should be intact with no cracks.
f. The STEAM ADMISSION VALVE must be CHECKED for general condition. There should
be no obvious signs of leakage around the valve. The valve should move from fully closed
to fully open with no binding.
g. The STEAM LINES must be CHECKED for general condition. There should be no obvious
signs of leakage around any STEAM LINE fittings. The lines must be free from kinks or
non-original bends. The orange insulating tape should be secure at all locations.
h. The OPERATOR PANEL must be CHECKED for general condition. All switches, controls
and meters should be secure in the console. The clear meter face plates must be in place
and not cracked or otherwise damaged.
i. The CONDENSER TOWER must be CHECKED for general condition. The CONDENSER
TOWER should be free from dents or other damage. The outlet must be free from obstruc-
tion.
9. The CONDENSER TOWER should be DRAINED. This provides a known starting condition for
the next experimental run. CONDENSER TOWER condensate will usually contain some amount
of minerals depending upon water quality. Drain the CONDENSER TOWER using the attached
clear tubing and pinch-clamp. Discard any condensate collected from the CONDENSER TOWER.
10. The FRONT and REAR BOILER DOORS must be CLOSED and LATCHED.
11. The STEAM ADMISSION VALVE must be OPEN to allow air to vent out of the boiler during
the fill operation. Water will not enter the boiler with the STEAM ADMISSION VALVE closed.
12. The BOILER should be DRAINED completely. This provides a known starting condition for
the next experimental run. The BOILER can be quickly drained using the fill/drain valve and
beaker assembly. Place the beaker on a firm support lower than the boiler fill/drain valve at
the rear of the boiler. Insert the aluminum coupler at the end of the beaker hose assembly into
the fill/drain valve coupling hole. Firmly pressing the coupler into the fill/drain valve will open
the internal valve and allow water to flow out of the boiler. Open the beaker ball valve to allow
water to drain into the beaker. When it appears that no more water is draining from the boiler,
close the beaker ball valve and remove the aluminum coupler from the fill/drain valve. The
water collected from this draining operation may be discarded.
13. Fill the BOILER with 203 oz (6,000 ml) of clean, distilled water (tap water is acceptable, although,
depending on dissolved mineral content, boiler fouling may eventually result). This amount will
fill the boiler to the recommended level allowing for the most efficient operation. Any quantity
over this recommended amount will likely degrade boiler performance and may prevent the
boiler from producing any pressure. With the beaker ball valve closed, fill the beaker to the
desired boiler level. Place the beaker on a firm support higher than the boiler fill/drain valve
at the rear of the boiler. If this is the first run of the day or adequate time has passed that the
condenser tower is sufficiently cool, the base of the beaker may be placed into the top opening of
the condenser tower for convenience. Insert the aluminum coupler at the end of the beaker hose
NORMAL PROCEDURES 35
assembly into the fill/drain valve coupling hole. Firmly pressing the coupler into the fill/drain
valve will open the internal valve and allow water to flow into the boiler. Open the beaker
ball valve to allow water to fill the boiler. When all the water has emptied from the beaker,
close the beaker ball valve and remove the aluminum coupler from the fill/drain valve. Allow
approximately five minutes to completely fill the boiler using the beaker.
14. The FILL EQUIPMENT should be STOWED, keeping it out of the way during operation and in
a safe location. If the beaker assembly was placed into the top opening of the condenser tower
while filling the boiler, remove it before proceeding to the next step.
15. The STEAM ADMISSION VALUE to the CLOSED position puts the system into a known, safe
condition from which it can be properly started. Starting with a closed valve allows boiler
pressure to properly build.
16. The COMPUTER DAQ SYSTEM USB cable should now be CONNECTED to the DigiDAQ
system receptacle on the left side panel of the RankineCycler. A computer with the appropriate
data acquisition software should be connected to the opposite end of the cable. Make sure the
computer is OFF prior to connecting the cable or the DAQ Module hardware/software may not
properly initialize.
17. The RANKINECYCLER ELECTRICAL SERVICE should be CONNECTED to the electrical outlet.
18. The FUEL SOURCE line should be CONNECTED to the barbed gas inlet underneath the Rank-
ineCycler cabinet. Verify that the Turbine Technologies, LTD gas source regulator and hose
assembly are used for this purpose. Use of any other regulator or hose combination may result
in poor RankineCycler performance. If any other regulator or hose combination is to be used,
please consult the factory for assistance.
19. Insure that a FINAL CHECK of all items is COMPLETE. Verify that each checklist item has
been covered.
1. The COMPUTER DAQ SYSTEM (data acquisition computer) should be turned ON. This allows
the computer adequate time to initialize prior to data collection. Make sure the computer is
connected via USB cable to the DigiDAQ system receptacle on the left side panel of the Rank-
ineCycler prior to turning the computer ON or the DAQ Module hardware/software may not
properly initialize.
3. A FUEL LEAK CHECK must be COMPLETED prior to proceeding further. A “hissing” gas
sound and/or gaseous odor (characterized as “rotten eggs”) will indicate that there is a problem
with the fuel supply connection to the RankineCycler. IMMEDIATELY shut the FUEL SOURCE
OFF. DO NOT proceed further until the source of the gas leak can be determined and rectified.
4. Turn the RankineCycle OPERATOR PANEL GAS VALVE to ON. This permits the flow of fuel
to the fuel control system.
36 SECTION 4
5. Select the MASTER SWITCH to the ON position. Verify illumination of the GREEN panel light.
Electrical power is now available to the system and the controls.
