Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev

Supply & Fabrication of 15 Jackets


TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
476
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev 12-Jul-19 17-Jan-21 0 17-Jan-21, Formosa II OWF Supply a

FOUNDATION PACKAGE 476 12-Jul-19 17-Jan-21 0 17-Jan-21, FOUNDATION PACKAGE

MILESTONES 525 12-Jul-19 17-Dec-20 31 17-Dec-20, MILESTONES


GENERAL 49 12-Jul-19 30-Aug-19 9 30-Aug-19, GENERAL
F2-JK2-GA-1 Contract award Jacket Foundation Fabricator 1 - Sembcorp 0 12-Jul-19* 0
F2-JK2-GA-2 Ordering of Primary Steel 0 30-Aug-19 9
MTS EMPLOYER/CONTRACTOR 350 12-Jul-19 26-Jun-20 206 26-Jun-20, MTS EMPLOYER/CONTRACTOR
F2-JK2-MT-17 Completion of constructability review of final WTG Foundation design drawings
0 15-Sep-19 21 15-Sep-19
F2-JK2-MT-18 WTG Foundation design certification sufficient for steel order 0 15-Oct-19 57 15-Oct-19
F2-JK2-MT-19 Final WTG Foundation design certification (including transportation and
0 installation analysis) 14-Nov-19 57 14-Nov-19
F2-JK2-MT-20 Delivery of Free Issue Equipment as per Schedule 10-13 for eight (8) number
0 TPs to TP fabrication
13-May-20*
facility 70 13-May-20*
F2-JK2-MT-21 Delivery of Free Issue Equipment as per Schedule 10-13 for eight (7) number
0 TPs to TP fabrication
26-Jun-20*
facility 206 26-Jun-20*
F2-JK2-MT-5 Completion of constructability review of preliminary WTG Foundation design
0 drawings 12-Jul-19 202 12-Jul-19
MTS SUPPLIER 517 15-Jul-19 12-Dec-20 36 12-Dec-20, MTS SUPPLIER
F2-JK2-MT-1 Jacket Delivery Section 1 (1-4 of 15) 0 17-Aug-20 153 17-Aug-20
F2-JK2-MT-10 Submission of the first Programme by the Supplier after the Base Date0 11-Aug-19 67 11-Aug-19
F2-JK2-MT-11 Submission of Project Control Procedures as specified in schedule 9-11
0 11-Aug-19 67 11-Aug-19
F2-JK2-MT-12 Submission of the Quality Plan 0 11-Aug-19 67 11-Aug-19
F2-JK2-MT-13 Submission of the revision of the Inspection and Test Plan which is approved
0 by the Employer15-Sep-19 32 15-Sep-19
F2-JK2-MT-14 Submission of the revision of the Detailed Fabrication Plan which is approved
0 by the Employer15-Sep-19 299 15-Sep-19
F2-JK2-MT-15 Submission of the revision of the Health and Safety Plan which is approved
0 by the Employer 15-Sep-19 299 15-Sep-19
F2-JK2-MT-16 Submission of the revision of the Environmental Management Plan which
0 is approved by the Employer
15-Sep-19 137 15-Sep-19
F2-JK2-MT-2 Jacket Delivery Section 2 (5-8 of 15) 0 31-Aug-20 139 31-Aug-20
F2-JK2-MT-22 Ready for load out on quay side Section 1 (1-4 of 15) 0 13-Sep-20 126 13-Sep-20
F2-JK2-MT-23 Ready for load out on quay side Section 2 (6-8 of 15) 0 13-Oct-20 96 13-Oct-20
F2-JK2-MT-24 Ready for load out on quay side Section 3 (9-12 of 15) 0 12-Nov-20 66 12-Nov-20
F2-JK2-MT-25 Ready for load out on quay side Section 4 (13-15 of 15) 0 12-Dec-20 36 12-Dec-20
F2-JK2-MT-3 Jacket Delivery Section 3 (9-12 of 15) 0 17-Oct-20 92 17-Oct-20
F2-JK2-MT-4 Jacket Delivery Section 4 (13-15 of 15) 0 31-Oct-20 78 31-Oct-20
F2-JK2-MT-6 First submission of the Inspection and Test Plan 0 15-Jul-19 199 15-Jul-19
F2-JK2-MT-7 First submission of the Detailed Fabrication Plan 0 15-Jul-19 199 15-Jul-19
F2-JK2-MT-8 First submission of the Health and Safety Plan 0 15-Jul-19 199 15-Jul-19
F2-JK2-MT-9 First submission of the Environmental Management Plan 0 15-Jul-19 199 15-Jul-19
LD MILESTONES 90 18-Sep-20 17-Dec-20 31 17-Dec-20, LD MILESTONES
F2-JK2-LD-1 Latest Works Taking Over Section 4 0 17-Dec-20 0 17-Dec-20
F2-JK2-LD-2 Latest Works Taking Over Section 1 0 18-Sep-20 121 18-Sep-20
F2-JK2-LD-3 Latest Works Taking Over Section 2 0 18-Oct-20 31 18-Oct-20
F2-JK2-LD-4 Latest Works Taking Over Section 3 0 17-Nov-20 61 17-Nov-20
ENGINEERING & DOCUMENTS 352 12-Jul-19 16-Nov-20 44 16-Nov-20, ENGINEERING & DOCUMENTS
PROJECT MANAGEMENT DOCUMENTS 72 12-Jul-19 21-Oct-19 121 21-Oct-19, PROJECT MANAGEMENT DOCUMENTS
Master Document Register 51 12-Aug-19 21-Oct-19 72 21-Oct-19, Master Document Register
F2-JK2-ENGD-109 IFR 1 06-Sep-19 06-Sep-19 72 06-Sep-19, IFR
F2-JK2-ENGD-199 AFC 1 21-Oct-19 21-Oct-19 72 21-Oct-19, AFC
F2-JK2-ENGD-38 IDC 1 20-Aug-19 20-Aug-19 72 20-Aug-19, IDC
F2-JK2-ENGD-9 Start 1 12-Aug-19 12-Aug-19 72 12-Aug-19, Start
Foundation Fabrication Plan 66 12-Jul-19 11-Oct-19 78 11-Oct-19, Foundation Fabrication Plan
F2-JK2-ENGD-222 Start 1 12-Jul-19 12-Jul-19 78 12-Jul-19, Start
F2-JK2-ENGD-330 IDC 1 22-Jul-19 22-Jul-19 78 22-Jul-19, IDC
F2-JK2-ENGD-435 IFR 1 08-Aug-19 08-Aug-19 78 08-Aug-19, IFR
F2-JK2-ENGD-442 AFC 1 11-Oct-19 11-Oct-19 78 11-Oct-19, AFC
Project Schedule 33 26-Jul-19 10-Sep-19 101 10-Sep-19, Project Schedule
F2-JK2-ENGD-308 Start 1 26-Jul-19 26-Jul-19 101 26-Jul-19, Start
F2-JK2-ENGD-414 IDC 1 05-Aug-19 05-Aug-19 101 05-Aug-19, IDC
F2-JK2-ENGD-441 IFR 1 09-Aug-19 09-Aug-19 101 09-Aug-19, IFR

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 1 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-ENGD-447 AFC 1 10-Sep-19 10-Sep-19 101 10-Sep-19, AFC
Fabrication Control Procedure 51 12-Jul-19 20-Sep-19 93 20-Sep-19, Fabrication Control Procedure
F2-JK2-ENGD-1 IDC 1 22-Jul-19 22-Jul-19 93 22-Jul-19, IDC
F2-JK2-ENGD-2 IFR 1 08-Aug-19 08-Aug-19 93 08-Aug-19, IFR
F2-JK2-ENGD-3 AFC 1 20-Sep-19 20-Sep-19 93 20-Sep-19, AFC
F2-JK2-ENGD-448 Start 1 12-Jul-19 12-Jul-19 93 12-Jul-19, Start
Procurement Procedure 51 12-Jul-19 20-Sep-19 142 20-Sep-19, Procurement Procedure
F2-JK2-ENGD-4 Start 1 12-Jul-19 12-Jul-19 142 12-Jul-19, Start
F2-JK2-ENGD-5 IDC 1 22-Jul-19 22-Jul-19 142 22-Jul-19, IDC
F2-JK2-ENGD-6 IFR 1 08-Aug-19 08-Aug-19 142 08-Aug-19, IFR
F2-JK2-ENGD-7 AFC 1 20-Sep-19 20-Sep-19 142 20-Sep-19, AFC
Project Control Procedure 33 26-Jul-19 10-Sep-19 101 10-Sep-19, Project Control Procedure
F2-JK2-ENGD-25 Start 1 26-Jul-19 26-Jul-19 101 26-Jul-19, Start
F2-JK2-ENGD-29 IDC 1 05-Aug-19 05-Aug-19 101 05-Aug-19, IDC
F2-JK2-ENGD-31 IFR 1 09-Aug-19 09-Aug-19 101 09-Aug-19, IFR
F2-JK2-ENGD-32 AFC 1 10-Sep-19 10-Sep-19 101 10-Sep-19, AFC
Procurement Plan 51 12-Jul-19 20-Sep-19 142 20-Sep-19, Procurement Plan
F2-JK2-ENGD-33 Start 1 12-Jul-19 12-Jul-19 142 12-Jul-19, Start
F2-JK2-ENGD-36 IDC 1 22-Jul-19 22-Jul-19 142 22-Jul-19, IDC
F2-JK2-ENGD-37 IFR 1 08-Aug-19 08-Aug-19 142 08-Aug-19, IFR
F2-JK2-ENGD-46 AFC 1 20-Sep-19 20-Sep-19 142 20-Sep-19, AFC
Subcontracting Plan 51 12-Jul-19 20-Sep-19 142 20-Sep-19, Subcontracting Plan
F2-JK2-ENGD-57 Start 1 12-Jul-19 12-Jul-19 142 12-Jul-19, Start
F2-JK2-ENGD-68 IDC 1 22-Jul-19 22-Jul-19 142 22-Jul-19, IDC
F2-JK2-ENGD-79 IFR 1 08-Aug-19 08-Aug-19 142 08-Aug-19, IFR
F2-JK2-ENGD-90 AFC 1 20-Sep-19 20-Sep-19 142 20-Sep-19, AFC
General Material Management and Preservation Procedure 66 12-Jul-19 11-Oct-19 127 11-Oct-19, General Material Management and Preservation Procedure
F2-JK2-ENGD-101 Start 1 12-Jul-19 12-Jul-19 127 12-Jul-19, Start
F2-JK2-ENGD-105 IDC 1 22-Jul-19 22-Jul-19 127 22-Jul-19, IDC
F2-JK2-ENGD-106 IFR 1 08-Aug-19 08-Aug-19 127 08-Aug-19, IFR
F2-JK2-ENGD-107 AFC 1 11-Oct-19 11-Oct-19 127 11-Oct-19, AFC
Coating Plan Procedure 66 12-Jul-19 11-Oct-19 78 11-Oct-19, Coating Plan Procedure
F2-JK2-ENGD-108 Start 1 12-Jul-19 12-Jul-19 78 12-Jul-19, Start
F2-JK2-ENGD-110 IDC 1 22-Jul-19 22-Jul-19 78 22-Jul-19, IDC
F2-JK2-ENGD-111 IFR 1 08-Aug-19 08-Aug-19 78 08-Aug-19, IFR
F2-JK2-ENGD-119 AFC 1 11-Oct-19 11-Oct-19 78 11-Oct-19, AFC
Risk Register 66 12-Jul-19 11-Oct-19 78 11-Oct-19, Risk Register
F2-JK2-ENGD-130 Start 1 12-Jul-19 12-Jul-19 78 12-Jul-19, Start
F2-JK2-ENGD-141 IDC 1 22-Jul-19 22-Jul-19 78 22-Jul-19, IDC
F2-JK2-ENGD-152 IFR 1 08-Aug-19 08-Aug-19 78 08-Aug-19, IFR
F2-JK2-ENGD-163 AFC 1 11-Oct-19 11-Oct-19 78 11-Oct-19, AFC
List Subcontractors 66 12-Jul-19 11-Oct-19 78 11-Oct-19, List Subcontractors
F2-JK2-ENGD-174 Start 1 12-Jul-19 12-Jul-19 78 12-Jul-19, Start
F2-JK2-ENGD-185 IDC 1 22-Jul-19 22-Jul-19 78 22-Jul-19, IDC
F2-JK2-ENGD-196 IFR 1 08-Aug-19 08-Aug-19 78 08-Aug-19, IFR
F2-JK2-ENGD-208 AFC 1 11-Oct-19 11-Oct-19 78 11-Oct-19, AFC
Material Handling Procedure 66 12-Jul-19 11-Oct-19 78 11-Oct-19, Material Handling Procedure
F2-JK2-ENGD-219 Start 1 12-Jul-19 12-Jul-19 78 12-Jul-19, Start
F2-JK2-ENGD-231 IDC 1 22-Jul-19 22-Jul-19 78 22-Jul-19, IDC
F2-JK2-ENGD-242 IFR 1 08-Aug-19 08-Aug-19 78 08-Aug-19, IFR
F2-JK2-ENGD-253 AFC 1 11-Oct-19 11-Oct-19 78 11-Oct-19, AFC
QA/QC DOCUMENTS 154 15-Jul-19 13-Feb-20 145 13-Feb-20, QA/QC DOCUMENTS
Project Quality Plan 23 15-Jul-19 14-Aug-19 131 14-Aug-19, Project Quality Plan
F2-JK2-ENGD-284 IFR 1 15-Jul-19 15-Jul-19 131 15-Jul-19, IFR
F2-JK2-ENGD-295 AFC 1 14-Aug-19 14-Aug-19 131 14-Aug-19, AFC

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 2 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
Inspection And Test Plans - Fabrication 23 15-Jul-19 14-Aug-19 131 14-Aug-19, Inspection And Test Plans - Fabrication
F2-JK2-ENGD-327 IFR 1 15-Jul-19 15-Jul-19 131 15-Jul-19, IFR
F2-JK2-ENGD-339 AFC 1 14-Aug-19 14-Aug-19 131 14-Aug-19, AFC
Inspection And Test Plans - Coating 23 15-Jul-19 14-Aug-19 120 14-Aug-19, Inspection And Test Plans - Coating
F2-JK2-ENGD-370 IFR 1 15-Jul-19 15-Jul-19 120 15-Jul-19, IFR
F2-JK2-ENGD-381 AFC 1 14-Aug-19 14-Aug-19 120 14-Aug-19, AFC
Quality Audit Procedure 50 16-Sep-19 22-Nov-19 48 22-Nov-19, Quality Audit Procedure
F2-JK2-ENGD-349 Start 1 16-Sep-19 16-Sep-19 48 16-Sep-19, Start
F2-JK2-ENGD-350 IDC 1 01-Oct-19 01-Oct-19 48 01-Oct-19, IDC
F2-JK2-ENGD-351 IFR 1 15-Oct-19 15-Oct-19 48 15-Oct-19, IFR
F2-JK2-ENGD-352 AFC 1 22-Nov-19 22-Nov-19 48 22-Nov-19, AFC
Material Traceability Procedure 50 16-Sep-19 22-Nov-19 48 22-Nov-19, Material Traceability Procedure
F2-JK2-ENGD-353 Start 1 16-Sep-19 16-Sep-19 48 16-Sep-19, Start
F2-JK2-ENGD-354 IDC 1 01-Oct-19 01-Oct-19 48 01-Oct-19, IDC
F2-JK2-ENGD-355 IFR 1 15-Oct-19 15-Oct-19 48 15-Oct-19, IFR
F2-JK2-ENGD-356 AFC 1 22-Nov-19 22-Nov-19 48 22-Nov-19, AFC
Calibration, Measuring & Test Equipment Procedure 50 16-Sep-19 22-Nov-19 204 22-Nov-19, Calibration, Measuring & Test Equipment Procedure
F2-JK2-ENGD-357 Start 1 16-Sep-19 16-Sep-19 204 16-Sep-19, Start
F2-JK2-ENGD-358 IDC 1 01-Oct-19 01-Oct-19 204 01-Oct-19, IDC
F2-JK2-ENGD-359 IFR 1 15-Oct-19 15-Oct-19 204 15-Oct-19, IFR
F2-JK2-ENGD-360 AFC 1 22-Nov-19 22-Nov-19 204 22-Nov-19, AFC
Welding Consumable Control Procedure 50 16-Sep-19 22-Nov-19 131 22-Nov-19, Welding Consumable Control Procedure
F2-JK2-ENGD-361 Start 1 16-Sep-19 16-Sep-19 131 16-Sep-19, Start
F2-JK2-ENGD-362 IDC 1 01-Oct-19 01-Oct-19 131 01-Oct-19, IDC
F2-JK2-ENGD-363 IFR 1 15-Oct-19 15-Oct-19 131 15-Oct-19, IFR
F2-JK2-ENGD-364 AFC 1 22-Nov-19 22-Nov-19 131 22-Nov-19, AFC
Welder Qualification Procedure 43 23-Jul-19 19-Sep-19 177 19-Sep-19, Welder Qualification Procedure
F2-JK2-ENGD-443 Start 1 23-Jul-19 23-Jul-19 177 23-Jul-19, Start
F2-JK2-ENGD-444 IDC 1 14-Aug-19 14-Aug-19 177 14-Aug-19, IDC
F2-JK2-ENGD-445 IFR 1 20-Aug-19 20-Aug-19 177 20-Aug-19, IFR
F2-JK2-ENGD-446 AFC 1 19-Sep-19 19-Sep-19 177 19-Sep-19, AFC
Non & Conformance Control Procedure 50 16-Sep-19 22-Nov-19 59 22-Nov-19, Non & Conformance Control Procedure
F2-JK2-ENGD-365 Start 1 16-Sep-19 16-Sep-19 59 16-Sep-19, Start
F2-JK2-ENGD-366 IDC 1 01-Oct-19 01-Oct-19 59 01-Oct-19, IDC
F2-JK2-ENGD-367 IFR 1 15-Oct-19 15-Oct-19 59 15-Oct-19, IFR
F2-JK2-ENGD-368 AFC 1 22-Nov-19 22-Nov-19 59 22-Nov-19, AFC
In-process Inspection Procedure 50 16-Sep-19 22-Nov-19 59 22-Nov-19, In-process Inspection Procedure
F2-JK2-ENGD-369 Start 1 16-Sep-19 16-Sep-19 59 16-Sep-19, Start
F2-JK2-ENGD-371 IDC 1 01-Oct-19 01-Oct-19 59 01-Oct-19, IDC
F2-JK2-ENGD-372 IFR 1 15-Oct-19 15-Oct-19 59 15-Oct-19, IFR
F2-JK2-ENGD-373 AFC 1 22-Nov-19 22-Nov-19 59 22-Nov-19, AFC
Dimensional Control Procedure 50 06-Dec-19 13-Feb-20 0 13-Feb-20, Dimensional Control Procedure
F2-JK2-ENGD-374 Start 1 06-Dec-19 06-Dec-19 0 06-Dec-19, Start
F2-JK2-ENGD-375 IDC 1 23-Dec-19 23-Dec-19 0 23-Dec-19, IDC
F2-JK2-ENGD-376 IFR 1 06-Jan-20 06-Jan-20 0 06-Jan-20, IFR
F2-JK2-ENGD-377 AFC 1 13-Feb-20 13-Feb-20 0 13-Feb-20, AFC
Welding Procedure Specification - Piping 50 06-Dec-19 13-Feb-20 0 13-Feb-20, Welding Procedure Specification - Piping
F2-JK2-ENGD-378 Start 1 06-Dec-19 06-Dec-19 0 06-Dec-19, Start
F2-JK2-ENGD-379 IDC 1 23-Dec-19 23-Dec-19 0 23-Dec-19, IDC
F2-JK2-ENGD-380 IFR 1 06-Jan-20 06-Jan-20 0 06-Jan-20, IFR
F2-JK2-ENGD-382 AFC 1 13-Feb-20 13-Feb-20 0 13-Feb-20, AFC
Welding Control Procedure 50 16-Sep-19 22-Nov-19 59 22-Nov-19, Welding Control Procedure
F2-JK2-ENGD-383 Start 1 16-Sep-19 16-Sep-19 59 16-Sep-19, Start
F2-JK2-ENGD-384 IDC 1 01-Oct-19 01-Oct-19 59 01-Oct-19, IDC
F2-JK2-ENGD-385 IFR 1 15-Oct-19 15-Oct-19 59 15-Oct-19, IFR

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 3 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-ENGD-386 AFC 1 22-Nov-19 22-Nov-19 59 22-Nov-19, AFC
List Of Qualified Welders Structural & Piping 50 25-Nov-19 31-Jan-20 9 31-Jan-20, List Of Qualified Welders Structural & Piping
F2-JK2-ENGD-387 Start 1 25-Nov-19 25-Nov-19 9 25-Nov-19, Start
F2-JK2-ENGD-388 IDC 1 10-Dec-19 10-Dec-19 9 10-Dec-19, IDC
F2-JK2-ENGD-389 IFR 1 24-Dec-19 24-Dec-19 9 24-Dec-19, IFR
F2-JK2-ENGD-390 AFC 1 31-Jan-20 31-Jan-20 9 31-Jan-20, AFC
List Of NDT Operators & Qualification 50 25-Nov-19 31-Jan-20 9 31-Jan-20, List Of NDT Operators & Qualification
F2-JK2-ENGD-391 Start 1 25-Nov-19 25-Nov-19 9 25-Nov-19, Start
F2-JK2-ENGD-392 IDC 1 10-Dec-19 10-Dec-19 9 10-Dec-19, IDC
F2-JK2-ENGD-393 IFR 1 24-Dec-19 24-Dec-19 9 24-Dec-19, IFR
F2-JK2-ENGD-394 AFC 1 31-Jan-20 31-Jan-20 9 31-Jan-20, AFC
Magnetic Particle Testing Procedure Structural 50 25-Nov-19 31-Jan-20 9 31-Jan-20, Magnetic Particle Testing Procedure Structural
F2-JK2-ENGD-395 Start 1 25-Nov-19 25-Nov-19 9 25-Nov-19, Start
F2-JK2-ENGD-396 IDC 1 10-Dec-19 10-Dec-19 9 10-Dec-19, IDC
F2-JK2-ENGD-397 IFR 1 24-Dec-19 24-Dec-19 9 24-Dec-19, IFR
F2-JK2-ENGD-398 AFC 1 31-Jan-20 31-Jan-20 9 31-Jan-20, AFC
Ultrasonic Testing Procedure - Structural 50 25-Nov-19 31-Jan-20 9 31-Jan-20, Ultrasonic Testing Procedure - Structural
F2-JK2-ENGD-399 Start 1 25-Nov-19 25-Nov-19 9 25-Nov-19, Start
F2-JK2-ENGD-400 IDC 1 10-Dec-19 10-Dec-19 9 10-Dec-19, IDC
F2-JK2-ENGD-401 IFR 1 24-Dec-19 24-Dec-19 9 24-Dec-19, IFR
F2-JK2-ENGD-402 AFC 1 31-Jan-20 31-Jan-20 9 31-Jan-20, AFC
Radiography Testing Procedure (Structural) 50 25-Nov-19 31-Jan-20 9 31-Jan-20, Radiography Testing Procedure (Structural)
F2-JK2-ENGD-403 Start 1 25-Nov-19 25-Nov-19 9 25-Nov-19, Start
F2-JK2-ENGD-404 IDC 1 10-Dec-19 10-Dec-19 9 10-Dec-19, IDC
F2-JK2-ENGD-405 IFR 1 24-Dec-19 24-Dec-19 9 24-Dec-19, IFR
F2-JK2-ENGD-406 AFC 1 31-Jan-20 31-Jan-20 9 31-Jan-20, AFC
Liquid Penetrant Testing Procedure (Structural) 50 25-Nov-19 31-Jan-20 9 31-Jan-20, Liquid Penetrant Testing Procedure (Structural)
F2-JK2-ENGD-407 Start 1 25-Nov-19 25-Nov-19 9 25-Nov-19, Start
F2-JK2-ENGD-408 IDC 1 10-Dec-19 10-Dec-19 9 10-Dec-19, IDC
F2-JK2-ENGD-409 IFR 1 24-Dec-19 24-Dec-19 9 24-Dec-19, IFR
F2-JK2-ENGD-410 AFC 1 31-Jan-20 31-Jan-20 9 31-Jan-20, AFC
Magnetic Particle Testing Procedure (Piping) 50 25-Nov-19 31-Jan-20 9 31-Jan-20, Magnetic Particle Testing Procedure (Piping)
F2-JK2-ENGD-411 Start 1 25-Nov-19 25-Nov-19 9 25-Nov-19, Start
F2-JK2-ENGD-412 IDC 1 10-Dec-19 10-Dec-19 9 10-Dec-19, IDC
F2-JK2-ENGD-413 IFR 1 24-Dec-19 24-Dec-19 9 24-Dec-19, IFR
F2-JK2-ENGD-415 AFC 1 31-Jan-20 31-Jan-20 9 31-Jan-20, AFC
Radiography Testing Procedure (Piping) 50 25-Nov-19 31-Jan-20 81 31-Jan-20, Radiography Testing Procedure (Piping)
F2-JK2-ENGD-437 Start 1 25-Nov-19 25-Nov-19 81 25-Nov-19, Start
F2-JK2-ENGD-438 IDC 1 10-Dec-19 10-Dec-19 81 10-Dec-19, IDC
F2-JK2-ENGD-439 IFR 1 24-Dec-19 24-Dec-19 81 24-Dec-19, IFR
F2-JK2-ENGD-440 AFC 1 31-Jan-20 31-Jan-20 81 31-Jan-20, AFC
Liquid Penetrant Testing Procedure (Piping) 50 25-Nov-19 31-Jan-20 9 31-Jan-20, Liquid Penetrant Testing Procedure (Piping)
F2-JK2-ENGD-432 Start 1 25-Nov-19 25-Nov-19 9 25-Nov-19, Start
F2-JK2-ENGD-433 IDC 1 10-Dec-19 10-Dec-19 9 10-Dec-19, IDC
F2-JK2-ENGD-434 IFR 1 24-Dec-19 24-Dec-19 9 24-Dec-19, IFR
F2-JK2-ENGD-436 AFC 1 31-Jan-20 31-Jan-20 9 31-Jan-20, AFC
Surface Preparation And Coating Procedures 50 21-Nov-19 29-Jan-20 11 29-Jan-20, Surface Preparation And Coating Procedures
F2-JK2-ENGD-428 Start 1 21-Nov-19 21-Nov-19 11 21-Nov-19, Start
F2-JK2-ENGD-429 IDC 1 06-Dec-19 06-Dec-19 11 06-Dec-19, IDC
F2-JK2-ENGD-430 IFR 1 20-Dec-19 20-Dec-19 11 20-Dec-19, IFR
F2-JK2-ENGD-431 AFC 1 29-Jan-20 29-Jan-20 11 29-Jan-20, AFC
Inspection And Test Plan - Piping 50 21-Nov-19 29-Jan-20 83 29-Jan-20, Inspection And Test Plan - Piping
F2-JK2-ENGD-424 Start 1 21-Nov-19 21-Nov-19 83 21-Nov-19, Start
F2-JK2-ENGD-425 IDC 1 06-Dec-19 06-Dec-19 83 06-Dec-19, IDC
F2-JK2-ENGD-426 IFR 1 20-Dec-19 20-Dec-19 83 20-Dec-19, IFR

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 4 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-ENGD-427 AFC 1 29-Jan-20 29-Jan-20 83 29-Jan-20, AFC
MRB Index 50 25-Nov-19 31-Jan-20 9 31-Jan-20, MRB Index
F2-JK2-ENGD-420 Start 1 25-Nov-19 25-Nov-19 9 25-Nov-19, Start
F2-JK2-ENGD-421 IDC 1 10-Dec-19 10-Dec-19 9 10-Dec-19, IDC
F2-JK2-ENGD-422 IFR 1 24-Dec-19 24-Dec-19 9 24-Dec-19, IFR
F2-JK2-ENGD-423 AFC 1 31-Jan-20 31-Jan-20 9 31-Jan-20, AFC
Welding Procedure Specification For Structural 50 21-Oct-19 27-Dec-19 23 27-Dec-19, Welding Procedure Specification For Structural
F2-JK2-ENGD-416 Start 1 21-Oct-19 21-Oct-19 23 21-Oct-19, Start
F2-JK2-ENGD-417 IDC 1 05-Nov-19 05-Nov-19 23 05-Nov-19, IDC
F2-JK2-ENGD-418 IFR 1 19-Nov-19 19-Nov-19 23 19-Nov-19, IFR
F2-JK2-ENGD-419 AFC 1 27-Dec-19 27-Dec-19 23 27-Dec-19, AFC
ENGINEERING 302 20-Sep-19 16-Nov-20 44 16-Nov-20, ENGINEERING
Construction Sequence 62 20-Sep-19 16-Dec-19 32 16-Dec-19, Construction Sequence
F2-JK2-ENGD-11 Start 1 20-Sep-19 20-Sep-19 32 20-Sep-19, Start
F2-JK2-ENGD-12 IDC 1 07-Oct-19 07-Oct-19 32 07-Oct-19, IDC
F2-JK2-ENGD-13 IFR 1 06-Nov-19 06-Nov-19 32 06-Nov-19, IFR
F2-JK2-ENGD-14 AFC 1 16-Dec-19 16-Dec-19 32 16-Dec-19, AFC
Jacket Fabrication Yard Foundation Strength Check 62 20-Sep-19 16-Dec-19 32 16-Dec-19, Jacket Fabrication Yard Foundation Strength Check
F2-JK2-ENGD-15 Start 1 20-Sep-19 20-Sep-19 32 20-Sep-19, Start
F2-JK2-ENGD-17 IDC 1 07-Oct-19 07-Oct-19 32 07-Oct-19, IDC
F2-JK2-ENGD-18 IFR 1 06-Nov-19 06-Nov-19 32 06-Nov-19, IFR
F2-JK2-ENGD-19 AFC 1 16-Dec-19 16-Dec-19 32 16-Dec-19, AFC
Jacket Fabrication Temporary Support Design 62 20-Sep-19 16-Dec-19 32 16-Dec-19, Jacket Fabrication Temporary Support Design
F2-JK2-ENGD-20 Start 1 20-Sep-19 20-Sep-19 32 20-Sep-19, Start
F2-JK2-ENGD-21 IDC 1 07-Oct-19 07-Oct-19 32 07-Oct-19, IDC
F2-JK2-ENGD-22 IFR 1 06-Nov-19 06-Nov-19 32 06-Nov-19, IFR
F2-JK2-ENGD-23 AFC 1 16-Dec-19 16-Dec-19 32 16-Dec-19, AFC
Jacket Foundation 1 - Lower Jacket Assembly Sequence 62 23-Oct-19 16-Jan-20 118 16-Jan-20, Jacket Foundation 1 - Lower Jacket Assembly Sequence
F2-JK2-ENGD-39 Start 1 23-Oct-19 23-Oct-19 118 23-Oct-19, Start
F2-JK2-ENGD-40 IDC 1 07-Nov-19 07-Nov-19 118 07-Nov-19, IDC
F2-JK2-ENGD-41 IFR 1 06-Dec-19 06-Dec-19 118 06-Dec-19, IFR
F2-JK2-ENGD-42 AFC 1 16-Jan-20 16-Jan-20 118 16-Jan-20, AFC
Jacket Foundation 2 - Lower Jacket Assembly Sequence 62 23-Oct-19 16-Jan-20 118 16-Jan-20, Jacket Foundation 2 - Lower Jacket Assembly Sequence
F2-JK2-ENGD-43 Start 1 23-Oct-19 23-Oct-19 118 23-Oct-19, Start
F2-JK2-ENGD-44 IDC 1 07-Nov-19 07-Nov-19 118 07-Nov-19, IDC
F2-JK2-ENGD-45 IFR 1 06-Dec-19 06-Dec-19 118 06-Dec-19, IFR
F2-JK2-ENGD-47 AFC 1 16-Jan-20 16-Jan-20 118 16-Jan-20, AFC
Jacket Foundation 3 - Lower Jacket Assembly Sequence 62 30-Oct-19 23-Jan-20 113 23-Jan-20, Jacket Foundation 3 - Lower Jacket Assembly Sequence
F2-JK2-ENGD-48 Start 1 30-Oct-19 30-Oct-19 113 30-Oct-19, Start
F2-JK2-ENGD-49 IDC 1 14-Nov-19 14-Nov-19 113 14-Nov-19, IDC
F2-JK2-ENGD-50 IFR 1 13-Dec-19 13-Dec-19 113 13-Dec-19, IFR
F2-JK2-ENGD-51 AFC 1 23-Jan-20 23-Jan-20 113 23-Jan-20, AFC
Jacket Foundation 4 - Lower Jacket Assembly Sequence 62 30-Oct-19 23-Jan-20 90 23-Jan-20, Jacket Foundation 4 - Lower Jacket Assembly Sequence
F2-JK2-ENGD-52 Start 1 30-Oct-19 30-Oct-19 90 30-Oct-19, Start
F2-JK2-ENGD-53 IDC 1 14-Nov-19 14-Nov-19 90 14-Nov-19, IDC
F2-JK2-ENGD-54 IFR 1 13-Dec-19 13-Dec-19 90 13-Dec-19, IFR
F2-JK2-ENGD-55 AFC 1 23-Jan-20 23-Jan-20 90 23-Jan-20, AFC
Jacket Foundation 5 - Lower Jacket Assembly Sequence 62 06-Nov-19 30-Jan-20 130 30-Jan-20, Jacket Foundation 5 - Lower Jacket Assembly Sequence
F2-JK2-ENGD-56 Start 1 06-Nov-19 06-Nov-19 130 06-Nov-19, Start
F2-JK2-ENGD-58 IDC 1 21-Nov-19 21-Nov-19 130 21-Nov-19, IDC
F2-JK2-ENGD-59 IFR 1 20-Dec-19 20-Dec-19 130 20-Dec-19, IFR
F2-JK2-ENGD-60 AFC 1 30-Jan-20 30-Jan-20 130 30-Jan-20, AFC
Jacket Foundation 6 - Lower Jacket Assembly Sequence 62 06-Nov-19 30-Jan-20 130 30-Jan-20, Jacket Foundation 6 - Lower Jacket Assembly Sequence
F2-JK2-ENGD-61 Start 1 06-Nov-19 06-Nov-19 130 06-Nov-19, Start
F2-JK2-ENGD-62 IDC 1 21-Nov-19 21-Nov-19 130 21-Nov-19, IDC

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 5 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-ENGD-63 IFR 1 20-Dec-19 20-Dec-19 130 20-Dec-19, IFR
F2-JK2-ENGD-64 AFC 1 30-Jan-20 30-Jan-20 130 30-Jan-20, AFC
Jacket Foundation 7 - Lower Jacket Assembly Sequence 62 13-Nov-19 06-Feb-20 125 06-Feb-20, Jacket Foundation 7 - Lower Jacket Assembly Sequence
F2-JK2-ENGD-65 Start 1 13-Nov-19 13-Nov-19 125 13-Nov-19, Start
F2-JK2-ENGD-66 IDC 1 28-Nov-19 28-Nov-19 125 28-Nov-19, IDC
F2-JK2-ENGD-67 IFR 1 27-Dec-19 27-Dec-19 125 27-Dec-19, IFR
F2-JK2-ENGD-69 AFC 1 06-Feb-20 06-Feb-20 125 06-Feb-20, AFC
Jacket Foundation 8 - Lower Jacket Assembly Sequence 62 13-Nov-19 06-Feb-20 91 06-Feb-20, Jacket Foundation 8 - Lower Jacket Assembly Sequence
F2-JK2-ENGD-70 Start 1 13-Nov-19 13-Nov-19 91 13-Nov-19, Start
F2-JK2-ENGD-71 IDC 1 28-Nov-19 28-Nov-19 91 28-Nov-19, IDC
F2-JK2-ENGD-72 IFR 1 27-Dec-19 27-Dec-19 91 27-Dec-19, IFR
F2-JK2-ENGD-73 AFC 1 06-Feb-20 06-Feb-20 91 06-Feb-20, AFC
Jacket Foundation 9 - Lower Jacket Assembly Sequence 62 24-Dec-19 18-Mar-20 117 18-Mar-20, Jacket Foundation 9 - Lower Jacket Assembly Sequence
F2-JK2-ENGD-74 Start 1 24-Dec-19 24-Dec-19 117 24-Dec-19, Start
F2-JK2-ENGD-75 IDC 1 08-Jan-20 08-Jan-20 117 08-Jan-20, IDC
F2-JK2-ENGD-76 IFR 1 06-Feb-20 06-Feb-20 117 06-Feb-20, IFR
F2-JK2-ENGD-77 AFC 1 18-Mar-20 18-Mar-20 117 18-Mar-20, AFC
Jacket Foundation 10 - Lower Jacket Assembly Sequence 62 24-Dec-19 18-Mar-20 117 18-Mar-20, Jacket Foundation 10 - Lower Jacket Assembly Sequence
F2-JK2-ENGD-78 Start 1 24-Dec-19 24-Dec-19 117 24-Dec-19, Start
F2-JK2-ENGD-80 IDC 1 08-Jan-20 08-Jan-20 117 08-Jan-20, IDC
F2-JK2-ENGD-81 IFR 1 06-Feb-20 06-Feb-20 117 06-Feb-20, IFR
F2-JK2-ENGD-82 AFC 1 18-Mar-20 18-Mar-20 117 18-Mar-20, AFC
Jacket Foundation 11 - Lower Jacket Assembly Sequence 62 31-Dec-19 25-Mar-20 112 25-Mar-20, Jacket Foundation 11 - Lower Jacket Assembly Sequence
F2-JK2-ENGD-83 Start 1 31-Dec-19 31-Dec-19 112 31-Dec-19, Start
F2-JK2-ENGD-84 IDC 1 15-Jan-20 15-Jan-20 112 15-Jan-20, IDC
F2-JK2-ENGD-85 IFR 1 13-Feb-20 13-Feb-20 112 13-Feb-20, IFR
F2-JK2-ENGD-86 AFC 1 25-Mar-20 25-Mar-20 112 25-Mar-20, AFC
Jacket Foundation 12 - Lower Jacket Assembly Sequence 62 31-Dec-19 25-Mar-20 72 25-Mar-20, Jacket Foundation 12 - Lower Jacket Assembly Sequence
F2-JK2-ENGD-87 Start 1 31-Dec-19 31-Dec-19 72 31-Dec-19, Start
F2-JK2-ENGD-88 IDC 1 15-Jan-20 15-Jan-20 72 15-Jan-20, IDC
F2-JK2-ENGD-89 IFR 1 13-Feb-20 13-Feb-20 72 13-Feb-20, IFR
F2-JK2-ENGD-91 AFC 1 25-Mar-20 25-Mar-20 72 25-Mar-20, AFC
Jacket Foundation 13 - Lower Jacket Assembly Sequence 62 07-Jan-20 01-Apr-20 128 01-Apr-20, Jacket Foundation 13 - Lower Jacket Assembly Sequence
F2-JK2-ENGD-92 Start 1 07-Jan-20 07-Jan-20 128 07-Jan-20, Start
F2-JK2-ENGD-93 IDC 1 22-Jan-20 22-Jan-20 128 22-Jan-20, IDC
F2-JK2-ENGD-94 IFR 1 19-Feb-20 19-Feb-20 128 19-Feb-20, IFR
F2-JK2-ENGD-95 AFC 1 01-Apr-20 01-Apr-20 128 01-Apr-20, AFC
Jacket Foundation 14 - Lower Jacket Assembly Sequence 62 07-Jan-20 01-Apr-20 128 01-Apr-20, Jacket Foundation 14 - Lower Jacket Assembly Sequence
F2-JK2-ENGD-96 Start 1 07-Jan-20 07-Jan-20 128 07-Jan-20, Start
F2-JK2-ENGD-97 IDC 1 22-Jan-20 22-Jan-20 128 22-Jan-20, IDC
F2-JK2-ENGD-98 IFR 1 19-Feb-20 19-Feb-20 128 19-Feb-20, IFR
F2-JK2-ENGD-99 AFC 1 01-Apr-20 01-Apr-20 128 01-Apr-20, AFC
Jacket Foundation 15 - Lower Jacket Assembly Sequence 62 14-Jan-20 08-Apr-20 79 08-Apr-20, Jacket Foundation 15 - Lower Jacket Assembly Sequence
F2-JK2-ENGD-100 Start 1 14-Jan-20 14-Jan-20 79 14-Jan-20, Start
F2-JK2-ENGD-102 IDC 1 29-Jan-20 29-Jan-20 79 29-Jan-20, IDC
F2-JK2-ENGD-103 IFR 1 26-Feb-20 26-Feb-20 79 26-Feb-20, IFR
F2-JK2-ENGD-104 AFC 1 08-Apr-20 08-Apr-20 79 08-Apr-20, AFC
Jacket Foundation 1 - Upper Jacket Assembly Sequence 62 23-Oct-19 16-Jan-20 116 16-Jan-20, Jacket Foundation 1 - Upper Jacket Assembly Sequence
F2-JK2-ENGD-178 Start 1 23-Oct-19 23-Oct-19 116 23-Oct-19, Start
F2-JK2-ENGD-179 IDC 1 07-Nov-19 07-Nov-19 116 07-Nov-19, IDC
F2-JK2-ENGD-180 IFR 1 06-Dec-19 06-Dec-19 116 06-Dec-19, IFR
F2-JK2-ENGD-181 AFC 1 16-Jan-20 16-Jan-20 116 16-Jan-20, AFC
Jacket Foundation 2 - Upper Jacket Assembly Sequence 62 23-Oct-19 16-Jan-20 116 16-Jan-20, Jacket Foundation 2 - Upper Jacket Assembly Sequence
F2-JK2-ENGD-182 Start 1 23-Oct-19 23-Oct-19 116 23-Oct-19, Start
F2-JK2-ENGD-183 IDC 1 07-Nov-19 07-Nov-19 116 07-Nov-19, IDC

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 6 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-ENGD-184 IFR 1 06-Dec-19 06-Dec-19 116 06-Dec-19, IFR
F2-JK2-ENGD-186 AFC 1 16-Jan-20 16-Jan-20 116 16-Jan-20, AFC
Jacket Foundation 3 - Upper Jacket Assembly Sequence 62 30-Oct-19 23-Jan-20 111 23-Jan-20, Jacket Foundation 3 - Upper Jacket Assembly Sequence
F2-JK2-ENGD-187 Start 1 30-Oct-19 30-Oct-19 111 30-Oct-19, Start
F2-JK2-ENGD-188 IDC 1 14-Nov-19 14-Nov-19 111 14-Nov-19, IDC
F2-JK2-ENGD-189 IFR 1 13-Dec-19 13-Dec-19 111 13-Dec-19, IFR
F2-JK2-ENGD-190 AFC 1 23-Jan-20 23-Jan-20 111 23-Jan-20, AFC
Jacket Foundation 4 - Upper Jacket Assembly Sequence 62 30-Oct-19 23-Jan-20 87 23-Jan-20, Jacket Foundation 4 - Upper Jacket Assembly Sequence
F2-JK2-ENGD-191 Start 1 30-Oct-19 30-Oct-19 87 30-Oct-19, Start
F2-JK2-ENGD-192 IDC 1 14-Nov-19 14-Nov-19 87 14-Nov-19, IDC
F2-JK2-ENGD-193 IFR 1 13-Dec-19 13-Dec-19 87 13-Dec-19, IFR
F2-JK2-ENGD-194 AFC 1 23-Jan-20 23-Jan-20 87 23-Jan-20, AFC
Jacket Foundation 5 - Upper Jacket Assembly Sequence 62 06-Nov-19 30-Jan-20 127 30-Jan-20, Jacket Foundation 5 - Upper Jacket Assembly Sequence
F2-JK2-ENGD-195 Start 1 06-Nov-19 06-Nov-19 127 06-Nov-19, Start
F2-JK2-ENGD-197 IDC 1 21-Nov-19 21-Nov-19 127 21-Nov-19, IDC
F2-JK2-ENGD-198 IFR 1 20-Dec-19 20-Dec-19 127 20-Dec-19, IFR
F2-JK2-ENGD-200 AFC 1 30-Jan-20 30-Jan-20 127 30-Jan-20, AFC
Jacket Foundation 6 - Upper Jacket Assembly Sequence 62 06-Nov-19 30-Jan-20 127 30-Jan-20, Jacket Foundation 6 - Upper Jacket Assembly Sequence
F2-JK2-ENGD-201 Start 1 06-Nov-19 06-Nov-19 127 06-Nov-19, Start
F2-JK2-ENGD-202 IDC 1 21-Nov-19 21-Nov-19 127 21-Nov-19, IDC
F2-JK2-ENGD-203 IFR 1 20-Dec-19 20-Dec-19 127 20-Dec-19, IFR
F2-JK2-ENGD-204 AFC 1 30-Jan-20 30-Jan-20 127 30-Jan-20, AFC
Jacket Foundation 7 - Upper Jacket Assembly Sequence 62 13-Nov-19 06-Feb-20 122 06-Feb-20, Jacket Foundation 7 - Upper Jacket Assembly Sequence
F2-JK2-ENGD-205 Start 1 13-Nov-19 13-Nov-19 122 13-Nov-19, Start
F2-JK2-ENGD-206 IDC 1 28-Nov-19 28-Nov-19 122 28-Nov-19, IDC
F2-JK2-ENGD-207 IFR 1 27-Dec-19 27-Dec-19 122 27-Dec-19, IFR
F2-JK2-ENGD-209 AFC 1 06-Feb-20 06-Feb-20 122 06-Feb-20, AFC
Jacket Foundation 8 - Upper Jacket Assembly Sequence 62 13-Nov-19 06-Feb-20 88 06-Feb-20, Jacket Foundation 8 - Upper Jacket Assembly Sequence
F2-JK2-ENGD-210 Start 1 13-Nov-19 13-Nov-19 88 13-Nov-19, Start
F2-JK2-ENGD-211 IDC 1 28-Nov-19 28-Nov-19 88 28-Nov-19, IDC
F2-JK2-ENGD-212 IFR 1 27-Dec-19 27-Dec-19 88 27-Dec-19, IFR
F2-JK2-ENGD-213 AFC 1 06-Feb-20 06-Feb-20 88 06-Feb-20, AFC
Jacket Foundation 9 - Upper Jacket Assembly Sequence 62 24-Dec-19 18-Mar-20 114 18-Mar-20, Jacket Foundation 9 - Upper Jacket Assembly Sequence
F2-JK2-ENGD-214 Start 1 24-Dec-19 24-Dec-19 114 24-Dec-19, Start
F2-JK2-ENGD-215 IDC 1 08-Jan-20 08-Jan-20 114 08-Jan-20, IDC
F2-JK2-ENGD-216 IFR 1 06-Feb-20 06-Feb-20 114 06-Feb-20, IFR
F2-JK2-ENGD-217 AFC 1 18-Mar-20 18-Mar-20 114 18-Mar-20, AFC
Jacket Foundation 10 - Upper Jacket Assembly Sequence 62 24-Dec-19 18-Mar-20 114 18-Mar-20, Jacket Foundation 10 - Upper Jacket Assembly Sequence
F2-JK2-ENGD-218 Start 1 24-Dec-19 24-Dec-19 114 24-Dec-19, Start
F2-JK2-ENGD-220 IDC 1 08-Jan-20 08-Jan-20 114 08-Jan-20, IDC
F2-JK2-ENGD-221 IFR 1 06-Feb-20 06-Feb-20 114 06-Feb-20, IFR
F2-JK2-ENGD-223 AFC 1 18-Mar-20 18-Mar-20 114 18-Mar-20, AFC
Jacket Foundation 11 - Upper Jacket Assembly Sequence 62 31-Dec-19 25-Mar-20 109 25-Mar-20, Jacket Foundation 11 - Upper Jacket Assembly Sequence
F2-JK2-ENGD-224 Start 1 31-Dec-19 31-Dec-19 109 31-Dec-19, Start
F2-JK2-ENGD-225 IDC 1 15-Jan-20 15-Jan-20 109 15-Jan-20, IDC
F2-JK2-ENGD-226 IFR 1 13-Feb-20 13-Feb-20 109 13-Feb-20, IFR
F2-JK2-ENGD-227 AFC 1 25-Mar-20 25-Mar-20 109 25-Mar-20, AFC
Jacket Foundation 12 - Upper Jacket Assembly Sequence 62 31-Dec-19 25-Mar-20 69 25-Mar-20, Jacket Foundation 12 - Upper Jacket Assembly Sequence
F2-JK2-ENGD-228 Start 1 31-Dec-19 31-Dec-19 69 31-Dec-19, Start
F2-JK2-ENGD-229 IDC 1 15-Jan-20 15-Jan-20 69 15-Jan-20, IDC
F2-JK2-ENGD-230 IFR 1 13-Feb-20 13-Feb-20 69 13-Feb-20, IFR
F2-JK2-ENGD-232 AFC 1 25-Mar-20 25-Mar-20 69 25-Mar-20, AFC
Jacket Foundation 13 - Upper Jacket Assembly Sequence 62 07-Jan-20 01-Apr-20 126 01-Apr-20, Jacket Foundation 13 - Upper Jacket Assembly Sequence
F2-JK2-ENGD-233 Start 1 07-Jan-20 07-Jan-20 126 07-Jan-20, Start
F2-JK2-ENGD-234 IDC 1 22-Jan-20 22-Jan-20 126 22-Jan-20, IDC

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 7 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-ENGD-235 IFR 1 19-Feb-20 19-Feb-20 126 19-Feb-20, IFR
F2-JK2-ENGD-236 AFC 1 01-Apr-20 01-Apr-20 126 01-Apr-20, AFC
Jacket Foundation 14 - Upper Jacket Assembly Sequence 62 07-Jan-20 01-Apr-20 126 01-Apr-20, Jacket Foundation 14 - Upper Jacket Assembly Sequence
F2-JK2-ENGD-237 Start 1 07-Jan-20 07-Jan-20 126 07-Jan-20, Start
F2-JK2-ENGD-238 IDC 1 22-Jan-20 22-Jan-20 126 22-Jan-20, IDC
F2-JK2-ENGD-239 IFR 1 19-Feb-20 19-Feb-20 126 19-Feb-20, IFR
F2-JK2-ENGD-240 AFC 1 01-Apr-20 01-Apr-20 126 01-Apr-20, AFC
Jacket Foundation 15 - Upper Jacket Assembly Sequence 62 14-Jan-20 08-Apr-20 77 08-Apr-20, Jacket Foundation 15 - Upper Jacket Assembly Sequence
F2-JK2-ENGD-241 Start 1 14-Jan-20 14-Jan-20 77 14-Jan-20, Start
F2-JK2-ENGD-243 IDC 1 29-Jan-20 29-Jan-20 77 29-Jan-20, IDC
F2-JK2-ENGD-244 IFR 1 26-Feb-20 26-Feb-20 77 26-Feb-20, IFR
F2-JK2-ENGD-245 AFC 1 08-Apr-20 08-Apr-20 77 08-Apr-20, AFC
Jacket Foundation 1 - Transition Piece Installation Procedure 62 11-Dec-19 05-Mar-20 126 05-Mar-20, Jacket Foundation 1 - Transition Piece Installation Procedure
F2-JK2-ENGD-112 Start 1 11-Dec-19 11-Dec-19 126 11-Dec-19, Start
F2-JK2-ENGD-113 IDC 1 26-Dec-19 26-Dec-19 126 26-Dec-19, IDC
F2-JK2-ENGD-114 IFR 1 27-Jan-20 27-Jan-20 126 27-Jan-20, IFR
F2-JK2-ENGD-115 AFC 1 05-Mar-20 05-Mar-20 126 05-Mar-20, AFC
Jacket Foundation 2 - Transition Piece Installation Procedure 62 11-Dec-19 05-Mar-20 62 05-Mar-20, Jacket Foundation 2 - Transition Piece Installation Procedure
F2-JK2-ENGD-116 Start 1 11-Dec-19 11-Dec-19 62 11-Dec-19, Start
F2-JK2-ENGD-117 IDC 1 26-Dec-19 26-Dec-19 62 26-Dec-19, IDC
F2-JK2-ENGD-118 IFR 1 27-Jan-20 27-Jan-20 62 27-Jan-20, IFR
F2-JK2-ENGD-120 AFC 1 05-Mar-20 05-Mar-20 62 05-Mar-20, AFC
Jacket Foundation 3 - Transition Piece Installation Procedure 62 18-Dec-19 12-Mar-20 57 12-Mar-20, Jacket Foundation 3 - Transition Piece Installation Procedure
F2-JK2-ENGD-121 Start 1 18-Dec-19 18-Dec-19 57 18-Dec-19, Start
F2-JK2-ENGD-122 IDC 1 02-Jan-20 02-Jan-20 57 02-Jan-20, IDC
F2-JK2-ENGD-123 IFR 1 03-Feb-20 03-Feb-20 57 03-Feb-20, IFR
F2-JK2-ENGD-124 AFC 1 12-Mar-20 12-Mar-20 57 12-Mar-20, AFC
Jacket Foundation 4 - Transition Piece Installation Procedure 62 18-Dec-19 12-Mar-20 34 12-Mar-20, Jacket Foundation 4 - Transition Piece Installation Procedure
F2-JK2-ENGD-125 Start 1 18-Dec-19 18-Dec-19 34 18-Dec-19, Start
F2-JK2-ENGD-126 IDC 1 02-Jan-20 02-Jan-20 34 02-Jan-20, IDC
F2-JK2-ENGD-127 IFR 1 03-Feb-20 03-Feb-20 34 03-Feb-20, IFR
F2-JK2-ENGD-128 AFC 1 12-Mar-20 12-Mar-20 34 12-Mar-20, AFC
Jacket Foundation 5 - Transition Piece Installation Procedure 62 25-Dec-19 19-Mar-20 74 19-Mar-20, Jacket Foundation 5 - Transition Piece Installation Procedure
F2-JK2-ENGD-129 Start 1 25-Dec-19 25-Dec-19 74 25-Dec-19, Start
F2-JK2-ENGD-131 IDC 1 09-Jan-20 09-Jan-20 74 09-Jan-20, IDC
F2-JK2-ENGD-132 IFR 1 10-Feb-20 10-Feb-20 74 10-Feb-20, IFR
F2-JK2-ENGD-133 AFC 1 19-Mar-20 19-Mar-20 74 19-Mar-20, AFC
Jacket Foundation 6 - Transition Piece Installation Procedure 62 25-Dec-19 19-Mar-20 74 19-Mar-20, Jacket Foundation 6 - Transition Piece Installation Procedure
F2-JK2-ENGD-134 Start 1 25-Dec-19 25-Dec-19 74 25-Dec-19, Start
F2-JK2-ENGD-135 IDC 1 09-Jan-20 09-Jan-20 74 09-Jan-20, IDC
F2-JK2-ENGD-136 IFR 1 10-Feb-20 10-Feb-20 74 10-Feb-20, IFR
F2-JK2-ENGD-137 AFC 1 19-Mar-20 19-Mar-20 74 19-Mar-20, AFC
Jacket Foundation 7 - Transition Piece Installation Procedure 62 01-Jan-20 26-Mar-20 69 26-Mar-20, Jacket Foundation 7 - Transition Piece Installation Procedure
F2-JK2-ENGD-138 Start 1 01-Jan-20 01-Jan-20 69 01-Jan-20, Start
F2-JK2-ENGD-139 IDC 1 16-Jan-20 16-Jan-20 69 16-Jan-20, IDC
F2-JK2-ENGD-140 IFR 1 17-Feb-20 17-Feb-20 69 17-Feb-20, IFR
F2-JK2-ENGD-142 AFC 1 26-Mar-20 26-Mar-20 69 26-Mar-20, AFC
Jacket Foundation 8 - Transition Piece Installation Procedure 62 01-Jan-20 26-Mar-20 35 26-Mar-20, Jacket Foundation 8 - Transition Piece Installation Procedure
F2-JK2-ENGD-143 Start 1 01-Jan-20 01-Jan-20 35 01-Jan-20, Start
F2-JK2-ENGD-144 IDC 1 16-Jan-20 16-Jan-20 35 16-Jan-20, IDC
F2-JK2-ENGD-145 IFR 1 17-Feb-20 17-Feb-20 35 17-Feb-20, IFR
F2-JK2-ENGD-146 AFC 1 26-Mar-20 26-Mar-20 35 26-Mar-20, AFC
Jacket Foundation 9 - Transition Piece Installation Procedure 62 12-Feb-20 07-May-20 60 07-May-20, Jacket Foundation 9 - Transition Piece Installation Procedure
F2-JK2-ENGD-147 Start 1 12-Feb-20 12-Feb-20 60 12-Feb-20, Start
F2-JK2-ENGD-148 IDC 1 27-Feb-20 27-Feb-20 60 27-Feb-20, IDC

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 8 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-ENGD-149 IFR 1 27-Mar-20 27-Mar-20 60 27-Mar-20, IFR
F2-JK2-ENGD-150 AFC 1 07-May-20 07-May-20 60 07-May-20, AFC
Jacket Foundation 10 - Transition Piece Installation Procedure 62 12-Feb-20 07-May-20 60 07-May-20, Jacket Foundation 10 - Transition Piece Installation Procedure
F2-JK2-ENGD-151 Start 1 12-Feb-20 12-Feb-20 60 12-Feb-20, Start
F2-JK2-ENGD-153 IDC 1 27-Feb-20 27-Feb-20 60 27-Feb-20, IDC
F2-JK2-ENGD-154 IFR 1 27-Mar-20 27-Mar-20 60 27-Mar-20, IFR
F2-JK2-ENGD-155 AFC 1 07-May-20 07-May-20 60 07-May-20, AFC
Jacket Foundation 11 - Transition Piece Installation Procedure 62 19-Feb-20 14-May-20 55 14-May-20, Jacket Foundation 11 - Transition Piece Installation Procedure
F2-JK2-ENGD-156 Start 1 19-Feb-20 19-Feb-20 55 19-Feb-20, Start
F2-JK2-ENGD-157 IDC 1 05-Mar-20 05-Mar-20 55 05-Mar-20, IDC
F2-JK2-ENGD-158 IFR 1 03-Apr-20 03-Apr-20 55 03-Apr-20, IFR
F2-JK2-ENGD-159 AFC 1 14-May-20 14-May-20 55 14-May-20, AFC
Jacket Foundation 12 - Transition Piece Installation Procedure 62 19-Feb-20 14-May-20 15 14-May-20, Jacket Foundation 12 - Transition Piece Installation Procedure
F2-JK2-ENGD-160 Start 1 19-Feb-20 19-Feb-20 15 19-Feb-20, Start
F2-JK2-ENGD-161 IDC 1 05-Mar-20 05-Mar-20 15 05-Mar-20, IDC
F2-JK2-ENGD-162 IFR 1 03-Apr-20 03-Apr-20 15 03-Apr-20, IFR
F2-JK2-ENGD-164 AFC 1 14-May-20 14-May-20 15 14-May-20, AFC
Jacket Foundation 13 - Transition Piece Installation Procedure 62 26-Feb-20 21-May-20 71 21-May-20, Jacket Foundation 13 - Transition Piece Installation Procedure
F2-JK2-ENGD-165 Start 1 26-Feb-20 26-Feb-20 71 26-Feb-20, Start
F2-JK2-ENGD-166 IDC 1 12-Mar-20 12-Mar-20 71 12-Mar-20, IDC
F2-JK2-ENGD-167 IFR 1 10-Apr-20 10-Apr-20 71 10-Apr-20, IFR
F2-JK2-ENGD-168 AFC 1 21-May-20 21-May-20 71 21-May-20, AFC
Jacket Foundation 14 - Transition Piece Installation Procedure 62 26-Feb-20 21-May-20 71 21-May-20, Jacket Foundation 14 - Transition Piece Installation Procedure
F2-JK2-ENGD-169 Start 1 26-Feb-20 26-Feb-20 71 26-Feb-20, Start
F2-JK2-ENGD-170 IDC 1 12-Mar-20 12-Mar-20 71 12-Mar-20, IDC
F2-JK2-ENGD-171 IFR 1 10-Apr-20 10-Apr-20 71 10-Apr-20, IFR
F2-JK2-ENGD-172 AFC 1 21-May-20 21-May-20 71 21-May-20, AFC
Jacket Foundation 15 - Transition Piece Installation Procedure 62 04-Mar-20 28-May-20 22 28-May-20, Jacket Foundation 15 - Transition Piece Installation Procedure
F2-JK2-ENGD-173 Start 1 04-Mar-20 04-Mar-20 22 04-Mar-20, Start
F2-JK2-ENGD-175 IDC 1 19-Mar-20 19-Mar-20 22 19-Mar-20, IDC
F2-JK2-ENGD-176 IFR 1 17-Apr-20 17-Apr-20 22 17-Apr-20, IFR
F2-JK2-ENGD-177 AFC 1 28-May-20 28-May-20 22 28-May-20, AFC
Weight Control & C.O.G. Report 57 14-Nov-19 31-Jan-20 41 31-Jan-20, Weight Control & C.O.G. Report
F2-JK2-ENGD-26 Start 1 14-Nov-19 14-Nov-19 41 14-Nov-19, Start
F2-JK2-ENGD-27 IDC 1 22-Nov-19 22-Nov-19 41 22-Nov-19, IDC
F2-JK2-ENGD-28 IFR 1 23-Dec-19 23-Dec-19 41 23-Dec-19, IFR
F2-JK2-ENGD-30 AFC 1 31-Jan-20 31-Jan-20 41 31-Jan-20, AFC
Jacket Weighing Procedure 62 08-Apr-20 02-Jul-20 49 02-Jul-20, Jacket Weighing Procedure
F2-JK2-ENGD-246 Start 1 08-Apr-20 08-Apr-20 41 08-Apr-20, Start
F2-JK2-ENGD-247 IDC 1 23-Apr-20 23-Apr-20 49 23-Apr-20, IDC
F2-JK2-ENGD-248 IFR 1 25-May-20 25-May-20 49 25-May-20, IFR
F2-JK2-ENGD-249 AFC 1 02-Jul-20 02-Jul-20 49 02-Jul-20, AFC
Jacket Foundation 1 - Actual Weighing Report 62 10-Apr-20 06-Jul-20 48 06-Jul-20, Jacket Foundation 1 - Actual Weighing Report
F2-JK2-ENGD-250 Start 1 10-Apr-20 10-Apr-20 41 10-Apr-20, Start
F2-JK2-ENGD-251 IDC 1 27-Apr-20 27-Apr-20 48 27-Apr-20, IDC
F2-JK2-ENGD-252 IFR 1 27-May-20 27-May-20 48 27-May-20, IFR
F2-JK2-ENGD-254 AFC 1 06-Jul-20 06-Jul-20 48 06-Jul-20, AFC
Jacket Foundation 2 - Actual Weighing Report 62 10-Apr-20 06-Jul-20 48 06-Jul-20, Jacket Foundation 2 - Actual Weighing Report
F2-JK2-ENGD-255 Start 1 10-Apr-20 10-Apr-20 41 10-Apr-20, Start
F2-JK2-ENGD-256 IDC 1 27-Apr-20 27-Apr-20 48 27-Apr-20, IDC
F2-JK2-ENGD-257 IFR 1 27-May-20 27-May-20 48 27-May-20, IFR
F2-JK2-ENGD-258 AFC 1 06-Jul-20 06-Jul-20 48 06-Jul-20, AFC
Jacket Foundation 3 - Actual Weighing Report 62 17-Apr-20 13-Jul-20 43 13-Jul-20, Jacket Foundation 3 - Actual Weighing Report
F2-JK2-ENGD-259 Start 1 17-Apr-20 17-Apr-20 41 17-Apr-20, Start
F2-JK2-ENGD-260 IDC 1 04-May-20 04-May-20 43 04-May-20, IDC

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 9 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-ENGD-261 IFR 1 03-Jun-20 03-Jun-20 43 03-Jun-20, IFR
F2-JK2-ENGD-262 AFC 1 13-Jul-20 13-Jul-20 43 13-Jul-20, AFC
Jacket Foundation 4 - Actual Weighing Report 62 17-Apr-20 13-Jul-20 43 13-Jul-20, Jacket Foundation 4 - Actual Weighing Report
F2-JK2-ENGD-263 Start 1 17-Apr-20 17-Apr-20 41 17-Apr-20, Start
F2-JK2-ENGD-264 IDC 1 04-May-20 04-May-20 43 04-May-20, IDC
F2-JK2-ENGD-265 IFR 1 03-Jun-20 03-Jun-20 43 03-Jun-20, IFR
F2-JK2-ENGD-266 AFC 1 13-Jul-20 13-Jul-20 43 13-Jul-20, AFC
Jacket Foundation 5 - Actual Weighing Report 62 24-Apr-20 20-Jul-20 59 20-Jul-20, Jacket Foundation 5 - Actual Weighing Report
F2-JK2-ENGD-267 Start 1 24-Apr-20 24-Apr-20 41 24-Apr-20, Start
F2-JK2-ENGD-268 IDC 1 11-May-20 11-May-20 59 11-May-20, IDC
F2-JK2-ENGD-269 IFR 1 10-Jun-20 10-Jun-20 59 10-Jun-20, IFR
F2-JK2-ENGD-270 AFC 1 20-Jul-20 20-Jul-20 59 20-Jul-20, AFC
Jacket Foundation 6 - Actual Weighing Report 62 24-Apr-20 20-Jul-20 59 20-Jul-20, Jacket Foundation 6 - Actual Weighing Report
F2-JK2-ENGD-271 Start 1 24-Apr-20 24-Apr-20 41 24-Apr-20, Start
F2-JK2-ENGD-272 IDC 1 11-May-20 11-May-20 59 11-May-20, IDC
F2-JK2-ENGD-273 IFR 1 10-Jun-20 10-Jun-20 59 10-Jun-20, IFR
F2-JK2-ENGD-274 AFC 1 20-Jul-20 20-Jul-20 59 20-Jul-20, AFC
Jacket Foundation 7 - Actual Weighing Report 62 01-May-20 27-Jul-20 54 27-Jul-20, Jacket Foundation 7 - Actual Weighing Report
F2-JK2-ENGD-275 Start 1 01-May-20 01-May-20 41 01-May-20, Start
F2-JK2-ENGD-276 IDC 1 18-May-20 18-May-20 54 18-May-20, IDC
F2-JK2-ENGD-277 IFR 1 17-Jun-20 17-Jun-20 54 17-Jun-20, IFR
F2-JK2-ENGD-278 AFC 1 27-Jul-20 27-Jul-20 54 27-Jul-20, AFC
Jacket Foundation 8 - Actual Weighing Report 62 01-May-20 27-Jul-20 54 27-Jul-20, Jacket Foundation 8 - Actual Weighing Report
F2-JK2-ENGD-279 Start 1 01-May-20 01-May-20 41 01-May-20, Start
F2-JK2-ENGD-280 IDC 1 18-May-20 18-May-20 54 18-May-20, IDC
F2-JK2-ENGD-281 IFR 1 17-Jun-20 17-Jun-20 54 17-Jun-20, IFR
F2-JK2-ENGD-282 AFC 1 27-Jul-20 27-Jul-20 54 27-Jul-20, AFC
Jacket Foundation 9 - Actual Weighing Report 62 11-Jun-20 04-Sep-20 46 04-Sep-20, Jacket Foundation 9 - Actual Weighing Report
F2-JK2-ENGD-283 Start 1 11-Jun-20 11-Jun-20 41 11-Jun-20, Start
F2-JK2-ENGD-285 IDC 1 26-Jun-20 26-Jun-20 46 26-Jun-20, IDC
F2-JK2-ENGD-286 IFR 1 28-Jul-20 28-Jul-20 46 28-Jul-20, IFR
F2-JK2-ENGD-287 AFC 1 04-Sep-20 04-Sep-20 46 04-Sep-20, AFC
Jacket Foundation 10 - Actual Weighing Report 62 11-Jun-20 04-Sep-20 46 04-Sep-20, Jacket Foundation 10 - Actual Weighing Report
F2-JK2-ENGD-288 Start 1 11-Jun-20 11-Jun-20 41 11-Jun-20, Start
F2-JK2-ENGD-289 IDC 1 26-Jun-20 26-Jun-20 46 26-Jun-20, IDC
F2-JK2-ENGD-290 IFR 1 28-Jul-20 28-Jul-20 46 28-Jul-20, IFR
F2-JK2-ENGD-291 AFC 1 04-Sep-20 04-Sep-20 46 04-Sep-20, AFC
Jacket Foundation 11 - Actual Weighing Report 62 18-Jun-20 11-Sep-20 41 11-Sep-20, Jacket Foundation 11 - Actual Weighing Report
F2-JK2-ENGD-292 Start 1 18-Jun-20 18-Jun-20 41 18-Jun-20, Start
F2-JK2-ENGD-293 IDC 1 03-Jul-20 03-Jul-20 41 03-Jul-20, IDC
F2-JK2-ENGD-294 IFR 1 03-Aug-20 03-Aug-20 41 03-Aug-20, IFR
F2-JK2-ENGD-296 AFC 1 11-Sep-20 11-Sep-20 41 11-Sep-20, AFC
Jacket Foundation 12 - Actual Weighing Report 62 18-Jun-20 11-Sep-20 41 11-Sep-20, Jacket Foundation 12 - Ac tual Weighing Report
F2-JK2-ENGD-297 Start 1 18-Jun-20 18-Jun-20 41 18-Jun-20, Start
F2-JK2-ENGD-298 IDC 1 03-Jul-20 03-Jul-20 41 03-Jul-20, IDC
F2-JK2-ENGD-299 IFR 1 03-Aug-20 03-Aug-20 41 03-Aug-20, IFR
F2-JK2-ENGD-300 AFC 1 11-Sep-20 11-Sep-20 41 11-Sep-20, AFC
Jacket Foundation 13 - Actual Weighing Report 62 25-Jun-20 18-Sep-20 58 18-Sep-20, Jacket Foundation 13 - Actual Weighing Report
F2-JK2-ENGD-301 Start 1 25-Jun-20 25-Jun-20 52 25-Jun-20, Start
F2-JK2-ENGD-302 IDC 1 10-Jul-20 10-Jul-20 58 10-Jul-20, IDC
F2-JK2-ENGD-303 IFR 1 07-Aug-20 07-Aug-20 58 07-Aug-20, IFR
F2-JK2-ENGD-304 AFC 1 18-Sep-20 18-Sep-20 58 18-Sep-20, AFC
Jacket Foundation 14 - Actual Weighing Report 62 25-Jun-20 18-Sep-20 58 18-Sep-20, Jacket Foundation 14 - Actual Weighing Report
F2-JK2-ENGD-305 Start 1 25-Jun-20 25-Jun-20 52 25-Jun-20, Start
F2-JK2-ENGD-306 IDC 1 10-Jul-20 10-Jul-20 58 10-Jul-20, IDC

