Beruflich Dokumente
Kultur Dokumente
Page 2 of 139
Table of Contents
Executive Summary
ES.1 Project Purpose.....................................................................................................................................................ES-1
ES.2 Hydraulic Modeling.............................................................................................................................................ES-2
ES.3 Alternatives Evaluation.....................................................................................................................................ES-3
ES.4 Recommendations...............................................................................................................................................ES-6
ES.4.1 Interconnection Recommendations..........................................................................................ES-9
ES.4.2 Fee to Brunswick County ............................................................................................................ES-10
Section 1 - Introduction
1.1 Background ...............................................................................................................................................................1-1
1.2 Project Purpose .......................................................................................................................................................1-3
i
Page 3 of 139
Table of Contents Eastern Pender Service Area Water System Improvement – Final Report
ii
Page 4 of 139
Table of Contents Eastern Pender Service Area Water System Improvement – Final Report
iii
Page 5 of 139
Table of Contents • Eastern Pender Service Area Water System Improvement – Final Report
List of Figures
Figure ES-1 Recommended Alternative (Alternative 2)
Figure ES-2 Conceptual RO WTP Wellfield
Figure 4-1 Alternative 1 Recommended Improvements - Water Supply from Existing WTP
Figure 4-2 NC 210 Water Booster Pumping Station Expansion
Figure 4-3 Alternative 1A Recommended Improvements - Water Supply from Existing
WTP
Figure 4-4 Alternative 1B Recommended Improvements - Water Supply from Existing
WTP
Figure 4-5 Hampstead and Holly Shelter Game Lands Area and County-Owned Properties
Figure 4-6 Existing Water Supply Wells
Figure 4-7 Hydrogeologic Cross Section Locations
Figure 4-8 Hydrogeologic Cross Section A-A’
Figure 4-9 Hydrogeologic Cross Section B-B’
Figure 4-10 Peedee Aquifer Potentiometric Surface Map
Figure 4-11 Castle Hayne Aquifer Potentiometric Surface Map
Figure 4-12 Water Supply Well Yields
Figure 4-13 Conceptual RO WTP Wellfield – Site 1
Figure 4-14 Conceptual RO WTP Wellfield – Site 2
Figure 4-15 Proposed Process Flow Diagram
Figure 4-16 Typical Reverse Osmosis Unit with Sample and Control Panels
Horizontal Skid Layout
Figure 4-17 Typical Reverse Osmosis Facility Layout
iv
Page 6 of 139
Table of Contents • Eastern Pender Service Area Water System Improvement – Final Report
v
Page 7 of 139
Table of Contents Eastern Pender Service Area Water System Improvement – Final Report
List of Tables
Table ES.1 Projected Water Demands by District
Table ES.2 Conceptual Cost Estimate Summary for all Alternatives
Table ES.3 Alternative 2 Conceptual Cost by Phase
Table ES.4 Project Schedule for Recommended Improvements
vi
Page 8 of 139
Table of Contents Eastern Pender Service Area Water System Improvement – Final Report
Appendices
Appendix A Modeling
Appendix B DWR Topsail Station Chlorides
vii
Page 9 of 139
Executive Summary
Introduction
ES.1 Project Purpose
Pender County Utilities (PCU) administers water and wastewater for six Water and Sewer
Districts established in 1996 to serve the residents of Pender County. The Districts include:
Rocky Point/Topsail, Maple Hill, Scotts Hill, Central Pender, Moore’s Creek, and Columbia-Union.
Within the County, PCU operates two public water supply systems: the Maple Hill Water District
and the PCU water system.
As the PCU water system has grown, particularly in the eastern portion of the service area near
Highway 17 (Rocky Point/Topsail and Scotts Hill Districts), the water transmission system
between the WTP and eastern portions of the service area has become limited in capacity to
support further growth. However, the majority of the County’s growth is expected in the
easternmost portion of the Rocky Point/Topsail District and the Scotts Hill District due to its
location near the City of Wilmington, Intracoastal Waterway, and Atlantic Ocean. Therefore, PCU
initiated a study to evaluate the capacity of the existing water system and recommend
improvements to serve this future growth.
The purpose of this project is to analyze the most efficient way to provide potable water to the
rapidly expanding eastern service area. The scope of work includes the following tasks:
ES-1
Page 10 of 139
Executive Summary
Evaluate a potential interconnection with the Town of Topsail Beach supplying up to 1 MGD
in the peak season
Review of results provided by others on the feasibility of a potential interconnection with
Cape Fear Public Utility Authority (CFPUA) on US 17 at the County line for up to 200,000
gpd
Development of planning-level opinion of probable capital cost and annual operation and
maintenance cost estimates for the water supply alternatives and associated distribution
system improvements
Preparation of a technical report summarizing the results of each task
Projected average day demands (ADDs) and maximum day demands (MDDs) provided by PCU are
based on the 2017 Interbasin Transfer Petition (IBT) and are summarized in Table ES-1.
PCU provided geographic information system (GIS) data to CDM Smith that reflected new
pipelines installed since the water model was last updated. CDM Smith updated the modeled
pipes to include pipes 12-inch diameter and greater that were recently added as well as any
additional pipes that would provide looping within the eastern portion of the system. The
updated existing system water model consists of 196 miles of pipe with diameters ranging from 4
to 24 inches.
ES-2
Page 11 of 139
Executive Summary
The model was calibrated based on hydrant flow tests which were conducted by PCU staff at
strategic locations in the system. Tank levels, pump flow and pump discharge pressure data was
recorded at the time of each flow. Once the model was calibrated to the hydrant flow data,
extended period simulations of the existing system were run for a 72-hour period to verify model
results with SCADA data from June 26, 2019 through June 28, 2019.
Under existing average and summer conditions, the system meets the minimum pressure,
maximum velocity and maximum headloss criteria. However, during summer demand, the
turnover is limited in the Malpass Tank due to the significant headloss in the single long
transmission main between the Malpass and Rocky Point tanks.
Under existing maximum day demands (MDD), the system has inadequate capacity to
convey water to the eastern portions of the service area. Storage tanks empty and
minimum pressures cannot be maintained in the distribution system. This is consistent
with the operational difficulties experienced during recent maximum day demand conditions.
Due to these limitations, critical upgrades are required to provide uninterrupted drinking water
to customers.
ALTERNATIVE 1: Surface Water Supply from Pender County WTP Only; Transmission
along Hwy. 210 routing.
New parallel pipeline routes from the WTP to Highway 17 follow existing alignments.
New Highway 210 Booster Pump Station (PS)
Expand the existing WTP capacity from 2 mgd to 10 mgd.
Install a new 700,000-gallon elevated storage tank (EST) in Rocky Point
Install a new 300,000-gallon EST in Scotts Hill
ALTERNATIVE 1A: Surface Water Supply from Pender County WTP Only; Alternative
Transmission Routing through New Hanover County.
New pipeline alignment running south from existing WTP along Highway 17, following
I-140 corridor to Scotts Hill
Other parallel pipeline improvements following existing alignments.
Expand the existing WTP capacity from 2 mgd to 10 mgd.
Install a new 700,000-gallon EST in Rocky Point
Install a new 300,000-gallon EST in Scotts Hill
ALTERNATIVE 1B: Surface Water Supply from Pender County WTP Only; Alternative
Transmission Routing from Hwy. 421 to Hwy. 210.
ES-3
Page 12 of 139
Executive Summary
New pipeline alignment between Highway 421 to Highway 210; additional pipeline
improvements along Highway 210 to Highway 17 following existing alignments.
New Highway 210 Booster PS
Expand the existing WTP capacity from 2 mgd to 10 mgd.
Install a new 700,000-gallon EST in Rocky Point
Install a new 300,000-gallon EST in Scotts Hill
ALTERNATIVE 2: New PCU-Owned Reverse Osmosis (RO) Groundwater WTP
New RO WTP in the Hampstead area
o PCU-owned and operated
o 3 mgd initial capacity, expandable to 5 mgd by 2040
Miscellaneous pipeline improvements
Expand the existing WTP capacity from 2 mgd to 6 mgd.
Install a new 700,000-gallon EST in Rocky Point
ES-4
Page 13 of 139
Executive Summary
Improvement Type Description (feet) (inches) Estimate (inches) Estimate (inches) Estimate (inches) Estimate (inches) Estimate
Segment A 43,200 36 $26,600,000
Segment A* 41,700 36 $32,300,000
Segment B 31,100 30 $13,700,000 16 $9,100,000 16 $9,100,000 16 $9,100,000
Segment C 27,700 36 $15,600,000 20 $8,500,000 20 $8,500,000 20 $8,500,000 20 $8,500,000
Segment D 32,700 24 $16,800,000 24 $16,800,000
Transmission
Segment E 40,300 24 $13,700,000 24 $13,700,000
Segment F 17,100 16 $4,100,000 16 $4,100,000 16 $4,100,000 16 $4,100,000 16 $4,100,000
Segment G 13,800 8 $2,000,000 24 $5,800,000 8 $2,000,000 8 $2,000,000 8 $2,000,000
Segment H 91,600 30 $45,500,000
Concentrate Discharge 52,800 $3,900,000
New Rocky Point EST (0.7
MG) $2,700,000 $2,700,000 $2,700,000 $2,700,000 $2,700,000
Storage
New Scotts Hill EST (0.3
MG) $1,500,000 $1,500,000 $1,500,000 $1,500,000 $1,500,000
New Hwy. 210 Booster PS
Phase 1 $3,60,000 $3,600,000
Phase 2 $300,000 $300,000
Pumping
HSPS
Increase to 6 mgd $500,000 $500,000 $500,000 $500,000 $500,000
Increase to 12.4 mgd $3,000,000 $3,000,000 $3,000,000
Existing WTP
2 to 6 mgd $1,300,000 $1,300,000 $1,300,000 $1,300,000 $1,300,000
6 to 10 mgd $27,000,000 $27,000,000 $27,000,000
WTP
New RO WTP
Initial 3 mgd $44,200,000 $3,900,000
3 to 6 mgd $10,000,000 $0
Inflation (2.4% per year through 2023) $6,800,000 $6,300,000 $8,000,000 $5,600,000 $1,600,000
Inflation (2.4% per year through 2035) $49,400,000 $21,200,000 $17,100,000 $12,800,000 $8,200,000
Fee to Brunswick Co. for Raw water pipeline upgrades $5,000,000 $5,000,000 $5,000,000 $5,000,000 $5,000,000
Engineering/Admin/Construction Mgmt. (Approx. 15%) $25,300,000 $20,400,000 $21,400,000 $15,300,000 $6,500,000
Total Planning Level Capital Cost Estimate $198,900,000 $162,000,000 $168,800,000 $122,600,000 $54,900,000
Annual O&M Cost Estimate (Year 2025) $1,550,000 $1,480,000 $1,550,000 $1,615,000 $4,434,000
Annual O&M Cost Estimate (Year 2040) $4,471,000 $4,309,000 $4,471,000 $4,014,000 $11,616,000
20-Year Net Present Worth (O&M + Capital), 2019 dollars $151,000,000 $129,000,000 $143,000,000 $109,000,000 $100,000,000
1) It is assumed the county would be responsible for the concentrate pipeline installation with the privately funded RO WTP
ES-5
Executive Summary
ES.4 Recommendations
Based on an evaluation of capital cost, operation and maintenance (O&M) cost, and non-cost
factors, the recommended alternative for improvements to meet the long-term demands of the
eastern service area is Alternative 2 which includes a new RO WTP in the Hampstead Area,
owned and operated by PCU.
See Figure ES-1 for recommended PCU improvements. See Figure ES-2 for a conceptual RO WTP
wellfield site.
A summary of the associated conceptual cost estimate for the improvements necessary to meet
near-term (2025) and long-term (2040) needs of the system is presented in Table ES-3.
As shown in Table ES-2, Alternative 2 capital costs and present worth are lower than alternatives
1, 1a, 1b but higher than alternative 2A. However, alternative 2 has better O&M costs and the
County would be able to recover costs in an estimated 16 to 20-year time period after the new RO
WTP is put into operation (Estimated recovery year of 2041-2045).
The additional water source would improve reliability and redundancy of PCU’s water system
and allow the ability to feed the system with one water source out of service.
Although upfront costs are substantial, this alternative provides PCU full control of water quality,
production and distribution and eliminates additional stakeholder coordination when making
decisions. This option also allows better rate structure control.
Table ES-4 shows a breakdown of projects with recommended start and completion dates for
planning purposes.
ES-6
Page 15 of 139
Legend
T
U New Elevated Tanks
New Parallel Pipe Segment
B (16-inch)
Page 16 of 139
C (20-inch)
F (16-inch)
G (8-inch)
Malpass Tank
T
U
Topsail Tank
T
U
B( Rocky Point Tank
16 Hwy 210 Tank
'') '')
C (20 T
U
T
U Ú
"
Additional 0.7 MG T
U
New RO WTP (5 MGD) Ú "
Hampstead Tank
3
Q
T
U
'')
6
(1
F
'')
(8
G
T
U
3
Q Additional 0.3 MG (Scotts Hill Tank)
´
Miles
0 2.5 5 Pender County Utilities
Legend
Road
215 acre eastern !
!
Holly
!
! Well portion of existing, Shelter Game
privately owned !
RO Plant
!
Lands
#
Water Line property
Hampstead Bypass
!
!
Proposed Right of Way !
!
Page
Game Lands
Si 17 of 139
!
!
rW
alt
er
Ct
!
! !
!
Wells !
!
!
!
(15 total)
#
!
Highlan
!
!
d s Dr
!
!
!
!
Ca
iso
n
Dr
!
!
RO Plant !
!
#
le
st r
Ca y D
M
Ba
oo C
W
re t
so
a
r
Proposed
d
Ct
Right of Way
Tr
an
sf
er
17
£
¤
St
17
at
-
io
US
n
Rd
Blu
Annand
Ests ebird
Vi MH
sta P
Ln
a
iah
le Ter
ar
M Cv
FigureES-2:
Figure 4-13: Conceptual RO WTP Wellfield
´
Feet Site 1
0 500 1,000 2,000 3,000 Pender County Utilities
1 in = 1,000 ft
Executive Summary
CFPUA
Prior to this study, a technical memorandum titled “SHWSD – CFPUA Interconnect Feasibility
Analysis” was prepared by Highfill in August, 2018 analyzing a potential interconnection with
CFPUA to supply water during high usage demand periods. The report recommended moving
forward with the interconnection and installing a pump station to account for hydraulic grade
line differences between CFPUA and PCU.