6. Select the BURNER SWITCH to the ON position. Verify illumination of the RED panel light.
Electrical power is now available to the combustion blower.
7. Observe the COMBUSTION BLOWER and VERIFY ON. The COMBUSTION BLOWER motor
will begin to rotate, drawing air into the burner and forcing it through the boiler.
9. VERIFY that the BURNER has LIT within 45 SECONDS of selecting the BURNER switch to the
ON position. It should be noted that the burner may occasionally “burp” - producing an audible
popping noise with a small blue flame present at the blower inlet. This behavior is normal and
should NOT be considered a fire requiring the execution of the fire abnormal procedures.
10. Monitor BOILER PRESSURE. VERIFY POSITIVE PRESSURE within 3 MINUTES from
BURNER start. If there is no positive indication of boiler pressure within three minutes of
starting the BURNER, select the BURNER switch to OFF and investigate. Verify that the
proper amount of water is in the boiler and the STEAM ADMISSION VALVE is fully CLOSED.
When ready to proceed, start with Step 9 above.
11. The system should now be PREHEATED. This allows the steam lines, valves and turbine to come
up to the proper operating temperature. The turbine bearings are also lubricated at this time.
During the preheating period, small vapor leaks and condensation droplets may be seen around
the turbine and related fittings. This is normal and should subside once the turbine bearing
clearances close due to thermal expansion. The preheating process outlined below should take
approximately 7 to 10 minutes to complete. This preheating process is essential to supplying
the highest quality steam available to the turbine. If preheating is omitted, condensation will
form in the steam lines degrading system performance overall.
a. Allow the indicated BOILER PRESSURE to rise to approximately 110 psi (758 kPa).
b. The STEAM ADMISSION VALVE should be turned counter-clockwise to OPEN. This will
allow steam to flow throughout the system. The turbine/generator may or may not rotate
at this point.
c. Monitor BOILER PRESSURE until it falls to approximately 40 psi (276 kPa).
d. The STEAM ADMISSION VALVE should be turned clockwise to CLOSE. This will stop the
flow of steam throughout the system and allow the boiler pressure to build again.
e. Allow the indicated BOILER PRESSURE to rise to approximately 110 psi (758 kPa).
f. The STEAM ADMISSION VALVE should be turned counter-clockwise to OPEN. This will
allow steam to flow throughout the system. The turbine/generator may or may not rotate
at this point.
g. Monitor BOILER PRESSURE until it falls to approximately 40 psi (276 kPa).
h. The STEAM ADMISSION VALVE should be turned clockwise to CLOSE. This will stop the
flow of steam throughout the system and allow the boiler pressure to build again.
i. Allow the indicated BOILER PRESSURE to rise to approximately 110 psi (758 kPa).
NORMAL PROCEDURES 37
12. While maintaining approximately 110 psi (758 kPa) of BOILER PRESSURE, the STEAM ADMIS-
SION VALVE should be OPENED slowly. The rate at which the STEAM ADMISSION VALVE
is OPENED should be just enough to maintain 110 psi (758 kPa) of BOILER PRESSURE and
to counter any tendency for the BOILER PRESSURE to increase beyond this value. Once the
turbine begins to rotate, the generator will produce electricity. Generator output will be directly
indicated on the VOLT METER.
13. Continue opening the STEAM ADMISSION VALVE until the VOLT METER shows an approximate
FULL SCALE DEFLECTION or an indicated 15.0 Volts.
14. The LOAD SWITCH should be selected to ON.
15. The LOAD RHEOSTAT should be ADJUSTED to MAINTAIN:
16. A BOILER PRESSURE of approximately 110 psi (758 kPa). This is nothing more than a
starting point and the operator should not spend a great deal of time trying to achieve these
values exactly.
17. In preparation of an experimental data run, the STEAM ADMISSION VALVE and the LOAD
RHEOSTAT may now be adjusted to achieve a STEADY STATE CONDITION. Satisfactory run-
time results can be achieved with the following STEADY STATE values:
18. To begin an experimental run, the TIME should be NOTED. This allows a steam rate calculation
to be made at the conclusion of the experimental run.
19. SET the SIGHT GLASS UPPER BEZEL to the current, indicated WATER LEVEL. This allows
measurement of the boiler water consumed during the experimental run.
20. Use the STEAM ADMISSION VALVE to make PERIODIC ADJUSTMENT maintaining the
STEADY STATE established in Step 17.
21. Allow time to CONDUCT THE EXPERIMENT AS REQUIRED. Once the STEADY STATE has
been achieved, this is usually nothing more than collecting an appropriate amount of data
with the DAQ system for later analysis. While CONDUCTING THE EXPERIMENT, MONITOR
WATER LEVEL in the BOILER using the SIGHT GLASS. The WATER LEVEL must NOT fall
to LESS THAN 1.0 in (2.5 cm) FROM BOTTOM OF SIGHT GLASS. Serious BOILER or
BURNER damage may result if the BOILER is allowed to run out of water. At the conclusion of
the experiment, or should the WATER LEVEL fall below the lower limit, proceed immediately
to the SHUTDOWN checklist, Section 4.1.4.
Momentarily moving the mouse pointer over a button will reveal the name of that button.
38 SECTION 4
1. From Windows, Open the PersonalDaqView software by double-clicking on the pDaqView short-
cut icon in the RankineCycler folder located on the Windows Desktop. PersonalDaqView will
start with the Main Control Window and Channel Configuration Window displayed.