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 10 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-ENGD-307 IFR 1 07-Aug-20 07-Aug-20 58 07-Aug-20, IFR
F2-JK2-ENGD-309 AFC 1 18-Sep-20 18-Sep-20 58 18-Sep-20, AFC
Jacket Foundation 15 - Actual Weighing Report 62 03-Jul-20 28-Sep-20 52 28-Sep-20, Jacket Foundation 15 - Actual Weighing Report
F2-JK2-ENGD-310 Start 1 03-Jul-20 03-Jul-20 52 03-Jul-20, Start
F2-JK2-ENGD-311 IDC 1 20-Jul-20 20-Jul-20 52 20-Jul-20, IDC
F2-JK2-ENGD-312 IFR 1 17-Aug-20 17-Aug-20 52 17-Aug-20, IFR
F2-JK2-ENGD-313 AFC 1 28-Sep-20 28-Sep-20 52 28-Sep-20, AFC
Design Brief For Grillage and Sea-fastening 62 07-Jan-20 01-Apr-20 116 01-Apr-20, Design Brief For Grillage and Sea-fastening
F2-JK2-ENGD-314 Start 1 07-Jan-20 07-Jan-20 116 07-Jan-20, Start
F2-JK2-ENGD-315 IDC 1 22-Jan-20 22-Jan-20 116 22-Jan-20, IDC
F2-JK2-ENGD-316 IFR 1 21-Feb-20 21-Feb-20 116 21-Feb-20, IFR
F2-JK2-ENGD-317 AFC 1 01-Apr-20 01-Apr-20 116 01-Apr-20, AFC
Jacket Upper Grillage Design 62 07-Jan-20 01-Apr-20 116 01-Apr-20, Jacket Upper Grillage Design
F2-JK2-ENGD-318 Start 1 07-Jan-20 07-Jan-20 116 07-Jan-20, Start
F2-JK2-ENGD-319 IDC 1 22-Jan-20 22-Jan-20 116 22-Jan-20, IDC
F2-JK2-ENGD-320 IFR 1 21-Feb-20 21-Feb-20 116 21-Feb-20, IFR
F2-JK2-ENGD-321 AFC 1 01-Apr-20 01-Apr-20 116 01-Apr-20, AFC
Jacket Load Out and Sea-fastening Procedure 62 17-Apr-20 13-Jul-20 43 13-Jul-20, Jacket Load Out and Sea-fastening Procedure
F2-JK2-ENGD-322 Start 1 17-Apr-20 17-Apr-20 43 17-Apr-20, Start
F2-JK2-ENGD-323 IDC 1 04-May-20 04-May-20 43 04-May-20, IDC
F2-JK2-ENGD-324 IFR 1 01-Jun-20 01-Jun-20 43 01-Jun-20, IFR
F2-JK2-ENGD-325 AFC 1 13-Jul-20 13-Jul-20 43 13-Jul-20, AFC
J-Tubes Bending Procedure 62 29-Nov-19 24-Feb-20 106 24-Feb-20, J-Tubes Bending Procedure
F2-JK2-ENGD-326 Start 1 29-Nov-19 29-Nov-19 106 29-Nov-19, Start
F2-JK2-ENGD-328 IDC 1 16-Dec-19 16-Dec-19 106 16-Dec-19, IDC
F2-JK2-ENGD-329 IFR 1 13-Jan-20 13-Jan-20 106 13-Jan-20, IFR
F2-JK2-ENGD-331 AFC 1 24-Feb-20 24-Feb-20 106 24-Feb-20, AFC
Mooring Design Data 62 07-Jan-20 01-Apr-20 116 01-Apr-20, Mooring Design Data
F2-JK2-ENGD-332 Start 1 07-Jan-20 07-Jan-20 116 07-Jan-20, Start
F2-JK2-ENGD-333 IDC 1 22-Jan-20 22-Jan-20 116 22-Jan-20, IDC
F2-JK2-ENGD-334 IFR 1 19-Feb-20 19-Feb-20 116 19-Feb-20, IFR
F2-JK2-ENGD-335 AFC 1 01-Apr-20 01-Apr-20 116 01-Apr-20, AFC
Grating Specification 62 14-Nov-19 07-Feb-20 120 07-Feb-20, Grating Specification
F2-JK2-ENGD-336 Start 1 14-Nov-19 14-Nov-19 120 14-Nov-19, Start
F2-JK2-ENGD-337 IDC 1 29-Nov-19 29-Nov-19 120 29-Nov-19, IDC
F2-JK2-ENGD-338 IFR 1 27-Dec-19 27-Dec-19 120 27-Dec-19, IFR
F2-JK2-ENGD-340 AFC 1 07-Feb-20 07-Feb-20 120 07-Feb-20, AFC
Anodes Documentation 62 21-Aug-20 16-Nov-20 44 16-Nov-20, Anodes Documentation
F2-JK2-ENGD-341 Start 1 21-Aug-20 21-Aug-20 44 21-Aug-20, Start
F2-JK2-ENGD-342 IDC 1 07-Sep-20 07-Sep-20 44 07-Sep-20, IDC
F2-JK2-ENGD-343 IFR 1 05-Oct-20 05-Oct-20 44 05-Oct-20, IFR
F2-JK2-ENGD-344 AFC 1 16-Nov-20 16-Nov-20 44 16-Nov-20, AFC
HSE 47 15-Jul-19 17-Sep-19 96 17-Sep-19, HSE
HSE Plan Fabrication 47 15-Jul-19 17-Sep-19 96 17-Sep-19, HSE Plan Fabrication
F2-JK2-ENGD-34 IFR 1 15-Jul-19 15-Jul-19 96 15-Jul-19, IFR
F2-JK2-ENGD-35 AFC 1 17-Sep-19 17-Sep-19 96 17-Sep-19, AFC
COMMISSIONING 62 21-Aug-20 16-Nov-20 44 16-Nov-20, COMMISSIONING
Mock-up Testing Procedure 62 21-Aug-20 16-Nov-20 44 16-Nov-20, Mock-up Testing Procedure
F2-JK2-ENGD-345 Start 1 21-Aug-20 21-Aug-20 44 21-Aug-20, Start
F2-JK2-ENGD-346 IDC 1 07-Sep-20 07-Sep-20 44 07-Sep-20, IDC
F2-JK2-ENGD-347 IFR 1 05-Oct-20 05-Oct-20 44 05-Oct-20, IFR
F2-JK2-ENGD-348 AFC 1 16-Nov-20 16-Nov-20 44 16-Nov-20, AFC
PROCUREMENT 220 16-Sep-19 29-May-20 45 29-May-20, PROCUREMENT
F2-JK2-PROC-1 Purchase and Delivery of Primary Structure Material 185 16-Sep-19 18-Apr-20 27 18-Apr-20, Purchase and Delivery of Primary Structure Material
F2-JK2-PROC-2 Purchase and Delivery of Secondary Structure Material 190 21-Oct-19 29-May-20 45 29-May-20, Purchase and Delivery of Secondary Structure Material

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 11 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
Steel delivered, stored and marked at Site 90 28-Dec-19 27-Mar-20 11 27-Mar-20, Steel delivered, stored and marked at Site
Plate primary steel delivery 90 28-Dec-19 27-Mar-20 11 27-Mar-20, Plate primary steel delivery
F2-JK2-PROC-3 Batch 1 (5 Jackets) 0 28-Dec-19 11 28-Dec-19
F2-JK2-PROC-4 Batch 2 (5 Jackets) 0 11-Feb-20 11 11-Feb-20
F2-JK2-PROC-5 Batch 3 (5 Jackets) 0 27-Mar-20 11 27-Mar-20
Pipe primary steel delivery 60 27-Jan-20 27-Mar-20 11 27-Mar-20, Pipe primary steel delivery
F2-JK2-PROC-6 Batch 1 (5 Jackets) 0 27-Jan-20 9 27-Jan-20
F2-JK2-PROC-7 Batch 2 (5 Jackets) 0 26-Feb-20 11 26-Feb-20
F2-JK2-PROC-8 Batch 3 (5 Jackets) 0 27-Mar-20 11 27-Mar-20
CONSTRUCTION 231 12-Jan-20 07-Oct-20 53 07-Oct-20, CONSTRUCTION
F2-JK2-CONS-1 Blasting & Priming of Material 120 12-Jan-20 11-May-20 18 11-May-20, Blasting & Priming of Material
LOT A - 5 Jacket Foundations 158 13-Feb-20 15-Aug-20 47 15-Aug-20, LOT A - 5 Jacket Foundations
Jacket Foundation 1 130 13-Feb-20 14-Jul-20 49 14-Jul-20, Jacket Foundation 1
Fabrication 81 13-Feb-20 18-May-20 88 18-May-20, Fabrication
Pre-Fabrication 38 13-Feb-20 28-Mar-20 98 28-Mar-20, Pre-Fabrication
F2-JK2-JACF1-140
Rolling of Can Transition Piece Flange 10 17-Mar-20 28-Mar-20 98 28-Mar-20, Rolling of Can Transition Piece Flange
F2-JK2-JACF1-141
Rolling of Can Transition Piece Barrel 10 25-Feb-20 07-Mar-20 49 07-Mar-20, Rolling of Can Transition Piece Barrel
F2-JK2-JACF1-24
Rolling of Can Row 2 Brace 10 13-Feb-20 25-Feb-20 0 25-Feb-20, Rolling of Can Row 2 Brace
F2-JK2-JACF1-25
Rolling of Can Leg 1A & 1B 10 13-Feb-20 25-Feb-20 62 25-Feb-20, Rolling of Can Leg 1A & 1B
F2-JK2-JACF1-26
Rolling of Can Leg 2A & 2B 10 21-Feb-20 04-Mar-20 62 04-Mar-20, Rolling of Can Leg 2A & 2B
F2-JK2-JACF1-27
Rolling of Node Can Row 1 10 21-Feb-20 04-Mar-20 62 04-Mar-20, Rolling of Node Can Row 1
F2-JK2-JACF1-28
Rolling of Node Can Row 2 10 29-Feb-20 12-Mar-20 62 12-Mar-20, Rolling of Node Can Row 2
F2-JK2-JACF1-29
Rolling of Can Row 1 Brace 10 29-Feb-20 12-Mar-20 62 12-Mar-20, Rolling of Can Row 1 Brace
F2-JK2-JACF1-30
Rolling of J-Tubes & J-Tubes Support 10 09-Mar-20 20-Mar-20 63 20-Mar-20, Rolling of J-Tubes & J-Tubes Support
F2-JK2-JACF1-31
Rolling of Can Plan Level Tubular 10 09-Mar-20 20-Mar-20 98 20-Mar-20, Rolling of Can Plan Level Tubular
F2-JK2-JACF1-32
Rolling of Can Top Bay X-Brace 10 17-Mar-20 28-Mar-20 98 28-Mar-20, Rolling of Can Top Bay X-Brace
Row 1 Fabrication 42 25-Feb-20 14-Apr-20 103 14-Apr-20, Row 1 Fabrication
Legs 40 25-Feb-20 13-Apr-20 65 13-Apr-20, Legs
F2-JK2-JACF1-40
Install Stubs on to Leg 1A & 1B Nodes 2 02-Apr-20 04-Apr-20 62 04-Apr-20, Install Stubs on to Leg 1A & 1B Nodes
F2-JK2-JACF1-41
Install Anodes on Row-1 Legs 4 03-Apr-20 08-Apr-20 64 08-Apr-20, Install Anodes on Row-1 Legs
F2-JK2-JACF1-42
Join of Can Legs 1A 9 29-Feb-20 11-Mar-20 77 11-Mar-20, Join of Can Legs 1A
F2-JK2-JACF1-43
Join of Can Legs 1B 9 29-Feb-20 11-Mar-20 77 11-Mar-20, Join of Can Legs 1B
F2-JK2-JACF1-44
Mark and Profile Leg 1A & 1B Node 4 04-Mar-20 09-Mar-20 87 09-Mar-20, Mark and Profile Leg 1A & 1B Node
F2-JK2-JACF1-45
Profilling of Legs 1A & 1B (Inc. Cones) 4 25-Feb-20 29-Feb-20 77 29-Feb-20, Profilling of Legs 1A & 1B (Inc. Cones)
F2-JK2-JACF1-46
Join of Leg 1A & 1B Node 2 03-Apr-20 06-Apr-20 65 06-Apr-20, Join of Leg 1A & 1B Node
F2-JK2-JACF1-47
Blasting and Painting for Leg 1A & 1B Node 5 06-Apr-20 13-Apr-20 65 13-Apr-20, Blasting and Painting for Leg 1A & 1B Node
F2-JK2-JACF1-48
Assembly Leg 1A 3 01-Apr-20 03-Apr-20 62 03-Apr-20, Assembly Leg 1A
F2-JK2-JACF1-49
Assembly Leg 1B 3 01-Apr-20 03-Apr-20 62 03-Apr-20, Assembly Leg 1B
Braces 28 12-Mar-20 14-Apr-20 62 14-Apr-20, Braces
F2-JK2-JACF1-50
Fit & Weld Top X Brace Between Legs 1A & 1B 5 04-Apr-20 10-Apr-20 62 10-Apr-20, Fit & Weld Top X Brace Between Legs 1A & 1B
F2-JK2-JACF1-51
Join of Row-1 Can Brace (Inc. Stub) 13 17-Mar-20 01-Apr-20 62 01-Apr-20, Join of Row-1 Can Brace (Inc. Stub)
F2-JK2-JACF1-52
Join of Can Brace for Between Row 1 & 2 (Inc. Stub) 13 17-Mar-20 01-Apr-20 62 01-Apr-20, Join of Can Brace for Between Row 1 & 2 (Inc. Stub)
F2-JK2-JACF1-53
Assembly of Row-1 Top Brace 4 01-Apr-20 04-Apr-20 62 04-Apr-20, Assembly of Row-1 Top Brace
F2-JK2-JACF1-54
Fit & Weld Row-2 K-Brace (Inc. Vertical Braces) 5 04-Apr-20 10-Apr-20 62 10-Apr-20, Fit & Weld Row-2 K-Brace (Inc. Vertical Braces)
F2-JK2-JACF1-55
Assembly of Row-1 K-Brace 4 01-Apr-20 04-Apr-20 62 04-Apr-20, Assembly of Row-1 K-Brace
F2-JK2-JACF1-56
Fit & Weld X-Brace Between Row 1 & 2 5 04-Apr-20 10-Apr-20 62 10-Apr-20, Fit & Weld X-Brace Between Row 1 & 2
F2-JK2-JACF1-57
Assembly of Brace Between Row 1 & 2 4 01-Apr-20 04-Apr-20 62 04-Apr-20, Assembly of Brace Between Row 1 & 2
F2-JK2-JACF1-58
Profilling of Row-1 Braces and Stubs 4 12-Mar-20 17-Mar-20 62 17-Mar-20, Profilling of Row-1 Braces and Stubs
F2-JK2-JACF1-59
Install Anodes on Row-1 Braces 4 10-Apr-20 14-Apr-20 62 14-Apr-20, Install Anodes on Row-1 Braces
J-Tubes 19 20-Mar-20 11-Apr-20 105 11-Apr-20, J-Tubes
F2-JK2-JACF1-60
Join of Row-1 J-Tubes 5 25-Mar-20 31-Mar-20 105 31-Mar-20, Join of Row-1 J-Tubes
F2-JK2-JACF1-61
Profilling of Row-1 J-Tubes 4 20-Mar-20 25-Mar-20 105 25-Mar-20, Profilling of Row-1 J-Tubes
F2-JK2-JACF1-62
Bending of Row-1 J-Tubes 4 31-Mar-20 03-Apr-20 105 03-Apr-20, Bending of Row-1 J-Tubes
F2-JK2-JACF1-63
Blast and Paint for Row-1 J-Tubes 3 03-Apr-20 08-Apr-20 105 08-Apr-20, Blast and Paint for Row-1 J-Tubes
F2-JK2-JACF1-64
Assembly Row-1 J-Tubes 3 08-Apr-20 11-Apr-20 105 11-Apr-20, Assembly Row- 1 J-Tubes

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 12 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JACF1-65
Cut and Profile Row-1 J-Tubes Support 4 20-Mar-20 25-Mar-20 105 25-Mar-20, Cut and Profile Row-1 J-Tubes Support
F2-JK2-JACF1-66
Assembly Row-1 J-Tubes Support 2 25-Mar-20 28-Mar-20 105 28-Mar-20, Assembly Row-1 J-Tubes Support
F2-JK2-JACF1-67
Paint Row-1 J-Tubes Support 3 28-Mar-20 01-Apr-20 105 01-Apr-20, Paint Row-1 J-Tubes Support
F2-JK2-JACF1-68
Install J-Tubes Support on to Row-1 J-Tubes 3 01-Apr-20 03-Apr-20 105 03-Apr-20, Install J-Tubes Support on to Row-1 J-Tubes
Common 23 19-Mar-20 14-Apr-20 63 14-Apr-20, Common
Structure 3 19-Mar-20 23-Mar-20 70 23-Mar-20, Structure
F2-JK2-JACF1-33
Marking & Cutting of Leg and Brace Node 3 19-Mar-20 23-Mar-20 70 23-Mar-20, Marking & Cutting of Leg and Brace Node
F2-JK2-JACF1-34
Marking & Cutting of Brace Stub 3 19-Mar-20 23-Mar-20 70 23-Mar-20, Marking & Cutting of Brace Stub
F2-JK2-JACF1-35
Marking & Cutting of Leg and Brace Member 3 19-Mar-20 23-Mar-20 70 23-Mar-20, Marking & Cutting of Leg and Brace Member
Final Painting 23 19-Mar-20 14-Apr-20 63 14-Apr-20, Final Painting
F2-JK2-JACF1-36
Blast and Paint Leg and Brace (Initial Paint) 11 19-Mar-20 01-Apr-20 62 01-Apr-20, Blast and Paint Leg and Brace (Initial Paint)
F2-JK2-JACF1-37
Build Painting Habitat Protection 1 10-Apr-20 13-Apr-20 65 13-Apr-20, Build Painting Habitat Protection
F2-JK2-JACF1-38
Row-1 Ready for Assembly & Roll-up 0 13-Apr-20 65 13-Apr-20
F2-JK2-JACF1-39
Row-1 Touch up and Final Painting 3 10-Apr-20 14-Apr-20 62 14-Apr-20, Row-1 Touch up and Final Painting
Row 2 Fabrication 42 25-Feb-20 14-Apr-20 63 14-Apr-20, Row 2 Fabrication
Legs 23 04-Mar-20 31-Mar-20 76 31-Mar-20, Legs
F2-JK2-JACF1-76
Install Anodes on Row-2 Legs 4 21-Mar-20 26-Mar-20 75 26-Mar-20, Install Anodes on Row-2 Legs
F2-JK2-JACF1-77
Join of Can Legs 2A 9 09-Mar-20 19-Mar-20 70 19-Mar-20, Join of Can Legs 2A
F2-JK2-JACF1-78
Join of Can Legs 2B 9 09-Mar-20 19-Mar-20 70 19-Mar-20, Join of Can Legs 2B
F2-JK2-JACF1-79
Profilling of Legs 2A & 2B (Inc. Cones) 4 04-Mar-20 09-Mar-20 70 09-Mar-20, Profilling of Legs 2A & 2B (Inc. Cones)
F2-JK2-JACF1-80
Mark and Profile Leg 2A & 2B Node 4 12-Mar-20 17-Mar-20 80 17-Mar-20, Mark and Profile Leg 2A & 2B Node
F2-JK2-JACF1-81
Join of Leg 2A & 2B Node 2 21-Mar-20 24-Mar-20 76 24-Mar-20, Join of Leg 2A & 2B Node
F2-JK2-JACF1-82
Blasting and Painting for Leg 2A & 2B Node (Initial) 5 24-Mar-20 31-Mar-20 76 31-Mar-20, Blasting and Painting for Leg 2A & 2B Node (Initial)
F2-JK2-JACF1-83
Assembly Leg 2A 3 19-Mar-20 21-Mar-20 68 21-Mar-20, Assembly Leg 2A
F2-JK2-JACF1-84
Assembly Leg 2B 3 19-Mar-20 21-Mar-20 68 21-Mar-20, Assembly Leg 2B
F2-JK2-JACF1-85
Install Stubs on to Leg 2A & 2B Nodes 2 21-Mar-20 24-Mar-20 68 24-Mar-20, Install Stubs on to Leg 2A & 2B Nodes
Braces 32 25-Feb-20 02-Apr-20 68 02-Apr-20, Braces
F2-JK2-JACF1-138
Fit & Weld Row-2 K-Brace (Inc. Vertical Braces) 5 24-Mar-20 30-Mar-20 68 30-Mar-20, Fit & Weld Row-2 K-Brace (Inc. Vertical Braces)
F2-JK2-JACF1-139
Assembly of Row-2 K-Brace 4 19-Mar-20 23-Mar-20 69 23-Mar-20, Assembly of Row-2 K-Brace
F2-JK2-JACF1-86
Fit & Weld Top X-Brace Between Legs 2A & 2B 4 24-Mar-20 28-Mar-20 71 28-Mar-20, Fit & Weld Top X-Brace Between Legs 2A & 2B
F2-JK2-JACF1-87
Fit & Weld Mid X-Brace Between Legs 2A & 2B 4 24-Mar-20 28-Mar-20 71 28-Mar-20, Fit & Weld Mid X-Brace Between Legs 2A & 2B
F2-JK2-JACF1-88
Join of Row-2 Can Brace (Inc. Stub) 10 29-Feb-20 12-Mar-20 68 12-Mar-20, Join of Row-2 Can Brace (Inc. Stub)
F2-JK2-JACF1-89
Assembly of Row-2 Top Brace 3 19-Mar-20 23-Mar-20 72 23-Mar-20, Assembly of Row-2 Top Brace
F2-JK2-JACF1-90
Assembly of Row-2 Mid Brace 3 19-Mar-20 23-Mar-20 72 23-Mar-20, Assembly of Row-2 Mid Brace
F2-JK2-JACF1-91
Profilling of Row-2 Braces and Stubs 4 25-Feb-20 29-Feb-20 68 29-Feb-20, Profilling of Row-2 Braces and Stubs
F2-JK2-JACF1-92
Install Anodes on Row-2 Braces 4 30-Mar-20 02-Apr-20 68 02-Apr-20, Install Anodes on Row-2 Braces
J-Tubes 21 20-Mar-20 14-Apr-20 63 14-Apr-20, J-Tubes
F2-JK2-JACF1-128
Join of Row-2 J-Tubes 5 25-Mar-20 31-Mar-20 66 31-Mar-20, Join of Row-2 J-Tubes
F2-JK2-JACF1-129
Profilling of Row-2 J-Tubes 4 20-Mar-20 25-Mar-20 66 25-Mar-20, Profilling of Row-2 J-Tubes
F2-JK2-JACF1-130
Bending of Row-2 J-Tubes 4 31-Mar-20 03-Apr-20 66 03-Apr-20, Bending of Row-2 J-Tubes
F2-JK2-JACF1-131
Blast and Paint for Row-2 J-Tubes 3 07-Apr-20 10-Apr-20 63 10-Apr-20, Blast and Paint for Row-2 J-Tubes
F2-JK2-JACF1-132
Assembly Row-2 J-Tubes 3 10-Apr-20 14-Apr-20 63 14-Apr-20, Assembly Row-2 J-Tubes
F2-JK2-JACF1-133
Cut and Profile Row-2 J-Tubes Support 4 20-Mar-20 25-Mar-20 63 25-Mar-20, Cut and Profile Row-2 J-Tubes Support
F2-JK2-JACF1-134
Assembly Row-2 J-Tubes Support 2 25-Mar-20 28-Mar-20 63 28-Mar-20, Assembly Row-2 J-Tubes Support
F2-JK2-JACF1-135
Vulcanized Row-2 J-Tubes Support 2 28-Mar-20 31-Mar-20 63 31-Mar-20, Vulcanized Row-2 J-Tubes Support
F2-JK2-JACF1-136
Paint Row-2 J-Tubes Support 3 31-Mar-20 03-Apr-20 63 03-Apr-20, Paint Row-2 J-Tubes Support
F2-JK2-JACF1-137
Install J-Tubes Support on to Row-2 J-Tubes 3 03-Apr-20 07-Apr-20 63 07-Apr-20, Install J-Tubes Support on to Row-2 J-Tubes
Common 23 12-Mar-20 08-Apr-20 68 08-Apr-20, Common
Structure 3 12-Mar-20 16-Mar-20 72 16-Mar-20, Structure
F2-JK2-JACF1-69
Marking & Cutting of Leg and Brace Node 3 12-Mar-20 16-Mar-20 72 16-Mar-20, Marking & Cutting of Leg and Brace Node
F2-JK2-JACF1-70
Marking & Cutting of Brace Stub 3 12-Mar-20 16-Mar-20 72 16-Mar-20, Marking & Cutting of Brace Stub
F2-JK2-JACF1-71
Marking & Cutting of Leg and Brace Member 3 12-Mar-20 16-Mar-20 72 16-Mar-20, Marking & Cutting of Leg and Brace Member
Final Painting 23 12-Mar-20 08-Apr-20 68 08-Apr-20, Final Painting
F2-JK2-JACF1-72
Row-2 Touch up and Final Painting 3 02-Apr-20 07-Apr-20 68 07-Apr-20, Row-2 Touch up and Final Painting
F2-JK2-JACF1-73
Blast and Paint Leg and Brace (Initial Paint) 5 12-Mar-20 19-Mar-20 68 19-Mar-20, Blast and Paint Leg and Brace (Initial Paint)

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 13 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JACF1-74
Build Painting Habitat Protection 1 07-Apr-20 08-Apr-20 68 08-Apr-20, Build Painting Habitat Protection
F2-JK2-JACF1-75
Row-2 Ready for Assembly & Roll-up 0 08-Apr-20 68 08-Apr-20
Transition Piece 65 21-Feb-20 06-May-20 98 06-May-20, Transition Piece
F2-JK2-JACF1-1Assembly Strut Plate 21 13-Mar-20 07-Apr-20 117 07-Apr-20, Assembly Strut Plate
F2-JK2-JACF1-100
Fit Grating Supports 4 04-Mar-20 10-Mar-20 119 10-Mar-20, Fit Grating Supports
F2-JK2-JACF1-101
Fab Main Deck Handrails 4 27-Feb-20 03-Mar-20 120 03-Mar-20, Fab Main Deck Handrails
F2-JK2-JACF1-102
Fab Padeye inc Top of Jacket 4 28-Feb-20 04-Mar-20 145 04-Mar-20, Fab Padeye inc Top of Jacket
F2-JK2-JACF1-103
Blast and Paint Transition Piece 7 28-Apr-20 06-May-20 98 06-May-20, Blast and Paint Transition Piece
F2-JK2-JACF1-16
Fabrication of Can Transition Piece Barrel 24 07-Mar-20 04-Apr-20 49 04-Apr-20, Fabrication of Can Transition Piece Barrel
F2-JK2-JACF1-17
Fabrication of Strut Plate 18 21-Feb-20 13-Mar-20 20 13-Mar-20, Fabrication of Strut Plate
F2-JK2-JACF1-18
Fabrication of Internal Platform 21 21-Feb-20 17-Mar-20 131 17-Mar-20, Fabrication of Internal Platform
F2-JK2-JACF1-19
Fabrication of External Platform 25 21-Feb-20 21-Mar-20 131 21-Mar-20, Fabrication of External Platform
F2-JK2-JACF1-2Fabrication of Ring Stiffener 21 03-Apr-20 28-Apr-20 98 28-Apr-20, Fabrication of Ring Stiffener
F2-JK2-JACF1-3Fabrication of Crane Pedestal 21 17-Mar-20 10-Apr-20 92 10-Apr-20, Fabrication of Crane Pedestal
F2-JK2-JACF1-93
Galvanizing Handrails 5 03-Mar-20 07-Mar-20 120 07-Mar-20, Galvanizing Handrails
F2-JK2-JACF1-94
Erect Deck Plate Areas 5 28-Feb-20 04-Mar-20 118 04-Mar-20, Erect Deck Plate Areas
F2-JK2-JACF1-95
Transition Piece Fabrication Complete 0 28-Apr-20 98 28-Apr-20
F2-JK2-JACF1-96
Fabrication Assemble Walkways / Platforms 21 17-Mar-20 10-Apr-20 114 10-Apr-20, Fabrication Assemble Walkways / Platforms
F2-JK2-JACF1-97
Fit and Weld TP's Equipment Supports 5 29-Feb-20 06-Mar-20 118 06-Mar-20, Fit and Weld TP's Equipment Supports
F2-JK2-JACF1-98
Plate Profiling for Main Deck 5 21-Feb-20 27-Feb-20 73 27-Feb-20, Plate Profiling for Main Deck
F2-JK2-JACF1-99
Fab Main Deck Main Steel 5 22-Feb-20 28-Feb-20 73 28-Feb-20, Fab Main Deck Main Steel
Lifting Trunnion 7 28-Feb-20 07-Mar-20 73 07-Mar-20, Lifting Trunnion
F2-JK2-JACF1-104
Fabricate Lifting Trunion 7 28-Feb-20 07-Mar-20 73 07-Mar-20, Fabricate Lifting Trunion
Boat Landing 44 09-Mar-20 29-Apr-20 94 29-Apr-20, Boat Landing
F2-JK2-JACF1-123
Blast and Paint Boat Landing 5 23-Apr-20 29-Apr-20 94 29-Apr-20, Blast and Paint Boat Landing
F2-JK2-JACF1-124
Fabricate Boat Landing 21 09-Mar-20 02-Apr-20 45 02-Apr-20, Fabricate Boat Landing
F2-JK2-JACF1-159
Fabricate Boat Landing Access platform 24 26-Mar-20 23-Apr-20 94 23-Apr-20, Fabricate Boat Landing Access platform
F2-JK2-JACF1-160
Fabricate Boat Landing Ladders 15 03-Apr-20 21-Apr-20 96 21-Apr-20, Fabricate Boat Landing Ladders
Grouting Line 23 22-Apr-20 18-May-20 81 18-May-20, Grouting Line
F2-JK2-JACF1-126
Fabricate Grouting Line & Grouting Line Support 23 22-Apr-20 18-May-20 81 18-May-20, Fabricate Grouting Line & Grouting Line Support
Assembly 88 01-Apr-20 11-Jul-20 50 11-Jul-20, Assembly
Row Assembly 81 01-Apr-20 03-Jul-20 53 03-Jul-20, Row Assembly
F2-JK2-JACF1-113
Fabricate Upper Grillage & Truss Support 18 01-Apr-20 22-Apr-20 52 22-Apr-20, Fabricate Upper Grillage & Truss Support
F2-JK2-JACF1-114
Layout Concrete Blocks/ Grillages and Truss Support Steel 4 22-Apr-20 27-Apr-20 52 27-Apr-20, Layout Concrete Blocks/ Grillages and Truss Support Steel
Row-1 & 2 (Upper Jacket) Assembly 46 27-Apr-20 19-Jun-20 52 19-Jun-20, Row-1 & 2 (Upper Jacket) Assembly
F2-JK2-JACF1-115
Installation of Grouting Line 1 14-May-20 15-May-20 72 15-May-20, Installation of Grouting Line
F2-JK2-JACF1-117
Installation of J-Tube At Row-1B & 2A 5 14-May-20 21-May-20 77 21-May-20, Installation of J-Tube At Row-1B & 2A
F2-JK2-JACF1-118
Row-2 - Touch Up, 2nd Coat & Top Coat 3 16-Jun-20 19-Jun-20 53 19-Jun-20, Row-2 - Touch Up, 2nd Coat & Top Coat
F2-JK2-JACF1-119
Installation of Row-1B & 2B X-Brace 7 06-May-20 14-May-20 52 14-May-20, Installation of Row-1B & 2B X-Brace
F2-JK2-JACF1-120
Installation of Leg 1A & 1B Onto Support 1 27-Apr-20 28-Apr-20 52 28-Apr-20, Installation of Leg 1A & 1B Onto Support
F2-JK2-JACF1-121
Installation of Row-1A & 1B X-Brace 7 28-Apr-20 06-May-20 52 06-May-20, Installation of Row-1A & 1B X-Brace
F2-JK2-JACF1-122
Installation of Row-2A & 2B X-Brace in Final Position 7 08-Jun-20 16-Jun-20 52 16-Jun-20, Installation of Row-2A & 2B X-Brace in Final Position
F2-JK2-JACF1-142
Installation of Leg 2A & 2B Onto Support 1 27-Apr-20 28-Apr-20 59 28-Apr-20, Installation of Leg 2A & 2B Onto Support
F2-JK2-JACF1-143
Installation of Row-1A & 2A X-Brace 7 06-May-20 14-May-20 52 14-May-20, Installation of Row-1A & 2A X-Brace
F2-JK2-JACF1-144
Installation of Row-1A & 1B X-Brace in Final Position 7 30-May-20 08-Jun-20 52 08-Jun-20, Installation of Row-1A & 1B X-Brace in Final Position
F2-JK2-JACF1-145
Roll Up X-Brace Row A&B to Final Position 7 14-May-20 22-May-20 52 22-May-20, Roll Up X-Brace Row A&B to Final Position
F2-JK2-JACF1-146
Installing Tie-back for Fastener 7 22-May-20 30-May-20 52 30-May-20, Installing Tie-back for Fastener
F2-JK2-JACF1-147
Installation of Boat Landing 3 16-Jun-20 19-Jun-20 52 19-Jun-20, Installation of Boat Landing
Row-1 & 2 (Lower Jacket) Assembly 44 13-Apr-20 02-Jun-20 67 02-Jun-20, Row-1 & 2 (Lower Jacket) Assembly
F2-JK2-JACF1-116
Installation of Pile Stopper 4 13-May-20 16-May-20 67 16-May-20, Installation of Pile Stopper
F2-JK2-JACF1-148
Installation of Leg 1A & 1B Onto Support 1 13-Apr-20 14-Apr-20 67 14-Apr-20, Installation of Leg 1A & 1B Onto Support
F2-JK2-JACF1-149
Installation of Leg 2A & 2B Onto Support 1 13-Apr-20 14-Apr-20 74 14-Apr-20, Installation of Leg 2A & 2B Onto Support
F2-JK2-JACF1-150
Installation of Row-1A & 1B X-Brace 7 14-Apr-20 22-Apr-20 67 22-Apr-20, Installation of Row-1A & 1B X-Brace
F2-JK2-JACF1-151
Installation of Row-1B & 2B X-Brace 7 22-Apr-20 30-Apr-20 67 30-Apr-20, Installation of Row-1B & 2B X-Brace
F2-JK2-JACF1-152
Installation of Row-1A & 2A X-Brace 7 22-Apr-20 30-Apr-20 67 30-Apr-20, Installation of Row-1A & 2A X-Brace

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 14 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JACF1-153
Installation of Grouting Line 1 30-Apr-20 01-May-20 88 01-May-20, Installation of Grouting Line
F2-JK2-JACF1-154
Installation of J-Tube At Row-1B & 2A 5 30-Apr-20 06-May-20 77 06-May-20, Installation of J-Tube At Row-1B & 2A
F2-JK2-JACF1-155
Roll Up X-Brace Row A&B to Final Position 7 30-Apr-20 08-May-20 67 08-May-20, Roll Up X-Brace Row A&B to Final Position
F2-JK2-JACF1-156
Installing Tie-back for Fastener 4 08-May-20 13-May-20 67 13-May-20, Installing Tie-back for Fastener
F2-JK2-JACF1-157
Installation of Row-1A & 1B X-Brace in Final Position 7 16-May-20 25-May-20 67 25-May-20, Installation of Row-1A & 1B X-Brace in Final Position
F2-JK2-JACF1-158
Installation of Row-2A & 2B X-Brace in Final Position 7 25-May-20 02-Jun-20 67 02-Jun-20, Installation of Row-2A & 2B X-Brace in Final Position
Grouting Line 40 18-May-20 03-Jul-20 53 03-Jul-20, Grouting Line
F2-JK2-JACF1-125
Installation Of Grouting Line 5 29-Jun-20 03-Jul-20 53 03-Jul-20, Installation Of Grouting Line
F2-JK2-JACF1-127
Installation Grouting Line Support 7 18-May-20 26-May-20 81 26-May-20, Installation Grouting Line Support
Row Roll Up 7 19-Jun-20 29-Jun-20 52 29-Jun-20, Row Roll Up
F2-JK2-JACF1-105
Roll Up Of Lower Jacket To Final Position 2 19-Jun-20 22-Jun-20 52 22-Jun-20, Roll Up Of Lower Jacket To Final Position
F2-JK2-JACF1-106
Roll Up Of Upper Jacket To Final Position 5 22-Jun-20 29-Jun-20 52 29-Jun-20, Roll Up Of Upper Jacket To Final Position
Transition Piece (TP) 76 04-Apr-20 02-Jul-20 49 02-Jul-20, Transition Piece (TP)
F2-JK2-JACF1-10
Install Platform & Internal Structure into Upper Can 7 24-Jun-20 02-Jul-20 49 02-Jul-20, Install Platform & Internal Structure into Upper Can
F2-JK2-JACF1-11
Door opening & Installation of Door frame 5 22-Apr-20 28-Apr-20 88 28-Apr-20, Door opening & Installation of Door frame
F2-JK2-JACF1-12
Installation & Assembly of Strut 15 22-Apr-20 09-May-20 49 09-May-20, Installation & Assembly of Strut
F2-JK2-JACF1-13
Install Free-Issued Items 15 26-May-20 12-Jun-20 49 12-Jun-20, Install Free-Issued Items
F2-JK2-JACF1-14
Install Architectural items, Electrical & Instrument Equipments 15 22-Apr-20 09-May-20 78 09-May-20, Install Architectural items, Electrical & Instrument Equipments
F2-JK2-JACF1-15
Install External Platform & Handrail 12 25-Apr-20 09-May-20 78 09-May-20, Install External Platform & Handrail
F2-JK2-JACF1-4Installation & Assembly of Ring Stiffener 21 30-Apr-20 25-May-20 49 25-May-20, Installation & Assembly of Ring Stiffener
F2-JK2-JACF1-5Installation of Transition Piece Flange 15 08-May-20 26-May-20 49 26-May-20, Installation of Transition Piece Flange
F2-JK2-JACF1-6Install Crane Pedestal 12 10-Apr-20 24-Apr-20 92 24-Apr-20, Install Crane Pedestal
F2-JK2-JACF1-7Install Door Platform 10 28-Apr-20 09-May-20 78 09-May-20, Install Door Platform
F2-JK2-JACF1-8Blasting & Painting 10 12-Jun-20 24-Jun-20 49 24-Jun-20, Blasting & Painting
F2-JK2-JACF1-9Assemble Can Transition Piece Barrel to Main Deck 15 04-Apr-20 22-Apr-20 49 22-Apr-20, Assemble Can Transition Piece Barrel to Main Deck
Final Assembly 8 02-Jul-20 11-Jul-20 50 11-Jul-20, Final Ass embly
F2-JK2-JACF1-107
Installation of Transition Piece 3 02-Jul-20 06-Jul-20 49 06-Jul-20, Installation of Transition Piece
F2-JK2-JACF1-108
Installation of Mudmad Plate 5 04-Jul-20 10-Jul-20 49 10-Jul-20, Installation of Mudmad Plate
F2-JK2-JACF1-109
Installation of Lifting Trunnion 4 06-Jul-20 10-Jul-20 51 10-Jul-20, Installation of Lifting Trunnion
F2-JK2-JACF1-110
Installation of Skirt Pile Sleeve 2 04-Jul-20 07-Jul-20 49 07-Jul-20, Installation of Skirt Pile Sleeve
F2-JK2-JACF1-111
Final Touch Up Coating 3 08-Jul-20 11-Jul-20 49 11-Jul-20, Final Touch Up Coating
F2-JK2-JACF1-112
Installation of Lifting Slings 1 07-Jul-20 08-Jul-20 49 08-Jul-20, Installation of Lifting Slings
F2-JK2-JACF1-161
Jacket Fabrication Completed 0 11-Jul-20 49 11-Jul-20
Testing & Commissioning 9 03-Jul-20 14-Jul-20 49 14-Jul-20, Testing & Commissioning
Grouting & Gripper Test 3 03-Jul-20 08-Jul-20 53 08-Jul-20, Grouting & Gripper Test
F2-JK2-JACF1-20
Gripper Test 2 06-Jul-20 08-Jul-20 53 08-Jul-20, Gripper Test
F2-JK2-JACF1-21
Grouting Test 1 03-Jul-20 06-Jul-20 53 06-Jul-20, Grouting Test
Mechanical Completion 2 11-Jul-20 14-Jul-20 49 14-Jul-20, Mechanical Completion
F2-JK2-JACF1-22
Main Structure, Boat Landing, J-Tube, Transition Piece 2 11-Jul-20 14-Jul-20 49 14-Jul-20, Main Structure, Boat Landing, J-Tube, Transition Piece
Jacket & Piles Ready For Loadout 0 14-Jul-20 14-Jul-20 49 14-Jul-20, Jacket & Piles Ready For Loadout
F2-JK2-JACF1-23
Jacket Ready For Load Out 0 14-Jul-20 49 14-Jul-20
Jacket Foundation 2a 130 21-Feb-20 22-Jul-20 42 22-Jul-20, Jacket Foundation 2a
Fabrication 72 21-Feb-20 15-May-20 90 15-May-20, Fabrication
Pre-Fabrication 38 21-Feb-20 06-Apr-20 91 06-Apr-20, Pre-Fabrication
F2-JK2-JF02-47Rolling of Can Transition Piece Flange 10 25-Mar-20 06-Apr-20 91 06-Apr-20, Rolling of Can Transition Piece Flange
F2-JK2-JF02-48Rolling of Can Transition Piece Barrel 10 04-Mar-20 16-Mar-20 42 16-Mar-20, Rolling of Can Transition Piece Barrel
F2-JK2-JF02-79Rolling of Can Row 2 Brace 10 21-Feb-20 04-Mar-20 0 04-Mar-20, Rolling of Can Row 2 Brace
F2-JK2-JF02-80Rolling of Can Leg 1A & 1B 10 21-Feb-20 04-Mar-20 55 04-Mar-20, Rolling of Can Leg 1A & 1B
F2-JK2-JF02-81Rolling of Can Leg 2A & 2B 10 29-Feb-20 12-Mar-20 55 12-Mar-20, Rolling of Can Leg 2A & 2B
F2-JK2-JF02-82Rolling of Node Can Row 1 10 29-Feb-20 12-Mar-20 55 12-Mar-20, Rolling of Node Can Row 1
F2-JK2-JF02-83Rolling of Node Can Row 2 10 09-Mar-20 20-Mar-20 55 20-Mar-20, Rolling of Node Can Row 2
F2-JK2-JF02-84Rolling of Can Row 1 Brace 10 09-Mar-20 20-Mar-20 55 20-Mar-20, Rolling of Can Row 1 Brace
F2-JK2-JF02-86Rolling of J-Tubes & J-Tubes Support 10 17-Mar-20 28-Mar-20 56 28-Mar-20, Rolling of J-Tubes & J-Tubes Support
F2-JK2-JF02-87Rolling of Can Plan Level Tubular 10 17-Mar-20 28-Mar-20 91 28-Mar-20, Rolling of Can Plan Level Tubular
F2-JK2-JF02-88Rolling of Can Top Bay X-Brace 10 25-Mar-20 06-Apr-20 91 06-Apr-20, Rolling of Can Top Bay X-Brace

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 15 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
Row 1 Fabrication 42 04-Mar-20 22-Apr-20 96 22-Apr-20, Row 1 Fabrication
Legs 40 04-Mar-20 21-Apr-20 58 21-Apr-20, Legs
F2-JK2-JF02-100
Join of Can Legs 1B 9 09-Mar-20 19-Mar-20 70 19-Mar-20, Join of Can Legs 1B
F2-JK2-JF02-101
Mark and Profile Leg 1A & 1B Node 4 12-Mar-20 17-Mar-20 80 17-Mar-20, Mark and Profile Leg 1A & 1B Node
F2-JK2-JF02-102
Profilling of Legs 1A & 1B (Inc. Cones) 4 04-Mar-20 09-Mar-20 70 09-Mar-20, Profilling of Legs 1A & 1B (Inc. Cones)
F2-JK2-JF02-103
Join of Leg 1A & 1B Node 2 11-Apr-20 14-Apr-20 58 14-Apr-20, Join of Leg 1A & 1B Node
F2-JK2-JF02-104
Blasting and Painting for Leg 1A & 1B Node 5 14-Apr-20 21-Apr-20 58 21-Apr-20, Blasting and Painting for Leg 1A & 1B Node
F2-JK2-JF02-105
Assembly Leg 1A 3 09-Apr-20 11-Apr-20 55 11-Apr-20, Assembly Leg 1A
F2-JK2-JF02-106
Assembly Leg 1B 3 09-Apr-20 11-Apr-20 55 11-Apr-20, Assembly Leg 1B
F2-JK2-JF02-97
Install Stubs on to Leg 1A & 1B Nodes 2 10-Apr-20 13-Apr-20 55 13-Apr-20, Install Stubs on to Leg 1A & 1B Nodes
F2-JK2-JF02-98
Install Anodes on Row-1 Legs 4 11-Apr-20 16-Apr-20 57 16-Apr-20, Install Anodes on Row-1 Legs
F2-JK2-JF02-99
Join of Can Legs 1A 9 09-Mar-20 19-Mar-20 70 19-Mar-20, Join of Can Legs 1A
Braces 28 20-Mar-20 22-Apr-20 55 22-Apr-20, Braces
F2-JK2-JF02-108
Fit & Weld Top X Brace Between Legs 1A & 1B 5 13-Apr-20 18-Apr-20 55 18-Apr-20, Fit & Weld Top X Brace Between Legs 1A & 1B
F2-JK2-JF02-109
Join of Row-1 Can Brace (Inc. Stub) 13 25-Mar-20 09-Apr-20 55 09-Apr-20, Join of Row-1 Can Brace (Inc. Stub)
F2-JK2-JF02-110
Join of Can Brace for Between Row 1 & 2 (Inc. Stub) 13 25-Mar-20 09-Apr-20 55 09-Apr-20, Join of Can Brace for Between Row 1 & 2 (Inc. Stub)
F2-JK2-JF02-111
Assembly of Row-1 Top Brace 4 09-Apr-20 13-Apr-20 55 13-Apr-20, Assembly of Row-1 Top Brace
F2-JK2-JF02-112
Fit & Weld Row-2 K-Brace (Inc. Vertical Braces) 5 13-Apr-20 18-Apr-20 55 18-Apr-20, Fit & Weld Row-2 K-Brace (Inc. Vertical Braces)
F2-JK2-JF02-113
Assembly of Row-1 K-Brace 4 09-Apr-20 13-Apr-20 55 13-Apr-20, Assembly of Row-1 K-Brace
F2-JK2-JF02-114
Fit & Weld X-Brace Between Row 1 & 2 5 13-Apr-20 18-Apr-20 55 18-Apr-20, Fit & Weld X-Brace Between Row 1 & 2
F2-JK2-JF02-115
Assembly of Brace Between Row 1 & 2 4 09-Apr-20 13-Apr-20 55 13-Apr-20, Assembly of Brace Between Row 1 & 2
F2-JK2-JF02-116
Profilling of Row-1 Braces and Stubs 4 20-Mar-20 25-Mar-20 55 25-Mar-20, Profilling of Row-1 Braces and Stubs
F2-JK2-JF02-117
Install Anodes on Row-1 Braces 4 18-Apr-20 22-Apr-20 55 22-Apr-20, Install Anodes on Row-1 Braces
J-Tubes 19 28-Mar-20 20-Apr-20 98 20-Apr-20, J-Tubes
F2-JK2-JF02-119
Join of Row-1 J-Tubes 5 02-Apr-20 08-Apr-20 98 08-Apr-20, Join of Row-1 J-Tubes
F2-JK2-JF02-120
Profilling of Row-1 J-Tubes 4 28-Mar-20 02-Apr-20 98 02-Apr-20, Profilling of Row-1 J-Tubes
F2-JK2-JF02-121
Bending of Row-1 J-Tubes 4 08-Apr-20 11-Apr-20 98 11-Apr-20, Bending of Row-1 J-Tubes
F2-JK2-JF02-122
Blast and Paint for Row-1 J-Tubes 3 11-Apr-20 16-Apr-20 98 16-Apr-20, Blast and Paint for Row-1 J-Tubes
F2-JK2-JF02-123
Assembly Row-1 J-Tubes 3 16-Apr-20 20-Apr-20 98 20-Apr-20, Assembly Row-1 J-Tubes
F2-JK2-JF02-124
Cut and Profile Row-1 J-Tubes Support 4 28-Mar-20 02-Apr-20 98 02-Apr-20, Cut and Profile Row-1 J-Tubes Support
F2-JK2-JF02-125
Assembly Row-1 J-Tubes Support 2 02-Apr-20 06-Apr-20 98 06-Apr-20, Assembly Row-1 J-Tubes Support
F2-JK2-JF02-126
Paint Row-1 J-Tubes Support 3 06-Apr-20 09-Apr-20 98 09-Apr-20, Paint Row-1 J-Tubes Support
F2-JK2-JF02-127
Install J-Tubes Support on to Row-1 J-Tubes 3 09-Apr-20 11-Apr-20 98 11-Apr-20, Install J-Tubes Support on to Row-1 J-Tubes
Common 23 27-Mar-20 22-Apr-20 56 22-Apr-20, Common
Structure 3 27-Mar-20 31-Mar-20 63 31-Mar-20, Structure
F2-JK2-JF02-89
Marking & Cutting of Leg and Brace Node 3 27-Mar-20 31-Mar-20 63 31-Mar-20, Marking & Cutting of Leg and Brace Node
F2-JK2-JF02-90
Marking & Cutting of Brace Stub 3 27-Mar-20 31-Mar-20 63 31-Mar-20, Marking & Cutting of Brace Stub
F2-JK2-JF02-91
Marking & Cutting of Leg and Brace Member 3 27-Mar-20 31-Mar-20 63 31-Mar-20, Marking & Cutting of Leg and Brace Member
Final Painting 23 27-Mar-20 22-Apr-20 56 22-Apr-20, Final Painting
F2-JK2-JF02-92
Blast and Paint Leg and Brace (Initial Paint) 11 27-Mar-20 09-Apr-20 55 09-Apr-20, Blast and Paint Leg and Brace (Initial Paint)
F2-JK2-JF02-93
Build Painting Habitat Protection 1 18-Apr-20 21-Apr-20 58 21-Apr-20, Build Painting Habitat Protection
F2-JK2-JF02-94
Row-1 Ready for Assembly & Roll-up 0 21-Apr-20 58 21-Apr-20
F2-JK2-JF02-95
Row-1 Touch up and Final Painting 3 18-Apr-20 22-Apr-20 55 22-Apr-20, Row-1 Touch up and Final Painting
Row 2 Fabrication 42 04-Mar-20 22-Apr-20 56 22-Apr-20, Row 2 Fabrication
Legs 23 12-Mar-20 08-Apr-20 69 08-Apr-20, Legs
F2-JK2-JF02-136
Install Anodes on Row-2 Legs 4 30-Mar-20 03-Apr-20 68 03-Apr-20, Install Anodes on Row-2 Legs
F2-JK2-JF02-137
Join of Can Legs 2A 9 17-Mar-20 27-Mar-20 63 27-Mar-20, Join of Can Legs 2A
F2-JK2-JF02-138
Join of Can Legs 2B 9 17-Mar-20 27-Mar-20 63 27-Mar-20, Join of Can Legs 2B
F2-JK2-JF02-139
Profilling of Legs 2A & 2B (Inc. Cones) 4 12-Mar-20 17-Mar-20 63 17-Mar-20, Profilling of Legs 2A & 2B (Inc. Cones)
F2-JK2-JF02-141
Mark and Profile Leg 2A & 2B Node 4 20-Mar-20 25-Mar-20 73 25-Mar-20, Mark and Profile Leg 2A & 2B Node
F2-JK2-JF02-142
Join of Leg 2A & 2B Node 2 30-Mar-20 01-Apr-20 69 01-Apr-20, Join of Leg 2A & 2B Node
F2-JK2-JF02-143
Blasting and Painting for Leg 2A & 2B Node (Initial) 5 01-Apr-20 08-Apr-20 69 08-Apr-20, Blasting and Painting for Leg 2A & 2B Node (Initial)
F2-JK2-JF02-144
Assembly Leg 2A 3 27-Mar-20 30-Mar-20 61 30-Mar-20, Assembly Leg 2A
F2-JK2-JF02-145
Assembly Leg 2B 3 27-Mar-20 30-Mar-20 61 30-Mar-20, Assembly Leg 2B
F2-JK2-JF02-146
Install Stubs on to Leg 2A & 2B Nodes 2 30-Mar-20 01-Apr-20 61 01-Apr-20, Install Stubs on to Leg 2A & 2B Nodes

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 16 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
Braces 32 04-Mar-20 10-Apr-20 61 10-Apr-20, Braces
F2-JK2-JF02-147
Fit & Weld Top X-Brace Between Legs 2A & 2B 4 01-Apr-20 06-Apr-20 64 06-Apr-20, Fit & Weld Top X-Brace Between Legs 2A & 2B
F2-JK2-JF02-148
Fit & Weld Mid X-Brace Between Legs 2A & 2B 4 01-Apr-20 06-Apr-20 64 06-Apr-20, Fit & Weld Mid X-Brace Between Legs 2A & 2B
F2-JK2-JF02-149
Join of Row-2 Can Brace (Inc. Stub) 10 09-Mar-20 20-Mar-20 61 20-Mar-20, Join of Row-2 Can Brace (Inc. Stub)
F2-JK2-JF02-150
Assembly of Row-2 Top Brace 3 27-Mar-20 31-Mar-20 65 31-Mar-20, Assembly of Row-2 Top Brace
F2-JK2-JF02-152
Assembly of Row-2 Mid Brace 3 27-Mar-20 31-Mar-20 65 31-Mar-20, Assembly of Row-2 Mid Brace
F2-JK2-JF02-153
Profilling of Row-2 Braces and Stubs 4 04-Mar-20 09-Mar-20 61 09-Mar-20, Profilling of Row-2 Braces and Stubs
F2-JK2-JF02-154
Install Anodes on Row-2 Braces 4 07-Apr-20 10-Apr-20 61 10-Apr-20, Install Anodes on Row-2 Braces
F2-JK2-JF02-44
Fit & Weld Row-2 K-Brace (Inc. Vertical Braces) 5 01-Apr-20 07-Apr-20 61 07-Apr-20, Fit & Weld Row-2 K-Brace (Inc. Vertical Braces)
F2-JK2-JF02-45
Assembly of Row-2 K-Brace 4 27-Mar-20 31-Mar-20 62 31-Mar-20, Assembly of Row-2 K-Brace
J-Tubes 21 28-Mar-20 22-Apr-20 56 22-Apr-20, J-Tubes
F2-JK2-JF02-33
Join of Row-2 J-Tubes 5 02-Apr-20 08-Apr-20 59 08-Apr-20, Join of Row-2 J-Tubes
F2-JK2-JF02-34
Profilling of Row-2 J-Tubes 4 28-Mar-20 02-Apr-20 59 02-Apr-20, Profilling of Row-2 J-Tubes
F2-JK2-JF02-36
Bending of Row-2 J-Tubes 4 08-Apr-20 11-Apr-20 59 11-Apr-20, Bending of Row-2 J-Tubes
F2-JK2-JF02-37
Blast and Paint for Row-2 J-Tubes 3 15-Apr-20 18-Apr-20 56 18-Apr-20, Blast and Paint for Row-2 J-Tubes
F2-JK2-JF02-38
Assembly Row-2 J-Tubes 3 18-Apr-20 22-Apr-20 56 22-Apr-20, Assembly Row-2 J-Tubes
F2-JK2-JF02-39
Cut and Profile Row-2 J-Tubes Support 4 28-Mar-20 02-Apr-20 56 02-Apr-20, Cut and Profile Row-2 J-Tubes Support
F2-JK2-JF02-40
Assembly Row-2 J-Tubes Support 2 02-Apr-20 06-Apr-20 56 06-Apr-20, Assembly Row-2 J-Tubes Support
F2-JK2-JF02-41
Vulcanized Row-2 J-Tubes Support 2 06-Apr-20 08-Apr-20 56 08-Apr-20, Vulcanized Row-2 J-Tubes Support
F2-JK2-JF02-42
Paint Row-2 J-Tubes Support 3 08-Apr-20 11-Apr-20 56 11-Apr-20, Paint Row-2 J-Tubes Support
F2-JK2-JF02-43
Install J-Tubes Support on to Row-2 J-Tubes 3 11-Apr-20 15-Apr-20 56 15-Apr-20, Install J-Tubes Support on to Row-2 J-Tubes
Common 23 20-Mar-20 16-Apr-20 61 16-Apr-20, Common
Structure 3 20-Mar-20 24-Mar-20 65 24-Mar-20, Structure
F2-JK2-JF02-128
Marking & Cutting of Leg and Brace Node 3 20-Mar-20 24-Mar-20 65 24-Mar-20, Marking & Cutting of Leg and Brace Node
F2-JK2-JF02-130
Marking & Cutting of Brace Stub 3 20-Mar-20 24-Mar-20 65 24-Mar-20, Marking & Cutting of Brace Stub
F2-JK2-JF02-131
Marking & Cutting of Leg and Brace Member 3 20-Mar-20 24-Mar-20 65 24-Mar-20, Marking & Cutting of Leg and Brace Member
Final Painting 23 20-Mar-20 16-Apr-20 61 16-Apr-20, Final Painting
F2-JK2-JF02-132
Row-2 Touch up and Final Painting 3 10-Apr-20 15-Apr-20 61 15-Apr-20, Row-2 Touch up and Final Painting
F2-JK2-JF02-133
Blast and Paint Leg and Brace (Initial Paint) 5 20-Mar-20 27-Mar-20 61 27-Mar-20, Blast and Paint Leg and Brace (Initial Paint)
F2-JK2-JF02-134
Build Painting Habitat Protection 1 15-Apr-20 16-Apr-20 61 16-Apr-20, Build Painting Habitat Protection
F2-JK2-JF02-135
Row-2 Ready for Assembly & Roll-up 0 16-Apr-20 61 16-Apr-20
Transition Piece 65 29-Feb-20 14-May-20 91 14-May-20, Transition Piece
F2-JK2-JF02-13Fabrication of Strut Plate 18 29-Feb-20 21-Mar-20 20 21-Mar-20, Fabrication of Strut Plate
F2-JK2-JF02-155G alvanizing Handrails 5 11-Mar-20 16-Mar-20 113 16-Mar-20, Galvanizing Handrails
F2-JK2-JF02-156Erect Deck Plate Areas 5 07-Mar-20 12-Mar-20 111 12-Mar-20, Erect Deck Plate Areas
F2-JK2-JF02-157Transition Piece Fabrication Complete 0 06-May-20 91 06-May-20
F2-JK2-JF02-158Fabrication Assemble Walkways / Platforms 21 21-Mar-20 15-Apr-20 110 15-Apr-20, Fabrication Assemble Walkways / Platforms
F2-JK2-JF02-159Fit and Weld TP's Equipment Supports 5 09-Mar-20 14-Mar-20 111 14-Mar-20, Fit and Weld TP's Equipment Supports
F2-JK2-JF02-160Plate Profiling for Main Deck 5 29-Feb-20 06-Mar-20 66 06-Mar-20, Plate Profiling for Main Deck
F2-JK2-JF02-161Fab Main Deck Main Steel 5 02-Mar-20 07-Mar-20 66 07-Mar-20, Fab Main Deck Main Steel
F2-JK2-JF02-2 Fabrication of Can Transition Piece Barrel 24 16-Mar-20 13-Apr-20 42 13-Apr-20, Fabrication of Can Transition Piece Barrel
F2-JK2-JF02-24Fabrication of Internal Platform 21 29-Feb-20 25-Mar-20 124 25-Mar-20, Fabrication of Internal Platform
F2-JK2-JF02-3 Fit Grating Supports 4 12-Mar-20 18-Mar-20 112 18-Mar-20, Fit Grating Supports
F2-JK2-JF02-35Fabrication of External Platform 25 29-Feb-20 29-Mar-20 124 29-Mar-20, Fabrication of External Platform
F2-JK2-JF02-4 Fab Main Deck Handrails 4 06-Mar-20 11-Mar-20 113 11-Mar-20, Fab Main Deck Handrails
F2-JK2-JF02-46Assembly Strut Plate 21 21-Mar-20 15-Apr-20 110 15-Apr-20, Assembly Strut Plate
F2-JK2-JF02-5 Fab Padeye inc Top of Jacket 4 07-Mar-20 12-Mar-20 138 12-Mar-20, Fab Padeye inc Top of Jacket
F2-JK2-JF02-57Fabrication of Ring Stiffener 21 11-Apr-20 06-May-20 91 06-May-20, Fabrication of Ring Stiffener
F2-JK2-JF02-6 Blast and Paint Transition Piece 7 06-May-20 14-May-20 91 14-May-20, Blast and Paint Transition Piece
F2-JK2-JF02-68Fabrication of Crane Pedestal 21 21-Mar-20 15-Apr-20 88 15-Apr-20, Fabrication of Crane Pedestal
Lifting Trunnion 7 07-Mar-20 16-Mar-20 66 16-Mar-20, Lifting Trunnion
F2-JK2-JF02-7 Fabricate Lifting Trunion 7 07-Mar-20 16-Mar-20 66 16-Mar-20, Fabricate Lifting Trunion
Boat Landing 44 17-Mar-20 07-May-20 87 07-May-20, Boat Landing
F2-JK2-JF02-28Blast and Paint Boat Landing 5 01-May-20 07-May-20 87 07-May-20, Blast and Paint Boat Landing
F2-JK2-JF02-29Fabricate Boat Landing 21 17-Mar-20 10-Apr-20 45 10-Apr-20, Fabricate Boat Landing

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 17 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF02-67Fabricate Boat Landing Access platform 24 03-Apr-20 01-May-20 87 01-May-20, Fabricate Boat Landing Access platform
F2-JK2-JF02-69Fabricate Boat Landing Ladders 15 11-Apr-20 29-Apr-20 89 29-Apr-20, Fabricate Boat Landing Ladders
Grouting Line 23 18-Apr-20 15-May-20 84 15-May-20, Grouting Line
F2-JK2-JF02-31Fabricate Grouting Line & Grouting Line Support 23 18-Apr-20 15-May-20 84 15-May-20, Fabricate Grouting Line & Grouting Line Support
Assembly 109 16-Mar-20 20-Jul-20 43 20-Jul-20, Assembly
Row Assembly 92 16-Mar-20 01-Jul-20 55 01-Jul-20, Row Assembly
F2-JK2-JF02-17Fabricate Upper Grillage & Truss Support 18 16-Mar-20 06-Apr-20 66 06-Apr-20, Fabricate Upper Grillage & Truss Support
F2-JK2-JF02-18Layout Concrete Blocks/ Grillages and Truss Support Steel 4 18-Apr-20 24-Apr-20 55 24-Apr-20, Layout Concrete Blocks/ Grillages and Truss Support Steel
Row-1 & 2 (Upper Jacket) Assembly 46 24-Apr-20 17-Jun-20 55 17-Jun-20, Row-1 & 2 (Upper Jacket) Assembly
F2-JK2-JF02-19
Installation of Grouting Line 1 12-May-20 13-May-20 75 13-May-20, Installation of Grouting Line
F2-JK2-JF02-21
Installation of J-Tube At Row-1B & 2A 5 12-May-20 18-May-20 79 18-May-20, Installation of J-Tube At Row-1B & 2A
F2-JK2-JF02-22
Row-2 - Touch Up, 2nd Coat & Top Coat 3 13-Jun-20 16-Jun-20 55 16-Jun-20, Row-2 - Touch Up, 2nd Coat & Top Coat
F2-JK2-JF02-23
Installation of Row-1B & 2B X-Brace 7 04-May-20 12-May-20 55 12-May-20, Installation of Row-1B & 2B X-Brace
F2-JK2-JF02-25
Installation of Leg 1A & 1B Onto Support 1 24-Apr-20 25-Apr-20 55 25-Apr-20, Installation of Leg 1A & 1B Onto Support
F2-JK2-JF02-26
Installation of Row-1A & 1B X-Brace 7 25-Apr-20 04-May-20 55 04-May-20, Installation of Row-1A & 1B X-Brace
F2-JK2-JF02-27
Installation of Row-2A & 2B X-Brace in Final Position 7 05-Jun-20 13-Jun-20 55 13-Jun-20, Installation of Row-2A & 2B X-Brace in Final Position
F2-JK2-JF02-49
Installation of Leg 2A & 2B Onto Support 1 24-Apr-20 25-Apr-20 62 25-Apr-20, Installation of Leg 2A & 2B Onto Support
F2-JK2-JF02-50
Installation of Row-1A & 2A X-Brace 7 04-May-20 12-May-20 55 12-May-20, Installation of Row-1A & 2A X-Brace
F2-JK2-JF02-51
Installation of Row-1A & 1B X-Brace in Final Position 7 28-May-20 05-Jun-20 55 05-Jun-20, Installation of Row-1A & 1B X-Brace in Final Position
F2-JK2-JF02-52
Roll Up X-Brace Row A&B to Final Position 7 12-May-20 20-May-20 55 20-May-20, Roll Up X-Brace Row A&B to Final Position
F2-JK2-JF02-53
Installing Tie-back for Fastener 7 20-May-20 28-May-20 55 28-May-20, Installing Tie-back for Fastener
F2-JK2-JF02-54
Installation of Boat Landing 3 13-Jun-20 17-Jun-20 55 17-Jun-20, Installation of Boat Landing
Row-1 & 2 (Lower Jacket) Assembly 44 21-Apr-20 10-Jun-20 60 10-Jun-20, Row-1 & 2 (Lower Jacket) Assembly
F2-JK2-JF02-20
Installation of Pile Stopper 4 21-May-20 25-May-20 60 25-May-20, Installation of Pile Stopper
F2-JK2-JF02-55
Installation of Grouting Line 1 08-May-20 09-May-20 81 09-May-20, Installation of Grouting Line
F2-JK2-JF02-56
Installation of J-Tube At Row-1B & 2A 5 08-May-20 14-May-20 70 14-May-20, Installation of J-Tube At Row-1B & 2A
F2-JK2-JF02-58
Installation of Row-1B & 2B X-Brace 7 30-Apr-20 08-May-20 60 08-May-20, Installation of Row-1B & 2B X-Brace
F2-JK2-JF02-59
Installation of Leg 1A & 1B Onto Support 1 21-Apr-20 22-Apr-20 60 22-Apr-20, Installation of Leg 1A & 1B Onto Support
F2-JK2-JF02-60
Installation of Row-1A & 1B X-Brace 7 22-Apr-20 30-Apr-20 60 30-Apr-20, Installation of Row-1A & 1B X-Brace
F2-JK2-JF02-61
Installation of Row-2A & 2B X-Brace in Final Position 7 02-Jun-20 10-Jun-20 60 10-Jun-20, Installation of Row-2A & 2B X-Brace in Final Position
F2-JK2-JF02-62
Installation of Leg 2A & 2B Onto Support 1 21-Apr-20 22-Apr-20 67 22-Apr-20, Installation of Leg 2A & 2B Onto Support
F2-JK2-JF02-63
Installation of Row-1A & 2A X-Brace 7 30-Apr-20 08-May-20 60 08-May-20, Installation of Row-1A & 2A X-Brace
F2-JK2-JF02-64
Installation of Row-1A & 1B X-Brace in Final Position 7 25-May-20 02-Jun-20 60 02-Jun-20, Installation of Row-1A & 1B X-Brace in Final Position
F2-JK2-JF02-65
Roll Up X-Brace Row A&B to Final Position 7 08-May-20 16-May-20 60 16-May-20, Roll Up X-Brace Row A&B to Final Position
F2-JK2-JF02-66
Installing Tie-back for Fastener 4 16-May-20 21-May-20 60 21-May-20, Installing Tie-back for Fastener
Grouting Line 40 15-May-20 01-Jul-20 55 01-Jul-20, Grouting Line
F2-JK2-JF02-30
Installation Of Grouting Line 5 25-Jun-20 01-Jul-20 55 01-Jul-20, Installation Of Grouting Line
F2-JK2-JF02-32
Installation Grouting Line Support 7 15-May-20 23-May-20 84 23-May-20, Installation Grouting Line Support
Row Roll Up 7 17-Jun-20 25-Jun-20 55 25-Jun-20, Row Roll Up
F2-JK2-JF02-8 Roll Up Of Lower Jacket To Final Position 2 17-Jun-20 19-Jun-20 55 19-Jun-20, Roll Up Of Lower Jacket To Final Position
F2-JK2-JF02-9 Roll Up Of Upper Jacket To Final Position 5 19-Jun-20 25-Jun-20 55 25-Jun-20, Roll Up Of Upper Jacket To Final Position
Transition Piece (TP) 76 13-Apr-20 10-Jul-20 42 10-Jul-20, Transition Piece (TP)
F2-JK2-JF02-1 Install Door Platform 10 06-May-20 18-May-20 71 18-May-20, Install Door Platform
F2-JK2-JF02-107Door opening & Installation of Door frame 5 30-Apr-20 06-May-20 81 06-May-20, Door opening & Installation of Door frame
F2-JK2-JF02-118Installation & Assembly of Strut 15 30-Apr-20 18-May-20 42 18-May-20, Installation & Assembly of Strut
F2-JK2-JF02-129Install Free-Issued Items 15 03-Jun-20 20-Jun-20 42 20-Jun-20, Install Free-Issued Items
F2-JK2-JF02-140Install Architectural items, Electrical & Instrument Equipments 15 30-Apr-20 18-May-20 71 18-May-20, Install Architectural items, Electrical & Instrument Equipments
F2-JK2-JF02-151Install External Platform & Handrail 12 04-May-20 18-May-20 71 18-May-20, Install External Platform & Handrail
F2-JK2-JF02-71Installation & Assembly of Ring Stiffener 21 08-May-20 02-Jun-20 42 02-Jun-20, Installation & Assembly of Ring Stiffener
F2-JK2-JF02-72Installation of Transition Piece Flange 15 16-May-20 03-Jun-20 42 03-Jun-20, Installation of Transition Piece Flange
F2-JK2-JF02-73Install Crane Pedestal 12 15-Apr-20 29-Apr-20 88 29-Apr-20, Install Crane Pedestal
F2-JK2-JF02-74Blasting & Painting 10 20-Jun-20 02-Jul-20 42 02-Jul-20, Blasting & Painting
F2-JK2-JF02-85Assemble Can Transition Piece Barrel to Main Deck 15 13-Apr-20 30-Apr-20 42 30-Apr-20, Assemble Can Transition Piece Barrel to Main Deck
F2-JK2-JF02-96Install Platform & Internal Structure into Upper Can 7 02-Jul-20 10-Jul-20 42 10-Jul-20, Install Platform & Internal Structure into Upper Can
Final Assembly 8 10-Jul-20 20-Jul-20 43 20-Jul-20, Final Assembly