The new improvements recommended make the need for an interconnection with CFPUA less
urgent; however, having a backup water source between agencies can be mutually beneficial.
CDM Smith has reviewed the Highfill report analyzing this interconnection and believe PCU
should move forward with the interconnection.
ES-9
Page 18 of 139
Executive Summary
Under the terms of the MOU, PCU has the option to purchase from Brunswick County an
additional 5 mgd of raw water capacity from the new LCFWASA pipeline. PCU must decide by
July 1, 2028 whether to make this purchase or the 5 mgd capacity is forfeited and will be claimed
by Brunswick County.
PCU’s portion of construction is 12.195% as shown in the MOU and with current construction and
engineering costs of slightly over $40,000,000, PCU’s portion would be approximately
$5,000,000. CDM Smith recommends PCU plan to purchase this additional 5 mgd capacity by July
1, 2028.
ES-10
Page 19 of 139
Section 1
Introduction
1.1 Background
Pender County encompasses approximately 933 square miles and is part of the City of
Wilmington’s metropolitan area. Located in the Coastal Plains section of North Carolina, the land
is essentially flat and consists mostly of agricultural lands, forest, and low-density residential area
and several small towns including the County seat of Burgaw.
Pender County Utilities (PCU) administers water and wastewater for six Water and Sewer
Districts established in 1996 to serve the residents of Pender County. The Districts, identified on
Figure 1-1, include: Rocky Point/Topsail, Maple Hill, Scotts Hill, Central Pender, Moore’s Creek
and Columbia-Union. Within the County, PCU operates two public water supply systems: the
Maple Hill Water District and the PCU water system.
The Maple Hill Water District serves approximately 20 commercial customers and 340 residential
customers and is located in the far northeast corner of the County. The Maple Hill Water District
purchases groundwater from the Chinquapin Water Association in neighboring Duplin County.
Due to its remote location and sparse population between Maple Hill and the PCU water system
with limited potential for growth between the two, it is anticipated that the Maple Hill Water
District will remain a separate system and supplied via the current water source into the future.
As of the date of this report, PCU was in discussions with Onslow Water and Sewer Authority
(ONWASA) for 2 interconnections to feed Maple Hill because it is anticipated the State may be
removing Maple Hill from the Chinquapin system.
The PCU water system originated in 1996 to supply the newly formed Rocky Point/Topsail Water
and Sewer District. Water was originally supplied from the Town of Wallace. In 2012, the Pender
County Surface Water Treatment Plant (WTP) was completed and the source water was changed
to surface water from the Cape Fear River provided by the Lower Cape Fear Water and Sewer
Authority (LCFWASA).
The PCU water system has since been expanded to provide water to approximately 400
commercial customers and 8,260 residential customers in the Moore’s Creek, Central Pender,
Rocky Point/Topsail, and Scotts Hill Water Districts. The PCU water system service area excludes
the Town of Burgaw, Surf City, Topsail Beach, Belvedere Plantation, and several other small
communities which have separate water systems. Many residents of unincorporated areas within
the County are still served by private wells, but PCU is planning to expand water services to
currently unserved portions of the County.
1-1
Page 20 of 139
V
U411
U
V
1828
V
U
1213
V
U
1116
V
U
41 Wallace 1152
U
V
V
U1309
V
U 1526
Maple Hill V
U
1106 V U
U
1105
V 1107
U
V
1007
V
U 11 V
U
1313 V
U
1520
V
U53
Page 21 of 139
V
U1100 Columbia-Union V
U
50
V
U
1318
117 Central
£
¤
U
V 1200 Burgaw
17
£
V
U 1550
421
£
¤ ¤UV 172
V
U
210
§
¦
¨
40
B l ack
V
U 53 Ri V
U
1121 Surf City
ve
V
U V
U
210
r
r
ive
Legend Rocky
F e ar R
River Point/Topsail Topsail Beach
V
U 11
Municipal Boundary p
t Ca
e
V
U
1741
District Boundary theas V
U
1574 V
U 50
N or
Central ar River V
U
1002
V
U 87
C ape Fe V
U
1338
Columbia-Union
Maple Hill
V
U
1559
V
U
1572 Atlantic Ocean
Moores Creek
V
U
1878 Scotts Hill
Rocky Point/Topsail
Scotts Hill
£
¤74 V
U
1820
V
U
1426 §
¦
¨140
117
£
¤ £
¤ 17
County Boundary
V
U
1419
V
U
133 VU
U
1400
V 1491
Pender County
´
Miles Pender County Utilities
0 2.5 5 10
1 inch = 5 miles
Section 1 Introduction
As the PCU water system has grown, particularly in the eastern portion of the service area near
Highway 17 (Rocky Point/Topsail and Scotts Hill Districts), the water transmission system
between the WTP and eastern portions of the service area has become limited in capacity to
support further growth. However, the majority of the County’s growth is expected in the
easternmost portion of the Rocky Point/Topsail District and the Scotts Hill District due to its
location near the City of Wilmington, Intracoastal Waterway, and Atlantic Ocean. Therefore, PCU
initiated a study to evaluate the capacity of the existing PCU water system and recommend
improvements to serve future growth in the eastern portion of the service area.
1-3
Page 22 of 139
Section 2
Existing System Description
2.1 Water Service Area
The Pender County Utilities (PCU) water system currently provides water from the Pender
County Surface Water Treatment Plant (WTP) to residents within the following four Water and
Sewer Districts as shown on Figure 2-1:
Rocky Point/ Topsail - The Rocky Point/Topsail District is located in the southeast
quadrant of the County and is bounded by the New Hanover County border and Scotts Hill
District to the south, the Onslow County border and Atlantic Ocean to the east, the Central
Pender District to the north, and the Moore’s Creek District to the west. Rocky
Point/Topsail has the largest water demand within the service area and serves
approximately 362 commercial customers and 6,843 residential customers.
Scotts Hill - The Scotts Hill District is located in the very southeast corner of the County and
is bounded to the south and west by the New Hanover County border and to the north and
east by the Rocky Point/Topsail District and Atlantic Ocean. Scotts Hill has approximately
11 commercial customers and 538 residential customers.
Central Pender - The Central Pender District is located in the northeast quadrant of the
County and is bounded to the north by the Duplin County border, to the northeast by the
Maple Hill District, to the south by the Rocky Point/Topsail District, to the east by the
Onslow County border, and to the west by the Columbia-Union and Moore’s Creek Districts.
Central Pender has approximately 6 commercial customers and 363 residential customers.
Moore’s Creek - The Moore’s Creek District is located in the southwest quadrant of the
County and is bounded to the north by the Columbia-Union District, to the south by
Brunswick and New Hanover counties, to the west by Columbus, Bladen, and Sampson
counties, and to the east by the Central Pender and Rocky Point/Topsail Districts. Moore’s
Creek has approximately 19 commercial customers and 514 residential customers.
The PCU water system service area excludes the Town of Burgaw, Surf City, Topsail Beach,
Belvedere Plantation, and several other small communities which have separate water systems.
2-1
Page 23 of 139
DUPLIN COUNTY
Wallace
" Booster PS
Ú
SAMPSON
COUNTY
Page 24 of 139
Columbia-Union
Central ONSLOW COUNTY
St Helena
Malpass Tank Booster PS Ú
"
T
U
Topsail Tank
Rocky
BLADEN COUNTY Point Tank T
U
Rocky
T
U Ú
"
T
U Point/Topsail
Legend
Hampstead
" Sloop
Ú Point
Booster PS
3 WTP Water Pipe Diameter
Q Tank
T
U
6-inch and smaller
Ú
" Pump Station
8
Moores Creek
Tank 10
T
U
District Boundary
12 Scotts
16 WTP NEW Hill
COLUMBUS
Central
3
Q
COUNTY
20 HANOVER Atlantic Ocean
Columbia-Union
24 BRUNSWICK COUNTY
Moores Creek
Unknown COUNTY
Rocky Point/Topsail
County Boundary
Scotts Hill
Pender County
´
Miles Pender County Utilities
0 2.5 5 10
1 inch = 5 miles
Section 2 Existing System Description
Raw water is supplied to the WTP via an interconnection with the Lower Cape Fear Water and
Sewer Authority (LCFWASA) raw water pipeline. The LCFWASA draws water from the Cape Fear
River through an intake located above Lock and Dam Number 1 where the King’s Bluff Pump
Station delivers water through the 48-inch diameter raw water pipeline supplying Brunswick
County, Cape Fear Public Utilities Authority (CFPUA), several industries, and PCU’s WTP. The
current contract requires LCFWASA to provide up to 6 mgd to PCU.
2-3
Page 25 of 139
Section 2 Existing System Description
Sloop Point PS
The Sloop Point PS consists of a pre-packaged water booster pump station manufactured by EFI-
Solutions. The station contains two 50-hp, 1800-revolutions-per-minute (rpm) Aurora pumps,
providing 400 gpm at 84 feet TDH.
NC Highway 210 PS
The existing NC Highway 210 (Highway 210) PS is a packaged water booster pump station
manufactured by EFI-Solutions coupled with an auxiliary 200,000-gallon water tank. Water
enters the station via a 10-inch diameter polyvinylchloride (PVC) waterline where it passes
through a 10-inch diameter Cla-Val back pressure and solenoid shut-off control valve. The
control valve maintains backpressure in the 12-inch diameter main in Highway 210 while filling
the tank. Once the tank reaches a preset level, the solenoid shutoff is activated, closing the valve.
The filled tank then provides a constant head (~12-20 feet) to the station’s two 50-hp horizontal,
end-suction pumps. Each pump can provide 450 gpm at 200 feet TDH. With each pump running,
the station produces approximately 900 gpm at 90 psi to the downstream distribution system.
The eastern service area is fed entirely through a 12-inch diameter main which follows Highway
210 to Highway 17 where it tees into a 12-inch diameter main running south on Highway 17 and
2-4
Page 26 of 139
Section 2 Existing System Description
16-inch diameter main running north on Highway 17. Any disruption to the 12-inch diameter
main in Highway 210 would cut off the eastern service area.
2.2.5 Interconnections
PCU has 2 interconnections system-wide supplying emergency water to the system:
Surf City Interconnection - This interconnection is located at the intersection of Deer Run
Road and Highway 210 and consists of a 6-inch meter supplying approximately 100,000
gpd. PCU has a neighborhood off of Cedar Avenue near the Topsail tank supplied by Surf
City that is isolated from the rest of the system.
Wallace Interconnection - This interconnection is located along Highway 117 at the
Pender/Duplin County line and serves as an emergency supply from Wallace to PCU’s
water system. PCU can receive up to 1.1 mgd from Wallace during an emergency situation.
2-5
Page 27 of 139
Section 3
Hydraulic Modeling
A hydraulic evaluation was conducted to determine the adequacy of PCU’s water system to meet
existing and projected demands using a computer model of the water distribution system. The
evaluation focused on the transmission to the eastern portion of PCU’s service area (Rocky
Point/Topsail and Scotts Hill Districts) where growth is anticipated to occur.
This section describes the hydraulic evaluation including existing and projected water demands,
model development and calibration, general approach and evaluation criteria for the hydraulic
modeling, and storage, pumping and transmission improvements to address system deficiencies.
Finished water output from the Pender County WTP from May 2018 to July 2019 (includes
billed and non-revenue water)
Total monthly water billed by district from July 2010 through August 2019
Water demand projections from the 2017 Pender County Interbasin Transfer Petition
(includes projected customer demands and non-revenue and operational water demands)
3.1.1 Existing System Demands & Maximum Day Demand Peaking Factors
The existing average day demand (ADD) was determined based on review of WTP production
data from June 2018 through July 2019. To determine the projected maximum day demand
(MDD), a peaking factor of 1.65 is applied to the average day demand based on the MDD:ADD for
July 2018 through June 2019. This peaking factor is higher than factors used in previous studies
but reflects the seasonal nature of PCU’s demands in the coastal areas. The existing ADD and
MDD are 1.31 mgd and 2.16 mgd, respectively.
As discussed in Section 2.1, the PCU water system provides water to the following districts:
Central, Moore’s Creek, Rocky Point/Topsail, and Scotts Hill. Existing demands were allocated to
each of these districts based on the spatial allocation of demands in the existing hydraulic model
and review of billed water consumption by district. The majority of the existing water users are
in the Rocky Point/Topsail district which represents the eastern portion of the system (see Table
3-1).
3-1
Page 28 of 139
Section 3 Hydraulic Modeling
The total projected ADD and MDD for PCU’s water districts are summarized in Table 3-1. As
shown in Table 3-1, the majority of growth is anticipated to occur in the Rocky Point/Topsail
District. Based on Pender County’s GIS future land use classifications and discussions with PCU
staff, growth within the Rocky Point/Topsail District is projected to occur mainly along NC
Highway 17 and NC Highway 210. By near-term, the water demand within PCU’s water and
sewer districts is anticipated to double. By long-term, the water demand within PCU’s water and
sewer districts is projected to be approximately 4 times the existing demand.
The Town of Topsail Beach maintains its own water system and currently relies on groundwater
wells for water supply. It is anticipated that as demands in this area increase, the current water
source will not be able to meet the increase in the Town’s demands. In the future, it is assumed
that the Town of Topsail Beach will purchase water from PCU at a connection point along the
existing 16-inch diameter PCU main along Highway 17 near Transfer Station Road. Based on
discussion with PCU staff, it is anticipated that PCU should plan to supply an average of 0.2 mgd to
Topsail Beach by the near-term planning period, increasing to an average of 0.33 mgd by long-
term. Due to Topsail’s high seasonal demands, for this study, it was assumed that the MDD being
purchased by Topsail Beach would be 0.6 mgd in the near-term, increasing to 1.0 mgd by the
long-term as shown in Table 3-1.
3-2
Page 29 of 139
Section 3 Hydraulic Modeling
Main pressure zone - The Main pressure zone extends from the Pender County WTP to the
Highway 210 ground storage tank and booster pump station (PS). The Main pressure zone
operates at a hydraulic grade line elevation (HGLE) of 184.5 feet and includes the Rocky
Point and Malpass elevated storage tanks. The following water districts are included in the
Main pressure zone: Central, Moore’s Creek, and a portion of the Rocky Point/ Topsail
District.
