Beruflich Dokumente
Kultur Dokumente
SEGMENTS
AMERICAN
SEGMENTAL
BRIDGE
INSTITUTE
INSIDE
Editorial
Figure 4 -
Concrete box girder segments were manufactured 15
in a long line fashion in a casting yard adjacent
to the bridge construction site. (Photo courtesy of
FIGG).
Minnesota Crosstown
Segmental Bridges Near
“Half-Way” Point
The Minnesota T.H. 62/35W
Crosstown project includes six curved
precast segmental bridges with
varying geometry that that are under 1
199
construction employing the balanced
cantilver method. All six bridges utilize
a modified AASHTO/ASBI/PCI
section 8-2 with an 8 foot depth and Figure 14 -
Crosstown
maximum spans of 200 feet. July 10th
Segmental Bridge
marked the day that the Contractor, Construction, MN,
Lunda Construction, celebrated the (Photo courtesy of
halfway point with casting of the 231st MnDOT).
segment of projects 462 total segments.
The Contractor chose to utilize his per day with the 260th segment cast segmental bridges is scheduled to occur
existing property by converting one and 202 segments to go at the time of in 2009 with much of the remaining
of his buildings into an indoor heated this update (Aug 12th). construction occurring in highly
short-line casting facility. Segments are So far, 146 segments have been congested traffic areas.
cast, cured, transversely post-tensioned erected which has completed Since the project criteria requires
and stored at the casting yard with approximately 2¾ of the 6 segmental minimal impact to the traveling
an approximate 20 mile hauling bridges (see Figs. 14, 15 and 16). public, much of the remaining work
distance to the bridge site. Casting The first two bridges that were erected of erecting the segments must be
operations are expected to continue are located in a construction staging completed during either brief night-
through January of 2009 to complete area that is off to the side of the main time traffic closures, or during a
the casting of all 462 segments. The traffic area, so these bridges could limited number of weekend closures.
contractor continues to cast segments be erected during normal day time The project is currently on schedule.
at the rate of approximately 2 segments operations. However, the 3rd bridge
Owner: State of Minnesota
Designers: ( 3 firms designed 2 bridges each) PB Americas, URS, and Parsons Transportation Group
Contractor: A mes, Lunda, Shafer (A Joint Venture)
Construction Engineer: M cNary Bergeron & Associates
Construction Engineering Inspection: Figg Bridge Inspection
Formwork for Precast Segments: Southern Forms, Inc.
Post-Tensioning Materials: VSL
Bearings and Expansion Joints: D.S. Brown
Epoxy Supplier and Prepackaged Grout: Pilgrims Segmental Epoxy and
Sika pre-bagged grout
Figure 15 -
Erection of Pier Segment, Crosstown Bridge, MN.
(Photo courtesy of MnDOT.)
Longitudinal
layout of the
Kishwaukee River
Bridge (Drawing
courtesy of Parsons
Transportation
Group).
new anchor zones and deviators were
cast in place within the segmental
box and then post tensioned. Instead
of using steel pipes at the deviators,
continuously curved voids (diablos)
were cast in the deviation diapraghm
to allow large deviations from the
theoretical tendon profile. In order
to meet the higer standards of today’s
post tensioning technology the PT
was designed with a continuous air Folsom Dam Bridge, Folsom, (2003). The American River crossing Figure 25-
tight HDPE pipe from anchor to California Folsom Bridge
at this location is an important
The new Folsom Dam Bridge Construction
anchor grouted with high performance transportation link for the neighboring (Photo courtesy
grout and equipment. Due to the (Fig. 25) is a 970-foot, cast-in-place communities of El Dorado and Placer CH2M HILL).
diablos and continuous HDPE pipe segmentally constructed bridge 200 counties, and the city of Folsom.
requirements; specially designed PT feet above the American River canyon
Project Highlights:
anchors were installed at the faces of below the Folsom Dam. As a Joint
• Major new bridge crossing
the existing diapraghms. The location Venture lead for the project, CH2M
downstream from Folsom Dam
of the new anchors was made more HILL provided environmental
• Coordination with state and
difficult by the tight constraints of the document development and approval,
federal regulatory agencies
existing reinforcement and PT. alternatives selection, and roadway and
• Accelerated bridge construction
EKS, IDOT, PTG, and DSI worked bridge design for the 2-mile connector
project that will be completed
very closely throughout the project route that will allow traffic to bypass
within 5 years, including planning,
due to the complex 3D geometry the existing roadway over the Folsom
design, and construction
and challenges of accommodating Dam.