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 18 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF02-10Installation of Transition Piece 3 10-Jul-20 14-Jul-20 42 14-Jul-20, Installation of Transition Piece
F2-JK2-JF02-11 Installation of Mudmad Plate 5 13-Jul-20 18-Jul-20 42 18-Jul-20, Installation of Mudmad Plate
F2-JK2-JF02-12Installation of Lifting Trunnion 4 14-Jul-20 18-Jul-20 44 18-Jul-20, Installation of Lifting Trunnion
F2-JK2-JF02-14Installation of Skirt Pile Sleeve 2 13-Jul-20 15-Jul-20 42 15-Jul-20, Installation of Skirt Pile Sleeve
F2-JK2-JF02-15Final Touch Up Coating 3 16-Jul-20 20-Jul-20 42 20-Jul-20, Final Touch Up Coating
F2-JK2-JF02-16Installation of Lifting Slings 1 15-Jul-20 16-Jul-20 42 16-Jul-20, Installation of Lifting Slings
F2-JK2-JF02-70Jacket Fabrication Completed 0 20-Jul-20 42 20-Jul-20
Testing & Commissioning 18 01-Jul-20 22-Jul-20 42 22-Jul-20, Testing & Commissioning
Grouting & Gripper Test 3 01-Jul-20 04-Jul-20 55 04-Jul-20, Grouting & Gripper Test
F2-JK2-JF02-75Gripper Test 2 02-Jul-20 04-Jul-20 55 04-Jul-20, Gripper Test
F2-JK2-JF02-76Grouting Test 1 01-Jul-20 02-Jul-20 55 02-Jul-20, Grouting Test
Mechanical Completion 2 20-Jul-20 22-Jul-20 42 22-Jul-20, Mechanical Completion
F2-JK2-JF02-77Main Structure, Boat Landing, J-Tube, Transition Piece 2 20-Jul-20 22-Jul-20 42 22-Jul-20, Main Structure, Boat Landing, J-Tube, Transition Piece
Jacket & Piles Ready For Loadout 0 22-Jul-20 22-Jul-20 42 22-Jul-20, Jacket & Piles Ready For Loadout
F2-JK2-JF02-78Jacket Ready For Load Out 0 22-Jul-20 42 22-Jul-20
Jacket Foundation 3a 130 29-Feb-20 30-Jul-20 35 30-Jul-20, Jacket Foundation 3a
Fabrication 72 29-Feb-20 23-May-20 83 23-May-20, Fabrication
Pre-Fabrication 38 29-Feb-20 14-Apr-20 84 14-Apr-20, Pre-Fabrication
F2-JK2-JF03-140Rolling of Can Transition Piece Flange 10 02-Apr-20 14-Apr-20 84 14-Apr-20, Rolling of Can Transition Piece Flange
F2-JK2-JF03-141Rolling of Can Transition Piece Barrel 10 12-Mar-20 24-Mar-20 35 24-Mar-20, Rolling of Can Transition Piece Barrel
F2-JK2-JF03-24Rolling of Can Row 2 Brace 10 29-Feb-20 12-Mar-20 0 12-Mar-20, Rolling of Can Row 2 Brace
F2-JK2-JF03-25Rolling of Can Leg 1A & 1B 10 29-Feb-20 12-Mar-20 48 12-Mar-20, Rolling of Can Leg 1A & 1B
F2-JK2-JF03-26Rolling of Can Leg 2A & 2B 10 09-Mar-20 20-Mar-20 48 20-Mar-20, Rolling of Can Leg 2A & 2B
F2-JK2-JF03-27Rolling of Node Can Row 1 10 09-Mar-20 20-Mar-20 48 20-Mar-20, Rolling of Node Can Row 1
F2-JK2-JF03-28Rolling of Node Can Row 2 10 17-Mar-20 28-Mar-20 48 28-Mar-20, Rolling of Node Can Row 2
F2-JK2-JF03-29Rolling of Can Row 1 Brace 10 17-Mar-20 28-Mar-20 48 28-Mar-20, Rolling of Can Row 1 Brace
F2-JK2-JF03-30Rolling of J-Tubes & J-Tubes Support 10 25-Mar-20 06-Apr-20 49 06-Apr-20, Rolling of J-Tubes & J-Tubes Support
F2-JK2-JF03-31Rolling of Can Plan Level Tubular 10 25-Mar-20 06-Apr-20 84 06-Apr-20, Rolling of Can Plan Level Tubular
F2-JK2-JF03-32Rolling of Can Top Bay X-Brace 10 02-Apr-20 14-Apr-20 84 14-Apr-20, Rolling of Can Top Bay X-Brace
Row 1 Fabrication 42 12-Mar-20 30-Apr-20 89 30-Apr-20, Row 1 Fabrication
Legs 40 12-Mar-20 29-Apr-20 51 29-Apr-20, Legs
F2-JK2-JF03-40
Install Stubs on to Leg 1A & 1B Nodes 2 18-Apr-20 21-Apr-20 48 21-Apr-20, Install Stubs on to Leg 1A & 1B Nodes
F2-JK2-JF03-41
Install Anodes on Row-1 Legs 4 20-Apr-20 24-Apr-20 50 24-Apr-20, Install Anodes on Row-1 Legs
F2-JK2-JF03-42
Join of Can Legs 1A 9 17-Mar-20 27-Mar-20 63 27-Mar-20, Join of Can Legs 1A
F2-JK2-JF03-43
Join of Can Legs 1B 9 17-Mar-20 27-Mar-20 63 27-Mar-20, Join of Can Legs 1B
F2-JK2-JF03-44
Mark and Profile Leg 1A & 1B Node 4 20-Mar-20 25-Mar-20 73 25-Mar-20, Mark and Profile Leg 1A & 1B Node
F2-JK2-JF03-45
Profilling of Legs 1A & 1B (Inc. Cones) 4 12-Mar-20 17-Mar-20 63 17-Mar-20, Profilling of Legs 1A & 1B (Inc. Cones)
F2-JK2-JF03-46
Join of Leg 1A & 1B Node 2 20-Apr-20 22-Apr-20 51 22-Apr-20, Join of Leg 1A & 1B Node
F2-JK2-JF03-47
Blasting and Painting for Leg 1A & 1B Node 5 22-Apr-20 29-Apr-20 51 29-Apr-20, Blasting and Painting for Leg 1A & 1B Node
F2-JK2-JF03-48
Assembly Leg 1A 3 17-Apr-20 20-Apr-20 48 20-Apr-20, Assembly Leg 1A
F2-JK2-JF03-49
Assembly Leg 1B 3 17-Apr-20 20-Apr-20 48 20-Apr-20, Assembly Leg 1B
Braces 28 28-Mar-20 30-Apr-20 48 30-Apr-20, Braces
F2-JK2-JF03-50
Fit & Weld Top X Brace Between Legs 1A & 1B 5 21-Apr-20 27-Apr-20 48 27-Apr-20, Fit & Weld Top X Brace Between Legs 1A & 1B
F2-JK2-JF03-51
Join of Row-1 Can Brace (Inc. Stub) 13 02-Apr-20 17-Apr-20 48 17-Apr-20, Join of Row-1 Can Brace (Inc. Stub)
F2-JK2-JF03-52
Join of Can Brace for Between Row 1 & 2 (Inc. Stub) 13 02-Apr-20 17-Apr-20 48 17-Apr-20, Join of Can Brace for Between Row 1 & 2 (Inc. Stub)
F2-JK2-JF03-53
Assembly of Row-1 Top Brace 4 17-Apr-20 21-Apr-20 48 21-Apr-20, Assembly of Row-1 Top Brace
F2-JK2-JF03-54
Fit & Weld Row-2 K-Brace (Inc. Vertical Braces) 5 21-Apr-20 27-Apr-20 48 27-Apr-20, Fit & Weld Row-2 K-Brace (Inc. Vertical Braces)
F2-JK2-JF03-55
Assembly of Row-1 K-Brace 4 17-Apr-20 21-Apr-20 48 21-Apr-20, Assembly of Row-1 K-Brace
F2-JK2-JF03-56
Fit & Weld X-Brace Between Row 1 & 2 5 21-Apr-20 27-Apr-20 48 27-Apr-20, Fit & Weld X-Brace Between Row 1 & 2
F2-JK2-JF03-57
Assembly of Brace Between Row 1 & 2 4 17-Apr-20 21-Apr-20 48 21-Apr-20, Assembly of Brace Between Row 1 & 2
F2-JK2-JF03-58
Profilling of Row-1 Braces and Stubs 4 28-Mar-20 02-Apr-20 48 02-Apr-20, Profilling of Row-1 Braces and Stubs
F2-JK2-JF03-59
Install Anodes on Row-1 Braces 4 27-Apr-20 30-Apr-20 48 30-Apr-20, Install Anodes on Row-1 Braces
J-Tubes 19 06-Apr-20 28-Apr-20 91 28-Apr-20, J-Tubes
F2-JK2-JF03-60
Join of Row-1 J-Tubes 5 10-Apr-20 16-Apr-20 91 16-Apr-20, Join of Row-1 J-Tubes
F2-JK2-JF03-61
Profilling of Row-1 J-Tubes 4 06-Apr-20 10-Apr-20 91 10-Apr-20, Profilling of Row-1 J-Tubes

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 19 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF03-62
Bending of Row-1 J-Tubes 4 16-Apr-20 20-Apr-20 91 20-Apr-20, Bending of Row-1 J-Tubes
F2-JK2-JF03-63
Blast and Paint for Row-1 J-Tubes 3 20-Apr-20 24-Apr-20 91 24-Apr-20, Blast and Paint for Row-1 J-Tubes
F2-JK2-JF03-64
Assembly Row-1 J-Tubes 3 24-Apr-20 28-Apr-20 91 28-Apr-20, Assembly Row-1 J-Tubes
F2-JK2-JF03-65
Cut and Profile Row-1 J-Tubes Support 4 06-Apr-20 10-Apr-20 91 10-Apr-20, Cut and Profile Row-1 J-Tubes Support
F2-JK2-JF03-66
Assembly Row-1 J-Tubes Support 2 10-Apr-20 14-Apr-20 91 14-Apr-20, Assembly Row-1 J-Tubes Support
F2-JK2-JF03-67
Paint Row-1 J-Tubes Support 3 14-Apr-20 17-Apr-20 91 17-Apr-20, Paint Row-1 J-Tubes Support
F2-JK2-JF03-68
Install J-Tubes Support on to Row-1 J-Tubes 3 17-Apr-20 20-Apr-20 91 20-Apr-20, Install J-Tubes Support on to Row-1 J-Tubes
Common 23 04-Apr-20 30-Apr-20 49 30-Apr-20, Common
Structure 3 04-Apr-20 08-Apr-20 56 08-Apr-20, Structure
F2-JK2-JF03-33
Marking & Cutting of Leg and Brace Node 3 04-Apr-20 08-Apr-20 56 08-Apr-20, Marking & Cutting of Leg and Brace Node
F2-JK2-JF03-34
Marking & Cutting of Brace Stub 3 04-Apr-20 08-Apr-20 56 08-Apr-20, Marking & Cutting of Brace Stub
F2-JK2-JF03-35
Marking & Cutting of Leg and Brace Member 3 04-Apr-20 08-Apr-20 56 08-Apr-20, Marking & Cutting of Leg and Brace Member
Final Painting 23 04-Apr-20 30-Apr-20 49 30-Apr-20, Final Painting
F2-JK2-JF03-36
Blast and Paint Leg and Brace (Initial Paint) 11 04-Apr-20 17-Apr-20 48 17-Apr-20, Blast and Paint Leg and Brace (Initial Paint)
F2-JK2-JF03-37
Build Painting Habitat Protection 1 27-Apr-20 29-Apr-20 51 29-Apr-20, Build Painting Habitat Protection
F2-JK2-JF03-38
Row-1 Ready for Assembly & Roll-up 0 29-Apr-20 51 29-Apr-20
F2-JK2-JF03-39
Row-1 Touch up and Final Painting 3 27-Apr-20 30-Apr-20 48 30-Apr-20, Row-1 Touch up and Final Painting
Row 2 Fabrication 42 12-Mar-20 30-Apr-20 49 30-Apr-20, Row 2 Fabrication
Legs 23 20-Mar-20 16-Apr-20 62 16-Apr-20, Legs
F2-JK2-JF03-76
Install Anodes on Row-2 Legs 4 07-Apr-20 11-Apr-20 61 11-Apr-20, Install Anodes on Row- 2 Legs
F2-JK2-JF03-77
Join of Can Legs 2A 9 25-Mar-20 04-Apr-20 56 04-Apr-20, Join of Can Legs 2A
F2-JK2-JF03-78
Join of Can Legs 2B 9 25-Mar-20 04-Apr-20 56 04-Apr-20, Join of Can Legs 2B
F2-JK2-JF03-79
Profilling of Legs 2A & 2B (Inc. Cones) 4 20-Mar-20 25-Mar-20 56 25-Mar-20, Profilling of Legs 2A & 2B (Inc. Cones)
F2-JK2-JF03-80
Mark and Profile Leg 2A & 2B Node 4 28-Mar-20 02-Apr-20 66 02-Apr-20, Mark and Profile Leg 2A & 2B Node
F2-JK2-JF03-81
Join of Leg 2A & 2B Node 2 07-Apr-20 09-Apr-20 62 09-Apr-20, Join of Leg 2A & 2B Node
F2-JK2-JF03-82
Blasting and Painting for Leg 2A & 2B Node (Initial) 5 09-Apr-20 16-Apr-20 62 16-Apr-20, Blasting and Painting for Leg 2A & 2B Node (Initial)
F2-JK2-JF03-83
Assembly Leg 2A 3 04-Apr-20 07-Apr-20 54 07-Apr-20, Assembly Leg 2A
F2-JK2-JF03-84
Assembly Leg 2B 3 04-Apr-20 07-Apr-20 54 07-Apr-20, Assembly Leg 2B
F2-JK2-JF03-85
Install Stubs on to Leg 2A & 2B Nodes 2 07-Apr-20 09-Apr-20 54 09-Apr-20, Install Stubs on to Leg 2A & 2B Nodes
Braces 32 12-Mar-20 18-Apr-20 54 18-Apr-20, Braces
F2-JK2-JF03-138
Fit & Weld Row-2 K-Brace (Inc. Vertical Braces) 5 09-Apr-20 15-Apr-20 54 15-Apr-20, Fit & Weld Row-2 K-Brace (Inc. Vertical Braces)
F2-JK2-JF03-139
Assembly of Row-2 K-Brace 4 04-Apr-20 08-Apr-20 55 08-Apr-20, Assembly of Row-2 K-Brace
F2-JK2-JF03-86
Fit & Weld Top X-Brace Between Legs 2A & 2B 4 09-Apr-20 14-Apr-20 57 14-Apr-20, Fit & Weld Top X-Brace Between Legs 2A & 2B
F2-JK2-JF03-87
Fit & Weld Mid X-Brace Between Legs 2A & 2B 4 09-Apr-20 14-Apr-20 57 14-Apr-20, Fit & Weld Mid X-Brace Between Legs 2A & 2B
F2-JK2-JF03-88
Join of Row-2 Can Brace (Inc. Stub) 10 17-Mar-20 28-Mar-20 54 28-Mar-20, Join of Row-2 Can Brace (Inc. Stub)
F2-JK2-JF03-89
Assembly of Row-2 Top Brace 3 04-Apr-20 08-Apr-20 58 08-Apr-20, Assembly of Row-2 Top Brace
F2-JK2-JF03-90
Assembly of Row-2 Mid Brace 3 04-Apr-20 08-Apr-20 58 08-Apr-20, Assembly of Row-2 Mid Brace
F2-JK2-JF03-91
Profilling of Row-2 Braces and Stubs 4 12-Mar-20 17-Mar-20 54 17-Mar-20, Profilling of Row-2 Braces and Stubs
F2-JK2-JF03-92
Install Anodes on Row-2 Braces 4 15-Apr-20 18-Apr-20 54 18-Apr-20, Install Anodes on Row-2 Braces
J-Tubes 21 06-Apr-20 30-Apr-20 49 30-Apr-20, J-Tubes
F2-JK2-JF03-128
Join of Row-2 J-Tubes 5 10-Apr-20 16-Apr-20 52 16-Apr-20, Join of Row-2 J-Tubes
F2-JK2-JF03-129
Profilling of Row-2 J-Tubes 4 06-Apr-20 10-Apr-20 52 10-Apr-20, Profilling of Row-2 J-Tubes
F2-JK2-JF03-130
Bending of Row-2 J-Tubes 4 16-Apr-20 20-Apr-20 52 20-Apr-20, Bending of Row-2 J-Tubes
F2-JK2-JF03-131
Blast and Paint for Row-2 J-Tubes 3 23-Apr-20 27-Apr-20 49 27-Apr-20, Blast and Paint for Row-2 J-Tubes
F2-JK2-JF03-132
Assembly Row-2 J-Tubes 3 27-Apr-20 30-Apr-20 49 30-Apr-20, Assembly Row-2 J-Tubes
F2-JK2-JF03-133
Cut and Profile Row-2 J-Tubes Support 4 06-Apr-20 10-Apr-20 49 10-Apr-20, Cut and Profile Row-2 J-Tubes Support
F2-JK2-JF03-134
Assembly Row-2 J-Tubes Support 2 10-Apr-20 14-Apr-20 49 14-Apr-20, Assembly Row-2 J-Tubes Support
F2-JK2-JF03-135
Vulcanized Row-2 J-Tubes Support 2 14-Apr-20 16-Apr-20 49 16-Apr-20, Vulcanized Row-2 J-Tubes Support
F2-JK2-JF03-136
Paint Row-2 J-Tubes Support 3 16-Apr-20 20-Apr-20 49 20-Apr-20, Paint Row-2 J-Tubes Support
F2-JK2-JF03-137
Install J-Tubes Support on to Row-2 J-Tubes 3 20-Apr-20 23-Apr-20 49 23-Apr-20, Install J-Tubes Support on to Row-2 J-Tubes
Common 23 28-Mar-20 24-Apr-20 54 24-Apr-20, Common
Structure 3 28-Mar-20 01-Apr-20 58 01-Apr-20, Structure
F2-JK2-JF03-69
Marking & Cutting of Leg and Brace Node 3 28-Mar-20 01-Apr-20 58 01-Apr-20, Marking & Cutting of Leg and Brace Node
F2-JK2-JF03-70
Marking & Cutting of Brace Stub 3 28-Mar-20 01-Apr-20 58 01-Apr-20, Marking & Cutting of Brace Stub
F2-JK2-JF03-71
Marking & Cutting of Leg and Brace Member 3 28-Mar-20 01-Apr-20 58 01-Apr-20, Marking & Cutting of Leg and Brace Member

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 20 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
Final Painting 23 28-Mar-20 24-Apr-20 54 24-Apr-20, Final Painting
F2-JK2-JF03-72
Row-2 Touch up and Final Painting 3 18-Apr-20 23-Apr-20 54 23-Apr-20, Row-2 Touch up and Final Painting
F2-JK2-JF03-73
Blast and Paint Leg and Brace (Initial Paint) 5 28-Mar-20 04-Apr-20 54 04-Apr-20, Blast and Paint Leg and Brace (Initial Paint)
F2-JK2-JF03-74
Build Painting Habitat Protection 1 23-Apr-20 24-Apr-20 54 24-Apr-20, Build Painting Habitat Protection
F2-JK2-JF03-75
Row-2 Ready for Assembly & Roll-up 0 24-Apr-20 54 24-Apr-20
Transition Piece 65 09-Mar-20 22-May-20 84 22-May-20, Transition Piece
F2-JK2-JF03-10Fabrication of Can Transition Piece Barrel 24 24-Mar-20 21-Apr-20 35 21-Apr-20, Fabrication of Can Transition Piece Barrel
F2-JK2-JF03-100Fit Grating Supports 4 20-Mar-20 26-Mar-20 105 26-Mar-20, Fit Grating Supports
F2-JK2-JF03-101Fab Main Deck Handrails 4 14-Mar-20 19-Mar-20 106 19-Mar-20, Fab Main Deck Handrails
F2-JK2-JF03-102Fab Padeye inc Top of Jacket 4 16-Mar-20 20-Mar-20 131 20-Mar-20, Fab Padeye inc Top of Jacket
F2-JK2-JF03-103Blast and Paint Transition Piece 7 14-May-20 22-May-20 84 22-May-20, Blast and Paint Transition Piece
F2-JK2-JF03-11 Fabrication of Strut Plate 18 09-Mar-20 29-Mar-20 20 29-Mar-20, Fabrication of Strut Plate
F2-JK2-JF03-12Fabrication of Internal Platform 21 09-Mar-20 02-Apr-20 117 02-Apr-20, Fabrication of Internal Platform
F2-JK2-JF03-13Fabrication of External Platform 25 09-Mar-20 07-Apr-20 117 07-Apr-20, Fabrication of External Platform
F2-JK2-JF03-14Assembly Strut Plate 21 30-Mar-20 23-Apr-20 103 23-Apr-20, Assembly Strut Plate
F2-JK2-JF03-15Fabrication of Ring Stiffener 21 20-Apr-20 14-May-20 84 14-May-20, Fabrication of Ring Stiffener
F2-JK2-JF03-16Fabrication of Crane Pedestal 21 30-Mar-20 23-Apr-20 81 23-Apr-20, Fabrication of Crane Pedestal
F2-JK2-JF03-93Galvanizing Handrails 5 19-Mar-20 24-Mar-20 106 24-Mar-20, Galvanizing Handrails
F2-JK2-JF03-94Erect Deck Plate Areas 5 16-Mar-20 20-Mar-20 104 20-Mar-20, Erect Deck Plate Areas
F2-JK2-JF03-95Transition Piece Fabrication Complete 0 14-May-20 84 14-May-20
F2-JK2-JF03-96Fabrication Assemble Walkways / Platforms 21 30-Mar-20 23-Apr-20 103 23-Apr-20, Fabrication Assemble Walkways / Platforms
F2-JK2-JF03-97Fit and Weld TP's Equipment Supports 5 17-Mar-20 23-Mar-20 104 23-Mar-20, Fit and Weld TP's Equipment Supports
F2-JK2-JF03-98Plate Profiling for Main Deck 5 09-Mar-20 14-Mar-20 59 14-Mar-20, Plate Profiling for Main Deck
F2-JK2-JF03-99Fab Main Deck Main Steel 5 10-Mar-20 16-Mar-20 59 16-Mar-20, Fab Main Deck Main Steel
Lifting Trunnion 7 16-Mar-20 24-Mar-20 59 24-Mar-20, Lifting Trunnion
F2-JK2-JF03-104Fabricate Lifting Trunion 7 16-Mar-20 24-Mar-20 59 24-Mar-20, Fabricate Lifting Trunion
Boat Landing 44 25-Mar-20 15-May-20 80 15-May-20, Boat Landing
F2-JK2-JF03-123Blast and Paint Boat Landing 5 09-May-20 15-May-20 80 15-May-20, Blast and Paint Boat Landing
F2-JK2-JF03-124Fabricate Boat Landing 21 25-Mar-20 18-Apr-20 45 18-Apr-20, Fabricate Boat Landing
F2-JK2-JF03-159Fabricate Boat Landing Access platform 24 11-Apr-20 09-May-20 80 09-May-20, Fabricate Boat Landing Access platform
F2-JK2-JF03-160Fabricate Boat Landing Ladders 15 20-Apr-20 07-May-20 82 07-May-20, Fabricate Boat Landing Ladders
Grouting Line 23 27-Apr-20 23-May-20 77 23-May-20, Grouting Line
F2-JK2-JF03-126Fabricate Grouting Line & Grouting Line Support 23 27-Apr-20 23-May-20 77 23-May-20, Fabricate Grouting Line & Grouting Line Support
Assembly 109 24-Mar-20 28-Jul-20 36 28-Jul-20, Assembly
Row Assembly 92 24-Mar-20 09-Jul-20 48 09-Jul-20, Row Assembly
F2-JK2-JF03-113Fabricate Upper Grillage & Truss Support 18 24-Mar-20 14-Apr-20 59 14-Apr-20, Fabricate Upper Grillage & Truss Support
F2-JK2-JF03-114Layout Concrete Blocks/ Grillages and Truss Support Steel 4 27-Apr-20 02-May-20 48 02-May-20, Layout Concrete Blocks/ Grillages and Truss Support Steel
Row-1 & 2 (Upper Jacket) Assembly 46 02-May-20 25-Jun-20 48 25-Jun-20, Row-1 & 2 (Upper Jacket) Assembly
F2-JK2-JF03-115
Installation of Grouting Line 1 20-May-20 21-May-20 68 21-May-20, Installation of Grouting Line
F2-JK2-JF03-117
Installation of J-Tube At Row-1B & 2A 5 20-May-20 26-May-20 72 26-May-20, Installation of J-Tube At Row-1B & 2A
F2-JK2-JF03-118
Row-2 - Touch Up, 2nd Coat & Top Coat 3 22-Jun-20 24-Jun-20 48 24-Jun-20, Row-2 - Touch Up, 2nd Coat & Top Coat
F2-JK2-JF03-119
Installation of Row-1B & 2B X-Brace 7 12-May-20 20-May-20 48 20-May-20, Installation of Row-1B & 2B X-Brace
F2-JK2-JF03-120
Installation of Leg 1A & 1B Onto Support 1 02-May-20 04-May-20 48 04-May-20, Installation of Leg 1A & 1B Onto Support
F2-JK2-JF03-121
Installation of Row-1A & 1B X-Brace 7 04-May-20 12-May-20 48 12-May-20, Installation of Row-1A & 1B X-Brace
F2-JK2-JF03-122
Installation of Row-2A & 2B X-Brace in Final Position 7 13-Jun-20 22-Jun-20 48 22-Jun-20, Installation of Row-2A & 2B X-Brace in Final Position
F2-JK2-JF03-142
Installation of Leg 2A & 2B Onto Support 1 02-May-20 04-May-20 55 04-May-20, Installation of Leg 2A & 2B Onto Support
F2-JK2-JF03-143
Installation of Row-1A & 2A X-Brace 7 12-May-20 20-May-20 48 20-May-20, Installation of Row-1A & 2A X-Brace
F2-JK2-JF03-144
Installation of Row-1A & 1B X-Brace in Final Position 7 05-Jun-20 13-Jun-20 48 13-Jun-20, Installation of Row-1A & 1B X-Brace in Final Position
F2-JK2-JF03-145
Roll Up X-Brace Row A&B to Final Position 7 20-May-20 28-May-20 48 28-May-20, Roll Up X-Brace Row A&B to Final Position
F2-JK2-JF03-146
Installing Tie-back for Fastener 7 28-May-20 05-Jun-20 48 05-Jun-20, Installing Tie-back for Fastener
F2-JK2-JF03-147
Installation of Boat Landing 3 22-Jun-20 25-Jun-20 48 25-Jun-20, Installation of Boat Landing
Row-1 & 2 (Lower Jacket) Assembly 44 29-Apr-20 18-Jun-20 53 18-Jun-20, Row-1 & 2 (Lower Jacket) Assembly
F2-JK2-JF03-116
Installation of Pile Stopper 4 29-May-20 02-Jun-20 53 02-Jun-20, Installation of Pile Stopper
F2-JK2-JF03-148
Installation of Grouting Line 1 16-May-20 18-May-20 74 18-May-20, Installation of Grouting Line
F2-JK2-JF03-149
Installation of J-Tube At Row-1B & 2A 5 16-May-20 22-May-20 63 22-May-20, Installation of J-Tube At Row-1B & 2A

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 21 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF03-150
Installation of Row-1B & 2B X-Brace 7 08-May-20 16-May-20 53 16-May-20, Installation of Row-1B & 2B X-Brace
F2-JK2-JF03-151
Installation of Leg 1A & 1B Onto Support 1 29-Apr-20 30-Apr-20 53 30-Apr-20, Installation of Leg 1A & 1B Onto Support
F2-JK2-JF03-152
Installation of Row-1A & 1B X-Brace 7 30-Apr-20 08-May-20 53 08-May-20, Installation of Row-1A & 1B X-Brace
F2-JK2-JF03-153
Installation of Row-2A & 2B X-Brace in Final Position 7 10-Jun-20 18-Jun-20 53 18-Jun-20, Installation of Row-2A & 2B X-Brace in Final Position
F2-JK2-JF03-154
Installation of Leg 2A & 2B Onto Support 1 29-Apr-20 30-Apr-20 60 30-Apr-20, Installation of Leg 2A & 2B Onto Support
F2-JK2-JF03-155
Installation of Row-1A & 2A X-Brace 7 08-May-20 16-May-20 53 16-May-20, Installation of Row-1A & 2A X-Brace
F2-JK2-JF03-156
Installation of Row-1A & 1B X-Brace in Final Position 7 02-Jun-20 10-Jun-20 53 10-Jun-20, Installation of Row-1A & 1B X-Brace in Final Position
F2-JK2-JF03-157
Roll Up X-Brace Row A&B to Final Position 7 16-May-20 25-May-20 53 25-May-20, Roll Up X-Brace Row A&B to Final Position
F2-JK2-JF03-158
Installing Tie-back for Fastener 4 25-May-20 29-May-20 53 29-May-20, Installing Tie-back for Fastener
Grouting Line 40 23-May-20 09-Jul-20 48 09-Jul-20, Grouting Line
F2-JK2-JF03-125
Installation Of Grouting Line 5 03-Jul-20 09-Jul-20 48 09-Jul-20, Installation Of Grouting Line
F2-JK2-JF03-127
Installation Grouting Line Support 7 23-May-20 01-Jun-20 77 01-Jun-20, Installation Grouting Line Support
Row Roll Up 7 25-Jun-20 03-Jul-20 48 03-Jul-20, Row Roll Up
F2-JK2-JF03-105Roll Up Of Lower Jacket To Final Position 2 25-Jun-20 27-Jun-20 48 27-Jun-20, Roll Up Of Lower Jacket To Final Position
F2-JK2-JF03-106Roll Up Of Upper Jacket To Final Position 5 27-Jun-20 03-Jul-20 48 03-Jul-20, Roll Up Of Upper Jacket To Final Position
Transition Piece (TP) 76 21-Apr-20 18-Jul-20 35 18-Jul-20, Transition Piece (TP)
F2-JK2-JF03-1 Install Door Platform 10 14-May-20 26-May-20 64 26-May-20, Install Door Platform
F2-JK2-JF03-17Installation & Assembly of Ring Stiffener 21 16-May-20 10-Jun-20 35 10-Jun-20, Installation & Assembly of Ring Stiffener
F2-JK2-JF03-18Installation of Transition Piece Flange 15 25-May-20 11-Jun-20 35 11-Jun-20, Installation of Transition Piece Flange
F2-JK2-JF03-19Install Crane Pedestal 12 23-Apr-20 07-May-20 81 07-May-20, Install Crane Pedestal
F2-JK2-JF03-2 Blasting & Painting 10 29-Jun-20 10-Jul-20 35 10-Jul-20, Blasting & Painting
F2-JK2-JF03-3 Assemble Can Transition Piece Barrel to Main Deck 15 21-Apr-20 08-May-20 35 08-May-20, Assemble Can Transition Piece Barrel to Main Deck
F2-JK2-JF03-4 Install Platform & Internal Structure into Upper Can 7 10-Jul-20 18-Jul-20 35 18-Jul-20, Install Platform & Internal Structure into Upper Can
F2-JK2-JF03-5 Door opening & Installation of Door frame 5 08-May-20 14-May-20 74 14-May-20, Door opening & Installation of Door frame
F2-JK2-JF03-6 Installation & Assembly of Strut 15 08-May-20 26-May-20 35 26-May-20, Installation & Assembly of Strut
F2-JK2-JF03-7 Install Free-Issued Items 15 11-Jun-20 29-Jun-20 35 29-Jun-20, Install Free-Issued Items
F2-JK2-JF03-8 Install Architectural items, Electrical & Instrument Equipments 15 08-May-20 26-May-20 64 26-May-20, Install Architectural items, Electrical & Instrument Equipments
F2-JK2-JF03-9 Install External Platform & Handrail 12 12-May-20 26-May-20 64 26-May-20, Install External Platform & Handrail
Final Assembly 8 18-Jul-20 28-Jul-20 36 28-Jul-20, Final Assembly
F2-JK2-JF03-107Installation of Transition Piece 3 18-Jul-20 22-Jul-20 35 22-Jul-20, Installation of Transition Piece
F2-JK2-JF03-108Installation of Mudmad Plate 5 21-Jul-20 27-Jul-20 35 27-Jul-20, Installation of Mudmad Plate
F2-JK2-JF03-109Installation of Lifting Trunnion 4 22-Jul-20 27-Jul-20 37 27-Jul-20, Installation of Lifting Trunnion
F2-JK2-JF03-110Installation of Skirt Pile Sleeve 2 21-Jul-20 23-Jul-20 35 23-Jul-20, Installation of Skirt Pile Sleeve
F2-JK2-JF03-111Final Touch Up Coating 3 24-Jul-20 28-Jul-20 35 28-Jul-20, Final Touch Up Coating
F2-JK2-JF03-112Installation of Lifting Slings 1 23-Jul-20 24-Jul-20 35 24-Jul-20, Installation of Lifting Slings
F2-JK2-JF03-161J acket Fabrication Completed 0 28-Jul-20 35 28-Jul-20
Testing & Commissioning 18 09-Jul-20 30-Jul-20 35 30-Jul-20, Testing & Commissioning
Grouting & Gripper Test 3 09-Jul-20 13-Jul-20 48 13-Jul-20, Grouting & Gripper Test
F2-JK2-JF03-20Gripper Test 2 10-Jul-20 13-Jul-20 48 13-Jul-20, Gripper Test
F2-JK2-JF03-21Grouting Test 1 09-Jul-20 10-Jul-20 48 10-Jul-20, Grouting Test
Mechanical Completion 2 28-Jul-20 30-Jul-20 35 30-Jul-20, Mechanical Completion
F2-JK2-JF03-22Main Structure, Boat Landing, J-Tube, Transition Piece 2 28-Jul-20 30-Jul-20 35 30-Jul-20, Main Structure, Boat Landing, J-Tube, Transition Piece
Jacket & Piles Ready For Loadout 0 30-Jul-20 30-Jul-20 35 30-Jul-20, Jacket & Piles Ready For Loadout
F2-JK2-JF03-23Jacket Ready For Load Out 0 30-Jul-20 35 30-Jul-20
Jacket Foundation 4a 130 09-Mar-20 07-Aug-20 0 07-Aug-20, Jacket Foundation 4a
Fabrication 72 09-Mar-20 01-Jun-20 48 01-Jun-20, Fabrication
Pre-Fabrication 38 09-Mar-20 22-Apr-20 49 22-Apr-20, Pre-Fabrication
F2-JK2-JF04-140Rolling of Can Transition Piece Flange 10 10-Apr-20 22-Apr-20 49 22-Apr-20, Rolling of Can Transition Piece Flange
F2-JK2-JF04-141Rolling of Can Transition Piece Barrel 10 20-Mar-20 01-Apr-20 0 01-Apr-20, Rolling of Can Transition Piece Barrel
F2-JK2-JF04-24Rolling of Can Row 2 Brace 10 09-Mar-20 20-Mar-20 0 20-Mar-20, Rolling of Can Row 2 Brace
F2-JK2-JF04-25Rolling of Can Leg 1A & 1B 10 09-Mar-20 20-Mar-20 13 20-Mar-20, Rolling of Can Leg 1A & 1B
F2-JK2-JF04-26Rolling of Can Leg 2A & 2B 10 17-Mar-20 28-Mar-20 13 28-Mar-20, Rolling of Can Leg 2A & 2B
F2-JK2-JF04-27Rolling of Node Can Row 1 10 17-Mar-20 28-Mar-20 13 28-Mar-20, Rolling of Node Can Row 1
F2-JK2-JF04-28Rolling of Node Can Row 2 10 25-Mar-20 06-Apr-20 13 06-Apr-20, Rolling of Node Can Row 2
F2-JK2-JF04-29Rolling of Can Row 1 Brace 10 25-Mar-20 06-Apr-20 13 06-Apr-20, Rolling of Can Row 1 Brace

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 22 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF04-30Rolling of J-Tubes & J-Tubes Support 10 02-Apr-20 14-Apr-20 14 14-Apr-20, Rolling of J-Tubes & J-Tubes Support
F2-JK2-JF04-31Rolling of Can Plan Level Tubular 10 02-Apr-20 14-Apr-20 49 14-Apr-20, Rolling of Can Plan Level Tubular
F2-JK2-JF04-32Rolling of Can Top Bay X-Brace 10 10-Apr-20 22-Apr-20 49 22-Apr-20, Rolling of Can Top Bay X-Brace
Row 1 Fabrication 42 20-Mar-20 08-May-20 54 08-May-20, Row 1 Fabrication
Legs 40 20-Mar-20 07-May-20 16 07-May-20, Legs
F2-JK2-JF04-40
Install Stubs on to Leg 1A & 1B Nodes 2 27-Apr-20 29-Apr-20 13 29-Apr-20, Install Stubs on to Leg 1A & 1B Nodes
F2-JK2-JF04-41
Install Anodes on Row-1 Legs 4 28-Apr-20 02-May-20 15 02-May-20, Install Anodes on Row-1 Legs
F2-JK2-JF04-42
Join of Can Legs 1A 9 25-Mar-20 04-Apr-20 28 04-Apr-20, Join of Can Legs 1A
F2-JK2-JF04-43
Join of Can Legs 1B 9 25-Mar-20 04-Apr-20 28 04-Apr-20, Join of Can Legs 1B
F2-JK2-JF04-44
Mark and Profile Leg 1A & 1B Node 4 28-Mar-20 02-Apr-20 38 02-Apr-20, Mark and Profile Leg 1A & 1B Node
F2-JK2-JF04-45
Profilling of Legs 1A & 1B (Inc. Cones) 4 20-Mar-20 25-Mar-20 28 25-Mar-20, Profilling of Legs 1A & 1B (Inc. Cones)
F2-JK2-JF04-46
Join of Leg 1A & 1B Node 2 28-Apr-20 30-Apr-20 16 30-Apr-20, Join of Leg 1A & 1B Node
F2-JK2-JF04-47
Blasting and Painting for Leg 1A & 1B Node 5 30-Apr-20 07-May-20 16 07-May-20, Blasting and Painting for Leg 1A & 1B Node
F2-JK2-JF04-48
Assembly Leg 1A 3 25-Apr-20 28-Apr-20 13 28-Apr-20, Assembly Leg 1A
F2-JK2-JF04-49
Assembly Leg 1B 3 25-Apr-20 28-Apr-20 13 28-Apr-20, Assembly Leg 1B
Braces 28 06-Apr-20 08-May-20 13 08-May-20, Braces
F2-JK2-JF04-50
Fit & Weld Top X Brace Between Legs 1A & 1B 5 29-Apr-20 05-May-20 13 05-May-20, Fit & Weld Top X Brace Between Legs 1A & 1B
F2-JK2-JF04-51
Join of Row-1 Can Brace (Inc. Stub) 13 10-Apr-20 25-Apr-20 13 25-Apr-20, Join of Row-1 Can Brace (Inc. Stub)
F2-JK2-JF04-52
Join of Can Brace for Between Row 1 & 2 (Inc. Stub) 13 10-Apr-20 25-Apr-20 13 25-Apr-20, Join of Can Brace for Between Row 1 & 2 (Inc. Stub)
F2-JK2-JF04-53
Assembly of Row-1 Top Brace 4 25-Apr-20 29-Apr-20 13 29-Apr-20, Assembly of Row-1 Top Brace
F2-JK2-JF04-54
Fit & Weld Row-2 K-Brace (Inc. Vertical Braces) 5 29-Apr-20 05-May-20 13 05-May-20, Fit & Weld Row-2 K-Brace (Inc. Vertical Braces)
F2-JK2-JF04-55
Assembly of Row-1 K-Brace 4 25-Apr-20 29-Apr-20 13 29-Apr-20, Assembly of Row-1 K-Brace
F2-JK2-JF04-56
Fit & Weld X-Brace Between Row 1 & 2 5 29-Apr-20 05-May-20 13 05-May-20, Fit & Weld X-Brace Between Row 1 & 2
F2-JK2-JF04-57
Assembly of Brace Between Row 1 & 2 4 25-Apr-20 29-Apr-20 13 29-Apr-20, Assembly of Brace Between Row 1 & 2
F2-JK2-JF04-58
Profilling of Row-1 Braces and Stubs 4 06-Apr-20 10-Apr-20 13 10-Apr-20, Profilling of Row-1 Braces and Stubs
F2-JK2-JF04-59
Install Anodes on Row-1 Braces 4 05-May-20 08-May-20 13 08-May-20, Install Anodes on Row-1 Braces
J-Tubes 19 14-Apr-20 06-May-20 56 06-May-20, J-Tubes
F2-JK2-JF04-60
Join of Row-1 J-Tubes 5 18-Apr-20 24-Apr-20 56 24-Apr-20, Join of Row-1 J-Tubes
F2-JK2-JF04-61
Profilling of Row-1 J-Tubes 4 14-Apr-20 18-Apr-20 56 18-Apr-20, Profilling of Row-1 J-Tubes
F2-JK2-JF04-62
Bending of Row-1 J-Tubes 4 24-Apr-20 28-Apr-20 56 28-Apr-20, Bending of Row-1 J-Tubes
F2-JK2-JF04-63
Blast and Paint for Row-1 J-Tubes 3 28-Apr-20 02-May-20 56 02-May-20, Blast and Paint for Row-1 J-Tubes
F2-JK2-JF04-64
Assembly Row-1 J-Tubes 3 02-May-20 06-May-20 56 06-May-20, Assembly Row-1 J-Tubes
F2-JK2-JF04-65
Cut and Profile Row-1 J-Tubes Support 4 14-Apr-20 18-Apr-20 56 18-Apr-20, Cut and Profile Row-1 J-Tubes Support
F2-JK2-JF04-66
Assembly Row-1 J-Tubes Support 2 18-Apr-20 22-Apr-20 56 22-Apr-20, Assembly Row-1 J-Tubes Support
F2-JK2-JF04-67
Paint Row-1 J-Tubes Support 3 22-Apr-20 25-Apr-20 56 25-Apr-20, Paint Row-1 J-Tubes Support
F2-JK2-JF04-68
Install J-Tubes Support on to Row-1 J-Tubes 3 25-Apr-20 28-Apr-20 56 28-Apr-20, Install J-Tubes Support on to Row-1 J-Tubes
Common 23 13-Apr-20 08-May-20 14 08-May-20, Common
Structure 3 13-Apr-20 16-Apr-20 21 16-Apr-20, Structure
F2-JK2-JF04-33
Marking & Cutting of Leg and Brace Node 3 13-Apr-20 16-Apr-20 21 16-Apr-20, Marking & Cutting of Leg and Brace Node
F2-JK2-JF04-34
Marking & Cutting of Brace Stub 3 13-Apr-20 16-Apr-20 21 16-Apr-20, Marking & Cutting of Brace Stub
F2-JK2-JF04-35
Marking & Cutting of Leg and Brace Member 3 13-Apr-20 16-Apr-20 21 16-Apr-20, Marking & Cutting of Leg and Brace Member
Final Painting 23 13-Apr-20 08-May-20 14 08-May-20, Final Painting
F2-JK2-JF04-36
Blast and Paint Leg and Brace (Initial Paint) 11 13-Apr-20 25-Apr-20 13 25-Apr-20, Blast and Paint Leg and Brace (Initial Paint)
F2-JK2-JF04-37
Build Painting Habitat Protection 1 05-May-20 07-May-20 16 07-May-20, Build Painting Habitat Protection
F2-JK2-JF04-38
Row-1 Ready for Assembly & Roll-up 0 07-May-20 16 07-May-20
F2-JK2-JF04-39
Row-1 Touch up and Final Painting 3 05-May-20 08-May-20 13 08-May-20, Row-1 Touch up and Final Painting
Row 2 Fabrication 42 20-Mar-20 08-May-20 14 08-May-20, Row 2 Fabrication
Legs 23 28-Mar-20 24-Apr-20 27 24-Apr-20, Legs
F2-JK2-JF04-76
Install Anodes on Row-2 Legs 4 15-Apr-20 20-Apr-20 26 20-Apr-20, Install Anodes on Row-2 Legs
F2-JK2-JF04-77
Join of Can Legs 2A 9 02-Apr-20 13-Apr-20 21 13-Apr-20, Join of Can Legs 2A
F2-JK2-JF04-78
Join of Can Legs 2B 9 02-Apr-20 13-Apr-20 21 13-Apr-20, Join of Can Legs 2B
F2-JK2-JF04-79
Profilling of Legs 2A & 2B (Inc. Cones) 4 28-Mar-20 02-Apr-20 21 02-Apr-20, Profilling of Legs 2A & 2B (Inc. Cones)
F2-JK2-JF04-80
Mark and Profile Leg 2A & 2B Node 4 06-Apr-20 10-Apr-20 31 10-Apr-20, Mark and Profile Leg 2A & 2B Node
F2-JK2-JF04-81
Join of Leg 2A & 2B Node 2 15-Apr-20 17-Apr-20 27 17-Apr-20, Join of Leg 2A & 2B Node
F2-JK2-JF04-82
Blasting and Painting for Leg 2A & 2B Node (Initial) 5 17-Apr-20 24-Apr-20 27 24-Apr-20, Blasting and Painting for Leg 2A & 2B Node (Initial)

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 23 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF04-83
Assembly Leg 2A 3 13-Apr-20 15-Apr-20 19 15-Apr-20, Assembly Leg 2A
F2-JK2-JF04-84
Assembly Leg 2B 3 13-Apr-20 15-Apr-20 19 15-Apr-20, Assembly Leg 2B
F2-JK2-JF04-85
Install Stubs on to Leg 2A & 2B Nodes 2 15-Apr-20 17-Apr-20 19 17-Apr-20, Install Stubs on to Leg 2A & 2B Nodes
Braces 32 20-Mar-20 27-Apr-20 19 27-Apr-20, Braces
F2-JK2-JF04-138
Fit & Weld Row-2 K-Brace (Inc. Vertical Braces) 5 17-Apr-20 23-Apr-20 19 23-Apr-20, Fit & Weld Row-2 K-Brace (Inc. Vertical Braces)
F2-JK2-JF04-139
Assembly of Row-2 K-Brace 4 13-Apr-20 16-Apr-20 20 16-Apr-20, Assembly of Row-2 K-Brace
F2-JK2-JF04-86
Fit & Weld Top X-Brace Between Legs 2A & 2B 4 17-Apr-20 22-Apr-20 22 22-Apr-20, Fit & Weld Top X-Brace Between Legs 2A & 2B
F2-JK2-JF04-87
Fit & Weld Mid X-Brace Between Legs 2A & 2B 4 17-Apr-20 22-Apr-20 22 22-Apr-20, Fit & Weld Mid X-Brace Between Legs 2A & 2B
F2-JK2-JF04-88
Join of Row-2 Can Brace (Inc. Stub) 10 25-Mar-20 06-Apr-20 19 06-Apr-20, Join of Row-2 Can Brace (Inc. Stub)
F2-JK2-JF04-89
Assembly of Row-2 Top Brace 3 13-Apr-20 16-Apr-20 23 16-Apr-20, Assembly of Row-2 Top Brace
F2-JK2-JF04-90
Assembly of Row-2 Mid Brace 3 13-Apr-20 16-Apr-20 23 16-Apr-20, Assembly of Row-2 Mid Brace
F2-JK2-JF04-91
Profilling of Row-2 Braces and Stubs 4 20-Mar-20 25-Mar-20 19 25-Mar-20, Profilling of Row-2 Braces and Stubs
F2-JK2-JF04-92
Install Anodes on Row-2 Braces 4 23-Apr-20 27-Apr-20 19 27-Apr-20, Install Anodes on Row-2 Braces
J-Tubes 21 14-Apr-20 08-May-20 14 08-May-20, J-Tubes
F2-JK2-JF04-128
Join of Row-2 J-Tubes 5 18-Apr-20 24-Apr-20 17 24-Apr-20, Join of Row-2 J-Tubes
F2-JK2-JF04-129
Profilling of Row-2 J-Tubes 4 14-Apr-20 18-Apr-20 17 18-Apr-20, Profilling of Row-2 J-Tubes
F2-JK2-JF04-130
Bending of Row-2 J-Tubes 4 24-Apr-20 28-Apr-20 17 28-Apr-20, Bending of Row-2 J-Tubes
F2-JK2-JF04-131
Blast and Paint for Row-2 J-Tubes 3 01-May-20 05-May-20 14 05-May-20, Blast and Paint for Row-2 J-Tubes
F2-JK2-JF04-132
Assembly Row-2 J-Tubes 3 05-May-20 08-May-20 14 08-May-20, Assembly Row-2 J-Tubes
F2-JK2-JF04-133
Cut and Profile Row-2 J-Tubes Support 4 14-Apr-20 18-Apr-20 14 18-Apr-20, Cut and Profile Row-2 J-Tubes Support
F2-JK2-JF04-134
Assembly Row-2 J-Tubes Support 2 18-Apr-20 22-Apr-20 14 22-Apr-20, Assembly Row-2 J-Tubes Support
F2-JK2-JF04-135
Vulcanized Row-2 J-Tubes Support 2 22-Apr-20 24-Apr-20 14 24-Apr-20, Vulcanized Row-2 J-Tubes Support
F2-JK2-JF04-136
Paint Row-2 J-Tubes Support 3 24-Apr-20 28-Apr-20 14 28-Apr-20, Paint Row-2 J-Tubes Support
F2-JK2-JF04-137
Install J-Tubes Support on to Row-2 J-Tubes 3 28-Apr-20 01-May-20 14 01-May-20, Install J-Tubes Support on to Row-2 J-Tubes
Common 23 06-Apr-20 02-May-20 19 02-May-20, Common
Structure 3 06-Apr-20 09-Apr-20 23 09-Apr-20, Structure
F2-JK2-JF04-69
Marking & Cutting of Leg and Brace Node 3 06-Apr-20 09-Apr-20 23 09-Apr-20, Marking & Cutting of Leg and Brace Node
F2-JK2-JF04-70
Marking & Cutting of Brace Stub 3 06-Apr-20 09-Apr-20 23 09-Apr-20, Marking & Cutting of Brace Stub
F2-JK2-JF04-71
Marking & Cutting of Leg and Brace Member 3 06-Apr-20 09-Apr-20 23 09-Apr-20, Marking & Cutting of Leg and Brace Member
Final Painting 23 06-Apr-20 02-May-20 19 02-May-20, Final Painting
F2-JK2-JF04-72
Row-2 Touch up and Final Painting 3 27-Apr-20 01-May-20 19 01-May-20, Row-2 Touch up and Final Painting
F2-JK2-JF04-73
Blast and Paint Leg and Brace (Initial Paint) 5 06-Apr-20 13-Apr-20 19 13-Apr-20, Blast and Paint Leg and Brace (Initial Paint)
F2-JK2-JF04-74
Build Painting Habitat Protection 1 01-May-20 02-May-20 19 02-May-20, Build Painting Habitat Protection
F2-JK2-JF04-75
Row-2 Ready for Assembly & Roll-up 0 02-May-20 19 02-May-20
Transition Piece 65 17-Mar-20 30-May-20 49 30-May-20, Transition Piece
F2-JK2-JF04-10Fabrication of Can Transition Piece Barrel 24 01-Apr-20 29-Apr-20 0 29-Apr-20, Fabrication of Can Transition Piece Barrel
F2-JK2-JF04-100Fit Grating Supports 4 28-Mar-20 03-Apr-20 70 03-Apr-20, Fit Grating Supports
F2-JK2-JF04-101Fab Main Deck Handrails 4 23-Mar-20 27-Mar-20 71 27-Mar-20, Fab Main Deck Handrails
F2-JK2-JF04-102Fab Padeye inc Top of Jacket 4 24-Mar-20 28-Mar-20 96 28-Mar-20, Fab Padeye inc Top of Jacket
F2-JK2-JF04-103Blast and Paint Transition Piece 7 22-May-20 30-May-20 49 30-May-20, Blast and Paint Transition Piece
F2-JK2-JF04-11 Fabrication of Strut Plate 18 17-Mar-20 07-Apr-20 20 07-Apr-20, Fabrication of Strut Plate
F2-JK2-JF04-12Fabrication of Internal Platform 21 17-Mar-20 10-Apr-20 82 10-Apr-20, Fabrication of Internal Platform
F2-JK2-JF04-13Fabrication of External Platform 25 17-Mar-20 15-Apr-20 82 15-Apr-20, Fabrication of External Platform
F2-JK2-JF04-14Assembly Strut Plate 21 07-Apr-20 01-May-20 68 01-May-20, Assembly Strut Plate
F2-JK2-JF04-15Fabrication of Ring Stiffener 21 28-Apr-20 22-May-20 49 22-May-20, Fabrication of Ring Stiffener
F2-JK2-JF04-16Fabrication of Crane Pedestal 21 07-Apr-20 01-May-20 46 01-May-20, Fabrication of Crane Pedestal
F2-JK2-JF04-93Galvanizing Handrails 5 27-Mar-20 01-Apr-20 71 01-Apr-20, Galvanizing Handrails
F2-JK2-JF04-94Erect Deck Plate Areas 5 24-Mar-20 28-Mar-20 69 28-Mar-20, Erect Deck Plate Areas
F2-JK2-JF04-95Transition Piece Fabrication Complete 0 22-May-20 49 22-May-20
F2-JK2-JF04-96Fabrication Assemble Walkways / Platforms 21 07-Apr-20 01-May-20 68 01-May-20, Fabrication Assemble Walkways / Platforms
F2-JK2-JF04-97Fit and Weld TP's Equipment Supports 5 25-Mar-20 31-Mar-20 69 31-Mar-20, Fit and Weld TP's Equipment Supports
F2-JK2-JF04-98Plate Profiling for Main Deck 5 17-Mar-20 23-Mar-20 24 23-Mar-20, Plate Profiling for Main Deck
F2-JK2-JF04-99Fab Main Deck Main Steel 5 18-Mar-20 24-Mar-20 24 24-Mar-20, Fab Main Deck Main Steel
Lifting Trunnion 7 24-Mar-20 01-Apr-20 24 01-Apr-20, Lifting Trunnion
F2-JK2-JF04-104Fabricate Lifting Trunion 7 24-Mar-20 01-Apr-20 24 01-Apr-20, Fabricate Lifting Trunion

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 24 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
Boat Landing 44 02-Apr-20 23-May-20 45 23-May-20, Boat Landing
F2-JK2-JF04-123Blast and Paint Boat Landing 5 18-May-20 23-May-20 45 23-May-20, Blast and Paint Boat Landing
F2-JK2-JF04-124Fabricate Boat Landing 21 02-Apr-20 26-Apr-20 45 26-Apr-20, Fabricate Boat Landing
F2-JK2-JF04-159Fabricate Boat Landing Access platform 24 20-Apr-20 17-May-20 45 17-May-20, Fabricate Boat Landing Access platform
F2-JK2-JF04-160Fabricate Boat Landing Ladders 15 28-Apr-20 15-May-20 47 15-May-20, Fabricate Boat Landing Ladders
Grouting Line 23 05-May-20 01-Jun-20 42 01-Jun-20, Grouting Line
F2-JK2-JF04-126Fabricate Grouting Line & Grouting Line Support 23 05-May-20 01-Jun-20 42 01-Jun-20, Fabricate Grouting Line & Grouting Line Support
Assembly 109 01-Apr-20 05-Aug-20 1 05-Aug-20, Assembly
Row Assembly 92 01-Apr-20 17-Jul-20 13 17-Jul-20, Row Assembly
F2-JK2-JF04-113Fabricate Upper Grillage & Truss Support 18 01-Apr-20 22-Apr-20 24 22-Apr-20, Fabricate Upper Grillage & Truss Support
F2-JK2-JF04-114Layout Concrete Blocks/ Grillages and Truss Support Steel 4 05-May-20 11-May-20 13 11-May-20, Layout Concrete Blocks/ Grillages and Truss Support Steel
Row-1 & 2 (Upper Jacket) Assembly 46 11-May-20 03-Jul-20 13 03-Jul-20, Row-1 & 2 (Upper Jacket) Assembly
F2-JK2-JF04-115
Installation of Grouting Line 1 28-May-20 29-May-20 33 29-May-20, Installation of Grouting Line
F2-JK2-JF04-117
Installation of J-Tube At Row-1B & 2A 5 28-May-20 03-Jun-20 37 03-Jun-20, Installation of J-Tube At Row-1B & 2A
F2-JK2-JF04-118
Row-2 - Touch Up, 2nd Coat & Top Coat 3 30-Jun-20 02-Jul-20 13 02-Jul-20, Row-2 - Touch Up, 2nd Coat & Top Coat
F2-JK2-JF04-119
Installation of Row-1B & 2B X-Brace 7 20-May-20 28-May-20 13 28-May-20, Installation of Row-1B & 2B X-Brace
F2-JK2-JF04-120
Installation of Leg 1A & 1B Onto Support 1 11-May-20 12-May-20 13 12-May-20, Installation of Leg 1A & 1B Onto Support
F2-JK2-JF04-121
Installation of Row-1A & 1B X-Brace 7 12-May-20 20-May-20 13 20-May-20, Installation of Row-1A & 1B X-Brace
F2-JK2-JF04-122
Installation of Row-2A & 2B X-Brace in Final Position 7 22-Jun-20 30-Jun-20 13 30-Jun-20, Installation of Row-2A & 2B X-Brace in Final Position
F2-JK2-JF04-142
Installation of Leg 2A & 2B Onto Support 1 11-May-20 12-May-20 20 12-May-20, Installation of Leg 2A & 2B Onto Support
F2-JK2-JF04-143
Installation of Row-1A & 2A X-Brace 7 20-May-20 28-May-20 13 28-May-20, Installation of Row-1A & 2A X-Brace
F2-JK2-JF04-144
Installation of Row-1A & 1B X-Brace in Final Position 7 13-Jun-20 22-Jun-20 13 22-Jun-20, Installation of Row-1A & 1B X-Brace in Final Position
F2-JK2-JF04-145
Roll Up X-Brace Row A&B to Final Position 7 28-May-20 05-Jun-20 13 05-Jun-20, Roll Up X-Brace Row A&B to Final Position
F2-JK2-JF04-146
Installing Tie-back for Fastener 7 05-Jun-20 13-Jun-20 13 13-Jun-20, Installing Tie-back for Fastener
F2-JK2-JF04-147
Installation of Boat Landing 3 30-Jun-20 03-Jul-20 13 03-Jul-20, Installation of Boat Landing
Row-1 & 2 (Lower Jacket) Assembly 44 07-May-20 26-Jun-20 18 26-Jun-20, Row-1 & 2 (Lower Jacket) Assembly
F2-JK2-JF04-116
Installation of Pile Stopper 4 06-Jun-20 10-Jun-20 18 10-Jun-20, Installation of Pile Stopper
F2-JK2-JF04-148
Installation of Grouting Line 1 25-May-20 26-May-20 39 26-May-20, Installation of Grouting Line
F2-JK2-JF04-149
Installation of J-Tube At Row-1B & 2A 5 25-May-20 30-May-20 28 30-May-20, Installation of J-Tube At Row-1B & 2A
F2-JK2-JF04-150
Installation of Row-1B & 2B X-Brace 7 16-May-20 25-May-20 18 25-May-20, Installation of Row-1B & 2B X-Brace
F2-JK2-JF04-151
Installation of Leg 1A & 1B Onto Support 1 07-May-20 08-May-20 18 08-May-20, Installation of Leg 1A & 1B Onto Support
F2-JK2-JF04-152
Installation of Row-1A & 1B X-Brace 7 08-May-20 16-May-20 18 16-May-20, Installation of Row-1A & 1B X-Brace
F2-JK2-JF04-153
Installation of Row-2A & 2B X-Brace in Final Position 7 18-Jun-20 26-Jun-20 18 26-Jun-20, Installation of Row-2A & 2B X-Brace in Final Position
F2-JK2-JF04-154
Installation of Leg 2A & 2B Onto Support 1 07-May-20 08-May-20 25 08-May-20, Installation of Leg 2A & 2B Onto Support
F2-JK2-JF04-155
Installation of Row-1A & 2A X-Brace 7 16-May-20 25-May-20 18 25-May-20, Installation of Row-1A & 2A X-Brace
F2-JK2-JF04-156
Installation of Row-1A & 1B X-Brace in Final Position 7 10-Jun-20 18-Jun-20 18 18-Jun-20, Installation of Row-1A & 1B X-Brace in Final Position
F2-JK2-JF04-157
Roll Up X-Brace Row A&B to Final Position 7 25-May-20 02-Jun-20 18 02-Jun-20, Roll Up X-Brace Row A&B to Final Position
F2-JK2-JF04-158
Installing Tie-back for Fastener 4 02-Jun-20 06-Jun-20 18 06-Jun-20, Installing Tie-back for Fastener
Grouting Line 40 01-Jun-20 17-Jul-20 13 17-Jul-20, Grouting Line
F2-JK2-JF04-125
Installation Of Grouting Line 5 11-Jul-20 17-Jul-20 13 17-Jul-20, Installation Of Grouting Line
F2-JK2-JF04-127
Installation Grouting Line Support 7 01-Jun-20 09-Jun-20 42 09-Jun-20, Installation Grouting Line Support
Row Roll Up 7 03-Jul-20 11-Jul-20 13 11-Jul-20, Row Roll Up
F2-JK2-JF04-105Roll Up Of Lower Jacket To Final Position 2 03-Jul-20 06-Jul-20 13 06-Jul-20, Roll Up Of Lower Jacket To Final Position
F2-JK2-JF04-106Roll Up Of Upper Jacket To Final Position 5 06-Jul-20 11-Jul-20 13 11-Jul-20, Roll Up Of Upper Jacket To Final Position
Transition Piece (TP) 76 29-Apr-20 27-Jul-20 0 27-Jul-20, Transition Piece (TP)
F2-JK2-JF04-1 Install Door Platform 10 22-May-20 03-Jun-20 29 03-Jun-20, Install Door Platform
F2-JK2-JF04-17Installation & Assembly of Ring Stiffener 21 25-May-20 18-Jun-20 0 18-Jun-20, Installation & Assembly of Ring Stiffener
F2-JK2-JF04-18Installation of Transition Piece Flange 15 02-Jun-20 19-Jun-20 0 19-Jun-20, Installation of Transition Piece Flange
F2-JK2-JF04-19Install Crane Pedestal 12 01-May-20 15-May-20 46 15-May-20, Install Crane Pedestal
F2-JK2-JF04-2 Blasting & Painting 10 07-Jul-20 18-Jul-20 0 18-Jul-20, Blasting & Painting
F2-JK2-JF04-3 Assemble Can Transition Piece Barrel to Main Deck 15 29-Apr-20 16-May-20 0 16-May-20, Assemble Can Transition Piece Barrel to Main Deck
F2-JK2-JF04-4 Install Platform & Internal Structure into Upper Can 7 18-Jul-20 27-Jul-20 0 27-Jul-20, Install Platform & Internal Structure into Upper Can
F2-JK2-JF04-5 Door opening & Installation of Door frame 5 16-May-20 22-May-20 39 22-May-20, Door opening & Installation of Door frame
F2-JK2-JF04-6 Installation & Assembly of Strut 15 16-May-20 03-Jun-20 0 03-Jun-20, Installation & Assembly of Strut
F2-JK2-JF04-7 Install Free-Issued Items 15 19-Jun-20 07-Jul-20 0 07-Jul-20, Install Free-Issued Items

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 25 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF04-8 Install Architectural items, Electrical & Instrument Equipments 15 16-May-20 03-Jun-20 29 03-Jun-20, Install Architectural items, Electrical & Instrument Equipments
F2-JK2-JF04-9 Install External Platform & Handrail 12 20-May-20 03-Jun-20 29 03-Jun-20, Install External Platform & Handrail
Final Assembly 8 27-Jul-20 05-Aug-20 1 05-Aug-20, Final Assembly
F2-JK2-JF04-107Installation of Transition Piece 3 27-Jul-20 30-Jul-20 0 30-Jul-20, Installation of Transition Piece
F2-JK2-JF04-108Installation of Mudmad Plate 5 29-Jul-20 04-Aug-20 0 04-Aug-20, Installation of Mudmad Plate
F2-JK2-JF04-109Installation of Lifting Trunnion 4 30-Jul-20 04-Aug-20 2 04-Aug-20, Installation of Lifting Trunnion
F2-JK2-JF04-110Installation of Skirt Pile Sleeve 2 29-Jul-20 31-Jul-20 0 31-Jul-20, Installation of Skirt Pile Sleeve
F2-JK2-JF04-111Final Touch Up Coating 3 01-Aug-20 05-Aug-20 0 05-Aug-20, Final Touch Up Coating
F2-JK2-JF04-112Installation of Lifting Slings 1 31-Jul-20 01-Aug-20 0 01-Aug-20, Installation of Lifting Slings
F2-JK2-JF04-161J acket Fabrication Completed 0 05-Aug-20 0 05-Aug-20
Testing & Commissioning 18 17-Jul-20 07-Aug-20 0 07-Aug-20, Testing & Commissioning
Grouting & Gripper Test 3 17-Jul-20 21-Jul-20 13 21-Jul-20, Grouting & Gripper Test
F2-JK2-JF04-20Gripper Test 2 18-Jul-20 21-Jul-20 13 21-Jul-20, Gripper Test
F2-JK2-JF04-21Grouting Test 1 17-Jul-20 18-Jul-20 13 18-Jul-20, Grouting Test
Mechanical Completion 2 05-Aug-20 07-Aug-20 0 07-Aug-20, Mechanical Completion
F2-JK2-JF04-22Main Structure, Boat Landing, J-Tube, Transition Piece 2 05-Aug-20 07-Aug-20 0 07-Aug-20, Main Structure, Boat Landing, J-Tube, Transition Piece
Jacket & Piles Ready For Loadout 0 07-Aug-20 07-Aug-20 0 07-Aug-20, Jacket & Piles Ready For Loadout
F2-JK2-JF04-23Jacket Ready For Load Out 0 07-Aug-20 0 07-Aug-20
Jacket Foundation 5a 130 17-Mar-20 15-Aug-20 47 15-Aug-20, Jacket Foundation 5a
Fabrication 72 17-Mar-20 09-Jun-20 95 09-Jun-20, Fabrication
Pre-Fabrication 38 17-Mar-20 30-Apr-20 96 30-Apr-20, Pre-Fabrication
F2-JK2-JF05-140Rolling of Can Transition Piece Flange 10 18-Apr-20 30-Apr-20 96 30-Apr-20, Rolling of Can Transition Piece Flange
F2-JK2-JF05-141Rolling of Can Transition Piece Barrel 10 28-Mar-20 09-Apr-20 47 09-Apr-20, Rolling of Can Transition Piece Barrel
F2-JK2-JF05-24Rolling of Can Row 2 Brace 10 17-Mar-20 28-Mar-20 47 28-Mar-20, Rolling of Can Row 2 Brace
F2-JK2-JF05-25Rolling of Can Leg 1A & 1B 10 17-Mar-20 28-Mar-20 60 28-Mar-20, Rolling of Can Leg 1A & 1B
F2-JK2-JF05-26Rolling of Can Leg 2A & 2B 10 25-Mar-20 06-Apr-20 60 06-Apr-20, Rolling of Can Leg 2A & 2B
F2-JK2-JF05-27Rolling of Node Can Row 1 10 25-Mar-20 06-Apr-20 60 06-Apr-20, Rolling of Node Can Row 1
F2-JK2-JF05-28Rolling of Node Can Row 2 10 02-Apr-20 14-Apr-20 60 14-Apr-20, Rolling of Node Can Row 2
F2-JK2-JF05-29Rolling of Can Row 1 Brace 10 02-Apr-20 14-Apr-20 60 14-Apr-20, Rolling of Can Row 1 Brace
F2-JK2-JF05-30Rolling of J-Tubes & J-Tubes Support 10 10-Apr-20 22-Apr-20 61 22-Apr-20, Rolling of J-Tubes & J-Tubes Support
F2-JK2-JF05-31Rolling of Can Plan Level Tubular 10 10-Apr-20 22-Apr-20 96 22-Apr-20, Rolling of Can Plan Level Tubular
F2-JK2-JF05-32Rolling of Can Top Bay X-Brace 10 18-Apr-20 30-Apr-20 96 30-Apr-20, Rolling of Can Top Bay X-Brace
Row 1 Fabrication 42 28-Mar-20 16-May-20 101 16-May-20, Row 1 Fabrication
Legs 40 28-Mar-20 15-May-20 63 15-May-20, Legs
F2-JK2-JF05-40
Install Stubs on to Leg 1A & 1B Nodes 2 05-May-20 07-May-20 60 07-May-20, Install Stubs on to Leg 1A & 1B Nodes
F2-JK2-JF05-41
Install Anodes on Row-1 Legs 4 06-May-20 11-May-20 62 11-May-20, Install Anodes on Row-1 Legs
F2-JK2-JF05-42
Join of Can Legs 1A 9 02-Apr-20 13-Apr-20 75 13-Apr-20, Join of Can Legs 1A
F2-JK2-JF05-43
Join of Can Legs 1B 9 02-Apr-20 13-Apr-20 75 13-Apr-20, Join of Can Legs 1B
F2-JK2-JF05-44
Mark and Profile Leg 1A & 1B Node 4 06-Apr-20 10-Apr-20 85 10-Apr-20, Mark and Profile Leg 1A & 1B Node
F2-JK2-JF05-45
Profilling of Legs 1A & 1B (Inc. Cones) 4 28-Mar-20 02-Apr-20 75 02-Apr-20, Profilling of Legs 1A & 1B (Inc. Cones)
F2-JK2-JF05-46
Join of Leg 1A & 1B Node 2 06-May-20 08-May-20 63 08-May-20, Join of Leg 1A & 1B Node
F2-JK2-JF05-47
Blasting and Painting for Leg 1A & 1B Node 5 08-May-20 15-May-20 63 15-May-20, Blasting and Painting for Leg 1A & 1B Node
F2-JK2-JF05-48
Assembly Leg 1A 3 04-May-20 06-May-20 60 06-May-20, Assembly Leg 1A
F2-JK2-JF05-49
Assembly Leg 1B 3 04-May-20 06-May-20 60 06-May-20, Assembly Leg 1B
Braces 28 14-Apr-20 16-May-20 60 16-May-20, Braces
F2-JK2-JF05-50
Fit & Weld Top X Brace Between Legs 1A & 1B 5 07-May-20 13-May-20 60 13-May-20, Fit & Weld Top X Brace Between Legs 1A & 1B
F2-JK2-JF05-51
Join of Row-1 Can Brace (Inc. Stub) 13 18-Apr-20 04-May-20 60 04-May-20, Join of Row-1 Can Brace (Inc. Stub)
F2-JK2-JF05-52
Join of Can Brace for Between Row 1 & 2 (Inc. Stub) 13 18-Apr-20 04-May-20 60 04-May-20, Join of Can Brace for Between Row 1 & 2 (Inc. Stub)
F2-JK2-JF05-53
Assembly of Row-1 Top Brace 4 04-May-20 07-May-20 60 07-May-20, Assembly of Row-1 Top Brace
F2-JK2-JF05-54
Fit & Weld Row-2 K-Brace (Inc. Vertical Braces) 5 07-May-20 13-May-20 60 13-May-20, Fit & Weld Row-2 K-Brace (Inc. Vertical Braces)
F2-JK2-JF05-55
Assembly of Row-1 K-Brace 4 04-May-20 07-May-20 60 07-May-20, Assembly of Row-1 K-Brace
F2-JK2-JF05-56
Fit & Weld X-Brace Between Row 1 & 2 5 07-May-20 13-May-20 60 13-May-20, Fit & Weld X-Brace Between Row 1 & 2
F2-JK2-JF05-57
Assembly of Brace Between Row 1 & 2 4 04-May-20 07-May-20 60 07-May-20, Assembly of Brace Between Row 1 & 2
F2-JK2-JF05-58
Profilling of Row-1 Braces and Stubs 4 14-Apr-20 18-Apr-20 60 18-Apr-20, Profilling of Row-1 Braces and Stubs
F2-JK2-JF05-59
Install Anodes on Row-1 Braces 4 13-May-20 16-May-20 60 16-May-20, Install Anodes on Row-1 Braces