Hampstead booster area - The Hampstead booster area extends from the Highway 210
ground storage tank and booster PS to the Sloop Point booster PS. The Hampstead booster
area is supplied from the Highway 210 booster PS and operates at an HGLE of 194.5 feet as
dictated by the high water level in the Hampstead elevated storage tank. The following
water districts are included in the Hampstead booster area: Scotts Hill and a portion of
Rocky Point/ Topsail District.
Sloop Point/Topsail booster area – The Sloop Point/Topsail booster area extends from the
Sloop Point booster PS to the northern end of PCU’s water system on Highway 17. The
Sloop Point/Topsail booster area is supplied from the Sloop Point booster PS and operates
at a HGLE of 215 feet as dictated by the high water level in the Topsail elevated storage
tank. The Sloop Point/Topsail booster area includes a portion of the Rocky Point/ Topsail
District.
It should be noted that while PCU’s system currently has two interconnections with the
neighboring water systems, Wallace and Surf City, the interconnection with Wallace is used for
emergency situations only. Surf City currently supplies an isolated neighborhood at the far
northern end of the system near the Topsail tank. However, PCU intends to continue to serve
these customers from its own supplies in the future; hence, water transfer through these
connections was not simulated in the hydraulic model.
PCU is planning for an interconnection with CFPUA in 2020. However, this interconnection would
also be for emergency situations only and therefore was not included in the hydraulic model
evaluation for this study. Since the CFPUA system operates at an HGLE of 181.5 feet, which is 13
feet lower than the Hampstead booster area, water would need to be pumped from CFPUA to
PCU’s system to maintain desirable pressures. Additional details of the suggested infrastructure
to create an interconnection are given in the August 2018 SHWSD-CFPUA Interconnect Feasibility
Analysis Technical Memorandum by Highfill Infrastructure Engineering.
PCU also is planning to install up to three wells in the Hampstead area by May, 2020 providing a
total capacity up to 1 mgd. This is a stopgap measure needed to provide water to customers
3-3
Page 30 of 139
Page 31 of 139
Tank 10
T
U WTP
12 Atlantic Ocean
Hampstead Booster Area 3
Q
16
Main Pressure Zone
20
Sloop Point / Topsail Booster Area
24
County Boundary
Unknown
Pender County
´
Miles Pender County Utilities
0 2.5 5 10
1 inch = 5 miles
Page 32 of 139
´
Miles Pender County Utilities
0 2.5 5 10
1 inch = 5 miles
Section 3 Hydraulic Modeling
during peak day demands during summer months for several years while improvements are
being designed and built. Due to the unknowns of these well locations, capacities, etc., they have
not been included in the hydraulic model.
Table 3-2. Modeled Water Distribution System Pipe Sizes and Length
Diameter Length (ft)
6-inch and smaller 200,310
8 inches 290,870
10 inches 78,450
12 inches 314,260
16 inches 56,670
20 inches 53,420
24 inches 42,650
Total 1,036,630
The high service pump station (HSPS) pumps at the WTP were modeled based on pump curves
provided in the model. HSPS pump operations were controlled by the level in the Rocky Point
elevated tank as described in Section 3.2.5. Pump curves were also provided in the model for the
Highway 210 booster PS, and a single point pump curve was provided for the pump at Sloop Point
booster PS. The Highway 210 booster PS and Sloop Point booster PS operations were controlled
by the levels in the Hampstead and Topsail elevated tanks, respectively, as described in Section
3.2.5.
Storage tank data in the model (maximum water surface elevation, head range, and volume) was
adjusted based on as-built drawings for the Malpass elevated storage tank, Hampstead elevated
storage tank, Highway 210 ground storage tank, and Topsail elevated storage tank. A summary
of the modeled storage tanks is provided in Section 2.
The back pressure and solenoid shutoff valve that controls the filling of the Highway 210 ground
storage tank was modeled to maintain a pressure upstream of the tank of approximately 50
pounds per square inch (psi) based on the current operation controls.
3-6
Page 33 of 139
Section 3 Hydraulic Modeling
Smith applied a global factor to adjust the model demands to match the existing demand based on
the finished water production records.
The existing demands were adjusted in the model to near-term and long-term projected demands
by scaling demand nodes in each district from the existing district demand as provided in the
model from PCU to the projected district demand per the IBT using a global factor for each
district. A summary of the resulting demands in each of the three pressure zones for the existing,
near-term, and long-term planning periods is presented in Table 3-3.
Each demand node in the previous model included the general hourly diurnal pattern shown on
Figure 3-3. The same diurnal pattern was applied for the existing and future model simulations
in this study.
Figure 3-3. Diurnal Pattern Supplied in PCU’s EPA Net model files
1.6
1.4
Demand Factor
1.2
0.8
0.6
0.4
0.2
0
0 6 12 18
Simulation Hour
3-7
Page 34 of 139
Section 3 Hydraulic Modeling
Hydrant flow tests were conducted by PCU staff at strategic locations identified by CDM Smith.
The hydrant test locations are shown on Figure 3-4. Tank level, pump flow, and pump discharge
pressure data at the time of each flow test was recorded. Computer simulations were conducted
to compare model results with the field test results. A summary of the results is provided in
Table 3-4. The flow hydrant for hydrant test 3 was mistakenly performed on a parallel Surf City
hydrant therefore the results from the hydrant test were not used for calibrating the model. For
the remaining hydrant tests, the model results compared reasonably well with the field test
results except for hydrant test 5. While the static pressure was off by 12 psi, the model residual
pressure was within 1 psi and the static pressure recorded for the flowing hydrant prior to the
test was similar to the model results. In addition, the modeled flow/pressure at the high service
pump was within 5 gpm and 5 psi, and the modeled flow/pressure at the Highway 210 booster PS
was within 8 gpm and 2 psi, therefore it was concluded that the recorded static pressure may
have been inaccurate for hydrant test 5. The model was considered calibrated based on the other
hydrant test results.
For verification purposes, the following assumptions and inputs were applied in the model:
Demand: The total system demand was adjusted in the model using a global factor to
match the average water supplied during this time period (1.76 mgd). Diurnal demand
patterns presented in Section 3.2.3 were used in the model.
3-8
Page 35 of 139
Page 36 of 139
Malpass Tank Ú
"
T
U
Test 3
Topsail Tank !
.
Rocky T
U
Point Tank Test 1
T
U !
.
Ú
"
T
U Test 4
Hampstead
Tank
Ú
" !
.
T
U
Test 2
Legend
!
.
!
. Hydrant Tests Water Pipe Diameter
6-inch and smaller
3
Q WTP WTP
8-inch 3
Q Test 5
Ú
" Pump Station 10-inch
12-inch
!
.
Tank
T
U 16-inch
20-inch
24-inch
Unknown
´
Miles Pender County Utilities
0 2.5 5 10
1 inch = 4 miles
Section 3 Hydraulic Modeling
HSPS: The modeled pump curves for the HSPS at the WTP were provided in the EPA Net
model files. PCU staff indicate that a single high service pump is typically operated at
reduced speed based on the water levels of the Rocky Point elevated tank (pump on at tank
water level of 14 feet, pump off at tank water level of 26 feet.) For verification, the model
was setup to turn the pump on or off at a speed of approximately 80 percent based off of
the Rocky Point tank water levels.
Storage Tanks: The initial elevated tank water levels were obtained from SCADA data and
input into the model.
Highway 210 Booster Pump Station: For the Highway 210 booster PS, all water in the
existing 12-inch diameter transmission main is reduced in pressure to flow through the
ground storage tank. The filling of the tank is controlled by a valve that maintains a set
pressure of approximately 50 psi in the 12-inch diameter main on the upstream side of the
tank. The booster pump station takes suction from the ground tank and boosts flow to the
Hampstead booster area. Pumping at the Highway 210 ground storage tank is controlled
by the water level of the Hampstead elevated tank.
Sloop Point Booster Pumps: The Sloop Point booster pumps were modeled to turn on and
off based on water levels in the Topsail elevated tank.
Model-simulated tank levels, pump flow and pump discharge pressures resulting from the above
operational controls were verified with SCADA data to confirm that model results reasonably
match typical system operations. The model appears to reflect the existing system within
reasonable accuracy based on the following results:
3-10
Page 37 of 139
WTP HSPS Flow WTP HSPS Pressure
SCADA Model SCADA Model
2,000 100
1,800
80
1,200
1,000 70
800
600 60
400 50
200
0 40
26 Jun 0h 26 Jun 12h 27 Jun 0h 27 Jun 12h 28 Jun 0h 28 Jun 12h 29 Jun 0h 26 Jun 0h 26 Jun 12h 27 Jun 0h 27 Jun 12h 28 Jun 0h 28 Jun 12h 29 Jun 0h
Date Date
Hwy 210 Booster Pump Station Flow Hwy 210 Booster Pump Station Pressure
SCADA Model SCADA Model
1,000 110
800
700 90
600 80
500
70
400
300 60
200 50
100
40
0 26 Jun 0h 26 Jun 12h 27 Jun 0h 27 Jun 12h 28 Jun 0h 28 Jun 12h 29 Jun 0h
26 Jun 0h 26 Jun 12h 27 Jun 0h 27 Jun 12h 28 Jun 0h 28 Jun 12h 29 Jun 0h
Date
Date
Sloop Point Booster Pump Station Flow Sloop Point Booster Pump Station Pressure
Model SCADA Model
800 100
Discharge Pressure (PSI)
700
90
600
Flow (GPM)
500 80
400 70
300
60
200
100 50
0 40
26 Jun 0h 26 Jun 12h 27 Jun 0h 27 Jun 12h 28 Jun 0h 28 Jun 12h 29 Jun 0h
26 Jun 0h 26 Jun 12h 27 Jun 0h 27 Jun 12h 28 Jun 0h 28 Jun 12h 29 Jun 0h
Date Date
Figure 3-5. Modeled Pump Flow and Pressure Verification for June 26 – 28, 2019
Page 38 of 139
Section 3 Hydraulic Modeling
The model results were compared to the evaluation criteria developed for the water system
described in Section 3.3.2. The inability of system components to adhere to the evaluation
criteria was considered a deficiency and the potential need for an infrastructure and/or
operational improvement was assessed.
3-12
Page 39 of 139
Rocky Point Elevated Storage Tank Hwy 210 Ground Storage Tank
SCADA Model SCADA Model
30 25
25 20
20
15
15
10
10
5 5
0
26 Jun 0h 26 Jun 12h 27 Jun 0h 27 Jun 12h 28 Jun 0h 28 Jun 12h 29 Jun 0h 0
26 Jun 0h 26 Jun 12h 27 Jun 0h 27 Jun 12h 28 Jun 0h 28 Jun 12h 29 Jun 0h
Date
Date
30
20
25
15
20
15 10
10
5
5
0 0
26 Jun 0h 26 Jun 12h 27 Jun 0h 27 Jun 12h 28 Jun 0h 28 Jun 12h 29 Jun 0h 26 Jun 0h 26 Jun 12h 27 Jun 0h 27 Jun 12h 28 Jun 0h 28 Jun 12h 29 Jun 0h
Date Date
Figure 3-6. Modeled Storage Tank Level Verification for June 26 – 28, 2019
Page 40 of 139
Section 3 Hydraulic Modeling
Under ADD and summer demand conditions, the system meets the minimum pressure, maximum
velocity and maximum headloss criteria given in Table 3-5. However, during summer demand,
the turnover is limited in the Malpass Tank. The Malpass tank is filled first and remains full while
the WTP high service pumps operate to fill the Rocky Point tank. Figure 3-7 shows the difference
in HGLE between the WTP and Rocky Point tank during peak morning hours. The HGLE
difference, due to the significant headloss in the single long transmission main between the
Malpass and Rocky Point tanks (approximately 10 miles), results in the difficulty in operating
both the Malpass and Rocky Point tanks effectively.
Under MDD conditions, the transmission system has inadequate capacity to convey water to the
eastern portions of the service area. The storage tanks empty and minimum pressures cannot be
maintained in the distribution system. This is consistent with the operational difficulties
experienced during recent MDD conditions, resulting in the need for PCU to purchase water
through system interconnections to maintain acceptable operations.
3-14
Page 41 of 139
166ft
16
4 ft
Page 42 of 139
160 ft
t
6f
ft
162
17
154 ft
156 ft 158 ft
172 f
Malpass Tank
150 ft 2 ft
T
U 17
5
8 ft
1
146 ft
Topsail Tank
t
18
148 f
0 ft
T
U
142 ft
170 ft
174ft
Rocky Point Tank
Legend Hwy 210 Tank
t
144 f
T
U Ú
"
U
T
3 Pender Co WTP
Q 18
ft
2f Ú
"
168
184 ft t Hampstead Tank
Ú
" Existing Booster Pump Station
T
U
T Existing Tanks
U
Hydraulic Grade Line Elevation
18 t
18
6f
´
Miles
0 2.5 5 10
During Peak Hours (June 2019 Demand)
Pender County Utilities
Section 3 Hydraulic Modeling
Since the existing distribution system is unable to meet existing MDD under normal operating
conditions (without purchase of supplemental water supply), hydraulic improvements are
needed to meet both existing and future demands.
Average water age in the existing system, as simulated in the hydraulic model, is shown in Figure
3-8. Model results indicate that the majority of the system has water age less than 5 days;
however, some areas have water age greater than 10 days, including areas downstream of the
Topsail tank and in the portion of the system north of NC Highway 210 and east of Interstate 40.
PCU staff indicated that there are no significant water quality complaints in the distribution
system.
The required storage volume is generally considered to be the greater of the North Carolina
Department of Environmental Quality (NC DEQ) requirements or the volume needed to satisfy
equalization, fire protection, and emergency storage.
With the existing 2.0 MG of distribution storage and assumed 1.0 MG of clearwell storage
available at the WTP, the existing facilities are adequate to meet NC DEQ’s minimum storage
volume requirement through the long-term planning period.
