Sie sind auf Seite 1von 6

ENGINEERING AND CONSTRUCTION

MANAGING SMALL PROJECTS IS THE ESSENCE


OF ENGINEERING AND CONSTRUCTION
R. ELSHOUT, Energy Systems Engineering, Pasadena, California and D. CARAVAGGIO, Consultant, Newport Beach, California

Refineries and petrochemical com- A typical organizational structure for and profits of the facility. Supplanting
panies execute a wide range of projects. small projects should have minimal layers themselves into design and engineering
These projects may include maintenance to allow a short line of communication be- activities—other than providing direc-
projects, facility upgrades, retrofits and tween the decision-makers (FIG. 1). The tion—is not in the best interest of the
revamps, and debottlenecks. Some proj- characteristics of a small project include: operating company. The operator’s role
ects are done in-house, while others are • Short duration—small projects in small projects should be limited to the
contracted out. Each project requires its tend to have a maximum length definition of the projects, and review-
own approach to ensure efficiency and of 1 yr. This timetable ing the execution of the project by the
cost-effectiveness. requires that procurement selected engineering and construction
Grassroots projects tend to be ex- activities are executed early to (EnC) contractors.
ecuted by large task force teams that are obtain the necessary equipment
only concerned with completing a single onsite when it is needed. Onsite activities. The onsite team needs
major project at a time. Grassroots facil- • Personal characteristics require to gather the following information before
ity builds are mostly a thing of the past, stronger multi-purpose discipline starting work:
as costs and permitting have become pro- leads who keep communication • A 24 hr–72 hr test run,
hibitive. Assembling a team to execute a lines open and the workflow with a closed material
single project is much easier than com- moving through the system. balance approximating the
pleting small projects of various sizes. • The cost of small projects proposed/planned operation
Size, complexity, schedule duration and may range from a few • Process flow diagrams (PFDs),
costs are the determinants in the type of hundred thousand dollars utility flow diagrams (UFDs),
project execution management and team up to $50 MM. up-to-date piping and
that is assembled. Although similar ac- • Project personnel must manage instrumentation diagrams
tivities are performed on both small and multiple activities simultaneously. (P&IDs)
major projects, small projects tend to use • The controls of the project are • Equipment data sheets (must
different resources. much simpler, but it is important include modifications), plot plans,
Small projects use a team of multiple that no activities are missed. elevation drawings (if available)
discipline specialists. Typically, mul- Since multiple projects are • Operation and repair records over
tiple activities must be executed by each completed by the same group, the last 10 yr
team member, who would be working on activities are usually not all in the • Lead operator’s knowledge of
more than one project at any time. The same time reference. limitations—the lead process
team should be multiple-disciplined and engineer should be included in
include: Cost-effectiveness. Cost overruns on these meetings
• Project manager/project engineer small projects as a percentage of individual • Identification of the possible
• Process engineer/mechanical budgets are typically higher. Management tie-in locations.
process engineer control is usually the most common rea-
• Electrical/instrumentation son, but the definition of the project often Offsite activities. First, the records and
engineer changes dramatically from the initial esti- information obtained need to be docu-
• Civil/structural engineer mated scope of work, as well. During proj- mented. This action could be included
• Mechanical engineers who have the ect execution, it is common for the scope as part of the kickoff meeting notes. The
capabilities to design vessels, heat to change. To control costs, firm project owner should be kept aware of engineer-
exchangers, rotating equipment management is crucial. Both the owner’s ing activities, and should be updated peri-
(pumps and compressors) representative and project manager must odically to mitigate rework.
• Piping designer who can also do be disciplined in what gets added to the
plant layouts and pipe routing initial scope, or the project could suffer a A win-win situation. The engineering-
• Cost engineers/cost controls/cost major cost overrun. alliance concept provides better execution
estimating than the previous practice of the owner
• Scheduling/overall controls Forming engineering alliances. The selecting a new contractor for each new
• Purchasing/expediting/inspection operator’s best use of resources is spent project. The engineering-alliance con-
• Constructability coordinator. to maintain the optimum performance cept can be a win-win situation for both

