PROPOSED HOUSING PROJECT FOR RICHY PROJECTS (PVT) LTD IN SRI LANKA

GRAND SUMMARY - TYPE 01

1 EXCAVATION AND EARTH WORK SLRs. 40,725.00

2 CONCRETE WORK SLRs. 116,775.00

3 MASONRY WORK SLRs. 284,450.00

4 ASPHALT WORK SLRs. 32,715.00

5 DOORS AND WINDOWS SLRs. 406,000.00

6 ROOF AND ROOF PLUMBING WORK SLRs. 336,400.00

7 FLOOR, WALL & CEILING FINISHES SLRs. 594,875.00

8 PAINTING WORK SLRs. 139,675.00

9 PLUMBING WORK / SANITARY INSTALLATIONS SLRs. 127,500.00

10 DRAINAGE WORK SLRs. 44,000.00

11 ELECTRICAL INSTALLATION SLRs. 147,250.00

TOTAL ESTIMATED COST SLRs. 2,270,365.00

Rate Per Sq.ft. : Rs. 3783.94

Amount in words : Rupees Two Million & Two Hundred Seventy Thousand
Three Hundred Sixty Five Only.

Page 2
PROPOSED HOUSING PROJECT FOR RICHY PROJECTS (PVT) LTD IN SRI LANKA

SCOPE OF WORK BOQ


No
HOUSE TYPE - 01 UNIT QTY RATE AMOUNT
1.00 EXCAVATION AND EARTH WORK
1.01 The Contractors are requested to refer Bills of Quantities, Note
General Notes, Pricing Preambles, Drawings, Specifications,
Conditions of Contract, Special, Conditions of contracts and
other relevant documents prior to pricing of this section of
work.documents prior to pricing of this section of work.

1.02 The Contractors are requested to check ground water level, Note
limitation of transport, limitation of site, conditions of the
existing road for possibility of transportation of heavy
equipment etc., prior to pricing this section of work.

1.03 The contractor shall arrange and obtain necessary permission Note
from authorities for disposal and dumping of earth.

1.04 Contractor shall provide due protection to avoid any damages to Note
temporary work, any new or old structures during excavation.

1.05 Surface treatment shall be measured only for floor area covered Note
by building. Rate shall include for all the other surfaces like
bottom of excavation, vertical and sloping sides of cuttings,
etc..

1.06 Earth work supporting system and dewatering measured Note


separately.

Excavation

Excavation for Column footings from reduced ground level


except rock requiring blasting. Rate shall include for
compacting the bottom of excavation, part return fill to
excavation (backfilling) and rammed.

1.07 - Ditto - for wall foundation from -do- Cube 3.85 3,500.00 13,475.00

Hard Earth Filling

1.08 Approved hard earth filling from ground level to DPC level Cube 5.70 2,500.00 14,250.00
with available materials to be well compacted in not more than
6" thick layers as directed within the foundation.

1.09 - Ditto - with imported material from -do- Cube 2.00 6,500.00 13,000.00

TOTAL FOR EXCAVATION & EARTH WORK


CARRIED TO SUMMARY SLRs. 40,725.00

Page 3
PROPOSED HOUSING PROJECT FOR RICHY PROJECTS (PVT) LTD IN SRI LANKA

SCOPE OF WORK BOQ


No
HOUSE TYPE - 01 UNIT QTY RATE AMOUNT
2.00 CONCRETE WORK

2.01 The Contractors are requested to refer Bills of Quantities, Note


General Notes, Pricing Preambles, Drawings, Specifications,
Conditions of Contract, Special, Conditions of contracts and
other relevant documents prior to pricing of this section of
work.documents prior to pricing of this section of work.

2.02 All concrete works shall comply to the specifications, filled into Note
formwork and well consolidated around reinforcement by
vibration.

2.03 Rate for concreting columns, walls shall include for kickers. Note

2.04 Rates shall include for plant for mixing, handling, hoisting, Note
depositing, compacting, vibrating, curing, making good after
removal of formwork and for any tests as necessary.

2.05 All cement and reinforcement steel to be an approved make and Note
manufacturer.

2.06 All formwork shall be so constructed that no grout shall leak Note
out during concreting.

2.07 Formwork is measured as the net contact surface Note

2.08 Formwork shall be plywood or steel shutter and GI pipe Note


supporting system.
2.09 Rate for formwork shall include for necessary boarding Note
supports, erecting, framing, removing, cleaning and wetting.