NOTE: The computer must be connected to the RankineCycler USB port prior to opening
the PersonalDaqView software. The RankineCycler configuration software is dependent upon
the specific DAQ Module serial number as installed in the RankineCycler and will not function
properly if the DAQ Module cannot be found. Exit the program, attach the USB cable and start
over with Step 1 above. To verify that the software is communicating with the DAQ Module,
select View from the Main Control Window and select Active Devices... on the drop down
menu. Verify that a check appears in the check box next to the appropriate device name.
Generally, two device names will be present. A name specific to the DAQ Module installed
(with a corresponding serial number) and a generic name such as PD1 representing a Simulated
DAQ Module.
2. To record data to disk, select the Arm Trigger for Disk Recording button. This but-
ton appears as a play button with a red record indicator on it. Data acquisition be-
gins and data is stored to a disk file as indicated in the Data Destination Window.
The default destination, including the default file name of PDAQ.BIN is C:\Program
Files\pDaqView\Applications\DATA\PDAQ.BIN. A different location and/or file name may be
selected in the Data Destination Window. Step 2 may be skipped if recorded data is not
necessary.
3. Start sampling real time data by pushing the play button - Enable Readings Column, within
the Channel Configuration Window. Measured values are then displayed in the Reading column.
4. With the system sampling and displaying measured data, scrolling charts, bar graph, analog or
digital meters may be displayed for any of the various channels as deemed appropriate for the
type of data being collected. Select the appropriate button on the Main Control Window for
the type of chart, graph or meter desired.
5. To change any setting within the Channel Configuration Window, it is first necessary to push the
stop button - Disable Readings Column, within the Channel Configuration Window. Make the
changes as necessary, then repeat Step 3. Chart, graph and meter formatting may be changed
by left, right or double clicking in the chart, graph or meter area. In some cases, it may be
necessary to push the stop button - Disable Readings Column, to make changes to the chart,
graph or meter. Repeating Step 3 resumes the display of measured values. It may also be
necessary to push the play button on individual charts, graphs or meters if changes were made
to those independently.
6. At the conclusion of the data run, deselect the Arm Trigger for Disk Recording button. The
specific file saved during the data run must immediately be copied out of the present directory
and/or renamed. Attempting to take additionally data will overwrite the current file resulting
in the loss of that data. Read all dialog boxes that appear on the screen and understand the
result of any action selected.
4.2.4 SHUTDOWN
The SHUTDOWN checklists ceases RankineCycler operation and places the system into a known,
safe condition.
NORMAL PROCEDURES 39
1. At the conclusion of the experimental run, the TIME should be NOTED for a steam rate calcu-
lation.
3. SET the SIGHT GLASS LOWER BEZEL to the current, indicated WATER LEVEL. This allows
measurement of the boiler water consumed during the experimental run.
4. Select the BURNER SWITCH to OFF. Verify that the RED light is extinguished indicating that
no electrical power is available at the burner or the blower. The blower should immediately stop
rotating.
8. The MASTER SWITCH should be selected OFF. Verify that the GREEN light is extinguished.
9. The STEAM ADMISSION VALVE should be turned to the fully OPEN position. This relieves all
remaining boiler pressure.
4.2.5 MEASUREMENTS
1. To Measure Condensate Collected
the internal valve and allow water to flow into the boiler. Open the beaker ball valve to
allow water to fill the boiler. When the SIGHT GLASS water level reaches that marked by
the SIGHT GLASS UPPER BEZEL, close the beaker ball valve and remove the aluminum
coupler from the fill/drain valve.
d. Empty the fill beaker assembly of any water remaining from Item (c) above. Using the
fill beaker assembly, DRAIN the BOILER TO SIGHT GLASS LOWER BEZEL level. The
total volume of water drained into the fill beaker assembly represent the volume of water
converted into steam and consumed during the experimental run. Place the beaker on
a firm support lower than the boiler fill/drain valve at the rear of the boiler. Insert the
aluminum coupler at the end of the beaker hose assembly into the fill/drain valve coupling
hole. Firmly pressing the coupler into the fill/drain valve will open the internal valve and
allow water to flow out of the boiler. Open the beaker ball valve to allow water to drain
into the beaker. When the SIGHT GLASS water level reaches that marked by the SIGHT
GLASS LOWER BEZEL, close the beaker ball valve and remove the aluminum coupler
from the fill/drain valve.
e. The total amount of water now in the beaker represents the total amount of BOILER
WATER used during the steady state portion of the run. RECORD VOLUME.
f. STOW MEASUREMENT EQUIPMENT.
4.2.6 STORAGE
The STORAGE checklist prepares the system for an extended period of non-use. This can be anywhere
from overnight to several months. In general, the system needs to be cool, clean and fully drained
before being placed into storage. If the system is it be used within the same day, the STORAGE
checklist may be omitted. Resume operation with the PRE-START checklists.
1. The COMPUTER DAQ SYSTEM (data acquisition computer) should be turned OFF, the USB
CABLE DISCONNECTED from the DigiDAQ system receptacle on the side panel of the Rank-
ineCycler and all COMPUTER DAQ SYSTEM components STOWED for safe keeping.
5. KEYED MASTER SWITCH to the OFF position. The MASTER SWITCH KEYS should be re-
moved and stored in a secure location.
8. FUEL SOURCE should be DISCONNECTED from the barbed fitting underneath the system.
The hose assembly should be STOWED.