E–52 ENGINEERING AND CONSTRUCTION | MAY 2017 | HydrocarbonProcessing.com


ENGINEERING AND CONSTRUCTION

the owner and the contractor. It is best Base Case heat and material balances then use this package to bid on the proj-
for the contractor to keep a core team of could not be scaled up. The work was ect. This workflow eliminates the three-
dedicated personnel who know what the to determine the limiting capacity, and step approach, and can potentially add
clients’ requirements are and how to meet then perform factor-type (equipment considerable savings to the project’s cost.
the client’s standards. Client needs are cost multiplied by factors) to estimate If we revert to the responsibility ma-
also best served with a project team that the debottleneck cost. Finally, the team trix, the process and project leads start
is dedicated to their long-term objectives. put together a Schedule “A” debottleneck by conducting a kickoff meeting. The
Relationships and trust can be developed package for the detailed engineer/con- project teams will then gather the nec-
between the client and the contractor only structor to bid. essary documents required to execute
when staffing is stable. The client does not the project, and develop a preliminary
want the engineering contractor to use his Responsibility matrix. Ultimately, exe- schedule. The process team takes test-
project as a place to park engineers and cution must be broken down to several run data and processes it through a simu-
designers between other major projects. items as part of the responsibility matrix. lator program to develop the Base Case
Engineering contractors operate with very The activities executed by the different heat and material balance. The process
low overheads. The contractor must keep disciplines are identifiable and quantifi- and equipment engineers use the heat
a dedicated core of personnel. The present able items in the responsibility matrix. and materials balance data to evaluate
contractor staffing policy (to keep over- The project manager can check these the individual equipment items to de-
head low) is to put the engineering staff items as the project progresses through termine which pieces of equipment are
member on leave of absence once they the EPC phase. limiting and how much extra capacity
become unbillable. Regarding the example, three cases is available for expansion. The process
are evaluated and compared to the Base engineers will then establish expansion
PROJECT EXECUTION Case (present operation). The scope cases (e.g., 105% of Base Case, etc.) for
Project execution is the key to a suc- includes performing a cost estimate of an evaluation plan. Next, the process
cessful project. Typically, projects are the three cases and developing a single and equipment engineers will evaluate
undertaken on either an engineering, Schedule “A” design package for a de- the existing equipment and determine
purchasing and construction manage- tailed EnC contractor to execute. which pieces of equipment need to be re-
ment (EPCM) or engineering, procure- This project was executed in parallel placed, modified or supplemented with
ment, construction (EPC) basis. Either with several other ongoing projects by the additional equipment.
way, certain activities must be executed small projects group. The project required The mechanical process team will
in a prescribed sequence. Avoiding re- certain specialists—mechanical special- conduct a hydraulic evaluation to de-
work is the key. Getting it done right the ists for heat exchangers, pumps, furnaces, termine—for the various cases—what
first time is essential to staying within piping, civil/structural, etc.—for short piping needs to be modified and what
budget and schedule. periods of time. The 24-wk bid package pumps can be reutilized. New pumps
The EPCM approach requires the schedule included several “pause” periods may be required in some situations, but
engineering contractor to assemble bid to allow the owner to approve the proj- staying with the same frame size can re-
packages for the construction contractors ect’s approach, for the vendors to bid on use a foundation. Vessel engineers de-
to execute. The better the definition, the equipment, and for the owner to issue bid termine the modifications that may be
better the scope the contractor has to bid. packages to detailed EnC companies. needed, such as new internals, trays, etc.
The EPC approach uses one con- It is believed that using a small-project Original tray suppliers can be very useful
tractor to do both the engineering and manager to conduct the study and devel- in evaluating tray performance, and can
construction work. The EPC contractor op the project is preferred over the final suggest modifications or replacements,
should still provide cost estimates to the engineer/constructor. For example, if the where needed.
owner for approval before starting con- project is bid on a fixed price, the detailed Heat transfer engineers evaluate the
struction. To avoid surprises, accurate engineer can custom-design the scope to requirements of heat exchangers in the
cost estimating is a key activity. When fit the bid package. The constructor can new services. Individual exchangers can
costs exceed the client’s expectations, it
may be necessary to re-engineer parts of
the project to provide a more cost-effec- Licensors Project manager Client’s staff
tive approach that satisfies the owner’s
expectations.
Vendors Support staff
For example, a refinery crude unit
debottlenecking project was executed
as one of many other projects simulta-
Process/mechanical Electrical/ Civil/structural Mechanical Piping/layout Cost engineering
neously. The scope of the project was process lead instrumentation lead lead lead lead lead
to complete a front-end evaluation and
determine how to cost-effectively debot-
tleneck an existing unit. The project was Engineers/designers
based on adding light tight oil (LTO) to
the refinery’s crude mix; therefore, the FIG. 1. Organizational chart for a typical small project.