2.10 All reinforcement shall be as per specifications and relevant Note


drawings.

2.11 All reinforcement shall be free from rust, grease, oil and plants Note

2.12 Rebending of incorrectly bend bares shall be not be allowed. Note

2.13 Rage shall include for cutting fabricating placing in position Note
including, hangers, binding wire, spaces and waste

Page 4
PROPOSED HOUSING PROJECT FOR RICHY PROJECTS (PVT) LTD IN SRI LANKA

SCOPE OF WORK BOQ


No
HOUSE TYPE - 01 UNIT QTY RATE AMOUNT
Mass Concrete
2.14 2" thick lean cement concrete 1:3:6 (1") screed under wall Sqrs 1.70 6,500.00 11,050.00
foundations.

2.15 3" thick mass concrete 1:2:4 mixed under floor on well Sqrs 4.85 11,500.00 55,775.00
compacted earth

Lintels

2.16 Lintel at specified high doors,windows & walls with form work Note
& steel.

2.17 4 1/2" x 6" Lintels with form work and steel L.ft 141.00 300.00 42,300.00

2.18 Construction of 75mm thk. 600 mm wide RCC pantry tops L.ft 9.00 850.00 7,650.00
including rowlock supporting brick work as per detail drawings
& specifications. Rate to include form work, reinforcement,
concreting, etc.

TOTAL FOR CONCRETE WORK CARRIED TO


SUMMARY SLRs. 116,775.00

Page 5
PROPOSED HOUSING PROJECT FOR RICHY PROJECTS (PVT) LTD IN SRI LANKA

SCOPE OF WORK BOQ


No
HOUSE TYPE - 01 UNIT QTY RATE AMOUNT
3.00 MASONRY WORK

3.01 The Contractors are requested to refer Bills of Quantities, Note


General Notes, Pricing Preambles, Drawings, Specifications,
Conditions of Contract, Special, Conditions of contracts and
other relevant documents prior to pricing of this section of
work.documents prior to pricing of this section of work.

3.02 Rate for masonry works shall include for plumbing angles, Note
forming rebates, square cutting and racking of joints for
plastering.

3.03 Any cost due to rejection of poor quality bricks to be borne by Note
the contractor. (Shall be in Grade 1 quality)

3.04 Rate shall include for stiffners unless otherwise measured Note
seperately.

Random Rubble Work


3.05 Random rubble masonry work in 1:5 cement sand mortar mix to Cube 4.90 25,500.00 124,950.00
foundation.

Cement Block Work

3.06 4" thick cement block work in approved common blocks and Sqrs 14.50 11,000.00 159,500.00
cement and sand 1:5

TOTAL FOR MASONRY WORK CARRIED TO


SUMMARY SLRs. 284,450.00

Page 6
PROPOSED HOUSING PROJECT FOR RICHY PROJECTS (PVT) LTD IN SRI LANKA

SCOPE OF WORK BOQ


No
HOUSE TYPE - 01 UNIT QTY RATE AMOUNT
4.00 ASPHALT WORK

4.01 The Contractors are requested to refer Bills of Quantities, Note


General Notes, Pricing Preambles, Drawings, Specifications,
Conditions of Contract, Special, Conditions of contracts and
other relevant documents prior to pricing of this section of
work.documents prior to pricing of this section of work.

4.02 The finish of the concrete slab shall be acceptable to the


Consultants prior to carrying out the water proofing
system.

4.03 Rate shall include for


(a.) Clean with wire brush where necessary the concrete surface Note
and remove dust, etc,. Prepare the concrete surface to receive
the treatment.

4.04 The Tenderer shall refer the followings prior to pricing


the items in this trade.
a. All relevant drawings b. Specifications
c. Location of the site d. Access to the site
e. Type of water proofing suit to the nature of location
and surface.
f. Tender and Contract conditions Note

4.05 Contractor shall submit ten years guarantee for water proofing Note
material and workmanship through his specialist sub
contractor in the name of the Employer in an acceptable format.

4.06 Damp Proof Course 18 mm thick in cement sand 1:2 mix Sqrs 1.70 7,500.00 12,750.00
finished with application of two coats of hot tar blinded with
sand.

4.07 1000 gauge polythene below the ground floor slab. Rate shall Sqrs 4.85 900.00 4,365.00
include for necessary laps.