3-16
Page 43 of 139
Page 44 of 139
Malpass Tank
T
U
Topsail Tank
T
U
Rocky Point Tank Hwy 210 Tank
T
U Ú
"
U
T
Hampstead Tank
Ú
"
Legend
T
U
3 Pender Co WTP
Q
Ú
" Existing Booster Pump Station
T Existing Tanks
U
Average Water Age
Less than 2 days
3
Q
2 to 3 days
3 to 5 days
5 to 7 days
7 to 10 days
Greater than 10 days
´
Miles
0 2.5 5 10 Pender County Utilities
Section 3 Hydraulic Modeling
Fire flow requirements vary based on the type and use of buildings within a service area. For the
primary portions of PCU’s service area, the fire protection storage is estimated to be the volume
required to provide 3,500 gpm for a duration of 3 hours. For the booster areas, which are
primarily residential, the fire protection storage is estimated to be the volume required to
provide 1,500 gpm for a duration of 2 hours.
Emergency storage is used to satisfy system demands during any disruption in supply such as
water main breaks. The volume of emergency storage necessary can vary based on service area
needs and operations preferences. PCU has emergency standby power at the WTP and at the
Highway 210 booster PS. For the purposes of this analysis, emergency storage requirements of
25 and 50 percent of the ADD are considered.
Table 3-6 presents the estimated combined storage volume requirements for equalization, fire
protection, and emergency for each scenario. Volume requirements are calculated separately for
the Main pressure zone and each boosted pressure zone.
Assuming 25 percent emergency storage, the resulting storage requirements can be met with
existing distribution and clearwell storage through the near-term planning period. By the long-
term planning period, additional storage is needed in the Main pressure zone and Hampstead
booster area. Recommendations for location and size of future storage facilities are discussed in
the improvements evaluation in Section 3.6.
To address system needs to meet future demands, two alternatives for water supply were
evaluated:
Alternative 1 – Surface water supply from the Pender County WTP only (Sub-alternatives
1A and 1B present two different transmission main routing options for this alternative.)
Alternative 2 –New reverse osmosis (RO) groundwater WTP in the Hampstead area
3-18
Page 45 of 139
Section 3 Hydraulic Modeling
Table 3-6. System Storage Requirements based on Equalization, Fire Protection, and Emergency Storage
Available Clearwell Storage for Main Zone (MG) 1.0 1.0 1.0
Storage Requirement:
Equalization + Fire Protection + Emergency @ 25% ADD (MG) 1.0 1.3 2.2
Equalization + Fire Protection + Emergency @ 50% ADD (MG) 1.1 1.6 3.0
Storage Requirement:
Equalization + Fire Protection + Emergency @ 25% ADD (MG) 0.4 0.6 0.9
Equalization + Fire Protection + Emergency @ 50% ADD (MG) 0.5 0.9 1.3
Storage Requirement:
Equalization + Fire Protection + Emergency @ 25% ADD (MG) 0.3 0.4 0.5
Equalization + Fire Protection + Emergency @ 50% ADD (MG) 0.4 0.5 0.7
TOTAL
3-19
Page 46 of 139
Section 3 Hydraulic Modeling
Water supply, transmission, storage, and pumping improvements for each alternative are
discussed in the following sections. Improvements were identified and sized to meet the criteria
given in Table 3-5 for long-term demand projections. Section 4 provides cost estimates,
additional details and discussion of the advantages and disadvantages of each alternative.
3.6.1 Alternative 1 – Surface Water Supply from Pender County WTP Only
Alternative 1 evaluates the water system improvements assuming all water supply is from the
current Pender County surface WTP. Because of the substantial distance between the existing
WTP and the eastern service area combined with the large amount of growth expected, significant
pipeline, storage and pumping improvements are necessary. Recommended improvements are
shown in Figure 3-9 and described in the following paragraphs.
Additional HSPS capacity will also be needed. Based on the proposed phasing of the transmission
improvements, additional high service pumps are recommended to provide firm pumping
capacity of 4,500 gpm at a total dynamic head (TDH) of 220 feet for near-term and 7,000 gpm at a
TDH of 165 feet for long-term. The near-term pumping capacity exceeds the treatment capacity
since the HSPS will supplement peak hour demands from storage in the clearwell until additional
in-system storage is implemented in the long-term. Implementing the new pipe segment A from
the WTP to Highway 210 in the long-term reduces the TDH requirement for the HSPS. The
pumps should be controlled based on levels in the Rocky Point elevated storage tank.
For near-term, a new package duplex booster pump station with firm capacity of 2,300 gpm at a
TDH of 50 feet is recommended along Highway 210 near the existing pump station. By long-term,
the station will need to provide a firm pumping capacity of 3,400 gpm at a TDH of 70 feet. The
pumps should be controlled based on levels in the Hampstead elevated storage tank.
3-20
Page 47 of 139
Legend
C (36-inch)
D (24-inch)
Malpass Tank E (24-inch)
F (16-inch)
T
U G (8-inch)
Topsail Tank
'') T
U
24
D(
B( Rocky Point Tank
30 Hwy 210 Tank
'') '')
C (36 T
U
T
U Ú
Ú
"
[
Additional 0.7 MG T
U
E(
24
Ú
"
'')
Hampstead Tank
T
U
'')
6
(1
F
A(
36'
')
'')
(8
G
T
U
3
Q Additional 0.3 MG (Scotts Hill Tank)
´
Miles
0 2.5 5 Pender County Utilities
Section 3 Hydraulic Modeling
The recommended pipeline improvements identified in Table 3-7 represent parallel pipeline
sizes. Existing pipelines are to remain in operation. The need for large pipelines is due to
minimal system looping, the long distance (approximately 33 miles) between the WTP and
Highway 17, and the large portion of system demand located at the Hampstead and Sloop
Point/Topsail booster areas. These factors lead to substantial head losses in the existing system
and create the need for considerably more capacity.
New pipeline along Montague Rd from Hwy 421 to Hwy 210 and along
B 30 31,100
Hwy 210 to Little Kelly Rd; parallel to existing 20-inch transmission main
New pipeline along Hwy 210 from Little Kelly Rd to Hwy 117; parallel to
C 36 27,700
existing 12-inch transmission main
New pipeline along Hwy 210 from Hwy 117 to 210 Booster PS; parallel to
D 24 32,700
existing 12-inch transmission main
New pipeline along Hwy 210 from 210 Booster PS to Hwy 17; parallel to
E 24 40,300
existing 12-inch transmission main
New pipeline along Hwy 17 from Hwy 210 to Hampstead Tank; parallel to
F 16 17,100
existing 16-inch transmission main
New pipeline along Hwy 17 from Hwy 210 to New Scotts Hill WSD Tank;
G 8 13,800
parallel to existing 12-inch transmission main
1) See Figure 3-9 for a map showing the locations of piping upgrades.
The proposed sizes represent the diameters necessary to move water from the WTP to the
Hampstead Tank while minimizing headlosses and meeting desired system pressures. Parallel
pipelines will provide additional capacity and also add redundancy to the system if one pipeline
were to be out of service during an emergency. The phasing and need for each project are as
follows:
Parallel pipe segment A is needed in the long-term to increase capacity since this segment
delivers water to the entire PCU system.
Parallel pipe segments B and C are needed in the near-term to convey water to the Rocky
Point elevated tank. These improvements increase capacity and decrease headloss
3-22
Page 49 of 139
Section 3 Hydraulic Modeling
between the Malpass tank and Rocky Point tank, allowing both tanks to function effectively
and turnover during MDD (see Figure A1-6 in Appendix A).
Parallel pipe segments D and E are needed in the near-term to provide adequate capacity
for pumping water from the Main pressure zone to the Hampstead booster area.
Parallel pipe segment F is needed in the long-term to fill the Hampstead tank as demands in
the Hampstead and Sloop Point/Topsail booster areas increase. This includes delivering up
to 1.0 mgd from Highway 17 near Transfer Station Road to Topsail Beach during MDD.
Parallel pipe segment G is needed in the long-term to fill the proposed Scotts Hill elevated
storage tank.
Storage Improvements
Results of the storage volume evaluation presented in Section 3.4 indicate that additional storage
volume is needed in the Main pressure zone and Hampstead booster area in the long-term to
meet growing demands. The effectiveness of additional storage was evaluated in the hydraulic
model. The following new storage facilities are recommended for the long-term planning period:
Main Pressure Zone Storage: Add a new 0.7-MG elevated storage tank or replace the
existing Rocky Point elevated storage tank with a new 1.0-MG elevated storage tank. The
new tank will provide water supply for daily demand peaks and reduce peak pumping at
the WTP. The new storage tank is recommended to be located near the existing Rocky
Point tank since this is close to the location of existing/projected demand growth.
However, as the system grows, the location of the tank should be re-evaluated with respect
to the demand centroid.
Hampstead Booster Area Storage: Add a new elevated storage tank along Highway 17 in
the Scotts Hill WSD adjacent to the Pender EMS and Fire Station 18 (see Figure 3-9). This is
the same tank location that was evaluated in the August 2018 SHWSD-CFPUA Interconnect
Feasibility Analysis Technical Memorandum by Highfill Infrastructure Engineering. This
tank will also provide benefits for increasing fire flow and maximizing potential transfer of
water from Cape Fear Public Utilities Authority (CFPUA) to PCU in an emergency. A
minimum volume of 0.3 MG is recommended to meet the storage criteria for the
Hampstead booster area in Table 3-6. However, if the existing 0.2-MG ground storage tank
at Highway 210 is decommissioned, the new Scotts Hill tank should be at least 0.5 MG.
Improvements to increase available fire flow would include looping or increasing the size of the
neighborhood distribution lines. Since this evaluation focuses on the transmission to eastern
Pender County (i.e. pipe sizes greater than or equal to 12-inch diameter), specific fire flow
improvements are not identified.
3-23
Page 50 of 139
Section 3 Hydraulic Modeling
Water age in the eastern portion of the system is anticipated to decrease in the future, even with
the addition of large transmission mains in near-term.
Table 3-8 presents a summary of the recommended phasing for the Alternative 1 improvements.
Costs are presented in Section 4.
3-24
Page 51 of 139
Section 3 Hydraulic Modeling
Additional HSPS capacity will also be needed. For Alternative 1A, it is recommended that
separate high service pumps be dedicated to the Main pressure zone, transmitting flow through
the existing 24-inch diameter transmission main on Highway 421 and to the Hampstead booster
area via the new transmission main through portions of New Hanover County. Based on the
proposed phasing of the transmission improvements, additional high service pumping capacity to
each zone is recommended in Table 3-9. The Main pressure zone pumps should be controlled
based on water levels in the Rocky Point elevated storage tank. The Hampstead booster area
pumps should be controlled based on water levels in the Hampstead tank. The total HSPS
pumping capacity is greater in Alternative 1A (12.4 mgd) versus Alternative 1 (10 mgd) since the
storage in the Main pressure zone does not supplement peak hour demands and additional
pumping from clearwell is needed for peak hours.
It is recommended that the existing ground storage tank and booster pumps remain in service to
provide redundancy in supply to the eastern portions of the service area from the existing
transmission mains along Highway 210. The pumps could be used as-needed to operate similar
to the current set-up (boosting from the storage tank). It is also recommended that a bypass be
constructed to allow water from the new transmission main to supply back to the Main pressure
zone for redundancy in case of emergency.
3-25
Page 52 of 139
Legend
G (24-inch)
H (30-inch)
Malpass Tank
T
U
Topsail Tank
B (1 Additional T
U
6 '') 0.7 MG Hwy 210 Tank
)
C (20'' T
U
T
U Ú
"
Rocky
T
U
Point
Tank Hampstead Ú
"
Tank
'')
T
U
6
(1
F
'')
4
(2
G
U Additional 0.3
T
3
Q MG (Scotts
Hill Tank)
H (30
'')
´
Miles
0 2.5 5 Pender County Utilities
Section 3 Hydraulic Modeling
New pipe segment H and parallel pipe segment G are needed in the near-term to convey
water from the WTP to the Hampstead booster area and fill the Hampstead tank.
Parallel pipe segment C is needed in the near-term to convey water to the Rocky Point
elevated tank since the existing 12-inch diameter pipe has inadequate capacity.
Parallel pipe segment B is needed in the long-term to increase capacity and decrease
headloss between the Malpass tank and Rocky Point tank, allowing both tanks to function
effectively and turnover during MDD (see Figure A2-6 in Appendix A).
Parallel pipe segment F is needed in the long-term to fill the Hampstead tank as demands in
the Hampstead and Sloop Point/Topsail booster areas increase. This includes delivering up
to 1.0 mgd from Highway 17 near Transfer Station Road to Topsail Beach during MDD.
Storage Improvements
New storage facilities recommended for Alternative 1A are the same as those presented for
Alternative 1 in Section 3.6.1.
3-27
Page 54 of 139
Section 3 Hydraulic Modeling
Improvements to increase available fire flow would include looping or increasing the size of the
neighborhood distribution lines. Since this evaluation focuses on the transmission to eastern
Pender County (i.e. pipe sizes greater than or equal to 12-inch diameter), specific fire flow
improvements are not identified.
Water age in the eastern portion of the system is anticipated to decrease in the future, even with
the addition of large transmission mains in near-term.
Table 3-11 presents a summary of the recommended phasing for the Alternative 1A
improvements. Costs are presented in Section 4.
3-28
Page 55 of 139
Section 3 Hydraulic Modeling
New pipeline from the WTP to Hwy 210 along Cowpen Landing
A 36 41,700
Rd, new easements, Clarks Landing Loop Rd
New pipeline along Hwy 210 from Little Kelly Rd to Hwy 117;
C 36 27,700
parallel to existing 12-inch transmission main
New pipeline along Hwy 210 from Hwy 117 to 210 Booster PS;
D 24 32,700
parallel to existing 12-inch transmission main
New pipeline along Hwy 210 from 210 Booster PS to Hwy 17;
E 24 40,300
parallel to existing 12-inch transmission main
New pipeline along Hwy 17 from Hwy 210 to Hampstead Tank;
F 16 17,100
parallel to existing 16-inch transmission main
New pipeline along Hwy 17 from Hwy 210 to New Scotts Hill
G 8 13,800
WSD Tank; parallel to existing 12-inch transmission main
Note: See Figure 3-11 for a map showing the locations of piping upgrades.