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 26 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
J-Tubes 19 22-Apr-20 14-May-20 103 14-May-20, J-Tubes
F2-JK2-JF05-60
Join of Row-1 J-Tubes 5 27-Apr-20 02-May-20 103 02-May-20, Join of Row-1 J-Tubes
F2-JK2-JF05-61
Profilling of Row-1 J-Tubes 4 22-Apr-20 27-Apr-20 103 27-Apr-20, Profilling of Row-1 J-Tubes
F2-JK2-JF05-62
Bending of Row-1 J-Tubes 4 02-May-20 06-May-20 103 06-May-20, Bending of Row-1 J-Tubes
F2-JK2-JF05-63
Blast and Paint for Row-1 J-Tubes 3 06-May-20 11-May-20 103 11-May-20, Blast and Paint for Row-1 J-Tubes
F2-JK2-JF05-64
Assembly Row-1 J-Tubes 3 11-May-20 14-May-20 103 14-May-20, Assembly Row-1 J-Tubes
F2-JK2-JF05-65
Cut and Profile Row-1 J-Tubes Support 4 22-Apr-20 27-Apr-20 103 27-Apr-20, Cut and Profile Row-1 J-Tubes Support
F2-JK2-JF05-66
Assembly Row-1 J-Tubes Support 2 27-Apr-20 30-Apr-20 103 30-Apr-20, Assembly Row-1 J-Tubes Support
F2-JK2-JF05-67
Paint Row-1 J-Tubes Support 3 30-Apr-20 04-May-20 103 04-May-20, Paint Row-1 J-Tubes Support
F2-JK2-JF05-68
Install J-Tubes Support on to Row-1 J-Tubes 3 04-May-20 06-May-20 103 06-May-20, Install J-Tubes Support on to Row-1 J-Tubes
Common 23 21-Apr-20 16-May-20 61 16-May-20, Common
Structure 3 21-Apr-20 24-Apr-20 68 24-Apr-20, Structure
F2-JK2-JF05-33
Marking & Cutting of Leg and Brace Node 3 21-Apr-20 24-Apr-20 68 24-Apr-20, Marking & Cutting of Leg and Brace Node
F2-JK2-JF05-34
Marking & Cutting of Brace Stub 3 21-Apr-20 24-Apr-20 68 24-Apr-20, Marking & Cutting of Brace Stub
F2-JK2-JF05-35
Marking & Cutting of Leg and Brace Member 3 21-Apr-20 24-Apr-20 68 24-Apr-20, Marking & Cutting of Leg and Brace Member
Final Painting 23 21-Apr-20 16-May-20 61 16-May-20, Final Painting
F2-JK2-JF05-36
Blast and Paint Leg and Brace (Initial Paint) 11 21-Apr-20 04-May-20 60 04-May-20, Blast and Paint Leg and Brace (Initial Paint)
F2-JK2-JF05-37
Build Painting Habitat Protection 1 13-May-20 15-May-20 63 15-May-20, Build Painting Habitat Protection
F2-JK2-JF05-38
Row-1 Ready for Assembly & Roll-up 0 15-May-20 63 15-May-20
F2-JK2-JF05-39
Row-1 Touch up and Final Painting 3 13-May-20 16-May-20 60 16-May-20, Row-1 Touch up and Final Painting
Row 2 Fabrication 42 28-Mar-20 16-May-20 61 16-May-20, Row 2 Fabrication
Legs 23 06-Apr-20 02-May-20 74 02-May-20, Legs
F2-JK2-JF05-76
Install Anodes on Row-2 Legs 4 23-Apr-20 28-Apr-20 73 28-Apr-20, Install Anodes on Row-2 Legs
F2-JK2-JF05-77
Join of Can Legs 2A 9 10-Apr-20 21-Apr-20 68 21-Apr-20, Join of Can Legs 2A
F2-JK2-JF05-78
Join of Can Legs 2B 9 10-Apr-20 21-Apr-20 68 21-Apr-20, Join of Can Legs 2B
F2-JK2-JF05-79
Profilling of Legs 2A & 2B (Inc. Cones) 4 06-Apr-20 10-Apr-20 68 10-Apr-20, Profilling of Legs 2A & 2B (Inc. Cones)
F2-JK2-JF05-80
Mark and Profile Leg 2A & 2B Node 4 14-Apr-20 18-Apr-20 78 18-Apr-20, Mark and Profile Leg 2A & 2B Node
F2-JK2-JF05-81
Join of Leg 2A & 2B Node 2 23-Apr-20 25-Apr-20 74 25-Apr-20, Join of Leg 2A & 2B Node
F2-JK2-JF05-82
Blasting and Painting for Leg 2A & 2B Node (Initial) 5 25-Apr-20 02-May-20 74 02-May-20, Blasting and Painting for Leg 2A & 2B Node (Initial)
F2-JK2-JF05-83
Assembly Leg 2A 3 21-Apr-20 23-Apr-20 66 23-Apr-20, Assembly Leg 2A
F2-JK2-JF05-84
Assembly Leg 2B 3 21-Apr-20 23-Apr-20 66 23-Apr-20, Assembly Leg 2B
F2-JK2-JF05-85
Install Stubs on to Leg 2A & 2B Nodes 2 23-Apr-20 25-Apr-20 66 25-Apr-20, Install Stubs on to Leg 2A & 2B Nodes
Braces 32 28-Mar-20 05-May-20 66 05-May-20, Braces
F2-JK2-JF05-138
Fit & Weld Row-2 K-Brace (Inc. Vertical Braces) 5 25-Apr-20 01-May-20 66 01-May-20, Fit & Weld Row-2 K-Brace (Inc. Vertical Braces)
F2-JK2-JF05-139
Assembly of Row-2 K-Brace 4 21-Apr-20 24-Apr-20 67 24-Apr-20, Assembly of Row-2 K-Brace
F2-JK2-JF05-86
Fit & Weld Top X-Brace Between Legs 2A & 2B 4 25-Apr-20 30-Apr-20 69 30-Apr-20, Fit & Weld Top X-Brace Between Legs 2A & 2B
F2-JK2-JF05-87
Fit & Weld Mid X-Brace Between Legs 2A & 2B 4 25-Apr-20 30-Apr-20 69 30-Apr-20, Fit & Weld Mid X-Brace Between Legs 2A & 2B
F2-JK2-JF05-88
Join of Row-2 Can Brace (Inc. Stub) 10 02-Apr-20 14-Apr-20 66 14-Apr-20, Join of Row-2 Can Brace (Inc. Stub)
F2-JK2-JF05-89
Assembly of Row-2 Top Brace 3 21-Apr-20 24-Apr-20 70 24-Apr-20, Assembly of Row-2 Top Brace
F2-JK2-JF05-90
Assembly of Row-2 Mid Brace 3 21-Apr-20 24-Apr-20 70 24-Apr-20, Assembly of Row-2 Mid Brace
F2-JK2-JF05-91
Profilling of Row-2 Braces and Stubs 4 28-Mar-20 02-Apr-20 66 02-Apr-20, Profilling of Row-2 Braces and Stubs
F2-JK2-JF05-92
Install Anodes on Row-2 Braces 4 01-May-20 05-May-20 66 05-May-20, Install Anodes on Row-2 Braces
J-Tubes 21 22-Apr-20 16-May-20 61 16-May-20, J-Tubes
F2-JK2-JF05-128
Join of Row-2 J-Tubes 5 27-Apr-20 02-May-20 64 02-May-20, Join of Row-2 J-Tubes
F2-JK2-JF05-129
Profilling of Row-2 J-Tubes 4 22-Apr-20 27-Apr-20 64 27-Apr-20, Profilling of Row-2 J-Tubes
F2-JK2-JF05-130
Bending of Row-2 J-Tubes 4 02-May-20 06-May-20 64 06-May-20, Bending of Row-2 J-Tubes
F2-JK2-JF05-131
Blast and Paint for Row-2 J-Tubes 3 09-May-20 13-May-20 61 13-May-20, Blast and Paint for Row-2 J-Tubes
F2-JK2-JF05-132
Assembly Row-2 J-Tubes 3 13-May-20 16-May-20 61 16-May-20, Assembly Row-2 J-Tubes
F2-JK2-JF05-133
Cut and Profile Row-2 J-Tubes Support 4 22-Apr-20 27-Apr-20 61 27-Apr-20, Cut and Profile Row-2 J-Tubes Support
F2-JK2-JF05-134
Assembly Row-2 J-Tubes Support 2 27-Apr-20 30-Apr-20 61 30-Apr-20, Assembly Row-2 J-Tubes Support
F2-JK2-JF05-135
Vulcanized Row-2 J-Tubes Support 2 30-Apr-20 02-May-20 61 02-May-20, Vulcanized Row-2 J-Tubes Support
F2-JK2-JF05-136
Paint Row-2 J-Tubes Support 3 02-May-20 06-May-20 61 06-May-20, Paint Row-2 J-Tubes Support
F2-JK2-JF05-137
Install J-Tubes Support on to Row-2 J-Tubes 3 06-May-20 09-May-20 61 09-May-20, Install J-Tubes Support on to Row-2 J-Tubes
Common 23 14-Apr-20 11-May-20 66 11-May-20, Common
Structure 3 14-Apr-20 17-Apr-20 70 17-Apr-20, Structure

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 27 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF05-69
Marking & Cutting of Leg and Brace Node 3 14-Apr-20 17-Apr-20 70 17-Apr-20, Marking & Cutting of Leg and Brace Node
F2-JK2-JF05-70
Marking & Cutting of Brace Stub 3 14-Apr-20 17-Apr-20 70 17-Apr-20, Marking & Cutting of Brace Stub
F2-JK2-JF05-71
Marking & Cutting of Leg and Brace Member 3 14-Apr-20 17-Apr-20 70 17-Apr-20, Marking & Cutting of Leg and Brace Member
Final Painting 23 14-Apr-20 11-May-20 66 11-May-20, Final Painting
F2-JK2-JF05-72
Row-2 Touch up and Final Painting 3 05-May-20 09-May-20 66 09-May-20, Row-2 Touch up and Final Painting
F2-JK2-JF05-73
Blast and Paint Leg and Brace (Initial Paint) 5 14-Apr-20 21-Apr-20 66 21-Apr-20, Blast and Paint Leg and Brace (Initial Paint)
F2-JK2-JF05-74
Build Painting Habitat Protection 1 09-May-20 11-May-20 66 11-May-20, Build Painting Habitat Protection
F2-JK2-JF05-75
Row-2 Ready for Assembly & Roll-up 0 11-May-20 66 11-May-20
Transition Piece 65 25-Mar-20 08-Jun-20 96 08-Jun-20, Transition Piece
F2-JK2-JF05-10Fabrication of Can Transition Piece Barrel 24 09-Apr-20 07-May-20 47 07-May-20, Fabrication of Can Transition Piece Barrel
F2-JK2-JF05-100Fit Grating Supports 4 06-Apr-20 11-Apr-20 117 11-Apr-20, Fit Grating Supports
F2-JK2-JF05-101Fab Main Deck Handrails 4 31-Mar-20 04-Apr-20 118 04-Apr-20, Fab Main Deck Handrails
F2-JK2-JF05-102Fab Padeye inc Top of Jacket 4 01-Apr-20 05-Apr-20 143 05-Apr-20, Fab Padeye inc Top of Jacket
F2-JK2-JF05-103Blast and Paint Transition Piece 7 30-May-20 08-Jun-20 96 08-Jun-20, Blast and Paint Transition Piece
F2-JK2-JF05-11 Fabrication of Strut Plate 18 25-Mar-20 15-Apr-20 67 15-Apr-20, Fabrication of Strut Plate
F2-JK2-JF05-12Fabrication of Internal Platform 21 25-Mar-20 18-Apr-20 129 18-Apr-20, Fabrication of Internal Platform
F2-JK2-JF05-13Fabrication of External Platform 25 25-Mar-20 23-Apr-20 129 23-Apr-20, Fabrication of External Platform
F2-JK2-JF05-14Assembly Strut Plate 21 15-Apr-20 09-May-20 115 09-May-20, Assembly Strut Plate
F2-JK2-JF05-15Fabrication of Ring Stiffener 21 06-May-20 30-May-20 96 30-May-20, Fabrication of Ring Stiffener
F2-JK2-JF05-16Fabrication of Crane Pedestal 21 15-Apr-20 09-May-20 93 09-May-20, Fabrication of Crane Pedestal
F2-JK2-JF05-93Galvanizing Handrails 5 04-Apr-20 09-Apr-20 118 09-Apr-20, Galvanizing Handrails
F2-JK2-JF05-94Erect Deck Plate Areas 5 01-Apr-20 06-Apr-20 116 06-Apr-20, Erect Deck Plate Areas
F2-JK2-JF05-95Transition Piece Fabrication Complete 0 30-May-20 96 30-May-20
F2-JK2-JF05-96Fabrication Assemble Walkways / Platforms 21 15-Apr-20 09-May-20 115 09-May-20, Fabrication Assemble Walkways / Platforms
F2-JK2-JF05-97Fit and Weld TP's Equipment Supports 5 02-Apr-20 08-Apr-20 116 08-Apr-20, Fit and Weld TP's Equipment Supports
F2-JK2-JF05-98Plate Profiling for Main Deck 5 25-Mar-20 31-Mar-20 71 31-Mar-20, Plate Profiling for Main Deck
F2-JK2-JF05-99Fab Main Deck Main Steel 5 26-Mar-20 01-Apr-20 71 01-Apr-20, Fab Main Deck Main Steel
Lifting Trunnion 7 01-Apr-20 09-Apr-20 71 09-Apr-20, Lifting Trunnion
F2-JK2-JF05-104Fabricate Lifting Trunion 7 01-Apr-20 09-Apr-20 71 09-Apr-20, Fabricate Lifting Trunion
Boat Landing 44 10-Apr-20 01-Jun-20 92 01-Jun-20, Boat Landing
F2-JK2-JF05-123Blast and Paint Boat Landing 5 26-May-20 01-Jun-20 92 01-Jun-20, Blast and Paint Boat Landing
F2-JK2-JF05-124Fabricate Boat Landing 21 10-Apr-20 05-May-20 92 05-May-20, Fabricate Boat Landing
F2-JK2-JF05-159Fabricate Boat Landing Access platform 24 28-Apr-20 26-May-20 92 26-May-20, Fabricate Boat Landing Access platform
F2-JK2-JF05-160Fabricate Boat Landing Ladders 15 06-May-20 23-May-20 94 23-May-20, Fabricate Boat Landing Ladders
Grouting Line 23 13-May-20 09-Jun-20 89 09-Jun-20, Grouting Line
F2-JK2-JF05-126Fabricate Grouting Line & Grouting Line Support 23 13-May-20 09-Jun-20 89 09-Jun-20, Fabricate Grouting Line & Grouting Line Support
Assembly 109 09-Apr-20 13-Aug-20 48 13-Aug-20, Assembly
Row Assembly 92 09-Apr-20 25-Jul-20 60 25-Jul-20, Row Assembly
F2-JK2-JF05-113Fabricate Upper Grillage & Truss Support 18 09-Apr-20 30-Apr-20 71 30-Apr-20, Fabricate Upper Grillage & Truss Support
F2-JK2-JF05-114Layout Concrete Blocks/ Grillages and Truss Support Steel 4 13-May-20 19-May-20 60 19-May-20, Layout Concrete Blocks/ Grillages and Truss Support Steel
Row-1 & 2 (Upper Jacket) Assembly 46 19-May-20 11-Jul-20 60 11-Jul-20, Row-1 & 2 (Upper Jacket) Assembly
F2-JK2-JF05-115
Installation of Grouting Line 1 05-Jun-20 06-Jun-20 80 06-Jun-20, Installation of Grouting Line
F2-JK2-JF05-117
Installation of J-Tube At Row-1B & 2A 5 05-Jun-20 11-Jun-20 84 11-Jun-20, Installation of J-Tube At Row-1B & 2A
F2-JK2-JF05-118
Row-2 - Touch Up, 2nd Coat & Top Coat 3 08-Jul-20 10-Jul-20 60 10-Jul-20, Row-2 - Touch Up, 2nd Coat & Top Coat
F2-JK2-JF05-119
Installation of Row-1B & 2B X-Brace 7 28-May-20 05-Jun-20 60 05-Jun-20, Installation of Row-1B & 2B X-Brace
F2-JK2-JF05-120
Installation of Leg 1A & 1B Onto Support 1 19-May-20 20-May-20 60 20-May-20, Installation of Leg 1A & 1B Onto Support
F2-JK2-JF05-121
Installation of Row-1A & 1B X-Brace 7 20-May-20 28-May-20 60 28-May-20, Installation of Row-1A & 1B X-Brace
F2-JK2-JF05-122
Installation of Row-2A & 2B X-Brace in Final Position 7 30-Jun-20 08-Jul-20 60 08-Jul-20, Installation of Row-2A & 2B X-Brace in Final Position
F2-JK2-JF05-142
Installation of Leg 2A & 2B Onto Support 1 19-May-20 20-May-20 67 20-May-20, Installation of Leg 2A & 2B Onto Support
F2-JK2-JF05-143
Installation of Row-1A & 2A X-Brace 7 28-May-20 05-Jun-20 60 05-Jun-20, Installation of Row-1A & 2A X-Brace
F2-JK2-JF05-144
Installation of Row-1A & 1B X-Brace in Final Position 7 22-Jun-20 30-Jun-20 60 30-Jun-20, Installation of Row-1A & 1B X-Brace in Final Position
F2-JK2-JF05-145
Roll Up X-Brace Row A&B to Final Position 7 05-Jun-20 13-Jun-20 60 13-Jun-20, Roll Up X-Brace Row A&B to Final Position
F2-JK2-JF05-146
Installing Tie-back for Fastener 7 13-Jun-20 22-Jun-20 60 22-Jun-20, Installing Tie-back for Fastener
F2-JK2-JF05-147
Installation of Boat Landing 3 08-Jul-20 11-Jul-20 60 11-Jul-20, Installation of Boat Landing
Row-1 & 2 (Lower Jacket) Assembly 44 15-May-20 04-Jul-20 65 04-Jul-20, Row-1 & 2 (Lower Jacket) Assembly

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 28 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF05-116
Installation of Pile Stopper 4 15-Jun-20 18-Jun-20 65 18-Jun-20, Installation of Pile Stopper
F2-JK2-JF05-148
Installation of Grouting Line 1 02-Jun-20 03-Jun-20 86 03-Jun-20, Installation of Grouting Line
F2-JK2-JF05-149
Installation of J-Tube At Row-1B & 2A 5 02-Jun-20 08-Jun-20 75 08-Jun-20, Installation of J-Tube At Row-1B & 2A
F2-JK2-JF05-150
Installation of Row-1B & 2B X-Brace 7 25-May-20 02-Jun-20 65 02-Jun-20, Installation of Row-1B & 2B X-Brace
F2-JK2-JF05-151
Installation of Leg 1A & 1B Onto Support 1 15-May-20 16-May-20 65 16-May-20, Installation of Leg 1A & 1B Onto Support
F2-JK2-JF05-152
Installation of Row-1A & 1B X-Brace 7 16-May-20 25-May-20 65 25-May-20, Installation of Row-1A & 1B X-Brace
F2-JK2-JF05-153
Installation of Row-2A & 2B X-Brace in Final Position 7 26-Jun-20 04-Jul-20 65 04-Jul-20, Installation of Row-2A & 2B X-Brace in Final Position
F2-JK2-JF05-154
Installation of Leg 2A & 2B Onto Support 1 15-May-20 16-May-20 72 16-May-20, Installation of Leg 2A & 2B Onto Support
F2-JK2-JF05-155
Installation of Row-1A & 2A X-Brace 7 25-May-20 02-Jun-20 65 02-Jun-20, Installation of Row-1A & 2A X-Brace
F2-JK2-JF05-156
Installation of Row-1A & 1B X-Brace in Final Position 7 18-Jun-20 26-Jun-20 65 26-Jun-20, Installation of Row-1A & 1B X-Brace in Final Position
F2-JK2-JF05-157
Roll Up X-Brace Row A&B to Final Position 7 02-Jun-20 10-Jun-20 65 10-Jun-20, Roll Up X-Brace Row A&B to Final Position
F2-JK2-JF05-158
Installing Tie-back for Fastener 4 10-Jun-20 15-Jun-20 65 15-Jun-20, Installing Tie-back for Fastener
Grouting Line 40 09-Jun-20 25-Jul-20 60 25-Jul-20, Grouting Line
F2-JK2-JF05-125
Installation Of Grouting Line 5 20-Jul-20 25-Jul-20 60 25-Jul-20, Installation Of Grouting Line
F2-JK2-JF05-127
Installation Grouting Line Support 7 09-Jun-20 17-Jun-20 89 17-Jun-20, Installation Grouting Line Support
Row Roll Up 7 11-Jul-20 20-Jul-20 60 20-Jul-20, Row Roll Up
F2-JK2-JF05-105Roll Up Of Lower Jacket To Final Position 2 11-Jul-20 14-Jul-20 60 14-Jul-20, Roll Up Of Lower Jacket To Final Position
F2-JK2-JF05-106Roll Up Of Upper Jacket To Final Position 5 14-Jul-20 20-Jul-20 60 20-Jul-20, Roll Up Of Upper Jacket To Final Position
Transition Piece (TP) 76 07-May-20 04-Aug-20 47 04-Aug-20, Transition Piece (TP)
F2-JK2-JF05-1 Install Door Platform 10 30-May-20 11-Jun-20 76 11-Jun-20, Install Door Platform
F2-JK2-JF05-17Installation & Assembly of Ring Stiffener 21 02-Jun-20 26-Jun-20 47 26-Jun-20, Installation & Assembly of Ring Stiffener
F2-JK2-JF05-18Installation of Transition Piece Flange 15 10-Jun-20 27-Jun-20 47 27-Jun-20, Installation of Transition Piece Flange
F2-JK2-JF05-19Install Crane Pedestal 12 09-May-20 23-May-20 93 23-May-20, Install Crane Pedestal
F2-JK2-JF05-2 Blasting & Painting 10 15-Jul-20 27-Jul-20 47 27-Jul-20, Blasting & Painting
F2-JK2-JF05-3 Assemble Can Transition Piece Barrel to Main Deck 15 07-May-20 25-May-20 47 25-May-20, Assemble Can Transition Piece Barrel to Main Deck
F2-JK2-JF05-4 Install Platform & Internal Structure into Upper Can 7 27-Jul-20 04-Aug-20 47 04-Aug-20, Install Platform & Internal Structure into Upper Can
F2-JK2-JF05-5 Door opening & Installation of Door frame 5 25-May-20 30-May-20 86 30-May-20, Door opening & Installation of Door frame
F2-JK2-JF05-6 Installation & Assembly of Strut 15 25-May-20 11-Jun-20 47 11-Jun-20, Installation & As sembly of Strut
F2-JK2-JF05-7 Install Free-Issued Items 15 27-Jun-20 15-Jul-20 47 15-Jul-20, Install Free-Issued Items
F2-JK2-JF05-8 Install Architectural items, Electrical & Instrument Equipments 15 25-May-20 11-Jun-20 76 11-Jun-20, Install Archit ectural it ems, Electrical & Instrument Equipments
F2-JK2-JF05-9 Install External Platform & Handrail 12 28-May-20 11-Jun-20 76 11-Jun-20, Install External Platform & Handrail
Final Assembly 8 04-Aug-20 13-Aug-20 48 13-Aug-20, Final Assembly
F2-JK2-JF05-107Installation of Transition Piece 3 04-Aug-20 07-Aug-20 47 07-Aug-20, Installation of Transition Piece
F2-JK2-JF05-108Installation of Mudmad Plate 5 06-Aug-20 12-Aug-20 47 12-Aug-20, Installation of Mudmad Plate
F2-JK2-JF05-109Installation of Lifting Trunnion 4 07-Aug-20 12-Aug-20 49 12-Aug-20, Installation of Lifting Trunnion
F2-JK2-JF05-110Installation of Skirt Pile Sleeve 2 06-Aug-20 08-Aug-20 47 08-Aug-20, Installation of Skirt Pile Sleeve
F2-JK2-JF05-111Final Touch Up Coating 3 10-Aug-20 13-Aug-20 47 13-Aug-20, Final Touch Up Coating
F2-JK2-JF05-112Installation of Lifting Slings 1 08-Aug-20 10-Aug-20 47 10-Aug-20, Installation of Lifting Slings
F2-JK2-JF05-161J acket Fabrication Completed 0 13-Aug-20 47 13-Aug-20
Testing & Commissioning 18 25-Jul-20 15-Aug-20 47 15-Aug-20, Testing & Commissioning
Grouting & Gripper Test 3 25-Jul-20 29-Jul-20 60 29-Jul-20, Grouting & Gripper Test
F2-JK2-JF05-20Gripper Test 2 27-Jul-20 29-Jul-20 60 29-Jul-20, Gripper Test
F2-JK2-JF05-21Grouting Test 1 25-Jul-20 27-Jul-20 60 27-Jul-20, Grouting Test
Mechanical Completion 2 13-Aug-20 15-Aug-20 47 15-Aug-20, Mechanical Completion
F2-JK2-JF05-22Main Structure, Boat Landing, J-Tube, Transition Piece 2 13-Aug-20 15-Aug-20 47 15-Aug-20, Main Structure, Boat Landing, J-Tube, Transition Piece
Jacket & Piles Ready For Loadout 0 15-Aug-20 15-Aug-20 47 15-Aug-20, Jacket & Piles Ready For Loadout
F2-JK2-JF05-23Jacket Ready For Load Out 0 15-Aug-20 47 15-Aug-20
LOT B - 5 Jacket Foundations 158 07-Mar-20 08-Sep-20 52 08-Sep-20, LOT B - 5 Jacket Foundations
Jacket Foundation 6a 130 07-Mar-20 06-Aug-20 55 06-Aug-20, Jacket Foundation 6a
Fabrication 72 07-Mar-20 30-May-20 103 30-May-20, Fabrication
Pre-Fabrication 38 07-Mar-20 21-Apr-20 104 21-Apr-20, Pre-Fabrication
F2-JK2-JF06-140Rolling of Can Transition Piece Flange 10 09-Apr-20 21-Apr-20 104 21-Apr-20, Rolling of Can Transition Piece Flange
F2-JK2-JF06-141Rolling of Can Transition Piece Barrel 10 19-Mar-20 31-Mar-20 55 31-Mar-20, Rolling of Can Transition Piece Barrel
F2-JK2-JF06-24Rolling of Can Row 2 Brace 10 07-Mar-20 19-Mar-20 0 19-Mar-20, Rolling of Can Row 2 Brace
F2-JK2-JF06-25Rolling of Can Leg 1A & 1B 10 07-Mar-20 19-Mar-20 68 19-Mar-20, Rolling of Can Leg 1A & 1B

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 29 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF06-26Rolling of Can Leg 2A & 2B 10 16-Mar-20 27-Mar-20 68 27-Mar-20, Rolling of Can Leg 2A & 2B
F2-JK2-JF06-27Rolling of Node Can Row 1 10 16-Mar-20 27-Mar-20 68 27-Mar-20, Rolling of Node Can Row 1
F2-JK2-JF06-28Rolling of Node Can Row 2 10 24-Mar-20 04-Apr-20 68 04-Apr-20, Rolling of Node Can Row 2
F2-JK2-JF06-29Rolling of Can Row 1 Brace 10 24-Mar-20 04-Apr-20 68 04-Apr-20, Rolling of Can Row 1 Brace
F2-JK2-JF06-30Rolling of J-Tubes & J-Tubes Support 10 01-Apr-20 13-Apr-20 69 13-Apr-20, Rolling of J-Tubes & J-Tubes Support
F2-JK2-JF06-31Rolling of Can Plan Level Tubular 10 01-Apr-20 13-Apr-20 104 13-Apr-20, Rolling of Can Plan Level Tubular
F2-JK2-JF06-32Rolling of Can Top Bay X-Brace 10 09-Apr-20 21-Apr-20 104 21-Apr-20, Rolling of Can Top Bay X-Brace
Row 1 Fabrication 42 19-Mar-20 07-May-20 109 07-May-20, Row 1 Fabrication
Legs 40 19-Mar-20 06-May-20 71 06-May-20, Legs
F2-JK2-JF06-40
Install Stubs on to Leg 1A & 1B Nodes 2 25-Apr-20 28-Apr-20 68 28-Apr-20, Install Stubs on to Leg 1A & 1B Nodes
F2-JK2-JF06-41
Install Anodes on Row-1 Legs 4 27-Apr-20 01-May-20 70 01-May-20, Install Anodes on Row-1 Legs
F2-JK2-JF06-42
Join of Can Legs 1A 9 24-Mar-20 03-Apr-20 83 03-Apr-20, Join of Can Legs 1A
F2-JK2-JF06-43
Join of Can Legs 1B 9 24-Mar-20 03-Apr-20 83 03-Apr-20, Join of Can Legs 1B
F2-JK2-JF06-44
Mark and Profile Leg 1A & 1B Node 4 27-Mar-20 01-Apr-20 93 01-Apr-20, Mark and Profile Leg 1A & 1B Node
F2-JK2-JF06-45
Profilling of Legs 1A & 1B (Inc. Cones) 4 19-Mar-20 24-Mar-20 83 24-Mar-20, Profilling of Legs 1A & 1B (Inc. Cones)
F2-JK2-JF06-46
Join of Leg 1A & 1B Node 2 27-Apr-20 29-Apr-20 71 29-Apr-20, Join of Leg 1A & 1B Node
F2-JK2-JF06-47
Blasting and Painting for Leg 1A & 1B Node 5 29-Apr-20 06-May-20 71 06-May-20, Blasting and Painting for Leg 1A & 1B Node
F2-JK2-JF06-48
Assembly Leg 1A 3 24-Apr-20 27-Apr-20 68 27-Apr-20, Assembly Leg 1A
F2-JK2-JF06-49
Assembly Leg 1B 3 24-Apr-20 27-Apr-20 68 27-Apr-20, Assembly Leg 1B
Braces 28 04-Apr-20 07-May-20 68 07-May-20, Braces
F2-JK2-JF06-50
Fit & Weld Top X Brace Between Legs 1A & 1B 5 28-Apr-20 04-May-20 68 04-May-20, Fit & Weld Top X Brace Between Legs 1A & 1B
F2-JK2-JF06-51
Join of Row-1 Can Brace (Inc. Stub) 13 09-Apr-20 24-Apr-20 68 24-Apr-20, Join of Row-1 Can Brace (Inc. Stub)
F2-JK2-JF06-52
Join of Can Brace for Between Row 1 & 2 (Inc. Stub) 13 09-Apr-20 24-Apr-20 68 24-Apr-20, Join of Can Brace for Between Row 1 & 2 (Inc. Stub)
F2-JK2-JF06-53
Assembly of Row-1 Top Brace 4 24-Apr-20 28-Apr-20 68 28-Apr-20, Assembly of Row-1 Top Brace
F2-JK2-JF06-54
Fit & Weld Row-2 K-Brace (Inc. Vertical Braces) 5 28-Apr-20 04-May-20 68 04-May-20, Fit & Weld Row-2 K-Brace (Inc. Vertical Braces)
F2-JK2-JF06-55
Assembly of Row-1 K-Brace 4 24-Apr-20 28-Apr-20 68 28-Apr-20, Assembly of Row-1 K-Brace
F2-JK2-JF06-56
Fit & Weld X-Brace Between Row 1 & 2 5 28-Apr-20 04-May-20 68 04-May-20, Fit & Weld X-Brace Between Row 1 & 2
F2-JK2-JF06-57
Assembly of Brace Between Row 1 & 2 4 24-Apr-20 28-Apr-20 68 28-Apr-20, Assembly of Brace Between Row 1 & 2
F2-JK2-JF06-58
Profilling of Row-1 Braces and Stubs 4 04-Apr-20 09-Apr-20 68 09-Apr-20, Profilling of Row-1 Braces and Stubs
F2-JK2-JF06-59
Install Anodes on Row-1 Braces 4 04-May-20 07-May-20 68 07-May-20, Install Anodes on Row-1 Braces
J-Tubes 19 13-Apr-20 05-May-20 111 05-May-20, J-Tubes
F2-JK2-JF06-60
Join of Row-1 J-Tubes 5 17-Apr-20 23-Apr-20 111 23-Apr-20, Join of Row-1 J-Tubes
F2-JK2-JF06-61
Profilling of Row-1 J-Tubes 4 13-Apr-20 17-Apr-20 111 17-Apr-20, Profilling of Row-1 J-Tubes
F2-JK2-JF06-62
Bending of Row-1 J-Tubes 4 23-Apr-20 27-Apr-20 111 27-Apr-20, Bending of Row-1 J-Tubes
F2-JK2-JF06-63
Blast and Paint for Row-1 J-Tubes 3 27-Apr-20 01-May-20 111 01-May-20, Blast and Paint for Row-1 J-Tubes
F2-JK2-JF06-64
Assembly Row-1 J-Tubes 3 01-May-20 05-May-20 111 05-May-20, Assembly Row-1 J-Tubes
F2-JK2-JF06-65
Cut and Profile Row-1 J-Tubes Support 4 13-Apr-20 17-Apr-20 111 17-Apr-20, Cut and Profile Row-1 J-Tubes Support
F2-JK2-JF06-66
Assembly Row-1 J-Tubes Support 2 17-Apr-20 21-Apr-20 111 21-Apr-20, Assembly Row-1 J-Tubes Support
F2-JK2-JF06-67
Paint Row-1 J-Tubes Support 3 21-Apr-20 24-Apr-20 111 24-Apr-20, Paint Row-1 J-Tubes Support
F2-JK2-JF06-68
Install J-Tubes Support on to Row-1 J-Tubes 3 24-Apr-20 27-Apr-20 111 27-Apr-20, Install J-Tubes Support on to Row-1 J-Tubes
Common 23 11-Apr-20 07-May-20 69 07-May-20, Common
Structure 3 11-Apr-20 15-Apr-20 76 15-Apr-20, Structure
F2-JK2-JF06-33
Marking & Cutting of Leg and Brace Node 3 11-Apr-20 15-Apr-20 76 15-Apr-20, Marking & Cutting of Leg and Brace Node
F2-JK2-JF06-34
Marking & Cutting of Brace Stub 3 11-Apr-20 15-Apr-20 76 15-Apr-20, Marking & Cutting of Brace Stub
F2-JK2-JF06-35
Marking & Cutting of Leg and Brace Member 3 11-Apr-20 15-Apr-20 76 15-Apr-20, Marking & Cutting of Leg and Brace Member
Final Painting 23 11-Apr-20 07-May-20 69 07-May-20, Final Painting
F2-JK2-JF06-36
Blast and Paint Leg and Brace (Initial Paint) 11 11-Apr-20 24-Apr-20 68 24-Apr-20, Blast and Paint Leg and Brace (Initial Paint)
F2-JK2-JF06-37
Build Painting Habitat Protection 1 04-May-20 06-May-20 71 06-May-20, Build Painting Habitat Protection
F2-JK2-JF06-38
Row-1 Ready for Assembly & Roll-up 0 06-May-20 71 06-May-20
F2-JK2-JF06-39
Row-1 Touch up and Final Painting 3 04-May-20 07-May-20 68 07-May-20, Row-1 Touch up and Final Painting
Row 2 Fabrication 42 19-Mar-20 07-May-20 69 07-May-20, Row 2 Fabrication
Legs 23 27-Mar-20 23-Apr-20 82 23-Apr-20, Legs
F2-JK2-JF06-76
Install Anodes on Row-2 Legs 4 14-Apr-20 18-Apr-20 81 18-Apr-20, Install Anodes on Row-2 Legs
F2-JK2-JF06-77
Join of Can Legs 2A 9 01-Apr-20 11-Apr-20 76 11-Apr-20, Join of Can Legs 2A
F2-JK2-JF06-78
Join of Can Legs 2B 9 01-Apr-20 11-Apr-20 76 11-Apr-20, Join of Can Legs 2B

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 30 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF06-79
Profilling of Legs 2A & 2B (Inc. Cones) 4 27-Mar-20 01-Apr-20 76 01-Apr-20, Profilling of Legs 2A & 2B (Inc. Cones)
F2-JK2-JF06-80
Mark and Profile Leg 2A & 2B Node 4 04-Apr-20 09-Apr-20 86 09-Apr-20, Mark and Profile Leg 2A & 2B Node
F2-JK2-JF06-81
Join of Leg 2A & 2B Node 2 14-Apr-20 16-Apr-20 82 16-Apr-20, Join of Leg 2A & 2B Node
F2-JK2-JF06-82
Blasting and Painting for Leg 2A & 2B Node (Initial) 5 16-Apr-20 23-Apr-20 82 23-Apr-20, Blasting and Painting for Leg 2A & 2B Node (Initial)
F2-JK2-JF06-83
Assembly Leg 2A 3 11-Apr-20 14-Apr-20 74 14-Apr-20, Assembly Leg 2A
F2-JK2-JF06-84
Assembly Leg 2B 3 11-Apr-20 14-Apr-20 74 14-Apr-20, Assembly Leg 2B
F2-JK2-JF06-85
Install Stubs on to Leg 2A & 2B Nodes 2 14-Apr-20 16-Apr-20 74 16-Apr-20, Install Stubs on to Leg 2A & 2B Nodes
Braces 32 19-Mar-20 25-Apr-20 74 25-Apr-20, Braces
F2-JK2-JF06-138
Fit & Weld Row-2 K-Brace (Inc. Vertical Braces) 5 16-Apr-20 22-Apr-20 74 22-Apr-20, Fit & Weld Row-2 K-Brace (Inc. Vertical Braces)
F2-JK2-JF06-139
Assembly of Row-2 K-Brace 4 11-Apr-20 15-Apr-20 75 15-Apr-20, Assembly of Row-2 K-Brace
F2-JK2-JF06-86
Fit & Weld Top X-Brace Between Legs 2A & 2B 4 16-Apr-20 21-Apr-20 77 21-Apr-20, Fit & Weld Top X-Brace Between Legs 2A & 2B
F2-JK2-JF06-87
Fit & Weld Mid X-Brace Between Legs 2A & 2B 4 16-Apr-20 21-Apr-20 77 21-Apr-20, Fit & Weld Mid X-Brace Between Legs 2A & 2B
F2-JK2-JF06-88
Join of Row-2 Can Brace (Inc. Stub) 10 24-Mar-20 04-Apr-20 74 04-Apr-20, Join of Row-2 Can Brace (Inc. Stub)
F2-JK2-JF06-89
Assembly of Row-2 Top Brace 3 11-Apr-20 15-Apr-20 78 15-Apr-20, Assembly of Row-2 Top Brace
F2-JK2-JF06-90
Assembly of Row-2 Mid Brace 3 11-Apr-20 15-Apr-20 78 15-Apr-20, Assembly of Row-2 Mid Brace
F2-JK2-JF06-91
Profilling of Row-2 Braces and Stubs 4 19-Mar-20 24-Mar-20 74 24-Mar-20, Profilling of Row-2 Braces and Stubs
F2-JK2-JF06-92
Install Anodes on Row-2 Braces 4 22-Apr-20 25-Apr-20 74 25-Apr-20, Install Anodes on Row-2 Braces
J-Tubes 21 13-Apr-20 07-May-20 69 07-May-20, J-Tubes
F2-JK2-JF06-128
Join of Row-2 J-Tubes 5 17-Apr-20 23-Apr-20 72 23-Apr-20, Join of Row-2 J-Tubes
F2-JK2-JF06-129
Profilling of Row-2 J-Tubes 4 13-Apr-20 17-Apr-20 72 17-Apr-20, Profilling of Row-2 J-Tubes
F2-JK2-JF06-130
Bending of Row-2 J-Tubes 4 23-Apr-20 27-Apr-20 72 27-Apr-20, Bending of Row-2 J-Tubes
F2-JK2-JF06-131
Blast and Paint for Row-2 J-Tubes 3 30-Apr-20 04-May-20 69 04-May-20, Blast and Paint for Row-2 J-Tubes
F2-JK2-JF06-132
Assembly Row-2 J-Tubes 3 04-May-20 07-May-20 69 07-May-20, Assembly Row-2 J-Tubes
F2-JK2-JF06-133
Cut and Profile Row-2 J-Tubes Support 4 13-Apr-20 17-Apr-20 69 17-Apr-20, Cut and Profile Row-2 J-Tubes Support
F2-JK2-JF06-134
Assembly Row-2 J-Tubes Support 2 17-Apr-20 21-Apr-20 69 21-Apr-20, Assembly Row-2 J-Tubes Support
F2-JK2-JF06-135
Vulcanized Row-2 J-Tubes Support 2 21-Apr-20 23-Apr-20 69 23-Apr-20, Vulcanized Row-2 J-Tubes Support
F2-JK2-JF06-136
Paint Row-2 J-Tubes Support 3 23-Apr-20 27-Apr-20 69 27-Apr-20, Paint Row-2 J-Tubes Support
F2-JK2-JF06-137
Install J-Tubes Support on to Row-2 J-Tubes 3 27-Apr-20 30-Apr-20 69 30-Apr-20, Install J-Tubes Support on to Row-2 J-Tubes
Common 23 04-Apr-20 01-May-20 74 01-May-20, Common
Structure 3 04-Apr-20 08-Apr-20 78 08-Apr-20, Structure
F2-JK2-JF06-69
Marking & Cutting of Leg and Brace Node 3 04-Apr-20 08-Apr-20 78 08-Apr-20, Marking & Cutting of Leg and Brace Node
F2-JK2-JF06-70
Marking & Cutting of Brace Stub 3 04-Apr-20 08-Apr-20 78 08-Apr-20, Marking & Cutting of Brace Stub
F2-JK2-JF06-71
Marking & Cutting of Leg and Brace Member 3 04-Apr-20 08-Apr-20 78 08-Apr-20, Marking & Cutting of Leg and Brace Member
Final Painting 23 04-Apr-20 01-May-20 74 01-May-20, Final Painting
F2-JK2-JF06-72
Row-2 Touch up and Final Painting 3 25-Apr-20 30-Apr-20 74 30-Apr-20, Row-2 Touch up and Final Painting
F2-JK2-JF06-73
Blast and Paint Leg and Brace (Initial Paint) 5 04-Apr-20 11-Apr-20 74 11-Apr-20, Blast and Paint Leg and Brace (Initial Paint)
F2-JK2-JF06-74
Build Painting Habitat Protection 1 30-Apr-20 01-May-20 74 01-May-20, Build Painting Habitat Protection
F2-JK2-JF06-75
Row-2 Ready for Assembly & Roll-up 0 01-May-20 74 01-May-20
Transition Piece 61 19-Mar-20 29-May-20 104 29-May-20, Transition Piece
F2-JK2-JF06-10Fabrication of Can Transition Piece Barrel 24 31-Mar-20 28-Apr-20 55 28-Apr-20, Fabrication of Can Transition Piece Barrel
F2-JK2-JF06-100Fit Grating Supports 4 01-Apr-20 06-Apr-20 121 06-Apr-20, Fit Grating Supports
F2-JK2-JF06-101Fab Main Deck Handrails 4 26-Mar-20 30-Mar-20 122 30-Mar-20, Fab Main Deck Handrails
F2-JK2-JF06-102Fab Padeye inc Top of Jacket 4 27-Mar-20 31-Mar-20 148 31-Mar-20, Fab Padeye inc Top of Jacket
F2-JK2-JF06-103Blast and Paint Transition Piece 7 21-May-20 29-May-20 104 29-May-20, Blast and Paint Transition Piece
F2-JK2-JF06-11 Fabrication of Strut Plate 18 19-Mar-20 09-Apr-20 16 09-Apr-20, Fabrication of Strut Plate
F2-JK2-JF06-12Fabrication of Internal Platform 21 19-Mar-20 13-Apr-20 133 13-Apr-20, Fabrication of Internal Platform
F2-JK2-JF06-13Fabrication of External Platform 25 19-Mar-20 17-Apr-20 133 17-Apr-20, Fabrication of External Platform
F2-JK2-JF06-14Assembly Strut Plate 21 09-Apr-20 04-May-20 119 04-May-20, Assembly Strut Plate
F2-JK2-JF06-15Fabrication of Ring Stiffener 21 27-Apr-20 21-May-20 104 21-May-20, Fabrication of Ring Stiffener
F2-JK2-JF06-16Fabrication of Crane Pedestal 21 09-Apr-20 04-May-20 97 04-May-20, Fabrication of Crane Pedestal
F2-JK2-JF06-93Galvanizing Handrails 5 30-Mar-20 04-Apr-20 122 04-Apr-20, Galvanizing Handrails
F2-JK2-JF06-94Erect Deck Plate Areas 5 27-Mar-20 01-Apr-20 120 01-Apr-20, Erect Deck Plate Areas
F2-JK2-JF06-95Transition Piece Fabrication Complete 0 21-May-20 104 21-May-20
F2-JK2-JF06-96Fabrication Assemble Walkways / Platforms 21 09-Apr-20 04-May-20 119 04-May-20, Fabrication Assemble Walkways / Platforms
F2-JK2-JF06-97Fit and Weld TP's Equipment Supports 5 27-Mar-20 03-Apr-20 120 03-Apr-20, Fit and Weld TP's Equipment Supports

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 31 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF06-98Plate Profiling for Main Deck 5 19-Mar-20 26-Mar-20 75 26-Mar-20, Plate Profiling for Main Deck
F2-JK2-JF06-99Fab Main Deck Main Steel 5 21-Mar-20 27-Mar-20 75 27-Mar-20, Fab Main Deck Main Steel
Lifting Trunnion 7 27-Mar-20 04-Apr-20 75 04-Apr-20, Lifting Trunnion
F2-JK2-JF06-104Fabricate Lifting Trunion 7 27-Mar-20 04-Apr-20 75 04-Apr-20, Fabricate Lifting Trunion
Boat Landing 44 31-Mar-20 22-May-20 100 22-May-20, Boat Landing
F2-JK2-JF06-123Blast and Paint Boat Landing 5 15-May-20 22-May-20 100 22-May-20, Blast and Paint Boat Landing
F2-JK2-JF06-124Fabricate Boat Landing 21 31-Mar-20 24-Apr-20 45 24-Apr-20, Fabricate Boat Landing
F2-JK2-JF06-159Fabricate Boat Landing Access platform 24 17-Apr-20 15-May-20 100 15-May-20, Fabricate Boat Landing Access platform
F2-JK2-JF06-160Fabricate Boat Landing Ladders 15 25-Apr-20 13-May-20 102 13-May-20, Fabricate Boat Landing Ladders
Grouting Line 23 04-May-20 30-May-20 97 30-May-20, Grouting Line
F2-JK2-JF06-126Fabricate Grouting Line & Grouting Line Support 23 04-May-20 30-May-20 97 30-May-20, Fabricate Grouting Line & Grouting Line Support
Assembly 105 04-Apr-20 04-Aug-20 56 04-Aug-20, Assembly
Row Assembly 88 04-Apr-20 16-Jul-20 68 16-Jul-20, Row Assembly
F2-JK2-JF06-113Fabricate Upper Grillage & Truss Support 18 04-Apr-20 25-Apr-20 75 25-Apr-20, Fabricate Upper Grillage & Truss Support
F2-JK2-JF06-114Layout Concrete Blocks/ Grillages and Truss Support Steel 4 04-May-20 09-May-20 68 09-May-20, Layout Concrete Blocks/ Grillages and Truss Support Steel
Row-1 & 2 (Upper Jacket) Assembly 46 09-May-20 02-Jul-20 68 02-Jul-20, Row-1 & 2 (Upper Jacket) Assembly
F2-JK2-JF06-115
Installation of Grouting Line 1 27-May-20 28-May-20 88 28-May-20, Installation of Grouting Line
F2-JK2-JF06-117
Installation of J-Tube At Row-1B & 2A 5 27-May-20 02-Jun-20 92 02-Jun-20, Installation of J-Tube At Row-1B & 2A
F2-JK2-JF06-118
Row-2 - Touch Up, 2nd Coat & Top Coat 3 29-Jun-20 01-Jul-20 68 01-Jul-20, Row-2 - Touch Up, 2nd Coat & Top Coat
F2-JK2-JF06-119
Installation of Row-1B & 2B X-Brace 7 19-May-20 27-May-20 68 27-May-20, Installation of Row-1B & 2B X-Brace
F2-JK2-JF06-120
Installation of Leg 1A & 1B Onto Support 1 09-May-20 11-May-20 68 11-May-20, Installation of Leg 1A & 1B Onto Suppor t
F2-JK2-JF06-121
Installation of Row-1A & 1B X-Brace 7 11-May-20 19-May-20 68 19-May-20, Installation of Row-1A & 1B X-Brace
F2-JK2-JF06-122
Installation of Row-2A & 2B X-Brace in Final Position 7 20-Jun-20 29-Jun-20 68 29-Jun-20, Installation of Row-2A & 2B X-Brace in Final Position
F2-JK2-JF06-142
Installation of Leg 2A & 2B Onto Support 1 09-May-20 11-May-20 75 11-May-20, Installation of Leg 2A & 2B Onto Suppor t
F2-JK2-JF06-143
Installation of Row-1A & 2A X-Brace 7 19-May-20 27-May-20 68 27-May-20, Installation of Row-1A & 2A X-Brace
F2-JK2-JF06-144
Installation of Row-1A & 1B X-Brace in Final Position 7 12-Jun-20 20-Jun-20 68 20-Jun-20, Installation of Row-1A & 1B X-Brace in Final Position
F2-JK2-JF06-145
Roll Up X-Brace Row A&B to Final Position 7 27-May-20 04-Jun-20 68 04-Jun-20, Roll Up X-Brace Row A&B to Final Position
F2-JK2-JF06-146
Installing Tie-back for Fastener 7 04-Jun-20 12-Jun-20 68 12-Jun-20, Installing Tie-back for Fastener
F2-JK2-JF06-147
Installation of Boat Landing 3 29-Jun-20 02-Jul-20 68 02-Jul-20, Installation of Boat Landing
Row-1 & 2 (Lower Jacket) Assembly 44 06-May-20 25-Jun-20 73 25-Jun-20, Row-1 & 2 (Lower Jacket) Assembly
F2-JK2-JF06-116
Installation of Pile Stopper 4 05-Jun-20 09-Jun-20 73 09-Jun-20, Installation of Pile Stopper
F2-JK2-JF06-148
Installation of Grouting Line 1 23-May-20 25-May-20 94 25-May-20, Installation of Grouting Line
F2-JK2-JF06-149
Installation of J-Tube At Row-1B & 2A 5 23-May-20 29-May-20 83 29-May-20, Installation of J-Tube At Row-1B & 2A
F2-JK2-JF06-150
Installation of Row-1B & 2B X-Brace 7 15-May-20 23-May-20 73 23-May-20, Installation of Row-1B & 2B X-Brace
F2-JK2-JF06-151
Installation of Leg 1A & 1B Onto Support 1 06-May-20 07-May-20 73 07-May-20, Installation of Leg 1A & 1B Onto Support
F2-JK2-JF06-152
Installation of Row-1A & 1B X-Brace 7 07-May-20 15-May-20 73 15-May-20, Installation of Row-1A & 1B X-Brace
F2-JK2-JF06-153
Installation of Row-2A & 2B X-Brace in Final Position 7 17-Jun-20 25-Jun-20 73 25-Jun-20, Installation of Row-2A & 2B X-Brace in Final Position
F2-JK2-JF06-154
Installation of Leg 2A & 2B Onto Support 1 06-May-20 07-May-20 80 07-May-20, Installation of Leg 2A & 2B Onto Support
F2-JK2-JF06-155
Installation of Row-1A & 2A X-Brace 7 15-May-20 23-May-20 73 23-May-20, Installation of Row-1A & 2A X-Brace
F2-JK2-JF06-156
Installation of Row-1A & 1B X-Brace in Final Position 7 09-Jun-20 17-Jun-20 73 17-Jun-20, Installation of Row-1A & 1B X-Brace in Final Position
F2-JK2-JF06-157
Roll Up X-Brace Row A&B to Final Position 7 23-May-20 01-Jun-20 73 01-Jun-20, Roll Up X-Brace Row A&B to Final Position
F2-JK2-JF06-158
Installing Tie-back for Fastener 4 01-Jun-20 05-Jun-20 73 05-Jun-20, Installing Tie-back for Fastener
Grouting Line 40 30-May-20 16-Jul-20 68 16-Jul-20, Grouting Line
F2-JK2-JF06-125
Installation Of Grouting Line 5 10-Jul-20 16-Jul-20 68 16-Jul-20, Installation Of Grouting Line
F2-JK2-JF06-127
Installation Grouting Line Support 7 30-May-20 08-Jun-20 97 08-Jun-20, Installation Grouting Line Support
Row Roll Up 7 02-Jul-20 10-Jul-20 68 10-Jul-20, Row Roll Up
F2-JK2-JF06-105Roll Up Of Lower Jacket To Final Position 2 02-Jul-20 04-Jul-20 68 04-Jul-20, Roll Up Of Lower Jacket To Final Position
F2-JK2-JF06-106Roll Up Of Upper Jacket To Final Position 5 04-Jul-20 10-Jul-20 68 10-Jul-20, Roll Up Of Upper Jacket To Final Position
Transition Piece (TP) 76 28-Apr-20 25-Jul-20 55 25-Jul-20, Transition Piece (TP)
F2-JK2-JF06-1 Install Door Platform 10 21-May-20 02-Jun-20 84 02-Jun-20, Install Door Platform
F2-JK2-JF06-17Installation & Assembly of Ring Stiffener 21 23-May-20 17-Jun-20 55 17-Jun-20, Installation & Assembly of Ring Stiffener
F2-JK2-JF06-18Installation of Transition Piece Flange 15 01-Jun-20 18-Jun-20 55 18-Jun-20, Installation of Transition Piece Flange
F2-JK2-JF06-19Install Crane Pedestal 12 04-May-20 18-May-20 97 18-May-20, Install Crane Pedestal
F2-JK2-JF06-2 Blasting & Painting 10 06-Jul-20 17-Jul-20 55 17-Jul-20, Blasting & Painting
F2-JK2-JF06-3 Assemble Can Transition Piece Barrel to Main Deck 15 28-Apr-20 15-May-20 55 15-May-20, Assemble Can Transition Piece Barrel to Main Deck

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 32 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF06-4 Install Platform & Internal Structure into Upper Can 7 17-Jul-20 25-Jul-20 55 25-Jul-20, Install Platform & Internal Structure into Upper Can
F2-JK2-JF06-5 Door opening & Installation of Door frame 5 15-May-20 21-May-20 94 21-May-20, Door opening & Installation of Door frame
F2-JK2-JF06-6 Installation & Assembly of Strut 15 15-May-20 02-Jun-20 55 02-Jun-20, Installation & Assembly of Strut
F2-JK2-JF06-7 Install Free-Issued Items 15 18-Jun-20 06-Jul-20 55 06-Jul-20, Install Free-Issued Items
F2-JK2-JF06-8 Install Architectural items, Electrical & Instrument Equipments 15 15-May-20 02-Jun-20 84 02-Jun-20, Install Architectural items, Electrical & Instrument Equipments
F2-JK2-JF06-9 Install External Platform & Handrail 12 19-May-20 02-Jun-20 84 02-Jun-20, Install External Platform & Handrail
Final Assembly 8 25-Jul-20 04-Aug-20 56 04-Aug-20, Final Assembly
F2-JK2-JF06-107Installation of Transition Piece 3 25-Jul-20 29-Jul-20 55 29-Jul-20, Installation of Transition Piece
F2-JK2-JF06-108Installation of Mudmad Plate 5 28-Jul-20 03-Aug-20 55 03-Aug-20, Installation of Mudmad Plate
F2-JK2-JF06-109Installation of Lifting Trunnion 4 29-Jul-20 03-Aug-20 57 03-Aug-20, Installation of Lifting Trunnion
F2-JK2-JF06-110Installation of Skirt Pile Sleeve 2 28-Jul-20 30-Jul-20 55 30-Jul-20, Installation of Skirt Pile Sleeve
F2-JK2-JF06-111Final Touch Up Coating 3 31-Jul-20 04-Aug-20 55 04-Aug-20, Final Touch Up Coating
F2-JK2-JF06-112Installation of Lifting Slings 1 30-Jul-20 31-Jul-20 55 31-Jul-20, Installation of Lifting Slings
F2-JK2-JF06-161J acket Fabrication Completed 0 04-Aug-20 55 04-Aug-20
Testing & Commissioning 18 16-Jul-20 06-Aug-20 55 06-Aug-20, Testing & Commissioning
Grouting & Gripper Test 3 16-Jul-20 20-Jul-20 68 20-Jul-20, Grouting & Gripper Test
F2-JK2-JF06-20Gripper Test 2 17-Jul-20 20-Jul-20 68 20-Jul-20, Gripper Test
F2-JK2-JF06-21Grouting Test 1 16-Jul-20 17-Jul-20 68 17-Jul-20, Grouting Test
Mechanical Completion 2 04-Aug-20 06-Aug-20 55 06-Aug-20, Mechanical Completion
F2-JK2-JF06-22Main Structure, Boat Landing, J-Tube, Transition Piece 2 04-Aug-20 06-Aug-20 55 06-Aug-20, Main Structure, Boat Landing, J-Tube, Transition Piece
Jacket & Piles Ready For Loadout 0 06-Aug-20 06-Aug-20 55 06-Aug-20, Jacket & Piles Ready For Loadout
F2-JK2-JF06-23Jacket Ready For Load Out 0 06-Aug-20 55 06-Aug-20
Jacket Foundation 7a 130 16-Mar-20 14-Aug-20 48 14-Aug-20, Jacket Foundation 7a
Fabrication 72 16-Mar-20 08-Jun-20 96 08-Jun-20, Fabrication
Pre-Fabrication 38 16-Mar-20 29-Apr-20 97 29-Apr-20, Pre-Fabrication
F2-JK2-JF07-140Rolling of Can Transition Piece Flange 10 17-Apr-20 29-Apr-20 97 29-Apr-20, Rolling of Can Transition Piece Flange
F2-JK2-JF07-141Rolling of Can Transition Piece Barrel 10 27-Mar-20 08-Apr-20 48 08-Apr-20, Rolling of Can Transition Piece Barrel
F2-JK2-JF07-24Rolling of Can Row 2 Brace 10 16-Mar-20 27-Mar-20 0 27-Mar-20, Rolling of Can Row 2 Brace
F2-JK2-JF07-25Rolling of Can Leg 1A & 1B 10 16-Mar-20 27-Mar-20 61 27-Mar-20, Rolling of Can Leg 1A & 1B
F2-JK2-JF07-26Rolling of Can Leg 2A & 2B 10 24-Mar-20 04-Apr-20 61 04-Apr-20, Rolling of Can Leg 2A & 2B
F2-JK2-JF07-27Rolling of Node Can Row 1 10 24-Mar-20 04-Apr-20 61 04-Apr-20, Rolling of Node Can Row 1
F2-JK2-JF07-28Rolling of Node Can Row 2 10 01-Apr-20 13-Apr-20 61 13-Apr-20, Rolling of Node Can Row 2
F2-JK2-JF07-29Rolling of Can Row 1 Brace 10 01-Apr-20 13-Apr-20 61 13-Apr-20, Rolling of Can Row 1 Brace
F2-JK2-JF07-30Rolling of J-Tubes & J-Tubes Support 10 09-Apr-20 21-Apr-20 62 21-Apr-20, Rolling of J-Tubes & J-Tubes Support
F2-JK2-JF07-31Rolling of Can Plan Level Tubular 10 09-Apr-20 21-Apr-20 97 21-Apr-20, Rolling of Can Plan Level Tubular
F2-JK2-JF07-32Rolling of Can Top Bay X-Brace 10 17-Apr-20 29-Apr-20 97 29-Apr-20, Rolling of Can Top Bay X-Brace
Row 1 Fabrication 42 27-Mar-20 15-May-20 102 15-May-20, Row 1 Fabrication
Legs 40 27-Mar-20 14-May-20 64 14-May-20, Legs
F2-JK2-JF07-40
Install Stubs on to Leg 1A & 1B Nodes 2 04-May-20 06-May-20 61 06-May-20, Install Stubs on to Leg 1A & 1B Nodes
F2-JK2-JF07-41
Install Anodes on Row-1 Legs 4 05-May-20 09-May-20 63 09-May-20, Install Anodes on Row-1 Legs
F2-JK2-JF07-42
Join of Can Legs 1A 9 01-Apr-20 11-Apr-20 76 11-Apr-20, Join of Can Legs 1A
F2-JK2-JF07-43
Join of Can Legs 1B 9 01-Apr-20 11-Apr-20 76 11-Apr-20, Join of Can Legs 1B
F2-JK2-JF07-44
Mark and Profile Leg 1A & 1B Node 4 04-Apr-20 09-Apr-20 86 09-Apr-20, Mark and Profile Leg 1A & 1B Node
F2-JK2-JF07-45
Profilling of Legs 1A & 1B (Inc. Cones) 4 27-Mar-20 01-Apr-20 76 01-Apr-20, Profilling of Legs 1A & 1B (Inc. Cones)
F2-JK2-JF07-46
Join of Leg 1A & 1B Node 2 05-May-20 07-May-20 64 07-May-20, Join of Leg 1A & 1B Node
F2-JK2-JF07-47
Blasting and Painting for Leg 1A & 1B Node 5 07-May-20 14-May-20 64 14-May-20, Blasting and Painting for Leg 1A & 1B Node
F2-JK2-JF07-48
Assembly Leg 1A 3 02-May-20 05-May-20 61 05-May-20, Assembly Leg 1A
F2-JK2-JF07-49
Assembly Leg 1B 3 02-May-20 05-May-20 61 05-May-20, Assembly Leg 1B
Braces 28 13-Apr-20 15-May-20 61 15-May-20, Braces
F2-JK2-JF07-50
Fit & Weld Top X Brace Between Legs 1A & 1B 5 06-May-20 12-May-20 61 12-May-20, Fit & Weld Top X Brace Between Legs 1A & 1B
F2-JK2-JF07-51
Join of Row-1 Can Brace (Inc. Stub) 13 17-Apr-20 02-May-20 61 02-May-20, Join of Row-1 Can Brace (Inc. Stub)
F2-JK2-JF07-52
Join of Can Brace for Between Row 1 & 2 (Inc. Stub) 13 17-Apr-20 02-May-20 61 02-May-20, Join of Can Brace for Between Row 1 & 2 (Inc. Stub)
F2-JK2-JF07-53
Assembly of Row-1 Top Brace 4 02-May-20 06-May-20 61 06-May-20, Assembly of Row-1 Top Brace
F2-JK2-JF07-54
Fit & Weld Row-2 K-Brace (Inc. Vertical Braces) 5 06-May-20 12-May-20 61 12-May-20, Fit & Weld Row-2 K-Brace (Inc. Vertical Braces)
F2-JK2-JF07-55
Assembly of Row-1 K-Brace 4 02-May-20 06-May-20 61 06-May-20, Assembly of Row-1 K-Brace