4.08 Approved water proofing system to toilets (Barralastic or Sqrs 1.30 12,000.00 15,600.00
equalent) floors & up to 1 feet in walls except 7 feets on the
walls of shower areas

TOTAL FOR ASPHALT WORK CARRIED TO


SUMMARY SLRs. 32,715.00

Page 7
PROPOSED HOUSING PROJECT FOR RICHY PROJECTS (PVT) LTD IN SRI LANKA

SCOPE OF WORK BOQ


No
HOUSE TYPE - 01 UNIT QTY RATE AMOUNT
5.00 DOORS AND WINDOWS

5.01 The Contractors are requested to refer Bills of Quantities, Note


General Notes, Pricing Preambles, Drawings, Specifications,
Conditions of Contract, Special, Conditions of contracts and
other relevant documents prior to pricing of this section of
work.documents prior to pricing of this section of work.

5.02 All Aluminum and glazing work shall be carried out by an Note
approved Specialist Contractor. Tenderer shall submit the
name of the Sub Contractor and details along with the tender.
All Aluminum extrusions shall be local manufacture of heavy
duty and joint details as per manufactures specifications.
powder coated not less than 60 - 80 microns from approved
source.

5.03 All aluminum frames shall be exterior quality powder coated Note
(not less than 60 - 80 microns) in approved colour with
correct sizes and thickness as specified by the manufacturer to
suit with the actual dimensions of openings including all
surfaces and method of construction and strong enough to
stand for the specified wind pressure. All fixings shall be to
suit the location and environment of the project and shall be in
materials free from corrosion with all primary and secondary
framing, fixings and accessories.

5.04 All glass shall be as per the schedule depend on the size of the Note
opening as per manufacturer's instruction in an approved
manufacture to suit with the specific requirements.

5.05 Sealant, beadings and gaskets to be used, shall be Note


appropriate to the climate of Sri Lanka and the environment of
the location of this project and necessary technical
information to be submitted for prior approval.

5.06 All ironmongery and fixing hardware for this section shall be Note
high quality fittings and rates shall include for all necessary
ironmongery.

5.07 Rate for Aluminum / Glass partitioning shall include for, other Note
necessary openings required, all fixing hardware and approved
ironmongery including locks should be "Union or equivalent.

Page 8
PROPOSED HOUSING PROJECT FOR RICHY PROJECTS (PVT) LTD IN SRI LANKA

SCOPE OF WORK BOQ


No
HOUSE TYPE - 01 UNIT QTY RATE AMOUNT

5.08 Shop drawings of aluminum doors, windows and fixing Note


details to be submitted for prior approval of the Engineer.

5.09 Rates to include All, Note


Masonary work
Steel work
as Shawn in detailed drawings & specifications
5.10 Aluminium framed, double sashed, glazed door, D1 type, Size Nr 1.00 55,000.00 55,000.00
4'-0" x 8'- 6" high overall with frame including all necessary
high quality iron mongeries and accessories and necessary
finish as per detail drawings and specifications.

5.11 Aluminium framed, single sashed, glazed door, type D2 size 3'- Nr 2.00 32,000.00 64,000.00
3" x 7'-0" high overall -do-

5.12 Aluminium framed, single sashed, glazed door, type D3 size 2'- Nr 1.00 30,000.00 30,000.00
9" x 7'-0" high overall -do-

5.13 Aluminium framed, glazed window type W size 6'-6" x 8'-6" Nr 4.00 46,000.00 184,000.00
high overall with frame including -do-

5.14 Aluminium framed, glazed window type W1 size 5'-0" x 5'-6" Nr 2.00 24,000.00 48,000.00
high overall with frame including -do-

5.15 Aluminium framed, glazed window type W2 size 2'-6" x 5'-6" Nr 1.00 15,000.00 15,000.00
high overall with frame including -do-

5.16 Aluminium framed, glazed fanlight type F1 size 2'-6" x 3'-6" Nr 1.00 10,000.00 10,000.00
high overall with frame including -do-

TOTAL FOR TIMBER DOORS AND WINDOWS


CARRIED TO SUMMARY SLRs. 406,000.00

Page 9
PROPOSED HOUSING PROJECT FOR RICHY PROJECTS (PVT) LTD IN SRI LANKA

SCOPE OF WORK BOQ


No
HOUSE TYPE - 01 UNIT QTY RATE AMOUNT
6.00 ROOF AND ROOF PLUMBING WORK
6.01 The Contractors are requested to refer Bills of Quantities, Note
General Notes, Pricing Preambles, Drawings, Specifications,
Conditions of Contract, Special, Conditions of contracts and
other relevant documents prior to pricing of this section of
work.documents prior to pricing of this section of work.