3-29
Page 56 of 139
Legend
D (24-inch)
E (24-inch)
F (16-inch)
G (8-inch)
Malpass Tank
T
U
Topsail Tank
'') T
U
24
D(
Rocky Point Tank Hwy 210 Tank
'')
C (36 T
U
T
U Ú
Ú
"
[
Additional 0.7 MG T
U
E(
24
Ú
"
'')
Hampstead Tank
T
U
')
36'
'')
A(
6
(1
F
'')
(8
G
T
U
3
Q Additional 0.3 MG (Scotts Hill Tank)
´
Miles
0 2.5 5 Pender County Utilities
Section 3 Hydraulic Modeling
Pipe segments A and C are needed in the near-term to convey water to the Rocky Point
elevated tank. These improvements increase capacity and decrease headloss between the
Malpass tank and Rocky Point tank, allowing both tanks to function effectively and turnover
during MDD (see Figure A3-6 in Appendix A).
Parallel pipe segments D and E are needed in the near-term to provide adequate capacity
for pumping water from the Main pressure zone to the Hampstead booster area.
Parallel pipe segment F is needed in the long-term to fill the Hampstead tank as demands in
the Hampstead and Sloop Point/Topsail booster areas increase. This includes delivering up
to 1.0 mgd from Highway 17 near Transfer Station Road to Topsail Beach during MDD.
Parallel pipe segment G is needed in the long-term to fill the proposed Scotts Hill elevated
storage tank.
Storage Improvements
New storage facilities recommended for Alternative 1B are the same as those presented for
Alternative 1 in Section 3.6.1.
Improvements to increase available fire flow would include looping or increasing the size of the
neighborhood distribution lines. Since this evaluation focuses on the transmission to eastern
Pender County (i.e. pipe sizes greater than or equal to 12-inch diameter), specific fire flow
improvements are not identified.
Water age in the eastern portion of the system is anticipated to decrease in the future, even with
the addition of large transmission mains in near-term.
Table 3-13 presents a summary of the recommended phasing for the Alternative 1B
improvements. Costs are presented in Section 4.
3-31
Page 58 of 139
Section 3 Hydraulic Modeling
3-32
Page 59 of 139
Legend
T
U New Elevated Tanks
New Parallel Pipe Segment
B (16-inch)
Page 60 of 139
C (20-inch)
F (16-inch)
G (8-inch)
Malpass Tank
T
U
Topsail Tank
T
U
B( Rocky Point Tank
16 Hwy 210 Tank
'') '')
C (20 T
U
T
U Ú
"
Additional 0.7 MG T
U
New RO WTP (5 MGD) Ú "
Hampstead Tank
3
Q
T
U
'')
6
(1
F
'')
(8
G
T
U
3
Q Additional 0.3 MG (Scotts Hill Tank)
´
Miles
0 2.5 5 Pender County Utilities
Section 3 Hydraulic Modeling
A new RO WTP is recommended in the vicinity of the Hampstead tank. The RO WTP would have
an initial capacity of 3 mgd in the near-term and expanded to a minimum of 5 mgd to meet long-
term demands. Additional discussion of the preliminary groundwater investigation and RO
treatment system are included in Section 4.
It is recommended that the existing ground storage tank and booster pumps remain in service to
provide redundancy in supply to the eastern portions of the service area from the existing WTP.
The booster PS should be operated regularly (at least once weekly) to maintain for emergencies.
It is also recommended that a bypass be constructed to allow water from the new RO WTP to
supply back to the Main pressure zone for redundancy and peaking supply.
3-34
Page 61 of 139
Section 3 Hydraulic Modeling
Parallel pipe segment C is needed in the near-term to convey water to the Rocky Point
elevated tank since the existing 12-inch diameter main has inadequate capacity.
Parallel pipe segment B is needed in the long-term to increase capacity and decrease
headloss between the Malpass tank and Rocky Point tank, allowing both tanks to function
effectively and turnover during MDD (see Figure A4-6 in Appendix A).
Parallel pipe segment F is needed in the long-term to convey water from the new RO WTP
south toward demands at Highway 210. This includes delivering up to 1.0 mgd from
Highway 17 near Transfer Station Road to Topsail Beach during MDD.
Parallel pipe segment G is needed in the long-term to fill the proposed Scotts Hill elevated
storage tank.
Storage Improvements
New storage facilities recommended for Alternative 2 are the same as those presented for
Alternative 1 in Section 3.6.1.
Improvements to increase available fire flow would include looping or increasing the size of the
neighborhood distribution lines. Since this evaluation focuses on the transmission to eastern
Pender County (i.e. pipe sizes greater than or equal to 12-inch diameter), specific fire flow
improvements are not identified.
Water age in the eastern portion of the system is decreased in the future, even with the addition
of large transmission mains in near-term.
Table 3-15 presents a summary of the recommended phasing for the Alternative 2
improvements. Costs are presented in Section 4.
3-35
Page 62 of 139
Section 3 Hydraulic Modeling
3-36
Page 63 of 139
Section 3 Hydraulic Modeling
The elevations in this area were evaluated to determine if modifications could be made to the
tanks to operate both zones without booster pumping. As shown in Figure 3-13, some areas in
the Sloop Point/Topsail booster area have elevation as high as 70 feet. If the Sloop Point/Topsail
booster area were to operate at an HGLE of 194.5 feet (same as the Hampstead booster area),
customers at elevations above 60 feet would experience pressures less than 50 psi during typical
operations. Additionally, the Topsail tank would need to be abandoned since the tank would not
fill at its current elevation.
Alternatively, the Hampstead booster area could be increased to operate at an HGLE of 215 feet.
This would impact the size of the booster and/or high service pumps needed to supply this zone.
The Hampstead tank would also need to be raised to a high water elevation of 215 feet or
abandoned in lieu of a new elevated tank.
As transmission improvements are implemented to convey more water to the eastern portion of
the service area, model results predict that operations between the Hampstead tank and Topsail
tank will improve. Since changes to the booster areas would require modification and/or
construction of new tanks and pumps, removing the Sloop Point booster PS is not recommended
at this time. However, PCU could consider constructing a larger proposed Scotts Hill elevated
tank at an HGLE of 215 feet to replace the Hampstead tank and operate the entire eastern service
area at an HGLE of 215 feet to eliminate the Sloop Point booster PS.
3.7 Conclusions
CDM Smith conducted hydraulic model analyses to evaluate the adequacy of the existing water
distribution and transmission system to meet existing and projected MDD. Based on the results
of the modeling analyses, the existing water transmission mains from the WTP to the eastern
portion of the system along Highway 17 are inadequate to meet existing MDD while maintaining
storage tank levels and adequate customer delivery pressures.
In addition, significant growth is projected for the PCU service area. By the near-term (2025), the
water demand within PCU’s water and sewer districts is anticipated to double. By the long-term
(2040), the water demand within PCU’s water and sewer districts is projected to be
approximately 4 times the existing demand, with an additional 1.0 mgd projected as bulk water
sales to the Town of Topsail Beach. To support this growth, particularly in the eastern portions of
the system, additional transmission mains, pumping, storage facilities, and water supply are
needed. Since future demands were modeled by scaling existing demand nodes, the location of
growth should be adjusted in the model as development is planned.
The primary difference in the improvement alternatives evaluated in this study is the source of
future water supply for the eastern portions of the service area. Alternative 1 expands and
reinforces the water transmission from the existing WTP with approximately 39 miles of new
transmission mains (Alternatives 1A and 1B present slightly shorter routes). Alternative 2
reduces the length of transmission mains to 17 miles but requires construction and maintenance
of a new groundwater RO WTP in the Hampstead area. Section 4 discusses the costs, advantages
and disadvantages of these alternatives.
3-37
Page 64 of 139
Page 65 of 139
Topsail Tank
Sloop Point
T
U / Topsail
Booster Area
Legend
Water Pipe Diameter
" Sloop Point Sloop Point /
Ú Booster PS 6-inch and smaller
Topsail Booster Area
Elevation
8
60 - 72 feet
10
50 - 60 feet
12
40 - 50 feet
16
Hampstead 30 - 40 feet
Tank 20
20 - 30 feet
24
T
U Unknown
10 - 20 feet
0 - 10 feet
Ú
" Pump Station
Tank
T
U
Figure 3-13: Elevations in the Sloop Point/Topsail Booster Area
´
Miles Pender County Utilities
0 1.5 3
1 inch = 1 mile
Section 4
Alternatives Evaluation
4.1 General
Table 4-1 lists the alternatives that were evaluated based on the hydraulic model simulations
discussed in Section 3. These alternatives were evaluated further in this section based on
planning-level capital and operation and maintenance (O&M) costs, advantages/disadvantages,
and economic and non-economic criteria. For the purposes of this evaluation, it was assumed that
any new reverse osmosis water treatment plant (RO WTP), whether privately-owned or PCU-
owned, would be located on a common site. Hence, transmission, storage, and pumping
requirements identified for Alternative 2 are identical for Alternative 2A.
Existing New
Alternative Surface Hampstead
No. WTP RO WTP Description
Pipeline improvements follow the existing alignments from the
1 X
WTP to Highway 17
New alignment would be installed running south from the WTP
1A X
parallel to I-140 and connecting in Scotts Hill
For the pipeline segment on Highway 421, a new alignment
1B X would be installed running due north and connecting
approximately in the Long Creek area near Little Kelly Road
2 PCU-owned Construct new groundwater RO WTP in Hampstead area;
evaluate the pros/cons of having a private water company
Privately- design, permit, construct and operate a new groundwater RO
2A WTP in the Hampstead area versus having PCU design, permit,
owned
construct and operate the same system
This section also discusses the feasibility and impact of installing groundwater wells in the
eastern service area to feed the RO WTP and the feasibility of installing interconnections with the
Town of Topsail Beach for up to 1 million gallons per day (mgd) and Cape Fear Public Utility
Authority (CFPUA) for up to 0.2 mgd.
4-1
Page 66 of 139
Section 4 Alternatives Evaluation
The accuracy of construction estimates should increase as the project moves through the process
from conceptual to detailed design and eventually to project bidding and actual construction. It
can be expected that conceptual and study-level estimates would have a wide range of accuracy
relative to the actual construction cost because not all the design features and details that would
impact the final cost have been addressed. The construction cost estimates prepared for this
report are at the “Conceptual Estimate” level (Category 1).
Cost estimates for the water supply, transmission, storage, and pumping improvements were
prepared using previous estimates for similar projects, historical data from comparable work,
and estimating guides and equipment costs. Factors such as competitive market conditions, actual
site conditions, and implementation schedule cannot be quantified at the current level of detail
but can significantly impact the project cost.
4-2
Page 67 of 139
Section 4 Alternatives Evaluation
Land acquisition, environmental mitigation, and permitting costs are not included
The following assumptions are used to develop the water transmission improvements cost
opinions:
All pipes are sized for 2040 maximum day demands (MDDs).
Improvements on existing pipeline routes are assumed to be installed parallel to the
existing pipe, i.e. the existing pipe will remain in service.
All pipe segments are assumed to be within roadway rights-of-way with alignments
between edge of pavement and right of way. Open cut construction is assumed with a
minimum of 3 feet of cover except where trenchless crossings are anticipated. Costs include
all pipeline appurtenances and minor pavement repairs along the pipe trench, where
applicable.
Water main pipes are assumed to be polyvinyl chloride (PVC) installed by open cut
methods. Major road and water crossings are assumed to be high-density polyethylene
(HDPE) installed by directional drilling methods
No rock excavation is required
Minimal shoring and dewatering requirements
Projecting costs into the future is speculative, as inflation rates for energy prices, building
materials, and construction labor fluctuate constantly. Care should be taken during future
updates to index costs for each year based on the inflation rate experienced over the update year.
Production of water at the existing surface water treatment plant (including high service
pumping)
Production of water from a new groundwater treatment plant using RO located in the
eastern service area (including well-field pumping, finished water pumping, and
concentrate disposal).
Annual costs were developed for operating labor, power, chemicals, and maintenance categories
of costs. The following O&M cost elements and unit costs (in 2019 dollars) were included in the
development of Operating Costs, Life Cycle Costs and Financial Costs.
O&M Labor Cost - Direct costs based on current fiscal year average hourly labor rates.
Burdened operations labor costs were used, but indirect labor was not included. Labor =
$40/hr.
4-3
Page 68 of 139
Section 4 Alternatives Evaluation
O&M Materials Expenses – Materials directly used in the normal course of operating and
maintaining the new facilities constructed as part of the alternative. Replacement
membrane elements = $600/element; Cartridge filter replacement elements = $5/element.
Energy Costs – Purchased power is presented as separate line items. Unit costs were
multiplied by annual quantity estimates to derive total annual energy costs. Unit cost for
electrical power = $0.10/kW-hr.
Chemical Costs – Direct expenses for various chemicals used in the normal course of project
operations. Unit costs were multiplied by annual quantity estimates to derive total annual
chemical costs. Chemical unit costs used on the analysis include:
Scale inhibitor (for RO) = $3/lb
Emulsified lime (for RO) = $0.06/lb
Carbon dioxide (for RO) = $0.10/lb
Sodium hypochlorite = $0.10/lb
Pender County Surface Water Treatment Plant – The cost to produce water (including
residuals handling and high service pumping) at Pender County Water Treatment Plant was
assumed to be $1.25/ 1000 gallons.
Inflation
Unit costs were inflated at a rate of 2.4 percent annually, matching the average inflation of the
southeast Consumer Price Index over the past 30 years (1990 – 2019). Capital costs were inflated
at 2.4 percent per year to the estimated mid-point of construction.
4-4
Page 69 of 139
Section 4 Alternatives Evaluation
4.2.1 Alternative 1: Surface Water Supply from Pender County WTP Only;
Transmission Along Hwy. 210 Routing
4.2.1.1 Conceptual Cost Estimates
This alternative evaluates the necessary water system improvements within the County if a new
RO WTP is not constructed within the eastern service area. Pipeline routes follow existing
alignments. Because of the substantial distance between the existing WTP and the eastern
service area, combined with the large amount of growth expected, significant pipeline, storage
4-5
Page 70 of 139
Section 4 Alternatives Evaluation
and pump station improvements are necessary. Pipeline, storage, pump station and WTP
improvements are all required as part of this alternative. The proposed improvements for
Alternative 1 are identified on Figure 4-1, and the specific proposed improvements to the
Highway 210 Water Booster Pump Station are identified on Figure 4-2. The conceptual cost
estimates for the recommended improvements are listed in Table 4-3.
