TGL 10 Okt
TGL 10 Okt
Preventif Maintenance Panel Panel , Panel SDP Lt.07 dan PP.Pen Lt.07
Pengecekan Power Counter 1 K2-01, 1 K2-02 dan 1 K2-03, ( Counter tersebut memakai Power
dari 1 MCB )
dibantu team sipil
OPERATOR SIFT SIANG
15:00 - Over shif
- Cek gwt 35%
- Cek roofank 40 full
16:00 - Tutup bypass roofank 40
- Off chiller
- Off pompa colling tower
- Off pompa make up water
- Off Fan ct
- Tutup valve make up water
17:00 - Off ahu
- Off lif panoramik
- Off exhause fc
- On diesel dan elektrik pump
- Off all escalator
18:00 - Off sound gedung
- Off penerangan gedung
- Off lif barat, atrium, utara
- Off penerangan lobby
- Off penerangan lt.4
- On lampu sorot roofop
19:00 - Cek roofank 40 full
- Cek roofank 20 full
- Cek gwt 25%
19:30 - Lanjut penggantian tombol push botton
dan lampu indikator panel control room
22:00 - Cek gwt 40%
PLUMBING & MEKANIK