9. ELECTRICAL SERVICE to the system should be DISCONNECTED and the CORD STOWED.
10. STEAM ADMISSION VALVE to the fully OPEN position. This vents the system and allows the
boiler to be completely drained.
11. For safety and before proceeding further, INSURE EQUIPMENT HAS SUITABLY COOLED FOR
HANDLING and THERE IS NO BOILER PRESSURE.
NORMAL PROCEDURES 41
12. The BOILER should be DRAINED completely. The BOILER can be quickly drained using the
fill/drain valve and beaker assembly. Place the beaker on a firm support lower than the boiler
fill/drain valve at the rear of the boiler. Insert the aluminum coupler at the end of the beaker hose
assembly into the fill/drain valve coupling hole. Firmly pressing the coupler into the fill/drain
valve will open the internal valve and allow water to flow out of the boiler. Open the beaker ball
valve to allow water to drain into the beaker. When it appears that no more water is draining
from the boiler, close the beaker ball valve and remove the aluminum coupler from the fill/drain
valve. The water collected from this draining operation may be discarded.
13. For protection, the FRONT and REAR BOILER DOORS should be CLOSED and LATCHED.
15. COMPLETE a FINAL CHECK of the system. Clean any accumulated dirt, oil or water from
the top surfaces as well as the individual components and operator panel. If the system is to
be stored for an extended period of time, breathable covering material such as a cotton sheet
should be placed over the system to prevent the accumulation of dust or dirt in the condenser
tower and boiler chimney.
16. The RankineCycler should be stored in a SECURED place. For long-term storage, the original
shipping container should be used for security and protection.
42 SECTION 4
• DO NOT operate the RankineCycler without first becoming familiar with the Operator’s
Manual.
• DO NOT operate the system unattended.
• DO NOT touch any surface during operation.
• DO NOT move the system while operating or when the boiler is pressurized.
• DO NOT allow the boiler water level to become less than 1.0 in (2.5 cm) as indicated on the
sight glass.
• DO NOT attempt to fill the boiler while the system is pressurized.
• DO NOT open the boiler doors while hot, doing so may cause permanent warp-age of the boiler
cradle.
• DO NOT exceed scale readings/limitations on any instrument or gauge.
• DO NOT tighten or adjust fittings while system is under pressure.
• DO NOT tap on or scratch boiler sight glass.
Section 5
Systems
5.1.1 Burner
A forced air gas burner provides the necessary energy to vaporize the liquid working fluid as it passes
through the boiler. The burner converts chemical energy in the form of gaseous fuel into heat energy
that the boiler can use.
An electrically driven centrifugal blower provides combustion air to the burner through a blower
duct. A fuel line is routed through this duct, delivering fuel to a gas mixing nozzle. The fuel and air
are further mixed by a vortex disk that introduces turbulence to the flow. Factory calibration of the
blower fan optimizes the mass flow rate of air for clean, efficient gas combustion.
Ignition and subsequent combustion of the fuel and air mixture takes place downstream of the
vortex dis within the primary flame tube of the boiler. A “hot surface” igniter located in the rear
boiler door and at the end of the primary flame tube provides the ignition source. The igniter is a
resistance element that glows when current is applied to it. The fuel and air mixture combusts when
it comes in contact with this glowing element producing a flame confined within the primary flame
tube. Once combustion commences, the flame is self sustaining and the igniter will shut off.
A flame sensor located within the blower duct and adjacent to the vortex disk monitors the
presence of the flame and provides feedback to the microprocessor based gas and ignition control
module. Operationally, the control module is designed to energize the gas valve and igniter through
the feedback loop. The system is a positive shut off design that locks out the gas valve if the burner
does not light within a four second ignition period.
Blower operation commences when the BURNER switch is selected ON. A red panel light illumi-
nates indicating that the switch is on and that power is available to the blower and the gas control
module. The blower starts and begins providing combustion air. The gas control module commands
the gas valve into a purge condition and then energizes the igniter for a period of 45 seconds. If the
burner lights as detected through the flame sensor, the control module will continue energizing the gas
valve as needed to maintain heat for the boiler. If the boiler does not light, it will repeat the process
in a second attempt to light the burner. If this second attempt fails, the gas valve will be deenergized
to prevent any further flow of gas. The system will then lock itself out as a safety precaution. The
system can only be reset by cycling the BURNER switch.
A boiler pressure transducer regulates a preset boiler pressure by cycling the burner on and off
(through the gas control module).
43
44 SECTION 5
A bi-metallic, self resetting switch on the boiler prevents the occurrence of high-temperature boil
over by opening the burner circuit should a preset temperature be exceeded.
The burner is attached to the forward boiler door via a flanged fitting on the blower duct. The
blower duct extends an additional length into the boiler and mates with the primary flame tube. A
positive seal between the blower duct and the primary flame tube is achieved through the flame seal
ring.
5.1.2 Boiler
The boiler facilitates the vaporization of the system working fluid, making it available to the turbine
for power extraction. All boilers provide for some manner of heat transfer between the heat source
and the system working fluid. The RankineCycler utilizes a firetube or shell type boiler arrangement
which is representative of over 80% of all boiler systems in use today.
The shell of the boiler is an 8 in (20.3 cm) diameter by 11.5 in (29.2 cm) long stainless steel
cylinder. The cylinder holds both the working fluid of the system as well as the high-pressure vapor
prior to it exiting to the turbine.