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 33 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF07-56
Fit & Weld X-Brace Between Row 1 & 2 5 06-May-20 12-May-20 61 12-May-20, Fit & Weld X-Brace Between Row 1 & 2
F2-JK2-JF07-57
Assembly of Brace Between Row 1 & 2 4 02-May-20 06-May-20 61 06-May-20, Assembly of Brace Between Row 1 & 2
F2-JK2-JF07-58
Profilling of Row-1 Braces and Stubs 4 13-Apr-20 17-Apr-20 61 17-Apr-20, Profilling of Row-1 Braces and Stubs
F2-JK2-JF07-59
Install Anodes on Row-1 Braces 4 12-May-20 15-May-20 61 15-May-20, Install Anodes on Row-1 Braces
J-Tubes 19 21-Apr-20 13-May-20 104 13-May-20, J-Tubes
F2-JK2-JF07-60
Join of Row-1 J-Tubes 5 25-Apr-20 01-May-20 104 01-May-20, Join of Row-1 J-Tubes
F2-JK2-JF07-61
Profilling of Row-1 J-Tubes 4 21-Apr-20 25-Apr-20 104 25-Apr-20, Profilling of Row-1 J-Tubes
F2-JK2-JF07-62
Bending of Row-1 J-Tubes 4 01-May-20 05-May-20 104 05-May-20, Bending of Row-1 J-Tubes
F2-JK2-JF07-63
Blast and Paint for Row-1 J-Tubes 3 05-May-20 09-May-20 104 09-May-20, Blast and Paint for Row-1 J-Tubes
F2-JK2-JF07-64
Assembly Row-1 J-Tubes 3 09-May-20 13-May-20 104 13-May-20, Assembly Row-1 J-Tubes
F2-JK2-JF07-65
Cut and Profile Row-1 J-Tubes Support 4 21-Apr-20 25-Apr-20 104 25-Apr-20, Cut and Profile Row-1 J-Tubes Support
F2-JK2-JF07-66
Assembly Row-1 J-Tubes Support 2 25-Apr-20 29-Apr-20 104 29-Apr-20, Assembly Row-1 J-Tubes Support
F2-JK2-JF07-67
Paint Row-1 J-Tubes Support 3 29-Apr-20 02-May-20 104 02-May-20, Paint Row-1 J-Tubes Support
F2-JK2-JF07-68
Install J-Tubes Support on to Row-1 J-Tubes 3 02-May-20 05-May-20 104 05-May-20, Install J-Tubes Support on to Row-1 J-Tubes
Common 23 20-Apr-20 15-May-20 62 15-May-20, Common
Structure 3 20-Apr-20 23-Apr-20 69 23-Apr-20, Structure
F2-JK2-JF07-33
Marking & Cutting of Leg and Brace Node 3 20-Apr-20 23-Apr-20 69 23-Apr-20, Marking & Cutting of Leg and Brace Node
F2-JK2-JF07-34
Marking & Cutting of Brace Stub 3 20-Apr-20 23-Apr-20 69 23-Apr-20, Marking & Cutting of Brace Stub
F2-JK2-JF07-35
Marking & Cutting of Leg and Brace Member 3 20-Apr-20 23-Apr-20 69 23-Apr-20, Marking & Cutting of Leg and Brace Member
Final Painting 23 20-Apr-20 15-May-20 62 15-May-20, Final Painting
F2-JK2-JF07-36
Blast and Paint Leg and Brace (Initial Paint) 11 20-Apr-20 02-May-20 61 02-May-20, Blast and Paint Leg and Brace (Initial Paint)
F2-JK2-JF07-37
Build Painting Habitat Protection 1 12-May-20 14-May-20 64 14-May-20, Build Painting Habitat Protection
F2-JK2-JF07-38
Row-1 Ready for Assembly & Roll-up 0 14-May-20 64 14-May-20
F2-JK2-JF07-39
Row-1 Touch up and Final Painting 3 12-May-20 15-May-20 61 15-May-20, Row-1 Touch up and Final Painting
Row 2 Fabrication 42 27-Mar-20 15-May-20 62 15-May-20, Row 2 Fabrication
Legs 23 04-Apr-20 01-May-20 75 01-May-20, Legs
F2-JK2-JF07-76
Install Anodes on Row-2 Legs 4 22-Apr-20 27-Apr-20 74 27-Apr-20, Install Anodes on Row-2 Legs
F2-JK2-JF07-77
Join of Can Legs 2A 9 09-Apr-20 20-Apr-20 69 20-Apr-20, Join of Can Legs 2A
F2-JK2-JF07-78
Join of Can Legs 2B 9 09-Apr-20 20-Apr-20 69 20-Apr-20, Join of Can Legs 2B
F2-JK2-JF07-79
Profilling of Legs 2A & 2B (Inc. Cones) 4 04-Apr-20 09-Apr-20 69 09-Apr-20, Profilling of Legs 2A & 2B (Inc. Cones)
F2-JK2-JF07-80
Mark and Profile Leg 2A & 2B Node 4 13-Apr-20 17-Apr-20 79 17-Apr-20, Mark and Profile Leg 2A & 2B Node
F2-JK2-JF07-81
Join of Leg 2A & 2B Node 2 22-Apr-20 24-Apr-20 75 24-Apr-20, Join of Leg 2A & 2B Node
F2-JK2-JF07-82
Blasting and Painting for Leg 2A & 2B Node (Initial) 5 24-Apr-20 01-May-20 75 01-May-20, Blasting and Painting for Leg 2A & 2B Node (Initial)
F2-JK2-JF07-83
Assembly Leg 2A 3 20-Apr-20 22-Apr-20 67 22-Apr-20, Assembly Leg 2A
F2-JK2-JF07-84
Assembly Leg 2B 3 20-Apr-20 22-Apr-20 67 22-Apr-20, Assembly Leg 2B
F2-JK2-JF07-85
Install Stubs on to Leg 2A & 2B Nodes 2 22-Apr-20 24-Apr-20 67 24-Apr-20, Install Stubs on to Leg 2A & 2B Nodes
Braces 32 27-Mar-20 04-May-20 67 04-May-20, Braces
F2-JK2-JF07-138
Fit & Weld Row-2 K-Brace (Inc. Vertical Braces) 5 24-Apr-20 30-Apr-20 67 30-Apr-20, Fit & Weld Row-2 K-Brace (Inc. Vertical Braces)
F2-JK2-JF07-139
Assembly of Row-2 K-Brace 4 20-Apr-20 23-Apr-20 68 23-Apr-20, Assembly of Row-2 K-Brace
F2-JK2-JF07-86
Fit & Weld Top X-Brace Between Legs 2A & 2B 4 24-Apr-20 29-Apr-20 70 29-Apr-20, Fit & Weld Top X-Brace Between Legs 2A & 2B
F2-JK2-JF07-87
Fit & Weld Mid X-Brace Between Legs 2A & 2B 4 24-Apr-20 29-Apr-20 70 29-Apr-20, Fit & Weld Mid X-Brace Between Legs 2A & 2B
F2-JK2-JF07-88
Join of Row-2 Can Brace (Inc. Stub) 10 01-Apr-20 13-Apr-20 67 13-Apr-20, Join of Row-2 Can Brace (Inc. Stub)
F2-JK2-JF07-89
Assembly of Row-2 Top Brace 3 20-Apr-20 23-Apr-20 71 23-Apr-20, Assembly of Row-2 Top Brace
F2-JK2-JF07-90
Assembly of Row-2 Mid Brace 3 20-Apr-20 23-Apr-20 71 23-Apr-20, Assembly of Row-2 Mid Brace
F2-JK2-JF07-91
Profilling of Row-2 Braces and Stubs 4 27-Mar-20 01-Apr-20 67 01-Apr-20, Profilling of Row-2 Braces and Stubs
F2-JK2-JF07-92
Install Anodes on Row-2 Braces 4 30-Apr-20 04-May-20 67 04-May-20, Install Anodes on Row-2 Braces
J-Tubes 21 21-Apr-20 15-May-20 62 15-May-20, J-Tubes
F2-JK2-JF07-128
Join of Row-2 J-Tubes 5 25-Apr-20 01-May-20 65 01-May-20, Join of Row-2 J-Tubes
F2-JK2-JF07-129
Profilling of Row-2 J-Tubes 4 21-Apr-20 25-Apr-20 65 25-Apr-20, Profilling of Row-2 J-Tubes
F2-JK2-JF07-130
Bending of Row-2 J-Tubes 4 01-May-20 05-May-20 65 05-May-20, Bending of Row-2 J-Tubes
F2-JK2-JF07-131
Blast and Paint for Row-2 J-Tubes 3 08-May-20 12-May-20 62 12-May-20, Blast and Paint for Row-2 J-Tubes
F2-JK2-JF07-132
Assembly Row-2 J-Tubes 3 12-May-20 15-May-20 62 15-May-20, Assembly Row-2 J-Tubes
F2-JK2-JF07-133
Cut and Profile Row-2 J-Tubes Support 4 21-Apr-20 25-Apr-20 62 25-Apr-20, Cut and Profile Row-2 J-Tubes Support
F2-JK2-JF07-134
Assembly Row-2 J-Tubes Support 2 25-Apr-20 29-Apr-20 62 29-Apr-20, Assembly Row-2 J-Tubes Support
F2-JK2-JF07-135
Vulcanized Row-2 J-Tubes Support 2 29-Apr-20 01-May-20 62 01-May-20, Vulcanized Row-2 J-Tubes Support

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 34 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF07-136
Paint Row-2 J-Tubes Support 3 01-May-20 05-May-20 62 05-May-20, Paint Row-2 J-Tubes Support
F2-JK2-JF07-137
Install J-Tubes Support on to Row-2 J-Tubes 3 05-May-20 08-May-20 62 08-May-20, Install J-Tubes Support on to Row-2 J-Tubes
Common 23 13-Apr-20 09-May-20 67 09-May-20, Common
Structure 3 13-Apr-20 16-Apr-20 71 16-Apr-20, Structure
F2-JK2-JF07-69
Marking & Cutting of Leg and Brace Node 3 13-Apr-20 16-Apr-20 71 16-Apr-20, Marking & Cutting of Leg and Brace Node
F2-JK2-JF07-70
Marking & Cutting of Brace Stub 3 13-Apr-20 16-Apr-20 71 16-Apr-20, Marking & Cutting of Brace Stub
F2-JK2-JF07-71
Marking & Cutting of Leg and Brace Member 3 13-Apr-20 16-Apr-20 71 16-Apr-20, Marking & Cutting of Leg and Brace Member
Final Painting 23 13-Apr-20 09-May-20 67 09-May-20, Final Painting
F2-JK2-JF07-72
Row-2 Touch up and Final Painting 3 04-May-20 08-May-20 67 08-May-20, Row-2 Touch up and Final Painting
F2-JK2-JF07-73
Blast and Paint Leg and Brace (Initial Paint) 5 13-Apr-20 20-Apr-20 67 20-Apr-20, Blast and Paint Leg and Brace (Initial Paint)
F2-JK2-JF07-74
Build Painting Habitat Protection 1 08-May-20 09-May-20 67 09-May-20, Build Painting Habitat Protection
F2-JK2-JF07-75
Row-2 Ready for Assembly & Roll-up 0 09-May-20 67 09-May-20
Transition Piece 61 27-Mar-20 06-Jun-20 97 06-Jun-20, Transition Piece
F2-JK2-JF07-10Fabrication of Can Transition Piece Barrel 24 08-Apr-20 06-May-20 48 06-May-20, Fabrication of Can Transition Piece Barrel
F2-JK2-JF07-100Fit Grating Supports 4 09-Apr-20 14-Apr-20 114 14-Apr-20, Fit Grating Supports
F2-JK2-JF07-101Fab Main Deck Handrails 4 03-Apr-20 07-Apr-20 115 07-Apr-20, Fab Main Deck Handrails
F2-JK2-JF07-102Fab Padeye inc Top of Jacket 4 04-Apr-20 08-Apr-20 141 08-Apr-20, Fab Padeye inc Top of Jacket
F2-JK2-JF07-103Blast and Paint Transition Piece 7 29-May-20 06-Jun-20 97 06-Jun-20, Blast and Paint Transition Piece
F2-JK2-JF07-11 Fabrication of Strut Plate 18 27-Mar-20 17-Apr-20 16 17-Apr-20, Fabrication of Strut Plate
F2-JK2-JF07-12Fabrication of Internal Platform 21 27-Mar-20 21-Apr-20 126 21-Apr-20, Fabrication of Internal Platform
F2-JK2-JF07-13Fabrication of External Platform 25 27-Mar-20 25-Apr-20 126 25-Apr-20, Fabrication of External Platform
F2-JK2-JF07-14Assembly Strut Plate 21 17-Apr-20 12-May-20 112 12-May-20, Assembly Strut Plate
F2-JK2-JF07-15Fabrication of Ring Stiffener 21 05-May-20 29-May-20 97 29-May-20, Fabrication of Ring Stiffener
F2-JK2-JF07-16Fabrication of Crane Pedestal 21 17-Apr-20 12-May-20 90 12-May-20, Fabrication of Crane Pedestal
F2-JK2-JF07-93Galvanizing Handrails 5 07-Apr-20 13-Apr-20 115 13-Apr-20, Galvanizing Handrails
F2-JK2-JF07-94Erect Deck Plate Areas 5 04-Apr-20 09-Apr-20 113 09-Apr-20, Erect Deck Plate Areas
F2-JK2-JF07-95Transition Piece Fabrication Complete 0 29-May-20 97 29-May-20
F2-JK2-JF07-96Fabrication Assemble Walkways / Platforms 21 17-Apr-20 12-May-20 112 12-May-20, Fabrication Assemble Walkways / Platforms
F2-JK2-JF07-97Fit and Weld TP's Equipment Supports 5 04-Apr-20 11-Apr-20 113 11-Apr-20, Fit and Weld TP's Equipment Supports
F2-JK2-JF07-98Plate Profiling for Main Deck 5 27-Mar-20 03-Apr-20 68 03-Apr-20, Plate Profiling for Main Deck
F2-JK2-JF07-99Fab Main Deck Main Steel 5 30-Mar-20 04-Apr-20 68 04-Apr-20, Fab Main Deck Main Steel
Lifting Trunnion 7 04-Apr-20 13-Apr-20 68 13-Apr-20, Lifting Trunnion
F2-JK2-JF07-104Fabricate Lifting Trunion 7 04-Apr-20 13-Apr-20 68 13-Apr-20, Fabricate Lifting Trunion
Boat Landing 44 08-Apr-20 30-May-20 93 30-May-20, Boat Landing
F2-JK2-JF07-123Blast and Paint Boat Landing 5 23-May-20 30-May-20 93 30-May-20, Blast and Paint Boat Landing
F2-JK2-JF07-124Fabricate Boat Landing 21 08-Apr-20 02-May-20 45 02-May-20, Fabricate Boat Landing
F2-JK2-JF07-159Fabricate Boat Landing Access platform 24 25-Apr-20 23-May-20 93 23-May-20, Fabricate Boat Landing Access platform
F2-JK2-JF07-160Fabricate Boat Landing Ladders 15 04-May-20 21-May-20 95 21-May-20, Fabricate Boat Landing Ladders
Grouting Line 23 12-May-20 08-Jun-20 90 08-Jun-20, Grouting Line
F2-JK2-JF07-126Fabricate Grouting Line & Grouting Line Support 23 12-May-20 08-Jun-20 90 08-Jun-20, Fabricate Grouting Line & Grouting Line Support
Assembly 105 13-Apr-20 12-Aug-20 49 12-Aug-20, Assembly
Row Assembly 88 13-Apr-20 24-Jul-20 61 24-Jul-20, Row Assembly
F2-JK2-JF07-113Fabricate Upper Grillage & Truss Support 18 13-Apr-20 04-May-20 68 04-May-20, Fabricate Upper Grillage & Truss Support
F2-JK2-JF07-114Layout Concrete Blocks/ Grillages and Truss Support Steel 4 12-May-20 18-May-20 61 18-May-20, Layout Concrete Blocks/ Grillages and Truss Support Steel
Row-1 & 2 (Upper Jacket) Assembly 46 18-May-20 10-Jul-20 61 10-Jul-20, Row-1 & 2 (Upper Jacket) Assembly
F2-JK2-JF07-115
Installation of Grouting Line 1 04-Jun-20 05-Jun-20 81 05-Jun-20, Installation of Grouting Line
F2-JK2-JF07-117
Installation of J-Tube At Row-1B & 2A 5 04-Jun-20 10-Jun-20 85 10-Jun-20, Installation of J-Tube At Row-1B & 2A
F2-JK2-JF07-118
Row-2 - Touch Up, 2nd Coat & Top Coat 3 07-Jul-20 09-Jul-20 61 09-Jul-20, Row-2 - Touch Up, 2nd Coat & Top Coat
F2-JK2-JF07-119
Installation of Row-1B & 2B X-Brace 7 27-May-20 04-Jun-20 61 04-Jun-20, Installation of Row-1B & 2B X-Brace
F2-JK2-JF07-120
Installation of Leg 1A & 1B Onto Support 1 18-May-20 19-May-20 61 19-May-20, Installation of Leg 1A & 1B Onto Support
F2-JK2-JF07-121
Installation of Row-1A & 1B X-Brace 7 19-May-20 27-May-20 61 27-May-20, Installation of Row-1A & 1B X-Brace
F2-JK2-JF07-122
Installation of Row-2A & 2B X-Brace in Final Position 7 29-Jun-20 07-Jul-20 61 07-Jul-20, Installation of Row-2A & 2B X-Brace in Final Position
F2-JK2-JF07-142
Installation of Leg 2A & 2B Onto Support 1 18-May-20 19-May-20 68 19-May-20, Installation of Leg 2A & 2B Onto Support
F2-JK2-JF07-143
Installation of Row-1A & 2A X-Brace 7 27-May-20 04-Jun-20 61 04-Jun-20, Installation of Row-1A & 2A X-Brace
F2-JK2-JF07-144
Installation of Row-1A & 1B X-Brace in Final Position 7 20-Jun-20 29-Jun-20 61 29-Jun-20, Installation of Row-1A & 1B X-Brace in Final Position

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 35 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF07-145
Roll Up X-Brace Row A&B to Final Position 7 04-Jun-20 12-Jun-20 61 12-Jun-20, Roll Up X-Brace Row A&B to Final Position
F2-JK2-JF07-146
Installing Tie-back for Fastener 7 12-Jun-20 20-Jun-20 61 20-Jun-20, Installing Tie-back for Fastener
F2-JK2-JF07-147
Installation of Boat Landing 3 07-Jul-20 10-Jul-20 61 10-Jul-20, Installation of Boat Landing
Row-1 & 2 (Lower Jacket) Assembly 44 14-May-20 03-Jul-20 66 03-Jul-20, Row-1 & 2 (Lower Jacket) Assembly
F2-JK2-JF07-116
Installation of Pile Stopper 4 13-Jun-20 17-Jun-20 66 17-Jun-20, Installation of Pile Stopper
F2-JK2-JF07-148
Installation of Grouting Line 1 01-Jun-20 02-Jun-20 87 02-Jun-20, Installation of Grouting Line
F2-JK2-JF07-149
Installation of J-Tube At Row-1B & 2A 5 01-Jun-20 06-Jun-20 76 06-Jun-20, Installation of J-Tube At Row-1B & 2A
F2-JK2-JF07-150
Installation of Row-1B & 2B X-Brace 7 23-May-20 01-Jun-20 66 01-Jun-20, Installation of Row-1B & 2B X-Brace
F2-JK2-JF07-151
Installation of Leg 1A & 1B Onto Support 1 14-May-20 15-May-20 66 15-May-20, Installation of Leg 1A & 1B Onto Support
F2-JK2-JF07-152
Installation of Row-1A & 1B X-Brace 7 15-May-20 23-May-20 66 23-May-20, Installation of Row-1A & 1B X-Brace
F2-JK2-JF07-153
Installation of Row-2A & 2B X-Brace in Final Position 7 25-Jun-20 03-Jul-20 66 03-Jul-20, Installation of Row-2A & 2B X-Brace in Final Position
F2-JK2-JF07-154
Installation of Leg 2A & 2B Onto Support 1 14-May-20 15-May-20 73 15-May-20, Installation of Leg 2A & 2B Onto Support
F2-JK2-JF07-155
Installation of Row-1A & 2A X-Brace 7 23-May-20 01-Jun-20 66 01-Jun-20, Installation of Row-1A & 2A X-Brace
F2-JK2-JF07-156
Installation of Row-1A & 1B X-Brace in Final Position 7 17-Jun-20 25-Jun-20 66 25-Jun-20, Installation of Row-1A & 1B X-Brace in Final Position
F2-JK2-JF07-157
Roll Up X-Brace Row A&B to Final Position 7 01-Jun-20 09-Jun-20 66 09-Jun-20, Roll Up X-Brace Row A&B to Final Position
F2-JK2-JF07-158
Installing Tie-back for Fastener 4 09-Jun-20 13-Jun-20 66 13-Jun-20, Installing Tie-back for Fastener
Grouting Line 40 08-Jun-20 24-Jul-20 61 24-Jul-20, Grouting Line
F2-JK2-JF07-125
Installation Of Grouting Line 5 18-Jul-20 24-Jul-20 61 24-Jul-20, Installation Of Grouting Line
F2-JK2-JF07-127
Installation Grouting Line Support 7 08-Jun-20 16-Jun-20 90 16-Jun-20, Installation Grouting Line Support
Row Roll Up 7 10-Jul-20 18-Jul-20 61 18-Jul-20, Row Roll Up
F2-JK2-JF07-105Roll Up Of Lower Jacket To Final Position 2 10-Jul-20 13-Jul-20 61 13-Jul-20, Roll Up Of Lower Jacket To Final Position
F2-JK2-JF07-106Roll Up Of Upper Jacket To Final Position 5 13-Jul-20 18-Jul-20 61 18-Jul-20, Roll Up Of Upper Jacket To Final Position
Transition Piece (TP) 76 06-May-20 03-Aug-20 48 03-Aug-20, Transition Piece (TP)
F2-JK2-JF07-1 Install Door Platform 10 29-May-20 10-Jun-20 77 10-Jun-20, Install Door Platform
F2-JK2-JF07-17Installation & Assembly of Ring Stiffener 21 01-Jun-20 25-Jun-20 48 25-Jun-20, Installation & Assembly of Ring Stiffener
F2-JK2-JF07-18Installation of Transition Piece Flange 15 09-Jun-20 26-Jun-20 48 26-Jun-20, Installation of Transition Piece Flange
F2-JK2-JF07-19Install Crane Pedestal 12 12-May-20 26-May-20 90 26-May-20, Install Crane Pedestal
F2-JK2-JF07-2 Blasting & Painting 10 14-Jul-20 25-Jul-20 48 25-Jul-20, Blasting & Painting
F2-JK2-JF07-3 Assemble Can Transition Piece Barrel to Main Deck 15 06-May-20 23-May-20 48 23-May-20, Assemble Can Transition Piece Barrel to Main Deck
F2-JK2-JF07-4 Install Platform & Internal Structure into Upper Can 7 25-Jul-20 03-Aug-20 48 03-Aug-20, Install Platform & Internal Structure into Upper Can
F2-JK2-JF07-5 Door opening & Installation of Door frame 5 23-May-20 29-May-20 87 29-May-20, Door opening & Installation of Door frame
F2-JK2-JF07-6 Installation & Assembly of Strut 15 23-May-20 10-Jun-20 48 10-Jun-20, Installation & Assembly of Strut
F2-JK2-JF07-7 Install Free-Issued Items 15 26-Jun-20 14-Jul-20 48 14-Jul-20, Install Free-Issued Items
F2-JK2-JF07-8 Install Architectural items, Electrical & Instrument Equipments 15 23-May-20 10-Jun-20 77 10-Jun-20, Install Architectural items, Electrical & Instrument Equipments
F2-JK2-JF07-9 Install External Platform & Handrail 12 27-May-20 10-Jun-20 77 10-Jun-20, Install External Platform & Handrail
Final Assembly 8 03-Aug-20 12-Aug-20 49 12-Aug-20, Final Assembly
F2-JK2-JF07-107Installation of Transition Piece 3 03-Aug-20 06-Aug-20 48 06-Aug-20, Installation of Transition Piece
F2-JK2-JF07-108Installation of Mudmad Plate 5 05-Aug-20 11-Aug-20 48 11-Aug-20, Installation of Mudmad Plate
F2-JK2-JF07-109Installation of Lifting Trunnion 4 06-Aug-20 11-Aug-20 50 11-Aug-20, Installation of Lifting Trunnion
F2-JK2-JF07-110Installation of Skirt Pile Sleeve 2 05-Aug-20 07-Aug-20 48 07-Aug-20, Installation of Skirt Pile Sleeve
F2-JK2-JF07-111Final Touch Up Coating 3 08-Aug-20 12-Aug-20 48 12-Aug-20, Final Touch Up Coating
F2-JK2-JF07-112Installation of Lifting Slings 1 07-Aug-20 08-Aug-20 48 08-Aug-20, Installation of Lifting Slings
F2-JK2-JF07-161J acket Fabrication Completed 0 12-Aug-20 48 12-Aug-20
Testing & Commissioning 18 24-Jul-20 14-Aug-20 48 14-Aug-20, Testing & Commissioning
Grouting & Gripper Test 3 24-Jul-20 28-Jul-20 61 28-Jul-20, Grouting & Gripper Test
F2-JK2-JF07-20Gripper Test 2 25-Jul-20 28-Jul-20 61 28-Jul-20, Gripper Test
F2-JK2-JF07-21Grouting Test 1 24-Jul-20 25-Jul-20 61 25-Jul-20, Grouting Test
Mechanical Completion 2 12-Aug-20 14-Aug-20 48 14-Aug-20, Mechanical Completion
F2-JK2-JF07-22Main Structure, Boat Landing, J-Tube, Transition Piece 2 12-Aug-20 14-Aug-20 48 14-Aug-20, Main Structure, Boat Landing, J-Tube, Transition Piece
Jacket & Piles Ready For Loadout 0 14-Aug-20 14-Aug-20 48 14-Aug-20, Jacket & Piles Ready For Loadout
F2-JK2-JF07-23Jacket Ready For Load Out 0 14-Aug-20 48 14-Aug-20
Jacket Foundation 8a 130 24-Mar-20 22-Aug-20 0 22-Aug-20, Jacket Foundation 8a
Fabrication 72 24-Mar-20 16-Jun-20 48 16-Jun-20, Fabrication
Pre-Fabrication 38 24-Mar-20 07-May-20 49 07-May-20, Pre-Fabrication
F2-JK2-JF08-140Rolling of Can Transition Piece Flange 10 25-Apr-20 07-May-20 49 07-May-20, Rolling of Can Transition Piece Flange

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 36 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF08-141Rolling of Can Transition Piece Barrel 10 04-Apr-20 16-Apr-20 0 16-Apr-20, Rolling of Can Transition Piece Barrel
F2-JK2-JF08-24Rolling of Can Row 2 Brace 10 24-Mar-20 04-Apr-20 0 04-Apr-20, Rolling of Can Row 2 Brace
F2-JK2-JF08-25Rolling of Can Leg 1A & 1B 10 24-Mar-20 04-Apr-20 13 04-Apr-20, Rolling of Can Leg 1A & 1B
F2-JK2-JF08-26Rolling of Can Leg 2A & 2B 10 01-Apr-20 13-Apr-20 13 13-Apr-20, Rolling of Can Leg 2A & 2B
F2-JK2-JF08-27Rolling of Node Can Row 1 10 01-Apr-20 13-Apr-20 13 13-Apr-20, Rolling of Node Can Row 1
F2-JK2-JF08-28Rolling of Node Can Row 2 10 09-Apr-20 21-Apr-20 13 21-Apr-20, Rolling of Node Can Row 2
F2-JK2-JF08-29Rolling of Can Row 1 Brace 10 09-Apr-20 21-Apr-20 13 21-Apr-20, Rolling of Can Row 1 Brace
F2-JK2-JF08-30Rolling of J-Tubes & J-Tubes Support 10 17-Apr-20 29-Apr-20 14 29-Apr-20, Rolling of J-Tubes & J-Tubes Support
F2-JK2-JF08-31Rolling of Can Plan Level Tubular 10 17-Apr-20 29-Apr-20 49 29-Apr-20, Rolling of Can Plan Level Tubular
F2-JK2-JF08-32Rolling of Can Top Bay X-Brace 10 25-Apr-20 07-May-20 49 07-May-20, Rolling of Can Top Bay X-Brace
Row 1 Fabrication 42 04-Apr-20 23-May-20 54 23-May-20, Row 1 Fabrication
Legs 40 04-Apr-20 22-May-20 16 22-May-20, Legs
F2-JK2-JF08-40
Install Stubs on to Leg 1A & 1B Nodes 2 12-May-20 14-May-20 13 14-May-20, Install Stubs on to Leg 1A & 1B Nodes
F2-JK2-JF08-41
Install Anodes on Row-1 Legs 4 13-May-20 18-May-20 15 18-May-20, Install Anodes on Row-1 Legs
F2-JK2-JF08-42
Join of Can Legs 1A 9 09-Apr-20 20-Apr-20 28 20-Apr-20, Join of Can Legs 1A
F2-JK2-JF08-43
Join of Can Legs 1B 9 09-Apr-20 20-Apr-20 28 20-Apr-20, Join of Can Legs 1B
F2-JK2-JF08-44
Mark and Profile Leg 1A & 1B Node 4 13-Apr-20 17-Apr-20 38 17-Apr-20, Mark and Profile Leg 1A & 1B Node
F2-JK2-JF08-45
Profilling of Legs 1A & 1B (Inc. Cones) 4 04-Apr-20 09-Apr-20 28 09-Apr-20, Profilling of Legs 1A & 1B (Inc. Cones)
F2-JK2-JF08-46
Join of Leg 1A & 1B Node 2 13-May-20 15-May-20 16 15-May-20, Join of Leg 1A & 1B Node
F2-JK2-JF08-47
Blasting and Painting for Leg 1A & 1B Node 5 15-May-20 22-May-20 16 22-May-20, Blasting and Painting for Leg 1A & 1B Node
F2-JK2-JF08-48
Assembly Leg 1A 3 11-May-20 13-May-20 13 13-May-20, Assembly Leg 1A
F2-JK2-JF08-49
Assembly Leg 1B 3 11-May-20 13-May-20 13 13-May-20, Assembly Leg 1B
Braces 28 21-Apr-20 23-May-20 13 23-May-20, Braces
F2-JK2-JF08-50
Fit & Weld Top X Brace Between Legs 1A & 1B 5 14-May-20 20-May-20 13 20-May-20, Fit & Weld Top X Brace Between Legs 1A & 1B
F2-JK2-JF08-51
Join of Row-1 Can Brace (Inc. Stub) 13 25-Apr-20 11-May-20 13 11-May-20, Join of Row-1 Can Brace (Inc. Stub)
F2-JK2-JF08-52
Join of Can Brace for Between Row 1 & 2 (Inc. Stub) 13 25-Apr-20 11-May-20 13 11-May-20, Join of Can Brace for Between Row 1 & 2 (Inc. Stub)
F2-JK2-JF08-53
Assembly of Row-1 Top Brace 4 11-May-20 14-May-20 13 14-May-20, Assembly of Row-1 Top Brace
F2-JK2-JF08-54
Fit & Weld Row-2 K-Brace (Inc. Vertical Braces) 5 14-May-20 20-May-20 13 20-May-20, Fit & Weld Row-2 K-Brace (Inc. Vertical Braces)
F2-JK2-JF08-55
Assembly of Row-1 K-Brace 4 11-May-20 14-May-20 13 14-May-20, Assembly of Row-1 K-Brace
F2-JK2-JF08-56
Fit & Weld X-Brace Between Row 1 & 2 5 14-May-20 20-May-20 13 20-May-20, Fit & Weld X-Brace Between Row 1 & 2
F2-JK2-JF08-57
Assembly of Brace Between Row 1 & 2 4 11-May-20 14-May-20 13 14-May-20, Assembly of Brace Between Row 1 & 2
F2-JK2-JF08-58
Profilling of Row-1 Braces and Stubs 4 21-Apr-20 25-Apr-20 13 25-Apr-20, Profilling of Row-1 Braces and Stubs
F2-JK2-JF08-59
Install Anodes on Row-1 Braces 4 20-May-20 23-May-20 13 23-May-20, Install Anodes on Row-1 Braces
J-Tubes 19 29-Apr-20 21-May-20 56 21-May-20, J-Tubes
F2-JK2-JF08-60
Join of Row-1 J-Tubes 5 04-May-20 09-May-20 56 09-May-20, Join of Row-1 J-Tubes
F2-JK2-JF08-61
Profilling of Row-1 J-Tubes 4 29-Apr-20 04-May-20 56 04-May-20, Profilling of Row-1 J-Tubes
F2-JK2-JF08-62
Bending of Row-1 J-Tubes 4 09-May-20 13-May-20 56 13-May-20, Bending of Row-1 J-Tubes
F2-JK2-JF08-63
Blast and Paint for Row-1 J-Tubes 3 13-May-20 18-May-20 56 18-May-20, Blast and Paint for Row-1 J-Tubes
F2-JK2-JF08-64
Assembly Row-1 J-Tubes 3 18-May-20 21-May-20 56 21-May-20, Assembly Row-1 J-Tubes
F2-JK2-JF08-65
Cut and Profile Row-1 J-Tubes Support 4 29-Apr-20 04-May-20 56 04-May-20, Cut and Profile Row-1 J-Tubes Support
F2-JK2-JF08-66
Assembly Row-1 J-Tubes Support 2 04-May-20 07-May-20 56 07-May-20, Assembly Row-1 J-Tubes Support
F2-JK2-JF08-67
Paint Row-1 J-Tubes Support 3 07-May-20 11-May-20 56 11-May-20, Paint Row-1 J-Tubes Support
F2-JK2-JF08-68
Install J-Tubes Support on to Row-1 J-Tubes 3 11-May-20 13-May-20 56 13-May-20, Install J-Tubes Support on to Row-1 J-Tubes
Common 23 28-Apr-20 23-May-20 14 23-May-20, Common
Structure 3 28-Apr-20 01-May-20 21 01-May-20, Structure
F2-JK2-JF08-33
Marking & Cutting of Leg and Brace Node 3 28-Apr-20 01-May-20 21 01-May-20, Marking & Cutting of Leg and Brace Node
F2-JK2-JF08-34
Marking & Cutting of Brace Stub 3 28-Apr-20 01-May-20 21 01-May-20, Marking & Cutting of Brace Stub
F2-JK2-JF08-35
Marking & Cutting of Leg and Brace Member 3 28-Apr-20 01-May-20 21 01-May-20, Marking & Cutting of Leg and Brace Member
Final Painting 23 28-Apr-20 23-May-20 14 23-May-20, Final Painting
F2-JK2-JF08-36
Blast and Paint Leg and Brace (Initial Paint) 11 28-Apr-20 11-May-20 13 11-May-20, Blast and Paint Leg and Brace (Initial Paint)
F2-JK2-JF08-37
Build Painting Habitat Protection 1 20-May-20 22-May-20 16 22-May-20, Build Painting Habitat Protection
F2-JK2-JF08-38
Row-1 Ready for Assembly & Roll-up 0 22-May-20 16 22-May-20
F2-JK2-JF08-39
Row-1 Touch up and Final Painting 3 20-May-20 23-May-20 13 23-May-20, Row-1 Touch up and Final Painting
Row 2 Fabrication 42 04-Apr-20 23-May-20 14 23-May-20, Row 2 Fabrication
Legs 23 13-Apr-20 09-May-20 27 09-May-20, Legs

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 37 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF08-76
Install Anodes on Row-2 Legs 4 30-Apr-20 05-May-20 26 05-May-20, Install Anodes on Row-2 Legs
F2-JK2-JF08-77
Join of Can Legs 2A 9 17-Apr-20 28-Apr-20 21 28-Apr-20, Join of Can Legs 2A
F2-JK2-JF08-78
Join of Can Legs 2B 9 17-Apr-20 28-Apr-20 21 28-Apr-20, Join of Can Legs 2B
F2-JK2-JF08-79
Profilling of Legs 2A & 2B (Inc. Cones) 4 13-Apr-20 17-Apr-20 21 17-Apr-20, Profilling of Legs 2A & 2B (Inc. Cones)
F2-JK2-JF08-80
Mark and Profile Leg 2A & 2B Node 4 21-Apr-20 25-Apr-20 31 25-Apr-20, Mark and Profile Leg 2A & 2B Node
F2-JK2-JF08-81
Join of Leg 2A & 2B Node 2 30-Apr-20 02-May-20 27 02-May-20, Join of Leg 2A & 2B Node
F2-JK2-JF08-82
Blasting and Painting for Leg 2A & 2B Node (Initial) 5 02-May-20 09-May-20 27 09-May-20, Blasting and Painting for Leg 2A & 2B Node (Initial)
F2-JK2-JF08-83
Assembly Leg 2A 3 28-Apr-20 30-Apr-20 19 30-Apr-20, Assembly Leg 2A
F2-JK2-JF08-84
Assembly Leg 2B 3 28-Apr-20 30-Apr-20 19 30-Apr-20, Assembly Leg 2B
F2-JK2-JF08-85
Install Stubs on to Leg 2A & 2B Nodes 2 30-Apr-20 02-May-20 19 02-May-20, Install Stubs on to Leg 2A & 2B Nodes
Braces 32 04-Apr-20 12-May-20 19 12-May-20, Braces
F2-JK2-JF08-138
Fit & Weld Row-2 K-Brace (Inc. Vertical Braces) 5 02-May-20 08-May-20 19 08-May-20, Fit & Weld Row-2 K-Brace (Inc. Vertical Braces)
F2-JK2-JF08-139
Assembly of Row-2 K-Brace 4 28-Apr-20 01-May-20 20 01-May-20, Assembly of Row-2 K-Brace
F2-JK2-JF08-86
Fit & Weld Top X-Brace Between Legs 2A & 2B 4 02-May-20 07-May-20 22 07-May-20, Fit & Weld Top X-Brace Between Legs 2A & 2B
F2-JK2-JF08-87
Fit & Weld Mid X-Brace Between Legs 2A & 2B 4 02-May-20 07-May-20 22 07-May-20, Fit & Weld Mid X-Brace Between Legs 2A & 2B
F2-JK2-JF08-88
Join of Row-2 Can Brace (Inc. Stub) 10 09-Apr-20 21-Apr-20 19 21-Apr-20, Join of Row-2 Can Brace (Inc. Stub)
F2-JK2-JF08-89
Assembly of Row-2 Top Brace 3 28-Apr-20 01-May-20 23 01-May-20, Assembly of Row-2 Top Brace
F2-JK2-JF08-90
Assembly of Row-2 Mid Brace 3 28-Apr-20 01-May-20 23 01-May-20, Assembly of Row-2 Mid Brace
F2-JK2-JF08-91
Profilling of Row-2 Braces and Stubs 4 04-Apr-20 09-Apr-20 19 09-Apr-20, Profilling of Row-2 Braces and Stubs
F2-JK2-JF08-92
Install Anodes on Row-2 Braces 4 08-May-20 12-May-20 19 12-May-20, Install Anodes on Row-2 Braces
J-Tubes 21 29-Apr-20 23-May-20 14 23-May-20, J-Tubes
F2-JK2-JF08-128
Join of Row-2 J-Tubes 5 04-May-20 09-May-20 17 09-May-20, Join of Row-2 J-Tubes
F2-JK2-JF08-129
Profilling of Row-2 J-Tubes 4 29-Apr-20 04-May-20 17 04-May-20, Profilling of Row-2 J-Tubes
F2-JK2-JF08-130
Bending of Row-2 J-Tubes 4 09-May-20 13-May-20 17 13-May-20, Bending of Row-2 J-Tubes
F2-JK2-JF08-131
Blast and Paint for Row-2 J-Tubes 3 16-May-20 20-May-20 14 20-May-20, Blast and Paint for Row-2 J-Tubes
F2-JK2-JF08-132
Assembly Row-2 J-Tubes 3 20-May-20 23-May-20 14 23-May-20, Assembly Row-2 J-Tubes
F2-JK2-JF08-133
Cut and Profile Row-2 J-Tubes Support 4 29-Apr-20 04-May-20 14 04-May-20, Cut and Profile Row-2 J-Tubes Support
F2-JK2-JF08-134
Assembly Row-2 J-Tubes Support 2 04-May-20 07-May-20 14 07-May-20, Assembly Row-2 J-Tubes Support
F2-JK2-JF08-135
Vulcanized Row-2 J-Tubes Support 2 07-May-20 09-May-20 14 09-May-20, Vulcanized Row-2 J-Tubes Support
F2-JK2-JF08-136
Paint Row-2 J-Tubes Support 3 09-May-20 13-May-20 14 13-May-20, Paint Row-2 J-Tubes Support
F2-JK2-JF08-137
Install J-Tubes Support on to Row-2 J-Tubes 3 13-May-20 16-May-20 14 16-May-20, Install J-Tubes Support on to Row-2 J-Tubes
Common 23 21-Apr-20 18-May-20 19 18-May-20, Common
Structure 3 21-Apr-20 24-Apr-20 23 24-Apr-20, Structure
F2-JK2-JF08-69
Marking & Cutting of Leg and Brace Node 3 21-Apr-20 24-Apr-20 23 24-Apr-20, Marking & Cutting of Leg and Brace Node
F2-JK2-JF08-70
Marking & Cutting of Brace Stub 3 21-Apr-20 24-Apr-20 23 24-Apr-20, Marking & Cutting of Brace Stub
F2-JK2-JF08-71
Marking & Cutting of Leg and Brace Member 3 21-Apr-20 24-Apr-20 23 24-Apr-20, Marking & Cutting of Leg and Brace Member
Final Painting 23 21-Apr-20 18-May-20 19 18-May-20, Final Painting
F2-JK2-JF08-72
Row-2 Touch up and Final Painting 3 12-May-20 16-May-20 19 16-May-20, Row-2 Touch up and Final Painting
F2-JK2-JF08-73
Blast and Paint Leg and Brace (Initial Paint) 5 21-Apr-20 28-Apr-20 19 28-Apr-20, Blast and Paint Leg and Brace (Initial Paint)
F2-JK2-JF08-74
Build Painting Habitat Protection 1 16-May-20 18-May-20 19 18-May-20, Build Painting Habitat Protection
F2-JK2-JF08-75
Row-2 Ready for Assembly & Roll-up 0 18-May-20 19 18-May-20
Transition Piece 61 04-Apr-20 15-Jun-20 49 15-Jun-20, Transition Piece
F2-JK2-JF08-10Fabrication of Can Transition Piece Barrel 24 16-Apr-20 14-May-20 0 14-May-20, Fabrication of Can Transition Piece Barrel
F2-JK2-JF08-100Fit Grating Supports 4 17-Apr-20 22-Apr-20 66 22-Apr-20, Fit Grating Supports
F2-JK2-JF08-101Fab Main Deck Handrails 4 11-Apr-20 15-Apr-20 67 15-Apr-20, Fab Main Deck Handrails
F2-JK2-JF08-102Fab Padeye inc Top of Jacket 4 13-Apr-20 16-Apr-20 93 16-Apr-20, Fab Padeye inc Top of Jacket
F2-JK2-JF08-103Blast and Paint Transition Piece 7 06-Jun-20 15-Jun-20 49 15-Jun-20, Blast and Paint Transition Piece
F2-JK2-JF08-11 Fabrication of Strut Plate 18 04-Apr-20 25-Apr-20 16 25-Apr-20, Fabrication of Strut Plate
F2-JK2-JF08-12Fabrication of Internal Platform 21 04-Apr-20 29-Apr-20 78 29-Apr-20, Fabrication of Internal Platform
F2-JK2-JF08-13Fabrication of External Platform 25 04-Apr-20 04-May-20 78 04-May-20, Fabrication of External Platform
F2-JK2-JF08-14Assembly Strut Plate 21 25-Apr-20 20-May-20 64 20-May-20, Assembly Strut Plate
F2-JK2-JF08-15Fabrication of Ring Stiffener 21 13-May-20 06-Jun-20 49 06-Jun-20, Fabrication of Ring Stiffener
F2-JK2-JF08-16Fabrication of Crane Pedestal 21 25-Apr-20 20-May-20 42 20-May-20, Fabrication of Crane Pedestal
F2-JK2-JF08-93Galvanizing Handrails 5 15-Apr-20 21-Apr-20 67 21-Apr-20, Galvanizing Handrails
F2-JK2-JF08-94Erect Deck Plate Areas 5 13-Apr-20 17-Apr-20 65 17-Apr-20, Erect Deck Plate Areas

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 38 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF08-95Transition Piece Fabrication Complete 0 06-Jun-20 49 06-Jun-20
F2-JK2-JF08-96Fabrication Assemble Walkways / Platforms 21 25-Apr-20 20-May-20 64 20-May-20, Fabrication Assemble Walkways / Platforms
F2-JK2-JF08-97Fit and Weld TP's Equipment Supports 5 13-Apr-20 20-Apr-20 65 20-Apr-20, Fit and Weld TP's Equipment Supports
F2-JK2-JF08-98Plate Profiling for Main Deck 5 04-Apr-20 11-Apr-20 20 11-Apr-20, Plate Profiling for Main Deck
F2-JK2-JF08-99Fab Main Deck Main Steel 5 07-Apr-20 13-Apr-20 20 13-Apr-20, Fab Main Deck Main Steel
Lifting Trunnion 7 13-Apr-20 21-Apr-20 20 21-Apr-20, Lifting Trunnion
F2-JK2-JF08-104Fabricate Lifting Trunion 7 13-Apr-20 21-Apr-20 20 21-Apr-20, Fabricate Lifting Trunion
Boat Landing 44 16-Apr-20 08-Jun-20 45 08-Jun-20, Boat Landing
F2-JK2-JF08-123Blast and Paint Boat Landing 5 01-Jun-20 08-Jun-20 45 08-Jun-20, Blast and Paint Boat Landing
F2-JK2-JF08-124Fabricate Boat Landing 21 16-Apr-20 11-May-20 45 11-May-20, Fabricate Boat Landing
F2-JK2-JF08-159Fabricate Boat Landing Access platform 24 04-May-20 01-Jun-20 45 01-Jun-20, Fabricate Boat Landing Access platform
F2-JK2-JF08-160Fabricate Boat Landing Ladders 15 12-May-20 29-May-20 47 29-May-20, Fabricate Boat Landing Ladders
Grouting Line 23 20-May-20 16-Jun-20 42 16-Jun-20, Grouting Line
F2-JK2-JF08-126Fabricate Grouting Line & Grouting Line Support 23 20-May-20 16-Jun-20 42 16-Jun-20, Fabricate Grouting Line & Grouting Line Support
Assembly 105 21-Apr-20 20-Aug-20 1 20-Aug-20, Assembly
Row Assembly 88 21-Apr-20 01-Aug-20 13 01-Aug-20, Row Assembly
F2-JK2-JF08-113Fabricate Upper Grillage & Truss Support 18 21-Apr-20 12-May-20 20 12-May-20, Fabricate Upper Grillage & Truss Support
F2-JK2-JF08-114Layout Concrete Blocks/ Grillages and Truss Support Steel 4 20-May-20 26-May-20 13 26-May-20, Layout Concrete Blocks/ Grillages and Truss Support Steel
Row-1 & 2 (Upper Jacket) Assembly 46 26-May-20 18-Jul-20 13 18-Jul-20, Row-1 & 2 (Upper Jacket) Assembly
F2-JK2-JF08-115
Installation of Grouting Line 1 12-Jun-20 13-Jun-20 33 13-Jun-20, Installation of Grouting Line
F2-JK2-JF08-117
Installation of J-Tube At Row-1B & 2A 5 12-Jun-20 18-Jun-20 37 18-Jun-20, Installation of J-Tube At Row-1B & 2A
F2-JK2-JF08-118
Row-2 - Touch Up, 2nd Coat & Top Coat 3 15-Jul-20 17-Jul-20 13 17-Jul-20, Row-2 - Touch Up, 2nd Coat & Top Coat
F2-JK2-JF08-119
Installation of Row-1B & 2B X-Brace 7 04-Jun-20 12-Jun-20 13 12-Jun-20, Installation of Row-1B & 2B X-Brace
F2-JK2-JF08-120
Installation of Leg 1A & 1B Onto Support 1 26-May-20 27-May-20 13 27-May-20, Installation of Leg 1A & 1B Onto Support
F2-JK2-JF08-121
Installation of Row-1A & 1B X-Brace 7 27-May-20 04-Jun-20 13 04-Jun-20, Installation of Row-1A & 1B X-Brace
F2-JK2-JF08-122
Installation of Row-2A & 2B X-Brace in Final Position 7 07-Jul-20 15-Jul-20 13 15-Jul-20, Installation of Row-2A & 2B X-Brace in Final Position
F2-JK2-JF08-142
Installation of Leg 2A & 2B Onto Support 1 26-May-20 27-May-20 20 27-May-20, Installation of Leg 2A & 2B Onto Support
F2-JK2-JF08-143
Installation of Row-1A & 2A X-Brace 7 04-Jun-20 12-Jun-20 13 12-Jun-20, Installation of Row-1A & 2A X-Brace
F2-JK2-JF08-144
Installation of Row-1A & 1B X-Brace in Final Position 7 29-Jun-20 07-Jul-20 13 07-Jul-20, Installation of Row-1A & 1B X-Brace in Final Position
F2-JK2-JF08-145
Roll Up X-Brace Row A&B to Final Position 7 12-Jun-20 20-Jun-20 13 20-Jun-20, Roll Up X-Brace Row A&B to Final Position
F2-JK2-JF08-146
Installing Tie-back for Fastener 7 20-Jun-20 29-Jun-20 13 29-Jun-20, Installing Tie-back for Fastener
F2-JK2-JF08-147
Installation of Boat Landing 3 15-Jul-20 18-Jul-20 13 18-Jul-20, Installation of Boat Landing
Row-1 & 2 (Lower Jacket) Assembly 44 22-May-20 11-Jul-20 18 11-Jul-20, Row-1 & 2 (Lower Jacket) Assembly
F2-JK2-JF08-116
Installation of Pile Stopper 4 22-Jun-20 25-Jun-20 18 25-Jun-20, Installation of Pile Stopper
F2-JK2-JF08-148
Installation of Grouting Line 1 09-Jun-20 10-Jun-20 39 10-Jun-20, Installation of Grouting Line
F2-JK2-JF08-149
Installation of J-Tube At Row-1B & 2A 5 09-Jun-20 15-Jun-20 28 15-Jun-20, Installation of J-Tube At Row-1B & 2A
F2-JK2-JF08-150
Installation of Row-1B & 2B X-Brace 7 01-Jun-20 09-Jun-20 18 09-Jun-20, Installation of Row-1B & 2B X-Brace
F2-JK2-JF08-151
Installation of Leg 1A & 1B Onto Support 1 22-May-20 23-May-20 18 23-May-20, Installation of Leg 1A & 1B Onto Support
F2-JK2-JF08-152
Installation of Row-1A & 1B X-Brace 7 23-May-20 01-Jun-20 18 01-Jun-20, Installation of Row-1A & 1B X-Brace
F2-JK2-JF08-153
Installation of Row-2A & 2B X-Brace in Final Position 7 03-Jul-20 11-Jul-20 18 11-Jul-20, Installation of Row-2A & 2B X-Br ace in F inal Posit io n
F2-JK2-JF08-154
Installation of Leg 2A & 2B Onto Support 1 22-May-20 23-May-20 25 23-May-20, Installation of Leg 2A & 2B Onto Support
F2-JK2-JF08-155
Installation of Row-1A & 2A X-Brace 7 01-Jun-20 09-Jun-20 18 09-Jun-20, Installation of Row-1A & 2A X-Brace
F2-JK2-JF08-156
Installation of Row-1A & 1B X-Brace in Final Position 7 25-Jun-20 03-Jul-20 18 03-Jul-20, Installation of Row-1A & 1B X-Brace in Final Position
F2-JK2-JF08-157
Roll Up X-Brace Row A&B to Final Position 7 09-Jun-20 17-Jun-20 18 17-Jun-20, Roll Up X-Brace Row A&B to Final Position
F2-JK2-JF08-158
Installing Tie-back for Fastener 4 17-Jun-20 22-Jun-20 18 22-Jun-20, Installing Tie-back for Fastener
Grouting Line 40 16-Jun-20 01-Aug-20 13 01-Aug-20, Grouting Line
F2-JK2-JF08-125
Installation Of Grouting Line 5 27-Jul-20 01-Aug-20 13 01-Aug-20, Installation Of Grouting Line
F2-JK2-JF08-127
Installation Grouting Line Support 7 16-Jun-20 24-Jun-20 42 24-Jun-20, Installation Grouting Line Support
Row Roll Up 7 18-Jul-20 27-Jul-20 13 27-Jul-20, Row Roll Up
F2-JK2-JF08-105Roll Up Of Lower Jacket To Final Position 2 18-Jul-20 21-Jul-20 13 21-Jul-20, Roll Up Of Lower Jacket To Final Position
F2-JK2-JF08-106Roll Up Of Upper Jacket To Final Position 5 21-Jul-20 27-Jul-20 13 27-Jul-20, Roll Up Of Upper Jacket To Final Position
Transition Piece (TP) 76 14-May-20 11-Aug-20 0 11-Aug-20, Transition Piece (TP)
F2-JK2-JF08-1 Install Door Platform 10 06-Jun-20 18-Jun-20 29 18-Jun-20, Install Door Platform
F2-JK2-JF08-17Installation & Assembly of Ring Stiffener 21 09-Jun-20 03-Jul-20 0 03-Jul-20, Installation & Assembly of Ring Stiffener
F2-JK2-JF08-18Installation of Transition Piece Flange 15 17-Jun-20 04-Jul-20 0 04-Jul-20, Installation of Transition Piece Flange

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 39 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF08-19Install Crane Pedestal 12 20-May-20 03-Jun-20 42 03-Jun-20, Install Crane Pedestal
F2-JK2-JF08-2 Blasting & Painting 10 22-Jul-20 03-Aug-20 0 03-Aug-20, Blasting & Painting
F2-JK2-JF08-3 Assemble Can Transition Piece Barrel to Main Deck 15 14-May-20 01-Jun-20 0 01-Jun-20, Assemble Can Transition Piece Barrel to Main Deck
F2-JK2-JF08-4 Install Platform & Internal Structure into Upper Can 7 03-Aug-20 11-Aug-20 0 11-Aug-20, Install Platform & Internal Structure into Upper Can
F2-JK2-JF08-5 Door opening & Installation of Door frame 5 01-Jun-20 06-Jun-20 39 06-Jun-20, Door opening & Installation of Door frame
F2-JK2-JF08-6 Installation & Assembly of Strut 15 01-Jun-20 18-Jun-20 0 18-Jun-20, Installation & Assembly of Strut
F2-JK2-JF08-7 Install Free-Issued Items 15 04-Jul-20 22-Jul-20 0 22-Jul-20, Install Free-Issued Items
F2-JK2-JF08-8 Install Architectural items, Electrical & Instrument Equipments 15 01-Jun-20 18-Jun-20 29 18-Jun-20, Install Architectural items, Electrical & Instrument Equipments
F2-JK2-JF08-9 Install External Platform & Handrail 12 04-Jun-20 18-Jun-20 29 18-Jun-20, Install External Platform & Handrail
Final Assembly 8 11-Aug-20 20-Aug-20 1 20-Aug-20, Final Assembly
F2-JK2-JF08-107Installation of Transition Piece 3 11-Aug-20 14-Aug-20 0 14-Aug-20, Installation of Transition Piece
F2-JK2-JF08-108Installation of Mudmad Plate 5 13-Aug-20 19-Aug-20 0 19-Aug-20, Installation of Mudmad Plate
F2-JK2-JF08-109Installation of Lifting Trunnion 4 14-Aug-20 19-Aug-20 2 19-Aug-20, Installation of Lifting Trunnion
F2-JK2-JF08-110Installation of Skirt Pile Sleeve 2 13-Aug-20 15-Aug-20 0 15-Aug-20, Installation of Skirt Pile Sleeve
F2-JK2-JF08-111Final Touch Up Coating 3 17-Aug-20 20-Aug-20 0 20-Aug-20, Final Touch Up Coating
F2-JK2-JF08-112Installation of Lifting Slings 1 15-Aug-20 17-Aug-20 0 17-Aug-20, Installation of Lifting Slings
F2-JK2-JF08-161J acket Fabrication Completed 0 20-Aug-20 0 20-Aug-20
Testing & Commissioning 18 01-Aug-20 22-Aug-20 0 22-Aug-20, Testing & Commissioning
Grouting & Gripper Test 3 01-Aug-20 05-Aug-20 13 05-Aug-20, Grouting & Gripper Test
F2-JK2-JF08-20Gripper Test 2 03-Aug-20 05-Aug-20 13 05-Aug-20, Gripper Test
F2-JK2-JF08-21Grouting Test 1 01-Aug-20 03-Aug-20 13 03-Aug-20, Grouting Test
Mechanical Completion 2 20-Aug-20 22-Aug-20 0 22-Aug-20, Mechanical Completion
F2-JK2-JF08-22Main Structure, Boat Landing, J-Tube, Transition Piece 2 20-Aug-20 22-Aug-20 0 22-Aug-20, Main Structure, Boat Landing, J-Tube, Transition Piece
Jacket & Piles Ready For Loadout 0 22-Aug-20 22-Aug-20 0 22-Aug-20, Jacket & Piles Ready For Loadout
F2-JK2-JF08-23Jacket Ready For Load Out 0 22-Aug-20 0 22-Aug-20
Jacket Foundation 9a 130 01-Apr-20 31-Aug-20 59 31-Aug-20, Jacket Foundation 9a
Fabrication 72 01-Apr-20 24-Jun-20 107 24-Jun-20, Fabrication
Pre-Fabrication 38 01-Apr-20 15-May-20 108 15-May-20, Pre-Fabrication
F2-JK2-JF09-140Rolling of Can Transition Piece Flange 10 04-May-20 15-May-20 108 15-May-20, Rolling of Can Transition Piece Flange
F2-JK2-JF09-141Rolling of Can Transition Piece Barrel 10 13-Apr-20 24-Apr-20 59 24-Apr-20, Rolling of Can Transition Piece Barrel
F2-JK2-JF09-24Rolling of Can Row 2 Brace 10 01-Apr-20 13-Apr-20 52 13-Apr-20, Rolling of Can Row 2 Brace
F2-JK2-JF09-25Rolling of Can Leg 1A & 1B 10 01-Apr-20 13-Apr-20 72 13-Apr-20, Rolling of Can Leg 1A & 1B
F2-JK2-JF09-26Rolling of Can Leg 2A & 2B 10 09-Apr-20 21-Apr-20 72 21-Apr-20, Rolling of Can Leg 2A & 2B
F2-JK2-JF09-27Rolling of Node Can Row 1 10 09-Apr-20 21-Apr-20 72 21-Apr-20, Rolling of Node Can Row 1
F2-JK2-JF09-28Rolling of Node Can Row 2 10 17-Apr-20 29-Apr-20 72 29-Apr-20, Rolling of Node Can Row 2
F2-JK2-JF09-29Rolling of Can Row 1 Brace 10 17-Apr-20 29-Apr-20 72 29-Apr-20, Rolling of Can Row 1 Brace
F2-JK2-JF09-30Rolling of J-Tubes & J-Tubes Support 10 25-Apr-20 07-May-20 73 07-May-20, Rolling of J-Tubes & J-Tubes Support
F2-JK2-JF09-31Rolling of Can Plan Level Tubular 10 25-Apr-20 07-May-20 108 07-May-20, Rolling of Can Plan Level Tubular
F2-JK2-JF09-32Rolling of Can Top Bay X-Brace 10 04-May-20 15-May-20 108 15-May-20, Rolling of Can Top Bay X-Brace
Row 1 Fabrication 42 13-Apr-20 01-Jun-20 113 01-Jun-20, Row 1 Fabrication
Legs 40 13-Apr-20 30-May-20 75 30-May-20, Legs
F2-JK2-JF09-40
Install Stubs on to Leg 1A & 1B Nodes 2 20-May-20 22-May-20 72 22-May-20, Install Stubs on to Leg 1A & 1B Nodes
F2-JK2-JF09-41
Install Anodes on Row-1 Legs 4 21-May-20 26-May-20 74 26-May-20, Install Anodes on Row-1 Legs
F2-JK2-JF09-42
Join of Can Legs 1A 9 17-Apr-20 28-Apr-20 87 28-Apr-20, Join of Can Legs 1A
F2-JK2-JF09-43
Join of Can Legs 1B 9 17-Apr-20 28-Apr-20 87 28-Apr-20, Join of Can Legs 1B
F2-JK2-JF09-44
Mark and Profile Leg 1A & 1B Node 4 21-Apr-20 25-Apr-20 97 25-Apr-20, Mark and Profile Leg 1A & 1B Node
F2-JK2-JF09-45
Profilling of Legs 1A & 1B (Inc. Cones) 4 13-Apr-20 17-Apr-20 87 17-Apr-20, Profilling of Legs 1A & 1B (Inc. Cones)
F2-JK2-JF09-46
Join of Leg 1A & 1B Node 2 21-May-20 23-May-20 75 23-May-20, Join of Leg 1A & 1B Node
F2-JK2-JF09-47
Blasting and Painting for Leg 1A & 1B Node 5 23-May-20 30-May-20 75 30-May-20, Blasting and Painting for Leg 1A & 1B Node
F2-JK2-JF09-48
Assembly Leg 1A 3 19-May-20 21-May-20 72 21-May-20, Assembly Leg 1A
F2-JK2-JF09-49
Assembly Leg 1B 3 19-May-20 21-May-20 72 21-May-20, Assembly Leg 1B
Braces 28 29-Apr-20 01-Jun-20 72 01-Jun-20, Braces
F2-JK2-JF09-50
Fit & Weld Top X Brace Between Legs 1A & 1B 5 22-May-20 28-May-20 72 28-May-20, Fit & Weld Top X Brace Between Legs 1A & 1B
F2-JK2-JF09-51
Join of Row-1 Can Brace (Inc. Stub) 13 04-May-20 19-May-20 72 19-May-20, Join of Row-1 Can Brace (Inc. Stub)
F2-JK2-JF09-52
Join of Can Brace for Between Row 1 & 2 (Inc. Stub) 13 04-May-20 19-May-20 72 19-May-20, Join of Can Brace for Between Row 1 & 2 (Inc. Stub)

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 40 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF09-53
Assembly of Row-1 Top Brace 4 19-May-20 22-May-20 72 22-May-20, Assembly of Row-1 Top Brace
F2-JK2-JF09-54
Fit & Weld Row-2 K-Brace (Inc. Vertical Braces) 5 22-May-20 28-May-20 72 28-May-20, Fit & Weld Row-2 K-Brace (Inc. Vertical Braces)
F2-JK2-JF09-55
Assembly of Row-1 K-Brace 4 19-May-20 22-May-20 72 22-May-20, Assembly of Row-1 K-Brace
F2-JK2-JF09-56
Fit & Weld X-Brace Between Row 1 & 2 5 22-May-20 28-May-20 72 28-May-20, Fit & Weld X-Brace Between Row 1 & 2
F2-JK2-JF09-57
Assembly of Brace Between Row 1 & 2 4 19-May-20 22-May-20 72 22-May-20, Assembly of Brace Between Row 1 & 2
F2-JK2-JF09-58
Profilling of Row-1 Braces and Stubs 4 29-Apr-20 04-May-20 72 04-May-20, Profilling of Row-1 Braces and Stubs
F2-JK2-JF09-59
Install Anodes on Row-1 Braces 4 28-May-20 01-Jun-20 72 01-Jun-20, Install Anodes on Row-1 Braces
J-Tubes 19 07-May-20 29-May-20 115 29-May-20, J-Tubes
F2-JK2-JF09-60
Join of Row-1 J-Tubes 5 12-May-20 18-May-20 115 18-May-20, Join of Row-1 J-Tubes
F2-JK2-JF09-61
Profilling of Row-1 J-Tubes 4 07-May-20 12-May-20 115 12-May-20, Profilling of Row-1 J-Tubes
F2-JK2-JF09-62
Bending of Row-1 J-Tubes 4 18-May-20 21-May-20 115 21-May-20, Bending of Row-1 J-Tubes
F2-JK2-JF09-63
Blast and Paint for Row-1 J-Tubes 3 21-May-20 26-May-20 115 26-May-20, Blast and Paint for Row-1 J-Tubes
F2-JK2-JF09-64
Assembly Row-1 J-Tubes 3 26-May-20 29-May-20 115 29-May-20, Assembly Row-1 J-Tubes
F2-JK2-JF09-65
Cut and Profile Row-1 J-Tubes Support 4 07-May-20 12-May-20 115 12-May-20, Cut and Profile Row-1 J-Tubes Support
F2-JK2-JF09-66
Assembly Row-1 J-Tubes Support 2 12-May-20 15-May-20 115 15-May-20, Assembly Row-1 J-Tubes Support
F2-JK2-JF09-67
Paint Row-1 J-Tubes Support 3 15-May-20 19-May-20 115 19-May-20, Paint Row-1 J-Tubes Support
F2-JK2-JF09-68
Install J-Tubes Support on to Row-1 J-Tubes 3 19-May-20 21-May-20 115 21-May-20, Install J-Tubes Support on to Row-1 J-Tubes
Common 23 06-May-20 01-Jun-20 73 01-Jun-20, Common
Structure 3 06-May-20 09-May-20 80 09-May-20, Structure
F2-JK2-JF09-33
Marking & Cutting of Leg and Brace Node 3 06-May-20 09-May-20 80 09-May-20, Marking & Cutting of Leg and Brace Node
F2-JK2-JF09-34
Marking & Cutting of Brace Stub 3 06-May-20 09-May-20 80 09-May-20, Marking & Cutting of Brace Stub
F2-JK2-JF09-35
Marking & Cutting of Leg and Brace Member 3 06-May-20 09-May-20 80 09-May-20, Marking & Cutting of Leg and Brace Member
Final Painting 23 06-May-20 01-Jun-20 73 01-Jun-20, Final Painting
F2-JK2-JF09-36
Blast and Paint Leg and Brace (Initial Paint) 11 06-May-20 19-May-20 72 19-May-20, Blast and Paint Leg and Brace (Initial Paint)
F2-JK2-JF09-37
Build Painting Habitat Protection 1 28-May-20 30-May-20 75 30-May-20, Build Painting Habitat Protection
F2-JK2-JF09-38
Row-1 Ready for Assembly & Roll-up 0 30-May-20 75 30-May-20
F2-JK2-JF09-39
Row-1 Touch up and Final Painting 3 28-May-20 01-Jun-20 72 01-Jun-20, Row-1 Touch up and Final Painting
Row 2 Fabrication 42 13-Apr-20 01-Jun-20 73 01-Jun-20, Row 2 Fabrication
Legs 23 21-Apr-20 18-May-20 86 18-May-20, Legs
F2-JK2-JF09-76
Install Anodes on Row-2 Legs 4 08-May-20 13-May-20 85 13-May-20, Install Anodes on Row-2 Legs
F2-JK2-JF09-77
Join of Can Legs 2A 9 25-Apr-20 06-May-20 80 06-May-20, Join of Can Legs 2A
F2-JK2-JF09-78
Join of Can Legs 2B 9 25-Apr-20 06-May-20 80 06-May-20, Join of Can Legs 2B
F2-JK2-JF09-79
Profilling of Legs 2A & 2B (Inc. Cones) 4 21-Apr-20 25-Apr-20 80 25-Apr-20, Profilling of Legs 2A & 2B (Inc. Cones)
F2-JK2-JF09-80
Mark and Profile Leg 2A & 2B Node 4 29-Apr-20 04-May-20 90 04-May-20, Mark and Profile Leg 2A & 2B Node
F2-JK2-JF09-81
Join of Leg 2A & 2B Node 2 08-May-20 11-May-20 86 11-May-20, Join of Leg 2A & 2B Node
F2-JK2-JF09-82
Blasting and Painting for Leg 2A & 2B Node (Initial) 5 11-May-20 18-May-20 86 18-May-20, Blasting and Painting for Leg 2A & 2B Node (Initial)
F2-JK2-JF09-83
Assembly Leg 2A 3 06-May-20 08-May-20 78 08-May-20, Assembly Leg 2A
F2-JK2-JF09-84
Assembly Leg 2B 3 06-May-20 08-May-20 78 08-May-20, Assembly Leg 2B
F2-JK2-JF09-85
Install Stubs on to Leg 2A & 2B Nodes 2 08-May-20 11-May-20 78 11-May-20, Install Stubs on to Leg 2A & 2B Nodes
Braces 32 13-Apr-20 20-May-20 78 20-May-20, Braces
F2-JK2-JF09-138
Fit & Weld Row-2 K-Brace (Inc. Vertical Braces) 5 11-May-20 16-May-20 78 16-May-20, Fit & Weld Row-2 K-Brace (Inc. Vertical Braces)
F2-JK2-JF09-139
Assembly of Row-2 K-Brace 4 06-May-20 09-May-20 79 09-May-20, Assembly of Row-2 K-Brace
F2-JK2-JF09-86
Fit & Weld Top X-Brace Between Legs 2A & 2B 4 11-May-20 15-May-20 81 15-May-20, Fit & Weld Top X-Brace Between Legs 2A & 2B
F2-JK2-JF09-87
Fit & Weld Mid X-Brace Between Legs 2A & 2B 4 11-May-20 15-May-20 81 15-May-20, Fit & Weld Mid X-Brace Between Legs 2A & 2B
F2-JK2-JF09-88
Join of Row-2 Can Brace (Inc. Stub) 10 17-Apr-20 29-Apr-20 78 29-Apr-20, Join of Row-2 Can Brace (Inc. Stub)
F2-JK2-JF09-89
Assembly of Row-2 Top Brace 3 06-May-20 09-May-20 82 09-May-20, Assembly of Row-2 Top Brace
F2-JK2-JF09-90
Assembly of Row-2 Mid Brace 3 06-May-20 09-May-20 82 09-May-20, Assembly of Row-2 Mid Brace
F2-JK2-JF09-91
Profilling of Row-2 Braces and Stubs 4 13-Apr-20 17-Apr-20 78 17-Apr-20, Profilling of Row-2 Braces and Stubs
F2-JK2-JF09-92
Install Anodes on Row-2 Braces 4 16-May-20 20-May-20 78 20-May-20, Install Anodes on Row-2 Braces
J-Tubes 21 07-May-20 01-Jun-20 73 01-Jun-20, J-Tubes
F2-JK2-JF09-128
Join of Row-2 J-Tubes 5 12-May-20 18-May-20 76 18-May-20, Join of Row-2 J-Tubes
F2-JK2-JF09-129
Profilling of Row-2 J-Tubes 4 07-May-20 12-May-20 76 12-May-20, Profilling of Row-2 J-Tubes
F2-JK2-JF09-130
Bending of Row-2 J-Tubes 4 18-May-20 21-May-20 76 21-May-20, Bending of Row-2 J-Tubes
F2-JK2-JF09-131
Blast and Paint for Row-2 J-Tubes 3 25-May-20 28-May-20 73 28-May-20, Blast and Paint for Row-2 J-Tubes
F2-JK2-JF09-132
Assembly Row-2 J-Tubes 3 28-May-20 01-Jun-20 73 01-Jun-20, Assembly Row-2 J-Tubes