HYDROCARBON PROCESSING | MAY 2017 | ENGINEERING AND CONSTRUCTION E–53


ENGINEERING AND CONSTRUCTION

be rated again in the new services by the fications on the existing plot plans and “A” debottleneck package. The descrip-
exchanger rating models that are includ- elevation drawings—showing the tie-in tion and job scope, supplemented with
ed. Then, the mechanical process engi- to the existing equipment and preparing all the developed attachments, can be
neer can mark up the existing P&IDs to a tie-in list can be useful at this point. organized into a bid package. The bid
show the modifications required and the Next, a factor cost estimate is prepared package can then be bid on by detailed
new equipment that needs to be added (equipment price multiplied by a factor EnC contractors. With this level of detail
to accommodate the higher capacity to get estimated cost—pump cost multi- provided in the bid package, the bidders’
cases. The plot plan should be marked plied by 4, vessels multiplied by 3, etc.). packages should be comparable on an
to show where new equipment needs to These three estimates (one for each case) apples-to-apples basis.
be added, or where existing equipment are based on prices for the new equip-
needs to be removed, as well. Piping ment and modifications to the existing Turnaround schedules drive the overall
modifications and/or new piping addi- equipment. A conceptual cost estimator schedule. Small projects must be exe-
tions should be marked on the elevation is key to getting a reasonable inside bat- cuted so that they fit into the turnaround
drawings, if available. tery limits (ISBL) cost estimate, with schedule and shutdown period. Refin-
Equipment data sheets—vessels, approximately +50%/–25% accuracy. eries and petrochemical facilities have
drums, distillation columns, etc.—need The outside battery limits (OSBL) cost scheduled turnaround periods, where the
to be marked to show required modifica- equates to a percentage of ISBL costs plant is shut down for a schedule period
tions. New equipment data sheets must (usually a minimum of 50%). OSBL costs to perform maintenance. This period
be prepared and issued to vendors for are associated with things not shown on is ideal for small projects to tie-in their
quotes. The vendor will need sufficient the P&IDs, such as utilities and offsites. modifications.
time to provide an accurate quote. Costs An evaluation of the three cases can Usually, the contractor tries to execute
in the modified specifications sheets now be made to calculate a simple pay- as much work as possible ahead of the
should be estimated by either the vessel out evaluation. The incremental rev- turnaround shutdown. Pre-shutdown
group or by a fabricator. enues—based on gate-product pricing, work consists of:
Once these steps are completed, the utilities and operating labor—are com- • Excavating and pouring
process and project engineers can assem- pared for the three cases vs the operation foundations
ble the full scope of the debottlenecking Base Case (reference case). The selected • Installing equipment on the
project. Piping engineers can mark modi- case can be used to prepare a Schedule foundations

TABLE 1. Gantt chart schedule for the front-end package


Weeks from kickoff meeting

Activity 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

Kickoff meeting
Gather data at the site
Simulate heat/material balances
for Base Case
Evaluate equipment for Base Case
Simulate expansion cases
Check/rate existing equipment
Issue data sheets to vendors
for quotes
Vendor evaluation/quote
PFD markup
Hydraulic calculations
(pumps/compressors)
P&ID markup
Pipe routing and tie-in locations list
Markup of plot plan
Update equipment list
Electrical modifications
Cost estimates for three cases
Economics and selection of final case
Prepare project description/
assemble Schedule “A” package
Issue detailed EnC package to bid