4-6
Page 71 of 139
Legend
C (36-inch)
D (24-inch)
Malpass Tank E (24-inch)
F (16-inch)
T
U G (8-inch)
Topsail Tank
'') T
U
24
D(
B( Rocky Point Tank
30 Hwy 210 Tank
'') '')
C (36 T
U
T
U Ú
Ú
"
[
Additional 0.7 MG T
U
E(
24
Ú
"
'')
Hampstead Tank
T
U
'')
6
(1
F
A(
36'
')
'')
(8
G
T
U
3
Q Additional 0.3 MG (Scotts Hill Tank)
´
Miles
0 2.5 5 Pender County Utilities
Ex. 12" DIP Water Line, Feed
From Rocky Point Tank
Demolish or Continue Using
Existing 200,000 Gal
Ground Storage Tank
Page 73 of 139
Generator
Surge Protection
Ex. 12"
Gate Valve Ex. Hwy 210 Pump
Station. Demolish or
Legend .
& Continue Using
Proposed Improvement Existing Water Pipe Diameter
Generator 6-inch and smaller è
Æ
Pump Station Expansion 8
Ex. 10" Suction and
Surge Protection 10 dddd
Discharge Pipes
Existing Pipe 12
Proposed Pipe 16
20
è
Æ Existing Valve
24
.
& Proposed Valve
Unknown
´
Feet
0 25 50 100 150 Pender County Utilities
1 inch = 50 feet
Section 4 Alternatives Evaluation
4-9
Page 74 of 139
Section 4 Alternatives Evaluation
4.2.2 Alternative 1A: Surface Water Supply from Pender County WTP Only;
Alternative Transmission Routing through New Hanover County
4.2.2.1 Conceptual Cost Estimate
Alternative 1A evaluates the necessary water system improvements if a new RO WTP is not
constructed within the eastern service area but with an alternative pipeline route to Alternative
1. Some pipeline routes follow existing alignments; a new alignment would be installed from the
WTP, south, and ultimately to Scotts Hill. The pipeline route would leave the WTP, run south
along Highway 421 to Industrial Area Bond Road where it follows a northeast alignment to the
Northeast Cape Fear River. From here, a trenchless installation would take the pipeline east
under the river and connect to Rockhill Road where it runs easterly to Castle Hayne Road.
Approximately ¼ mile south on Castle Hayne, the pipeline turns east on Old Mill Road to Blue
Clay Road. On Blue Clay, the pipeline runs north to Sidbury Road where it follows Sidbury to the
east and terminating in Scotts Hill on Highway 17. This would eliminate proposed pipeline
segments A, D and E, reduce proposed segments B and C to 16- and 20-inch diameter,
respectively, increase segment G to a 24-inch diameter and eliminate the Highway 210 pump
station improvements. The proposed improvements for Alternative 1A are identified on Figure
4-3. The conceptual cost estimates for the recommended improvements are listed in Table 4-7.
4-10
Page 75 of 139
Legend
G (24-inch)
H (30-inch)
Malpass Tank
T
U
Topsail Tank
B (1 Additional T
U
6 '') 0.7 MG Hwy 210 Tank
)
C (20'' T
U
T
U Ú
"
Rocky
T
U
Point
Tank Hampstead Ú
"
Tank
'')
T
U
6
(1
F
'')
4
(2
G
U Additional 0.3
T
3
Q MG (Scotts
Hill Tank)
H (30
'')
´
Miles
0 2.5 5 Pender County Utilities
Section 4 Alternatives Evaluation
4-12
Page 77 of 139
Section 4 Alternatives Evaluation
4.2.3 Alternative 1B: Surface Water Supply from Pender County WTP Only;
Alternative Transmission Routing from Hwy. 421 to Hwy. 210
4.2.3.1 Conceptual Cost Estimate
Alternative 1B evaluates the necessary water system improvements if a new RO WTP is not
constructed within the eastern service area and some pipeline routes follow existing alignments
and a new pipeline alignment installed from the WTP, north on Highway 421 and connecting to
Highway 210. This would eliminate pipeline segment B and shorten segment A. The proposed
improvements for Alternative 1B are identified on Figure 4-4. The conceptual cost estimates for
the recommended improvements are listed in Table 4-9.
4-13
Page 78 of 139
Legend
D (24-inch)
E (24-inch)
F (16-inch)
G (8-inch)
Malpass Tank
T
U
Topsail Tank
'') T
U
24
D(
Rocky Point Tank Hwy 210 Tank
'')
C (36 T
U
T
U Ú
Ú
"
[
Additional 0.7 MG T
U
E(
24
Ú
"
'')
Hampstead Tank
T
U
')
36'
'')
A(
6
(1
F
'')
(8
G
T
U
3
Q Additional 0.3 MG (Scotts Hill Tank)
´
Miles
0 2.5 5 Pender County Utilities
Section 4 Alternatives Evaluation
4-15
Page 80 of 139
Section 4 Alternatives Evaluation
4-16
Page 81 of 139
Section 4 Alternatives Evaluation
4.2.4.1.3 Hydrogeology
Pender County is in the Coastal Plain Physiographic Province within the Tidewater region. Land
surface altitudes in the Tidewater region range from sea level to 10 feet above mean sea level
(Winner and Coble, 1989). The Tidewater region is relatively flat and contains swampy areas. The
Coastal Plain aquifers in this area contain alternating units of sand, clay, silt, limestone, and
sandstone, which thicken towards the east (McSwain et al., 2014).
The hydrogeology of the Hampstead area of Pender County consists of a series of aquifers,
including the surficial, Castle Hayne, Peedee, Black Creek, Upper Cape Fear, and Lower Cape Fear
aquifers, and corresponding confining units overlying Cambrian age basement rocks. The Castle
Hayne aquifer is separated from the surficial aquifer by the Castle Hayne confining unit. The
Peedee confining unit and aquifer underlie the Castle Hayne aquifer. The Castle Hayne and
Peedee confining units are made up of silt, clay, and sandy clay. The Castle Hayne aquifer is
comprised of highly permeable limestone and the Peedee aquifer is comprised of sandstone
(McSwain et al., 2014).
4-17
Page 82 of 139
Holly Shelter
Game Lands
£
¤ 17
Page 83 of 139
11
15
12
13
6 8 14
4 9
10
Topsail 5
7
£
17
¤ Parcel Label
Parcel Identification
Acres
Number
1 3282-29-4762-0000 0.57
2
2 3283-83-2003-0000 40.53
3 3292-19-1804-0000 0.97
4 3293-77-4609-0000 26.81
5 3293-86-1860-0000 2.14
V
U
210 3 6 3293-87-2994-0000 27.38
1 7 3293-87-3230-0000 7.17
8 3293-88-6360-0000 41.43
9 4203-17-8616-0000 19.50
10 4203-67-2174-0000
V
U50 0.50
Legend 11 4204-73-3307-0000 0.45
Hampstead
Game Lands 12 4204-81-4932-0000 17.91
13 4213-19-2302-0000 30.95
Parcel Boundary
14 4213-18-2238-0000 1.35
County-Owned Property 15 4214-12-5195-0000 0.25
Parcels and Game Lands Figure 4-5: Hampstead and Holly Shelter
from NCONEMAP, 2018. Game Lands Area and
´
Miles
0 0.5 1 2
County-Owned Properties
1 inch = 1 mile Pender County Utilities
Section 4 Alternatives Evaluation
4-19
Page 84 of 139
Legend
Topsail Senior
Well Location Center - Well #2 =
&
=
& Castle Hayne Aquifer
=
& Peedee Aquifer Holly Shelter Coastal
Game Lands Fitness
=
& Castle Hayne/Peedee Aquifer Center
£ 17
County-Owned Property ¤
Page 85 of 139
=
&
Game Lands
DWR Topsail Topsail
Station - =
& Greens -
Well #1 PE-099 MAS
BB 28J2
Castle 12B NR
Castle Bay Corp. Castle Bay S/D - =
& =
&
Castle Bay Golf Bay S/D - Well #2 Topsail
Course - Well 1 Well #1 Greens - =
&
Belvedere Well #2
=
&
PE-107 =
& Plantation
Castle Bay PE-112 NR
- Well #2
- Well #2 &
=
=
&=&
&= &
=
=
&
Cedar on DWR Topsail
Castle Bay Station - BB 28J4
- Well #1 the Green
- Well #1 17
=
& Belvedere
Topsail
£
¤ Country Club
=
& Carolina Water - Well #1
Spring Branch Junction & Service, Inc. -
South Topsail Bus - Well #1
= =
&
Olde Point Well #1
Elem. School
- Well #1 PE-123 NR Olde &
=
Point S/D Olde Point S/D
=
& Hampstead - Well #1 - Well #2A
=
&
NC Oil and Pines -
Gas Lea No. Vintage Well #2 Hampstead Belvedere
1 - BB 28N Associates Pines - Plantation
LLC - Well #2 =
& = Well #1
& - Well #1
V
U
210 &
= =
&
CVS Pharmacy Hampstead
#7046 - Hampstead Station Shopping
- Well #1 Ctr - Well #1
PE-116 NR V
U50
&
=
1. Well locations obtained from the North Carolina Department
&
=
PE-094 MAS 12 =
& Hampstead PE-117 NR of Environmental Quality - Division of Water Resources -
Groundwater Management Branch Databases or the United
=
&
=
& Port City Java
- Hampstead Sidbury's =
& =
& States Geological Survey National Water Information System
- Well #1 MHP - Lea's Waterfront for USA: Site Inventory
Well #2 =
& MHP - Well #1 2. Wells located in the Castle Hayne/Peedee are screened
£
¤17 across both aquifers
V
U
1559
Parcels and Game Lands Figure 4-6: Existing Water Supply Wells
´
from NCONEMAP, 2018. Miles Pender County Utilities
0 0.5 1 2
1 inch = 1 mile
Section 4 Alternatives Evaluation
Hydrogeologic cross-sections across Hampstead and the Holly Shelter Game Lands were created
from the DWR Groundwater Management Branch database (See Appendix B). The hydrogeologic
cross sections show the thickness of the aquifers and confining units, and the estimated location
of the saltwater interface (250 mg/L chloride concentration). Cross-section locations with
borehole locations are shown on Figure 4-7. The Castle Hayne aquifer is approximately 100- to
125-feet thick in the Hampstead area and the Peedee aquifer is approximately 250 to 350-feet
thick, as shown on Figures 4-8 and 4-9. The Castle Hayne confining unit and aquifer, as well as
the Peedee confining unit, thicken slightly from west to east. The Peedee aquifer generally
remains the same thickness throughout. From the Hampstead area to the Holly Shelter Game
Lands in the north, the thickness of the aquifers and the confining units generally remains the
same. The Castle Hayne and the uppermost part of the Peedee aquifer is freshwater, as shown by
the saltwater interfaces on Figures 4-8 and 4-9. The saltwater interface through the Peedee
aquifer becomes deeper to the north, away from the coast.
In the Peedee aquifer, groundwater generally flows from west to east, as shown in Figure 4-10.
In the Castle Hayne aquifer, groundwater flows from northwest to southeast, as shown in the
potentiometric surface map provided in Figure 4-11.
All USGS wells (well names beginning with “PE”) and the DWR’s Topsail Station – BB 28J4 well
are screened across the Castle Hayne aquifer. DWR’s Topsail Station BB 28J2 well is screened in
the lower portion of the Peedee aquifer, below the saltwater interface. Chloride concentrations in
the lower Peedee aquifer have ranged from 300 to 1,535 mg/L.
Hampstead-area public water systems that withdraw from the Castle Hayne and/or upper Peedee
aquifers, including Hampstead Pines, Castle Bay, Olde Point, Belvedere Plantation, and Topsail
Greens, use pressure sand filtration, greensand filtration/permanganate, or sequestration for iron
removal; ion exchange for inorganics removal and/or softening; orthophosphate for corrosion
control; and hypochlorination for disinfection.
4-21
Page 86 of 139
B'
"
Holly Shelter
Game Lands
£
¤17
DWR Topsail
Station -
BB 28J2
&
=
=
&
DWR Topsail
Station -
BB 28J4
Topsail
17
£
¤
V
U
1574
V
U210
A'
A
" NC Oil and
"
= Gas Lea No.