Asbastos Roof

6.02 Asbastos (Corrugated) sheet roof to a pitch of 20° roof with Sqrs 9.60 32,500.00 312,000.00
timber framework consisting of timber wall plates, rafters,
purlines, reepers, ridge plates, timber struts and timber beams
etc., as per detail drawings & specifications

6.03 25mm x 230mm Valance board (Ginisapu) with necessary paint L.ft 61.00 400.00 24,400.00
finish as per detail drawings & specifications. Colour to be
decided by the architect.

TOTAL FOR ROOF AND ROOF PLUMBING WORK


CARRIED TO SUMMARY SLRs. 336,400.00

Page 10
PROPOSED HOUSING PROJECT FOR RICHY PROJECTS (PVT) LTD IN SRI LANKA

SCOPE OF WORK BOQ


No
HOUSE TYPE - 01 UNIT QTY RATE AMOUNT
7.00 FLOOR, WALL & CEILING FINISHES

7.01 The Contractors are requested to refer Bills of Quantities, Note


General Notes, Pricing Preambles, Drawings, Specifications,
Conditions of Contract, Special, Conditions of contracts and
other relevant documents prior to pricing of this section of
work.documents prior to pricing of this section of work.

7.02 All the tile joints to be filled in with coloured cement mortar Note
1:2 mix to match the colour of the tiles.

7.03 Rate shall include for all tile specials such as corners edges etc., Note

7.04 Rate for plastering shall include for providing expanded metal Note
lath at different surfaces to avoid cracks.

7.05 Plaster of door window reveals not measured seperately. Rate Note
shall include for the above cost.

Floor Finishes

7.06 Supplying & laying of size 600mm x 600mm homogeneous Sqrs 4.95 32,500.00 160,875.00
procelain floor tiles, set in 18mm thk. cement sand motar 1:3
bedding with joints, pointed with and approved grout mix in
floor areas. (Tile cost per ft2 150/-)

7.07 Supply & fixing 75mm high Tile skirting to walls and L.ft. 175.00 160.00 28,000.00
finished with approved grout mix

Toilet Floor & Wall


7.08 12" x 12" non skid ceramic floor tilling including joint and Sqrs 0.41 35,000.00 14,350.00
point in coloured cement to match on and including 3/4" thick
cement and sand (1:3) screeded backing in toilet area. (Tile cost
per ft2 175/-)

7.09 12" x 12" coloured glazed ceramic wall tilling joint and point in Sqrs 1.90 35,000.00 66,500.00
coloured cement to match on and including 1/2" thick cement
and sand (1:3) screeded backing in toilet area. (Tile cost per ft2
175/-)

Page 11
PROPOSED HOUSING PROJECT FOR RICHY PROJECTS (PVT) LTD IN SRI LANKA

SCOPE OF WORK BOQ


No
HOUSE TYPE - 01 UNIT QTY RATE AMOUNT
Wall finishes.
7.10 5/8" thick cement lime and sand (1:1:5) plaster and finished Sqrs 19.60 6,500.00 127,400.00
with neat lime (internally) general and narrow surface in
ground floor

7.11 6/8" thick cement lime and sand (1:1:5) plaster and finished Sqrs 7.50 6,500.00 48,750.00
with neat lime (externally) general and narrow surface in
ground floor

Special Wall Finishes

7.12 Smooth cement rendered Plinth plaster as specified. Sqrs 1.00 9,000.00 9,000.00

Ceiling Finishes

7.13 Asbastos sheet flat ceiling on timber framework as per detail Sqrs 5.60 25,000.00 140,000.00
drawings & specifications

TOTAL FOR FLOOR, WALL & CEILING FINISHES


CARRIED TO SUMMARY SLRs. 594,875.00

Page 12
PROPOSED HOUSING PROJECT FOR RICHY PROJECTS (PVT) LTD IN SRI LANKA

SCOPE OF WORK BOQ


No
HOUSE TYPE - 01 UNIT QTY RATE AMOUNT
8.00 PAINTING WORK

8.01 The Contractors are requested to refer Bills of Quantities, Note


General Notes, Pricing Preambles, Drawings, Specifications,
Conditions of Contract, Special, Conditions of contracts and
other relevant documents prior to pricing of this section of
work.documents prior to pricing of this section of work.