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 41 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF09-133
Cut and Profile Row-2 J-Tubes Support 4 07-May-20 12-May-20 73 12-May-20, Cut and Profile Row-2 J-Tubes Support
F2-JK2-JF09-134
Assembly Row-2 J-Tubes Support 2 12-May-20 15-May-20 73 15-May-20, Assembly Row-2 J-Tubes Support
F2-JK2-JF09-135
Vulcanized Row-2 J-Tubes Support 2 15-May-20 18-May-20 73 18-May-20, Vulcanized Row-2 J-Tubes Support
F2-JK2-JF09-136
Paint Row-2 J-Tubes Support 3 18-May-20 21-May-20 73 21-May-20, Paint Row-2 J-Tubes Support
F2-JK2-JF09-137
Install J-Tubes Support on to Row-2 J-Tubes 3 21-May-20 25-May-20 73 25-May-20, Install J-Tubes Support on to Row-2 J-Tubes
Common 23 29-Apr-20 26-May-20 78 26-May-20, Common
Structure 3 29-Apr-20 02-May-20 82 02-May-20, Structure
F2-JK2-JF09-69
Marking & Cutting of Leg and Brace Node 3 29-Apr-20 02-May-20 82 02-May-20, Marking & Cutting of Leg and Brace Node
F2-JK2-JF09-70
Marking & Cutting of Brace Stub 3 29-Apr-20 02-May-20 82 02-May-20, Marking & Cutting of Brace Stub
F2-JK2-JF09-71
Marking & Cutting of Leg and Brace Member 3 29-Apr-20 02-May-20 82 02-May-20, Marking & Cutting of Leg and Brace Member
Final Painting 23 29-Apr-20 26-May-20 78 26-May-20, Final Painting
F2-JK2-JF09-72
Row-2 Touch up and Final Painting 3 20-May-20 25-May-20 78 25-May-20, Row-2 Touch up and Final Painting
F2-JK2-JF09-73
Blast and Paint Leg and Brace (Initial Paint) 5 29-Apr-20 06-May-20 78 06-May-20, Blast and Paint Leg and Brace (Initial Paint)
F2-JK2-JF09-74
Build Painting Habitat Protection 1 25-May-20 26-May-20 78 26-May-20, Build Painting Habitat Protection
F2-JK2-JF09-75
Row-2 Ready for Assembly & Roll-up 0 26-May-20 78 26-May-20
Transition Piece 61 13-Apr-20 23-Jun-20 108 23-Jun-20, Transition Piece
F2-JK2-JF09-10Fabrication of Can Transition Piece Barrel 24 24-Apr-20 22-May-20 59 22-May-20, Fabrication of Can Transition Piece Barrel
F2-JK2-JF09-100Fit Grating Supports 4 25-Apr-20 30-Apr-20 125 30-Apr-20, Fit Grating Supports
F2-JK2-JF09-101Fab Main Deck Handrails 4 20-Apr-20 23-Apr-20 126 23-Apr-20, Fab Main Deck Handrails
F2-JK2-JF09-102Fab Padeye inc Top of Jacket 4 21-Apr-20 24-Apr-20 152 24-Apr-20, Fab Padeye inc Top of Jacket
F2-JK2-JF09-103Blast and Paint Transition Piece 7 15-Jun-20 23-Jun-20 108 23-Jun-20, Blast and Paint Transition Piece
F2-JK2-JF09-11 Fabrication of Strut Plate 18 13-Apr-20 04-May-20 68 04-May-20, Fabrication of Strut Plate
F2-JK2-JF09-12Fabrication of Internal Platform 21 13-Apr-20 07-May-20 137 07-May-20, Fabrication of Internal Platform
F2-JK2-JF09-13Fabrication of External Platform 25 13-Apr-20 12-May-20 137 12-May-20, Fabrication of External Platform
F2-JK2-JF09-14Assembly Strut Plate 21 04-May-20 28-May-20 123 28-May-20, Assembly Strut Plate
F2-JK2-JF09-15Fabrication of Ring Stiffener 21 21-May-20 15-Jun-20 108 15-Jun-20, Fabrication of Ring Stiffener
F2-JK2-JF09-16Fabrication of Crane Pedestal 21 04-May-20 28-May-20 101 28-May-20, Fabrication of Crane Pedestal
F2-JK2-JF09-93Galvanizing Handrails 5 23-Apr-20 29-Apr-20 126 29-Apr-20, Galvanizing Handrails
F2-JK2-JF09-94Erect Deck Plate Areas 5 21-Apr-20 25-Apr-20 124 25-Apr-20, Erect Deck Plate Areas
F2-JK2-JF09-95Transition Piece Fabrication Complete 0 15-Jun-20 108 15-Jun-20
F2-JK2-JF09-96Fabrication Assemble Walkways / Platforms 21 04-May-20 28-May-20 123 28-May-20, Fabrication Assemble Walkways / Platforms
F2-JK2-JF09-97Fit and Weld TP's Equipment Supports 5 21-Apr-20 28-Apr-20 124 28-Apr-20, Fit and Weld TP's Equipment Supports
F2-JK2-JF09-98Plate Profiling for Main Deck 5 13-Apr-20 20-Apr-20 79 20-Apr-20, Plate Profiling for Main Deck
F2-JK2-JF09-99Fab Main Deck Main Steel 5 15-Apr-20 21-Apr-20 79 21-Apr-20, Fab Main Deck Main Steel
Lifting Trunnion 7 21-Apr-20 29-Apr-20 79 29-Apr-20, Lifting Trunnion
F2-JK2-JF09-104Fabricate Lifting Trunion 7 21-Apr-20 29-Apr-20 79 29-Apr-20, Fabricate Lifting Trunion
Boat Landing 44 24-Apr-20 16-Jun-20 104 16-Jun-20, Boat Landing
F2-JK2-JF09-123Blast and Paint Boat Landing 5 09-Jun-20 16-Jun-20 104 16-Jun-20, Blast and Paint Boat Landing
F2-JK2-JF09-124Fabricate Boat Landing 21 24-Apr-20 19-May-20 97 19-May-20, Fabricate Boat Landing
F2-JK2-JF09-159Fabricate Boat Landing Access platform 24 12-May-20 09-Jun-20 104 09-Jun-20, Fabricate Boat Landing Access platform
F2-JK2-JF09-160Fabricate Boat Landing Ladders 15 20-May-20 06-Jun-20 106 06-Jun-20, Fabricate Boat Landing Ladders
Grouting Line 23 28-May-20 24-Jun-20 101 24-Jun-20, Grouting Line
F2-JK2-JF09-126Fabricate Grouting Line & Grouting Line Support 23 28-May-20 24-Jun-20 101 24-Jun-20, Fabricate Grouting Line & Grouting Line Support
Assembly 105 29-Apr-20 28-Aug-20 60 28-Aug-20, Assembly
Row Assembly 88 29-Apr-20 10-Aug-20 72 10-Aug-20, Row Assembly
F2-JK2-JF09-113Fabricate Upper Grillage & Truss Support 18 29-Apr-20 20-May-20 79 20-May-20, Fabricate Upper Grillage & Truss Support
F2-JK2-JF09-114Layout Concrete Blocks/ Grillages and Truss Support Steel 4 28-May-20 03-Jun-20 72 03-Jun-20, Layout Concrete Blocks/ Grillages and Truss Support Steel
Row-1 & 2 (Upper Jacket) Assembly 46 03-Jun-20 27-Jul-20 72 27-Jul-20, Row-1 & 2 (Upper Jacket) Assembly
F2-JK2-JF09-115
Installation of Grouting Line 1 20-Jun-20 22-Jun-20 92 22-Jun-20, Installation of Grouting Line
F2-JK2-JF09-117
Installation of J-Tube At Row-1B & 2A 5 20-Jun-20 26-Jun-20 96 26-Jun-20, Installation of J-Tube At Row-1B & 2A
F2-JK2-JF09-118
Row-2 - Touch Up, 2nd Coat & Top Coat 3 23-Jul-20 25-Jul-20 72 25-Jul-20, Row-2 - Touch Up, 2nd Coat & Top Coat
F2-JK2-JF09-119
Installation of Row-1B & 2B X-Brace 7 12-Jun-20 20-Jun-20 72 20-Jun-20, Installation of Row-1B & 2B X-Brace
F2-JK2-JF09-120
Installation of Leg 1A & 1B Onto Support 1 03-Jun-20 04-Jun-20 72 04-Jun-20, Installation of Leg 1A & 1B Onto Support
F2-JK2-JF09-121
Installation of Row-1A & 1B X-Brace 7 04-Jun-20 12-Jun-20 72 12-Jun-20, Installation of Row-1A & 1B X-Brace
F2-JK2-JF09-122
Installation of Row-2A & 2B X-Brace in Final Position 7 15-Jul-20 23-Jul-20 72 23-Jul-20, Installation of Row-2A & 2B X-Brace in Final Position

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 42 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF09-142
Installation of Leg 2A & 2B Onto Support 1 03-Jun-20 04-Jun-20 79 04-Jun-20, Installation of Leg 2A & 2B Onto Support
F2-JK2-JF09-143
Installation of Row-1A & 2A X-Brace 7 12-Jun-20 20-Jun-20 72 20-Jun-20, Installation of Row-1A & 2A X-Brace
F2-JK2-JF09-144
Installation of Row-1A & 1B X-Brace in Final Position 7 07-Jul-20 15-Jul-20 72 15-Jul-20, Installation of Row-1A & 1B X-Brace in Final Position
F2-JK2-JF09-145
Roll Up X-Brace Row A&B to Final Position 7 20-Jun-20 29-Jun-20 72 29-Jun-20, Roll Up X-Brace Row A&B to Final Position
F2-JK2-JF09-146
Installing Tie-back for Fastener 7 29-Jun-20 07-Jul-20 72 07-Jul-20, Installing Tie-back for Fastener
F2-JK2-JF09-147
Installation of Boat Landing 3 23-Jul-20 27-Jul-20 72 27-Jul-20, Installation of Boat Landing
Row-1 & 2 (Lower Jacket) Assembly 44 30-May-20 20-Jul-20 77 20-Jul-20, Row-1 & 2 (Lower Jacket) Assembly
F2-JK2-JF09-116
Installation of Pile Stopper 4 30-Jun-20 03-Jul-20 77 03-Jul-20, Installation of Pile Stopper
F2-JK2-JF09-148
Installation of Grouting Line 1 17-Jun-20 18-Jun-20 98 18-Jun-20, Installation of Grouting Line
F2-JK2-JF09-149
Installation of J-Tube At Row-1B & 2A 5 17-Jun-20 23-Jun-20 87 23-Jun-20, Installation of J-Tube At Row-1B & 2A
F2-JK2-JF09-150
Installation of Row-1B & 2B X-Brace 7 09-Jun-20 17-Jun-20 77 17-Jun-20, Installation of Row-1B & 2B X-Brace
F2-JK2-JF09-151
Installation of Leg 1A & 1B Onto Support 1 30-May-20 01-Jun-20 77 01-Jun-20, Installation of Leg 1A & 1B Onto Support
F2-JK2-JF09-152
Installation of Row-1A & 1B X-Brace 7 01-Jun-20 09-Jun-20 77 09-Jun-20, Installation of Row-1A & 1B X-Brace
F2-JK2-JF09-153
Installation of Row-2A & 2B X-Brace in Final Position 7 11-Jul-20 20-Jul-20 77 20-Jul-20, Installation of Row-2A & 2B X-Brace in Final Position
F2-JK2-JF09-154
Installation of Leg 2A & 2B Onto Support 1 30-May-20 01-Jun-20 84 01-Jun-20, Installation of Leg 2A & 2B Onto Support
F2-JK2-JF09-155
Installation of Row-1A & 2A X-Brace 7 09-Jun-20 17-Jun-20 77 17-Jun-20, Installation of Row-1A & 2A X-Brace
F2-JK2-JF09-156
Installation of Row-1A & 1B X-Brace in Final Position 7 03-Jul-20 11-Jul-20 77 11-Jul-20, Installation of Row-1A & 1B X-Br ace in F inal Posit io n
F2-JK2-JF09-157
Roll Up X-Brace Row A&B to Final Position 7 17-Jun-20 25-Jun-20 77 25-Jun-20, Roll Up X-Brace Row A&B to Final Position
F2-JK2-JF09-158
Installing Tie-back for Fastener 4 25-Jun-20 30-Jun-20 77 30-Jun-20, Installing Tie-back for Fastener
Grouting Line 40 24-Jun-20 10-Aug-20 72 10-Aug-20, Grouting Line
F2-JK2-JF09-125
Installation Of Grouting Line 5 04-Aug-20 10-Aug-20 72 10-Aug-20, Installation Of Grouting Line
F2-JK2-JF09-127
Installation Grouting Line Support 7 24-Jun-20 02-Jul-20 101 02-Jul-20, Installation Grouting Line Support
Row Roll Up 7 27-Jul-20 04-Aug-20 72 04-Aug-20, Row Roll Up
F2-JK2-JF09-105Roll Up Of Lower Jacket To Final Position 2 27-Jul-20 29-Jul-20 72 29-Jul-20, Roll Up Of Lower Jacket To Final Position
F2-JK2-JF09-106Roll Up Of Upper Jacket To Final Position 5 29-Jul-20 04-Aug-20 72 04-Aug-20, Roll Up Of Upper Jacket To Final Position
Transition Piece (TP) 76 22-May-20 19-Aug-20 59 19-Aug-20, Transition Piece (TP)
F2-JK2-JF09-1 Install Door Platform 10 15-Jun-20 26-Jun-20 88 26-Jun-20, Install Door Platform
F2-JK2-JF09-17Installation & Assembly of Ring Stiffener 21 17-Jun-20 11-Jul-20 59 11-Jul-20, Installation & Assembly of R ing Stiffener
F2-JK2-JF09-18Installation of Transition Piece Flange 15 25-Jun-20 13-Jul-20 59 13-Jul-20, Installation of Transition Piece Flange
F2-JK2-JF09-19Install Crane Pedestal 12 28-May-20 11-Jun-20 101 11-Jun-20, Install Crane Pedestal
F2-JK2-JF09-2 Blasting & Painting 10 30-Jul-20 11-Aug-20 59 11-Aug-20, Blasting & Painting
F2-JK2-JF09-3 Assemble Can Transition Piece Barrel to Main Deck 15 22-May-20 09-Jun-20 59 09-Jun-20, Assemble Can Transition Piece Barrel to Main Deck
F2-JK2-JF09-4 Install Platform & Internal Structure into Upper Can 7 11-Aug-20 19-Aug-20 59 19-Aug-20, Install Platform & Internal Structure into Upper Can
F2-JK2-JF09-5 Door opening & Installation of Door frame 5 09-Jun-20 15-Jun-20 98 15-Jun-20, Door opening & Installation of Door frame
F2-JK2-JF09-6 Installation & Assembly of Strut 15 09-Jun-20 26-Jun-20 59 26-Jun-20, Installation & Assembly of Strut
F2-JK2-JF09-7 Install Free-Issued Items 15 13-Jul-20 30-Jul-20 59 30-Jul-20, Install Free-Issued Items
F2-JK2-JF09-8 Install Architectural items, Electrical & Instrument Equipments 15 09-Jun-20 26-Jun-20 88 26-Jun-20, Install Architectural items, Electrical & Instrument Equipments
F2-JK2-JF09-9 Install External Platform & Handrail 12 12-Jun-20 26-Jun-20 88 26-Jun-20, Install External Platform & Handrail
Final Assembly 8 19-Aug-20 28-Aug-20 60 28-Aug-20, Final Assembly
F2-JK2-JF09-107Installation of Transition Piece 3 19-Aug-20 22-Aug-20 59 22-Aug-20, Installation of Transition Piece
F2-JK2-JF09-108Installation of Mudmad Plate 5 21-Aug-20 27-Aug-20 59 27-Aug-20, Installation of Mudmad Plate
F2-JK2-JF09-109Installation of Lifting Trunnion 4 22-Aug-20 27-Aug-20 61 27-Aug-20, Installation of Lifting Trunnion
F2-JK2-JF09-110Installation of Skirt Pile Sleeve 2 21-Aug-20 24-Aug-20 59 24-Aug-20, Installation of Skirt Pile Sleeve
F2-JK2-JF09-111Final Touch Up Coating 3 25-Aug-20 28-Aug-20 59 28-Aug-20, Final Touch Up Coating
F2-JK2-JF09-112Installation of Lifting Slings 1 24-Aug-20 25-Aug-20 59 25-Aug-20, Installation of Lifting Slings
F2-JK2-JF09-161J acket Fabrication Completed 0 28-Aug-20 59 28-Aug-20
Testing & Commissioning 18 10-Aug-20 31-Aug-20 59 31-Aug-20, Testing & Commissioning
Grouting & Gripper Test 3 10-Aug-20 13-Aug-20 72 13-Aug-20, Grouting & Gripper Test
F2-JK2-JF09-20Gripper Test 2 11-Aug-20 13-Aug-20 72 13-Aug-20, Gripper Test
F2-JK2-JF09-21Grouting Test 1 10-Aug-20 11-Aug-20 72 11-Aug-20, Grouting Test
Mechanical Completion 2 28-Aug-20 31-Aug-20 59 31-Aug-20, Mechanical Completion
F2-JK2-JF09-22Main Structure, Boat Landing, J-Tube, Transition Piece 2 28-Aug-20 31-Aug-20 59 31-Aug-20, Main Structure, Boat Landing, J-Tube, Transition Piece
Jacket & Piles Ready For Loadout 0 31-Aug-20 31-Aug-20 59 31-Aug-20, Jacket & Piles Ready For Loadout
F2-JK2-JF09-23Jacket Ready For Load Out 0 31-Aug-20 59 31-Aug-20
Jacket Foundation 10a 130 09-Apr-20 08-Sep-20 52 08-Sep-20, Jacket Foundation 10a

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 43 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
Fabrication 72 09-Apr-20 02-Jul-20 100 02-Jul-20, Fabrication
Pre-Fabrication 38 09-Apr-20 23-May-20 101 23-May-20, Pre-Fabrication
F2-JK2-JF10-140Rolling of Can Transition Piece Flange 10 12-May-20 23-May-20 101 23-May-20, Rolling of Can Transition Piece Flange
F2-JK2-JF10-141Rolling of Can Transition Piece Barrel 10 21-Apr-20 02-May-20 52 02-May-20, Rolling of Can Transition Piece Barrel
F2-JK2-JF10-24Rolling of Can Row 2 Brace 10 09-Apr-20 21-Apr-20 52 21-Apr-20, Rolling of Can Row 2 Brace
F2-JK2-JF10-25Rolling of Can Leg 1A & 1B 10 09-Apr-20 21-Apr-20 65 21-Apr-20, Rolling of Can Leg 1A & 1B
F2-JK2-JF10-26Rolling of Can Leg 2A & 2B 10 17-Apr-20 29-Apr-20 65 29-Apr-20, Rolling of Can Leg 2A & 2B
F2-JK2-JF10-27Rolling of Node Can Row 1 10 17-Apr-20 29-Apr-20 65 29-Apr-20, Rolling of Node Can Row 1
F2-JK2-JF10-28Rolling of Node Can Row 2 10 25-Apr-20 07-May-20 65 07-May-20, Rolling of Node Can Row 2
F2-JK2-JF10-29Rolling of Can Row 1 Brace 10 25-Apr-20 07-May-20 65 07-May-20, Rolling of Can Row 1 Brace
F2-JK2-JF10-30Rolling of J-Tubes & J-Tubes Support 10 04-May-20 15-May-20 66 15-May-20, Rolling of J-Tubes & J-Tubes Support
F2-JK2-JF10-31Rolling of Can Plan Level Tubular 10 04-May-20 15-May-20 101 15-May-20, Rolling of Can Plan Level Tubular
F2-JK2-JF10-32Rolling of Can Top Bay X-Brace 10 12-May-20 23-May-20 101 23-May-20, Rolling of Can Top Bay X-Brace
Row 1 Fabrication 42 21-Apr-20 09-Jun-20 106 09-Jun-20, Row 1 Fabrication
Legs 40 21-Apr-20 08-Jun-20 68 08-Jun-20, Legs
F2-JK2-JF10-40
Install Stubs on to Leg 1A & 1B Nodes 2 28-May-20 30-May-20 65 30-May-20, Install Stubs on to Leg 1A & 1B Nodes
F2-JK2-JF10-41
Install Anodes on Row-1 Legs 4 29-May-20 03-Jun-20 67 03-Jun-20, Install Anodes on Row-1 Legs
F2-JK2-JF10-42
Join of Can Legs 1A 9 25-Apr-20 06-May-20 80 06-May-20, Join of Can Legs 1A
F2-JK2-JF10-43
Join of Can Legs 1B 9 25-Apr-20 06-May-20 80 06-May-20, Join of Can Legs 1B
F2-JK2-JF10-44
Mark and Profile Leg 1A & 1B Node 4 29-Apr-20 04-May-20 90 04-May-20, Mark and Profile Leg 1A & 1B Node
F2-JK2-JF10-45
Profilling of Legs 1A & 1B (Inc. Cones) 4 21-Apr-20 25-Apr-20 80 25-Apr-20, Profilling of Legs 1A & 1B (Inc. Cones)
F2-JK2-JF10-46
Join of Leg 1A & 1B Node 2 29-May-20 01-Jun-20 68 01-Jun-20, Join of Leg 1A & 1B Node
F2-JK2-JF10-47
Blasting and Painting for Leg 1A & 1B Node 5 01-Jun-20 08-Jun-20 68 08-Jun-20, Blasting and Painting for Leg 1A & 1B Node
F2-JK2-JF10-48
Assembly Leg 1A 3 27-May-20 29-May-20 65 29-May-20, Assembly Leg 1A
F2-JK2-JF10-49
Assembly Leg 1B 3 27-May-20 29-May-20 65 29-May-20, Assembly Leg 1B
Braces 28 07-May-20 09-Jun-20 65 09-Jun-20, Braces
F2-JK2-JF10-50
Fit & Weld Top X Brace Between Legs 1A & 1B 5 30-May-20 05-Jun-20 65 05-Jun-20, Fit & Weld Top X Brace Between Legs 1A & 1B
F2-JK2-JF10-51
Join of Row-1 Can Brace (Inc. Stub) 13 12-May-20 27-May-20 65 27-May-20, Join of Row-1 Can Brace (Inc. Stub)
F2-JK2-JF10-52
Join of Can Brace for Between Row 1 & 2 (Inc. Stub) 13 12-May-20 27-May-20 65 27-May-20, Join of Can Brace for Between Row 1 & 2 (Inc. Stub)
F2-JK2-JF10-53
Assembly of Row-1 Top Brace 4 27-May-20 30-May-20 65 30-May-20, Assembly of Row-1 Top Brace
F2-JK2-JF10-54
Fit & Weld Row-2 K-Brace (Inc. Vertical Braces) 5 30-May-20 05-Jun-20 65 05-Jun-20, Fit & Weld Row-2 K-Brace (Inc. Vertical Braces)
F2-JK2-JF10-55
Assembly of Row-1 K-Brace 4 27-May-20 30-May-20 65 30-May-20, Assembly of Row-1 K-Brace
F2-JK2-JF10-56
Fit & Weld X-Brace Between Row 1 & 2 5 30-May-20 05-Jun-20 65 05-Jun-20, Fit & Weld X-Brace Between Row 1 & 2
F2-JK2-JF10-57
Assembly of Brace Between Row 1 & 2 4 27-May-20 30-May-20 65 30-May-20, Assembly of Brace Between Row 1 & 2
F2-JK2-JF10-58
Profilling of Row-1 Braces and Stubs 4 07-May-20 12-May-20 65 12-May-20, Profilling of Row-1 Braces and Stubs
F2-JK2-JF10-59
Install Anodes on Row-1 Braces 4 05-Jun-20 09-Jun-20 65 09-Jun-20, Install Anodes on Row-1 Braces
J-Tubes 19 15-May-20 06-Jun-20 108 06-Jun-20, J-Tubes
F2-JK2-JF10-60
Join of Row-1 J-Tubes 5 20-May-20 26-May-20 108 26-May-20, Join of Row-1 J-Tubes
F2-JK2-JF10-61
Profilling of Row-1 J-Tubes 4 15-May-20 20-May-20 108 20-May-20, Profilling of Row-1 J-Tubes
F2-JK2-JF10-62
Bending of Row-1 J-Tubes 4 26-May-20 29-May-20 108 29-May-20, Bending of Row-1 J-Tubes
F2-JK2-JF10-63
Blast and Paint for Row-1 J-Tubes 3 29-May-20 03-Jun-20 108 03-Jun-20, Blast and Paint for Row-1 J-Tubes
F2-JK2-JF10-64
Assembly Row-1 J-Tubes 3 03-Jun-20 06-Jun-20 108 06-Jun-20, Assembly Row-1 J-Tubes
F2-JK2-JF10-65
Cut and Profile Row-1 J-Tubes Support 4 15-May-20 20-May-20 108 20-May-20, Cut and Profile Row-1 J-Tubes Support
F2-JK2-JF10-66
Assembly Row-1 J-Tubes Support 2 20-May-20 23-May-20 108 23-May-20, Assembly Row-1 J-Tubes Support
F2-JK2-JF10-67
Paint Row-1 J-Tubes Support 3 23-May-20 27-May-20 108 27-May-20, Paint Row-1 J-Tubes Support
F2-JK2-JF10-68
Install J-Tubes Support on to Row-1 J-Tubes 3 27-May-20 29-May-20 108 29-May-20, Install J-Tubes Support on to Row-1 J-Tubes
Common 23 14-May-20 09-Jun-20 66 09-Jun-20, Common
Structure 3 14-May-20 18-May-20 73 18-May-20, Structure
F2-JK2-JF10-33
Marking & Cutting of Leg and Brace Node 3 14-May-20 18-May-20 73 18-May-20, Marking & Cutting of Leg and Brace Node
F2-JK2-JF10-34
Marking & Cutting of Brace Stub 3 14-May-20 18-May-20 73 18-May-20, Marking & Cutting of Brace Stub
F2-JK2-JF10-35
Marking & Cutting of Leg and Brace Member 3 14-May-20 18-May-20 73 18-May-20, Marking & Cutting of Leg and Brace Member
Final Painting 23 14-May-20 09-Jun-20 66 09-Jun-20, Final Painting
F2-JK2-JF10-36
Blast and Paint Leg and Brace (Initial Paint) 11 14-May-20 27-May-20 65 27-May-20, Blast and Paint Leg and Brace (Initial Paint)
F2-JK2-JF10-37
Build Painting Habitat Protection 1 05-Jun-20 08-Jun-20 68 08-Jun-20, Build Painting Habitat Protection
F2-JK2-JF10-38
Row-1 Ready for Assembly & Roll-up 0 08-Jun-20 68 08-Jun-20

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 44 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF10-39
Row-1 Touch up and Final Painting 3 05-Jun-20 09-Jun-20 65 09-Jun-20, Row-1 Touch up and Final Painting
Row 2 Fabrication 42 21-Apr-20 09-Jun-20 66 09-Jun-20, Row 2 Fabrication
Legs 23 29-Apr-20 26-May-20 79 26-May-20, Legs
F2-JK2-JF10-76
Install Anodes on Row-2 Legs 4 16-May-20 21-May-20 78 21-May-20, Install Anodes on Row-2 Legs
F2-JK2-JF10-77
Join of Can Legs 2A 9 04-May-20 14-May-20 73 14-May-20, Join of Can Legs 2A
F2-JK2-JF10-78
Join of Can Legs 2B 9 04-May-20 14-May-20 73 14-May-20, Join of Can Legs 2B
F2-JK2-JF10-79
Profilling of Legs 2A & 2B (Inc. Cones) 4 29-Apr-20 04-May-20 73 04-May-20, Profilling of Legs 2A & 2B (Inc. Cones)
F2-JK2-JF10-80
Mark and Profile Leg 2A & 2B Node 4 07-May-20 12-May-20 83 12-May-20, Mark and Profile Leg 2A & 2B Node
F2-JK2-JF10-81
Join of Leg 2A & 2B Node 2 16-May-20 19-May-20 79 19-May-20, Join of Leg 2A & 2B Node
F2-JK2-JF10-82
Blasting and Painting for Leg 2A & 2B Node (Initial) 5 19-May-20 26-May-20 79 26-May-20, Blasting and Painting for Leg 2A & 2B Node (Initial)
F2-JK2-JF10-83
Assembly Leg 2A 3 14-May-20 16-May-20 71 16-May-20, Assembly Leg 2A
F2-JK2-JF10-84
Assembly Leg 2B 3 14-May-20 16-May-20 71 16-May-20, Assembly Leg 2B
F2-JK2-JF10-85
Install Stubs on to Leg 2A & 2B Nodes 2 16-May-20 19-May-20 71 19-May-20, Install Stubs on to Leg 2A & 2B Nodes
Braces 32 21-Apr-20 28-May-20 71 28-May-20, Braces
F2-JK2-JF10-138
Fit & Weld Row-2 K-Brace (Inc. Vertical Braces) 5 19-May-20 25-May-20 71 25-May-20, Fit & Weld Row-2 K-Brace (Inc. Vertical Braces)
F2-JK2-JF10-139
Assembly of Row-2 K-Brace 4 14-May-20 18-May-20 72 18-May-20, Assembly of Row-2 K-Brace
F2-JK2-JF10-86
Fit & Weld Top X-Brace Between Legs 2A & 2B 4 19-May-20 23-May-20 74 23-May-20, Fit & Weld Top X-Brace Between Legs 2A & 2B
F2-JK2-JF10-87
Fit & Weld Mid X-Brace Between Legs 2A & 2B 4 19-May-20 23-May-20 74 23-May-20, Fit & Weld Mid X-Brace Between Legs 2A & 2B
F2-JK2-JF10-88
Join of Row-2 Can Brace (Inc. Stub) 10 25-Apr-20 07-May-20 71 07-May-20, Join of Row-2 Can Brace (Inc. Stub)
F2-JK2-JF10-89
Assembly of Row-2 Top Brace 3 14-May-20 18-May-20 75 18-May-20, Assembly of Row-2 Top Brace
F2-JK2-JF10-90
Assembly of Row-2 Mid Brace 3 14-May-20 18-May-20 75 18-May-20, Assembly of Row-2 Mid Brace
F2-JK2-JF10-91
Profilling of Row-2 Braces and Stubs 4 21-Apr-20 25-Apr-20 71 25-Apr-20, Profilling of Row-2 Braces and Stubs
F2-JK2-JF10-92
Install Anodes on Row-2 Braces 4 25-May-20 28-May-20 71 28-May-20, Install Anodes on Row-2 Braces
J-Tubes 21 15-May-20 09-Jun-20 66 09-Jun-20, J-Tubes
F2-JK2-JF10-128
Join of Row-2 J-Tubes 5 20-May-20 26-May-20 69 26-May-20, Join of Row-2 J-Tubes
F2-JK2-JF10-129
Profilling of Row-2 J-Tubes 4 15-May-20 20-May-20 69 20-May-20, Profilling of Row-2 J-Tubes
F2-JK2-JF10-130
Bending of Row-2 J-Tubes 4 26-May-20 29-May-20 69 29-May-20, Bending of Row-2 J-Tubes
F2-JK2-JF10-131
Blast and Paint for Row-2 J-Tubes 3 02-Jun-20 05-Jun-20 66 05-Jun-20, Blast and Paint for Row-2 J-Tubes
F2-JK2-JF10-132
Assembly Row-2 J-Tubes 3 05-Jun-20 09-Jun-20 66 09-Jun-20, Assembly Row-2 J-Tubes
F2-JK2-JF10-133
Cut and Profile Row-2 J-Tubes Support 4 15-May-20 20-May-20 66 20-May-20, Cut and Profile Row-2 J-Tubes Support
F2-JK2-JF10-134
Assembly Row-2 J-Tubes Support 2 20-May-20 23-May-20 66 23-May-20, Assembly Row-2 J-Tubes Support
F2-JK2-JF10-135
Vulcanized Row-2 J-Tubes Support 2 23-May-20 26-May-20 66 26-May-20, Vulcanized Row-2 J-Tubes Support
F2-JK2-JF10-136
Paint Row-2 J-Tubes Support 3 26-May-20 29-May-20 66 29-May-20, Paint Row-2 J-Tubes Support
F2-JK2-JF10-137
Install J-Tubes Support on to Row-2 J-Tubes 3 29-May-20 02-Jun-20 66 02-Jun-20, Install J-Tubes Support on to Row-2 J-Tubes
Common 23 07-May-20 03-Jun-20 71 03-Jun-20, Common
Structure 3 07-May-20 11-May-20 75 11-May-20, Structure
F2-JK2-JF10-69
Marking & Cutting of Leg and Brace Node 3 07-May-20 11-May-20 75 11-May-20, Marking & Cutting of Leg and Brace Node
F2-JK2-JF10-70
Marking & Cutting of Brace Stub 3 07-May-20 11-May-20 75 11-May-20, Marking & Cutting of Brace Stub
F2-JK2-JF10-71
Marking & Cutting of Leg and Brace Member 3 07-May-20 11-May-20 75 11-May-20, Marking & Cutting of Leg and Brace Member
Final Painting 23 07-May-20 03-Jun-20 71 03-Jun-20, Final Painting
F2-JK2-JF10-72
Row-2 Touch up and Final Painting 3 28-May-20 02-Jun-20 71 02-Jun-20, Row-2 Touch up and Final Painting
F2-JK2-JF10-73
Blast and Paint Leg and Brace (Initial Paint) 5 07-May-20 14-May-20 71 14-May-20, Blast and Paint Leg and Brace (Initial Paint)
F2-JK2-JF10-74
Build Painting Habitat Protection 1 02-Jun-20 03-Jun-20 71 03-Jun-20, Build Painting Habitat Protection
F2-JK2-JF10-75
Row-2 Ready for Assembly & Roll-up 0 03-Jun-20 71 03-Jun-20
Transition Piece 61 21-Apr-20 01-Jul-20 101 01-Jul-20, Transition Piece
F2-JK2-JF10-10Fabrication of Can Transition Piece Barrel 24 02-May-20 30-May-20 52 30-May-20, Fabrication of Can Transition Piece Barrel
F2-JK2-JF10-100Fit Grating Supports 4 04-May-20 08-May-20 118 08-May-20, Fit Grating Supports
F2-JK2-JF10-101Fab Main Deck Handrails 4 28-Apr-20 01-May-20 119 01-May-20, Fab Main Deck Handrails
F2-JK2-JF10-102Fab Padeye inc Top of Jacket 4 29-Apr-20 02-May-20 145 02-May-20, Fab Padeye inc Top of Jacket
F2-JK2-JF10-103Blast and Paint Transition Piece 7 23-Jun-20 01-Jul-20 101 01-Jul-20, Blast and Paint Transition Piece
F2-JK2-JF10-11 Fabrication of Strut Plate 18 21-Apr-20 12-May-20 68 12-May-20, Fabrication of Strut Plate
F2-JK2-JF10-12Fabrication of Internal Platform 21 21-Apr-20 15-May-20 130 15-May-20, Fabrication of Internal Platform
F2-JK2-JF10-13Fabrication of External Platform 25 21-Apr-20 20-May-20 130 20-May-20, Fabrication of External Platform
F2-JK2-JF10-14Assembly Strut Plate 21 12-May-20 05-Jun-20 116 05-Jun-20, Assembly Strut Plate
F2-JK2-JF10-15Fabrication of Ring Stiffener 21 29-May-20 23-Jun-20 101 23-Jun-20, Fabrication of Ring Stiffener

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 45 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF10-16Fabrication of Crane Pedestal 21 12-May-20 05-Jun-20 94 05-Jun-20, Fabrication of Crane Pedestal
F2-JK2-JF10-93Galvanizing Handrails 5 01-May-20 07-May-20 119 07-May-20, Galvanizing Handrails
F2-JK2-JF10-94Erect Deck Plate Areas 5 29-Apr-20 04-May-20 117 04-May-20, Erect Deck Plate Areas
F2-JK2-JF10-95Transition Piece Fabrication Complete 0 23-Jun-20 101 23-Jun-20
F2-JK2-JF10-96Fabrication Assemble Walkways / Platforms 21 12-May-20 05-Jun-20 116 05-Jun-20, Fabrication Assemble Walkways / Platforms
F2-JK2-JF10-97Fit and Weld TP's Equipment Supports 5 29-Apr-20 06-May-20 117 06-May-20, Fit and Weld TP's Equipment Supports
F2-JK2-JF10-98Plate Profiling for Main Deck 5 21-Apr-20 28-Apr-20 72 28-Apr-20, Plate Profiling for Main Deck
F2-JK2-JF10-99Fab Main Deck Main Steel 5 23-Apr-20 29-Apr-20 72 29-Apr-20, Fab Main Deck Main Steel
Lifting Trunnion 7 29-Apr-20 07-May-20 72 07-May-20, Lifting Trunnion
F2-JK2-JF10-104Fabricate Lifting Trunion 7 29-Apr-20 07-May-20 72 07-May-20, Fabricate Lifting Trunion
Boat Landing 44 02-May-20 24-Jun-20 97 24-Jun-20, Boat Landing
F2-JK2-JF10-123Blast and Paint Boat Landing 5 17-Jun-20 24-Jun-20 97 24-Jun-20, Blast and Paint Boat Landing
F2-JK2-JF10-124Fabricate Boat Landing 21 02-May-20 27-May-20 97 27-May-20, Fabricate Boat Landing
F2-JK2-JF10-159Fabricate Boat Landing Access platform 24 20-May-20 17-Jun-20 97 17-Jun-20, Fabricate Boat Landing Access platform
F2-JK2-JF10-160Fabricate Boat Landing Ladders 15 28-May-20 15-Jun-20 99 15-Jun-20, Fabricate Boat Landing Ladders
Grouting Line 23 05-Jun-20 02-Jul-20 94 02-Jul-20, Grouting Line
F2-JK2-JF10-126Fabricate Grouting Line & Grouting Line Support 23 05-Jun-20 02-Jul-20 94 02-Jul-20, Fabricate Grouting Line & Grouting Line Support
Assembly 105 07-May-20 05-Sep-20 53 05-Sep-20, Assembly
Row Assembly 88 07-May-20 18-Aug-20 65 18-Aug-20, Row Assembly
F2-JK2-JF10-113Fabricate Upper Grillage & Truss Support 18 07-May-20 28-May-20 72 28-May-20, Fabricate Upper Grillage & Truss Support
F2-JK2-JF10-114Layout Concrete Blocks/ Grillages and Truss Support Steel 4 05-Jun-20 11-Jun-20 65 11-Jun-20, Layout Concrete Blocks/ Grillages and Truss Support Steel
Row-1 & 2 (Upper Jacket) Assembly 46 11-Jun-20 04-Aug-20 65 04-Aug-20, Row-1 & 2 (Upper Jacket) Assembly
F2-JK2-JF10-115
Installation of Grouting Line 1 29-Jun-20 30-Jun-20 85 30-Jun-20, Installation of Grouting Line
F2-JK2-JF10-117
Installation of J-Tube At Row-1B & 2A 5 29-Jun-20 04-Jul-20 89 04-Jul-20, Installation of J-Tube At Row-1B & 2A
F2-JK2-JF10-118
Row-2 - Touch Up, 2nd Coat & Top Coat 3 31-Jul-20 03-Aug-20 65 03-Aug-20, Row-2 - Touch Up, 2nd Coat & Top Coat
F2-JK2-JF10-119
Installation of Row-1B & 2B X-Brace 7 20-Jun-20 29-Jun-20 65 29-Jun-20, Installation of Row-1B & 2B X-Brace
F2-JK2-JF10-120
Installation of Leg 1A & 1B Onto Support 1 11-Jun-20 12-Jun-20 65 12-Jun-20, Installation of Leg 1A & 1B Onto Support
F2-JK2-JF10-121
Installation of Row-1A & 1B X-Brace 7 12-Jun-20 20-Jun-20 65 20-Jun-20, Installation of Row-1A & 1B X-Brace
F2-JK2-JF10-122
Installation of Row-2A & 2B X-Brace in Final Position 7 23-Jul-20 31-Jul-20 65 31-Jul-20, Installation of Row-2A & 2B X-Brace in Final Position
F2-JK2-JF10-142
Installation of Leg 2A & 2B Onto Support 1 11-Jun-20 12-Jun-20 72 12-Jun-20, Installation of Leg 2A & 2B Onto Support
F2-JK2-JF10-143
Installation of Row-1A & 2A X-Brace 7 20-Jun-20 29-Jun-20 65 29-Jun-20, Installation of Row-1A & 2A X-Brace
F2-JK2-JF10-144
Installation of Row-1A & 1B X-Brace in Final Position 7 15-Jul-20 23-Jul-20 65 23-Jul-20, Installation of Row-1A & 1B X-Brace in Final Position
F2-JK2-JF10-145
Roll Up X-Brace Row A&B to Final Position 7 29-Jun-20 07-Jul-20 65 07-Jul-20, Roll Up X-Brace Row A&B to Final Position
F2-JK2-JF10-146
Installing Tie-back for Fastener 7 07-Jul-20 15-Jul-20 65 15-Jul-20, Installing Tie-back for Fastener
F2-JK2-JF10-147
Installation of Boat Landing 3 31-Jul-20 04-Aug-20 65 04-Aug-20, Installation of Boat Landing
Row-1 & 2 (Lower Jacket) Assembly 44 08-Jun-20 28-Jul-20 70 28-Jul-20, Row-1 & 2 (Lower Jacket) Assembly
F2-JK2-JF10-116
Installation of Pile Stopper 4 08-Jul-20 11-Jul-20 70 11-Jul-20, Installation of Pile Stopper
F2-JK2-JF10-148
Installation of Grouting Line 1 25-Jun-20 26-Jun-20 91 26-Jun-20, Installation of Grouting Line
F2-JK2-JF10-149
Installation of J-Tube At Row-1B & 2A 5 25-Jun-20 01-Jul-20 80 01-Jul-20, Installation of J-Tube At Row-1B & 2A
F2-JK2-JF10-150
Installation of Row-1B & 2B X-Brace 7 17-Jun-20 25-Jun-20 70 25-Jun-20, Installation of Row-1B & 2B X-Brace
F2-JK2-JF10-151
Installation of Leg 1A & 1B Onto Support 1 08-Jun-20 09-Jun-20 70 09-Jun-20, Installation of Leg 1A & 1B Onto Support
F2-JK2-JF10-152
Installation of Row-1A & 1B X-Brace 7 09-Jun-20 17-Jun-20 70 17-Jun-20, Installation of Row-1A & 1B X-Brace
F2-JK2-JF10-153
Installation of Row-2A & 2B X-Brace in Final Position 7 20-Jul-20 28-Jul-20 70 28-Jul-20, Installation of Row-2A & 2B X-Brace in Final Position
F2-JK2-JF10-154
Installation of Leg 2A & 2B Onto Support 1 08-Jun-20 09-Jun-20 77 09-Jun-20, Installation of Leg 2A & 2B Onto Support
F2-JK2-JF10-155
Installation of Row-1A & 2A X-Brace 7 17-Jun-20 25-Jun-20 70 25-Jun-20, Installation of Row-1A & 2A X-Brace
F2-JK2-JF10-156
Installation of Row-1A & 1B X-Brace in Final Position 7 11-Jul-20 20-Jul-20 70 20-Jul-20, Installation of Row-1A & 1B X-Brace in Final Position
F2-JK2-JF10-157
Roll Up X-Brace Row A&B to Final Position 7 25-Jun-20 03-Jul-20 70 03-Jul-20, Roll Up X-Brace Row A&B to Final Position
F2-JK2-JF10-158
Installing Tie-back for Fastener 4 03-Jul-20 08-Jul-20 70 08-Jul-20, Installing Tie-back for Fastener
Grouting Line 40 02-Jul-20 18-Aug-20 65 18-Aug-20, Grouting Line
F2-JK2-JF10-125
Installation Of Grouting Line 5 12-Aug-20 18-Aug-20 65 18-Aug-20, Installation Of Grouting Line
F2-JK2-JF10-127
Installation Grouting Line Support 7 02-Jul-20 10-Jul-20 94 10-Jul-20, Installation Grouting Line Support
Row Roll Up 7 04-Aug-20 12-Aug-20 65 12-Aug-20, Row Roll Up
F2-JK2-JF10-105Roll Up Of Lower Jacket To Final Position 2 04-Aug-20 06-Aug-20 65 06-Aug-20, Roll Up Of Lower Jacket To Final Position
F2-JK2-JF10-106Roll Up Of Upper Jacket To Final Position 5 06-Aug-20 12-Aug-20 65 12-Aug-20, Roll Up Of Upper Jacket To Final Position
Transition Piece (TP) 76 30-May-20 27-Aug-20 52 27-Aug-20, Transition Piece (TP)

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 46 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF10-1 Install Door Platform 10 23-Jun-20 04-Jul-20 81 04-Jul-20, Install Door Platform
F2-JK2-JF10-17Installation & Assembly of Ring Stiffener 21 25-Jun-20 20-Jul-20 52 20-Jul-20, Installation & Assembly of Ring Stiffener
F2-JK2-JF10-18Installation of Transition Piece Flange 15 03-Jul-20 21-Jul-20 52 21-Jul-20, Installation of Transition Piece Flange
F2-JK2-JF10-19Install Crane Pedestal 12 05-Jun-20 19-Jun-20 94 19-Jun-20, Install Crane Pedestal
F2-JK2-JF10-2 Blasting & Painting 10 07-Aug-20 19-Aug-20 52 19-Aug-20, Blasting & Painting
F2-JK2-JF10-3 Assemble Can Transition Piece Barrel to Main Deck 15 30-May-20 17-Jun-20 52 17-Jun-20, Assemble Can Transition Piece Barrel to Main Deck
F2-JK2-JF10-4 Install Platform & Internal Structure into Upper Can 7 19-Aug-20 27-Aug-20 52 27-Aug-20, Install Platform & Internal Structure into Upper Can
F2-JK2-JF10-5 Door opening & Installation of Door frame 5 17-Jun-20 23-Jun-20 91 23-Jun-20, Door opening & Installation of Door frame
F2-JK2-JF10-6 Installation & Assembly of Strut 15 17-Jun-20 04-Jul-20 52 04-Jul-20, Installation & Assembly of Strut
F2-JK2-JF10-7 Install Free-Issued Items 15 21-Jul-20 07-Aug-20 52 07-Aug-20, Install Free-Issued Items
F2-JK2-JF10-8 Install Architectural items, Electrical & Instrument Equipments 15 17-Jun-20 04-Jul-20 81 04-Jul-20, Install Architectural items, Electrical & Instrument Equipments
F2-JK2-JF10-9 Install External Platform & Handrail 12 20-Jun-20 04-Jul-20 81 04-Jul-20, Install External Platform & Handrail
Final Assembly 8 27-Aug-20 05-Sep-20 53 05-Sep-20, Final Assembly
F2-JK2-JF10-107Installation of Transition Piece 3 27-Aug-20 31-Aug-20 52 31-Aug-20, Installation of Transition Piece
F2-JK2-JF10-108Installation of Mudmad Plate 5 29-Aug-20 04-Sep-20 52 04-Sep-20, Installation of Mudmad Plate
F2-JK2-JF10-109Installation of Lifting Trunnion 4 31-Aug-20 04-Sep-20 54 04-Sep-20, Installation of Lifting Trunnion
F2-JK2-JF10-110Installation of Skirt Pile Sleeve 2 29-Aug-20 01-Sep-20 52 01-Sep-20, Installation of Skirt Pile Sleeve
F2-JK2-JF10-111Final Touch Up Coating 3 02-Sep-20 05-Sep-20 52 05-Sep-20, Final Touch Up Coating
F2-JK2-JF10-112Installation of Lifting Slings 1 01-Sep-20 02-Sep-20 52 02-Sep-20, Installation of Lifting Slings
F2-JK2-JF10-161J acket Fabrication Completed 0 05-Sep-20 52 05-Sep-20
Testing & Commissioning 18 18-Aug-20 08-Sep-20 52 08-Sep-20, Testing & Commissioning
Grouting & Gripper Test 3 18-Aug-20 21-Aug-20 65 21-Aug-20, Grouting & Gripper Test
F2-JK2-JF10-20Gripper Test 2 19-Aug-20 21-Aug-20 65 21-Aug-20, Gripper Test
F2-JK2-JF10-21Grouting Test 1 18-Aug-20 19-Aug-20 65 19-Aug-20, Grouting Test
Mechanical Completion 2 05-Sep-20 08-Sep-20 52 08-Sep-20, Mechanical Completion
F2-JK2-JF10-22Main Structure, Boat Landing, J-Tube, Transition Piece 2 05-Sep-20 08-Sep-20 52 08-Sep-20, Main Structure, Boat Landing, J-Tube, Transition Piece
Jacket & Piles Ready For Loadout 0 08-Sep-20 08-Sep-20 52 08-Sep-20, Jacket & Piles Ready For Loadout
F2-JK2-JF10-23Jacket Ready For Load Out 0 08-Sep-20 52 08-Sep-20
LOT C - 5 Jacket Foundations 158 06-Apr-20 07-Oct-20 53 07-Oct-20, LOT C - 5 Jacket Foundations
Jacket Foundation 11a 130 06-Apr-20 04-Sep-20 55 04-Sep-20, Jacket Foundation 11a
Fabrication 72 06-Apr-20 29-Jun-20 103 29-Jun-20, Fabrication
Pre-Fabrication 38 06-Apr-20 20-May-20 104 20-May-20, Pre-Fabrication
F2-JK2-JF11-140Rolling of Can Transition Piece Flange 10 08-May-20 20-May-20 104 20-May-20, Rolling of Can Transition Piece Flange
F2-JK2-JF11-141Rolling of Can Transition Piece Barrel 10 17-Apr-20 29-Apr-20 55 29-Apr-20, Rolling of Can Transition Piece Barrel
F2-JK2-JF11-24 Rolling of Can Row 2 Brace 10 06-Apr-20 17-Apr-20 0 17-Apr-20, Rolling of Can Row 2 Brace
F2-JK2-JF11-25 Rolling of Can Leg 1A & 1B 10 06-Apr-20 17-Apr-20 68 17-Apr-20, Rolling of Can Leg 1A & 1B
F2-JK2-JF11-26 Rolling of Can Leg 2A & 2B 10 14-Apr-20 25-Apr-20 68 25-Apr-20, Rolling of Can Leg 2A & 2B
F2-JK2-JF11-27 Rolling of Node Can Row 1 10 14-Apr-20 25-Apr-20 68 25-Apr-20, Rolling of Node Can Row 1
F2-JK2-JF11-28 Rolling of Node Can Row 2 10 22-Apr-20 04-May-20 68 04-May-20, Rolling of Node Can Row 2
F2-JK2-JF11-29 Rolling of Can Row 1 Brace 10 22-Apr-20 04-May-20 68 04-May-20, Rolling of Can Row 1 Brace
F2-JK2-JF11-30 Rolling of J-Tubes & J-Tubes Support 10 30-Apr-20 12-May-20 69 12-May-20, Rolling of J-Tubes & J-Tubes Support
F2-JK2-JF11-31 Rolling of Can Plan Level Tubular 10 30-Apr-20 12-May-20 104 12-May-20, Rolling of Can Plan Level Tubular
F2-JK2-JF11-32 Rolling of Can Top Bay X-Brace 10 08-May-20 20-May-20 104 20-May-20, Rolling of Can Top Bay X-Brace
Row 1 Fabrication 42 17-Apr-20 05-Jun-20 109 05-Jun-20, Row 1 Fabrication
Legs 40 17-Apr-20 04-Jun-20 71 04-Jun-20, Legs
F2-JK2-JF11-40
Install Stubs on to Leg 1A & 1B Nodes 2 25-May-20 27-May-20 68 27-May-20, Install Stubs on to Leg 1A & 1B Nodes
F2-JK2-JF11-41
Install Anodes on Row-1 Legs 4 26-May-20 30-May-20 70 30-May-20, Install Anodes on Row-1 Legs
F2-JK2-JF11-42
Join of Can Legs 1A 9 22-Apr-20 02-May-20 83 02-May-20, Join of Can Legs 1A
F2-JK2-JF11-43
Join of Can Legs 1B 9 22-Apr-20 02-May-20 83 02-May-20, Join of Can Legs 1B
F2-JK2-JF11-44
Mark and Profile Leg 1A & 1B Node 4 25-Apr-20 30-Apr-20 93 30-Apr-20, Mark and Profile Leg 1A & 1B Node
F2-JK2-JF11-45
Profilling of Legs 1A & 1B (Inc. Cones) 4 17-Apr-20 22-Apr-20 83 22-Apr-20, Profilling of Legs 1A & 1B (Inc. Cones)
F2-JK2-JF11-46
Join of Leg 1A & 1B Node 2 26-May-20 28-May-20 71 28-May-20, Join of Leg 1A & 1B Node
F2-JK2-JF11-47
Blasting and Painting for Leg 1A & 1B Node 5 28-May-20 04-Jun-20 71 04-Jun-20, Blasting and Painting for Leg 1A & 1B Node
F2-JK2-JF11-48
Assembly Leg 1A 3 23-May-20 26-May-20 68 26-May-20, Assembly Leg 1A
F2-JK2-JF11-49
Assembly Leg 1B 3 23-May-20 26-May-20 68 26-May-20, Assembly Leg 1B

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 47 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
Braces 28 04-May-20 05-Jun-20 68 05-Jun-20, Braces
F2-JK2-JF11-50
Fit & Weld Top X Brace Between Legs 1A & 1B 5 27-May-20 02-Jun-20 68 02-Jun-20, Fit & Weld Top X Brace Between Legs 1A & 1B
F2-JK2-JF11-51
Join of Row-1 Can Brace (Inc. Stub) 13 08-May-20 23-May-20 68 23-May-20, Join of Row-1 Can Brace (Inc. Stub)
F2-JK2-JF11-52
Join of Can Brace for Between Row 1 & 2 (Inc. Stub) 13 08-May-20 23-May-20 68 23-May-20, Join of Can Brace for Between Row 1 & 2 (Inc. Stub)
F2-JK2-JF11-53
Assembly of Row-1 Top Brace 4 23-May-20 27-May-20 68 27-May-20, Assembly of Row-1 Top Brace
F2-JK2-JF11-54
Fit & Weld Row-2 K-Brace (Inc. Vertical Braces) 5 27-May-20 02-Jun-20 68 02-Jun-20, Fit & Weld Row-2 K-Brace (Inc. Vertical Braces)
F2-JK2-JF11-55
Assembly of Row-1 K-Brace 4 23-May-20 27-May-20 68 27-May-20, Assembly of Row-1 K-Brace
F2-JK2-JF11-56
Fit & Weld X-Brace Between Row 1 & 2 5 27-May-20 02-Jun-20 68 02-Jun-20, Fit & Weld X-Brace Between Row 1 & 2
F2-JK2-JF11-57
Assembly of Brace Between Row 1 & 2 4 23-May-20 27-May-20 68 27-May-20, Assembly of Brace Between Row 1 & 2
F2-JK2-JF11-58
Profilling of Row-1 Braces and Stubs 4 04-May-20 08-May-20 68 08-May-20, Profilling of Row-1 Braces and Stubs
F2-JK2-JF11-59
Install Anodes on Row-1 Braces 4 02-Jun-20 05-Jun-20 68 05-Jun-20, Install Anodes on Row-1 Braces
J-Tubes 19 12-May-20 03-Jun-20 111 03-Jun-20, J-Tubes
F2-JK2-JF11-60
Join of Row-1 J-Tubes 5 16-May-20 22-May-20 111 22-May-20, Join of Row-1 J-Tubes
F2-JK2-JF11-61
Profilling of Row-1 J-Tubes 4 12-May-20 16-May-20 111 16-May-20, Profilling of Row-1 J-Tubes
F2-JK2-JF11-62
Bending of Row-1 J-Tubes 4 22-May-20 26-May-20 111 26-May-20, Bending of Row-1 J-Tubes
F2-JK2-JF11-63
Blast and Paint for Row-1 J-Tubes 3 26-May-20 30-May-20 111 30-May-20, Blast and Paint for Row-1 J-Tubes
F2-JK2-JF11-64
Assembly Row-1 J-Tubes 3 30-May-20 03-Jun-20 111 03-Jun-20, Assembly Row-1 J-Tubes
F2-JK2-JF11-65
Cut and Profile Row-1 J-Tubes Support 4 12-May-20 16-May-20 111 16-May-20, Cut and Profile Row-1 J-Tubes Support
F2-JK2-JF11-66
Assembly Row-1 J-Tubes Support 2 16-May-20 20-May-20 111 20-May-20, Assembly Row-1 J-Tubes Support
F2-JK2-JF11-67
Paint Row-1 J-Tubes Support 3 20-May-20 23-May-20 111 23-May-20, Paint Row-1 J-Tubes Support
F2-JK2-JF11-68
Install J-Tubes Support on to Row-1 J-Tubes 3 23-May-20 26-May-20 111 26-May-20, Install J-Tubes Support on to Row-1 J-Tubes
Common 23 11-May-20 05-Jun-20 69 05-Jun-20, Common
Structure 3 11-May-20 14-May-20 76 14-May-20, Structure
F2-JK2-JF11-33
Marking & Cutting of Leg and Brace Node 3 11-May-20 14-May-20 76 14-May-20, Marking & Cutting of Leg and Brace Node
F2-JK2-JF11-34
Marking & Cutting of Brace Stub 3 11-May-20 14-May-20 76 14-May-20, Marking & Cutting of Brace Stub
F2-JK2-JF11-35
Marking & Cutting of Leg and Brace Member 3 11-May-20 14-May-20 76 14-May-20, Marking & Cutting of Leg and Brace Member
Final Painting 23 11-May-20 05-Jun-20 69 05-Jun-20, Final Painting
F2-JK2-JF11-36
Blast and Paint Leg and Brace (Initial Paint) 11 11-May-20 23-May-20 68 23-May-20, Blast and Paint Leg and Brace (Initial Paint)
F2-JK2-JF11-37
Build Painting Habitat Protection 1 02-Jun-20 04-Jun-20 71 04-Jun-20, Build Painting Habitat Protection
F2-JK2-JF11-38
Row-1 Ready for Assembly & Roll-up 0 04-Jun-20 71 04-Jun-20
F2-JK2-JF11-39
Row-1 Touch up and Final Painting 3 02-Jun-20 05-Jun-20 68 05-Jun-20, Row-1 Touch up and Final Painting
Row 2 Fabrication 42 17-Apr-20 05-Jun-20 69 05-Jun-20, Row 2 Fabrication
Legs 23 25-Apr-20 22-May-20 82 22-May-20, Legs
F2-JK2-JF11-76
Install Anodes on Row-2 Legs 4 13-May-20 18-May-20 81 18-May-20, Install Anodes on Row-2 Legs
F2-JK2-JF11-77
Join of Can Legs 2A 9 30-Apr-20 11-May-20 76 11-May-20, Join of Can Legs 2A
F2-JK2-JF11-78
Join of Can Legs 2B 9 30-Apr-20 11-May-20 76 11-May-20, Join of Can Legs 2B
F2-JK2-JF11-79
Profilling of Legs 2A & 2B (Inc. Cones) 4 25-Apr-20 30-Apr-20 76 30-Apr-20, Profilling of Legs 2A & 2B (Inc. Cones)
F2-JK2-JF11-80
Mark and Profile Leg 2A & 2B Node 4 04-May-20 08-May-20 86 08-May-20, Mark and Profile Leg 2A & 2B Node
F2-JK2-JF11-81
Join of Leg 2A & 2B Node 2 13-May-20 15-May-20 82 15-May-20, Join of Leg 2A & 2B Node
F2-JK2-JF11-82
Blasting and Painting for Leg 2A & 2B Node (Initial) 5 15-May-20 22-May-20 82 22-May-20, Blasting and Painting for Leg 2A & 2B Node (Initial)
F2-JK2-JF11-83
Assembly Leg 2A 3 11-May-20 13-May-20 74 13-May-20, Assembly Leg 2A
F2-JK2-JF11-84
Assembly Leg 2B 3 11-May-20 13-May-20 74 13-May-20, Assembly Leg 2B
F2-JK2-JF11-85
Install Stubs on to Leg 2A & 2B Nodes 2 13-May-20 15-May-20 74 15-May-20, Install Stubs on to Leg 2A & 2B Nodes
Braces 32 17-Apr-20 25-May-20 74 25-May-20, Braces
F2-JK2-JF11-138
Fit & Weld Row-2 K-Brace (Inc. Vertical Braces) 5 15-May-20 21-May-20 74 21-May-20, Fit & Weld Row-2 K-Brace (Inc. Vertical Braces)
F2-JK2-JF11-139
Assembly of Row-2 K-Brace 4 11-May-20 14-May-20 75 14-May-20, Assembly of Row-2 K-Brace
F2-JK2-JF11-86
Fit & Weld Top X-Brace Between Legs 2A & 2B 4 15-May-20 20-May-20 77 20-May-20, Fit & Weld Top X-Brace Between Legs 2A & 2B
F2-JK2-JF11-87
Fit & Weld Mid X-Brace Between Legs 2A & 2B 4 15-May-20 20-May-20 77 20-May-20, Fit & Weld Mid X-Brace Between Legs 2A & 2B
F2-JK2-JF11-88
Join of Row-2 Can Brace (Inc. Stub) 10 22-Apr-20 04-May-20 74 04-May-20, Join of Row-2 Can Brace (Inc. Stub)
F2-JK2-JF11-89
Assembly of Row-2 Top Brace 3 11-May-20 14-May-20 78 14-May-20, Assembly of Row-2 Top Brace
F2-JK2-JF11-90
Assembly of Row-2 Mid Brace 3 11-May-20 14-May-20 78 14-May-20, Assembly of Row-2 Mid Brace
F2-JK2-JF11-91
Profilling of Row-2 Braces and Stubs 4 17-Apr-20 22-Apr-20 74 22-Apr-20, Profilling of Row-2 Braces and Stubs
F2-JK2-JF11-92
Install Anodes on Row-2 Braces 4 21-May-20 25-May-20 74 25-May-20, Install Anodes on Row-2 Braces
J-Tubes 21 12-May-20 05-Jun-20 69 05-Jun-20, J-Tubes
F2-JK2-JF11-128
Join of Row-2 J-Tubes 5 16-May-20 22-May-20 72 22-May-20, Join of Row-2 J-Tubes

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 48 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF11-129
Profilling of Row-2 J-Tubes 4 12-May-20 16-May-20 72 16-May-20, Profilling of Row-2 J-Tubes
F2-JK2-JF11-130
Bending of Row-2 J-Tubes 4 22-May-20 26-May-20 72 26-May-20, Bending of Row-2 J-Tubes
F2-JK2-JF11-131
Blast and Paint for Row-2 J-Tubes 3 29-May-20 02-Jun-20 69 02-Jun-20, Blast and Paint for Row-2 J-Tubes
F2-JK2-JF11-132
Assembly Row-2 J-Tubes 3 02-Jun-20 05-Jun-20 69 05-Jun-20, Assembly Row-2 J-Tubes
F2-JK2-JF11-133
Cut and Profile Row-2 J-Tubes Support 4 12-May-20 16-May-20 69 16-May-20, Cut and Profile Row-2 J-Tubes Support
F2-JK2-JF11-134
Assembly Row-2 J-Tubes Support 2 16-May-20 20-May-20 69 20-May-20, Assembly Row-2 J-Tubes Support
F2-JK2-JF11-135
Vulcanized Row-2 J-Tubes Support 2 20-May-20 22-May-20 69 22-May-20, Vulcanized Row-2 J-Tubes Support
F2-JK2-JF11-136
Paint Row-2 J-Tubes Support 3 22-May-20 26-May-20 69 26-May-20, Paint Row-2 J-Tubes Support
F2-JK2-JF11-137
Install J-Tubes Support on to Row-2 J-Tubes 3 26-May-20 29-May-20 69 29-May-20, Install J-Tubes Support on to Row-2 J-Tubes
Common 23 04-May-20 30-May-20 74 30-May-20, Common
Structure 3 04-May-20 07-May-20 78 07-May-20, Structure
F2-JK2-JF11-69
Marking & Cutting of Leg and Brace Node 3 04-May-20 07-May-20 78 07-May-20, Marking & Cutting of Leg and Brace Node
F2-JK2-JF11-70
Marking & Cutting of Brace Stub 3 04-May-20 07-May-20 78 07-May-20, Marking & Cutting of Brace Stub
F2-JK2-JF11-71
Marking & Cutting of Leg and Brace Member 3 04-May-20 07-May-20 78 07-May-20, Marking & Cutting of Leg and Brace Member
Final Painting 23 04-May-20 30-May-20 74 30-May-20, Final Painting
F2-JK2-JF11-72
Row-2 Touch up and Final Painting 3 25-May-20 29-May-20 74 29-May-20, Row-2 Touch up and Final Painting
F2-JK2-JF11-73
Blast and Paint Leg and Brace (Initial Paint) 5 04-May-20 11-May-20 74 11-May-20, Blast and Paint Leg and Brace (Initial Paint)
F2-JK2-JF11-74
Build Painting Habitat Protection 1 29-May-20 30-May-20 74 30-May-20, Build Painting Habitat Protection
F2-JK2-JF11-75
Row-2 Ready for Assembly & Roll-up 0 30-May-20 74 30-May-20
Transition Piece 61 17-Apr-20 27-Jun-20 104 27-Jun-20, Transition Piece
F2-JK2-JF11-10 Fabrication of Can Transition Piece Barrel 24 29-Apr-20 27-May-20 55 27-May-20, Fabrication of Can Transition Piece Barrel
F2-JK2-JF11-100Fit Grating Supports 4 30-Apr-20 05-May-20 121 05-May-20, Fit Grating Supports
F2-JK2-JF11-101Fab Main Deck Handrails 4 24-Apr-20 28-Apr-20 122 28-Apr-20, Fab Main Deck Handrails
F2-JK2-JF11-102Fab Padeye inc Top of Jacket 4 25-Apr-20 29-Apr-20 148 29-Apr-20, Fab Padeye inc Top of Jacket
F2-JK2-JF11-103Blast and Paint Transition Piece 7 19-Jun-20 27-Jun-20 104 27-Jun-20, Blast and Paint Transition Piece
F2-JK2-JF11-11 Fabrication of Strut Plate 18 17-Apr-20 08-May-20 16 08-May-20, Fabrication of Strut Plate
F2-JK2-JF11-12 Fabrication of Internal Platform 21 17-Apr-20 12-May-20 133 12-May-20, Fabrication of Internal Platform
F2-JK2-JF11-13 Fabrication of External Platform 25 17-Apr-20 16-May-20 133 16-May-20, Fabrication of External Platform
F2-JK2-JF11-14 Assembly Strut Plate 21 08-May-20 02-Jun-20 119 02-Jun-20, Assembly Strut Plate
F2-JK2-JF11-15 Fabrication of Ring Stiffener 21 26-May-20 19-Jun-20 104 19-Jun-20, Fabrication of Ring Stiffener
F2-JK2-JF11-16 Fabrication of Crane Pedestal 21 08-May-20 02-Jun-20 97 02-Jun-20, Fabrication of Crane Pedestal
F2-JK2-JF11-93 Galvanizing Handrails 5 28-Apr-20 04-May-20 122 04-May-20, Galvanizing Handrails
F2-JK2-JF11-94 Erect Deck Plate Areas 5 25-Apr-20 30-Apr-20 120 30-Apr-20, Erect Deck Plate Areas
F2-JK2-JF11-95 Transition Piece Fabrication Complete 0 19-Jun-20 104 19-Jun-20
F2-JK2-JF11-96 Fabrication Assemble Walkways / Platforms 21 08-May-20 02-Jun-20 119 02-Jun-20, Fabrication Assemble Walkways / Platforms
F2-JK2-JF11-97 Fit and Weld TP's Equipment Supports 5 25-Apr-20 02-May-20 120 02-May-20, Fit and Weld TP's Equipment Supports
F2-JK2-JF11-98 Plate Profiling for Main Deck 5 17-Apr-20 24-Apr-20 75 24-Apr-20, Plate Profiling for Main Deck
F2-JK2-JF11-99 Fab Main Deck Main Steel 5 20-Apr-20 25-Apr-20 75 25-Apr-20, Fab Main Deck Main Steel
Lifting Trunnion 7 25-Apr-20 04-May-20 75 04-May-20, Lifting Trunnion
F2-JK2-JF11-104Fabricate Lifting Trunion 7 25-Apr-20 04-May-20 75 04-May-20, Fabricate Lifting Trunion
Boat Landing 44 29-Apr-20 20-Jun-20 100 20-Jun-20, Boat Landing
F2-JK2-JF11-123Blast and Paint Boat Landing 5 13-Jun-20 20-Jun-20 100 20-Jun-20, Blast and Paint Boat Landing
F2-JK2-JF11-124Fabricate Boat Landing 21 29-Apr-20 23-May-20 45 23-May-20, Fabricate Boat Landing
F2-JK2-JF11-159Fabricate Boat Landing Access platform 24 16-May-20 13-Jun-20 100 13-Jun-20, Fabricate Boat Landing Access platform
F2-JK2-JF11-160Fabricate Boat Landing Ladders 15 25-May-20 11-Jun-20 102 11-Jun-20, Fabricate Boat Landing Ladders
Grouting Line 23 02-Jun-20 29-Jun-20 97 29-Jun-20, Grouting Line
F2-JK2-JF11-126Fabricate Grouting Line & Grouting Line Support 23 02-Jun-20 29-Jun-20 97 29-Jun-20, Fabricate Grouting Line & Grouting Line Support
Assembly 105 04-May-20 02-Sep-20 56 02-Sep-20, Assembly
Row Assembly 88 04-May-20 14-Aug-20 68 14-Aug-20, Row Assembly
F2-JK2-JF11-113Fabricate Upper Grillage & Truss Support 18 04-May-20 25-May-20 75 25-May-20, Fabricate Upper Grillage & Truss Support
F2-JK2-JF11-114Layout Concrete Blocks/ Grillages and Truss Support Steel 4 02-Jun-20 08-Jun-20 68 08-Jun-20, Layout Concrete Blocks/ Grillages and Truss Support Steel
Row-1 & 2 (Upper Jacket) Assembly 46 08-Jun-20 31-Jul-20 68 31-Jul-20, Row-1 & 2 (Upper Jacket) Assembly
F2-JK2-JF11-115
Installation of Grouting Line 1 25-Jun-20 26-Jun-20 88 26-Jun-20, Installation of Grouting Line
F2-JK2-JF11-117
Installation of J-Tube At Row-1B & 2A 5 25-Jun-20 01-Jul-20 92 01-Jul-20, Installation of J-Tube At Row-1B & 2A
F2-JK2-JF11-118
Row-2 - Touch Up, 2nd Coat & Top Coat 3 28-Jul-20 30-Jul-20 68 30-Jul-20, Row-2 - Touch Up, 2nd Coat & Top Coat