E–54 ENGINEERING AND CONSTRUCTION | MAY 2017 | HydrocarbonProcessing.com


ENGINEERING AND CONSTRUCTION

• Running piping between the ed. Lockout procedures must be followed • Modified PFDs, P&IDs, plot plan
newly installed equipment and double-checked to protect workers. (as built), and piping isometrics
back to the tie-in points Fire concerns are another major safety is- and orthographics
• Running electrical back to the sue. Welding procedures must address the • Tie-in list, and equipment list
electrical tie-in point, which is need to provide isolation from potential showing new and modified
usually an electrical panel or fire situations, including liquid hydrocar- equipment
junction box. The final electrical bons and other combustible materials. • Modified utility drawings,
connection can only be made new/modified equipment data
safely at shutdown. Constructability. During the kickoff sheets, foundation drawings
Equipment and materials must be meeting, spaces available to add new • Revised electrical drawings,
delivered to the construction site in ad- pieces of equipment are determined. How including additions and
vance of when the work is to be complet- will new equipment be transported to the changes (as built)
ed. This schedule allows the pre-turn- proposed site location and installed on • New electrical specifications,
around activities to be completed ahead the foundation? The plot plan and the an equipment list showing
of the shutdown. elevation drawings are useful for this new instrumentation (as built),
In some instances, the turnaround tie- assessment. Typically, there are open along with new instrumentation
ins are completed during the turnaround, spots for new exchangers and pumps, as data sheets.
and the actual completion of the proj- well as open areas in the structure if more This narrative was the beginning of
ect is carried out later. Therefore, tie-in space is required. the project Schedule “A” debottleneck
points need to be identified and stubbed The pipe rack should be evaluated to bid package example that was issued to
in with an isolation block valve, where determine if open lanes for adding new the detailed EnC.
possible. This action requires planning pipe runs are available. Otherwise, an-
to validate that all tie-ins are installed and other level may need to be added to the COMMUNICATIONS
can be connected into the modification pipe rack. Sometimes, extensions on
when they are completed. each side of the pipe rack can be added. Project contract. The contract is where
Once again, piping activities are usu- However, structural engineering must be the rubber meets the road, and it provides
ally the key to meeting the schedule. It is used to evaluate these potentials. an understanding of what the contrac-
essential that someone from the owner’s Utilities, primarily cooling water, tor is expected to ultimately deliver. The
operating group confirms that the tie-in steam and condensate additions, may be contract should be considered a guide-
locations are correct. required. Water coolers at the extreme line. Again, good alliances are based on
end of the cooling water circulation the owner and the contractor working
Safety concerns. Safety is the most impor- system tend to be starved if the cooling together as a team. The development of
tant concern of all refinery and petrochem- water system is overloaded. A booster an adversarial relationship does not facili-
ical projects. A good project can turn bad pump may need to be added to provide tate the work.
with just one accident. Following the own- the additional flow to the new exchang- It is extremely important to have a
er’s project execution manual is essential ers. Steam and condensate systems must project description, an equipment list
during the construction phase. Some of the be evaluated for extra capacity. New, that matches the process flow diagrams,
owner’s requirements include obtaining larger headers may be required. There- P&IDs and equipment data sheets early
construction permits, which requires fill- fore, the OSBL modification costs must in the project.
ing in approval documents in a timely man- be added to the cost estimate. Equipment lists provide the basic
ner so that safety concerns are addressed. A laydown area adjacent to the work equipment titles and numbers. Equip-
Scaffolding design and support con- area should be created to store equip- ment numbering sequences can provide
siderations are a must before construction ment as it comes onsite. Major equip- insight as to how the project is progress-
begins. Safe welding practices, along with ment can be transferred from the deliv- ing. Note: In revamps and debottle-
using the correct welding procedures for ery truck directly to the foundation, if it necks, certain equipment is reused in
the appropriate metallurgy, can prevent is pre-poured and cured. the same service, along with additional
having to redo entire sections of construc- equipment to do more than what the
tion. This rework might have to be done at Project deliverables. Deliverables are original equipment can perform. This
the contractor’s expense due to fault. usually included in all projects. The action requires a number indicating that
Safe-trench supports are required to contractor will provide these in a timely the equipment is new, but in the same
hold back soil (to prevent cave-ins) if manner. It is useful to have the owner service as an existing item.
an underground piping run is to be fab- review these deliverables to confirm that The key to successful and cost-effec-
ricated. Any work below a certain level they are in accordance with the project’s tive revamps in debottlenecks is making
requires supporting the side walls of the execution. Typical small-project deliver- the maximum use of existing equipment.
construction trench. ables include: However, certain equipment may not
Electrical isolation is an area where • A descriptive narrative of the fit the new plan and should be removed
there can be no compromises. The opera- project’s scope from service. It is important for the cost
tions team can best determine how to en- • A printout of the heat and material estimator to be aware of when items are
sure that electrical components are isolat- balance for the final case removed. Frequently, cost estimate over-