8.02 Rate for painting to plastered areas shall include for painting to Note
reveals.

8.03 Rate shall include for all preparation of surfaces, cleaning Note
down, smooth, protection and cleaning of floors, door window
ad furniture, etc.,

8.04 Painting cost of door window reveals not measured separately. Note
Rate shall include for the above.

8.05 Sample approval should be obtained from Architect prior to Note


start work.

Internal

8.06 Prepare and apply one coat of primer and three coats of Sqrs 19.60 4,000.00 78,400.00
emulsion paint (CIC or asion) of approved colour and quality
to the followings standard Colour in ground floor

8.07 Prepare and apply two coats of wall putty & cutting with sand Sqrs 19.60 1,500.00 29,400.00
papers of approved colour and quality to the followings
standard Colour in ground floor (Including soffits)

External

8.08 Prepare and apply one coat of primer and three coats of weather Sqrs 7.50 4,250.00 31,875.00
shield emulsion paint (CIC or asion) of approved colour and
quality in the ground floor

TOTAL FOR PAINTING WORK CARRIED TO


SUMMARY SLRs. 139,675.00

Page 13
PROPOSED HOUSING PROJECT FOR RICHY PROJECTS (PVT) LTD IN SRI LANKA

SCOPE OF WORK BOQ


No
HOUSE TYPE - 01 UNIT QTY RATE AMOUNT
9.00 PLUMBING WORK / SANITARY INSTALLATIONS

9.01 The Contractors are requested to refer Bills of Quantities, Note


General Notes, Pricing Preambles, Drawings, Specifications,
Conditions of Contract, Special, Conditions of contracts and
other relevant documents prior to pricing of this section of
work.documents prior to pricing of this section of work.

9.02 Contractors are requested to refer Bill of Quantities, General Note


Notes, Pricing Preambles, Drawings, Specifications, Conditions
of contract and other relevant documents prior to pricing of this
section of work.

9.03 This trade include the following works :


a. Sanitary fittings, toilet accessories
b. Water supply
c. External sewerage and waste water disposal (up to the nearest
city sewer manhole)
d. Internal drainage (up to the nearest first manhole) Note
9.04 The Contractor shall provide all dimensions, and technical Note
information, of all builders work to the Consultant in
accordance with the programme of work.

9.05 Rate shall include for insurance during handling, rehandling, Note
transport, storage, delivery to the point of installation and until
handing over.

9.06 The tenderer shall submit the following information's on the


items/equipments/ fittings quoted for together with the tender.
1 Make
2. Model No.
3. Technical data
4. Country of manufacture
5. Delivery period
6. Lead time for manufacturing.

9.07 All control valves etc., shall be Hattersly, Crane, Pegler or Note
equivalent make to the approval of the Consultant.

Page 14
PROPOSED HOUSING PROJECT FOR RICHY PROJECTS (PVT) LTD IN SRI LANKA

SCOPE OF WORK BOQ


No
HOUSE TYPE - 01 UNIT QTY RATE AMOUNT
9.08 All pipes to be fixed to the soffit with necessary fixing Note
accessories and pipe supports hangers etc. to the hot dipped
galvanised finish to the approval of the Consultant.

9.09 Rates of plumbing work shall include for providing shop Note
drawing and as built drawing.

9.10 All pipes to be fixed with necessary fixing accessories and pipe Note
supports hangers etc (If required) to be hot dipped galvanised
finish to the approval of the Consultant.

Water Distribution System

9.11 Rates for all pipes shall include for pipes supports, saddles, Note
clips, screws, nails, hardware fixing, jointing, materials cutting
holes, chasing in brickwork, concrete etc., and making good the
same in all trades concrete etc., and making good the same in all
trades and under ground piping all necessary excavation,
backfilling, planking and strutting, concrete bedding and hunch,
dewatering and disposal of surplus material as directed. The
proposal for pipe fixing method to be submitted for prior
approval of the Consultant.

9.12 Rates for pipes shall include for burying in ground or walls or Note
clipping to wall and all pipe supports fixed to under side of the
soffit as required and for pipe fittings such as bends, tees, "Y"
junctions, reducers, inspection openings, stopends,etc., as
required.

9.13 All hot water pipes (supply and delivery) shall be polybutalene Note
from approved European manufacture and in appropriate type
as per specification.