&
1 - BB 28N
Legend Hampstead
£17
Parcel Boundary ¤
t S
´ 0
Page 87 of1 139
0.5
inch = 1 mile
1 2
Miles Section Locations
Pender County Utilities
West East
Ground Surface
Castle Hayne
Confining Unit
Castle Hayne Aquifer
Peedee
Confining Unit
Page 88 of 139
Saltwater Interface
Peedee Aquifer
Black Creek
Confining Unit
Basement
Ground Surface
Castle Hayne
Confining Unit
Castle Hayne Aquifer
Peedee
Page 89 of 139
Confining Unit
Peedee Aquifer
Saltwater Interface
Black Creek
Confining Unit
Black Creek Aquifer
Basement
Hampstead Legend
Peedee Aquifer (fresh extent)
Potentiometric Contour
Contour Interval = 10 feet
Notes:
1. Image and contours were generated from
the North Carolina Department of
Environmental Quality – Division of Water
Resources – Groundwater Data Map Interface
2. Groundwater levels were measured in 2018
´
Figure 4-10:
Figure Castle
4-10: Hayne
Peedee Potentiometric
Aquifer PotentiometricSurface
SurfaceMap
Map
Miles Pender County Utilities
0 3 6 12 18
1 inch = 6 miles
Page 91 of 139
´
Miles
Figure 4-11: Castle Hayne Aquifer
0 1 2 Potentiometric Surface Map
1 inch = 1 mile Pender County Utilities
Section 4 Alternatives Evaluation
Castle Hayne
9/21/2010 -- 3,560 -- 12.34
Topsail Station - BB 28J4 9/12/2012 -- 373 -- 8.63
9/3/2015 -- 3,914 -- 12.44
9/7/2017 -- 3,066 -- 12.13
8/6/1998 -- 5,980 -- --
10/12/1999 -- 1,248 -- --
9/10/2004 -- 3,102 -- --
Peedee
9/25/2007 -- 1,273 -- 8.31
Topsail Station - BB 28J2
9/21/2010 -- 4,565 -- 9.30
9/12/2012 -- 4,410 -- 8.77
9/3/2015 -- 5,250 -- 9.26
9/7/2017 -- 4,895 -- 9.29
USGS Well Site Number USGS Well Site Name
342142077430701 PE-094 MAS 12 9/11/2002 21.9 308 0.1 7.5
9/10/2013 18.7 475 0.2 7.0
342300077425401 PE-123 NR 9/10/2013 -- -- 0.3 --
9/10/2013 -- -- 0.2 --
Castle Hayne
4-27
Page 92 of 139
Section 4 Alternatives Evaluation
4-28
Section 4 Alternatives Evaluation
342142077430701 PE-094 MAS 12 9/11/2002 < 0.050 1.4 < 0.2 22.7 < 0.060 18 < 0.040 < 0.8 0.112 E 0.1 1210 E 0.051
342300077425401 PE-123 NR 9/10/2013 0.16 6.7 0.05 13.6 < 0.006 24 0.729 0.51 0.1 41.9 591 1.28
8/30/2012 -- -- -- -- -- -- -- -- -- -- 1,800 --
342135077404501 PE-117 NR
Castle Hayne 8/21/2013 < 0.027 < 2.2 0.06 19.3 < 0.006 19 < 0.016 < 0.07 0.076 < 0.80 3,210 < 0.025
342200077412901 PE-116 NR 8/30/2012 -- -- -- -- -- -- -- -- -- -- 481 --
342359077404104 PE-107 6/16/2009 -- -- -- -- -- -- -- -- -- -- E 3.5 --
342423077365201 PE-112 NR 8/30/2012 -- -- -- -- -- -- -- -- -- -- 294 --
USGS Well Site Number USGS Well Site Name Aquifer Sample Date Lithium Manganese Magnesium Molybdenum Nickel Selenium Silver Strontium Thallium Vanadium Zinc
Units (µg/L) (µg/L) (mg/L) (µg/L) (µg/L) (µg/L) (µg/L) (µg/L) (µg/L) (µg/L) (µg/L)
342142077430701 PE-094 MAS 12 9/11/2002 1.48 20.4 1.73 < 0.200 2.28 < 0.3 < 1.00 119 0.298 2.3 1.4
342300077425401 PE-123 NR 9/10/2013 3.66 42 2.68 0.17 16.3 < 0.03 0.016 159 < 0.010 0.15 53.6
8/30/2012 -- -- 6.4 -- -- -- -- -- -- -- --
342135077404501 PE-117 NR
Castle Hayne 8/21/2013 2.94 75.2 6.95 0.155 0.97 < 0.03 < 0.005 166 < 0.010 0.15 18.1
342200077412901 PE-116 NR 8/30/2012 -- -- 2.28 -- -- -- -- -- -- -- --
342359077404104 PE-107 6/16/2009 -- < 0.60 < 0.036 -- -- -- -- -- -- -- --
342423077365201 PE-112 NR 8/30/2012 -- -- 2.65 -- -- -- -- -- -- -- --
Notes:
1. Data obtained from the North Carolina Department of Environmental Quality - Division of Water Resources (DWR) - Groundwater Management Branch Databases of the United States Geological Survey (USGS) National Water Information System for USA: Site Inventory
2. µg/L – Micrograms per liter
3. mg/L – Milligrams per liter
4. E – The concentration is estimated
5. (--) – Not analyzed
4-29
Section 4 Alternatives Evaluation
Based on a review of available groundwater information and investigations in the eastern service
area, it is anticipated the quality of groundwater associated with a withdrawal of 5 mgd or more
will require treatment to remove contaminants such as chlorides and hardness. A new RO WTP is
an option to provide the required treatment.
To meet the long-term water supply needs due to growth in the eastern Pender service area, a RO
WTP producing up to 6 mgd of finished water was evaluated as an option. To support a 6-mgd RO
WTP, approximately 15 wells would be necessary assuming an average daily yield of 350 gpm per
well. For conceptual planning purposes, two Castle Hayne aquifer wells providing approximately
10 percent of the total 6 mgd were assumed. These wells would not require treatment by RO.
Thirteen wells would be screened across the entire Peedee aquifer and require treatment by RO
to remove salt and other dissolves solids.
Because of the number of wells required, it is assumed that the County would need to purchase
property in the Hampstead area to develop a centralized or distributed wellfield. Assuming a
minimum well spacing of approximately 1,000 feet, between 200 and 350 acres of land would be
necessary for a centralized wellfield.
Figure 4-13 provides a conceptual representation of a wellfield with 15 wells, piping, and a RO
WTP site located on approximately 215 acres of undeveloped property immediately west of the
Holly Shelter Game Lands and north of the Topsail Middle School. Note that this is only a
conceptual representation. No evaluation of the suitability of this particular property for a
wellfield and RO WTP was performed, other than to account for the North Carolina Department of
Transportation (NCDOT) proposed Hampstead Bypass (Transportation Improvement Project R-
3300B) which includes right-of-way at the southern portion of the property.
An alternative site was also identified just west of SR 210 and north of US 17, as shown in Figure
4-14. Approximately 275 acres would be needed for 15-well wellfield and a RO WTP at this
location. Additional studies would be necessary to further determine the suitability of these or
other properties for a centralized wellfield. Alternatively, a distributed wellfield could be
developed on several non-adjacent properties. Wells distributed across multiple, non-adjacent
properties would require a larger capital investment in pumping and conveyance infrastructure.
4-30
Page 95 of 139
Legend 25
County-Owned Property =
&
Game Lands
Aquifer Holly Shelter
Game Lands
=
& Castle Hayne Aquifer
10 £ 17
=
& Peedee Aquifer ¤
Page 96 of 139
=
&
=
& Castle Hayne/Peedee Aquifer
Location of well and reported 300
well yield, in gallons per minute =
& 300
= <100
= 100 - 199
=
&
500
= 200 - 299 70
10
Topsail 500
= >499 &
=
150
100
150 &
&
=&
= &
=
= 200
=
&
180
60
=
& &
= 130
V
U
210 =
&
100 V
U50
&
=
40 = 180
& Hampstead
114 1. Well locations and yield information obtained from the North
=
&
=
& Carolina Department of Environmental Quality - Division of
Water Resources - Groundwater Management Branch Databases
2. Wells located in the Castle Hayne/Peedee are screened
17
& 210
= across both aquifers
V
U
1559
£
¤
Parcels and Game Lands Figure 4-12: Water Supply Well Yields
from NCONEMAP, 2018.
´
Miles Pender County Utilities
0 0.5 1 2
1 inch = 1 mile
Legend
Road
215 acre eastern !
!
Holly
!
! Well portion of existing, Shelter Game
privately owned !
RO Plant
!
Lands
#
Water Line property
Hampstead Bypass
!
!
Proposed Right of Way !
!
Page
Game Lands
Si 97 of 139
!
!
rW
alt
er
Ct
!
! !
!
Wells !
!
!
!
(15 total)
#
!
Highlan
!
!
d s Dr
!
!
!
!
Ca
iso
n
Dr
!
!
RO Plant !
!
#
le
st r
Ca y D
M
Ba
oo C
W
re t
so
a
r
Proposed
d
Ct
Right of Way
Tr
an
sf
er
17
£
¤
St
17
at
-
io
US
n
Rd
Blu
Annand
Ests ebird
Vi MH
sta P
Ln
a
iah
le Ter
ar
M Cv
´
Feet Site 1
0 500 1,000 2,000 3,000 Pender County Utilities
1 in = 1,000 ft
Legend V
U
210
Road NC
Berry
Hoo
-21
Well 0W
ver R
!
!
P
atch R
RO Plant
RO Plant Ln
d
Water Line
PIN V
U 210
rn
s
3282-68-9314-000 Bu
Pe
#
(36 acres)
a
Potential Wellfield Property
nu
Ln
tR
y
Page 98 of 139
ns
d
Pa
#
!
Co Rd
!
lle
ge
!
! !
!
Lea Dr
EXT
Wells !
! Fa
cto
(15 Total) Rd r y
!
!
#
!
!
!
275 acre portion of
!
Dan
two privately owned Ow
en
D r
properties
#
!
! !
!
17
£
¤
PIN
!
!
7
-1
3282-15-9252-000
US
Hea
(239 of 1,261 acres)
d wa
#
!
! !
!
De
ters
r
tD
er
fie
nu
Dr
ld
ka
!
!
berry
Dr
uc
Blue
Ch
Ln
!
!
r
rD
!
Gr ire
!
Wa ss
nt
Hu
W
Ce
a
y
gh
SE
es
Washin d
Cre
Rd
Acres R
C ekv
en iew
t er Dr
gton
D
r
´
Feet Site 2
0 500 1,000 2,000 3,000 Pender County Utilities
1 in = 1,000 ft
Section 4 Alternatives Evaluation
Although the County owns several properties in the Hampstead area that could be considered for
locating wellheads and/or a new RO WTP, most of these properties are already used for other
purposes.
Figures 4-15 is a typical process flow diagram for an RO water treatment plant. Figure 4-16
shows renderings of typical RO skid configurations. The skids shown have a permeate capacity of
1.5 mgd. This skid size can be assembled and prewired at a shop and delivered as a single unit to
Pender County for installation. To meet the near-term water demand of 3 mgd, a minimum of
two skids would be required. Long-term water demands (5 mgd) will require a minimum of four
RO skids. The skids, cartridge filters, feed pumps, and cleaning systems would be housed inside
an RO Building. A typical configuration of an building with the RO skids is shown in Figure 4-17.
4-34
Page 99 of 139
Page 100 of 139
© 2012
4-15
Figure No. 4-14
Pender County RO Water Treatment Plant
Propsed Process Flow Diagram
Proposed
Page 101 of 139
© 2012
4-17
4-16
Figure No. 2-16
Typical Reverse Osmosis Facility Layout
Section 4 Alternatives Evaluation
A new concentrate discharge pipeline would be required to take RO reject water from the RO
WTP most likely to the Intracoastal Waterway. Permitting of this concentrate disposal is
expected to take a minimum of one year for approval after all required studies have been
performed. Based on CDM Smith’s recent experience in Brunswick County, the State will require
a bathymetric survey of the outfall location, study of tidal impacts, determination of highwater
elevations and a dispersion study. The dispersion study will result in the preliminary design of a
diffuser system which will be included in the submittal package to the State.
In addition to an NPDES permit, depending on the outfall location, a Coastal Area Management
Act (CAMA) permit and 404/401 permit could be required.
Implementation timeline for a RO WTP owned by PCU is expected to take 4-5 years. This includes
up to 1 year for project planning and pilot testing, 1 year for environmental permitting (including
NPDES permitting for concentrate discharge), up to 1 additional year for design and bidding, and
2 years for construction.
4-38
Page 103 of 139
Legend
T
U New Elevated Tanks
New Parallel Pipe Segment
B (16-inch)
Page 104 of 139
C (20-inch)
F (16-inch)
G (8-inch)
Malpass Tank
T
U
Topsail Tank
T
U
B( Rocky Point Tank
16 Hwy 210 Tank
'') '')
C (20 T
U
T
U Ú
"
Additional 0.7 MG T
U
New RO WTP (5 MGD) Ú "
Hampstead Tank
3
Q
T
U
'')
6
(1
F
'')
(8
G
T
U
3
Q Additional 0.3 MG (Scotts Hill Tank)
´
Miles
0 2.5 5 Pender County Utilities
Section 4 Alternatives Evaluation
4-40
Page 105 of 139
Section 4 Alternatives Evaluation
PCU has spoken with a private water company that provides water and wastewater services in
four southeastern states, including North Carolina. The company operates three wastewater
treatment systems for communities in Pender County and Onslow County. They have provided
Pender County a proposal to provide approximately 1 mgd of potable water from an RO plant to a
portion of the eastern service area with an assumed 0.2 mgd going to the Town of Topsail Beach.
The private water company would provide design, permitting, construction, operation, and
maintenance of a new 1-mgd RO WTP including concentrate disposal and wellhead construction
located in the Hampstead area. The treated water would be sold at a bulk rate of $5.95/1000
gallons to PCU who in turn would provide distribution to customers in the service area. The
private water company has stated they can have a plant online by spring 2021.
NOTE: In accordance with PCU’s direction, CDM Smith has made the assumption that the private
water provider can provide a RO WTP of 3 mgd initially and 5 mgd ultimate design by 2040 and the
rate of $5.95/1,000 gallons will be the initial rate and only adjusted for inflation. CDM Smith has
also assumed that PCU would fund the cost of the concentrate disposal pipeline with this option.
This has not been confirmed with the private water company as of the date of this report.
4-41
Page 106 of 139
Section 4 Alternatives Evaluation
4-42
Page 107 of 139
Section 4 Alternatives Evaluation
Table 4-20. Pros and Cons of Alternative 2A (Privately-Owned RO WTP) Versus Alternative 2 (PCU-Owned
RO WTP)
Pros Cons
The Private utility finances the PCU is responsible for water quality but won’t have control over the supply
design, permitting, and and treatment of water. Compliance with distribution regulations such as
construction of the the Stage 2 Disinfection and Disinfection Byproducts Rule and the Lead and
infrastructure. Reduces PCU’s Copper Rule will reside with PCU; however, treatment that may be required
capital outlay. to stay in compliance would occur at the WTP and not be provided by PCU.
PCU does not have to hire Water provided must meet State and Federal drinking water standards. PCU
additional staff to operate and may have additional water quality standards that would need to be
maintain the RO WTP. negotiated.
The current proposal from a private water company is for a 1-mgd RO WTP.
The near-term and long-term demands in the eastern service area are
projected to exceed this demand. It is assumed a larger treatment plant can
be provided, but no proposal has been received and therefore, extrapolation
in this report may not be appropriate or accurate.
The Private utility contacted does not currently operate any drinking water
systems in NC. Also, a review of installations did not indicate they have
experience with any RO membrane plants. Limited information is available to
determine qualifications to deliver the project. Their proposed timeline of 18
months would be challenging in NC.
The contract terms for purchase of water are unknown, but these may
require guaranteed minimum purchase. This would require PCU to purchase
and pay for water even though it may not be necessary to meet customer
demands. This is a particularly important consideration during low demand
seasons when the existing surface water treatment plant can meet the
demands of PCU customers. Cost recovery and profit for private utility will be
through purchase guarantees and adjustments to the bulk rate (price per
1000 gallons) for water sold.