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 49 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF11-119
Installation of Row-1B & 2B X-Brace 7 17-Jun-20 25-Jun-20 68 25-Jun-20, Installation of Row-1B & 2B X-Brace
F2-JK2-JF11-120
Installation of Leg 1A & 1B Onto Support 1 08-Jun-20 09-Jun-20 68 09-Jun-20, Installation of Leg 1A & 1B Onto Support
F2-JK2-JF11-121
Installation of Row-1A & 1B X-Brace 7 09-Jun-20 17-Jun-20 68 17-Jun-20, Installation of Row-1A & 1B X-Brace
F2-JK2-JF11-122
Installation of Row-2A & 2B X-Brace in Final Position 7 20-Jul-20 28-Jul-20 68 28-Jul-20, Installation of Row-2A & 2B X-Brace in Final Position
F2-JK2-JF11-142
Installation of Leg 2A & 2B Onto Support 1 08-Jun-20 09-Jun-20 75 09-Jun-20, Installation of Leg 2A & 2B Onto Support
F2-JK2-JF11-143
Installation of Row-1A & 2A X-Brace 7 17-Jun-20 25-Jun-20 68 25-Jun-20, Installation of Row-1A & 2A X-Brace
F2-JK2-JF11-144
Installation of Row-1A & 1B X-Brace in Final Position 7 11-Jul-20 20-Jul-20 68 20-Jul-20, Installation of Row-1A & 1B X-Brace in Final Position
F2-JK2-JF11-145
Roll Up X-Brace Row A&B to Final Position 7 25-Jun-20 03-Jul-20 68 03-Jul-20, Roll Up X-Brace Row A&B to Final Position
F2-JK2-JF11-146
Installing Tie-back for Fastener 7 03-Jul-20 11-Jul-20 68 11-Jul-20, Installing Tie-back for Fastener
F2-JK2-JF11-147
Installation of Boat Landing 3 28-Jul-20 31-Jul-20 68 31-Jul-20, Installation of Boat Landing
Row-1 & 2 (Lower Jacket) Assembly 44 04-Jun-20 24-Jul-20 73 24-Jul-20, Row-1 & 2 (Lower Jacket) Assembly
F2-JK2-JF11-116
Installation of Pile Stopper 4 04-Jul-20 08-Jul-20 73 08-Jul-20, Installation of Pile Stopper
F2-JK2-JF11-148
Installation of Grouting Line 1 22-Jun-20 23-Jun-20 94 23-Jun-20, Installation of Grouting Line
F2-JK2-JF11-149
Installation of J-Tube At Row-1B & 2A 5 22-Jun-20 27-Jun-20 83 27-Jun-20, Installation of J-Tube At Row-1B & 2A
F2-JK2-JF11-150
Installation of Row-1B & 2B X-Brace 7 13-Jun-20 22-Jun-20 73 22-Jun-20, Installation of Row-1B & 2B X-Brace
F2-JK2-JF11-151
Installation of Leg 1A & 1B Onto Support 1 04-Jun-20 05-Jun-20 73 05-Jun-20, Installation of Leg 1A & 1B Onto Support
F2-JK2-JF11-152
Installation of Row-1A & 1B X-Brace 7 05-Jun-20 13-Jun-20 73 13-Jun-20, Installation of Row-1A & 1B X-Brace
F2-JK2-JF11-153
Installation of Row-2A & 2B X-Brace in Final Position 7 16-Jul-20 24-Jul-20 73 24-Jul-20, Installation of Row-2A & 2B X-Brace in Final Position
F2-JK2-JF11-154
Installation of Leg 2A & 2B Onto Support 1 04-Jun-20 05-Jun-20 80 05-Jun-20, Installation of Leg 2A & 2B Onto Support
F2-JK2-JF11-155
Installation of Row-1A & 2A X-Brace 7 13-Jun-20 22-Jun-20 73 22-Jun-20, Installation of Row-1A & 2A X-Brace
F2-JK2-JF11-156
Installation of Row-1A & 1B X-Brace in Final Position 7 08-Jul-20 16-Jul-20 73 16-Jul-20, Installation of Row-1A & 1B X-Brace in Final Position
F2-JK2-JF11-157
Roll Up X-Brace Row A&B to Final Position 7 22-Jun-20 30-Jun-20 73 30-Jun-20, Roll Up X-Brace Row A&B to Final Position
F2-JK2-JF11-158
Installing Tie-back for Fastener 4 30-Jun-20 04-Jul-20 73 04-Jul-20, Installing Tie-back for Fastener
Grouting Line 40 29-Jun-20 14-Aug-20 68 14-Aug-20, Grouting Line
F2-JK2-JF11-125
Installation Of Grouting Line 5 08-Aug-20 14-Aug-20 68 14-Aug-20, Installation Of Grouting Line
F2-JK2-JF11-127
Installation Grouting Line Support 7 29-Jun-20 07-Jul-20 97 07-Jul-20, Installation Grouting Line Support
Row Roll Up 7 31-Jul-20 08-Aug-20 68 08-Aug-20, Row Roll Up
F2-JK2-JF11-105Roll Up Of Lower Jacket To Final Position 2 31-Jul-20 03-Aug-20 68 03-Aug-20, Roll Up Of Lower Jacket To Final Position
F2-JK2-JF11-106Roll Up Of Upper Jacket To Final Position 5 03-Aug-20 08-Aug-20 68 08-Aug-20, Roll Up Of Upper Jacket To Final Position
Transition Piece (TP) 76 27-May-20 24-Aug-20 55 24-Aug-20, Transition Piece (TP)
F2-JK2-JF11-1 Install Door Platform 10 19-Jun-20 01-Jul-20 84 01-Jul-20, Install Door Platform
F2-JK2-JF11-17 Installation & Assembly of Ring Stiffener 21 22-Jun-20 16-Jul-20 55 16-Jul-20, Installation & Assembly of Ring Stiffener
F2-JK2-JF11-18 Installation of Transition Piece Flange 15 30-Jun-20 17-Jul-20 55 17-Jul-20, Installation of Transition Piece Flange
F2-JK2-JF11-19 Install Crane Pedestal 12 02-Jun-20 16-Jun-20 97 16-Jun-20, Install Crane Pedestal
F2-JK2-JF11-2 Blasting & Painting 10 04-Aug-20 15-Aug-20 55 15-Aug-20, Blasting & Painting
F2-JK2-JF11-3 Assemble Can Transition Piece Barrel to Main Deck 15 27-May-20 13-Jun-20 55 13-Jun-20, Assemble Can Transition Piece Barrel to Main Deck
F2-JK2-JF11-4 Install Platform & Internal Structure into Upper Can 7 15-Aug-20 24-Aug-20 55 24-Aug-20, Install Platform & Internal Structure into Upper Can
F2-JK2-JF11-5 Door opening & Installation of Door frame 5 13-Jun-20 19-Jun-20 94 19-Jun-20, Door opening & Installation of Door frame
F2-JK2-JF11-6 Installation & Assembly of Strut 15 13-Jun-20 01-Jul-20 55 01-Jul-20, Installation & Assembly of Strut
F2-JK2-JF11-7 Install Free-Issued Items 15 17-Jul-20 04-Aug-20 55 04-Aug-20, Install Free-Issued Items
F2-JK2-JF11-8 Install Architectural items, Electrical & Instrument Equipments 15 13-Jun-20 01-Jul-20 84 01-Jul-20, Install Architectural items, Electrical & Instrument Equipments
F2-JK2-JF11-9 Install External Platform & Handrail 12 17-Jun-20 01-Jul-20 84 01-Jul-20, Install External Platform & Handrail
Final Assembly 8 24-Aug-20 02-Sep-20 56 02-Sep-20, Final Assembly
F2-JK2-JF11-107Installation of Transition Piece 3 24-Aug-20 27-Aug-20 55 27-Aug-20, Installation of Transition Piece
F2-JK2-JF11-108Installation of Mudmad Plate 5 26-Aug-20 01-Sep-20 55 01-Sep-20, Installation of Mudmad Plate
F2-JK2-JF11-109Installation of Lifting Trunnion 4 27-Aug-20 01-Sep-20 57 01-Sep-20, Installation of Lifting Trunnion
F2-JK2-JF11-110Installation of Skirt Pile Sleeve 2 26-Aug-20 28-Aug-20 55 28-Aug-20, Installation of Skirt Pile Sleeve
F2-JK2-JF11-111Final Touch Up Coating 3 29-Aug-20 02-Sep-20 55 02-Sep-20, Final Touch Up Coating
F2-JK2-JF11-112Installation of Lifting Slings 1 28-Aug-20 29-Aug-20 55 29-Aug-20, Installation of Lifting Slings
F2-JK2-JF11-161Jacket Fabrication Completed 0 02-Sep-20 55 02-Sep-20
Testing & Commissioning 18 14-Aug-20 04-Sep-20 55 04-Sep-20, Testing & Commissioning
Grouting & Gripper Test 3 14-Aug-20 18-Aug-20 68 18-Aug-20, Grouting & Gripper Test
F2-JK2-JF11-20 Gripper Test 2 15-Aug-20 18-Aug-20 68 18-Aug-20, Gripper Test
F2-JK2-JF11-21 Grouting Test 1 14-Aug-20 15-Aug-20 68 15-Aug-20, Grouting Test
Mechanical Completion 2 02-Sep-20 04-Sep-20 55 04-Sep-20, Mechanical Completion

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 50 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF11-22 Main Structure, Boat Landing, J-Tube, Transition Piece 2 02-Sep-20 04-Sep-20 55 04-Sep-20, Main Structure, Boat Landing, J-Tube, Transition Piece
Jacket & Piles Ready For Loadout 0 04-Sep-20 04-Sep-20 55 04-Sep-20, Jacket & Piles Ready For Loadout
F2-JK2-JF11-23 Jacket Ready For Load Out 0 04-Sep-20 55 04-Sep-20
Jacket Foundation 12a 130 14-Apr-20 12-Sep-20 0 12-Sep-20, Jacket Foundation 12a
Fabrication 72 14-Apr-20 07-Jul-20 48 07-Jul-20, Fabrication
Pre-Fabrication 38 14-Apr-20 28-May-20 49 28-May-20, Pre-Fabrication
F2-JK2-JF12-140Rolling of Can Transition Piece Flange 10 16-May-20 28-May-20 49 28-May-20, Rolling of Can Transition Piece Flange
F2-JK2-JF12-141Rolling of Can Transition Piece Barrel 10 25-Apr-20 07-May-20 0 07-May-20, Rolling of Can Transition Piece Barrel
F2-JK2-JF12-24Rolling of Can Row 2 Brace 10 14-Apr-20 25-Apr-20 0 25-Apr-20, Rolling of Can Row 2 Brace
F2-JK2-JF12-25Rolling of Can Leg 1A & 1B 10 14-Apr-20 25-Apr-20 13 25-Apr-20, Rolling of Can Leg 1A & 1B
F2-JK2-JF12-26Rolling of Can Leg 2A & 2B 10 22-Apr-20 04-May-20 13 04-May-20, Rolling of Can Leg 2A & 2B
F2-JK2-JF12-27Rolling of Node Can Row 1 10 22-Apr-20 04-May-20 13 04-May-20, Rolling of Node Can Row 1
F2-JK2-JF12-28Rolling of Node Can Row 2 10 30-Apr-20 12-May-20 13 12-May-20, Rolling of Node Can Row 2
F2-JK2-JF12-29Rolling of Can Row 1 Brace 10 30-Apr-20 12-May-20 13 12-May-20, Rolling of Can Row 1 Brace
F2-JK2-JF12-30Rolling of J-Tubes & J-Tubes Support 10 08-May-20 20-May-20 14 20-May-20, Rolling of J-Tubes & J-Tubes Support
F2-JK2-JF12-31Rolling of Can Plan Level Tubular 10 08-May-20 20-May-20 49 20-May-20, Rolling of Can Plan Level Tubular
F2-JK2-JF12-32Rolling of Can Top Bay X-Brace 10 16-May-20 28-May-20 49 28-May-20, Rolling of Can Top Bay X-Brace
Row 1 Fabrication 42 25-Apr-20 13-Jun-20 54 13-Jun-20, Row 1 Fabrication
Legs 40 25-Apr-20 12-Jun-20 16 12-Jun-20, Legs
F2-JK2-JF12-40
Install Stubs on to Leg 1A & 1B Nodes 2 02-Jun-20 04-Jun-20 13 04-Jun-20, Install Stubs on to Leg 1A & 1B Nodes
F2-JK2-JF12-41
Install Anodes on Row-1 Legs 4 03-Jun-20 08-Jun-20 15 08-Jun-20, Install Anodes on Row-1 Legs
F2-JK2-JF12-42
Join of Can Legs 1A 9 30-Apr-20 11-May-20 28 11-May-20, Join of Can Legs 1A
F2-JK2-JF12-43
Join of Can Legs 1B 9 30-Apr-20 11-May-20 28 11-May-20, Join of Can Legs 1B
F2-JK2-JF12-44
Mark and Profile Leg 1A & 1B Node 4 04-May-20 08-May-20 38 08-May-20, Mark and Profile Leg 1A & 1B Node
F2-JK2-JF12-45
Profilling of Legs 1A & 1B (Inc. Cones) 4 25-Apr-20 30-Apr-20 28 30-Apr-20, Profilling of Legs 1A & 1B (Inc. Cones)
F2-JK2-JF12-46
Join of Leg 1A & 1B Node 2 03-Jun-20 05-Jun-20 16 05-Jun-20, Join of Leg 1A & 1B Node
F2-JK2-JF12-47
Blasting and Painting for Leg 1A & 1B Node 5 05-Jun-20 12-Jun-20 16 12-Jun-20, Blasting and Painting for Leg 1A & 1B Node
F2-JK2-JF12-48
Assembly Leg 1A 3 01-Jun-20 03-Jun-20 13 03-Jun-20, Assembly Leg 1A
F2-JK2-JF12-49
Assembly Leg 1B 3 01-Jun-20 03-Jun-20 13 03-Jun-20, Assembly Leg 1B
Braces 28 12-May-20 13-Jun-20 13 13-Jun-20, Braces
F2-JK2-JF12-50
Fit & Weld Top X Brace Between Legs 1A & 1B 5 04-Jun-20 10-Jun-20 13 10-Jun-20, Fit & Weld Top X Brace Between Legs 1A & 1B
F2-JK2-JF12-51
Join of Row-1 Can Brace (Inc. Stub) 13 16-May-20 01-Jun-20 13 01-Jun-20, Join of Row-1 Can Brace (Inc. Stub)
F2-JK2-JF12-52
Join of Can Brace for Between Row 1 & 2 (Inc. Stub) 13 16-May-20 01-Jun-20 13 01-Jun-20, Join of Can Brace for Between Row 1 & 2 (Inc. Stub)
F2-JK2-JF12-53
Assembly of Row-1 Top Brace 4 01-Jun-20 04-Jun-20 13 04-Jun-20, Assembly of Row-1 Top Brace
F2-JK2-JF12-54
Fit & Weld Row-2 K-Brace (Inc. Vertical Braces) 5 04-Jun-20 10-Jun-20 13 10-Jun-20, Fit & Weld Row-2 K-Brace (Inc. Vertical Braces)
F2-JK2-JF12-55
Assembly of Row-1 K-Brace 4 01-Jun-20 04-Jun-20 13 04-Jun-20, Assembly of Row-1 K-Brace
F2-JK2-JF12-56
Fit & Weld X-Brace Between Row 1 & 2 5 04-Jun-20 10-Jun-20 13 10-Jun-20, Fit & Weld X-Brace Between Row 1 & 2
F2-JK2-JF12-57
Assembly of Brace Between Row 1 & 2 4 01-Jun-20 04-Jun-20 13 04-Jun-20, Assembly of Brace Between Row 1 & 2
F2-JK2-JF12-58
Profilling of Row-1 Braces and Stubs 4 12-May-20 16-May-20 13 16-May-20, Profilling of Row-1 Braces and Stubs
F2-JK2-JF12-59
Install Anodes on Row-1 Braces 4 10-Jun-20 13-Jun-20 13 13-Jun-20, Install Anodes on Row-1 Braces
J-Tubes 19 20-May-20 11-Jun-20 56 11-Jun-20, J-Tubes
F2-JK2-JF12-60
Join of Row-1 J-Tubes 5 25-May-20 30-May-20 56 30-May-20, Join of Row-1 J-Tubes
F2-JK2-JF12-61
Profilling of Row-1 J-Tubes 4 20-May-20 25-May-20 56 25-May-20, Profilling of Row-1 J-Tubes
F2-JK2-JF12-62
Bending of Row-1 J-Tubes 4 30-May-20 03-Jun-20 56 03-Jun-20, Bending of Row-1 J-Tubes
F2-JK2-JF12-63
Blast and Paint for Row-1 J-Tubes 3 03-Jun-20 08-Jun-20 56 08-Jun-20, Blast and Paint for Row-1 J-Tubes
F2-JK2-JF12-64
Assembly Row-1 J-Tubes 3 08-Jun-20 11-Jun-20 56 11-Jun-20, Assembly Row-1 J- Tubes
F2-JK2-JF12-65
Cut and Profile Row-1 J-Tubes Support 4 20-May-20 25-May-20 56 25-May-20, Cut and Profile Row-1 J-Tubes Support
F2-JK2-JF12-66
Assembly Row-1 J-Tubes Support 2 25-May-20 28-May-20 56 28-May-20, Assembly Row-1 J-Tubes Support
F2-JK2-JF12-67
Paint Row-1 J-Tubes Support 3 28-May-20 01-Jun-20 56 01-Jun-20, Paint Row-1 J-Tubes Support
F2-JK2-JF12-68
Install J-Tubes Support on to Row-1 J-Tubes 3 01-Jun-20 03-Jun-20 56 03-Jun-20, Install J-Tubes Support on to Row-1 J-Tubes
Common 23 19-May-20 13-Jun-20 14 13-Jun-20, Common
Structure 3 19-May-20 22-May-20 21 22-May-20, Structure
F2-JK2-JF12-33
Marking & Cutting of Leg and Brace Node 3 19-May-20 22-May-20 21 22-May-20, Marking & Cutting of Leg and Brace Node
F2-JK2-JF12-34
Marking & Cutting of Brace Stub 3 19-May-20 22-May-20 21 22-May-20, Marking & Cutting of Brace Stub
F2-JK2-JF12-35
Marking & Cutting of Leg and Brace Member 3 19-May-20 22-May-20 21 22-May-20, Marking & Cutting of Leg and Brace Member

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 51 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
Final Painting 23 19-May-20 13-Jun-20 14 13-Jun-20, Final Painting
F2-JK2-JF12-36
Blast and Paint Leg and Brace (Initial Paint) 11 19-May-20 01-Jun-20 13 01-Jun-20, Blast and Paint Leg and Brace (Initial Paint)
F2-JK2-JF12-37
Build Painting Habitat Protection 1 10-Jun-20 12-Jun-20 16 12-Jun-20, Build Painting Habitat Protection
F2-JK2-JF12-38
Row-1 Ready for Assembly & Roll-up 0 12-Jun-20 16 12-Jun-20
F2-JK2-JF12-39
Row-1 Touch up and Final Painting 3 10-Jun-20 13-Jun-20 13 13-Jun-20, Row-1 Touch up and Final Painting
Row 2 Fabrication 42 25-Apr-20 13-Jun-20 14 13-Jun-20, Row 2 Fabrication
Legs 23 04-May-20 30-May-20 27 30-May-20, Legs
F2-JK2-JF12-76
Install Anodes on Row-2 Legs 4 21-May-20 26-May-20 26 26-May-20, Install Anodes on Row-2 Legs
F2-JK2-JF12-77
Join of Can Legs 2A 9 08-May-20 19-May-20 21 19-May-20, Join of Can Legs 2A
F2-JK2-JF12-78
Join of Can Legs 2B 9 08-May-20 19-May-20 21 19-May-20, Join of Can Legs 2B
F2-JK2-JF12-79
Profilling of Legs 2A & 2B (Inc. Cones) 4 04-May-20 08-May-20 21 08-May-20, Profilling of Legs 2A & 2B (Inc. Cones)
F2-JK2-JF12-80
Mark and Profile Leg 2A & 2B Node 4 12-May-20 16-May-20 31 16-May-20, Mark and Profile Leg 2A & 2B Node
F2-JK2-JF12-81
Join of Leg 2A & 2B Node 2 21-May-20 23-May-20 27 23-May-20, Join of Leg 2A & 2B Node
F2-JK2-JF12-82
Blasting and Painting for Leg 2A & 2B Node (Initial) 5 23-May-20 30-May-20 27 30-May-20, Blasting and Painting for Leg 2A & 2B Node (Initial)
F2-JK2-JF12-83
Assembly Leg 2A 3 19-May-20 21-May-20 19 21-May-20, Assembly Leg 2A
F2-JK2-JF12-84
Assembly Leg 2B 3 19-May-20 21-May-20 19 21-May-20, Assembly Leg 2B
F2-JK2-JF12-85
Install Stubs on to Leg 2A & 2B Nodes 2 21-May-20 23-May-20 19 23-May-20, Install Stubs on to Leg 2A & 2B Nodes
Braces 32 25-Apr-20 02-Jun-20 19 02-Jun-20, Braces
F2-JK2-JF12-138
Fit & Weld Row-2 K-Brace (Inc. Vertical Braces) 5 23-May-20 29-May-20 19 29-May-20, Fit & Weld Row-2 K-Brace (Inc. Vertical Braces)
F2-JK2-JF12-139
Assembly of Row-2 K-Brace 4 19-May-20 22-May-20 20 22-May-20, Assembly of Row-2 K-Brace
F2-JK2-JF12-86
Fit & Weld Top X-Brace Between Legs 2A & 2B 4 23-May-20 28-May-20 22 28-May-20, Fit & Weld Top X-Brace Between Legs 2A & 2B
F2-JK2-JF12-87
Fit & Weld Mid X-Brace Between Legs 2A & 2B 4 23-May-20 28-May-20 22 28-May-20, Fit & Weld Mid X-Brace Between Legs 2A & 2B
F2-JK2-JF12-88
Join of Row-2 Can Brace (Inc. Stub) 10 30-Apr-20 12-May-20 19 12-May-20, Join of Row-2 Can Brace (Inc. Stub)
F2-JK2-JF12-89
Assembly of Row-2 Top Brace 3 19-May-20 22-May-20 23 22-May-20, Assembly of Row-2 Top Brace
F2-JK2-JF12-90
Assembly of Row-2 Mid Brace 3 19-May-20 22-May-20 23 22-May-20, Assembly of Row-2 Mid Brace
F2-JK2-JF12-91
Profilling of Row-2 Braces and Stubs 4 25-Apr-20 30-Apr-20 19 30-Apr-20, Profilling of Row-2 Braces and Stubs
F2-JK2-JF12-92
Install Anodes on Row-2 Braces 4 29-May-20 02-Jun-20 19 02-Jun-20, Install Anodes on Row-2 Braces
J-Tubes 21 20-May-20 13-Jun-20 14 13-Jun-20, J-Tubes
F2-JK2-JF12-128
Join of Row-2 J-Tubes 5 25-May-20 30-May-20 17 30-May-20, Join of Row-2 J-Tubes
F2-JK2-JF12-129
Profilling of Row-2 J-Tubes 4 20-May-20 25-May-20 17 25-May-20, Profilling of Row-2 J-Tubes
F2-JK2-JF12-130
Bending of Row-2 J-Tubes 4 30-May-20 03-Jun-20 17 03-Jun-20, Bending of Row-2 J-Tubes
F2-JK2-JF12-131
Blast and Paint for Row-2 J-Tubes 3 06-Jun-20 10-Jun-20 14 10-Jun-20, Blast and Paint for Row-2 J-Tubes
F2-JK2-JF12-132
Assembly Row-2 J-Tubes 3 10-Jun-20 13-Jun-20 14 13-Jun-20, Assembly Row-2 J-Tubes
F2-JK2-JF12-133
Cut and Profile Row-2 J-Tubes Support 4 20-May-20 25-May-20 14 25-May-20, Cut and Profile Row-2 J-Tubes Support
F2-JK2-JF12-134
Assembly Row-2 J-Tubes Support 2 25-May-20 28-May-20 14 28-May-20, Assembly Row-2 J-Tubes Support
F2-JK2-JF12-135
Vulcanized Row-2 J-Tubes Support 2 28-May-20 30-May-20 14 30-May-20, Vulcanized Row-2 J-Tubes Support
F2-JK2-JF12-136
Paint Row-2 J-Tubes Support 3 30-May-20 03-Jun-20 14 03-Jun-20, Paint Row-2 J-Tubes Support
F2-JK2-JF12-137
Install J-Tubes Support on to Row-2 J-Tubes 3 03-Jun-20 06-Jun-20 14 06-Jun-20, Install J-Tubes Support on to Row-2 J-Tubes
Common 23 12-May-20 08-Jun-20 19 08-Jun-20, Common
Structure 3 12-May-20 15-May-20 23 15-May-20, Structure
F2-JK2-JF12-69
Marking & Cutting of Leg and Brace Node 3 12-May-20 15-May-20 23 15-May-20, Marking & Cutting of Leg and Brace Node
F2-JK2-JF12-70
Marking & Cutting of Brace Stub 3 12-May-20 15-May-20 23 15-May-20, Marking & Cutting of Brace Stub
F2-JK2-JF12-71
Marking & Cutting of Leg and Brace Member 3 12-May-20 15-May-20 23 15-May-20, Marking & Cutting of Leg and Brace Member
Final Painting 23 12-May-20 08-Jun-20 19 08-Jun-20, Final Painting
F2-JK2-JF12-72
Row-2 Touch up and Final Painting 3 02-Jun-20 06-Jun-20 19 06-Jun-20, Row-2 Touch up and Final Painting
F2-JK2-JF12-73
Blast and Paint Leg and Brace (Initial Paint) 5 12-May-20 19-May-20 19 19-May-20, Blast and Paint Leg and Brace (Initial Paint)
F2-JK2-JF12-74
Build Painting Habitat Protection 1 06-Jun-20 08-Jun-20 19 08-Jun-20, Build Painting Habitat Protection
F2-JK2-JF12-75
Row-2 Ready for Assembly & Roll-up 0 08-Jun-20 19 08-Jun-20
Transition Piece 61 25-Apr-20 06-Jul-20 49 06-Jul-20, Transition Piece
F2-JK2-JF12-10Fabrication of Can Transition Piece Barrel 24 07-May-20 04-Jun-20 0 04-Jun-20, Fabrication of Can Transition Piece Barrel
F2-JK2-JF12-100Fit Grating Supports 4 08-May-20 13-May-20 66 13-May-20, Fit Grating Supports
F2-JK2-JF12-101Fab Main Deck Handrails 4 02-May-20 06-May-20 67 06-May-20, Fab Main Deck Handrails
F2-JK2-JF12-102Fab Padeye inc Top of Jacket 4 04-May-20 07-May-20 93 07-May-20, Fab Padeye inc Top of Jacket
F2-JK2-JF12-103Blast and Paint Transition Piece 7 27-Jun-20 06-Jul-20 49 06-Jul-20, Blast and Paint Transition Piece
F2-JK2-JF12-11 Fabrication of Strut Plate 18 25-Apr-20 16-May-20 16 16-May-20, Fabrication of Strut Plate

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 52 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF12-12Fabrication of Internal Platform 21 25-Apr-20 20-May-20 78 20-May-20, Fabrication of Internal Platform
F2-JK2-JF12-13Fabrication of External Platform 25 25-Apr-20 25-May-20 78 25-May-20, Fabrication of External Platform
F2-JK2-JF12-14Assembly Strut Plate 21 16-May-20 10-Jun-20 64 10-Jun-20, Assembly Strut Plate
F2-JK2-JF12-15Fabrication of Ring Stiffener 21 03-Jun-20 27-Jun-20 49 27-Jun-20, Fabrication of Ring Stiffener
F2-JK2-JF12-16Fabrication of Crane Pedestal 21 16-May-20 10-Jun-20 42 10-Jun-20, Fabrication of Crane Pedestal
F2-JK2-JF12-93Galvanizing Handrails 5 06-May-20 12-May-20 67 12-May-20, Galvanizing Handrails
F2-JK2-JF12-94Erect Deck Plate Areas 5 04-May-20 08-May-20 65 08-May-20, Erect Deck Plate Areas
F2-JK2-JF12-95Transition Piece Fabrication Complete 0 27-Jun-20 49 27-Jun-20
F2-JK2-JF12-96Fabrication Assemble Walkways / Platforms 21 16-May-20 10-Jun-20 64 10-Jun-20, Fabrication Assemble Walkways / Platforms
F2-JK2-JF12-97Fit and Weld TP's Equipment Supports 5 04-May-20 11-May-20 65 11-May-20, Fit and Weld TP's Equipment Supports
F2-JK2-JF12-98Plate Profiling for Main Deck 5 25-Apr-20 02-May-20 20 02-May-20, Plate Profiling for Main Deck
F2-JK2-JF12-99Fab Main Deck Main Steel 5 28-Apr-20 04-May-20 20 04-May-20, Fab Main Deck Main Steel
Lifting Trunnion 7 04-May-20 12-May-20 20 12-May-20, Lifting Trunnion
F2-JK2-JF12-104Fabricate Lifting Trunion 7 04-May-20 12-May-20 20 12-May-20, Fabricate Lifting Trunion
Boat Landing 44 07-May-20 29-Jun-20 45 29-Jun-20, Boat Landing
F2-JK2-JF12-123Blast and Paint Boat Landing 5 22-Jun-20 29-Jun-20 45 29-Jun-20, Blast and Paint Boat Landing
F2-JK2-JF12-124Fabricate Boat Landing 21 07-May-20 01-Jun-20 45 01-Jun-20, Fabricate Boat Landing
F2-JK2-JF12-159Fabricate Boat Landing Access platform 24 25-May-20 22-Jun-20 45 22-Jun-20, Fabricate Boat Landing Access platform
F2-JK2-JF12-160Fabricate Boat Landing Ladders 15 02-Jun-20 19-Jun-20 47 19-Jun-20, Fabricate Boat Landing Ladders
Grouting Line 23 10-Jun-20 07-Jul-20 42 07-Jul-20, Grouting Line
F2-JK2-JF12-126Fabricate Grouting Line & Grouting Line Support 23 10-Jun-20 07-Jul-20 42 07-Jul-20, Fabricate Grouting Line & Grouting Line Support
Assembly 105 12-May-20 10-Sep-20 1 10-Sep-20, Assembly
Row Assembly 88 12-May-20 22-Aug-20 13 22-Aug-20, Row Assembly
F2-JK2-JF12-113Fabricate Upper Grillage & Truss Support 18 12-May-20 02-Jun-20 20 02-Jun-20, Fabricate Upper Grillage & Truss Support
F2-JK2-JF12-114Layout Concrete Blocks/ Grillages and Truss Support Steel 4 10-Jun-20 16-Jun-20 13 16-Jun-20, Layout Concrete Blocks/ Grillages and Truss Support Steel
Row-1 & 2 (Upper Jacket) Assembly 46 16-Jun-20 08-Aug-20 13 08-Aug-20, Row-1 & 2 (Upper Jacket) Assembly
F2-JK2-JF12-115
Installation of Grouting Line 1 03-Jul-20 04-Jul-20 33 04-Jul-20, Installation of Grouting Line
F2-JK2-JF12-117
Installation of J-Tube At Row-1B & 2A 5 03-Jul-20 09-Jul-20 37 09-Jul-20, Installation of J-Tube At Row-1B & 2A
F2-JK2-JF12-118
Row-2 - Touch Up, 2nd Coat & Top Coat 3 05-Aug-20 07-Aug-20 13 07-Aug-20, Row-2 - Touch Up, 2nd Coat & Top Coat
F2-JK2-JF12-119
Installation of Row-1B & 2B X-Brace 7 25-Jun-20 03-Jul-20 13 03-Jul-20, Installation of Row-1B & 2B X-Brace
F2-JK2-JF12-120
Installation of Leg 1A & 1B Onto Support 1 16-Jun-20 17-Jun-20 13 17-Jun-20, Installation of Leg 1A & 1B Onto Support
F2-JK2-JF12-121
Installation of Row-1A & 1B X-Brace 7 17-Jun-20 25-Jun-20 13 25-Jun-20, Installation of Row-1A & 1B X-Brace
F2-JK2-JF12-122
Installation of Row-2A & 2B X-Brace in Final Position 7 28-Jul-20 05-Aug-20 13 05-Aug-20, Installation of Row-2A & 2B X-Brace in Final Position
F2-JK2-JF12-142
Installation of Leg 2A & 2B Onto Support 1 16-Jun-20 17-Jun-20 20 17-Jun-20, Installation of Leg 2A & 2B Onto Support
F2-JK2-JF12-143
Installation of Row-1A & 2A X-Brace 7 25-Jun-20 03-Jul-20 13 03-Jul-20, Installation of Row-1A & 2A X-Brace
F2-JK2-JF12-144
Installation of Row-1A & 1B X-Brace in Final Position 7 20-Jul-20 28-Jul-20 13 28-Jul-20, Installation of Row-1A & 1B X-Brace in Final Position
F2-JK2-JF12-145
Roll Up X-Brace Row A&B to Final Position 7 03-Jul-20 11-Jul-20 13 11-Jul-20, Roll Up X-Brace Row A&B to F inal Posit io n
F2-JK2-JF12-146
Installing Tie-back for Fastener 7 11-Jul-20 20-Jul-20 13 20-Jul-20, Installing Tie-back for Fastener
F2-JK2-JF12-147
Installation of Boat Landing 3 05-Aug-20 08-Aug-20 13 08-Aug-20, Installation of Boat Landing
Row-1 & 2 (Lower Jacket) Assembly 44 12-Jun-20 01-Aug-20 18 01-Aug-20, Row-1 & 2 (Lower Jacket) Assembly
F2-JK2-JF12-116
Installation of Pile Stopper 4 13-Jul-20 16-Jul-20 18 16-Jul-20, Installation of Pile Stopper
F2-JK2-JF12-148
Installation of Grouting Line 1 30-Jun-20 01-Jul-20 39 01-Jul-20, Installation of Grouting Line
F2-JK2-JF12-149
Installation of J-Tube At Row-1B & 2A 5 30-Jun-20 06-Jul-20 28 06-Jul-20, Installation of J-Tube At Row-1B & 2A
F2-JK2-JF12-150
Installation of Row-1B & 2B X-Brace 7 22-Jun-20 30-Jun-20 18 30-Jun-20, Installation of Row-1B & 2B X-Brace
F2-JK2-JF12-151
Installation of Leg 1A & 1B Onto Support 1 12-Jun-20 13-Jun-20 18 13-Jun-20, Installation of Leg 1A & 1B Onto Support
F2-JK2-JF12-152
Installation of Row-1A & 1B X-Brace 7 13-Jun-20 22-Jun-20 18 22-Jun-20, Installation of Row-1A & 1B X-Brace
F2-JK2-JF12-153
Installation of Row-2A & 2B X-Brace in Final Position 7 24-Jul-20 01-Aug-20 18 01-Aug-20, Installation of Row-2A & 2B X-Brace in Final Position
F2-JK2-JF12-154
Installation of Leg 2A & 2B Onto Support 1 12-Jun-20 13-Jun-20 25 13-Jun-20, Installation of Leg 2A & 2B Onto Support
F2-JK2-JF12-155
Installation of Row-1A & 2A X-Brace 7 22-Jun-20 30-Jun-20 18 30-Jun-20, Installation of Row-1A & 2A X-Brace
F2-JK2-JF12-156
Installation of Row-1A & 1B X-Brace in Final Position 7 16-Jul-20 24-Jul-20 18 24-Jul-20, Installation of Row-1A & 1B X-Brace in Final Position
F2-JK2-JF12-157
Roll Up X-Brace Row A&B to Final Position 7 30-Jun-20 08-Jul-20 18 08-Jul-20, Roll Up X-Brace Row A&B to Final Position
F2-JK2-JF12-158
Installing Tie-back for Fastener 4 08-Jul-20 13-Jul-20 18 13-Jul-20, Installing Tie-back for Fastener
Grouting Line 40 07-Jul-20 22-Aug-20 13 22-Aug-20, Grouting Line
F2-JK2-JF12-125
Installation Of Grouting Line 5 17-Aug-20 22-Aug-20 13 22-Aug-20, Installation Of Grouting Line
F2-JK2-JF12-127
Installation Grouting Line Support 7 07-Jul-20 15-Jul-20 42 15-Jul-20, Installation Grouting Line Support

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 53 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
Row Roll Up 7 08-Aug-20 17-Aug-20 13 17-Aug-20, Row Roll Up
F2-JK2-JF12-105Roll Up Of Lower Jacket To Final Position 2 08-Aug-20 11-Aug-20 13 11-Aug-20, Roll Up Of Lower Jacket To Final Position
F2-JK2-JF12-106Roll Up Of Upper Jacket To Final Position 5 11-Aug-20 17-Aug-20 13 17-Aug-20, Roll Up Of Upper Jacket To Final Position
Transition Piece (TP) 76 04-Jun-20 01-Sep-20 0 01-Sep-20, Transition Piece (TP)
F2-JK2-JF12-1 Install Door Platform 10 27-Jun-20 09-Jul-20 29 09-Jul-20, Install Door Platform
F2-JK2-JF12-17Installation & Assembly of Ring Stiffener 21 30-Jun-20 24-Jul-20 0 24-Jul-20, Installation & Assembly of Ring Stiffener
F2-JK2-JF12-18Installation of Transition Piece Flange 15 08-Jul-20 25-Jul-20 0 25-Jul-20, Installation of Transition Piece Flange
F2-JK2-JF12-19Install Crane Pedestal 12 10-Jun-20 24-Jun-20 42 24-Jun-20, Install Crane Pedestal
F2-JK2-JF12-2 Blasting & Painting 10 12-Aug-20 24-Aug-20 0 24-Aug-20, Blasting & Painting
F2-JK2-JF12-3 Assemble Can Transition Piece Barrel to Main Deck 15 04-Jun-20 22-Jun-20 0 22-Jun-20, Assemble Can Transition Piece Barrel to Main Deck
F2-JK2-JF12-4 Install Platform & Internal Structure into Upper Can 7 24-Aug-20 01-Sep-20 0 01-Sep-20, Install Platform & Internal Structure into Upper Can
F2-JK2-JF12-5 Door opening & Installation of Door frame 5 22-Jun-20 27-Jun-20 39 27-Jun-20, Door opening & Installation of Door frame
F2-JK2-JF12-6 Installation & Assembly of Strut 15 22-Jun-20 09-Jul-20 0 09-Jul-20, Installation & Assembly of Strut
F2-JK2-JF12-7 Install Free-Issued Items 15 25-Jul-20 12-Aug-20 0 12-Aug-20, Install Free-Issued Items
F2-JK2-JF12-8 Install Architectural items, Electrical & Instrument Equipments 15 22-Jun-20 09-Jul-20 29 09-Jul-20, Install Architectural items, Electrical & Instrument Equipments
F2-JK2-JF12-9 Install External Platform & Handrail 12 25-Jun-20 09-Jul-20 29 09-Jul-20, Install External Platform & Handrail
Final Assembly 8 01-Sep-20 10-Sep-20 1 10-Sep-20, Final Assembly
F2-JK2-JF12-107Installation of Transition Piece 3 01-Sep-20 04-Sep-20 0 04-Sep-20, Installation of Transition Piece
F2-JK2-JF12-108Installation of Mudmad Plate 5 03-Sep-20 09-Sep-20 0 09-Sep-20, Installation of Mudmad Plate
F2-JK2-JF12-109Installation of Lifting Trunnion 4 04-Sep-20 09-Sep-20 2 09-Sep-20, Installation of Lifting Trunnion
F2-JK2-JF12-110Installation of Skirt Pile Sleeve 2 03-Sep-20 05-Sep-20 0 05-Sep-20, Installation of Skirt Pile Sleeve
F2-JK2-JF12-111Final Touch Up Coating 3 07-Sep-20 10-Sep-20 0 10-Sep-20, Final Touch Up Coating
F2-JK2-JF12-112Installation of Lifting Slings 1 05-Sep-20 07-Sep-20 0 07-Sep-20, Installation of Lifting Slings
F2-JK2-JF12-161J acket Fabrication Completed 0 10-Sep-20 0 10-Sep-20
Testing & Commissioning 18 22-Aug-20 12-Sep-20 0 12-Sep-20, Testing & Commissioning
Grouting & Gripper Test 3 22-Aug-20 26-Aug-20 13 26-Aug-20, Grouting & Gripper Test
F2-JK2-JF12-20Gripper Test 2 24-Aug-20 26-Aug-20 13 26-Aug-20, Gripper Test
F2-JK2-JF12-21Grouting Test 1 22-Aug-20 24-Aug-20 13 24-Aug-20, Grouting Test
Mechanical Completion 2 10-Sep-20 12-Sep-20 0 12-Sep-20, Mechanical Completion
F2-JK2-JF12-22Main Structure, Boat Landing, J-Tube, Transition Piece 2 10-Sep-20 12-Sep-20 0 12-Sep-20, Main Structure, Boat Landing, J-Tube, Transition Piece
Jacket & Piles Ready For Loadout 0 12-Sep-20 12-Sep-20 0 12-Sep-20, Jacket & Piles Ready For Loadout
F2-JK2-JF12-23Jacket Ready For Load Out 0 12-Sep-20 0 12-Sep-20
Jacket Foundation 13a 130 22-Apr-20 21-Sep-20 67 21-Sep-20, Jacket Foundation 13a
Fabrication 72 22-Apr-20 15-Jul-20 115 15-Jul-20, Fabrication
Pre-Fabrication 38 22-Apr-20 05-Jun-20 116 05-Jun-20, Pre-Fabrication
F2-JK2-JF13-140Rolling of Can Transition Piece Flange 10 25-May-20 05-Jun-20 116 05-Jun-20, Rolling of Can Transition Piece Flange
F2-JK2-JF13-141Rolling of Can Transition Piece Barrel 10 04-May-20 15-May-20 67 15-May-20, Rolling of Can Transition Piece Barrel
F2-JK2-JF13-24Rolling of Can Row 2 Brace 10 22-Apr-20 04-May-20 0 04-May-20, Rolling of Can Row 2 Brace
F2-JK2-JF13-25Rolling of Can Leg 1A & 1B 10 22-Apr-20 04-May-20 80 04-May-20, Rolling of Can Leg 1A & 1B
F2-JK2-JF13-26Rolling of Can Leg 2A & 2B 10 30-Apr-20 12-May-20 80 12-May-20, Rolling of Can Leg 2A & 2B
F2-JK2-JF13-27Rolling of Node Can Row 1 10 30-Apr-20 12-May-20 80 12-May-20, Rolling of Node Can Row 1
F2-JK2-JF13-28Rolling of Node Can Row 2 10 08-May-20 20-May-20 80 20-May-20, Rolling of Node Can Row 2
F2-JK2-JF13-29Rolling of Can Row 1 Brace 10 08-May-20 20-May-20 80 20-May-20, Rolling of Can Row 1 Brace
F2-JK2-JF13-30Rolling of J-Tubes & J-Tubes Support 10 16-May-20 28-May-20 81 28-May-20, Rolling of J-Tubes & J-Tubes Support
F2-JK2-JF13-31Rolling of Can Plan Level Tubular 10 16-May-20 28-May-20 116 28-May-20, Rolling of Can Plan Level Tubular
F2-JK2-JF13-32Rolling of Can Top Bay X-Brace 10 25-May-20 05-Jun-20 116 05-Jun-20, Rolling of Can Top Bay X-Brace
Row 1 Fabrication 42 04-May-20 22-Jun-20 121 22-Jun-20, Row 1 Fabrication
Legs 40 04-May-20 20-Jun-20 83 20-Jun-20, Legs
F2-JK2-JF13-40
Install Stubs on to Leg 1A & 1B Nodes 2 10-Jun-20 12-Jun-20 80 12-Jun-20, Install Stubs on to Leg 1A & 1B Nodes
F2-JK2-JF13-41
Install Anodes on Row-1 Legs 4 11-Jun-20 16-Jun-20 82 16-Jun-20, Install Anodes on Row-1 Legs
F2-JK2-JF13-42
Join of Can Legs 1A 9 08-May-20 19-May-20 95 19-May-20, Join of Can Legs 1A
F2-JK2-JF13-43
Join of Can Legs 1B 9 08-May-20 19-May-20 95 19-May-20, Join of Can Legs 1B
F2-JK2-JF13-44
Mark and Profile Leg 1A & 1B Node 4 12-May-20 16-May-20 105 16-May-20, Mark and Profile Leg 1A & 1B Node
F2-JK2-JF13-45
Profilling of Legs 1A & 1B (Inc. Cones) 4 04-May-20 08-May-20 95 08-May-20, Profilling of Legs 1A & 1B (Inc. Cones)
F2-JK2-JF13-46
Join of Leg 1A & 1B Node 2 11-Jun-20 13-Jun-20 83 13-Jun-20, Join of Leg 1A & 1B Node

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 54 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF13-47
Blasting and Painting for Leg 1A & 1B Node 5 13-Jun-20 20-Jun-20 83 20-Jun-20, Blasting and Painting for Leg 1A & 1B Node
F2-JK2-JF13-48
Assembly Leg 1A 3 09-Jun-20 11-Jun-20 80 11-Jun-20, Assembly Leg 1A
F2-JK2-JF13-49
Assembly Leg 1B 3 09-Jun-20 11-Jun-20 80 11-Jun-20, Assembly Leg 1B
Braces 28 20-May-20 22-Jun-20 80 22-Jun-20, Braces
F2-JK2-JF13-50
Fit & Weld Top X Brace Between Legs 1A & 1B 5 12-Jun-20 18-Jun-20 80 18-Jun-20, Fit & Weld Top X Brace Between Legs 1A & 1B
F2-JK2-JF13-51
Join of Row-1 Can Brace (Inc. Stub) 13 25-May-20 09-Jun-20 80 09-Jun-20, Join of Row-1 Can Brace (Inc. Stub)
F2-JK2-JF13-52
Join of Can Brace for Between Row 1 & 2 (Inc. Stub) 13 25-May-20 09-Jun-20 80 09-Jun-20, Join of Can Brace for Between Row 1 & 2 (Inc. Stub)
F2-JK2-JF13-53
Assembly of Row-1 Top Brace 4 09-Jun-20 12-Jun-20 80 12-Jun-20, Assembly of Row-1 Top Brace
F2-JK2-JF13-54
Fit & Weld Row-2 K-Brace (Inc. Vertical Braces) 5 12-Jun-20 18-Jun-20 80 18-Jun-20, Fit & Weld Row-2 K-Brace (Inc. Vertical Braces)
F2-JK2-JF13-55
Assembly of Row-1 K-Brace 4 09-Jun-20 12-Jun-20 80 12-Jun-20, Assembly of Row-1 K-Brace
F2-JK2-JF13-56
Fit & Weld X-Brace Between Row 1 & 2 5 12-Jun-20 18-Jun-20 80 18-Jun-20, Fit & Weld X-Brace Between Row 1 & 2
F2-JK2-JF13-57
Assembly of Brace Between Row 1 & 2 4 09-Jun-20 12-Jun-20 80 12-Jun-20, Assembly of Brace Between Row 1 & 2
F2-JK2-JF13-58
Profilling of Row-1 Braces and Stubs 4 20-May-20 25-May-20 80 25-May-20, Profilling of Row-1 Braces and Stubs
F2-JK2-JF13-59
Install Anodes on Row-1 Braces 4 18-Jun-20 22-Jun-20 80 22-Jun-20, Install Anodes on Row-1 Braces
J-Tubes 19 28-May-20 19-Jun-20 123 19-Jun-20, J-Tubes
F2-JK2-JF13-60
Join of Row-1 J-Tubes 5 02-Jun-20 08-Jun-20 123 08-Jun-20, Join of Row-1 J-Tubes
F2-JK2-JF13-61
Profilling of Row-1 J-Tubes 4 28-May-20 02-Jun-20 123 02-Jun-20, Profilling of Row-1 J-Tubes
F2-JK2-JF13-62
Bending of Row-1 J-Tubes 4 08-Jun-20 11-Jun-20 123 11-Jun-20, Bending of Row-1 J-Tubes
F2-JK2-JF13-63
Blast and Paint for Row-1 J-Tubes 3 11-Jun-20 16-Jun-20 123 16-Jun-20, Blast and Paint for Row-1 J-Tubes
F2-JK2-JF13-64
Assembly Row-1 J-Tubes 3 16-Jun-20 19-Jun-20 123 19-Jun-20, Assembly Row-1 J-Tubes
F2-JK2-JF13-65
Cut and Profile Row-1 J-Tubes Support 4 28-May-20 02-Jun-20 123 02-Jun-20, Cut and Profile Row-1 J-Tubes Support
F2-JK2-JF13-66
Assembly Row-1 J-Tubes Support 2 02-Jun-20 05-Jun-20 123 05-Jun-20, Assembly Row-1 J-Tubes Support
F2-JK2-JF13-67
Paint Row-1 J-Tubes Support 3 05-Jun-20 09-Jun-20 123 09-Jun-20, Paint Row-1 J-Tubes Support
F2-JK2-JF13-68
Install J-Tubes Support on to Row-1 J-Tubes 3 09-Jun-20 11-Jun-20 123 11-Jun-20, Install J-Tubes Support on to Row-1 J-Tubes
Common 23 27-May-20 22-Jun-20 81 22-Jun-20, Common
Structure 3 27-May-20 30-May-20 88 30-May-20, Structure
F2-JK2-JF13-33
Marking & Cutting of Leg and Brace Node 3 27-May-20 30-May-20 88 30-May-20, Marking & Cutting of Leg and Brace Node
F2-JK2-JF13-34
Marking & Cutting of Brace Stub 3 27-May-20 30-May-20 88 30-May-20, Marking & Cutting of Brace Stub
F2-JK2-JF13-35
Marking & Cutting of Leg and Brace Member 3 27-May-20 30-May-20 88 30-May-20, Marking & Cutting of Leg and Brace Member
Final Painting 23 27-May-20 22-Jun-20 81 22-Jun-20, Final Painting
F2-JK2-JF13-36
Blast and Paint Leg and Brace (Initial Paint) 11 27-May-20 09-Jun-20 80 09-Jun-20, Blast and Paint Leg and Brace (Initial Paint)
F2-JK2-JF13-37
Build Painting Habitat Protection 1 18-Jun-20 20-Jun-20 83 20-Jun-20, Build Painting Habitat Protection
F2-JK2-JF13-38
Row-1 Ready for Assembly & Roll-up 0 20-Jun-20 83 20-Jun-20
F2-JK2-JF13-39
Row-1 Touch up and Final Painting 3 18-Jun-20 22-Jun-20 80 22-Jun-20, Row-1 Touch up and Final Painting
Row 2 Fabrication 42 04-May-20 22-Jun-20 81 22-Jun-20, Row 2 Fabrication
Legs 23 12-May-20 08-Jun-20 94 08-Jun-20, Legs
F2-JK2-JF13-76
Install Anodes on Row-2 Legs 4 29-May-20 03-Jun-20 93 03-Jun-20, Install Anodes on Row-2 Legs
F2-JK2-JF13-77
Join of Can Legs 2A 9 16-May-20 27-May-20 88 27-May-20, Join of Can Legs 2A
F2-JK2-JF13-78
Join of Can Legs 2B 9 16-May-20 27-May-20 88 27-May-20, Join of Can Legs 2B
F2-JK2-JF13-79
Profilling of Legs 2A & 2B (Inc. Cones) 4 12-May-20 16-May-20 88 16-May-20, Profilling of Legs 2A & 2B (Inc. Cones)
F2-JK2-JF13-80
Mark and Profile Leg 2A & 2B Node 4 20-May-20 25-May-20 98 25-May-20, Mark and Profile Leg 2A & 2B Node
F2-JK2-JF13-81
Join of Leg 2A & 2B Node 2 29-May-20 01-Jun-20 94 01-Jun-20, Join of Leg 2A & 2B Node
F2-JK2-JF13-82
Blasting and Painting for Leg 2A & 2B Node (Initial) 5 01-Jun-20 08-Jun-20 94 08-Jun-20, Blasting and Painting for Leg 2A & 2B Node (Initial)
F2-JK2-JF13-83
Assembly Leg 2A 3 27-May-20 29-May-20 86 29-May-20, Assembly Leg 2A
F2-JK2-JF13-84
Assembly Leg 2B 3 27-May-20 29-May-20 86 29-May-20, Assembly Leg 2B
F2-JK2-JF13-85
Install Stubs on to Leg 2A & 2B Nodes 2 29-May-20 01-Jun-20 86 01-Jun-20, Install Stubs on to Leg 2A & 2B Nodes
Braces 32 04-May-20 10-Jun-20 86 10-Jun-20, Braces
F2-JK2-JF13-138
Fit & Weld Row-2 K-Brace (Inc. Vertical Braces) 5 01-Jun-20 06-Jun-20 86 06-Jun-20, Fit & Weld Row-2 K-Brace (Inc. Vertical Braces)
F2-JK2-JF13-139
Assembly of Row-2 K-Brace 4 27-May-20 30-May-20 87 30-May-20, Assembly of Row-2 K-Brace
F2-JK2-JF13-86
Fit & Weld Top X-Brace Between Legs 2A & 2B 4 01-Jun-20 05-Jun-20 89 05-Jun-20, Fit & Weld Top X-Brace Between Legs 2A & 2B
F2-JK2-JF13-87
Fit & Weld Mid X-Brace Between Legs 2A & 2B 4 01-Jun-20 05-Jun-20 89 05-Jun-20, Fit & Weld Mid X-Brace Between Legs 2A & 2B
F2-JK2-JF13-88
Join of Row-2 Can Brace (Inc. Stub) 10 08-May-20 20-May-20 86 20-May-20, Join of Row-2 Can Brace (Inc. Stub)
F2-JK2-JF13-89
Assembly of Row-2 Top Brace 3 27-May-20 30-May-20 90 30-May-20, Assembly of Row-2 Top Brace
F2-JK2-JF13-90
Assembly of Row-2 Mid Brace 3 27-May-20 30-May-20 90 30-May-20, Assembly of Row-2 Mid Brace
F2-JK2-JF13-91
Profilling of Row-2 Braces and Stubs 4 04-May-20 08-May-20 86 08-May-20, Profilling of Row-2 Braces and Stubs

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 55 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF13-92
Install Anodes on Row-2 Braces 4 06-Jun-20 10-Jun-20 86 10-Jun-20, Install Anodes on Row-2 Braces
J-Tubes 21 28-May-20 22-Jun-20 81 22-Jun-20, J-Tubes
F2-JK2-JF13-128
Join of Row-2 J-Tubes 5 02-Jun-20 08-Jun-20 84 08-Jun-20, Join of Row-2 J-Tubes
F2-JK2-JF13-129
Profilling of Row-2 J-Tubes 4 28-May-20 02-Jun-20 84 02-Jun-20, Profilling of Row-2 J-Tubes
F2-JK2-JF13-130
Bending of Row-2 J-Tubes 4 08-Jun-20 11-Jun-20 84 11-Jun-20, Bending of Row-2 J-Tubes
F2-JK2-JF13-131
Blast and Paint for Row-2 J-Tubes 3 15-Jun-20 18-Jun-20 81 18-Jun-20, Blast and Paint for Row-2 J-Tubes
F2-JK2-JF13-132
Assembly Row-2 J-Tubes 3 18-Jun-20 22-Jun-20 81 22-Jun-20, Assembly Row-2 J-Tubes
F2-JK2-JF13-133
Cut and Profile Row-2 J-Tubes Support 4 28-May-20 02-Jun-20 81 02-Jun-20, Cut and Profile Row-2 J-Tubes Support
F2-JK2-JF13-134
Assembly Row-2 J-Tubes Support 2 02-Jun-20 05-Jun-20 81 05-Jun-20, Assembly Row-2 J-Tubes Support
F2-JK2-JF13-135
Vulcanized Row-2 J-Tubes Support 2 05-Jun-20 08-Jun-20 81 08-Jun-20, Vulcanized Row-2 J-Tubes Support
F2-JK2-JF13-136
Paint Row-2 J-Tubes Support 3 08-Jun-20 11-Jun-20 81 11-Jun-20, Paint Row-2 J-Tubes Support
F2-JK2-JF13-137
Install J-Tubes Support on to Row-2 J-Tubes 3 11-Jun-20 15-Jun-20 81 15-Jun-20, Install J-Tubes Support on to Row-2 J-Tubes
Common 23 20-May-20 16-Jun-20 86 16-Jun-20, Common
Structure 3 20-May-20 23-May-20 90 23-May-20, Structure
F2-JK2-JF13-69
Marking & Cutting of Leg and Brace Node 3 20-May-20 23-May-20 90 23-May-20, Marking & Cutting of Leg and Brace Node
F2-JK2-JF13-70
Marking & Cutting of Brace Stub 3 20-May-20 23-May-20 90 23-May-20, Marking & Cutting of Brace Stub
F2-JK2-JF13-71
Marking & Cutting of Leg and Brace Member 3 20-May-20 23-May-20 90 23-May-20, Marking & Cutting of Leg and Brace Member
Final Painting 23 20-May-20 16-Jun-20 86 16-Jun-20, Final Painting
F2-JK2-JF13-72
Row-2 Touch up and Final Painting 3 10-Jun-20 15-Jun-20 86 15-Jun-20, Row-2 Touch up and Final Painting
F2-JK2-JF13-73
Blast and Paint Leg and Brace (Initial Paint) 5 20-May-20 27-May-20 86 27-May-20, Blast and Paint Leg and Brace (Initial Paint)
F2-JK2-JF13-74
Build Painting Habitat Protection 1 15-Jun-20 16-Jun-20 86 16-Jun-20, Build Painting Habitat Protection
F2-JK2-JF13-75
Row-2 Ready for Assembly & Roll-up 0 16-Jun-20 86 16-Jun-20
Transition Piece 61 04-May-20 14-Jul-20 116 14-Jul-20, Transition Piece
F2-JK2-JF13-10Fabrication of Can Transition Piece Barrel 24 15-May-20 12-Jun-20 67 12-Jun-20, Fabrication of Can Transition Piece Barrel
F2-JK2-JF13-100Fit Grating Supports 4 16-May-20 21-May-20 133 21-May-20, Fit Grating Supports
F2-JK2-JF13-101Fab Main Deck Handrails 4 11-May-20 14-May-20 134 14-May-20, Fab Main Deck Handrails
F2-JK2-JF13-102Fab Padeye inc Top of Jacket 4 12-May-20 15-May-20 160 15-May-20, Fab Padeye inc Top of Jacket
F2-JK2-JF13-103Blast and Paint Transition Piece 7 06-Jul-20 14-Jul-20 116 14-Jul-20, Blast and Paint Transition Piece
F2-JK2-JF13-11 Fabrication of Strut Plate 18 04-May-20 25-May-20 16 25-May-20, Fabrication of Strut Plate
F2-JK2-JF13-12Fabrication of Internal Platform 21 04-May-20 28-May-20 145 28-May-20, Fabrication of Internal Platform
F2-JK2-JF13-13Fabrication of External Platform 25 04-May-20 02-Jun-20 145 02-Jun-20, Fabrication of External Platform
F2-JK2-JF13-14Assembly Strut Plate 21 25-May-20 18-Jun-20 131 18-Jun-20, Assembly Strut Plate
F2-JK2-JF13-15Fabrication of Ring Stiffener 21 11-Jun-20 06-Jul-20 116 06-Jul-20, Fabrication of Ring Stiffener
F2-JK2-JF13-16Fabrication of Crane Pedestal 21 25-May-20 18-Jun-20 109 18-Jun-20, Fabrication of Crane Pedestal
F2-JK2-JF13-93Galvanizing Handrails 5 14-May-20 20-May-20 134 20-May-20, Galvanizing Handrails
F2-JK2-JF13-94Erect Deck Plate Areas 5 12-May-20 16-May-20 132 16-May-20, Erect Deck Plate Areas
F2-JK2-JF13-95Transition Piece Fabrication Complete 0 06-Jul-20 116 06-Jul-20
F2-JK2-JF13-96Fabrication Assemble Walkways / Platforms 21 25-May-20 18-Jun-20 131 18-Jun-20, Fabrication Assemble Walkways / Platforms
F2-JK2-JF13-97Fit and Weld TP's Equipment Supports 5 12-May-20 19-May-20 132 19-May-20, Fit and Weld TP's Equipment Supports
F2-JK2-JF13-98Plate Profiling for Main Deck 5 04-May-20 11-May-20 87 11-May-20, Plate Profiling for Main Deck
F2-JK2-JF13-99Fab Main Deck Main Steel 5 06-May-20 12-May-20 87 12-May-20, Fab Main Deck Main Steel
Lifting Trunnion 7 12-May-20 20-May-20 87 20-May-20, Lifting Trunnion
F2-JK2-JF13-104Fabricate Lifting Trunion 7 12-May-20 20-May-20 87 20-May-20, Fabricate Lifting Trunion
Boat Landing 44 15-May-20 07-Jul-20 112 07-Jul-20, Boat Landing
F2-JK2-JF13-123Blast and Paint Boat Landing 5 30-Jun-20 07-Jul-20 112 07-Jul-20, Blast and Paint Boat Landing
F2-JK2-JF13-124Fabricate Boat Landing 21 15-May-20 09-Jun-20 45 09-Jun-20, Fabricate Boat Landing
F2-JK2-JF13-159Fabricate Boat Landing Access platform 24 02-Jun-20 30-Jun-20 112 30-Jun-20, Fabricate Boat Landing Access platform
F2-JK2-JF13-160Fabricate Boat Landing Ladders 15 10-Jun-20 27-Jun-20 114 27-Jun-20, Fabricate Boat Landing Ladders
Grouting Line 23 18-Jun-20 15-Jul-20 109 15-Jul-20, Grouting Line
F2-JK2-JF13-126Fabricate Grouting Line & Grouting Line Support 23 18-Jun-20 15-Jul-20 109 15-Jul-20, Fabricate Grouting Line & Grouting Line Support
Assembly 105 20-May-20 18-Sep-20 68 18-Sep-20, Assembly
Row Assembly 88 20-May-20 31-Aug-20 80 31-Aug-20, Row Assembly
F2-JK2-JF13-113Fabricate Upper Grillage & Truss Support 18 20-May-20 10-Jun-20 87 10-Jun-20, Fabricate Upper Grillage & Truss Support
F2-JK2-JF13-114Layout Concrete Blocks/ Grillages and Truss Support Steel 4 18-Jun-20 24-Jun-20 80 24-Jun-20, Layout Concrete Blocks/ Grillages and Truss Support Steel
Row-1 & 2 (Upper Jacket) Assembly 46 24-Jun-20 17-Aug-20 80 17-Aug-20, Row-1 & 2 (Upper Jacket) Assembly

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 56 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF13-115
Installation of Grouting Line 1 11-Jul-20 13-Jul-20 100 13-Jul-20, Installation of Grouting Line
F2-JK2-JF13-117
Installation of J-Tube At Row-1B & 2A 5 11-Jul-20 17-Jul-20 104 17-Jul-20, Installation of J-Tube At Row-1B & 2A
F2-JK2-JF13-118
Row-2 - Touch Up, 2nd Coat & Top Coat 3 13-Aug-20 15-Aug-20 80 15-Aug-20, Row-2 - Touch Up, 2nd Coat & Top Coat
F2-JK2-JF13-119
Installation of Row-1B & 2B X-Brace 7 03-Jul-20 11-Jul-20 80 11-Jul-20, Installation of Row-1B & 2B X-Brace
F2-JK2-JF13-120
Installation of Leg 1A & 1B Onto Support 1 24-Jun-20 25-Jun-20 80 25-Jun-20, Installation of Leg 1A & 1B Onto Support
F2-JK2-JF13-121
Installation of Row-1A & 1B X-Brace 7 25-Jun-20 03-Jul-20 80 03-Jul-20, Installation of Row-1A & 1B X-Brace
F2-JK2-JF13-122
Installation of Row-2A & 2B X-Brace in Final Position 7 05-Aug-20 13-Aug-20 80 13-Aug-20, Installation of Row-2A & 2B X-Brace in Final Position
F2-JK2-JF13-142
Installation of Leg 2A & 2B Onto Support 1 24-Jun-20 25-Jun-20 87 25-Jun-20, Installation of Leg 2A & 2B Onto Support
F2-JK2-JF13-143
Installation of Row-1A & 2A X-Brace 7 03-Jul-20 11-Jul-20 80 11-Jul-20, Installation of Row-1A & 2A X-Brace
F2-JK2-JF13-144
Installation of Row-1A & 1B X-Brace in Final Position 7 28-Jul-20 05-Aug-20 80 05-Aug-20, Installation of Row-1A & 1B X-Brace in Final Position
F2-JK2-JF13-145
Roll Up X-Brace Row A&B to Final Position 7 11-Jul-20 20-Jul-20 80 20-Jul-20, Roll Up X-Brace Row A&B to Final Position
F2-JK2-JF13-146
Installing Tie-back for Fastener 7 20-Jul-20 28-Jul-20 80 28-Jul-20, Installing Tie-back for Fastener
F2-JK2-JF13-147
Installation of Boat Landing 3 13-Aug-20 17-Aug-20 80 17-Aug-20, Installation of Boat Landing
Row-1 & 2 (Lower Jacket) Assembly 44 20-Jun-20 10-Aug-20 85 10-Aug-20, Row-1 & 2 (Lower Jacket) Assembly
F2-JK2-JF13-116
Installation of Pile Stopper 4 21-Jul-20 24-Jul-20 85 24-Jul-20, Installation of Pile Stopper
F2-JK2-JF13-148
Installation of Grouting Line 1 08-Jul-20 09-Jul-20 106 09-Jul-20, Installation of Grouting Line
F2-JK2-JF13-149
Installation of J-Tube At Row-1B & 2A 5 08-Jul-20 14-Jul-20 95 14-Jul-20, Installation of J-Tube At Row-1B & 2A
F2-JK2-JF13-150
Installation of Row-1B & 2B X-Brace 7 30-Jun-20 08-Jul-20 85 08-Jul-20, Installation of Row-1B & 2B X-Brace
F2-JK2-JF13-151
Installation of Leg 1A & 1B Onto Support 1 20-Jun-20 22-Jun-20 85 22-Jun-20, Installation of Leg 1A & 1B Onto Support
F2-JK2-JF13-152
Installation of Row-1A & 1B X-Brace 7 22-Jun-20 30-Jun-20 85 30-Jun-20, Installation of Row-1A & 1B X-Brace
F2-JK2-JF13-153
Installation of Row-2A & 2B X-Brace in Final Position 7 01-Aug-20 10-Aug-20 85 10-Aug-20, Installation of Row-2A & 2B X-Brace in Final Position
F2-JK2-JF13-154
Installation of Leg 2A & 2B Onto Support 1 20-Jun-20 22-Jun-20 92 22-Jun-20, Installation of Leg 2A & 2B Onto Support
F2-JK2-JF13-155
Installation of Row-1A & 2A X-Brace 7 30-Jun-20 08-Jul-20 85 08-Jul-20, Installation of Row-1A & 2A X-Brace
F2-JK2-JF13-156
Installation of Row-1A & 1B X-Brace in Final Position 7 24-Jul-20 01-Aug-20 85 01-Aug-20, Installation of Row-1A & 1B X-Brace in Final Position
F2-JK2-JF13-157
Roll Up X-Brace Row A&B to Final Position 7 08-Jul-20 16-Jul-20 85 16-Jul-20, Roll Up X-Brace Row A&B to Final Position
F2-JK2-JF13-158
Installing Tie-back for Fastener 4 16-Jul-20 21-Jul-20 85 21-Jul-20, Installing Tie-back for Fastener
Grouting Line 40 15-Jul-20 31-Aug-20 80 31-Aug-20, Grouting Line
F2-JK2-JF13-125
Installation Of Grouting Line 5 25-Aug-20 31-Aug-20 80 31-Aug-20, Installation Of Grouting Line
F2-JK2-JF13-127
Installation Grouting Line Support 7 15-Jul-20 23-Jul-20 109 23-Jul-20, Installation Grouting Line Support
Row Roll Up 7 17-Aug-20 25-Aug-20 80 25-Aug-20, Row Roll Up
F2-JK2-JF13-105Roll Up Of Lower Jacket To Final Position 2 17-Aug-20 19-Aug-20 80 19-Aug-20, Roll Up Of Lower Jacket To Final Position
F2-JK2-JF13-106Roll Up Of Upper Jacket To Final Position 5 19-Aug-20 25-Aug-20 80 25-Aug-20, Roll Up Of Upper Jacket To Final Position
Transition Piece (TP) 76 12-Jun-20 09-Sep-20 67 09-Sep-20, Transition Piece (TP)
F2-JK2-JF13-1 Install Door Platform 10 06-Jul-20 17-Jul-20 96 17-Jul-20, Install Door Platform
F2-JK2-JF13-17Installation & Assembly of Ring Stiffener 21 08-Jul-20 01-Aug-20 67 01-Aug-20, Installation & Assembly of Ring Stiffener
F2-JK2-JF13-18Installation of Transition Piece Flange 15 16-Jul-20 03-Aug-20 67 03-Aug-20, Installation of Transition Piece Flange
F2-JK2-JF13-19Install Crane Pedestal 12 18-Jun-20 02-Jul-20 109 02-Jul-20, Install Crane Pedestal
F2-JK2-JF13-2 Blasting & Painting 10 20-Aug-20 01-Sep-20 67 01-Sep-20, Blasting & Painting
F2-JK2-JF13-3 Assemble Can Transition Piece Barrel to Main Deck 15 12-Jun-20 30-Jun-20 67 30-Jun-20, Assemble Can Transition Piece Barrel to Main Deck
F2-JK2-JF13-4 Install Platform & Internal Structure into Upper Can 7 01-Sep-20 09-Sep-20 67 09-Sep-20, Install Platform & Internal Structure into Upper Can
F2-JK2-JF13-5 Door opening & Installation of Door frame 5 30-Jun-20 06-Jul-20 106 06-Jul-20, Door opening & Installation of Door frame
F2-JK2-JF13-6 Installation & Assembly of Strut 15 30-Jun-20 17-Jul-20 67 17-Jul-20, Installation & Assembly of Strut
F2-JK2-JF13-7 Install Free-Issued Items 15 03-Aug-20 20-Aug-20 67 20-Aug-20, Install Free-Issued Items
F2-JK2-JF13-8 Install Architectural items, Electrical & Instrument Equipments 15 30-Jun-20 17-Jul-20 96 17-Jul-20, Install Architectural items, Electrical & Instrument Equipments
F2-JK2-JF13-9 Install External Platform & Handrail 12 03-Jul-20 17-Jul-20 96 17-Jul-20, Install External Platform & Handrail
Final Assembly 8 09-Sep-20 18-Sep-20 68 18-Sep-20, Final Assembly
F2-JK2-JF13-107Installation of Transition Piece 3 09-Sep-20 12-Sep-20 67 12-Sep-20, Installation of Transition Piece
F2-JK2-JF13-108Installation of Mudmad Plate 5 11-Sep-20 17-Sep-20 67 17-Sep-20, Installation of Mudmad Plate
F2-JK2-JF13-109Installation of Lifting Trunnion 4 12-Sep-20 17-Sep-20 69 17-Sep-20, Installation of Lifting Trunnion
F2-JK2-JF13-110Installation of Skirt Pile Sleeve 2 11-Sep-20 14-Sep-20 67 14-Sep-20, Installation of Skirt Pile Sleeve
F2-JK2-JF13-111Final Touch Up Coating 3 15-Sep-20 18-Sep-20 67 18-Sep-20, Final Touch Up Coating
F2-JK2-JF13-112Installation of Lifting Slings 1 14-Sep-20 15-Sep-20 67 15-Sep-20, Installation of Lifting Slings
F2-JK2-JF13-161J acket Fabrication Completed 0 18-Sep-20 67 18-Sep-20
Testing & Commissioning 18 31-Aug-20 21-Sep-20 67 21-Sep-20, Testing & Commissioning
Grouting & Gripper Test 3 31-Aug-20 03-Sep-20 80 03-Sep-20, Grouting & Gripper Test