9.14 All cold water pipes to be type 1000u. P.V.C and fittings to be Note
in moulded type.

9.15 Rate for all pipes shall include for necessary pipe fittings such Note
as bends, tees, Y junctions, angle valves, reducers inspection
openings, stop ends, etc., reducers inspection openings, stop
ends, etc.,

9.16 Allow a sum for Plumbing work inside the bathroom including Item 1.00 20,000.00 20,000.00
all extra over fittings for PVC pipes in ground floor

Page 15
PROPOSED HOUSING PROJECT FOR RICHY PROJECTS (PVT) LTD IN SRI LANKA

SCOPE OF WORK BOQ


No
HOUSE TYPE - 01 UNIT QTY RATE AMOUNT

9.17 Allow sum for Isolating valves with valve sockets Item 1.00 5,000.00 5,000.00

Sanitary Fittings

9.18 Cold water supply pipes to all WC cisterns, washbasins, sinks Note
etc., shall be provided with approved quality angle valves and
flexible hose. And these items shall measured with relavents
toilet fittings

9.19 Supplying, fixing and connecting into service wash basin, in Nrs 1.00 35,000.00 35,000.00
selected colour complete with chromium plated brass pillar tap,
strainer waste with rubber waste plug with bead chin, all of
approved quality and other necessary fitting. Rate to include
for fixing, placing all pipe work & fittings chrome plated 12mm
(1/2") dia. angle valve and stainless steel flexible coupling of
approved quality, supports, brackets and all necessary pipe
work and fittings, complete to working order. (PC 25,000/-)

9.20 Supplying, fixing and connecting into service low level W.C Nrs 1.00 40,000.00 40,000.00
Suite in selected colour with 9 lts. Capacity cistern, spray tap
and fittings, double plastice seat cover and "P" trap with
horizontal ouitlet, all of approved quality rate to include for ,
fixing, placing all pipe work & fittings, chrome plated 12mm
(1/2") dia. angle valve and stainless steel flexible coupling of
approved quality, supports, brackets and all necessary pipe
work and fittings, complete to working order. (PC 30,000/-)

9.21 Supply & Installation of head mixer shower with 1/2" dia Nrs 1.00 10,000.00 10,000.00
chromium plated shower arm with flange projection wall
mounted fix with head shower pulsator spray adjustable speed
clean anti-lime system with ball - joint connection thread with
stop cock including all necessary accessories complete with all
connection to working order In ground floor. (PC 5,000/-)

9.22 Installation of bathroom accessories Nrs 1.00 15,000.00 15,000.00

9.23 Supply and installation of hand bidet with necessary Nrs 1.00 2,500.00 2,500.00
accessories. (PC 1,500/-)

TOTAL FOR PLUMBING WORK / SANITARY


INSTALLATIONS CARRIED TO SUMMARY SLRs. 127,500.00

Page 16
PROPOSED HOUSING PROJECT FOR RICHY PROJECTS (PVT) LTD IN SRI LANKA

SCOPE OF WORK BOQ


No
HOUSE TYPE - 01 UNIT QTY RATE AMOUNT
10.00 DRAINAGE WORK

10.01 The Contractors are requested to refer Bills of Quantities, Note


General Notes, Pricing Preambles, Drawings, Specifications,
Conditions of Contract, Special, Conditions of contracts and
other relevant documents prior to pricing of this section of
work.documents prior to pricing of this section of work.

10.02 Rates for all ground piping shall include for pipe supports, Note
saddles, clips, screws, nails hardware fixing and jointing
materials, cutting holes chasing in brick work concrete etc., and
making good the same in all trades and under ground piping, all
necessary excavation,back filling,planking and strutting,concrte
bedding and haunching ,dewatering and disposal of surplus
material as directed.

10.03 Rate shall include for laying pipes / hume pipes according to Note
Specifications

10.04 Rate shall include for using pipes / hume pipes tested to Note
comply the relevant B.S. standards before laying and
embedding in the concrete floor slab

10.05 Rate shall include for easy cleaning maintenance provide a Note
clean out at every 15m intervals.

10.06 All storm / waste / sewer pipes to be approved quality type 600 Note
upvc or equivalent all fittings to be of moulded fittings.

10.07 Rigid U PVC pipes and fittings to conform BS4660, BS 5481, Note
BS 4576, BS 3943, BS 4514 and BS 5255 wherever applicable
to satisfy the specification and as per drawings.

10.08 Rates for all pipes to be fixed to the soffit with suitable pipe Note
supports in hot dipped galvanised finish and with necessary
fixing accessories etc., to the approval of the Consultant.