HYDROCARBON PROCESSING | MAY 2017 | ENGINEERING AND CONSTRUCTION E–55


ENGINEERING AND CONSTRUCTION

runs occur when an element has not been consider the time requirement in provide sufficient information
identified—e.g., when equipment is dis- procuring equipment. Typically, for a detailed engineering
posed of and not recorded. the procurement schedule contractor to bid on procurement
Another aspect of cost-effective re- requires time for equipment and construction management.
vamps and debottlenecks is to make specifications to be issued, and
maximum reuse of the existing support time for vendors to perform their Project schedule. Project scheduling
in ISBL and OSBL, such as foundations, bids and fabricate and ship the can be performed on many levels. The
electrical supply and utilities. Typically, equipment to the field. simplest is a bar chart that lists all of the
the cost for the OSBL required to sup- • Inter-discipline coordination— activities and shows the approximate time
port a revamp is at least 50% of the ISBL on a project, 20 different range during which each function was
cost. Anything that can be done to mini- disciplines can be involved. performed. However, these charts lack
mize the effect of ISBL modifications on The key to project management the details of how activities relate to other
OSBL modifications, can keep the OSBL is to coordinate the activities activities in the critical path. A typical bar
costs under this figure. between these diverse groups. chart (Gantt chart) is shown in TABLE 1.
Weekly progress meetings are Working back from the date a critical
Project planning. This operation is a held to determine if the necessary piece of equipment must be onsite is one
joint activity between the owner and the information has been exchanged example of defining a critical path activ-
contractor. Planning between the owner so that each of the disciplines can ity. The time to ship to the field and to
and contractor includes: accomplish its requirements. fabricate, the purchasing cycle and final-
• Scope definition. • Documentation of work— izing specifications determines the latest
• Schedule and associated costs. on a periodic basis, the contractor date an engineering specification can be
• Work breakdown structure should document the work completed. On some critical path items
(WBS)—this plan provides the that has been performed. with long delivery times, it is often re-
activities of the project down to Weekly progress reports are quired to issue a specification based on
the level of execution over time essential when certain phases a number of assumptions that will have
periods. of work are completed. to be confirmed during the engineering
• Schedule—it drives the project, • Issuing design packages— phase. Large compressors, heavy wall
and defines the critical path of Schedule “A” packages are one way reactors and alloy heat exchangers are
when various activities should be of providing a preliminary design some of the equipment that fall into this
executed. The critical path must package. This package should category.

Wash water
Offgas to NGL and OPS

Crude
LPG to NGL frac
Sour water to SWS Sour water to SWS
Atmospheric Naphtha
column stabilizer
ATM
naphtha

Kerosine Stabilized naphtha


stripper
Steam
Kerosine
Diesel Vacuum
stripper system
Arabian heavy Wash Steam
crude water Diesel
Preflash
drum HAGO
Cold Desalter
stripper Vacuum
preheat Steam column
exchangers
Desalted HAGO product
crude Atmospheric Combined VGO to storage
exchangers Reduced heaters
crude Quench
exchangers Asphalt and vacuum residue rundown

Vacuum residue to VBU


Vacuum
heaters

FIG. 2. Simplified process schematic of the crude unit debottleneck project.