To allow heat transfer, 17 0.5 in diameter (1.3 cm) tubes pass through the cylinder allowing hot
combustion gasses from the burner to “flow through” the boiler. Five of these boiler tubes lie above
the full water line. A primary flame tube 2 in (5.1 cm) in diameter also passes through the boiler
and holds the flame produced by the burner. The walls of the 17 tubes and the primary flame tube
provide nearly 380 in2 (2,451.6 cm2 ) of surface area for heat transfer.
Positive pressure provided by both the blower and the expansion of the combustion gasses moves
the hot air through and out of the primary flame tube. The rear boiler door then ducts this air
to the 17 through tubes. The combined volume of the 17 through tubes is just under that of the
primary flame tube, insuring an even air flow with maximum surface area contact. The hot air exits
the through tubes and is ducted by the front boiler door through a vertical stack, exhausting the
combustion gasses up and away from the boiler.
Both the front and rear boiler doors are hinged. Latches secure the doors in the closed position
while the system is operating. When the system is not operating and sufficiently cool, the doors may
be unlatched and opened for viewing. The general arrangement of the through tubes and the primary
flame tube can be seen. The rear door holds the hot surface gas igniter while the front door holds
the blower unit and the exhaust stack. All of these components are plainly visible while the doors
are open. In addition, each door is insulated and contains a refractory material to aid in the proper
and efficient transfer of heat. For optimum performance, the hot surface gas igniter should not be
touched.
Integral to the boiler’s construction are five threaded bosses. These bosses provide a way “in” or
“out” of the boiler. They are as follows:
1. Steam Dome Discharge Fitting This fitting allows the vaporized working fluid to exit the
boiler and ultimately be used for useful work. This fitting discharges to the boiler pressure gauge
and then the turbine through the steam admission valve.
3. Sight Glass Supply Fitting This fitting supplies the sight glass to indicate the relative level
of water in the boiler.
4. Sight Glass Vent Line / Overpressure Poppet Valve Fitting The sight glass is vented
through this fitting back into the boiler. An overpressure safety valve is also located at this
fitting. Should the boiler pressure exceed 130 psi (896 kPa), this valve will open, relieving boiler
pressure.
SYSTEMS 45
5. Fill/Drain Valve Fitting This fitting, located on the bottom of the boiler is attached to a
fill/drain valve that allows the filling and draining of the system working fluid.
The entire boiler shell is insulated with a ceramic blanket to stem heat loss through the boiler
wall. An external mantle protects this insulation from damage.
5.1.7 Generator
The generator utilizes the rotational motion of the turbine to produce electrical energy. A four-pole,
permanent magnet, brushless design, the generator is directly coupled to the output shaft of the
turbine and supported on its own set of preloaded ball bearings.
Both alternating current (AC) and direct current (DC) are available at the generator outputs.
The AC is as generated, while the DC is produced after having passed through a diode rectifier. No
filtering, ripple suppression or voltage regulation is provided following rectification.
1. Keyed Master Switch The key lockable system master switch controls the supply of electrical
power to the main bus that powers the indicator lights, boiler combustion boiler and the gas
control module. When selected ON, power is available to this main bus. A GREEN indicator
light will illuminate when this switch is selected ON and power is available to the main bus.
The separate steam generator bus is not controlled by this switch.
2. Burner Switch The burner switch enables the gas control module and powers the burner
blower. A RED indicator light will illuminate when this switch is selected ON and power is
available to the burner circuits. The burner switch only works if the keyed master switch is
selected on.
3. Load Switch The load switch enables the load bank. The load bank presents a true load to
the generator, allowing the operator to simulate conditions at a full scale power station when
consumer demand fluctuates.
4. Load Rheostat Control The load rheostat control varies the amount of load presented to the
generator. The generator sees this as a true electrical load quantified in terms of resistance,
measured in Ohms - Ω. The full counter-clockwise position of the control represents NO LOAD.
The full clockwise position of the control represents FULL LOAD. The range of control is linearly
variable, with NO LOAD equal to 0 Ω and FULL LOAD equal to 100 Ω.
5. Operator Panel Gas Valve The operator panel gas valve regulates the flow of gas to the on
board gas regulator. The burner controller modulates this gas valve internally to provide gaseous
fuel to the burner. Rotating the black gas valve knob counter-clockwise to the 3 o’clock position
OPENS the valve. Rotating the valve knob clockwise to the 6 o’clock position CLOSES the
valve and prevents any flow of gas through the regulator. The two valve positions are marked
on the face of the regulator near the black gas valve knob. The valve has spring locking detents
that indicate when the valve is properly positioned in either the open or closed positions.
SYSTEMS 47
6. Amp Meter The amp meter indicates the amount of current the load is drawing based upon
the load (as set by the Load Rheostat Control) and the available voltage (as provided by the
generator - a function of generator speed/RPM).
7. Volt Meter The volt meter indicate the amount of voltage the generator is providing (a function
of generator speed/RPM).
5.3.1 Computer
The RankineCycler is typically provided with a Microsoft Windows XP Professional based laptop
computer for portability and system security. Final factory sensor settings are saved to this computer
as well as a standard user interface display for initial system familiarization and data collection runs.
The computer is equipped with a writable CD-ROM and Ethernet interface to facilitate run-time data
dissemination.
For maximum flexibility, the system is designed to work with any Windows XP Professional com-
puter equipped with a standard Universal Serial Bus (USB).