Page 17
PROPOSED HOUSING PROJECT FOR RICHY PROJECTS (PVT) LTD IN SRI LANKA

SCOPE OF WORK BOQ


No
HOUSE TYPE - 01 UNIT QTY RATE AMOUNT
10.09 Rates for all piping shall include for pipe supports, saddles, Note
clips, screws, nails, hardware fixing and jointing materials
cutting holes, chasing in brick work, concrete etc., and making
good the same in all trades . Rates for under- ground piping
shall include for all necessary excavation and backfilling,
planking and strutting, concrete bedding and disposal of surplus
material as directed.

10.10 Rates for pipes shall include for pipe supports( in hot dipped Note
galvanised finish and with necessary fixing accessories)fixed to
soffit , walls or clipping to walls as required and for pipe
fittings such as bends, tees, Y junctions, reducers, inspection,
openings, stop ends, etc., as required.

10.11 All waste and sewer pipes shall be from approved manufacture Note
to satisfy BS specification and with moulded fittings

Waste Water Disposal System

Manholes

10.12 450mm x 450mm waste water trapped manholes including Nrs 1.00 8,500.00 8,500.00
excavation, backfilling, 4" thick grade 25 reinforced concrete
(1:1 1/2:3 (3/4")) in base slab and wall with necessary
reinforcement and form work with cement, sand 1:3 smooth
rendering / Bituminous application at invert level (on base
concrete) to maintain the water flow. And complete with RCC
manhole cover including forming benching hunching to
complete with all connections to working order.

Waste Water Pipes

10.13 Allow sum for Supply and laying of 2", 1 1/4" waste pipes. Item 1.00 10,000.00 10,000.00
Rates for pipes shall include for burying in ground or walls or
clipping to walls as required and for pipe fittings such as bends,
tees, reducers etc.

10.14 Floor Trapped gulley 100 x 100 mm internally with stainless Nos 1.00 2,500.00 2,500.00
steel grating as per detail drawing and consultant approval in all
toilet floors.

Page 18
PROPOSED HOUSING PROJECT FOR RICHY PROJECTS (PVT) LTD IN SRI LANKA

SCOPE OF WORK BOQ


No
HOUSE TYPE - 01 UNIT QTY RATE AMOUNT
Sewer Disposal System

10.15 Sewer disposal system has been measured up to the nearest first Note
manhole. All work beyond the first manhole has been measured
under drainage and storm water disposal trade.

10.16 Rates for pipes shall include for all pipe fittings such as bends, Note
tees, reducers, connectors cleaning point, etc., and inspection
openings as necessary for total completion of the work.

10.17 All sewer pipes shall be in the appropriate type as in the Note
specification with moulded fittings.

10.18 Rates for pipes shall include for fixing arrangements with clips Note
and/or pipe supports in hot dipped galvanised finish and with
necessary fixing accessories. The tenderer shall submit his
proposal for pipe supports/fixing system as per specification to
the approval of the Consultant.

10.19 Rates for all underground pipes shall include for all excavation, Note
laid to gradient filling with selected materials and encasing the
pipes with concrete as required.

Sewer Manhols

10.20 600mm x 600mm sewer manholes with "p" trap including Nrs 1.00 8,000.00 8,000.00
excavation backfilling, 4" thick grade 25 reinforced concrete
(1:1 1/2:3 (3/4")) in base slab and wall with necessary
reinforcement and form work with cement, sand 1:3 smooth
rendering / Bituminous application at invert level (on base
concrete) to maintain the water flow. And complete with RCC.
manhole cover including forming benching hunching to
complete with all connections to working order.

Sewer Disposal Pipes

10.21 Supply and laying of 4" dia under ground sewer pipes. Rates Item 1.00 15,000.00 15,000.00
for pipes shall include for fixing along wall or burying in
ground to required gradient.

TOTAL FOR DRAINAGE WORK CARRIED TO


SUMMARY SLRs. 44,000.00

Page 19
PROPOSED HOUSING PROJECT FOR RICHY PROJECTS (PVT) LTD IN SRI LANKA

SCOPE OF WORK BOQ


No
HOUSE TYPE - 01 UNIT QTY RATE AMOUNT
11.00 ELECTRICAL INSTALLATION

11.01 The Contractors are requested to refer Bills of Quantities, Note


General Notes, Pricing Preambles, Drawings, Specifications,
Conditions of Contract, Special, Conditions of contracts and
other relevant documents prior to pricing of this section of
work.documents prior to pricing of this section of work.

11.02 All electrical fittings shall be of best quality approved fittings. Note
All switches, socket outlets etc., shall be Clipsal, ABB or
equivalent. All MCCB, MCB, RCCB, etc., shall be approved
European/ Japanese makes.