E–56 ENGINEERING AND CONSTRUCTION | MAY 2017 | HydrocarbonProcessing.com


ENGINEERING AND CONSTRUCTION

One option some contractors use is provided was LTO from the Bakken. • Miscellaneous replacement
to make an arrangement with a vendor The required project modifications of process piping, which were
to provide a spot in their manufacturing included: too small.
operation for a piece of equipment with • The installation of a fourth
very general specifications. Reactors are a desalter for light crude processing. TAKEAWAYS
typical example of this approach. Special • An increase in heat exchange Conducting small projects requires a
alloy steel may have to be ordered in ad- upstream and downstream of the different approach than those used for
vance, as it can be the most critical item. desalter. larger projects. To be cost effective, mul-
The weekly progress review meetings • A new crude pre-flash system to tiple small projects should be executed
must address all of these critical path provide a means to recover the by small teams. Because individual proj-
scheduling concerns. Engineering disci- naphtha from the crude upstream ects are usually in different phases at any
plines should coordinate their activities of the main crude column. given time, keeping the work separated is
based on the knowledge of what specifi- • Additional heat exchange upstream a key challenge.
cations are critical to other disciplines. of the fired heater. Small projects require the use of
TABLE 1 shows a Gantt chart schedule • Adding convection section coils to multi-discipline individuals who can
based on weekly activities. This chart is for the crude heater. This allowed the perform more than just one specialty.
a 24-week project to execute a crude unit installation of an ammonia-type Communication is the key. The goal
expansion (debottlenecking) project to SCR system for NOx removal from is to have all project personnel on the
increase unit capacity. The numbers indi- the heater stack. This operation same page. This requires skillful project
cate how many weeks it would require to provided a justification for the new management, especially within the early
execute the given activity. permits (NOx reduction). stages of the project.
FIG. 2 shows a process schematic of • Modification to the AGO
RAY ELSHOUT has 30 years of process and project
the modifications made to increase the draw system and new AGO engineering experience with Fluor, Jacobs and
crude unit capacity from 140 Mbpd to product pump. Unocal. He is a consultant with Energy Systems
180 Mbpd. This drawing does not show • New, larger diameter impellers Engineering, and his primary experience is in process
design, including retrofits, revamps and expansions.
the pump around the loops, which remain for the overhead naphtha, kerosine Mr. Elshout holds BS and MS degrees from the
the same. In this case, all additional crude and diesel product pumps. University of Michigan.

Unlock the Archives,


Data Handbooks and More
HYDROCARBON PROCESSING

nProcessing.com
DECEMBE R 2016 | Hydrocarbo

with a Full Access Plan


DECEMBER 2016

INEERING
PLANT DESIGN, ENG Hydrocarbon Processing’s Full Data Access Plan
AND CONSTRUCTION
PLANT DESIGN, ENGINEERING

Modularization: The key


to success

Efficiently and safely revamp


in today’s market
provides subscribers with unlimited access to
HydrocarbonProcessing.com—the HPI’s most
or
an RFCC and regenerat

PROCESS OPTIMIZATION
AND CONSTRUCTION

in refinery flares
Optimize steam usage

TOP PROJECT AWARD


S
Winners of the top construct
ion powerful source of technical content, reference
project awards for 2016,
as chosen by HP readers
information and market data.

Highlights include:
• An online archive of issues and articles
dating back more than 16 years
• All process handbooks (refining,
gas processing, petrochemical)
• NEW! HPI Market Data Book 2017
• Access to the latest Construction
Boxscore Database project updates.

Subscribe online at HydrocarbonProcessing.com or contact J’Nette Davis-Nichols


at +1 (713) 520-4426 or Jnette.Davis-Nichols@GulfPub.com

HYDROCARBON PROCESSING | MAY 2017 | ENGINEERING AND CONSTRUCTION E–57

Das könnte Ihnen auch gefallen