The integrated USB connection allows a single cable interface of up to 16 feet (5 meters) between
the RankineCycler and the data acquisition computer. This distance is easily increased up to 98 feet
(30 meters) through the use of powered USB hubs (serving as data repeaters). The USB’s high-speed
data transfer rate (up to 12Mbits/s) allows for a real-time display of acquired data, while eliminating
the need for buffer memory in the data acquisition system itself.
Unused data channels are available for operator use. With sensors or transducers appropriate to
the variables of interests, interface to the DAQ Module is accomplished through convenient, removable
screw-terminal input connections. Optionally available snap-on expansion DAQ Modules increase the
total channel capacity to 60 analog or thermocouple channels, 32 digital I/O lines and four frequency
input channels. USB hubs used in conjunction with multiple DAQ Modules can further increase the
available channel count to over 8,000 - enough for any conceivable data acquisition need.
5.3.3 Sensors
Ten (10) system parameters are sensor measured with the stock RankineCycler configuration.
The basic sensor package includes pressure, temperature and flow sensors measuring parameters
common to Rankine Cycle type analysis. The following list details the measured system parameters
and their corresponding physical DAQ Module channel. Table 5.2 provides more detailed information
concerning channel assignments, installed sensor or transducer type and a listing of all open and
available DAQ Module channels.
1. Boiler Pressure (physical analog channel PD1 A01) - Boiler vapor pressure.
2. Steam Turbine Inlet Pressure (physical analog input channel PD1 A02) - Turbine vapor
pressure immediately prior to the turbine.
3. Steam Turbine Outlet Pressure (physical analog input channel PD1 A03) - Turbine vapor
pressure immediately after the turbine.
4. Boiler Pressure (physical analog input channel PD1 A04) - Boiler vapor pressure.
5. Steam Turbine Inlet Temperature (physical analog input channel PD1 A05) - Turbine vapor
temperature immediately prior to the turbine.
6. Steam Turbine Outlet Pressure (physical analog input channel PD1 A06) - Turbine vapor
pressure immediately after the turbine.
7. Generator Current (Amperage) Output (physical analog input channel PD1 A07) - Gen-
erator current output, should correspond to operator panel meter readout.
8. Generator Voltage Output (physical analog input channel PD1 A08) - Generator voltage
output, should correspond to operator panel meter readout.
9. Fuel Flow (physical analog input channel PD1 A09) - Turbine-based gas flow meter measures
the volume of gaseous fuel flowing per unit time.
10. Turbine/Generator RPM (physical analog input channel PD1 A10) - Turbine/Generator
rotational speed (in revolutions per minute, RPM) derived from measuring the voltage of the
direct current output voltage as provided by the rotating generator. Generated DC voltage is a
direct function of generator speed/RPM.
SYSTEMS 49
NOTE: These values represent the default Channel Configuration as set by the factory and should provide satisfactory performance under normal
conditions. Scale and Offset values may be changed if recalibration or other engineering units are required. Entering a Scale value of 1.0 and
an Offset value of 0.0 on any channel results in the display of raw voltage in the Reading column for that channel. Scale and Offset values are
derived from the linear mx + b transfer function for each sensor relative to the appropriate physical range and voltage output as provided in Table 5.2
(PhysicalValue = Scale · Voltage + Offset). The Reading column will only be populated when the data acquisition system is sampling data. It has
been omitted from this table for clarity. Chapter 4 of the PersonalDaq UsersManual .pdf contains further information on the Channel Configuration
Window.
SECTION 5
SYSTEMS 51
5.3.4 Software
The DigiDAQ System utilizes IOtech’s Personal DaqView software for Out-of-the-Box graphical data
acquisition. This software provides an easy-to-use yet powerful data acquisition application that allows
inexperienced users to test, display and record data within minutes of power-up while requiring no
programming. The software works seamlessly with the IOtech Personal Daq/56 USB Data Acquisition
Module installed in the RankineCycler. Individual channel configuration is accomplished through a
spreadsheet type interface. Each channel can be enabled, configured and labeled independently of
all other channels. Sensor output is converted into physical, engineering terms by applying Scale
and Offset values in an mX + b operation. The software allows the creation of customized real-time
displays using built-in display options including charts, graphs and meters. Each display option can
be independently configured by channel to show instantaneous values, peak hold and trends. All
displayed data is easily recorded for later play-back and follow-on analysis. Post-acquisition software
is also included to facilitate time-domain data viewing of multiple channels. Additional software to
enable real-time data acquisition from within Microsoft Excel is also available.
The DigiDAQ System is designed to work with other popular software packages including IOtech’s
DASYLab and National Instrument’s LabVIEW. With the appropriate software, advanced data ac-
quisition, control and virtual instruments (VI) may be utilized with the installed DigiDAQ System in
the RankineCycler. Application Programming Interface (API) code, documentation and drivers for
Visual Basic and C++ for Windows are freely available at the IOtech website.
5.4 Cabinetry
5.4.1 Chassis
The RankineCycler cabinetry is purpose built. Laser cut for precision and powder coated for long
lasting durability.
5.4.2 Electrical
Standard outlet service of 120 VAC, 60 Hz (220 VAC, 50 Hz) is the only electrical service necessary to
operate the RankineCycler. Gas regulation and control and the DigiDAQ system electrical require-
ments are served internally. No additional external electrical service is required. Computer equipment
or additional operator provided sensors, meters or instrumentation will necessarily require their own
electrical service as appropriate to the specific equipment used.