11.03 Rates shall include for:


(a) Supply, installing, testing and commissioning of the system
for power and lighting. All complete to working order and to
the entire satisfaction of the Consultant and the relevant
Authorities.

(b) Cutting, trimming, dressing, connection cables, cutting Note


holes and chases holes in brick work, concrete and connecting
cable with all accessories such as sockets connectors, conduit
cable trays, cable glands and boxes hardware clips fixing,
soldering and jointing materials.

(c) Rate shall include for necessary trenching, conduits, all Note
necessary materials, cables, fittings and clips, cutting holes and
chases in brick work and concrete work complete with all
accessories such as sockets, connections, cable glands and
boxes hardware clips, soldering and jointing materials etc., for
proper installing and laying of cables.

11.04 All materials, equipment wiring and workmanship shall confirm Note
to local codes and specification, B.S.standards/latest I.E.E.
regulations and Ceylon Electricity Board Specifications.

11.05 Rate for external lighting system shall include all materials Note
suitable for external purpose as per specifications.

11.06 All cables ACL or equivalent Note

11.07 Supplying of electricity for the building shall be in three phase Note
line As specified in the drawing & specification.

Page 20
PROPOSED HOUSING PROJECT FOR RICHY PROJECTS (PVT) LTD IN SRI LANKA

SCOPE OF WORK BOQ


No
HOUSE TYPE - 01 UNIT QTY RATE AMOUNT
Sub Main Cable

11.08 Main cable from meter to distribution panel board. Item 1.00 2,500.00 2,500.00

11.09 Allow for distribution panel board with internal cabling and Nos 1.00 50,000.00 50,000.00
enclosure (flush type) as per detail drawing & specifications to
the approval of the consultant with all connection working
order.

Earth Point

11.10 Supply and install main earths 600mm x 600mm x 3mm copper Item 1.00 10,000.00 10,000.00
plates and 25 x 3mm copper tape from roof top with all
accessories.

Point Wiring

11.11 Rates for point wiring shall include for all cables, switches(1 Note
way or 2 way as necessary) junction boxes, conduits, pull
boxes, clips, earth cables, draw wires, wiring accessories,
screws, nails, hardware, fixing and insulating materials, cutting
holes, chases, make good the same in all trades, holders, ceiling
boxes, flexible codes and any other wiring accessories require
up to the final fixing point where ever necessary and complete
with a holder and bulb.

11.12 All switches for lamp points to be Clipsal or equivalent make in Note
acceptable range suitable for luxury interior. All socket outlets
shall be Clipsal or equivalent make with a indicating bulb. All
junction boxes shall be injection moulded type. All conduits
shall be in reputed manufacture having SLS acceptable to the
Consultant.

11.13 All lamp point wiring shall be in 1 mm2 Cu/PVC/PVC cable


and 1mm 2 protective earth in PVC conduits including all
accessories

11.14 All ceiling fans points wiring to be also completed with fan Note
hooks excluding fan and regulator.(Fan and the regulator has
been measured under lamp fittings) The contractor shall carry
out the mega test and any other tests with a temporary switch
and bulb with a holder at ceiling fan points and other similar
items wherever necessary.

11.15 The contractor shall forward the conduit layout for prior Note
approval of the Consultant.

Page 21
PROPOSED HOUSING PROJECT FOR RICHY PROJECTS (PVT) LTD IN SRI LANKA

SCOPE OF WORK BOQ


No
HOUSE TYPE - 01 UNIT QTY RATE AMOUNT
11.16 Wall bracket light point Nos 3.00 2,750.00 8,250.00

11.17 Pendant light point Nos 6.00 2,750.00 16,500.00

11.18 Ceiling fan point. Nos 2.00 3,000.00 6,000.00

11.19 15 Amp Socket outlet. Nos 1.00 5,000.00 5,000.00

11.20 5 Amp Socket outlet Nos 6.00 2,750.00 16,500.00

11.21 Bell Nos 1.00 6,000.00 6,000.00


Light Fittings

11.22 Rates shall include for fixing all complete to working order Note
including all necessary accessories etc.

11.23 Wall bracket light fitting. Nos 3.00 1,500.00 4,500.00

11.24 Pendant light fitting. Nos 6.00 1,500.00 9,000.00

11.25 Ceiling fan.( KDK or equalent) Nos 2.00 6,500.00 13,000.00

TOTAL FOR ELECTRICAL INSTALLATION


CARRIED TO SUMMARY SLRs. 147,250.00