4-43
Page 108 of 139
Section 4 Alternatives Evaluation
4.3 Interconnections
4.3.1 Town of Topsail Beach
The Town of Topsail Beach has requested an interconnection with PCU where PCU will provide
up to 1 mgd of water for purchase by 2030. The Town will install a new pipeline under the
Intracoastal Waterway and connect to PCU’s existing distribution system with an assumed two-
way meter vault. It is anticipated that most water will be provided from PCU to the Town;
however, in case of pipeline rupture or other PCU system failure, water could be provided from
the Town to PCU. This interconnection will allow PCU to increase its revenue while also receiving
an emergency backup.
PCU has recently indicated a desire to construct emergency wells in the Hampstead area to
temporarily relieve some of the excessive water system demands for the eastern service area.
The construction of these wells combined with the new improvements presented in this report
make the need for an interconnection with CFPUA less urgent; however, having a backup water
source between agencies is always a good idea without the new booster pump station. With the
construction of the wells and improvements presented here, a new booster pump station would
be a large expense and would mostly sit idle.
The memorandum also evaluated and recommended a new elevated tank in the Scott’s Hill area.
CDM Smith has performed hydraulic modeling and confirmed that a new elevated tank in the
Scott’s Hill would be beneficial and is therefore recommended and included in the alternatives
presented above.
4-44
Page 109 of 139
Section 5
Conclusions and Recommendations
5.1 Summary of Evaluation Results
5.1.1 Water Demand Projections
The Pender County population is anticipated to increase substantially for the near-term and long-
term planning periods, with most of the growth projected in the rapidly expanding eastern
service area. The existing maximum day demand (MDD) of 2.16 million gallons per day (mgd) is
projected to increase to 4.92 mgd by 2025 and 9.94 mgd by 2040. The projections include MDD
bulk sales to Topsail Beach of 0.60 and 1.00 mgd by 2025 and 2040, respectively.
Expansion of the existing surface WTP with raw water obtained from the Cape Fear River
Construction and implementation of a new groundwater reverse osmosis (RO) WTP in the
Hampstead area
5-1
Page 110 of 139
Section 5 Conclusions and Recommendations
A new concentrate discharge pipeline would be required to take RO reject water from the RO
WTP most likely to the Intracoastal Waterway. Permitting of this concentrate disposal is expected
to take a minimum of one year for approval after all required studies have been performed.
Implementation timeline for a RO WTP owned by PCU is expected to take 4 to 5 years. This
includes up to 1 year for project planning and pilot testing, 1 year for environmental permitting
(including NPDES permitting for concentrate discharge), up to 1 additional year for design and
bidding, and 2 years for construction.
An option for a privately-owned and operated RO WTP was also considered. The private water
company would design, permit, construct, operate, and maintain the new RO WTP. For
comparative purposes, it was assumed that the privately-owned plant would be at the same
location as the PCU-owned plant.
CDM Smith estimated the value of each issue/constraint based on discussions with PCU staff.
Scores for each of the alternatives were estimated based on their relative comparison to one
another. See Table 5-2 for evaluation results.
5.3 Recommendations
5.3.1 ALTERNATIVE 2: New PCU-Owned RO WTP and Associated Infrastructure
Needs
A new RO WTP in the Hampstead Area, owned and operated by PCU is recommended with the
following infrastructure improvements:
New minimum 5-mgd RO WTP in Hampstead area with initial capacity of 3 mgd.
5-2
Page 111 of 139
Section 5 Conclusions and Recommendations
Improvement Type Description (feet) (inches) Estimate (inches) Estimate (inches) Estimate (inches) Estimate (inches) Estimate
Segment A 43,200 36 $26,600,000
Segment A* 41,700 36 $32,300,000
Segment B 31,100 30 $13,700,000 16 $9,100,000 16 $9,100,000 16 $9,100,000
Segment C 27,700 36 $15,600,000 20 $8,500,000 20 $8,500,000 20 $8,500,000 20 $8,500,000
Segment D 32,700 24 $16,800,000 24 $16,800,000
Transmission
Segment E 40,300 24 $13,700,000 24 $13,700,000
Segment F 17,100 16 $4,100,000 16 $4,100,000 16 $4,100,000 16 $4,100,000 16 $4,100,000
Segment G 13,800 8 $2,000,000 24 $5,800,000 8 $2,000,000 8 $2,000,000 8 $2,000,000
Segment H 91,600 30 $45,500,000
Concentrate Discharge 52,800 $3,900,000
New Rocky Point EST (0.7
MG) $2,700,000 $2,700,000 $2,700,000 $2,700,000 $2,700,000
Storage
New Scotts Hill EST (0.3
MG) $1,500,000 $1,500,000 $1,500,000 $1,500,000 $1,500,000
New Hwy. 210 Booster PS
Phase 1 $3,60,000 $3,600,000
Phase 2 $300,000 $300,000
Pumping
HSPS
Increase to 6.5 mgd $500,000 $500,000 $500,000 $500,000 $500,000
Increase to 12.4 mgd $3,000,000 $3,000,000 $3,000,000
Existing WTP
2 to 6 mgd $1,300,000 $1,300,000 $1,300,000 $1,300,000 $1,300,000
6 to 10 mgd $27,000,000 $27,000,000 $27,000,000
WTP
New RO WTP
Initial 3 mgd $44,200,000 $3,900,000
3 to 6 mgd $10,000,000 $0
Inflation (2.4% per year through 2023) $6,800,000 $6,300,000 $8,000,000 $5,600,000 $1,600,000
Inflation (2.4% per year through 2035) $49,400,000 $21,200,000 $17,100,000 $12,800,000 $8,200,000
Fee to Brunswick Co. for Raw water pipeline upgrades $5,000,000 $5,000,000 $5,000,000 $5,000,000 $5,000,000
Engineering/Admin/Construction Mgmt. Fees (Approx. 15%) $25,300,000 $20,400,000 $21,400,000 $15,300,000 $6,500,000
Total Conceptual Cost Estimate $198,900,000 $162,000,000 $168,800,000 $122,600,000 $54,900,000
Annual O&M Cost Estimate (Year 2025) $1,550,000 $1,480,000 $1,550,000 $1,615,000 $4,434,000
Annual O&M Cost Estimate (Year 2040) $4,471,000 $4,309,000 $4,471,000 $4,014,000 $11,616,000
20-Year Net Present Worth (O&M + Capital), 2019 dollars $151,000,000 $129,000,000 $143,000,000 $109,000,000 $100,000,000
1 It is assumed the county would be responsible for the concentrate pipeline installation with the privately funded RO WTP.
5-3
Section 5 Conclusions and Recommendations
WEIGHTING Importance Weighted Importance Weighted Importance Weighted Importance Weighted Importance Weighted
ISSUE OR CONSTRAINT FACTOR Rating Average Rating Average Rating Average Rating Average Rating Average
5-4
Section 5 Conclusions and Recommendations
By 2020, update the existing surface water WTP permitted capacity to 4.0 mgd to improve
supply to the Main pressure zone; add at least 0.5 mgd capacity from temporary wells
installed in the eastern service area.
By 2021, increase capacity from temporary wells installed in the eastern service area to at
least 1.0 mgd.
By 2024, increase capacity from temporary wells installed in the eastern service area to at
least 1.2 mgd.
By 2025, construct new RO WTP in the eastern service area with initial capacity of 3.0
mgd. It is assumed that wholesale of water to Topsail Beach will not begin until the new
RO WTP is in operation.
By 2031, expand the existing surface water WTP to a capacity of 6.0 mgd to provide
additional water supply to both the Main pressure zone and eastern service area (via the
existing NC 210 booster pump station).
By 2035, expand the RO WTP in the eastern service area to a capacity of 5.0 mgd to meet
entire demand of the eastern service area (transfer from the Main pressure zone is not
required once RO WTP is upgraded to 5.0 mgd).
Table 5-3 gives a preliminary schedule for improvements based on the projected demands
assuming linear growth between 2019, 2025, and 2040. This schedule should be adjusted based
on actual growth trends as additional development information becomes available. A more
detailed schedule for implementation of the new RO WTP is given in Figure 5-3.
5-5
Page 114 of 139
Legend
T
U New Elevated Tanks
New Parallel Pipe Segment
B (16-inch)
Page 115 of 139
C (20-inch)
F (16-inch)
G (8-inch)
Malpass Tank
T
U
Topsail Tank
T
U
B( Rocky Point Tank
16 Hwy 210 Tank
'') '')
C (20 T
U
T
U Ú
"
Additional 0.7 MG T
U
New RO WTP (5 MGD) Ú "
Hampstead Tank
3
Q
T
U
'')
6
(1
F
'')
(8
G
T
U
3
Q Additional 0.3 MG (Scotts Hill Tank)
´
Miles
0 2.5 5 Pender County Utilities
Total Water System
Expand RO WTP
12.0
to 5.0 mgd
New RO WTP
Temp Wells (3.0 mgd)
(1.0 mgd)
8.0
Surface WTP
Temp Wells
to 4.0 mgd;
(1.2 mgd)
6.0 Temp Wells
(0.5 mgd)
4.0
2.0
Max Day Water Demand
Water Supply
0.0
2018 2020 2022 2024 2026 2028 2030 2032 2034 2036 2038 2040
New RO WTP
(3.0 mgd)
4.0
Temp Wells
2.0 (0.5 mgd)
1.0
Max Day Water Demand
Water Supply
0.0
2018 2020 2022 2024 2026 2028 2030 2032 2034 2036 2038 2040
5.0
New RO WTP
(3.0 mgd)
Surface WTP
4.0 to 4.0 mgd
3.0
2.0
1.0
Max Day Water Demand
Water Supply
0.0
2018 2020 2022 2024 2026 2028 2030 2032 2034 2036 2038 2040
Figure 5-2
Page 116 of 139 Water Demand and Supply by Service Area
Figure 5-3. Alternative 2: Schedule for new 5 MGD RO WTP
ID Task Task Name Duration Start Finish Predecessors 2021 2022 2023 2024 2025
Mode Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1
1
2 NOTICE TO PROCEED 1 day Wed 4/15/20 Wed 4/15/20
3 RO WTP Site Analysis 45 days Thu 4/16/20 Wed 6/17/20 2
Page 117 of 139
Page 1
Section 5 • Conclusions and Recommendations
A summary of the associated conceptual cost estimate for the improvements necessary to meet
near-term (2025) and long-term (2040) needs of the system is presented in Table 5-4.
As shown in Table ES-2, Alternative 2 capital costs and present worth are lower than alternatives
1, 1a, 1b but higher than alternative 2A. However, alternative 2 has better O&M costs and the
County would be able to recover costs in an estimated 16 to 20-year time period after the new RO
WTP is put into operation (Estimated recovery year of 2041-2045).
The additional water source would improve reliability and redundancy of PCU’s water system
and allow the ability to feed the system with one water source out of service.
5-9
Page 118 of 139
Section 5 Conclusions and Recommendations
Although upfront costs are substantial, this alternative provides PCU full control of water quality,
production and distribution and eliminates additional stakeholder coordination when making
decisions. This option also allows better rate structure control.
5.3.2 Interconnections
5.3.2.1 Town of Topsail Beach
The Town of Topsail Beach has requested an interconnection with PCU where PCU will provide
up to 1 mgd of water for purchase by 2030. The Town will install a new pipeline under the
Intracoastal Waterway and connect to PCU’s existing distribution system with an assumed two-
way meter vault. It is anticipated that most water will be provided from PCU to the Town;
however, in case of pipeline rupture or other PCU system failure, water could be provided from
the Town. Once improvements are made, this interconnection will allow PCU to increase revenue
while also receiving an emergency backup, therefore CDM Smith recommends moving forward
with this project.
5.3.2.2 CFPUA
Prior to this study, a technical memorandum titled “SHWSD – CFPUA Interconnect Feasibility
Analysis” was prepared by Highfill in August, 2018 analyzing a potential interconnection with
CFPUA to supply water during high usage demand periods. The report recommended moving
forward with the interconnection and installing a pump station to account for hydraulic grade
line differences between CFPUA and PCU.
The new improvements recommended make the need for an interconnection with CFPUA less
urgent; however, having a backup water source between agencies can be mutually beneficial.
CDM Smith has reviewed the Highfill report analyzing this interconnection and believe PCU
should move forward with the interconnection; however, PCU should re-consider whether the
pump station is necessary or not.
Under the terms of the MOU, PCU has the option to purchase from Brunswick County an
additional 5 mgd safe yield from the new pipeline. PCU must decide by July 1, 2028 whether to
make this purchase or the 5 mgd capacity is forfeited and will be claimed by Brunswick County.
PCU’s portion of construction is 12.195% as shown in the MOU and with current construction and
engineering costs of slightly over $40,000,000, PCU’s portion would be approximately
$5,000,000. CDM Smith recommends PCU plan to purchase this additional 5 mgd capacity by July
1, 2028.
5-10
Page 119 of 139
Appendix A
Modeling
Figure A1-1. Alternative 1 Minimum Pressures with Recommended Improvements (2040 MDD)
Figure A1-2. Alternative 1 Maximum Pressures with Recommended Improvements (2040 MDD)
Figure A1-4. Alternative 1 Available Fire Flow with Recommended Improvements (2040 MDD)
Figure A1-6. Alternative 1 Model-Simulated Tanks Levels with Improvements (2040 MDD)
Figure A2-1. Alternative 1A Minimum Pressures with Recommended Improvements (2040 MDD)
Figure A2-3. Alternative 1A Water Age with Recommended Improvements (2025 ADD)
Figure A2-5. Alternative 1A Model-Simulated Tank Levels with Improvements (2040 ADD)
Figure A3-1. Alternative 1B Minimum Pressures with Recommended Improvements (2040 MDD)
Figure A3-2. Alternative 1B Maximum Pressures with Recommended Improvements (2040 MDD)
Figure A3-4. Alternative 1B Available Fire Flow with Recommended Improvements (2040 MDD)
Figure A3-6. Alternative 1B Model-Simulated Tanks Levels with Improvements (2040 MDD)
Figure A4-1. Alternative 2 Minimum Pressures with Recommended Improvements (2040 MDD)
Figure A4-2. Alternative 2 Maximum Pressures with Recommended Improvements (2040 MDD)
Figure A4-4. Alternative 2 Available Fire Flow with Recommended Improvements (2040 MDD)
Figure A4-6. Alternative 2 Model-Simulated Tanks Levels with Improvements (2040 MDD)
Appendix B
DWR Topsail Station Chlorides
Page 135 of 139
Page 136 of 139
Page 137 of 139
Page 138 of 139
Page 139 of 139