5.4.3 Fuel
Fuel is supplied to the RankineCycler through an external source, usually a standard Liquid Propane
(LP) bottle typical of the type used for gas grills and portable heating equipment. A fuel source gas
regulator and hose assembly is provided with the RankineCycler to make the connection between the
fuel source and the on board gas regulator. The provided fuel source gas regulator and hose assembly
are specially calibrated and adjusted to work with each RankineCycler. Any adjustment to this
regulator or deviation from the recommended fuel may result in poor system performance. Turbine
Technologies, LTD should be consulted if any changes are necessary due to local fuel availability.
A barbed fitting on the bottom of the RankineCycler provides a convenient and quick method of
attaching the fuel source gas regulator and hose assembly to the on board gas regulator.
5.4.4 Miscellaneous
The RankineCycler cabinetry is fitted with lockable caster wheels to facilitate movement of the system
for use and storage.
52 SECTION 5
Section 6
Service and Maintenance
6.1.1 Cleaning
Keeping the RankineCycler clean and free from dirt, oil and water accumulation is the best way to
maximize the usefulness and efficiency of the system. Typical household, non-flammable and non-
abrasive cleaners may be used where appropriate. Non-toxic, biodegradable, “green” or “citrus” type
concentrated cleaners are particularly well suited for cleaning the RankineCycler where mineral or
dirt buildup may occur.
Boiler Periodically flushing with clean, distilled water (fill and empty per normal procedures without
heating the boiler) will help prevent mineral build up and accumulation. Pay particular attention
to the fill/drain valve area. As this is the lowest point in the system, sediment may collect in
and around the fill/drain valve. Rapid opening and closing of the fill/drain valve by inserting
and removing the aluminum coupler will help dislodge sediment and insure the fill/drain valve
remains clean. DO NOT use any type of cleaner, soap or solvent when flushing the boiler.
Condenser Tower The condenser tower, over time, may acquire a thin film of mineral buildup on
the internal mantle and baffle surfaces depending upon local water conditions. A mild cleaner
dilution works well to remove this buildup.
Cabinetry All cabinet surfaces are electrostatically powder coated for maximum surface durability.
Mild soap and water should be sufficient for most cleaning needs.
Other Components All system components are manufactured of materials that provide sufficient
resistance to corrosion under normal usage. Mild soap and water should be sufficient for most
cleaning needs. Care should be taken to minimize any water or cleaning solution contact with
the generator assembly, particularly the coupling area between the turbine and the generator.
Water or cleaning solution usage should be the minimal amount necessary to prevent contact
with the wiring or electrical equipment within the system cabinetry.
53
54 SECTION 6
or after extended running periods, it is advisable to conduct a more thorough inspection of the entire
system to insure safety and reliability.
The following points provide a minimal checklist for a periodic Condition Inspection:
1. Cleanliness Keeping the system clean and free from dust and dirt, mineral buildup and water
will help in readily identifying problems. A regular cleaning helps the operator become more
familiar with the general arrangement of components and aware when things aren’t as they
should be.
2. Security of Fittings Ensuring all nuts, bolts, couplings and other areas where two components
are physically attached are tight and secure will prevent future problems stemming from leakage
or wear.
3. Proper Operation Simply monitoring the RankineCycler for operation consistent with the
manual will assist in determining if greater problems are imminent.
4. Boiler Door Gaskets The boiler doors are sealed with a fiberglass gasket material. Over time,
the material will degrade and begin to pull apart. This is normal. When the condition of the
door gaskets is such that it no longer appears to be sealing or appears to be rapidly deteriorating,
it should be replaced. The material is commonly available at fireplace or plumbing dealers as
well as most industrial supply companies. New gasket material should be positively attached to
the boiler door using high temperature stove and gasket cement or similar material.
Exercising common sense is the best action to follow. If something doesn’t “look” or “act” right,
there may be a problem. Usage should be delayed until the potential problem can be investigated
and rectified. Always err on the side of caution. This protects the user as well as the machine. The
RankineCycler should be afforded the same respect in operation, maintenance and overall care given
to any piece of laboratory grade equipment.
The design of the RankineCycler eliminates all periodic or reoccurring maintenance outside of that
specifically listed in Section 6.
SERVICE and MAINTENANCE 55
6.2 Troubleshooting
Troubleshooting information is provided to identify and provide solutions to common operator prob-
lems. These problems usually arise from not following the Normal Procedures in their proper order.
Use of the included checklists will eliminate the possibility that a necessary step is overlooked or
executed out of sequence (see Section 4 - Normal Procedures). Review the checklist steps prior
to consulting the Troubleshooting tables.
Problems that relate directly to RankineCycler hardware, such as a failed or damaged component,
should be directed to the factory for immediate attention. Readily diagnosed problems arising from
loose or broken electrical wires, loose fluid fittings and no or low fuel pressure are generally deferred
to the operator for troubleshooting and repair.
Data acquisition hardware and software usage and troubleshooting is covered in greater detail
within the provided users manuals. See PersonalDaq UsersManual.pdf and PostAcquisition-
Analysis.pdf within the C:\Program Files\pDaqView\Applications\Users Manuals directory of
the default DAQ software installation.
Operator modifications may adversely effect the overall operation of the system and may prevent
the following troubleshooting steps from being effective.
BOILER FILL/DRAIN
TROUBLE PROBABLE CAUSE REMEDY
Boiler will not drain. Fill/drain valve is not open or sys- Insert the aluminum fill/drain cou-
tem is under vacuum. pler fully into the boiler fill/drain
valve. Turn the steam admis-
sion valve fully counter-clockwise
to open the valve and vent the sys-
tem.