• Segmentally constructed post-
the tendon paths throughout the The federally funded project, which
tensioned concrete bridge
existing bridges. To assist with this task was administered by the Sacramento
construction, with limited
Ground Penetrating Radar was used to District of the U.S. Army Corps of
locate the existing PT and reinforcing Engineers, was the result of the Bureau
falsework, to minimize impact 113
to the environmentally sensitive
in the diapraghms and abutments of Reclamation’s closure of the existing
American River
so crews could follow closely behind river crossing, over the Folsom Dam
• Construction Cost $70 million
with coring of the holes (in 3D) due to homeland security concerns
(estimate)
for the tendon paths. After casting,
the PT install crew quickly went Figure 26 -
Rendering of
to work installing the new anchors
Folsom Bridge
and the HDPE pipe; overcoming (Drawing courtesy
the challenges compounded by the CH2M HILL).
largely deviated tendon paths and
longer tendons of over 770 feet. The
tendon stressing was difficult due to
the location of the tendons in the
upper corners of the box, along with
the congestion of the new tendons and
new anchors. (see Fig. 24) Owner: United States Army Corps of Engineers
The Southbound Bridge was Designer: CH2M HILL
completed in May 2008 and the Contractor: Kiewit
Northbound Post Tensiong portion of Construction Engineer: McNary Bergeron
the project was succesfully completed Construction Engineering Inspection: CH2M HILL / URS
in early August 2008 with final project Form Travelers for Cast-in-Place Segments: Parkin Engineering
completion coming shortly within the Post-Tensioning Materials: Schwager Davis Inc. (SDI)
Owner’s schedule. Epoxy Supplier and Prepackaged Grout: Sika
Figure 27 - Fourth Street Bridge, Pueblo,
Matagorda Bridge Colorado
Superstructure Flatiron Intermountain
Cross-Section Constructors is building the new 4th
at Piers. (Photo
courtesy of
Street Bridge in Pueblo, Colorado
TxDOT.) for the Colorado Department of
Transportation. Colorado's longest
highway span at 378' is being built
in concrete segmental construction
(Figs. 30 and 31) over the Pueblo
Rail Yard which contains 28 sets of
heavy rail tracks. The bridge also
spans the Arkansas River and a flood
protection wall that is celebrated as
the worldís longest mural. Bid against
steel bridge designs on August 30,
2007, FIGG's concrete segmental
design saved approximately $5 million.
Aesthetics were developed to follow the
community-selected theme of Natural
Environment, along with reflecting
Pueblo Heritage.
Figure 28 - First Cantilever Nearing Completion, Matagorda Bridge (Photo courtesy of TxDOT).
Correction – The Winter 2008
Gulf Intracoastal Waterway soffit gradually transitions into a full Newsletter credit listing for the Fourth
Bridge, FM 2031,
V-Hull shape at the piers (Fig. 28). Street Bridge contained an error in
Matagorda, Texas the credit listing for Construction
The first cantilever is nearly The piers themselves have a
complimentary beveled shape that Engineering. Construction
complete on this bridge connecting Engineering for the Fourth Street
14 1 the remote Matagorda Peninsula to the creates a mitred corner and unifies the
entire structure. Bridge is being provided by Finley
Texas mainland (Fig. 27). It will soon Engineering Group.
replace a 50-year old cable-actuated In order to provide sufficient longi-
floating swing bridge tudinal flexural strength, the opposing Figure 30 -
The main span is a relatively modest pier V-Hull faces are separated by a August 14, 2008 - The reinforcing for Pier 3 EB
single, long web (Fig. 29). The web column (on left) is completed and awaits form
320' and the deck is a narrow 46' installation. Span 1 WB Superstructure construction
overall. The vertical clearance is 73' in will also become a reflecting surface
continues in the background (Photo courtesy of FIGG).
order to allow for frequent passage of for fluorescent lights tucked into the
commercial and recreational vessels. wrapped flanges of the piers. The
Perhaps the most unique feature lighting fixtures are located every 10
on this bridge is the architecture. At feet to create tall windows of light that
mid-span, the box cross-section has announce the arrival in Matagorda, TX.
a typical segmental box girder cross- Expected completion of the bridge is
section. However the flat-bottomed Spring 2009.
Owner: TxDOT
Designer: TxDOT
Figure 29 - Light
Fixtures Contractor: Midwest Foundation Corporation
Matagorda Bridge,
Pier Cross-Section
Construction Engineering: Summit Engineering Group
and Lighting PT Supplier: VSL
(Illustration Form Travelers: Mexpressa
courtesy of Prepackaged Grout: Masterflow 1205
TxDOT).
Figure 31 -
Piers built next to the railroad yard get ready for
long span segmental construction. Twin 1,137'
bridges have spans of 151'/237'/379'/228'/142'.