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 57 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF13-20Gripper Test 2 01-Sep-20 03-Sep-20 80 03-Sep-20, Gripper Test
F2-JK2-JF13-21Grouting Test 1 31-Aug-20 01-Sep-20 80 01-Sep-20, Grouting Test
Mechanical Completion 2 18-Sep-20 21-Sep-20 67 21-Sep-20, Mechanical Completion
F2-JK2-JF13-22Main Structure, Boat Landing, J-Tube, Transition Piece 2 18-Sep-20 21-Sep-20 67 21-Sep-20, Main Structure, Boat Landing, J-Tube, Transition Piece
Jacket & Piles Ready For Loadout 0 21-Sep-20 21-Sep-20 67 21-Sep-20, Jacket & Piles Ready For Loadout
F2-JK2-JF13-23Jacket Ready For Load Out 0 21-Sep-20 67 21-Sep-20
Jacket Foundation 14a 130 30-Apr-20 29-Sep-20 60 29-Sep-20, Jacket Foundation 14a
Fabrication 72 30-Apr-20 23-Jul-20 108 23-Jul-20, Fabrication
Pre-Fabrication 38 30-Apr-20 13-Jun-20 109 13-Jun-20, Pre-Fabrication
F2-JK2-JF14-140Rolling of Can Transition Piece Flange 10 02-Jun-20 13-Jun-20 109 13-Jun-20, Rolling of Can Transition Piece Flange
F2-JK2-JF14-141Rolling of Can Transition Piece Barrel 10 12-May-20 23-May-20 60 23-May-20, Rolling of Can Transition Piece Barrel
F2-JK2-JF14-24Rolling of Can Row 2 Brace 10 30-Apr-20 12-May-20 0 12-May-20, Rolling of Can Row 2 Brace
F2-JK2-JF14-25Rolling of Can Leg 1A & 1B 10 30-Apr-20 12-May-20 73 12-May-20, Rolling of Can Leg 1A & 1B
F2-JK2-JF14-26Rolling of Can Leg 2A & 2B 10 08-May-20 20-May-20 73 20-May-20, Rolling of Can Leg 2A & 2B
F2-JK2-JF14-27Rolling of Node Can Row 1 10 08-May-20 20-May-20 73 20-May-20, Rolling of Node Can Row 1
F2-JK2-JF14-28Rolling of Node Can Row 2 10 16-May-20 28-May-20 73 28-May-20, Rolling of Node Can Row 2
F2-JK2-JF14-29Rolling of Can Row 1 Brace 10 16-May-20 28-May-20 73 28-May-20, Rolling of Can Row 1 Brace
F2-JK2-JF14-30Rolling of J-Tubes & J-Tubes Support 10 25-May-20 05-Jun-20 74 05-Jun-20, Rolling of J-Tubes & J-Tubes Support
F2-JK2-JF14-31Rolling of Can Plan Level Tubular 10 25-May-20 05-Jun-20 109 05-Jun-20, Rolling of Can Plan Level Tubular
F2-JK2-JF14-32Rolling of Can Top Bay X-Brace 10 02-Jun-20 13-Jun-20 109 13-Jun-20, Rolling of Can Top Bay X-Brace
Row 1 Fabrication 42 12-May-20 30-Jun-20 114 30-Jun-20, Row 1 Fabrication
Legs 40 12-May-20 29-Jun-20 76 29-Jun-20, Legs
F2-JK2-JF14-40
Install Stubs on to Leg 1A & 1B Nodes 2 18-Jun-20 20-Jun-20 73 20-Jun-20, Install Stubs on to Leg 1A & 1B Nodes
F2-JK2-JF14-41
Install Anodes on Row-1 Legs 4 19-Jun-20 24-Jun-20 75 24-Jun-20, Install Anodes on Row-1 Legs
F2-JK2-JF14-42
Join of Can Legs 1A 9 16-May-20 27-May-20 88 27-May-20, Join of Can Legs 1A
F2-JK2-JF14-43
Join of Can Legs 1B 9 16-May-20 27-May-20 88 27-May-20, Join of Can Legs 1B
F2-JK2-JF14-44
Mark and Profile Leg 1A & 1B Node 4 20-May-20 25-May-20 98 25-May-20, Mark and Profile Leg 1A & 1B Node
F2-JK2-JF14-45
Profilling of Legs 1A & 1B (Inc. Cones) 4 12-May-20 16-May-20 88 16-May-20, Profilling of Legs 1A & 1B (Inc. Cones)
F2-JK2-JF14-46
Join of Leg 1A & 1B Node 2 19-Jun-20 22-Jun-20 76 22-Jun-20, Join of Leg 1A & 1B Node
F2-JK2-JF14-47
Blasting and Painting for Leg 1A & 1B Node 5 22-Jun-20 29-Jun-20 76 29-Jun-20, Blasting and Painting for Leg 1A & 1B Node
F2-JK2-JF14-48
Assembly Leg 1A 3 17-Jun-20 19-Jun-20 73 19-Jun-20, Assembly Leg 1A
F2-JK2-JF14-49
Assembly Leg 1B 3 17-Jun-20 19-Jun-20 73 19-Jun-20, Assembly Leg 1B
Braces 28 28-May-20 30-Jun-20 73 30-Jun-20, Braces
F2-JK2-JF14-50
Fit & Weld Top X Brace Between Legs 1A & 1B 5 20-Jun-20 26-Jun-20 73 26-Jun-20, Fit & Weld Top X Brace Between Legs 1A & 1B
F2-JK2-JF14-51
Join of Row-1 Can Brace (Inc. Stub) 13 02-Jun-20 17-Jun-20 73 17-Jun-20, Join of Row-1 Can Brace (Inc. Stub)
F2-JK2-JF14-52
Join of Can Brace for Between Row 1 & 2 (Inc. Stub) 13 02-Jun-20 17-Jun-20 73 17-Jun-20, Join of Can Brace for Between Row 1 & 2 (Inc. Stub)
F2-JK2-JF14-53
Assembly of Row-1 Top Brace 4 17-Jun-20 20-Jun-20 73 20-Jun-20, Assembly of Row-1 Top Brace
F2-JK2-JF14-54
Fit & Weld Row-2 K-Brace (Inc. Vertical Braces) 5 20-Jun-20 26-Jun-20 73 26-Jun-20, Fit & Weld Row-2 K-Brace (Inc. Vertical Braces)
F2-JK2-JF14-55
Assembly of Row-1 K-Brace 4 17-Jun-20 20-Jun-20 73 20-Jun-20, Assembly of Row-1 K-Brace
F2-JK2-JF14-56
Fit & Weld X-Brace Between Row 1 & 2 5 20-Jun-20 26-Jun-20 73 26-Jun-20, Fit & Weld X-Brace Between Row 1 & 2
F2-JK2-JF14-57
Assembly of Brace Between Row 1 & 2 4 17-Jun-20 20-Jun-20 73 20-Jun-20, Assembly of Brace Between Row 1 & 2
F2-JK2-JF14-58
Profilling of Row-1 Braces and Stubs 4 28-May-20 02-Jun-20 73 02-Jun-20, Profilling of Row-1 Braces and Stubs
F2-JK2-JF14-59
Install Anodes on Row-1 Braces 4 26-Jun-20 30-Jun-20 73 30-Jun-20, Install Anodes on Row-1 Braces
J-Tubes 19 05-Jun-20 27-Jun-20 116 27-Jun-20, J-Tubes
F2-JK2-JF14-60
Join of Row-1 J-Tubes 5 10-Jun-20 16-Jun-20 116 16-Jun-20, Join of Row-1 J-Tubes
F2-JK2-JF14-61
Profilling of Row-1 J-Tubes 4 05-Jun-20 10-Jun-20 116 10-Jun-20, Profilling of Row-1 J-Tubes
F2-JK2-JF14-62
Bending of Row-1 J-Tubes 4 16-Jun-20 19-Jun-20 116 19-Jun-20, Bending of Row-1 J-Tubes
F2-JK2-JF14-63
Blast and Paint for Row-1 J-Tubes 3 19-Jun-20 24-Jun-20 116 24-Jun-20, Blast and Paint for Row-1 J-Tubes
F2-JK2-JF14-64
Assembly Row-1 J-Tubes 3 24-Jun-20 27-Jun-20 116 27-Jun-20, Assembly Row-1 J-Tubes
F2-JK2-JF14-65
Cut and Profile Row-1 J-Tubes Support 4 05-Jun-20 10-Jun-20 116 10-Jun-20, Cut and Profile Row-1 J-Tubes Support
F2-JK2-JF14-66
Assembly Row-1 J-Tubes Support 2 10-Jun-20 13-Jun-20 116 13-Jun-20, Assembly Row-1 J-Tubes Support
F2-JK2-JF14-67
Paint Row-1 J-Tubes Support 3 13-Jun-20 17-Jun-20 116 17-Jun-20, Paint Row-1 J-Tubes Support
F2-JK2-JF14-68
Install J-Tubes Support on to Row-1 J-Tubes 3 17-Jun-20 19-Jun-20 116 19-Jun-20, Install J-Tubes Support on to Row-1 J-Tubes
Common 23 04-Jun-20 30-Jun-20 74 30-Jun-20, Common
Structure 3 04-Jun-20 08-Jun-20 81 08-Jun-20, Structure

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 58 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF14-33
Marking & Cutting of Leg and Brace Node 3 04-Jun-20 08-Jun-20 81 08-Jun-20, Marking & Cutting of Leg and Brace Node
F2-JK2-JF14-34
Marking & Cutting of Brace Stub 3 04-Jun-20 08-Jun-20 81 08-Jun-20, Marking & Cutting of Brace Stub
F2-JK2-JF14-35
Marking & Cutting of Leg and Brace Member 3 04-Jun-20 08-Jun-20 81 08-Jun-20, Marking & Cutting of Leg and Brace Member
Final Painting 23 04-Jun-20 30-Jun-20 74 30-Jun-20, Final Painting
F2-JK2-JF14-36
Blast and Paint Leg and Brace (Initial Paint) 11 04-Jun-20 17-Jun-20 73 17-Jun-20, Blast and Paint Leg and Brace (Initial Paint)
F2-JK2-JF14-37
Build Painting Habitat Protection 1 26-Jun-20 29-Jun-20 76 29-Jun-20, Build Painting Habitat Protection
F2-JK2-JF14-38
Row-1 Ready for Assembly & Roll-up 0 29-Jun-20 76 29-Jun-20
F2-JK2-JF14-39
Row-1 Touch up and Final Painting 3 26-Jun-20 30-Jun-20 73 30-Jun-20, Row-1 Touch up and Final Painting
Row 2 Fabrication 42 12-May-20 30-Jun-20 74 30-Jun-20, Row 2 Fabrication
Legs 23 20-May-20 16-Jun-20 87 16-Jun-20, Legs
F2-JK2-JF14-76
Install Anodes on Row-2 Legs 4 06-Jun-20 11-Jun-20 86 11-Jun-20, Install Anodes on Row-2 Legs
F2-JK2-JF14-77
Join of Can Legs 2A 9 25-May-20 04-Jun-20 81 04-Jun-20, Join of Can Legs 2A
F2-JK2-JF14-78
Join of Can Legs 2B 9 25-May-20 04-Jun-20 81 04-Jun-20, Join of Can Legs 2B
F2-JK2-JF14-79
Profilling of Legs 2A & 2B (Inc. Cones) 4 20-May-20 25-May-20 81 25-May-20, Profilling of Legs 2A & 2B (Inc. Cones)
F2-JK2-JF14-80
Mark and Profile Leg 2A & 2B Node 4 28-May-20 02-Jun-20 91 02-Jun-20, Mark and Profile Leg 2A & 2B Node
F2-JK2-JF14-81
Join of Leg 2A & 2B Node 2 06-Jun-20 09-Jun-20 87 09-Jun-20, Join of Leg 2A & 2B Node
F2-JK2-JF14-82
Blasting and Painting for Leg 2A & 2B Node (Initial) 5 09-Jun-20 16-Jun-20 87 16-Jun-20, Blasting and Painting for Leg 2A & 2B Node (Initial)
F2-JK2-JF14-83
Assembly Leg 2A 3 04-Jun-20 06-Jun-20 79 06-Jun-20, Assembly Leg 2A
F2-JK2-JF14-84
Assembly Leg 2B 3 04-Jun-20 06-Jun-20 79 06-Jun-20, Assembly Leg 2B
F2-JK2-JF14-85
Install Stubs on to Leg 2A & 2B Nodes 2 06-Jun-20 09-Jun-20 79 09-Jun-20, Install Stubs on to Leg 2A & 2B Nodes
Braces 32 12-May-20 18-Jun-20 79 18-Jun-20, Braces
F2-JK2-JF14-138
Fit & Weld Row-2 K-Brace (Inc. Vertical Braces) 5 09-Jun-20 15-Jun-20 79 15-Jun-20, Fit & Weld Row-2 K-Brace (Inc. Vertical Braces)
F2-JK2-JF14-139
Assembly of Row-2 K-Brace 4 04-Jun-20 08-Jun-20 80 08-Jun-20, Assembly of Row-2 K-Brace
F2-JK2-JF14-86
Fit & Weld Top X-Brace Between Legs 2A & 2B 4 09-Jun-20 13-Jun-20 82 13-Jun-20, Fit & Weld Top X-Brace Between Legs 2A & 2B
F2-JK2-JF14-87
Fit & Weld Mid X-Brace Between Legs 2A & 2B 4 09-Jun-20 13-Jun-20 82 13-Jun-20, Fit & Weld Mid X-Brace Between Legs 2A & 2B
F2-JK2-JF14-88
Join of Row-2 Can Brace (Inc. Stub) 10 16-May-20 28-May-20 79 28-May-20, Join of Row-2 Can Brace (Inc. Stub)
F2-JK2-JF14-89
Assembly of Row-2 Top Brace 3 04-Jun-20 08-Jun-20 83 08-Jun-20, Assembly of Row-2 Top Brace
F2-JK2-JF14-90
Assembly of Row-2 Mid Brace 3 04-Jun-20 08-Jun-20 83 08-Jun-20, Assembly of Row-2 Mid Brace
F2-JK2-JF14-91
Profilling of Row-2 Braces and Stubs 4 12-May-20 16-May-20 79 16-May-20, Profilling of Row-2 Braces and Stubs
F2-JK2-JF14-92
Install Anodes on Row-2 Braces 4 15-Jun-20 18-Jun-20 79 18-Jun-20, Install Anodes on Row-2 Braces
J-Tubes 21 05-Jun-20 30-Jun-20 74 30-Jun-20, J-Tubes
F2-JK2-JF14-128
Join of Row-2 J-Tubes 5 10-Jun-20 16-Jun-20 77 16-Jun-20, Join of Row-2 J-Tubes
F2-JK2-JF14-129
Profilling of Row-2 J-Tubes 4 05-Jun-20 10-Jun-20 77 10-Jun-20, Profilling of Row-2 J-Tubes
F2-JK2-JF14-130
Bending of Row-2 J-Tubes 4 16-Jun-20 19-Jun-20 77 19-Jun-20, Bending of Row-2 J-Tubes
F2-JK2-JF14-131
Blast and Paint for Row-2 J-Tubes 3 23-Jun-20 26-Jun-20 74 26-Jun-20, Blast and Paint for Row-2 J-Tubes
F2-JK2-JF14-132
Assembly Row-2 J-Tubes 3 26-Jun-20 30-Jun-20 74 30-Jun-20, Assembly Row-2 J-Tubes
F2-JK2-JF14-133
Cut and Profile Row-2 J-Tubes Support 4 05-Jun-20 10-Jun-20 74 10-Jun-20, Cut and Profile Row-2 J-Tubes Support
F2-JK2-JF14-134
Assembly Row-2 J-Tubes Support 2 10-Jun-20 13-Jun-20 74 13-Jun-20, Assembly Row-2 J-Tubes Support
F2-JK2-JF14-135
Vulcanized Row-2 J-Tubes Support 2 13-Jun-20 16-Jun-20 74 16-Jun-20, Vulcanized Row-2 J-Tubes Support
F2-JK2-JF14-136
Paint Row-2 J-Tubes Support 3 16-Jun-20 19-Jun-20 74 19-Jun-20, Paint Row-2 J-Tubes Support
F2-JK2-JF14-137
Install J-Tubes Support on to Row-2 J-Tubes 3 19-Jun-20 23-Jun-20 74 23-Jun-20, Install J-Tubes Support on to Row-2 J-Tubes
Common 23 28-May-20 24-Jun-20 79 24-Jun-20, Common
Structure 3 28-May-20 01-Jun-20 83 01-Jun-20, Structure
F2-JK2-JF14-69
Marking & Cutting of Leg and Brace Node 3 28-May-20 01-Jun-20 83 01-Jun-20, Marking & Cutting of Leg and Brace Node
F2-JK2-JF14-70
Marking & Cutting of Brace Stub 3 28-May-20 01-Jun-20 83 01-Jun-20, Marking & Cutting of Brace Stub
F2-JK2-JF14-71
Marking & Cutting of Leg and Brace Member 3 28-May-20 01-Jun-20 83 01-Jun-20, Marking & Cutting of Leg and Brace Member
Final Painting 23 28-May-20 24-Jun-20 79 24-Jun-20, Final Painting
F2-JK2-JF14-72
Row-2 Touch up and Final Painting 3 18-Jun-20 23-Jun-20 79 23-Jun-20, Row-2 Touch up and Final Painting
F2-JK2-JF14-73
Blast and Paint Leg and Brace (Initial Paint) 5 28-May-20 04-Jun-20 79 04-Jun-20, Blast and Paint Leg and Brace (Initial Paint)
F2-JK2-JF14-74
Build Painting Habitat Protection 1 23-Jun-20 24-Jun-20 79 24-Jun-20, Build Painting Habitat Protection
F2-JK2-JF14-75
Row-2 Ready for Assembly & Roll-up 0 24-Jun-20 79 24-Jun-20
Transition Piece 61 12-May-20 22-Jul-20 109 22-Jul-20, Transition Piece
F2-JK2-JF14-10Fabrication of Can Transition Piece Barrel 24 23-May-20 20-Jun-20 60 20-Jun-20, Fabrication of Can Transition Piece Barrel
F2-JK2-JF14-100Fit Grating Supports 4 25-May-20 29-May-20 126 29-May-20, Fit Grating Supports
F2-JK2-JF14-101Fab Main Deck Handrails 4 19-May-20 22-May-20 127 22-May-20, Fab Main Deck Handrails

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 59 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF14-102Fab Padeye inc Top of Jacket 4 20-May-20 23-May-20 153 23-May-20, Fab Padeye inc Top of Jacket
F2-JK2-JF14-103Blast and Paint Transition Piece 7 14-Jul-20 22-Jul-20 109 22-Jul-20, Blast and Paint Transition Piece
F2-JK2-JF14-11 Fabrication of Strut Plate 18 12-May-20 02-Jun-20 16 02-Jun-20, Fabrication of Strut Plate
F2-JK2-JF14-12Fabrication of Internal Platform 21 12-May-20 05-Jun-20 138 05-Jun-20, Fabrication of Internal Platform
F2-JK2-JF14-13Fabrication of External Platform 25 12-May-20 10-Jun-20 138 10-Jun-20, Fabrication of External Platform
F2-JK2-JF14-14Assembly Strut Plate 21 02-Jun-20 26-Jun-20 124 26-Jun-20, Assembly Strut Plate
F2-JK2-JF14-15Fabrication of Ring Stiffener 21 19-Jun-20 14-Jul-20 109 14-Jul-20, Fabrication of Ring Stiffener
F2-JK2-JF14-16Fabrication of Crane Pedestal 21 02-Jun-20 26-Jun-20 102 26-Jun-20, Fabrication of Crane Pedestal
F2-JK2-JF14-93Galvanizing Handrails 5 22-May-20 28-May-20 127 28-May-20, Galvanizing Handrails
F2-JK2-JF14-94Erect Deck Plate Areas 5 20-May-20 25-May-20 125 25-May-20, Erect Deck Plate Areas
F2-JK2-JF14-95Transition Piece Fabrication Complete 0 14-Jul-20 109 14-Jul-20
F2-JK2-JF14-96Fabrication Assemble Walkways / Platforms 21 02-Jun-20 26-Jun-20 124 26-Jun-20, Fabrication Assemble Walkways / Platforms
F2-JK2-JF14-97Fit and Weld TP's Equipment Supports 5 20-May-20 27-May-20 125 27-May-20, Fit and Weld TP's Equipment Supports
F2-JK2-JF14-98Plate Profiling for Main Deck 5 12-May-20 19-May-20 80 19-May-20, Plate Profiling for Main Deck
F2-JK2-JF14-99Fab Main Deck Main Steel 5 14-May-20 20-May-20 80 20-May-20, Fab Main Deck Main Steel
Lifting Trunnion 7 20-May-20 28-May-20 80 28-May-20, Lifting Trunnion
F2-JK2-JF14-104Fabricate Lifting Trunion 7 20-May-20 28-May-20 80 28-May-20, Fabricate Lifting Trunion
Boat Landing 44 23-May-20 15-Jul-20 105 15-Jul-20, Boat Landing
F2-JK2-JF14-123Blast and Paint Boat Landing 5 08-Jul-20 15-Jul-20 105 15-Jul-20, Blast and Paint Boat Landing
F2-JK2-JF14-124Fabricate Boat Landing 21 23-May-20 17-Jun-20 45 17-Jun-20, Fabricate Boat Landing
F2-JK2-JF14-159Fabricate Boat Landing Access platform 24 10-Jun-20 08-Jul-20 105 08-Jul-20, Fabricate Boat Landing Access platform
F2-JK2-JF14-160Fabricate Boat Landing Ladders 15 18-Jun-20 06-Jul-20 107 06-Jul-20, Fabricate Boat Landing Ladders
Grouting Line 23 26-Jun-20 23-Jul-20 102 23-Jul-20, Grouting Line
F2-JK2-JF14-126Fabricate Grouting Line & Grouting Line Support 23 26-Jun-20 23-Jul-20 102 23-Jul-20, Fabricate Grouting Line & Grouting Line Support
Assembly 105 28-May-20 26-Sep-20 61 26-Sep-20, Assembly
Row Assembly 88 28-May-20 08-Sep-20 73 08-Sep-20, Row Assembly
F2-JK2-JF14-113Fabricate Upper Grillage & Truss Support 18 28-May-20 18-Jun-20 80 18-Jun-20, Fabricate Upper Grillage & Truss Support
F2-JK2-JF14-114Layout Concrete Blocks/ Grillages and Truss Support Steel 4 26-Jun-20 02-Jul-20 73 02-Jul-20, Layout Concrete Blocks/ Grillages and Truss Support Steel
Row-1 & 2 (Upper Jacket) Assembly 46 02-Jul-20 25-Aug-20 73 25-Aug-20, Row-1 & 2 (Upper Jacket) Assembly
F2-JK2-JF14-115
Installation of Grouting Line 1 20-Jul-20 21-Jul-20 93 21-Jul-20, Installation of Grouting Line
F2-JK2-JF14-117
Installation of J-Tube At Row-1B & 2A 5 20-Jul-20 25-Jul-20 97 25-Jul-20, Installation of J-Tube At Row-1B & 2A
F2-JK2-JF14-118
Row-2 - Touch Up, 2nd Coat & Top Coat 3 21-Aug-20 24-Aug-20 73 24-Aug-20, Row-2 - Touch Up, 2nd Coat & Top Coat
F2-JK2-JF14-119
Installation of Row-1B & 2B X-Brace 7 11-Jul-20 20-Jul-20 73 20-Jul-20, Installation of Row-1B & 2B X-Brace
F2-JK2-JF14-120
Installation of Leg 1A & 1B Onto Support 1 02-Jul-20 03-Jul-20 73 03-Jul-20, Installation of Leg 1A & 1B Onto Support
F2-JK2-JF14-121
Installation of Row-1A & 1B X-Brace 7 03-Jul-20 11-Jul-20 73 11-Jul-20, Installation of Row-1A & 1B X-Br ace
F2-JK2-JF14-122
Installation of Row-2A & 2B X-Brace in Final Position 7 13-Aug-20 21-Aug-20 73 21-Aug-20, Installation of Row-2A & 2B X-Brace in Final Position
F2-JK2-JF14-142
Installation of Leg 2A & 2B Onto Support 1 02-Jul-20 03-Jul-20 80 03-Jul-20, Installation of Leg 2A & 2B Onto Support
F2-JK2-JF14-143
Installation of Row-1A & 2A X-Brace 7 11-Jul-20 20-Jul-20 73 20-Jul-20, Installation of Row-1A & 2A X-Brace
F2-JK2-JF14-144
Installation of Row-1A & 1B X-Brace in Final Position 7 05-Aug-20 13-Aug-20 73 13-Aug-20, Installation of Row-1A & 1B X-Brace in Final Position
F2-JK2-JF14-145
Roll Up X-Brace Row A&B to Final Position 7 20-Jul-20 28-Jul-20 73 28-Jul-20, Roll Up X-Brace Row A&B to Final Position
F2-JK2-JF14-146
Installing Tie-back for Fastener 7 28-Jul-20 05-Aug-20 73 05-Aug-20, Installing Tie-back for Fastener
F2-JK2-JF14-147
Installation of Boat Landing 3 21-Aug-20 25-Aug-20 73 25-Aug-20, Installation of Boat Landing
Row-1 & 2 (Lower Jacket) Assembly 44 29-Jun-20 18-Aug-20 78 18-Aug-20, Row-1 & 2 (Lower Jacket) Assembly
F2-JK2-JF14-116
Installation of Pile Stopper 4 29-Jul-20 01-Aug-20 78 01-Aug-20, Installation of Pile Stopper
F2-JK2-JF14-148
Installation of Grouting Line 1 16-Jul-20 17-Jul-20 99 17-Jul-20, Installation of Grouting Line
F2-JK2-JF14-149
Installation of J-Tube At Row-1B & 2A 5 16-Jul-20 22-Jul-20 88 22-Jul-20, Installation of J-Tube At Row-1B & 2A
F2-JK2-JF14-150
Installation of Row-1B & 2B X-Brace 7 08-Jul-20 16-Jul-20 78 16-Jul-20, Installation of Row-1B & 2B X-Brace
F2-JK2-JF14-151
Installation of Leg 1A & 1B Onto Support 1 29-Jun-20 30-Jun-20 78 30-Jun-20, Installation of Leg 1A & 1B Onto Support
F2-JK2-JF14-152
Installation of Row-1A & 1B X-Brace 7 30-Jun-20 08-Jul-20 78 08-Jul-20, Installation of Row-1A & 1B X-Brace
F2-JK2-JF14-153
Installation of Row-2A & 2B X-Brace in Final Position 7 10-Aug-20 18-Aug-20 78 18-Aug-20, Installation of Row-2A & 2B X-Brace in Final Position
F2-JK2-JF14-154
Installation of Leg 2A & 2B Onto Support 1 29-Jun-20 30-Jun-20 85 30-Jun-20, Installation of Leg 2A & 2B Onto Support
F2-JK2-JF14-155
Installation of Row-1A & 2A X-Brace 7 08-Jul-20 16-Jul-20 78 16-Jul-20, Installation of Row-1A & 2A X-Brace
F2-JK2-JF14-156
Installation of Row-1A & 1B X-Brace in Final Position 7 01-Aug-20 10-Aug-20 78 10-Aug-20, Installation of Row-1A & 1B X-Brace in Final Position
F2-JK2-JF14-157
Roll Up X-Brace Row A&B to Final Position 7 16-Jul-20 24-Jul-20 78 24-Jul-20, Roll Up X-Brace Row A&B to Final Position
F2-JK2-JF14-158
Installing Tie-back for Fastener 4 24-Jul-20 29-Jul-20 78 29-Jul-20, Installing Tie-back for Fastener

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 60 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
Grouting Line 40 23-Jul-20 08-Sep-20 73 08-Sep-20, Grouting Line
F2-JK2-JF14-125
Installation Of Grouting Line 5 02-Sep-20 08-Sep-20 73 08-Sep-20, Installation Of Grouting Line
F2-JK2-JF14-127
Installation Grouting Line Support 7 23-Jul-20 31-Jul-20 102 31-Jul-20, Installation Grouting Line Support
Row Roll Up 7 25-Aug-20 02-Sep-20 73 02-Sep-20, Row Roll Up
F2-JK2-JF14-105Roll Up Of Lower Jacket To Final Position 2 25-Aug-20 27-Aug-20 73 27-Aug-20, Roll Up Of Lower Jacket To Final Position
F2-JK2-JF14-106Roll Up Of Upper Jacket To Final Position 5 27-Aug-20 02-Sep-20 73 02-Sep-20, Roll Up Of Upper Jacket To Final Position
Transition Piece (TP) 76 20-Jun-20 17-Sep-20 60 17-Sep-20, Transition Piece (TP)
F2-JK2-JF14-1 Install Door Platform 10 14-Jul-20 25-Jul-20 89 25-Jul-20, Install Door Platform
F2-JK2-JF14-17Installation & Assembly of Ring Stiffener 21 16-Jul-20 10-Aug-20 60 10-Aug-20, Installation & Assembly of Ring Stiffener
F2-JK2-JF14-18Installation of Transition Piece Flange 15 24-Jul-20 11-Aug-20 60 11-Aug-20, Installation of Transition Piece Flange
F2-JK2-JF14-19Install Crane Pedestal 12 26-Jun-20 10-Jul-20 102 10-Jul-20, Install Crane Pedestal
F2-JK2-JF14-2 Blasting & Painting 10 28-Aug-20 09-Sep-20 60 09-Sep-20, Blasting & Painting
F2-JK2-JF14-3 Assemble Can Transition Piece Barrel to Main Deck 15 20-Jun-20 08-Jul-20 60 08-Jul-20, Assemble Can Transition Piece Barrel to Main Deck
F2-JK2-JF14-4 Install Platform & Internal Structure into Upper Can 7 09-Sep-20 17-Sep-20 60 17-Sep-20, Install Platform & Internal Structure into Upper Can
F2-JK2-JF14-5 Door opening & Installation of Door frame 5 08-Jul-20 14-Jul-20 99 14-Jul-20, Door opening & Installation of Door frame
F2-JK2-JF14-6 Installation & Assembly of Strut 15 08-Jul-20 25-Jul-20 60 25-Jul-20, Installation & Assembly of Strut
F2-JK2-JF14-7 Install Free-Issued Items 15 11-Aug-20 28-Aug-20 60 28-Aug-20, Install Free-Issued Items
F2-JK2-JF14-8 Install Architectural items, Electrical & Instrument Equipments 15 08-Jul-20 25-Jul-20 89 25-Jul-20, Install Architectural items, Electrical & Instrument Equipments
F2-JK2-JF14-9 Install External Platform & Handrail 12 11-Jul-20 25-Jul-20 89 25-Jul-20, Install External Platform & Handrail
Final Assembly 8 17-Sep-20 26-Sep-20 61 26-Sep-20, Final Assembly
F2-JK2-JF14-107Installation of Transition Piece 3 17-Sep-20 21-Sep-20 60 21-Sep-20, Installation of Transition Piece
F2-JK2-JF14-108Installation of Mudmad Plate 5 19-Sep-20 25-Sep-20 60 25-Sep-20, Installation of Mudmad Plate
F2-JK2-JF14-109Installation of Lifting Trunnion 4 21-Sep-20 25-Sep-20 62 25-Sep-20, Installation of Lifting Trunnion
F2-JK2-JF14-110Installation of Skirt Pile Sleeve 2 19-Sep-20 22-Sep-20 60 22-Sep-20, Installation of Skirt Pile Sleeve
F2-JK2-JF14-111Final Touch Up Coating 3 23-Sep-20 26-Sep-20 60 26-Sep-20, Final Touch Up Coating
F2-JK2-JF14-112Installation of Lifting Slings 1 22-Sep-20 23-Sep-20 60 23-Sep-20, Installation of Lifting Slings
F2-JK2-JF14-161J acket Fabrication Completed 0 26-Sep-20 60 26-Sep-20
Testing & Commissioning 18 08-Sep-20 29-Sep-20 60 29-Sep-20, Testing & Commissioning
Grouting & Gripper Test 3 08-Sep-20 11-Sep-20 73 11-Sep-20, Grouting & Gripper Test
F2-JK2-JF14-20Gripper Test 2 09-Sep-20 11-Sep-20 73 11-Sep-20, Gripper Test
F2-JK2-JF14-21Grouting Test 1 08-Sep-20 09-Sep-20 73 09-Sep-20, Grouting Test
Mechanical Completion 2 26-Sep-20 29-Sep-20 60 29-Sep-20, Mechanical Completion
F2-JK2-JF14-22Main Structure, Boat Landing, J-Tube, Transition Piece 2 26-Sep-20 29-Sep-20 60 29-Sep-20, Main Structure, Boat Landing, J-Tube, Transition Piece
Jacket & Piles Ready For Loadout 0 29-Sep-20 29-Sep-20 60 29-Sep-20, Jacket & Piles Ready For Loadout
F2-JK2-JF14-23Jacket Ready For Load Out 0 29-Sep-20 60 29-Sep-20
Jacket Foundation 15a 130 08-May-20 07-Oct-20 0 07-Oct-20, Jacket Foundation 15a
Fabrication 72 08-May-20 31-Jul-20 48 31-Jul-20, Fabrication
Pre-Fabrication 38 08-May-20 22-Jun-20 49 22-Jun-20, Pre-Fabrication
F2-JK2-JF15-140Rolling of Can Transition Piece Flange 10 10-Jun-20 22-Jun-20 49 22-Jun-20, Rolling of Can Transition Piece Flange
F2-JK2-JF15-141Rolling of Can Transition Piece Barrel 10 20-May-20 01-Jun-20 0 01-Jun-20, Rolling of Can Transition Piece Barrel
F2-JK2-JF15-24Rolling of Can Row 2 Brace 10 08-May-20 20-May-20 0 20-May-20, Rolling of Can Row 2 Brace
F2-JK2-JF15-25Rolling of Can Leg 1A & 1B 10 08-May-20 20-May-20 13 20-May-20, Rolling of Can Leg 1A & 1B
F2-JK2-JF15-26Rolling of Can Leg 2A & 2B 10 16-May-20 28-May-20 13 28-May-20, Rolling of Can Leg 2A & 2B
F2-JK2-JF15-27Rolling of Node Can Row 1 10 16-May-20 28-May-20 13 28-May-20, Rolling of Node Can Row 1
F2-JK2-JF15-28Rolling of Node Can Row 2 10 25-May-20 05-Jun-20 13 05-Jun-20, Rolling of Node Can Row 2
F2-JK2-JF15-29Rolling of Can Row 1 Brace 10 25-May-20 05-Jun-20 13 05-Jun-20, Rolling of Can Row 1 Brace
F2-JK2-JF15-30Rolling of J-Tubes & J-Tubes Support 10 02-Jun-20 13-Jun-20 14 13-Jun-20, Rolling of J-Tubes & J-Tubes Support
F2-JK2-JF15-31Rolling of Can Plan Level Tubular 10 02-Jun-20 13-Jun-20 49 13-Jun-20, Rolling of Can Plan Level Tubular
F2-JK2-JF15-32Rolling of Can Top Bay X-Brace 10 10-Jun-20 22-Jun-20 49 22-Jun-20, Rolling of Can Top Bay X-Brace
Row 1 Fabrication 42 20-May-20 08-Jul-20 54 08-Jul-20, Row 1 Fabrication
Legs 40 20-May-20 07-Jul-20 16 07-Jul-20, Legs
F2-JK2-JF15-40
Install Stubs on to Leg 1A & 1B Nodes 2 26-Jun-20 29-Jun-20 13 29-Jun-20, Install Stubs on to Leg 1A & 1B Nodes
F2-JK2-JF15-41
Install Anodes on Row-1 Legs 4 27-Jun-20 02-Jul-20 15 02-Jul-20, Install Anodes on Row-1 Legs
F2-JK2-JF15-42
Join of Can Legs 1A 9 25-May-20 04-Jun-20 28 04-Jun-20, Join of Can Legs 1A
F2-JK2-JF15-43
Join of Can Legs 1B 9 25-May-20 04-Jun-20 28 04-Jun-20, Join of Can Legs 1B

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 61 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF15-44
Mark and Profile Leg 1A & 1B Node 4 28-May-20 02-Jun-20 38 02-Jun-20, Mark and Profile Leg 1A & 1B Node
F2-JK2-JF15-45
Profilling of Legs 1A & 1B (Inc. Cones) 4 20-May-20 25-May-20 28 25-May-20, Profilling of Legs 1A & 1B (Inc. Cones)
F2-JK2-JF15-46
Join of Leg 1A & 1B Node 2 27-Jun-20 30-Jun-20 16 30-Jun-20, Join of Leg 1A & 1B Node
F2-JK2-JF15-47
Blasting and Painting for Leg 1A & 1B Node 5 30-Jun-20 07-Jul-20 16 07-Jul-20, Blasting and Painting for Leg 1A & 1B Node
F2-JK2-JF15-48
Assembly Leg 1A 3 25-Jun-20 27-Jun-20 13 27-Jun-20, Assembly Leg 1A
F2-JK2-JF15-49
Assembly Leg 1B 3 25-Jun-20 27-Jun-20 13 27-Jun-20, Assembly Leg 1B
Braces 28 05-Jun-20 08-Jul-20 13 08-Jul-20, Braces
F2-JK2-JF15-50
Fit & Weld Top X Brace Between Legs 1A & 1B 5 29-Jun-20 04-Jul-20 13 04-Jul-20, Fit & Weld Top X Brace Between Legs 1A & 1B
F2-JK2-JF15-51
Join of Row-1 Can Brace (Inc. Stub) 13 10-Jun-20 25-Jun-20 13 25-Jun-20, Join of Row-1 Can Brace (Inc. Stub)
F2-JK2-JF15-52
Join of Can Brace for Between Row 1 & 2 (Inc. Stub) 13 10-Jun-20 25-Jun-20 13 25-Jun-20, Join of Can Brace for Between Row 1 & 2 (Inc. Stub)
F2-JK2-JF15-53
Assembly of Row-1 Top Brace 4 25-Jun-20 29-Jun-20 13 29-Jun-20, Assembly of Row-1 Top Brace
F2-JK2-JF15-54
Fit & Weld Row-2 K-Brace (Inc. Vertical Braces) 5 29-Jun-20 04-Jul-20 13 04-Jul-20, Fit & Weld Row-2 K-Brace (Inc. Vertical Braces)
F2-JK2-JF15-55
Assembly of Row-1 K-Brace 4 25-Jun-20 29-Jun-20 13 29-Jun-20, Assembly of Row-1 K-Brace
F2-JK2-JF15-56
Fit & Weld X-Brace Between Row 1 & 2 5 29-Jun-20 04-Jul-20 13 04-Jul-20, Fit & Weld X-Brace Between Row 1 & 2
F2-JK2-JF15-57
Assembly of Brace Between Row 1 & 2 4 25-Jun-20 29-Jun-20 13 29-Jun-20, Assembly of Brace Between Row 1 & 2
F2-JK2-JF15-58
Profilling of Row-1 Braces and Stubs 4 05-Jun-20 10-Jun-20 13 10-Jun-20, Profilling of Row-1 Braces and Stubs
F2-JK2-JF15-59
Install Anodes on Row-1 Braces 4 04-Jul-20 08-Jul-20 13 08-Jul-20, Install Anodes on Row-1 Braces
J-Tubes 19 13-Jun-20 06-Jul-20 56 06-Jul-20, J-Tubes
F2-JK2-JF15-60
Join of Row-1 J-Tubes 5 18-Jun-20 24-Jun-20 56 24-Jun-20, Join of Row-1 J-Tubes
F2-JK2-JF15-61
Profilling of Row-1 J-Tubes 4 13-Jun-20 18-Jun-20 56 18-Jun-20, Profilling of Row-1 J-Tubes
F2-JK2-JF15-62
Bending of Row-1 J-Tubes 4 24-Jun-20 27-Jun-20 56 27-Jun-20, Bending of Row-1 J-Tubes
F2-JK2-JF15-63
Blast and Paint for Row-1 J-Tubes 3 27-Jun-20 02-Jul-20 56 02-Jul-20, Blast and Paint for Row-1 J-Tubes
F2-JK2-JF15-64
Assembly Row-1 J-Tubes 3 02-Jul-20 06-Jul-20 56 06-Jul-20, Assembly Row-1 J-Tubes
F2-JK2-JF15-65
Cut and Profile Row-1 J-Tubes Support 4 13-Jun-20 18-Jun-20 56 18-Jun-20, Cut and Profile Row-1 J-Tubes Support
F2-JK2-JF15-66
Assembly Row-1 J-Tubes Support 2 18-Jun-20 22-Jun-20 56 22-Jun-20, Assembly Row-1 J-Tubes Support
F2-JK2-JF15-67
Paint Row-1 J-Tubes Support 3 22-Jun-20 25-Jun-20 56 25-Jun-20, Paint Row-1 J-Tubes Support
F2-JK2-JF15-68
Install J-Tubes Support on to Row-1 J-Tubes 3 25-Jun-20 27-Jun-20 56 27-Jun-20, Install J-Tubes Support on to Row-1 J-Tubes
Common 23 12-Jun-20 08-Jul-20 14 08-Jul-20, Common
Structure 3 12-Jun-20 16-Jun-20 21 16-Jun-20, Structure
F2-JK2-JF15-33
Marking & Cutting of Leg and Brace Node 3 12-Jun-20 16-Jun-20 21 16-Jun-20, Marking & Cutting of Leg and Brace Node
F2-JK2-JF15-34
Marking & Cutting of Brace Stub 3 12-Jun-20 16-Jun-20 21 16-Jun-20, Marking & Cutting of Brace Stub
F2-JK2-JF15-35
Marking & Cutting of Leg and Brace Member 3 12-Jun-20 16-Jun-20 21 16-Jun-20, Marking & Cutting of Leg and Brace Member
Final Painting 23 12-Jun-20 08-Jul-20 14 08-Jul-20, Final Painting
F2-JK2-JF15-36
Blast and Paint Leg and Brace (Initial Paint) 11 12-Jun-20 25-Jun-20 13 25-Jun-20, Blast and Paint Leg and Brace (Initial Paint)
F2-JK2-JF15-37
Build Painting Habitat Protection 1 04-Jul-20 07-Jul-20 16 07-Jul-20, Build Painting Habitat Protection
F2-JK2-JF15-38
Row-1 Ready for Assembly & Roll-up 0 07-Jul-20 16 07-Jul-20
F2-JK2-JF15-39
Row-1 Touch up and Final Painting 3 04-Jul-20 08-Jul-20 13 08-Jul-20, Row-1 Touch up and Final Painting
Row 2 Fabrication 42 20-May-20 08-Jul-20 14 08-Jul-20, Row 2 Fabrication
Legs 23 28-May-20 24-Jun-20 27 24-Jun-20, Legs
F2-JK2-JF15-76
Install Anodes on Row-2 Legs 4 15-Jun-20 19-Jun-20 26 19-Jun-20, Install Anodes on Row-2 Legs
F2-JK2-JF15-77
Join of Can Legs 2A 9 02-Jun-20 12-Jun-20 21 12-Jun-20, Join of Can Legs 2A
F2-JK2-JF15-78
Join of Can Legs 2B 9 02-Jun-20 12-Jun-20 21 12-Jun-20, Join of Can Legs 2B
F2-JK2-JF15-79
Profilling of Legs 2A & 2B (Inc. Cones) 4 28-May-20 02-Jun-20 21 02-Jun-20, Profilling of Legs 2A & 2B (Inc. Cones)
F2-JK2-JF15-80
Mark and Profile Leg 2A & 2B Node 4 05-Jun-20 10-Jun-20 31 10-Jun-20, Mark and Profile Leg 2A & 2B Node
F2-JK2-JF15-81
Join of Leg 2A & 2B Node 2 15-Jun-20 17-Jun-20 27 17-Jun-20, Join of Leg 2A & 2B Node
F2-JK2-JF15-82
Blasting and Painting for Leg 2A & 2B Node (Initial) 5 17-Jun-20 24-Jun-20 27 24-Jun-20, Blasting and Painting for Leg 2A & 2B Node (Initial)
F2-JK2-JF15-83
Assembly Leg 2A 3 12-Jun-20 15-Jun-20 19 15-Jun-20, Assembly Leg 2A
F2-JK2-JF15-84
Assembly Leg 2B 3 12-Jun-20 15-Jun-20 19 15-Jun-20, Assembly Leg 2B
F2-JK2-JF15-85
Install Stubs on to Leg 2A & 2B Nodes 2 15-Jun-20 17-Jun-20 19 17-Jun-20, Install Stubs on to Leg 2A & 2B Nodes
Braces 32 20-May-20 26-Jun-20 19 26-Jun-20, Braces
F2-JK2-JF15-138
Fit & Weld Row-2 K-Brace (Inc. Vertical Braces) 5 17-Jun-20 23-Jun-20 19 23-Jun-20, Fit & Weld Row-2 K-Brace (Inc. Vertical Braces)
F2-JK2-JF15-139
Assembly of Row-2 K-Brace 4 12-Jun-20 16-Jun-20 20 16-Jun-20, Assembly of Row-2 K-Brace
F2-JK2-JF15-86
Fit & Weld Top X-Brace Between Legs 2A & 2B 4 17-Jun-20 22-Jun-20 22 22-Jun-20, Fit & Weld Top X-Brace Between Legs 2A & 2B
F2-JK2-JF15-87
Fit & Weld Mid X-Brace Between Legs 2A & 2B 4 17-Jun-20 22-Jun-20 22 22-Jun-20, Fit & Weld Mid X-Brace Between Legs 2A & 2B
F2-JK2-JF15-88
Join of Row-2 Can Brace (Inc. Stub) 10 25-May-20 05-Jun-20 19 05-Jun-20, Join of Row-2 Can Brace (Inc. Stub)

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 62 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF15-89
Assembly of Row-2 Top Brace 3 12-Jun-20 16-Jun-20 23 16-Jun-20, Assembly of Row-2 Top Brace
F2-JK2-JF15-90
Assembly of Row-2 Mid Brace 3 12-Jun-20 16-Jun-20 23 16-Jun-20, Assembly of Row-2 Mid Brace
F2-JK2-JF15-91
Profilling of Row-2 Braces and Stubs 4 20-May-20 25-May-20 19 25-May-20, Profilling of Row-2 Braces and Stubs
F2-JK2-JF15-92
Install Anodes on Row-2 Braces 4 23-Jun-20 26-Jun-20 19 26-Jun-20, Install Anodes on Row-2 Braces
J-Tubes 21 13-Jun-20 08-Jul-20 14 08-Jul-20, J-Tubes
F2-JK2-JF15-128
Join of Row-2 J-Tubes 5 18-Jun-20 24-Jun-20 17 24-Jun-20, Join of Row-2 J-Tubes
F2-JK2-JF15-129
Profilling of Row-2 J-Tubes 4 13-Jun-20 18-Jun-20 17 18-Jun-20, Profilling of Row-2 J-Tubes
F2-JK2-JF15-130
Bending of Row-2 J-Tubes 4 24-Jun-20 27-Jun-20 17 27-Jun-20, Bending of Row-2 J-Tubes
F2-JK2-JF15-131
Blast and Paint for Row-2 J-Tubes 3 01-Jul-20 04-Jul-20 14 04-Jul-20, Blast and Paint for Row-2 J-Tubes
F2-JK2-JF15-132
Assembly Row-2 J-Tubes 3 04-Jul-20 08-Jul-20 14 08-Jul-20, Assembly Row-2 J-Tubes
F2-JK2-JF15-133
Cut and Profile Row-2 J-Tubes Support 4 13-Jun-20 18-Jun-20 14 18-Jun-20, Cut and Profile Row-2 J-Tubes Support
F2-JK2-JF15-134
Assembly Row-2 J-Tubes Support 2 18-Jun-20 22-Jun-20 14 22-Jun-20, Assembly Row-2 J-Tubes Support
F2-JK2-JF15-135
Vulcanized Row-2 J-Tubes Support 2 22-Jun-20 24-Jun-20 14 24-Jun-20, Vulcanized Row-2 J-Tubes Support
F2-JK2-JF15-136
Paint Row-2 J-Tubes Support 3 24-Jun-20 27-Jun-20 14 27-Jun-20, Paint Row-2 J-Tubes Support
F2-JK2-JF15-137
Install J-Tubes Support on to Row-2 J-Tubes 3 27-Jun-20 01-Jul-20 14 01-Jul-20, Install J-Tubes Support on to Row-2 J-Tubes
Common 23 05-Jun-20 02-Jul-20 19 02-Jul-20, Common
Structure 3 05-Jun-20 09-Jun-20 23 09-Jun-20, Structure
F2-JK2-JF15-69
Marking & Cutting of Leg and Brace Node 3 05-Jun-20 09-Jun-20 23 09-Jun-20, Marking & Cutting of Leg and Brace Node
F2-JK2-JF15-70
Marking & Cutting of Brace Stub 3 05-Jun-20 09-Jun-20 23 09-Jun-20, Marking & Cutting of Brace Stub
F2-JK2-JF15-71
Marking & Cutting of Leg and Brace Member 3 05-Jun-20 09-Jun-20 23 09-Jun-20, Marking & Cutting of Leg and Brace Member
Final Painting 23 05-Jun-20 02-Jul-20 19 02-Jul-20, Final Painting
F2-JK2-JF15-72
Row-2 Touch up and Final Painting 3 26-Jun-20 01-Jul-20 19 01-Jul-20, Row-2 Touch up and Final Painting
F2-JK2-JF15-73
Blast and Paint Leg and Brace (Initial Paint) 5 05-Jun-20 12-Jun-20 19 12-Jun-20, Blast and Paint Leg and Brace (Initial Paint)
F2-JK2-JF15-74
Build Painting Habitat Protection 1 01-Jul-20 02-Jul-20 19 02-Jul-20, Build Painting Habitat Protection
F2-JK2-JF15-75
Row-2 Ready for Assembly & Roll-up 0 02-Jul-20 19 02-Jul-20
Transition Piece 61 20-May-20 30-Jul-20 49 30-Jul-20, Transition Piece
F2-JK2-JF15-10Fabrication of Can Transition Piece Barrel 24 01-Jun-20 29-Jun-20 0 29-Jun-20, Fabrication of Can Transition Piece Barrel
F2-JK2-JF15-100Fit Grating Supports 4 02-Jun-20 06-Jun-20 66 06-Jun-20, Fit Grating Supports
F2-JK2-JF15-101Fab Main Deck Handrails 4 27-May-20 30-May-20 67 30-May-20, Fab Main Deck Handrails
F2-JK2-JF15-102Fab Padeye inc Top of Jacket 4 28-May-20 01-Jun-20 93 01-Jun-20, Fab Padeye inc Top of Jacket
F2-JK2-JF15-103Blast and Paint Transition Piece 7 22-Jul-20 30-Jul-20 49 30-Jul-20, Blast and Paint Transition Piece
F2-JK2-JF15-11 Fabrication of Strut Plate 18 20-May-20 10-Jun-20 16 10-Jun-20, Fabrication of Strut Plate
F2-JK2-JF15-12Fabrication of Internal Platform 21 20-May-20 13-Jun-20 78 13-Jun-20, Fabrication of Internal Platform
F2-JK2-JF15-13Fabrication of External Platform 25 20-May-20 18-Jun-20 78 18-Jun-20, Fabrication of External Platform
F2-JK2-JF15-14Assembly Strut Plate 21 10-Jun-20 04-Jul-20 64 04-Jul-20, Assembly Strut Plate
F2-JK2-JF15-15Fabrication of Ring Stiffener 21 27-Jun-20 22-Jul-20 49 22-Jul-20, Fabrication of Ring Stiffener
F2-JK2-JF15-16Fabrication of Crane Pedestal 21 10-Jun-20 04-Jul-20 42 04-Jul-20, Fabrication of Crane Pedestal
F2-JK2-JF15-93Galvanizing Handrails 5 30-May-20 05-Jun-20 67 05-Jun-20, Galvanizing Handrails
F2-JK2-JF15-94Erect Deck Plate Areas 5 28-May-20 02-Jun-20 65 02-Jun-20, Erect Deck Plate Areas
F2-JK2-JF15-95Transition Piece Fabrication Complete 0 22-Jul-20 49 22-Jul-20
F2-JK2-JF15-96Fabrication Assemble Walkways / Platforms 21 10-Jun-20 04-Jul-20 64 04-Jul-20, Fabrication Assemble Walkways / Platforms
F2-JK2-JF15-97Fit and Weld TP's Equipment Supports 5 28-May-20 04-Jun-20 65 04-Jun-20, Fit and Weld TP's Equipment Supports
F2-JK2-JF15-98Plate Profiling for Main Deck 5 20-May-20 27-May-20 20 27-May-20, Plate Profiling for Main Deck
F2-JK2-JF15-99Fab Main Deck Main Steel 5 22-May-20 28-May-20 20 28-May-20, Fab Main Deck Main Steel
Lifting Trunnion 7 28-May-20 05-Jun-20 20 05-Jun-20, Lifting Trunnion
F2-JK2-JF15-104Fabricate Lifting Trunion 7 28-May-20 05-Jun-20 20 05-Jun-20, Fabricate Lifting Trunion
Boat Landing 44 01-Jun-20 23-Jul-20 45 23-Jul-20, Boat Landing
F2-JK2-JF15-123Blast and Paint Boat Landing 5 16-Jul-20 23-Jul-20 45 23-Jul-20, Blast and Paint Boat Landing
F2-JK2-JF15-124Fabricate Boat Landing 21 01-Jun-20 25-Jun-20 45 25-Jun-20, Fabricate Boat Landing
F2-JK2-JF15-159Fabricate Boat Landing Access platform 24 18-Jun-20 16-Jul-20 45 16-Jul-20, Fabricate Boat Landing Access platform
F2-JK2-JF15-160Fabricate Boat Landing Ladders 15 26-Jun-20 14-Jul-20 47 14-Jul-20, Fabricate Boat Landing Ladders
Grouting Line 23 04-Jul-20 31-Jul-20 42 31-Jul-20, Grouting Line
F2-JK2-JF15-126Fabricate Grouting Line & Grouting Line Support 23 04-Jul-20 31-Jul-20 42 31-Jul-20, Fabricate Grouting Line & Grouting Line Support
Assembly 105 05-Jun-20 05-Oct-20 1 05-Oct-20, Assembly
Row Assembly 88 05-Jun-20 16-Sep-20 13 16-Sep-20, Row Assembly

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 63 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF15-113Fabricate Upper Grillage & Truss Support 18 05-Jun-20 26-Jun-20 20 26-Jun-20, Fabricate Upper Grillage & Truss Support
F2-JK2-JF15-114Layout Concrete Blocks/ Grillages and Truss Support Steel 4 04-Jul-20 10-Jul-20 13 10-Jul-20, Layout Concrete Blocks/ Grillages and Truss Support Steel
Row-1 & 2 (Upper Jacket) Assembly 46 10-Jul-20 02-Sep-20 13 02-Sep-20, Row-1 & 2 (Upper Jacket) Assembly
F2-JK2-JF15-115
Installation of Grouting Line 1 28-Jul-20 29-Jul-20 33 29-Jul-20, Installation of Grouting Line
F2-JK2-JF15-117
Installation of J-Tube At Row-1B & 2A 5 28-Jul-20 03-Aug-20 37 03-Aug-20, Installation of J-Tube At Row-1B & 2A
F2-JK2-JF15-118
Row-2 - Touch Up, 2nd Coat & Top Coat 3 29-Aug-20 01-Sep-20 13 01-Sep-20, Row-2 - Touch Up, 2nd Coat & Top Coat
F2-JK2-JF15-119
Installation of Row-1B & 2B X-Brace 7 20-Jul-20 28-Jul-20 13 28-Jul-20, Installation of Row-1B & 2B X-Brace
F2-JK2-JF15-120
Installation of Leg 1A & 1B Onto Support 1 10-Jul-20 11-Jul-20 13 11-Jul-20, Installation of Leg 1A & 1B Onto Support
F2-JK2-JF15-121
Installation of Row-1A & 1B X-Brace 7 11-Jul-20 20-Jul-20 13 20-Jul-20, Installation of Row-1A & 1B X-Brace
F2-JK2-JF15-122
Installation of Row-2A & 2B X-Brace in Final Position 7 21-Aug-20 29-Aug-20 13 29-Aug-20, Installation of Row-2A & 2B X-Brace in Final Position
F2-JK2-JF15-142
Installation of Leg 2A & 2B Onto Support 1 10-Jul-20 11-Jul-20 20 11-Jul-20, Installation of Leg 2A & 2B Onto Support
F2-JK2-JF15-143
Installation of Row-1A & 2A X-Brace 7 20-Jul-20 28-Jul-20 13 28-Jul-20, Installation of Row-1A & 2A X-Brace
F2-JK2-JF15-144
Installation of Row-1A & 1B X-Brace in Final Position 7 13-Aug-20 21-Aug-20 13 21-Aug-20, Installation of Row-1A & 1B X-Brace in Final Position
F2-JK2-JF15-145
Roll Up X-Brace Row A&B to Final Position 7 28-Jul-20 05-Aug-20 13 05-Aug-20, Roll Up X-Brace Row A&B to Final Position
F2-JK2-JF15-146
Installing Tie-back for Fastener 7 05-Aug-20 13-Aug-20 13 13-Aug-20, Installing Tie-back for Fastener
F2-JK2-JF15-147
Installation of Boat Landing 3 29-Aug-20 02-Sep-20 13 02-Sep-20, Installation of Boat Landing
Row-1 & 2 (Lower Jacket) Assembly 44 07-Jul-20 26-Aug-20 18 26-Aug-20, Row-1 & 2 (Lower Jacket) Assembly
F2-JK2-JF15-116
Installation of Pile Stopper 4 06-Aug-20 10-Aug-20 18 10-Aug-20, Installation of Pile Stopper
F2-JK2-JF15-148
Installation of Grouting Line 1 24-Jul-20 25-Jul-20 39 25-Jul-20, Installation of Grouting Line
F2-JK2-JF15-149
Installation of J-Tube At Row-1B & 2A 5 24-Jul-20 30-Jul-20 28 30-Jul-20, Installation of J-Tube At Row-1B & 2A
F2-JK2-JF15-150
Installation of Row-1B & 2B X-Brace 7 16-Jul-20 24-Jul-20 18 24-Jul-20, Installation of Row-1B & 2B X-Brace
F2-JK2-JF15-151
Installation of Leg 1A & 1B Onto Support 1 07-Jul-20 08-Jul-20 18 08-Jul-20, Installation of Leg 1A & 1B Onto Support
F2-JK2-JF15-152
Installation of Row-1A & 1B X-Brace 7 08-Jul-20 16-Jul-20 18 16-Jul-20, Installation of Row-1A & 1B X-Brace
F2-JK2-JF15-153
Installation of Row-2A & 2B X-Brace in Final Position 7 18-Aug-20 26-Aug-20 18 26-Aug-20, Installation of Row-2A & 2B X-Brace in Final Position
F2-JK2-JF15-154
Installation of Leg 2A & 2B Onto Support 1 07-Jul-20 08-Jul-20 25 08-Jul-20, Installation of Leg 2A & 2B Onto Support
F2-JK2-JF15-155
Installation of Row-1A & 2A X-Brace 7 16-Jul-20 24-Jul-20 18 24-Jul-20, Installation of Row-1A & 2A X-Brace
F2-JK2-JF15-156
Installation of Row-1A & 1B X-Brace in Final Position 7 10-Aug-20 18-Aug-20 18 18-Aug-20, Installation of Row-1A & 1B X-Brace in Final Position
F2-JK2-JF15-157
Roll Up X-Brace Row A&B to Final Position 7 24-Jul-20 01-Aug-20 18 01-Aug-20, Roll Up X-Brace Row A&B to Final Position
F2-JK2-JF15-158
Installing Tie-back for Fastener 4 01-Aug-20 06-Aug-20 18 06-Aug-20, Installing Tie-back for Fastener
Grouting Line 40 31-Jul-20 16-Sep-20 13 16-Sep-20, Grouting Line
F2-JK2-JF15-125
Installation Of Grouting Line 5 10-Sep-20 16-Sep-20 13 16-Sep-20, Installation Of Grouting Line
F2-JK2-JF15-127
Installation Grouting Line Support 7 31-Jul-20 08-Aug-20 42 08-Aug-20, Installation Grouting Line Support
Row Roll Up 7 02-Sep-20 10-Sep-20 13 10-Sep-20, Row Roll Up
F2-JK2-JF15-105Roll Up Of Lower Jacket To Final Position 2 02-Sep-20 04-Sep-20 13 04-Sep-20, Roll Up Of Lower Jacket To Final Position
F2-JK2-JF15-106Roll Up Of Upper Jacket To Final Position 5 04-Sep-20 10-Sep-20 13 10-Sep-20, Roll Up Of Upper Jacket To Final Position
Transition Piece (TP) 76 29-Jun-20 25-Sep-20 0 25-Sep-20, Transition Piece (TP)
F2-JK2-JF15-1 Install Door Platform 10 22-Jul-20 03-Aug-20 29 03-Aug-20, Install Door Platform
F2-JK2-JF15-17Installation & Assembly of Ring Stiffener 21 24-Jul-20 18-Aug-20 0 18-Aug-20, Installation & Assembly of Ring Stiffener
F2-JK2-JF15-18Installation of Transition Piece Flange 15 01-Aug-20 19-Aug-20 0 19-Aug-20, Installation of Transition Piece Flange
F2-JK2-JF15-19Install Crane Pedestal 12 04-Jul-20 18-Jul-20 42 18-Jul-20, Install Crane Pedestal
F2-JK2-JF15-2 Blasting & Painting 10 05-Sep-20 17-Sep-20 0 17-Sep-20, Blasting & Painting
F2-JK2-JF15-3 Assemble Can Transition Piece Barrel to Main Deck 15 29-Jun-20 16-Jul-20 0 16-Jul-20, Assemble Can Transition Piece Barrel to Main Deck
F2-JK2-JF15-4 Install Platform & Internal Structure into Upper Can 7 17-Sep-20 25-Sep-20 0 25-Sep-20, Install Platform & Internal Structure into Upper Can
F2-JK2-JF15-5 Door opening & Installation of Door frame 5 16-Jul-20 22-Jul-20 39 22-Jul-20, Door opening & Installation of Door frame
F2-JK2-JF15-6 Installation & Assembly of Strut 15 16-Jul-20 03-Aug-20 0 03-Aug-20, Installation & Assembly of Strut
F2-JK2-JF15-7 Install Free-Issued Items 15 19-Aug-20 05-Sep-20 0 05-Sep-20, Install Free-Issued Items
F2-JK2-JF15-8 Install Architectural items, Electrical & Instrument Equipments 15 16-Jul-20 03-Aug-20 29 03-Aug-20, Install Architectural items, Electrical & Instrument Equipments
F2-JK2-JF15-9 Install External Platform & Handrail 12 20-Jul-20 03-Aug-20 29 03-Aug-20, Install External Platform & Handrail
Final Assembly 8 25-Sep-20 05-Oct-20 1 05-Oct-20, Final Assembly
F2-JK2-JF15-107Installation of Transition Piece 3 25-Sep-20 29-Sep-20 0 29-Sep-20, Installation of Transition Piece
F2-JK2-JF15-108Installation of Mudmad Plate 5 28-Sep-20 03-Oct-20 0 03-Oct-20, Installation of Mudmad Plate
F2-JK2-JF15-109Installation of Lifting Trunnion 4 29-Sep-20 03-Oct-20 2 03-Oct-20, Installation of Lifting Trunnion
F2-JK2-JF15-110Installation of Skirt Pile Sleeve 2 28-Sep-20 30-Sep-20 0 30-Sep-20, Installation of Skirt Pile Sleeve
F2-JK2-JF15-111Final Touch Up Coating 3 01-Oct-20 05-Oct-20 0 05-Oct-20, Final Touch Up Coating
F2-JK2-JF15-112Installation of Lifting Slings 1 30-Sep-20 01-Oct-20 0 01-Oct-20, Installation of Lifting Slings

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 64 of 65
Remaining Work Summary Data date 12-Jul-19
Formosa II OWF Supply and Fabrication of Foundations (Level 4) Rev
Supply & Fabrication of 15 Jackets
TASK filter: All Activities
Activity ID Activity Name Original Start Finish Total
2019 2020 2021
Float
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Duration
F2-JK2-JF15-161J acket Fabrication Completed 0 05-Oct-20 0 05-Oct-20
Testing & Commissioning 18 16-Sep-20 07-Oct-20 0 07-Oct-20, Testing & Commissioning
Grouting & Gripper Test 3 16-Sep-20 19-Sep-20 13 19-Sep-20, Grouting & Gripper Test
F2-JK2-JF15-20Gripper Test 2 17-Sep-20 19-Sep-20 13 19-Sep-20, Gripper Test
F2-JK2-JF15-21Grouting Test 1 16-Sep-20 17-Sep-20 13 17-Sep-20, Grouting Test
Mechanical Completion 2 05-Oct-20 07-Oct-20 0 07-Oct-20, Mechanical Completion
F2-JK2-JF15-22Main Structure, Boat Landing, J-Tube, Transition Piece 2 05-Oct-20 07-Oct-20 0 07-Oct-20, Main Structure, Boat Landing, J-Tube, Transition Piece
Jacket & Piles Ready For Loadout 0 07-Oct-20 07-Oct-20 0 07-Oct-20, Jacket & Piles Ready For Loadout
F2-JK2-JF15-23Jacket Ready For Load Out 0 07-Oct-20 0 07-Oct-20
LOAD OUT & DELIVERY 99 09-Sep-20 17-Dec-20 0 17-Dec-20, LOAD OUT & DELIVERY
Batch 1 Jackets Delivery (Jacket #1 - #4) 9 09-Sep-20 18-Sep-20 0 18-Sep-20, Batch 1 Jackets Delivery (Jacket #1 - #4)
F2-JK2-LO1-1 Ready for load out on quay side 3 10-Sep-20 13-Sep-20 0 13-Sep-20, Ready for load out on quay side
F2-JK2-LO1-2 Sea-fastening 3 15-Sep-20 18-Sep-20 0 18-Sep-20, Sea-fastening
F2-JK2-LO1-3 Latest Works Taking Over 0 18-Sep-20* 0 18-Sep-20*
F2-JK2-LO1-4 Loadout of Jackets 2 13-Sep-20 15-Sep-20 0 15-Sep-20, Loadout of Jackets
F2-JK2-LO1-5 Weighing of Jackets 1 09-Sep-20 10-Sep-20 0 10-Sep-20, Weighing of Jackets
Batch 2 Jackets Delivery (Jacket #5 - #8) 9 09-Oct-20 18-Oct-20 0 18-Oct-20, Batch 2 Jackets Delivery (Jacket #5 - #8)
F2-JK2-LO2-1 Latest Works Taking Over 0 18-Oct-20* 0 18-Oct-20*
F2-JK2-LO2-2 Loadout of Jackets 2 13-Oct-20 15-Oct-20 0 15-Oct-20, Loadout of Jackets
F2-JK2-LO2-3 Weighing of Jackets 1 09-Oct-20 10-Oct-20 0 10-Oct-20, Weighing of Jackets
F2-JK2-LO2-4 Ready for load out on quay side 3 10-Oct-20 13-Oct-20 0 13-Oct-20, Ready for load out on quay side
F2-JK2-LO2-5 Sea-fastening 3 15-Oct-20 18-Oct-20 0 18-Oct-20, Sea-fastening
Batch 3 Jackets Delivery (Jacket #9 - #12) 10 07-Nov-20 17-Nov-20 0 17-Nov-20, Batch 3 Jackets Delivery (Jacket #9 - #12)
F2-JK2-LO3-1 Ready for load out on quay side 3 09-Nov-20 12-Nov-20 0 12-Nov-20, Ready for load out on quay side
F2-JK2-LO3-2 Sea-fastening 3 14-Nov-20 17-Nov-20 0 17-Nov-20, Sea-fastening
F2-JK2-LO3-3 Latest Works Taking Over 0 17-Nov-20* 0 17-Nov-20*
F2-JK2-LO3-4 Loadout of Jackets 2 12-Nov-20 14-Nov-20 0 14-Nov-20, Loadout of Jackets
F2-JK2-LO3-5 Weighing of Jackets 1 07-Nov-20 08-Nov-20 0 08-Nov-20, Weighing of Jackets
Batch 4 Jackets Delivery (Jacket #13 - #15) 9 08-Dec-20 17-Dec-20 0 17-Dec-20, Batch 4 Jackets Delivery (Jacket #
F2-JK2-LO4-1 Ready for load out on quay side 3 09-Dec-20 12-Dec-20 0 12-Dec-20, Ready for load out on quay side
F2-JK2-LO4-2 Sea-fastening 3 14-Dec-20 17-Dec-20 0 17-Dec-20, Sea-fastening
F2-JK2-LO4-3 Latest Works Taking Over 0 17-Dec-20* 0 17-Dec-20*
F2-JK2-LO4-4 Loadout of Jackets 2 12-Dec-20 14-Dec-20 0 14-Dec-20, Loadout of Jackets
F2-JK2-LO4-5 Weighing of Jackets 1 08-Dec-20 09-Dec-20 0 09-Dec-20, Weighing of Jackets
FINAL DOCUMENTATION & AS-B UILT 0 17-Jan-21 17-Jan-21 0 17-Jan-21, FINAL DOCUMENTATION
F2-JK2-FD-1 Employer's receipt and approval of Final documentation and as-built documentation
0 17-Jan-21 0 17-Jan-21

Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
09-Aug-19 Issue for Review JMK MLF
Actual Work Milestone Page 65 of 65
Remaining Work Summary Data date 12-Jul-19