Boiler will not fill. System is under pressure or the Turn the steam admission valve
fill/drain valve is not open. fully counter-clockwise to open the
valve and vent the system. In-
sert the aluminum fill/drain cou-
pler fully into the boiler fill/drain
valve.
Boiler will not accept a full 203 oz Boiler was not previously drained. Insure that the boiler was properly
(6,000 ml) of water. drained prior to filling.
Fill/drain valve does not open. Boiler under pressure. Relieve boiler pressure. Allow sys-
Cannot insert aluminum fill/drain tem to cool before attempting to
coupler. fill.
56 SECTION 6
BURNER OPERATION
TROUBLE PROBABLE CAUSE REMEDY
System does not indicate power up No electrical service to system. Verify that electrical service is
when MASTER SWITCH is se- available to the system. Check line
lected ON. power cord is plugged into wall.
Check that all applicable circuit
breakers and other protection de-
vices have not been tripped.
Burner does not light when Inadequate fuel supply or air in the Verify that the fuel source is prop-
BURNER SWITCH is selected to fuel lines. erly attached to the unit. Prop-
ON. erly purge the fuel lines per the
Expanded Normal Procedures sec-
tion.
Burner lights but operates rough, Improper fuel to air mixture. If fuel source gas bottle was stored
rapidly extinguishing and relight- outside, allow it to warm to room
ing. temperature and try again. Verify
that there are no leaks in the gas
line. Consult factory for instruc-
tions on adjusting the blower fan
speed.
GENERAL OPERATION
TROUBLE PROBABLE CAUSE REMEDY
Boiler does not come up to pres- Steam admission valve not fully Verify that the steam admission
sure. closed. valve is fully closed and that there
are no leaks in the steam tubing to
or from the turbine.
Cannot achieve steady state. Improper preheat. Load rheostat The system must be properly pre-
set too high. heated before a steady state can
be achieved. Steady state will be
difficult to achieve if there is too
much initial load on the generator.
Turn down the load rheostat.
Turbine squeals during operation. Turbine speed is too high. Reduce turbine speed by closing
steam admission valve and/or in-
creasing generator load through
the load rheostat.
SERVICE and MAINTENANCE 57
DATA COLLECTION
TROUBLE PROBABLE CAUSE REMEDY
Computer wont recognize DAQ USB cable not plugged in. Specific Make sure USB cable is con-
Module. device not selected. nected between the computer and
the DigiDAQ USB port on the
left side panel before the software
is started. To select the spe-
cific device, select View from the
Main Control Window and select
Active Devices... on the drop
down menu. Check the box next
to the serial numbered device.
Channel Configuration Window Factory configuration file has been The required configuration
appears blank. All sensor setting erased or overwritten. file is RankineCycler.cfg.
are gone. A backup copy is located in
the RankineCycler folder
on the desktop. COPY
this file to the DAQ Sys-
tem directory: C:\Program
Files\pDaqView\Applications.
Prior to doing this, make sure
the PersonalDAQ software is
shutdown and the USB cable
is connected. If the backup
RankineCycler.cfg file cannot
be found, a new configuration file
can be created by manually en-
tering the settings from Table 5.3
and Table ??. Charts, graphs and
meters will have to be re-created.
Run-time data doesn’t appear to Run-time data is getting over- All run-time data is saved as
be saving. written. PDAQ.BIN. Immediately after col-
lecting data, copy and rename
PDAQ.BIN to another location. It
will be necessary to first convert
this binary data file to a usable file
format such as text which is then
readable by Microsoft Excel and
other programs. To do so, from
within the Main Control Window,
select Tools and then Convert
Binary Data... from the drop
down menu.
58 SECTION 6
RANKINECYCLER WARRANTY
Two Year Warranty
Turbine Technologies, LTD warrants each RankineCycler, of its manufacture, to be free of defects in
materials and workmanship at time of shipment and to remain in serviceable condition for a period
of two years (24 calendar months) following date of shipment.
In the event of malfunction or failure, purchaser may, at its expense, return the RankineCycler
to Turbine Technologies, LTD for inspection. If, in the sole discretion of Turbine Technologies, LTD,
the malfunction or failure resulted from a defect in materials or workmanship, Turbine Technologies,
LTD will repair or replace any defective component or assembly.
Specific Exceptions
Specific exceptions to the above section include:
1. This warranty will become void if any person has made an attempt, regardless of extent, to repair
or modify the RankineCycler without express written authorization by Turbine Technologies,
LTD.
2. This warranty does not apply to any damage resulting from operation outside the published
operating limitations found in the Operator’s Manual.
3. The RankineCycler is not offered as and shall not be construed by purchaser, or any agent
thereof, as a “Consumer Product” (within the common definition or definitions of the United
States Federal Trade Commission).
4. The RankineCycler is represented to be, and is offered as, experimental technology, subject to
the limitations in performance and safety risks inherent to equipment so classified.
5. The Purchaser and agents thereof shall be solely responsible for determining, prior to purchase,
the suitability for any purpose or purposes intended of equipment, services or information offered
or supplied by Turbine Technologies, LTD.
6. This Limited Warranty, as written, constitutes the entire warranty offered or intended, expressed
or implied, and is offered in lieu of all other warranties.
7. The Limited Warranty does not apply to “on-board” hardware or software items that are covered
by other OEM warranties.
59